Opinion

Acuity Edge, Inc. v. United States

Court
United States Court of Federal Claims
Filed
Oct 24, 2024
Status
Published
On the bench
Zachary N. Somers
Cited by
0 cases
Authority
More cited than 32.9%

“The plaintiff bears the burden of showing standing . . . .”

How later courts described this case

  • “The plaintiff bears the burden of showing standing . . . .”
  • “[A]n interpretation which gives a reasonable meaning to all parts will be preferred to one which leaves a portion of it useless, inexplicable, inoperative, void, insignificant, meaningless, superfluous, or achieves a weird and whimsical result.”
  • “In sum, RPA has not satisfied the redressability prong of the standing requirement, because it has not alleged any facts showing that an order invalidating the safe harbor will likely cause dialysis facilities to increase the wages of RPA members.”
  • “Arguments that are not appropriately developed in a party’s briefing may be deemed waived.”

Written by the judges who cited it.

The opinion

In the United States Court of Federal Claims

No. 24-914 C

(Filed Under Seal: September 30, 2024)

Reissued: October 24, 2024 ∗

* * * * * * * * * * * * * * * * * * *

*

ACUITY EDGE, INC., *

*

Plaintiff, *

*

v. *

*

THE UNITED STATES, *

*

Defendant, *

*

SUMMIT TECHNOLOGIES & *

SOLUTIONS, INC., *

*

Defendant-Intervenor. *

*

*

* * * * * * * * * * * * * * * * ** *

W. Brad English, with whom were Emily J. Chancey and Taylor R. Holt, Maynard

Nexsen PC, all of Huntsville, Al., for Plaintiff.

Stephen J. Smith, Trial Attorney, Commercial Litigation Branch, Civil Division,

Department of Justice, with whom were Elizabeth M. Hosford, Assistant Director, Patricia M.

McCarthy., Director, and Brian M. Boynton, Principal Deputy Assistant Attorney General, all of

Washington, D.C., for Defendant, and Jennifer L. Howard, Senior Attorney, of Washington,

D.C., Vince Vanek, Assistant Chief Counsel, and Kristin Pollard Kiel, Attorney Advisor, Office

of the General Counsel, National Aeronautics and Space Administration, of Marshall Space

Flight Center, Al., of counsel.

Damien C. Specht, with whom were James A. Tucker, and Caitlin A. Crujido, Morrison

& Foerster LLP, all of Washington, D.C., for Defendant-Intervenor.

∗

Pursuant to the protective order entered in this case, this opinion was filed initially under seal.

The parties provided proposed redactions of confidential or proprietary information, which are redacted in

this version of the opinion. In addition, the Court made minor typographical and stylistic corrections to

this version of the opinion.

OPINION AND ORDER

SOMERS, Judge.

In this protest, the protestor, Acuity Edge, lodges two principal challenges to the agency’s

evaluation of proposals. As discussed in detail below, these challenges relate to the evaluation of

past performance references and a strength the protestor alleges should have been awarded for its

staffing plan. Before reaching these two challenges, though, Acuity must demonstrate that it

should have been eligible for award and thus has standing to protest the procurement errors it

alleges. For the reasons discussed below, the Court finds that Acuity has failed to demonstrate

standing.

BACKGROUND AND PROCEDURAL HISTORY

A. Solicitation

At issue in this case is a National Aeronautics and Space Administration (“NASA”)

Indefinite-Delivery Indefinite-Quantity (“IDIQ”) contract “to provide program support for the

Space Technology Mission Directorate (STMD) Technology Transfer Program (T2P).” ECF

No. 28 at 1–2 (“Pl.’s MJAR”). The solicitation was issued “as a 100% HUBZone set aside under

FAR Part 15 and NSF Part 1815.” Id. at 1 (citing AR 859). The T2P’s mission is to “identify

and protect . . . [NASA’s] intellectual property with commercial potential and transfer those

technologies through patent licensing agreements, software usage agreements, and related

technology transfer partnerships with entrepreneurs, companies, universities, non-profits,

business incubators and innovation ecosystems, and state and local governments.”

Administrative Record (“AR”) 951. The awardee will provide program support for T2P at

NASA headquarters, the Marshall Space Flight Center, and Stennis Space Center, as well as

have the potential for support at other NASA field centers. AR 859.

NASA intended this award to “be conducted utilizing a best value tradeoff between the

factors of Mission Suitability, Price, and Past Performance” in accordance with the Federal

Acquisition Regulation (“FAR”). AR 1102. All three factors were equally important when

compared to each other, but the combined non-price factors, Mission Suitability and Past

Performance, were significantly more important than Price. AR 1153–54. The Mission

Suitability evaluation criteria contained two subfactors: technical approach and management and

compensation approach. AR 1154–55. Both subfactors contained various additional evaluation

elements that NASA would use in evaluating the proposals. 1 Id.

Past Performance would be evaluated for both offerors and proposed subcontractors on a

scale ranging from Very High Level of Confidence to Neutral Confidence. AR 1158–59. The

1

For Technical Approach, the additional elements were TA-1 Technical Approach, TA-2

Technology, Innovations, and Process Improvements, and TA-3 Technical Risk Approach. AR 1154.

For Management and Compensation Approach, the additional elements were MCA-1 Management and

Total Compensation Approach, MCA-2 Business Approach, MCA-3 Organizational and Teaming

Structure, MCA-4 Contract Phase-In and Phase-Out Approach, and MCA-5 Management and

Compensation Risk Approach. AR 1155.

