Opinion

W & W Fiberglass Tank Co v. Reed Industrial Systems L L C

Court
District Court, W.D. Louisiana
Filed
Jul 30, 2024
Cited by
0 cases
Authority
More cited than 31.4%

illustrating that an “artist’s obligation to use his skill in painting [a] picture” is an obligation “to do”

How later courts described this case

  • illustrating that an “artist’s obligation to use his skill in painting [a] picture” is an obligation “to do”
  • finding that a corporation that performed the “design and engineering” of an elevator fell within the scope of Louisiana Revised Statute 9:2772

Written by the judges who cited it.

The opinion

UNITED STATES DISTRICT COURT

WESTERN DISTRICT OF LOUISIANA

SHREVEPORT DIVISION

______________________________________________________________________________

W&W FIBERGLASS TANK CIVIL ACTION NO. 22-5837

COMPANY

VERSUS JUDGE DONALD E. WALTER

REED INDUSTRIAL SYSTEMS, LLC MAGISTRATE JUDGE HORNSBY

______________________________________________________________________________

MEMORANDUM RULING

Before the Court is a motion for summary judgment filed by Defendant Reed Industrial

Systems, LLC (“Reed”). See Record Document 30. Plaintiff W&W Fiberglass Tank Company

(“W&W”) filed an opposition. See Record Document 34. For the reasons stated below, Reed’s

motion for summary judgment (Record Document 30) is GRANTED.

BACKGROUND

On August 13, 2014, W&W entered into a contract with Reed for the design and installation

of a “Stack and Ventilation System” for W&W’s manufacturing plant located in Pampa, Texas.

Record Document 30-4 at 1–2. The total contract price was $672,590.00. See id. Reed charged

$540,316.00 for the ventilation system and $132,274.00 for the installation. See id. For the cost of

the ventilation system, Reed charged approximately $67,259.00 to design and engineer it. See

Record Document 30-3 at 2. The ventilation system was a “custom design” by Reed for a single

application at W&W’s specific location. Id. After designing, Reed hired subcontractors to fabricate

the component parts. See id. The construction of the ventilation system was completed in May of

2015, and the operations of the system began in June of 2015. See Record Document 1 at 3.

The original design for the ventilation system allegedly included “two 111-feet tall exhaust

stacks which were designed to be anchored to a concrete foundation adjacent to the manufacturing

plant with multiple vertical sections joined by sixteen one-half inch bolts per joint and supported

by guy-wires.” Id. at 2. W&W asserts that the guy-wires were not suitable for the layout of W&W’s

plant, and therefore, W&W and Reed entered into a change order on or about October 19, 2014.

See Record Document 1 at 3. The new design called for twenty one-half inch bolts connecting the

vertical sections of each stack to provide additional security and stability in the absence of the guy-

wires. See id.

On October 28, 2021, W&W alleges that one of the two ventilation stacks failed at a section

joint about thirty-five feet above ground level, blew over, and damaged both the stack and W&W’s

manufacturing plant. See id. W&W claims that the stack did not comply with the revised plans,

which called for each section of the stacks to be secured with twenty one-half inch bolts. See id.

Rather, W&W asserts that the sections of the stack were secured to one another with sixteen one-

half inch bolts. See id.

As a result, W&W filed suit against Reed, asserting that the stack was defectively

manufactured. W&W seeks relief pursuant to the Louisiana Products Liability Act and the

Louisiana law of redhibition. Reed filed this motion for summary judgment arguing that W&W’s

claims are perempted pursuant to Louisiana Revised Statute 9:2772.

LAW AND ANALYSIS

A. Summary Judgment Standard.

Summary judgment is proper pursuant to Rule 56 of the Federal Rules of Civil Procedure

when “there is no genuine dispute as to any material fact and the movant is entitled to judgment

as a matter of law.” Quality Infusion Care, Inc. v. Health Care Serv. Corp., 628 F.3d 725, 728 (5th

Cir. 2010). A fact is “material” if proof of its existence or nonexistence would affect the outcome

of the lawsuit under applicable law in the case. See Anderson v. Liberty Lobby, Inc., 477 U.S. 242,

248, 106 S. Ct. 2505, 2510 (1986). A dispute about a material fact is “genuine” if the evidence is

such that a reasonable fact finder could render a verdict for the nonmoving party. See id. “[A] party

seeking summary judgment always bears the initial responsibility of informing the district court

of the basis of its motion, and identifying those portions of ‘the pleadings, depositions, answers to

interrogatories, and admissions on file, together with the affidavits, if any,’ which it believes

demonstrate the absence of a genuine issue of material fact by pointing out that the record contains

no support for the non-moving party’s claim.” Celotex Corp. v. Catrett, 477 U.S. 317, 323, 106 S.

Ct. 2548, 2553 (quoting Fed. R. Civ. P. 56(c)).

B. Peremption.

Peremption is a period of time fixed by law for the existence of a right, and it may not be

renounced, interrupted, or suspended. See Naghi v. Brener, 2008-2527, 17 So. 3d 919, 923 (La.

