Opinion

Waveseer of Oregon, LLC v. Deschutes County

  • 308 Or. App. 494
  • 482 P.3d 212
Court
Court of Appeals of Oregon
Filed
Jan 13, 2021
Status
Published
On the bench
Lagesen
Cited by
2 cases
Authority
More cited than 71.5%

rejecting procedural challenge where county did not identify a source of law that would allow the court to conclude that LUBA’s procedural choices were unlawful

How later courts described this case

  • rejecting procedural challenge where county did not identify a source of law that would allow the court to conclude that LUBA’s procedural choices were unlawful

Written by the judges who cited it.

The opinion

494

Argued and submitted November 12, 2020, affirmed January 13, 2021

WAVESEER OF OREGON, LLC,

Respondent,

v.

DESCHUTES COUNTY,

Petitioner.

Land Use Board of Appeals

2020038; A174515

482 P3d 212

Petitioner Deschutes County seeks judicial review of a decision of the

Land Use Board of Appeals (LUBA). LUBA reversed a decision by the board of

county commissioners denying respondent Waveseer of Oregon, LLC’s applica-

tion to develop a marijuana production facility. The board denied the applica-

tion based on its conclusion that the proposed facility would be located within

1,000 feet of two “youth activity center[s],” in violation of Deschutes County Code

18.116.330(B)(7)(a)(iv). LUBA reversed, concluding, among other things, that

the county’s interpretation and application of the term “youth activity center”

rested on uncodified criteria in violation of the codification requirement in ORS

215.416(8)(a). On judicial review, the county assigns error to, among other things,

LUBA’s determination that the county’s interpretation and application of the

term “youth activity center” violated the codification requirement. Held: LUBA

did not err in concluding that the county’s interpretation of the term “youth activ-

ity center” violated the statutory codification requirement. Nothing in the county

code signaled how the county interpreted the term—its standards were instead

promulgated through the process of adjudication, which did not satisfy the codi-

fication requirement.

Affirmed.

D. Adam Smith argued the cause for petitioner. Also on

the brief was Amy Heverly.

Corinne S. Celko argued the cause for respondent. Also

on the brief were Alex J. Berger and Emerge Law Group.

Before Lagesen, Presiding Judge, and James, Judge, and

Kamins, Judge.

LAGESEN, P. J.

Affirmed.

Cite as 308 Or App 494 (2021) 495

LAGESEN, P. J.

Petitioner Deschutes County seeks judicial review

of a decision of the Land Use Board of Appeals (LUBA) that

reversed a decision by the board of county commissioners

denying respondent Waveseer of Oregon, LLC’s application

to develop a marijuana production facility on land zoned for

exclusive farm use (EFU). The board denied the application

based on its conclusion that the proposed facility would be

located within 1,000 feet of two “youth activity center[s],”

in violation of Deschutes County Code (DCC) 18.116.330

(B)(7)(a)(iv). LUBA reversed, concluding, among other things,

that the county’s interpretation and application of the term

“youth activity center” rested on uncodified criteria in vio-

lation of the codification requirement contained in ORS

215.416(8)(a) and, for that reason, could not be applied

to deny Waveseer’s application. On review to determine

whether LUBA’s order is “unlawful in substance or proce-

dure,” ORS 197.850(9)(a), we affirm.

Under the Deschutes County Code, a marijuana

production facility cannot be located within 1,000 feet of a

school, childcare center, national monument, state park or,

as pertinent here, a “youth activity center.” DCC 18.116.330

(B)(7)(a). The code provides further that that 1,000-foot dis-

tance is “measured from the lot line of the affected prop-

erties listed in DCC 18.116.330(B)(7)(a) to the closest point

of the buildings and land area occupied by the marijuana

producer or marijuana processor.” DCC 18.116.330(B)(7)(b).

Waveseer applied to the county to develop a mari-

juana production facility on EFU-zoned land. That land cur-

rently is developed with a house and a barn. Immediately

to the south is a property known as the Rhinestone Ranch.

It serves as a family residence and as a working ranch.

The ranch hosts equestrian activities for youth, including

horseback-riding classes and camps, birthday parties, and

other similar events. Immediately to the east is a property

that LUBA referred to as the “Dodds Road Residence.” It

has a house and outbuildings and serves as a family resi-

dence but also hosts 4-H agricultural activities for youth.