2

solicitation informed offerors to provide up to five contract references for the offeror and

proposed subcontractors, at least two of which must be from the offeror. AR 1118. NASA’s

confidence evaluation would be based on its analysis of “each referenced contract’s ‘size,

content, and complexity, and performance history (i.e., quality of Past Performance).[’]” ECF

No. 29 at 4 (“Gov.’s MJAR”) (citing AR 1157–59). In order to be evaluated by NASA, the

referenced contracts had to be “relevant in either size, content, or complexity.” AR 1157. If a

referenced contract was not relevant in one of those categories, “it [would] be determined not

relevant overall and [would] not be further evaluated.” Id. In terms of size, “[f]or offerors, a

referenced contract will be determined relevant if it has an average annual value of $500,000 or

greater, and for proposed subcontractors, an average annual value of $200,000 or greater.” AR

1118. To be relevant for content, the evaluation of an offeror’s contracts will be based on how

well they aligned with the relevant performance work statements and for proposed

subcontractors “relevancy will be determined relative to the content element(s) assigned to that

subcontractor.” AR 1118–19. “The [] Solicitation did not set out separate complexity

requirements for the offeror and subcontractor reference contracts.” Gov.’s MJAR at 5 (citing

AR 1119). 2

Recognizing this discrepancy, the Source Evaluation Board (“SEB”) issued a

memorandum to correct this error. AR 4372. On March 21, 2024, the memorandum

documented the rationale to update the Source Evaluation Plan (“SEP”) stating that the plan

“included separate offeror and subcontractor thresholds for Size and Content, but Complexity

was inconsistent in that it lacked a separate subcontractor threshold. To correct for this

inconsistency, the SEB updated the SEP to include subcontractor thresholds for Complexity.”

Id. The memorandum further noted that “these SEP changes are strictly internal and will allow

the Government to better assess complexity.” AR 4373 (emphasis added).

According to the solicitation, “[c]onsistency between the Mission Suitability factor and

the Price factor volumes will be considered in determining if the offeror’s proposed price is fair

and reasonable.” AR 1156. And total price was to be “the sum of (1) the phase-in services

price; (2) the mission core services price for the contract period of performance, including all

options; and (3) an indefinite-delivery, indefinite-quantity (IDIQ) price using the offeror-

provided fully burdened rates applied to a pre-populated estimate of labor hours for each labor

category . . . .” AR 1157. Additionally, and critically for purposes of this protest, in order to be

eligible for the award, the solicitation required offers to “remain in effect not less than 365 days

after the date specified for receipt by the Government.” AR 1125. Finally, NASA intended to

issue this award without discussions. AR 1092. NASA did, however, provide itself with the

2

Instead, it stated:

For the offeror, to be considered relevant for complexity, the referenced contract shall

demonstrate performance at a single geographic location and success handling a moderate

(i.e., 1,250 or more work products annually) volume of work products processed,

developed, and delivered simultaneously or performance at multiple geographic locations

and success at handling a small (i.e., 800 or more work products annually) volume of work

products processed, developed, and delivered simultaneously.

AR 1119.

3

The Source Selection Authority (“SSA”) reviewed and compared the offers and awarded

the contract to Summit. AR 4622–31. According to the SSA, this was because “based on [his]

integrated assessment of all three proposals and in accordance with the evaluation criteria and

their relative importance established for the [solicitation], . . . the Summit proposal offered

advantages over the Acuity Edge proposal under the Mission Suitability and Price factors (with

the proposals considered essentially equal under the Past Performance factor) and advantages

over the EN4S proposal under all three factors.” AR 4631. Accordingly, he “determined the

Summit proposal represents the best value to the Government” and awarded the contract to

Summit. Id. Moreover, the SSA noted that “Acuity Edge’s proposal is ineligible for contract

award because its offer expired 60 calendar days from the date for receipt of offers.” AR 4627.

The solicitation provided that “[o]ffers submitted in response to this solicitation shall remain in

effect not less than 365 days after the date specified for receipt by the Government. However, in

accordance with FAR 52.215-1, a different (longer) validity period may be proposed.” AR 1125.

The SSA nonetheless comparatively assessed Acuity’s proposal “for the purpose of providing

Acuity Edge meaningful insight on how its proposal compared to the STS proposal in the event

discussions were conducted.” AR 4627.

C. Acuity Protests the Award to Summit

Acuity protests NASA’s award decision on three grounds. First, Acuity alleges that

NASA had discussions with Summit and because it had those discussions with Summit it was

required to have them with Acuity as well. Pl.’s MJAR at 12. Acuity, at oral argument,

acknowledged that if it was unsuccessful in convincing the Court on this point, then Acuity

would lack standing to challenge the protest. 3 Acuity challenges NASA’s exchanges with

Summit regarding its OCI plan as “exceed[ing] the bounds of the Solicitation’s exception to the

general discussions rule.” Pl.’s MJAR at 13. Critically, Acuity did not “challenge the

Solicitation provision that allowed these types of communications.” Id. at 13, n.2. Rather,

Acuity argues “[t]he Solicitation’s exception only extended to communications with offerors

about inconsistencies between the OCI plan and the rest of the offeror’s proposal.” Id. at 13.

Acuity further argues that the language “Organizational Conflict of Interest (OCI) Plan in

accordance with the Notice of Potential Organizational Conflicts of Interest in Section L and

FAR 9.504[,]” AR 1153, is a header and the following two sentences “are specifics that are

meant to modify the general statement that introduces the paragraph.” Pl.’s MJAR at 13.