6/26/09) (citing La. Civ. Code arts. 3458, 3461). “Unless timely exercised, the right is extinguished

upon the expiration of the peremptive period.” Id. (citing La. Civ. Code art. 3458). Because

peremptive statutes are strictly construed against peremption and in favor of the claim, when there

is more than one possible construction, “the one that maintains enforcement of the claim or action,

rather than the one that bars enforcement should be adopted.” Id. (internal citations omitted).

Louisiana law provides for a five-year peremptive period for cases arising out of

construction contracts:

[N]o action . . . including but not limited to an action for failure to warn, to recover

on a contract, or to recover damages, or otherwise arising out of an engagement of

planning, construction, design, or building immovable or movable property . . .

shall be brought . . . against any person performing or furnishing the design,

planning, supervision, inspection, or observation of construction or the construction

of immovables, or improvement to immovable property . . . .

(1) (a) More than five years after the date of registry in the mortgage office of

acceptance of the work by owner.

(b) If no such acceptance is recorded within six months from the date the owner has

occupied or taken possession of the improvement, in whole or in part, more than

five years after the improvement has been thus occupied by the owner.

La. R.S. 9:2772(A). For this statute to apply, Reed must establish (1) that more than five years

have elapsed since the owner recorded acceptance of the work, or that more than five years and

six months have elapsed since the owner took possession of the building; (2) that Reed

manufactured the ventilation system pursuant to a construction contract, as opposed to a sales

contract; and (3) that the ventilation system was either immovable property or an improvement

thereto. See Swope v. Columbian Chems. Co., 281 F.3d 185, 201 (5th Cir.2002); Summerfield v.

Harnischfeger Indus., Inc., No. 97-3683, 1998 WL 726080, *2 (E.D.La.1998); Poree v. Elite

Elevator Servs., Inc., 665 So.2d 133, 135 (La.App. 4 Cir. 11/16/95); Smith v. Arcadian Corp., 657

So.2d 464, 467 (La.App. 3 Cir. 5/31/95); ConstructionSouth, Inc. v. Fire Windows & Doors, Inc.,

No. 12-1258, 2013 WL 3242728, at *2 (E.D. La. June 25, 2013). W&W does not dispute the first

and third requirements. Thus, the disposition of Reed’s motion for summary judgment depends

entirely on whether the contract was a construction contract or a sales contract.

Section 9:2772 applies only to contracts of construction, not to contracts of sale. See Riley

Stoker Corp. v. Fid. & Guar. Ins. Underwriters, Inc., 26 F.3d 581, 591 (5th Cir.1994) (citing

DeWoody v. Citgo Petrol. Corp., 604 So.2d 92, 99 (La.App. 3d Cir. 6/24/92). To determine

“whether a contract is a construction contract or a sales contract, Louisiana courts generally weigh

the economics of the situation to determine whether the primary obligation is one ‘to give’ [sales

contract] or ‘to do’ [construction contract].” Harris v. Black Clawson Co., 961 F.2d 547, 553 (5th

Cir.1992) (internal citations omitted). For example, the sale of an off-the-shelf product, such as

“air conditioners, glass windows and doors,” is primarily an obligation to give. Id. Conversely, an

“artist’s obligation to use his skill in painting [a] picture” is an obligation “to do.” KSLA-TV, Inc.

v. Radio Corp. of Am., 501 F. Supp. 891, 894 (W.D. La. 1980). When a contract contains elements

of both a construction contract and a sales contract, the Court must analyze the contract to

determine which of the two obligations is fundamental. Smith, 657 So.2d at 468.

The determination of whether the contract is a sales contract or a construction contract is

made on a case-by-case basis. See Poree, 665 So. 2d at 135. Courts sometimes make this

determination based on a three-factor test:

First, in a contract to build, the “buyer” has some control over the specifications of

the object. Second, the negotiations in a contract to build take place before the

object is constructed. Third, and perhaps most importantly, a building contract

contemplates not only that one party will supply the materials, but also that that

party will furnish his skill and labor in order to build the desired object.

Duhon v. Three Friends Homebuilders Corp., 396 So.2d 559, 561 (La.App. 3d Cir. 3/11/81).

Courts may also utilize the “value test” to determine “whether the labor expended in constructing

the item, or the materials incorporated therein, constitute the ‘principal value of the contract.’”

Alonzo v. Chifici, 526 So. 2d 237, 241 (La.App. 5 Cir. 4/18/88). Lastly, courts may also pay

particular attention to “the extent to which the manufacturer custom designed the product for the

purchaser,” or whether the product was merely “a stock item.” Summerfield, 1998 WL 726080, at

*4; Poree v. Elite Elevator Servs., Inc., 711 So. 2d 816, 818–19 (La. App. 4 Cir. 4/8/98).

Both parties rely on the Louisiana Fourth Circuit’s ruling in Poree v. Elite Elevator

Services, Inc., 665 So.2d 133 (La. App. 4 Cir. 11/16/95). In Poree, a plaintiff was injured when

she attempted to get out of an elevator at a high school. See id. at 134. The plaintiff sued an elevator

company for negligence, and the elevator company argued that the claim was perempted pursuant

to Louisiana Revised Statute 9:2772. See id. To build the school, the school board contracted with

a contractor. See id. at 135. Then, the contractor subcontracted an elevator company because the

contractor “lacked the technical knowledge and skill necessary for construction of an elevator. . .