Waveseer’s proposed marijuana production facility would

be within 1,000 feet of both the Rhinestone Ranch and the

496 Waveseer of Oregon, LLC v. Deschutes County

Dodds Road residence, when the 1,000 feet is measured in

accordance with DCC 18.116.330(B)(7)(b).

The county planning department administratively

approved Waveseer’s application. Opponents—who are not

parties to this proceeding—appealed that approval to

the board of county commissioners. The board denied

Waveseer’s application based solely on its determination

that the Rhinestone Ranch and the Dodds Road residence

were “youth activity center[s]” within the meaning of DCC

18.116.330(B)(7)(a)(iv), so as to preclude Waveseer’s proposed

marijuana production facility given its less-than-1,000 feet

proximity to those properties. The board determined that

each property hosted farm and residential uses that “cen-

ter around youth on a regular basis,” making them each a

“youth activity center” for the purpose of the code.

Waveseer appealed to LUBA, and LUBA remanded

to the county. It determined that the county’s articulated

standard for what constituted a “youth activity center”—a

term undefined in the county code—was “unreasonable

because there is no way for an applicant to determine if a

particular EFU-zoned property could be used for marijuana

production,” given the breadth of the county’s standard.

Waveseer of Oregon, LLC v. Deschutes County, ___ Or LUBA

___, ___ (LUBA No 2019-036, Oct 17, 2019) (Waveseer I).

That breadth, LUBA concluded, meant the county’s inter-

pretation of what constituted a “youth activity center” con-

flicted with the requirement in ORS 215.416(8)(a) that stan-

dards for approving or denying a permit application must be

codified, that is, “set forth in the zoning ordinance or other

appropriate ordinance or regulation of the county.” LUBA

remanded to the county, suggesting that the board might

be able to interpret the provision in a manner that did not

run afoul of ORS 215.416(8)(a)’s codification requirement.

LUBA also noted that there were other aspects of Waveseer’s

application, regarding noise and odor, that the board had

not resolved that could potentially supply an independent

basis for denying Waveseer’s application.

On remand the board resolved the noise and odor

issues in Waveseer’s favor. But it again concluded that the

Rhinestone Ranch and the Dodds Road residence constituted

Cite as 308 Or App 494 (2021) 497

“youth activity center[s]” for purposes of DCC 18.116.330

(B)(7)(a). In so doing, the board incorporated by reference its

decision in another matter presenting the same issue, the

Nehmzow case.1

In the Nehmzow case, the board explained its view

that the term “youth activity center” generally means a

“gathering place[ ] for children.” It noted that the county

“intentionally separated youths from marijuana production

and processing, particularly concentrations of youths engag-

ing in organized activities.” The board further explained

that, in its view, whether a property was used as a “youth

activity center” was something that necessarily had to

be determined on a case-by-case basis based on a list of

10 factors:

“[T]his Board has compiled a list of ten factors that it col-

lectively has found persuasive when previously called to

interpret the otherwise undefined term. It should be noted

that the Board’s intention in setting forth the aforemen-

tioned ten factors is simply to consolidate and clarify our

previous interpretations. The Board intends that these ten

factors are to be applied as a checklist of considerations,

but not all such considerations are required elements for a

use to rise to the level of a ‘youth activity center.’ A use may

satisfy only some of the factors, and still qualify as a ‘youth

activity center.’ ”

The 10 factors identified by the board were:

“(1) Separate building, facility, or area for use

“(2) Youth recreation activity accommodated regularly

“(3) Adult supervision provided

“(4) Specific toys, games, or equipment available for

activity

“(5) Permitted or licensed activities

“(6) Organized group activities

“(7) School related activities

1

The board’s decision in Nehmzow was appealed to LUBA in Nehmzow v.

Deschutes County, ___ Or LUBA ___ (LUBA No 2019-110, Aug 10, 2020), and,

on judicial review before our court, was decided today. Nehmzow v. Deschutes

County, 308 Or App 533, 479 P3d 340 (2021).

498 Waveseer of Oregon, LLC v. Deschutes County

“(8)     Usage (frequency/ regularity/ intensity/ number of

participants) exceeds usual EFU use by 50% or more

“(9)     Use observable from neighboring properties

“(10) Youth activities marketed to the public (e.g., website,

social media, published or publicized).”