Therefore, according to Acuity, NASA’s exchange with Summit, which instructed it to make two

revisions to its OCI plan, exceeded the scope of the clause because the first change was not about

inconsistencies between Summit’s OCI plan and its proposal, but instead about “an inconsistency

between Summit’s OCI plan and the Solicitation.” Id. at 14 (emphasis omitted). Moreover,

Acuity asserts that the second change was about adding additional information into the OCI plan,

3

The Court stated “[a]s I take it, . . . I don’t think there’s a standing issue to raise the OCI issue,

but if you were unsuccessful in persuading me that you are correct on the OCI issue, you would not have

standing to raise the past performance and 100 percent agency capture issue. That’s how I look at it . . . .”

Tr. 4:7–4:12. To which Acuity responded, “I agree with that. . . . We’ve raised the discussions/OCI issue

because we think it gives us the opportunity to cure the defect in our proposal, and if [the Court] disagrees

with us, then we have an unawardable proposal, and, I assume, that would be the end of it.” Id. 4:14–

4:20.

5

Id. at 561 (quoting Simon, 426 U.S. at 38). Moreover, because standing is not a mere pleading

requirement, “but rather an indispensable part of the plaintiff’s case, each element must be

supported in the same way as any other matter on which the plaintiff bears the burden of proof,

i.e., with the manner and degree of evidence required at the successive stages of the litigation.”

Id.; see also Starr Int’l Co., Inc. v. United States, 856 F.3d 953, 964 (Fed. Cir. 2017) (“The

plaintiff bears the burden of showing standing . . . .”).

At issue in this case, as it relates to standing, is the redressability requirement. “Relief

that does not remedy the injury suffered cannot bootstrap a plaintiff into federal court; that is the

very essence of the redressability requirement.” Steel Co. v. Citizens for a Better Env’t, 523 U.S.

83, 107 (1998). In other words, redressability requires a showing “that prospective relief will

remove the harm.” Warth v. Seldin, 422 U.S. 490, 505 (1975). Therefore, a plaintiff must show

that it “would benefit in a tangible way from the court’s intervention.” Id. at 508. Stated

differently, if, for example, after the undoing of the government action the status quo remains in

place, the alleged injury is not redressable. See Renal Physicians Ass’n v. United States HHS,

489 F.3d 1267, 1278 (D.C. Cir. 2007) (“In sum, RPA has not satisfied the redressability prong of

the standing requirement, because it has not alleged any facts showing that an order invalidating

the safe harbor will likely cause dialysis facilities to increase the wages of RPA members.”).

Critically, although Article III’s standing requirements “are jurisdictional in a broad

sense, they are more accurately characterized as prerequisites to subject matter jurisdiction.”

Superior Waste Management LLC v. United States, 169 Fed. Cl. 239, 252–53 (2024) (collecting

cases). Accordingly, without satisfying these three prongs, the Court cannot adjudicate the

matter before it, because if the Court were to adjudicate such a claim, it would be “exceed[ing

its] authority as it has been traditionally understood.” Spokeo, Inc., 578 U.S. at 338 (citing

Raines v. Byrd, 521 U.S. 811, 820 (1997)). In short, “[t]o establish a case or controversy, a party

invoking federal jurisdiction must meet the ‘irreducible constitutional minimum of standing.’”

Allgenesis Biotherapeutics Inc. v. Cloudbreak Therapeutics, LLC, 85 F.4th 1377, 1380 (Fed. Cir.

2023) (quoting Lujan, 504 U.S. at 560).

B. Bid Protest Jurisdiction

The Tucker Act, as amended by the Administrative Dispute Resolution Act, provides the

Court of Federal Claims with “jurisdiction to render judgment on an action by an interested party

objecting to . . . the award of a contract or any alleged violation of statute or regulation in

connection with a procurement . . . .” 28 U.S.C. § 1491(b)(1). In such actions, the Court “shall

review the agency’s decision pursuant to the standards set forth in section 706 of title 5.” 28

U.S.C. § 1491(b)(4). “A bid protest proceeds in two steps.” Bannum, Inc. v. United States, 404

F.3d 1346, 1351 (Fed. Cir. 2005). First, a protestor must demonstrate error, meaning that the

agency violated section 706 of the Administrative Procedure Act. Id.; see also 5 U.S.C. §

706(2)(A) (requiring the reviewing court to “hold unlawful and set aside agency action, findings,

and conclusions found to be—arbitrary, capricious, an abuse of discretion, or otherwise not in

accordance with law . . .”). Second, such error must prejudice the protestor. Bannum, Inc., 404

F.3d at 1351.

7

“A government contract award may be set aside as erroneous under the arbitrary and

capricious standard if ‘(1) the procurement official’s decision lacked a rational basis; or (2) the

procurement procedure involved a violation of regulation or procedure.’” McVey Co. Inc. v.

United States, 111 Fed. Cl. 387, 402 (2013) (quoting Weeks Marine, Inc., 575 F.3d at 1358). To

show an agency acted arbitrarily or capriciously, a protestor must show the agency “‘entirely

failed to consider an important aspect of the problem, offered an explanation for its decision that

runs counter to the evidence before the agency, or [the decision] is so implausible that it could

not be ascribed to a difference in view or the product of agency expertise.’” Ala. Aircraft Indus.,

Inc.-Birmingham v. United States, 586 F.3d 1372, 1375 (Fed. Cir. 2009) (quoting Motor Vehicle

Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983)). “When a challenge is

brought on the second ground, the disappointed bidder must show ‘a clear and prejudicial

violation of applicable statutes or regulations.’” Impresa Construzioni Geom. Domenico Garufi

v. United States, 238 F.3d 1324, 1333 (Fed. Cir. 2001) (quoting Kentron Hawaii, Ltd. v. Warner,

480 F.2d 1166, 1169 (D.C. Cir. 1973)).

But error alone is not enough; prejudicial error to the protestor is required to set aside an

award. Glenn Def. Marine (ASIA), PTE Ltd. v. United States, 720 F.3d 901, 908 (Fed. Cir.