.” Id. Therefore, the elevator company built and installed the elevator in the high school. See id.

As a result, the court held that the evidence submitted “clearly establishe[d]” that the elevator

company was a subcontractor within the meaning of Louisiana Revised Statute 9:2772, and

therefore, all claims against the elevator company were perempted. Id. at 135–136.

Three years later, the Louisiana Fourth Circuit issued another ruling, Poree v. Elite Elevator

Services, Inc., 711 So. 2d 816 (La. App. 4 Cir. 4/8/98), addressing whether claims against a

corporation that furnished designing, planning, and engineering services for the elevator were also

perempted pursuant to Louisiana Revised Statute 9:2772. The court acknowledged that the elevator

was “constructed, installed and erected” by the elevator company, not the corporation. Id. at 819.

However, the court explained that the elevator was not a stock item; it was “custom-designed and

engineered to meet the school’s particular requirements” by the corporation. Id. As a result, the

court found that the corporation fell within the scope of Louisiana Revised Statute 9:2772 because

the corporation had performed the “design and engineering” of the elevator, even though it had

not performed the “construction, installation, or inspection” of the elevator. Id.

In contrast, the Louisiana Second Circuit examined whether a product manufacturer of a

central heating unit can receive the benefits of Louisiana Revised Statute 9:2772. See Jones v.

Crane Co., 653 So. 2d 822, 826 (La. App. 2 Cir. 4/5/95). According to the defendant’s affidavits,

the evidence showed that the product manufacturer did not install the unit nor design or

manufacture the unit specifically for that particular house. See id. at 7. As a result, the court found

that the sale of a standard heating unit was a sales contract “to give” because “[t]he unit appear[ed]

to be a typical central heating unit.” Id. Thus, the product manufacturer did not fall within the

scope of Louisiana Revised Statute 9:2772. See id.

Reed submitted an affidavit from Jimmie Talbot (“Talbot”), who is “employed as a Design

Engineer for Reed since August 11, 2003.” Record Document 30-3 at 1. Talbot testified that he

designed the ventilation system based on the contract between W&W and Reed. See id. at 2.

Additionally, Reed submitted an affidavit from Thomas Kerr (“Kerr”), the owner of Reed. See

Record Document 30-3 at 1. Kerr testified that the ventilation system was a custom design for a

single application at W&W’s specific location. See id. Kerr further testified that all “custom

designs are designed and fabricated by Reed from scratch.” Id. Additionally, Kerr stated that the

ventilation system is not one carried by Reed’s inventory and that Reed hired subcontractors to

fabricate the component parts. See id. Lastly, Kerr attested that of the total contract price of

$672,590.00, Reed charged approximately $67,259.00 for the design and $132,274.00 for the

installation of the ventilation system. See id. at 2. Therefore, Reed’s position is that it falls within

the scope of the peremptive statute because all obligations performed by Reed were obligations

“to do.”

W&W counters and argues that the delivery of the stack and ventilation system was the

predominant object of the contract, not the installation. See Record Document 34 at 2. To support

this position, W&W asserts that the installation cost of the contract was $132,274.00, which is less

than 20% of the total contract price of $672,590.00. See id. at 7. Additionally, W&W maintains

that the contract does not read like a typical construction contact because it lacks insurance

requirements, payment and performance bond requirements, and indemnification and defense

provisions in the event of injuries during performance. See id. Therefore, it is W&W’s position

that Reed is not entitled to the benefit of Louisiana Revised Statute 9:2772 because the contract is

a contract “to give.”

The undisputed facts are that the contract required Reed to custom design the ventilation

system for W&W’s specific location and install the ventilation system. Reed’s obligation to use

its design and engineering skills to create the ventilation system is akin to an artist’s obligation to

use his skill to paint a picture. See KSLA-TV, 501 F. Supp. at 894 (illustrating that an “artist’s

obligation to use his skill in painting [a] picture” is an obligation “to do”). Therefore, the Court

finds that the predominant objects of the contract were obligations “to do.” Additionally, the Court

finds that Reed falls within the scope of Louisiana Revised Statute 9:2772 because it performed

the design and installation of the ventilation systems. See generally Poree, 711 So.2d at 819

(finding that a corporation that performed the “design and engineering” of an elevator fell within

the scope of Louisiana Revised Statute 9:2772). Since the peremption statute is applicable, the

burden shifts to W&W to show the action has not prescribed. W&W fails to meet this burden.

Thus, W&W’s claims against Reed are perempted pursuant to Louisiana Revised Statute 9:2772.

CONCLUSION

For the foregoing reasons, IT IS ORDERED that Reed’s motion for summary judgment

(Record Document 30) is GRANTED. All W&W’s claims filed against Reed are DISMISSED.

A judgment consistent with the instant Memorandum Ruling shall be issued herewith.

THUS DONE AND SIGNED in Shreveport, Louisiana, this 30th day of July, 2024.

U bu.

bral

UNITED STATES DISTRICT JUDGE

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.