The board also stated that the analysis contained a

foreseeability component: whether it would be foreseeable to

an applicant who had exercised due diligence that the county

would consider a particular property to be a “youth activ-

ity center.” Applying that analysis to the current case, the

board concluded that the Rhinestone Ranch and the Dodds

Road residence were “youth activity center[s]” because of the

nature of the youth activities conducted on them, because

due diligence would have revealed those activities, and

because, according to the board, it would be foreseeable that

the county would view those properties as “youth activity

center[s]” based on those activities. The board again denied

Waveseer’s application, which again led Waveseer to appeal

to LUBA.

This time, LUBA reversed the denial of Waveseer’s

application outright. Rejecting the county’s contention that

Waveseer had waived the right to raise the issue, LUBA

concluded that the county’s interpretation and application

of the “youth activity center” provision still contravened the

codification requirement of ORS 215.416(8)(a) because an

applicant still could not discern from the terms of the code

itself what would constitute a “youth activity center.” LUBA

explained:

“Under the current DCC, an applicant or opponent can-

not know or predict whether activities on a property within

the separation buffer constitute a youth activity center with

reference to the DCC. The codified phrase ‘youth activity

center’ itself does not reasonably inform an applicant or

opponent what evidence and argument address that crite-

rion. As we pointed out in Waveseer I, the phrase ‘youth

activity center’ is not defined in the DCC, is not listed as

a permitted use in any zone, and is not defined or used in

any state statute or administrative rule. The board’s inter-

pretation and application of the Nehmzow factors demon-

strates that the code itself fails to sufficiently inform inter-

ested parties of the basis on which an application may be

Cite as 308 Or App 494 (2021) 499

approved or denied. That interpretation allows the county

to deny a marijuana production application if the county

finds that activities taking place on a neighboring prop-

erty satisfy one or more of the uncodified Nehmzow factors.

No applicant or opponent could reasonably predict whether

and when the county would determine that youth-oriented

activities constitute a youth activity center because the rel-

evant criteria do not appear in the DCC.”

Because it violated the codification requirement, LUBA con-

cluded that the county could not apply the “youth activity

center” provision to Waveseer’s application to deny it.2

In addition to concluding that the county’s interpre-

tation and application of the term “youth activity center”

was too “amorphous” to satisfy ORS 215.416(8)(a), LUBA also

determined that the county’s interpretation was not a plau-

sible reading of its text and context. Consequently, LUBA

opined, codification problems aside, the county’s interpre-

tation would not be entitled to deference under Siporen v.

City of Medford, 349 Or 247, 243 P3d 776 (2010), and was,

in fact, wrong. In particular, LUBA reasoned that the coun-

ty’s interpretation did not plausibly account for the word

“center” in the context of the code because it does not man-

date that a “youth activity center” involve a place “ ‘built,

constructed, installed, or established’ to serve or facilitate

‘youth activit[ies],’ and, instead, interprets the term as any

place where youth activities occur.” LUBA noted that other

provisions of the Deschutes County Code using the word

“center” appeared to require such separately constructed

or established facilities, and reasoned that it was inconsis-

tent with those other textual references to conclude that a

“youth activity center” did not require such a facility. LUBA

acknowledged that it did not need to reach the issue of the

plausibility of the county’s interpretation of the phrase

2

LUBA also addressed the goal-post standard of ORS 215.427(3), which

requires that an application for a land-use permit be evaluated under the stan-

dards and criteria existing as of the date the application is filed. As we under-

stand LUBA’s ruling, the goal-post rule informs the disposition in a matter in

which a standard has been applied in violation of the ORS 215.416(8)(a) codifi-

cation requirement. If a county erroneously applies uncodified standards, and

its decision is reversed for that reason, the goal-post standard of ORS 215.427(3)

precludes the county from fixing the codification problem in the case at hand

because it would prohibit the county from applying the newly codified standards.

500 Waveseer of Oregon, LLC v. Deschutes County

“youth activity center” but did so based on its view that the

issue was likely to arise again.

Finally, having concluded that the county’s inter-

pretation of the term “youth activity center” violated the cod-

ification requirement and could not be applied to Waveseer’s

application, LUBA reversed the board’s denial of Waveseer’s

application outright and ordered the county to approve it.