2013). “[T]here is no presumption of prejudice when a protestor demonstrates irrationality in an

agency decision.” Sys. Stud. & Simulation, Inc. v. United States, 22 F.4th 994, 998 (Fed. Cir.

2021). To establish prejudice, a protestor “must show that there was a substantial chance it

would have received the contract award but for the alleged error in the procurement process.”

REV, LLC v. United States, 91 F.4th 1156, 1163 (Fed. Cir. 2024) (internal citations and

quotations omitted). In order to show it had a substantial chance to receive the contract, the

protestor must show “that it is a qualified bidder and could compete for the contract.” Tinton

Falls Lodging Realty, LLC v. United States, 800 F.3d 1353, 1360 (Fed. Cir. 2015). Stated

differently, “the protestor’s chance of securing the award must not have been insubstantial.”

Info. Tech. & Applications Corp. v. United States, 316 F.3d 1312, 1319 (Fed. Cir. 2003).

Bid protests are generally decided on cross-motions for judgment on the administrative

record, pursuant to Rule 52.1 of the Rules of the United States Court of Federal Claims

(“RCFC”). RCFC 52.1 requires that the Court “make factual findings from the record evidence

as if it were conducting a trial on the record.” Bannum, Inc., 404 F.3d at 1354. Unlike a motion

for summary judgment, a genuine dispute of material fact does not preclude a judgment on the

administrative record. See id. at 1355–56. Therefore, in reviewing cross-motions for judgment

on the administrative record, “the court asks whether, given all the disputed and undisputed facts,

a party has met its burden of proof based on the evidence in the record.” Jordan Pond Co., LLC

v. United States, 115 Fed. Cl. 623, 630 (2014).

C. Acuity Has Not Established That It Has Standing Because the Agency’s OCI-

Related Exchanges with Summit Did Not Exceed the Solicitation’s Terms

The solicitation provided that “[o]ffers submitted in response to this solicitation shall

remain in effect not less than 365 days after the date specified for receipt by the Government.”

AR 1125. It is undisputed that Acuity’s proposal only reflected 60 days of validity and that

Acuity’s proposal was thus ineligible for award unless Acuity was permitted to modify its

proposal. It is also undisputed that unless Acuity can demonstrate to the Court that it should

8

have been permitted to fix this pricing issuing, Acuity does not have standing to challenge the

alleged errors in the procurement process that Acuity claims prejudiced it. See note 3 supra. In

order to get around its eligibility (and thus standing) problem, Acuity asserts that NASA was

required to conduct discussions with Acuity and that, through those discussions, Acuity could

have easily addressed its eligibility problem.

Although an agency is not generally required to conduct discussions, if an agency does

conduct discussions, it must do so with all offerors. FAR 15.306(d)(1) (requiring that once

discussions are initiated, they “must be conducted by the contracting officer with each offeror

within the competitive range.”). Acuity claims that the exchanges NASA had with Summit

regarding Summit’s OCI plan constituted discussions; therefore, NASA also had to have

discussions with Acuity. The key to this argument for Acuity is proving that the exchanges

between NASA and Summit regarding Summit’s OCI plan fall outside of the provision in the

solicitation that provided that NASA could have exchanges with an offeror about the offeror’s

OCI plan. Recall, this OCI plan carve-out language states that:

Additional requirements for eligibility have been established for this acquisition.

The Government may communicate with offerors about the eligibility

requirement(s) identified below outside of the evaluation process. This

communication does not constitute discussions as defined in FAR 15.306. If the

following eligibility requirements cannot be made acceptable to the Government,

the offeror will be considered ineligible for award:

Organizational Conflict of Interest (OCI) Plan in accordance with the Notice of

Potential Organizational Conflicts of Interest in Section L and FAR 9.504. The

proposed OCI plan shall be consistent with all other areas of the proposal.

Material inconsistencies between the plan and other proposal areas may render

the proposal invalid, resulting in an unacceptable proposal that is ineligible for

award.

AR 1153.

At first glance, this provision appears to run afoul of the FAR, because any exchanges

between NASA and an offeror that allow the offeror to revise its proposal would seem to be in

direct conflict with FAR § 15.306. 4 Under the FAR, if an award is intended to be made without

discussions, only limited exchanges are permitted. These limited exchanges, called

“clarifications,” allow offerors “the opportunity to clarify certain aspects of proposals . . . or to

resolve minor or clerical errors.” 48 C.F.R. § 15.306(a)(2). But “clarifications” do not allow for

proposal revisions. However, the solicitation’s carve-out clearly allows for proposal revisions in

order to enable “eligibility requirements [to] be made acceptable to the Government.” AR 1153.

Here, the only eligibility requirement covered by the carve-out was the OCI Plan, and allowing

an offeror to revise its OCI plan was certainly not a “minor or clerical error” as defined in FAR §

4

This provision appears to be a deviation as defined by the FAR. See 48 C.F.R. § 1.401. If that

is the case, the Administrative Record does not make clear if the procedures for deviations, both

individual and class deviations, were followed. See 48 C.F.R. §§ 1.403, 1.404.