The county petitioned us for judicial review of

LUBA’s decision. It raises four assignments of error. In its

first assignment of error, the county contends that LUBA

erred when it determined that the county’s interpretation

of the term “youth activity center” was implausible and not

entitled to deference under Siporen. In its second assign-

ment of error, the county asserts that LUBA erred in deter-

mining that the county’s interpretation and application of

the term “youth activity center” violated the codification

requirement. In its third assignment of error, the county

contends that LUBA erred by entertaining Waveseer’s argu-

ments regarding the codification requirement to the extent

that Waveseer did not raise those arguments to LUBA in its

initial appeal. Finally, in its fourth assignment, the county

contends that LUBA erred in reversing its decision outright

under ORS 197.835(10)(a)(A). As mentioned, our review is to

determine whether LUBA’s order is “unlawful in substance

or procedure.” ORS 197.850(9)(a).

We start with the primary basis for LUBA’s disposi-

tion, and the one addressed in the county’s second and third

assignments of error: that the county’s interpretation of the

“youth activity center” criterion in DCC 18.116.330(B)(7)(a)

violates the codification requirement of ORS 215.416(8)(a).

As an initial matter, we reject the county’s conten-

tion that LUBA erred in considering the arguments on that

point because Waveseer had not raised them in its initial

appeal. The county, to be sure, is correct that Waveseer’s

failure to raise those arguments initially has meant that

the county had to expend time and effort in resolving this

matter that could have been spared had Waveseer made

those arguments initially. But the county has identified no

source of law that would permit us to conclude that LUBA’s

procedural choice to consider those arguments is one that

Cite as 308 Or App 494 (2021) 501

is “unlawful,” so as to permit us to conclude that LUBA’s

order was “unlawful in * * * procedure” to the extent LUBA

decided to consider arguments that were not raised in the

initial appeal but could have been. ORS 197.850(9)(a).

As for the merits of LUBA’s determination, we con-

clude that it is legally correct. ORS 215.416(8)(a) states:

“Approval or denial of a permit application shall be

based on standards and criteria which shall be set forth

in the zoning ordinance or other appropriate ordinance or

regulation of the county and which shall relate approval or

denial of a permit application to the zoning ordinance and

comprehensive plan for the area in which the proposed use

of land would occur and to the zoning ordinance and com-

prehensive plan for the county as a whole.”

We have recognized that the nearly identically worded pro-

vision applicable to land use decisions by cities is satisfied

if the applicable code “contains provisions that can reason-

ably be interpreted and explained as embodying the stan-

dards and criteria applicable to the particular decision.”

BCT Partnership v. City of Portland, 130 Or App 271, 276,

881 P2d 176 (1994). The key is that the standards must be

ascertainable from the terms of the local government’s leg-

islation. Zirker v. City of Bend, 233 Or App 601, 610, 227

P3d 1174, rev den, 348 Or 415 (2010). In other words, ORS

215.416(8)(a) generally does not permit a county to develop

land use approval standards and criteria through quasi-

adjudicative decision-making; the standards must be rea-

sonably discernible from provisions of the code itself. See id.

As we recently explained,

“[i]n plain terms, ORS 215.416(8)(a) requires that a deci-

sion on a permit application be based on ‘standards and

criteria which shall be set forth in the zoning ordinance

or other appropriate ordinance or regulation of the county.’

The planning director’s interpretation was not something

set forth in the zoning ordinance or other appropriate ordi-

nance or regulation of the county. Therefore, we agree with

LUBA’s conclusion that the planning director’s similar use

determination was only an interpretation of a criterion and

not a criterion itself.”

Jones v. Willamette United Football Club, 307 Or App 502,

514, 479 P3d 326 (2020).

502 Waveseer of Oregon, LLC v. Deschutes County

True, we must acknowledge, it may often be a close

call whether a local government has, in effect, promulgated

new approval standards and criteria through the process of

adjudication, and not merely refined by interpretation exist-

ing codified standards and criteria. Detecting the precise

point at which an act of interpretation becomes an act of

legislation can hardly be said to be a science.

Here, though, the county’s interpretation and appli-

cation of the phrase “youth activity center” to involve a

case-by-case 10-factor checklist analysis is not in any way

signaled by the provisions of the Deschutes County Code.

Simply put, as LUBA recognized, no one could tell by read-

ing the Deschutes County Code what is likely to be deemed

a “youth activity center,” and the case-by-case approach con-

templated by the county under the unweighted Nehmzow fac-

tors does not improve matters. The case-by-case approach as

articulated by the county appears largely discretionary and

standardless at this juncture, and, in all events, nothing in

the provisions of the code signals the notion of a 10-factor

analysis, let alone the particular 10 factors identified by the

county as relevant. Under those circumstances, LUBA was

correct to conclude that the county’s interpretation of the

“youth activity center” criterion in DCC 18.116.330(B)(7)(a)

violates the codification requirement of ORS 215.416(8)(a).

We next turn to the issue of disposition, raised in

the county’s fourth assignment of error. The county con-

tends that LUBA erred in reversing outright and order-

ing the county to approve Waveseer’s application under

ORS 197.835(10)(a). In the county’s view, a remand was the

appropriate disposition. The county’s arguments on this

point largely focus on the fact that, in its view, it was not put

on notice of this possibility by the arguments in Waveseer’s

briefing to LUBA, and on the fact that this outcome will

subject it to attorney fees. We can see how LUBA’s disposi-

tion may have come as a surprise to the county, particularly

after LUBA’s previous remand to the board. That remand

would have suggested to the county the reasonable possibil-

ity that it could interpret and apply the “youth activity cen-

ter” criterion to deny Waveseer’s application in a way that

comported with ORS 215.416(8)(a). Ultimately, though, the

county’s arguments do not demonstrate any error by LUBA

Cite as 308 Or App 494 (2021) 503

in its choice of disposition. In particular, the county does not

posit to us any way in which it could interpret and apply the

“youth activity center” criterion to deny Waveseer’s applica-

tion, even if there might be plausible interpretations of that

criterion that would not contravene the codification require-

ment of ORS 215.416(8)(a). For those reasons, we reject the

county’s fourth assignment of error.

Finally, we address briefly the county’s argument in

its first assignment of error—that LUBA erred when it deter-

mined that the county’s interpretation of the phrase “youth

activity center” in DCC 18.116.330(B)(7)(a) is not plausible,

given the text and context of that provision. We ultimately

do not resolve the issue because resolution of the question

will not alter the outcome of this appeal. Regardless of

whether the county’s interpretation of the phrase is a plau-

sible one, it represents an interpretation and application of

the county code that contravenes the codification require-

ment. That, combined with the fact that the county has not

identified for us an alternative plausible interpretation that

would both (1) comport with the codification requirement

and (2) allow for the denial of Waveseer’s application means

that the county has not demonstrated that LUBA’s disposi-

tion of this matter was unlawful in substance so as to entitle

the county to a reversal.

We nevertheless note for the record that our opinion

should not be understood as an affirmance of LUBA’s rul-

ing on the plausibility of the county’s interpretation of the

phrase “youth activity center.” LUBA’s analysis on that point

focused on one common definition of the word “center,” but the

county’s (inadequately codified) interpretation is consistent

with another common definition of the word “center.” As the

dictionary and ordinary usage make clear, the word center

can be synonymous with hub: “a point, area, person, or thing

that is most important or pivotal in relation to an indicated

activity, interest, or condition * * * < a railroad ~>.” Webster’s

Third New Int’l Dictionary 362 (unabridged ed 2002). That

common understanding of the word “center” would appear

to track the county’s reading of the phrase to encompass

a “point” or “area” that is “important or pivotal in relation

to” the activities of youth, as well as the context of the rule

in which the county has employed the term “youth activity

504 Waveseer of Oregon, LLC v. Deschutes County

center”—a rule on its face aimed at distancing marijuana

production from places where youth regularly congregate.

That is an objective that might be undermined by LUBA’s

interpretive approach, which appears to be focused on the

facility-based definition of the word “center.” Although some

places where youth congregate for activities might involve

facilities (like the schools or child care centers mentioned

in other provisions of DCC 18.116.330(B)(7)(a)), other places

where youth congregate for activities might not (like the

national monuments and state parks mentioned in a dif-

ferent provision of DCC 18.116.330(B)(7)(a)). Thus, LUBA’s

conclusion that the county implausibly interpreted its code

is subject to question. We leave that question for another

day, which may not come. When the county either amends

its code or narrows its interpretation of it to address the

codification issue, that process might well and finally inter

the issue.

Affirmed.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.