9

15.306(a)(2). Instead, NASA reached out to Summit to have it make the following revisions to

its OCI Plan:

(1) Remove references to Section H.2 Clause, Limitation of Future Contracting, as

this clause was not included in the solicitation. Further, in those areas which relied

on references to this clause, make revisions such that the OCI Plan remains in

compliance with solicitation requirements.

(2) Provide further detail on how Summit will firewall employees with access to

sensitive information from others within the company, including measures it will

use to ensure that employees with access to sensitive information do not participate

on proposal teams for competitions in which the information would be

competitively useful.

AR 4567. Such revisions exceed what the FAR permits under clarifications and, because a

competitive range was not established, are also not covered by either of the other two categories

of exchanges permitted by FAR § 15.306: communications and discussions. See 48 C.F.R. §§

15.306(b) & (d).

Although the carve-out likely exceeds the exchanges permitted by the FAR (and there is

no evidence that the procedures for a deviation were followed, see note 4 supra), Acuity did not

protest NASA’s authority to include the carve-out as a provision in the solicitation. Quite the

opposite; Acuity expressly waived the argument in its MJAR. See Pl.’s MJAR at 13 n.2 (“In an

abundance of caution, and to avoid a debate later, Acuity is not challenging the Solicitation

provision that allowed for these types of communications.”); see also CardSoft v. Verifone, Inc.,

769 F.3d 1114, 1119 (Fed. Cir. 2014) (“Arguments that are not appropriately developed in a

party’s briefing may be deemed waived.”). As such, the propriety of the carve-out vis-à-vis the

FAR is not at issue in this protest.

But what Acuity does challenge is how the carve-out was applied during this

procurement. Acuity’s argument unfolds into two steps. First, Acuity argues that the exchanges

between Summit and NASA went beyond the scope of the carve-out because NASA’s

“communications about Summit’s OCI plan did not address inconsistencies between the plan and

the rest of Summit’s proposal.” Pl.’s MJAR at 14. Acuity’s position is that the “[t]he

Solicitation’s exception only extended to communications with offerors about inconsistencies

between the OCI plan and the rest of the offeror’s proposal.” Id. at 13 (citing AR 1153). Acuity

argues that the first sentence—“Organizational Conflict of Interest (OCI) Plan in accordance

with the Notice of Potential Organizational Conflicts of Interest in Section L and FAR 9.504[,]”

AR 1153—is a header and the next sentences “are specifics that are meant to modify the general

statement that introduces the paragraph.” Pl.’s MJAR at 13 (citing Dow Chem Co. v. Nova

Chems. Corp. (Can.), 458 F. App’x 910, 914 (Fed. Cir. 2012)). Acuity argues the exchanges and

revisions proposed by NASA to Summit’s OCI plan were not about inconsistencies between

Summit’s proposal and its OCI plan but rather were 1) about “an inconsistency between

Summit’s OCI plan and the Solicitation . . . [and 2) a request] for additional information to be

included in the OCI plan.” Id. at 14–15 (emphasis omitted). Therefore, according to Acuity,

10

these requests regarding Summit’s OCI plan were not covered by the carve-out and thus

constituted discussions governed by FAR § 15.306(d). See id.

Second, Acuity argues that because the exchanges between NASA and Summit regarding

Summit’s OCI plan were, in fact, discussions, Acuity was entitled to discussions as well. As

Acuity notes “[i]t is well settled that the government may not hold discussions with just one

offeror.” Id. at 15. (citing ENGlobal Gov’t Servs., Inc. v. United States, 159 Fed. Cl. 744, 765

(2022); Afghan Am. Army Servs. Corp. v. United States, 90 Fed. Cl. 341, 361 (2009); Info. Tech.

& Applications Corp., 316 F.3d at 1318)). Acuity represents that if it had been given the chance

to have discussions it would have been able to cure its eligibility issue by correcting the

expiration date of its offer. Acuity, citing Carahsoft Tech. Corp. v. United States, 86 Fed. Cl.

325, 341–42 (2009), argues that NASA “was required to raise [Acuity’s validity date eligibility

issue] in discussions, and [that it was] something Acuity could easily cure.” Pl.’s MJAR at 15.

NASA even seemed to acknowledge as much: “[w]ere discussions determined to be necessary

and were the Acuity Edge proposal determined to be one of the most highly rated proposals,

Acuity Edge would have had an opportunity as part of its final proposal revision to extend the

validity date of its proposal.” AR 4872.

Unfortunately for Acuity, its argument fails on the first step. The language of the carve-

out does not limit the covered exchanges to only inconsistencies between an offeror’s OCI plan

and the rest of its proposal. Rather, there is only one reasonable reading of the provision, which

is to place exchanges between NASA and an offeror about an offeror’s OCI plan outside of the

realm of discussions. See ECF No. 33 at 3–4. Specifically, the provision provides that NASA

“may communicate with offerors about the eligibility requirement(s) identified below outside of

the evaluation process” and that such a “communication does not constitute discussions as

defined in FAR 15.306.” AR 1153. The only eligibility requirement identified in the solicitation

was the OCI plan: “Organizational Conflict of Interest (OCI) Plan in accordance with the Notice

of Potential Organizational Conflicts of Interest in Section L and FAR 9.504.” Id. Thus, under

the terms of the carve-out, NASA’s exchanges with Summit concerning Summit’s OCI plan did

not constitute discussions. 5

5

Defendant-Intervenor argued that “Plaintiff’s interpretation conflicts with FAR 9.504 . . .

[which] specifically permits one-on-one exchanges with an offeror to discuss OCI concerns and adjust

mitigation, without constituting the opening of discussion and without limitation[.]” ECF No. 30 at 3

(emphasis in original). Defendant-Intervenor misreads the FAR. FAR 9.504(e) states:

The contracting officer shall award the contract to the apparent successful offeror unless a

conflict of interest is determined to exist that cannot be avoided or mitigated. Before

determining to withhold award based on conflict of interest considerations, the contracting

officer shall notify the contractor, provide the reasons therefor, and allow the contractor a

reasonable opportunity to respond. If the contracting officer finds that it is in the best

interest of the United States to award the contract notwithstanding a conflict of interest, a

request for waiver shall be submitted in accordance with 9.503. The waiver request and

decision shall be included in the contract file.

48 C.F.R. § 9.504(e). This section is only applicable upon two things happening: 1) a determination of an

apparent successful offeror, and 2) a finding of a conflict of interest. Id.; see also A Squared Joint

11

Acuity attempts to get around this reading of the carve-out by asserting that the two

sentences that follow the OCI plan language limit what aspects of an OCI plan are covered by

the carve-out. Immediately following the sentence that Acuity calls a header (quoted above), the

solicitation states that “[t]he proposed OCI plan shall be consistent with all other areas of the

proposal. Material inconsistencies between the plan and other proposal areas may render the

proposal invalid, resulting in an unacceptable proposal that is ineligible for award.” Id.

According to Acuity, these two sentences limit the exchanges NASA could have with an offeror

about an OCI plan to exchanges regarding inconsistencies between an offeror’s OCI plan and its

proposal. Acuity’s reading is unreasonable.

As the government points out in its reply brief, the only reasonable reading of the

sentences that Acuity references is that those two sentences outline “the consequence for offerors

should their revisions to the OCI Plan create inconsistences with other areas of their proposal.”

ECF No. 33 at 4. In other words, the sentences are a warning to offerors not to make changes to

their OCI plans that are inconsistent with their proposals during the course of any OCI plan

exchanges with NASA because any inconsistencies may make their proposals ineligible for

award. For several reasons, these sentences cannot reasonably be interpreted as a limit, as

Acuity argues, on what aspects of an OCI plan about which NASA could reach out to an offeror.

First, these exchanges were to occur “outside of the evaluation process.” Id. If the exchanges

were occurring outside of the evaluation process, NASA would not be concerned with what was

in an offeror’s proposal. But that is precisely what Acuity argues these exchanges are limited

to—an offeror’s proposal and whether that proposal is consistent with the OCI plan. Second,

Acuity’s reading implies that not only could an offeror revise its OCI plan as part of these

exchanges, but that it could revise its proposal as well if proposal revisions were needed to create

consistency between the OCI plan and the proposal. Thus, Acuity’s reading would effectively

allow NASA to communicate with an offeror about any aspect of an offeror’s proposal so long as

that aspect related in some way to the OCI plan. This is an unreasonably expansive reading of

the carve-out. Third, Acuity’s reading makes much of the verbiage in the sentence it calls a

“heading” mere surplusage. See Arizona v. United States, 216 Ct. Cl. 221, 235–36 (1978) (“[A]n

interpretation which gives a reasonable meaning to all parts will be preferred to one which leaves

a portion of it useless, inexplicable, inoperative, void, insignificant, meaningless, superfluous, or

achieves a weird and whimsical result.”). What is the purpose of the “heading” including the

language “in accordance with the Notice of Potential Organizational Conflicts of Interest in

Section L and FAR 9.504,” if the carve-out is not intended to allow NASA to communicate with

an offeror about issues that make its OCI plan not in accordance with the Notice of Potential

Organizational Conflicts of Interest in Section L and FAR 9.504? If Acuity’s reading were

reasonable, then a header simply stating “Organizational Conflict of Interest (OCI) Plan” would

both make more sense and avoid the inclusion of unnecessary verbiage. Fourth, Acuity’s

interpretation makes the third sentence of the carve-out surplusage as well. The third sentence

states that “[m]aterial inconsistencies between the plan and other proposal areas may render the

Venture v. United States, 136 Fed. Cl. 321, 328 (2018) (“FAR § 9.504(e) applies when an apparent

successful offeror has been identified and the CO learns that the apparent successful offeror has OCI. If

the OCI cannot be avoided or mitigated, the offeror can be eliminated.”) At the time of the exchanges

between NASA and Summit, neither of these prongs had been satisfied. Thus, FAR 9.504 does not apply.

12

proposal invalid, resulting in an unacceptable proposal that is ineligible for award.” AR 1153.

But the sentence from the carve-out leading into the OCI paragraph already states the same: “[i]f

the following eligibility requirements cannot be made acceptable to the Government, the offeror

will be considered ineligible for award.” Id. Thus, if the Court were to adopt Acuity’s reading,

it would make these two sentences redundant.

In short, Acuity’s reading of the carve-out is unreasonable. The only reasonable reading

of the carve-out put before the Court by the parties is that the first sentence—“Organizational

Conflict of Interest (OCI) Plan in accordance with the Notice of Potential Organizational

Conflicts of Interest in Section L and FAR 9.504”—was a list item that listed OCI plans as a

requirement that was covered by the carve-out and that the two sentences following this list item

were a warning to offerors as discussed above. Any confusion regarding this reading is likely

the result of this being a one-item list. But the language of the carve-out appears to be

boilerplate language, which indicates that it could have been followed by more than one

requirement. Id. (specifically, the language provides that “[t]he Government may communicate

with offerors about the eligibility requirement(s) identified below” (emphasis added)).

Once Acuity’s unreasonable reading of the carve-out is put aside, Acuity’s assertion—

that NASA conducted discussions with Summit regarding its OCI plan and thus was required to

conduct discussion with Acuity as well—clearly fails. Rather than constituting discussions,

NASA’s exchanges with Summit regarding its OCI plan fell directly within the solicitation’s

carve-out. Acuity, therefore, was not entitled to discussions and its proposal remains ineligible

for award. Accordingly, the alleged errors with NASA’s evaluation of proposals are not

redressable by the Court even if proved and thus Acuity lacks standing to challenge those alleged

errors. “To determine whether an injury is redressable [the Court] consider[s] the relationship

between the judicial relief requested and the injury suffered.” Murthy v. Missouri, 144 S. Ct.

1972, 1995 (2024) (cleaned up) (quoting California v. Texas, 593 U.S. 659, 671 (2021)). Here,

the relief requested cannot be granted. Even if the Court fully agreed with Acuity’s arguments

on past performance and incumbency capture rate, there is no redressable injury because Acuity

remains ineligible for award. Any order from the Court directing NASA to change its ratings or

redo its evaluation would have no effect on Acuity’s chances of contract award. Even if proved,

the alleged injuries are not redressable because the status quo would remain in place. See Renal

Physicians Ass’n, 489 F.3d at 1278. Based on its pleadings, the only way for Acuity to have

standing was for it to demonstrate that NASA was required to conduct discussions with all

offerors in the competitive range, which in turn would have permitted Acuity to cure its

eligibility issue. Only then would the Court’s action on Acuity’s additional arguments

potentially lead to relief. But that is not the case. The government proffered a reasonable

interpretation regarding the carve-out; the burden was on Acuity to convince the Court that its

interpretation was also reasonable, and Acuity has failed to carry that burden. Thus, the Court

cannot act. To act otherwise would be to overstep the bounds of the judicial power. See Spokeo,

Inc., 578 U.S. at 338. The Court declines to do so.

13

D. Even if Acuity Had Standing, it Did Not Demonstrate Prejudice with Regard to the

Procurement Errors it Alleges

Even had Acuity established that it had standing, Acuity’s additional arguments suffer

from several issues that likely would not entitle it to judgment on the administrative record in

any event. As Acuity has failed to establish standing, the Court will not address Acuity’s merits

arguments in total. The Court will, however, offer some observations on the merits prejudice

issues with Acuity’s additional protest grounds. Acuity alleges two main errors with regard to

the procurement. First, Acuity challenges NASA’s decision to relax the complexity threshold for

subcontractor past performance references. Pl.’s MJAR at 16. The complexity requirement

stated:

A referenced contract’s complexity relevancy will be determined based on how

well the complexity of the effort performed (e.g., performance across multiple

geographic locations, volume and types of work products processed, developed,

and delivered simultaneously) aligns with the effort delineated in Attachment J-1

and other pertinent sections of the solicitation. For the offeror, to be considered

relevant for complexity, the referenced contract shall demonstrate performance at

a single geographic location and success handling a moderate (i.e., 1,250 or more

work products annually) volume of work products processed, developed, and

delivered simultaneously or performance at multiple geographic locations and

success at handling a small (i.e., 800 or more work products annually) volume of

work products processed, developed, and delivered simultaneously.

AR 1119. Acuity argues that it believed that all submitted references—both of the offeror and

proposed subcontractors—had to meet the stated complexity threshold for offerors and submitted

its past performance references based on that understanding. Pl.’s MJAR at 17. However,

NASA, during proposal evaluation, changed the complexity requirement to include a different

complexity threshold for subcontractor references without amending the solicitation. AR 4372.

Acuity is correct; NASA’s actions likely were improper. FAR 15.305(a) states “[a]n

agency shall evaluate competitive proposals and then assess their relative qualities solely on the

factors and subfactors specified in the Solicitation.” 48 C.F.R. § 15.305(a). Moreover, if NASA

wanted to change its evaluation criteria, it was required to amend the solicitation to reflect the

changed criteria. 48 C.F.R. § 15.206(a) (“When, either before or after receipt of proposals, the

Government changes its requirements or terms and conditions, the contracting officer shall

amend the solicitation.”). When an agency uses an unstated evaluation criterion, it acts

irrationally. See Golden IT, LLC v. United States, 165 Fed. Cl. 676, 686 (2023) (“An agency

decision is also arbitrary and capricious if the decision is a product of the agency’s application of

unstated evaluation criteria.”). Here, NASA used an unstated evaluation criterion: the newly

created subcontractor complexity threshold. 6 Acuity, however, failed to demonstrate how the

use of this unstated evaluation criterion prejudiced it.

6

The government’s argument on this point is unavailing. The government argues for broad

deference, Gov.’s MJAR at 19–20, arguing “[i]t is well settled that the solicitation need not identify

criteria intrinsic to the stated evaluation factors, and agencies retain great discretion in determining the

14

Acuity admitted in its MJAR that “[it] understood [the complexity requirement] to mean

that all references had to meet the stated threshold.” Pl.’s MJAR at 17. In other words, Acuity

represents that it believed all past performance references (both for the offeror and any

subcontractors) had to meet the complexity threshold for offerors. However, if this was, in fact,

Acuity’s interpretation, Acuity has failed to show how it was prejudiced. As, “there is no

presumption of prejudice when a protestor demonstrates irrationality in an agency decision[,]”

Sys. Stud. & Simulation, 22 F.4th at 998, the burden remains on the protestor to show such

prejudice. See Bannum, Inc., 404 F.3d at 1353. Acuity needed to show “that there was a

‘substantial chance’ it would have received the contract award but for” the unstated evaluation

criterion. Id. Given the facts, it seems as though that would be almost impossible. Acuity was

rated “Very High Confidence” for the Past Performance factor, AR 4419, which is the highest

rating for this factor, AR 1158–59. Acuity argues that if it had been able to submit a difference

reference “it likely would have been deemed relevant and garnered Acuity a strength.” Pl.’s

MJAR at 19. But based on Acuity’s admitted understanding of the provision, it is unclear to the

Court (and Acuity failed to offer any evidence to support) how Acuity could submit another

reference to garner a strength when it failed to submit references that comported with its alleged

understanding of the provision to begin with. See Gov.’s MJAR at 22–24. 7 As the government

informed the Court at oral argument, all of Summit’s subcontractors met the higher offeror

criteria for complexity, so Acuity was the only party to benefit from the changed criteria. See Tr.

85:3–85:7. Had Acuity argued that it submitted subcontractor references based on an

understanding that the solicitation contained no requirement for subcontractor complexity to be

relevant, this potentially could establish prejudice. 8 But it did not. As such, Acuity would still,

if it had standing, fail to show that but for NASA’s improperly changed evaluation criteria, it

would have had a substantial chance at contract award.

Acuity’s second alleged procurement error is to the evaluation of incumbency capture.

Acuity asserts that it proposed a incumbency capture rate and that it should have been

awarded a strength for its ability to capture all incumbent staff. Pl.’s MJAR at 20–21. Acuity

scope of a given evaluation factor,” id. at 20 (quoting Harmonia Holdings Grp., LLC v. United States,

153 Fed. Cl. 245, 255 (2021)). This is incorrect. While it may be the case that an agency does not have

to describe every evaluation criterion for every subfactor, when a solicitation says that it will evaluate a

subfactor based on the following criteria and then the agency changes those same criteria to something

different it runs afoul of the FAR. Either NASA made a mistake in the complexity requirement that is

obvious on its face, leading to a Blue & Gold issue, or it changed the evaluation criteria in conflict with

the solicitation. Regardless of what explanation the government proffers, NASA changed the

requirements for complexity.

7

During oral argument, Acuity admitted that “[t]here’s no doubt we benefit from the way they

did [the past performance evaluation for subcontractor complexity] with the ones we submitted.” Tr.

80:4–80:5. And the government highlighted Acuity’s prejudice problem at oral argument as well: “[i]n

fact, were Acuity Edge to prevail and we applied the offeror criteria, they would have lost two references.

They would have lost a strength, and they would not have been found equal on this factor, and they

actually would have dropped behind Summit on all three evaluation factors.” Tr: 84:17–84:22. Thus,

there is no harm to Acuity from this error. Absent a showing of harm specific to the alleged error, there is

no prejudice to the protestor. See Labatt Food Serv. v. United States, 577 F.3d 1375, 1380 (Fed. Cir.

2009).

15

argues that one evaluator believed Acuity should have been awarded a strength, but the SEB

“decided to take that strength away ‘after discussion.’” Id. at 21 (quoting AR 4141). Acuity

claims that this failure to document why the strength was taken away conflicts with APA-

required documentation requirements. Id. at 21–22. Regardless of the accuracy of Acuity’s

argument—which is questionable—Acuity once again fails to demonstrate prejudice. The

incumbency capture rating was not a standalone factor but rather was a subfactor of management

and compensation approach, which was itself a subfactor of the mission suitability factor, AR

1103–08, which was to be “considered in tandem with the offeror’s proposed total compensation

plans.” Gov.’s MJAR at 26. Acuity’s own proposal makes this clear. Incumbent capture is

discussed under “MCA-1(A) Total Compensation Plan (TCP) Overview[,]” “MCA-1(B) Sources

of Staffing[,]” and “MCA-1(C) Staff Recruiting and Retention Approach[.]” AR 1250–51.

While certainly a relevant criterion, Acuity failed to demonstrate how such a minor factor could

make a large enough impact on the ratings to create prejudice to Acuity. Put another way, the

Court is not convinced that but for the so-called “removal of the incumbency capture strength,”

Acuity would have had a substantial chance to receive the contract award. See Bannum, Inc.,

404 F.3d at 1353.

More importantly, it is likely that if Acuity was given a strength for its proposed

capture rate, then Summit would have been given a strength for its proposed capture rate as well.

Gov.’s MJAR at 26, 27 (“Summit may also have been awarded a strength on this basis,

nullifying any comparative advantage that Acuity asserts.”). First, Summit also effectively

proposed a incumbency capture rate: “We capture all qualified incumbents and provide the

PM from Summit’s own workforce. While our initial plan is to provide a PM through our own

staff, we are amenable to capturing the incumbent PM, if possible and desired by NASA.” AR

2871 (emphasis added). Second, even to the extent that this proposal cannot be read as

proposing incumbency capture, it definitely provides for incumbency capture, and

Acuity failed to demonstrate that its incumbency capture rate was so far superior to a

capture rate that it either was worthy of a strength or that a capture rate would not have also

garnered the same strength. In short, Acuity failed to demonstrate prejudice on this point even

assuming it had standing and could demonstrate error.

CONCLUSION

For the reasons set forth above, Acuity has failed to establish that it has standing to bring

the instant protest. Accordingly, Acuity’s complaint is dismissed for lack of standing, and the

Clerk shall enter JUDGMENT accordingly.

IT IS SO ORDERED.

s/ Zachary N. Somers

ZACHARY N. SOMERS

Judge

16

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.