rejecting procedural challenge where county did not identify a source of law that would allow the court to conclude that LUBA’s procedural choices were unlawful
How later courts described this case
- rejecting procedural challenge where county did not identify a source of law that would allow the court to conclude that LUBA’s procedural choices were unlawful
Written by the judges who cited it.
The opinion
494
Argued and submitted November 12, 2020, affirmed January 13, 2021
WAVESEER OF OREGON, LLC,
Respondent,
v.
DESCHUTES COUNTY,
Petitioner.
Land Use Board of Appeals
2020038; A174515
482 P3d 212
Petitioner Deschutes County seeks judicial review of a decision of the
Land Use Board of Appeals (LUBA). LUBA reversed a decision by the board of
county commissioners denying respondent Waveseer of Oregon, LLC’s applica-
tion to develop a marijuana production facility. The board denied the applica-
tion based on its conclusion that the proposed facility would be located within
1,000 feet of two “youth activity center[s],” in violation of Deschutes County Code
18.116.330(B)(7)(a)(iv). LUBA reversed, concluding, among other things, that
the county’s interpretation and application of the term “youth activity center”
rested on uncodified criteria in violation of the codification requirement in ORS
215.416(8)(a). On judicial review, the county assigns error to, among other things,
LUBA’s determination that the county’s interpretation and application of the
term “youth activity center” violated the codification requirement. Held: LUBA
did not err in concluding that the county’s interpretation of the term “youth activ-
ity center” violated the statutory codification requirement. Nothing in the county
code signaled how the county interpreted the term—its standards were instead
promulgated through the process of adjudication, which did not satisfy the codi-
fication requirement.
Affirmed.
D. Adam Smith argued the cause for petitioner. Also on
the brief was Amy Heverly.
Corinne S. Celko argued the cause for respondent. Also
on the brief were Alex J. Berger and Emerge Law Group.
Before Lagesen, Presiding Judge, and James, Judge, and
Kamins, Judge.
LAGESEN, P. J.
Affirmed.
Cite as 308 Or App 494 (2021) 495
LAGESEN, P. J.
Petitioner Deschutes County seeks judicial review
of a decision of the Land Use Board of Appeals (LUBA) that
reversed a decision by the board of county commissioners
denying respondent Waveseer of Oregon, LLC’s application
to develop a marijuana production facility on land zoned for
exclusive farm use (EFU). The board denied the application
based on its conclusion that the proposed facility would be
located within 1,000 feet of two “youth activity center[s],”
in violation of Deschutes County Code (DCC) 18.116.330
(B)(7)(a)(iv). LUBA reversed, concluding, among other things,
that the county’s interpretation and application of the term
“youth activity center” rested on uncodified criteria in vio-
lation of the codification requirement contained in ORS
215.416(8)(a) and, for that reason, could not be applied
to deny Waveseer’s application. On review to determine
whether LUBA’s order is “unlawful in substance or proce-
dure,” ORS 197.850(9)(a), we affirm.
Under the Deschutes County Code, a marijuana
production facility cannot be located within 1,000 feet of a
school, childcare center, national monument, state park or,
as pertinent here, a “youth activity center.” DCC 18.116.330
(B)(7)(a). The code provides further that that 1,000-foot dis-
tance is “measured from the lot line of the affected prop-
erties listed in DCC 18.116.330(B)(7)(a) to the closest point
of the buildings and land area occupied by the marijuana
producer or marijuana processor.” DCC 18.116.330(B)(7)(b).
Waveseer applied to the county to develop a mari-
juana production facility on EFU-zoned land. That land cur-
rently is developed with a house and a barn. Immediately
to the south is a property known as the Rhinestone Ranch.
It serves as a family residence and as a working ranch.
The ranch hosts equestrian activities for youth, including
horseback-riding classes and camps, birthday parties, and
other similar events. Immediately to the east is a property
that LUBA referred to as the “Dodds Road Residence.” It
has a house and outbuildings and serves as a family resi-
dence but also hosts 4-H agricultural activities for youth.
Waveseer’s proposed marijuana production facility would
be within 1,000 feet of both the Rhinestone Ranch and the
496 Waveseer of Oregon, LLC v. Deschutes County
Dodds Road residence, when the 1,000 feet is measured in
accordance with DCC 18.116.330(B)(7)(b).
The county planning department administratively
approved Waveseer’s application. Opponents—who are not
parties to this proceeding—appealed that approval to
the board of county commissioners. The board denied
Waveseer’s application based solely on its determination
that the Rhinestone Ranch and the Dodds Road residence
were “youth activity center[s]” within the meaning of DCC
18.116.330(B)(7)(a)(iv), so as to preclude Waveseer’s proposed
marijuana production facility given its less-than-1,000 feet
proximity to those properties. The board determined that
each property hosted farm and residential uses that “cen-
ter around youth on a regular basis,” making them each a
“youth activity center” for the purpose of the code.
Waveseer appealed to LUBA, and LUBA remanded
to the county. It determined that the county’s articulated
standard for what constituted a “youth activity center”—a
term undefined in the county code—was “unreasonable
because there is no way for an applicant to determine if a
particular EFU-zoned property could be used for marijuana
production,” given the breadth of the county’s standard.
Waveseer of Oregon, LLC v. Deschutes County, ___ Or LUBA
___, ___ (LUBA No 2019-036, Oct 17, 2019) (Waveseer I).
That breadth, LUBA concluded, meant the county’s inter-
pretation of what constituted a “youth activity center” con-
flicted with the requirement in ORS 215.416(8)(a) that stan-
dards for approving or denying a permit application must be
codified, that is, “set forth in the zoning ordinance or other
appropriate ordinance or regulation of the county.” LUBA
remanded to the county, suggesting that the board might
be able to interpret the provision in a manner that did not
run afoul of ORS 215.416(8)(a)’s codification requirement.
LUBA also noted that there were other aspects of Waveseer’s
application, regarding noise and odor, that the board had
not resolved that could potentially supply an independent
basis for denying Waveseer’s application.
On remand the board resolved the noise and odor
issues in Waveseer’s favor. But it again concluded that the
Rhinestone Ranch and the Dodds Road residence constituted
Cite as 308 Or App 494 (2021) 497
“youth activity center[s]” for purposes of DCC 18.116.330
(B)(7)(a). In so doing, the board incorporated by reference its
decision in another matter presenting the same issue, the
Nehmzow case.1
In the Nehmzow case, the board explained its view
that the term “youth activity center” generally means a
“gathering place[ ] for children.” It noted that the county
“intentionally separated youths from marijuana production
and processing, particularly concentrations of youths engag-
ing in organized activities.” The board further explained
that, in its view, whether a property was used as a “youth
activity center” was something that necessarily had to
be determined on a case-by-case basis based on a list of
10 factors:
“[T]his Board has compiled a list of ten factors that it col-
lectively has found persuasive when previously called to
interpret the otherwise undefined term. It should be noted
that the Board’s intention in setting forth the aforemen-
tioned ten factors is simply to consolidate and clarify our
previous interpretations. The Board intends that these ten
factors are to be applied as a checklist of considerations,
but not all such considerations are required elements for a
use to rise to the level of a ‘youth activity center.’ A use may
satisfy only some of the factors, and still qualify as a ‘youth
activity center.’ ”
The 10 factors identified by the board were:
“(1) Separate building, facility, or area for use
“(2) Youth recreation activity accommodated regularly
“(3) Adult supervision provided
“(4) Specific toys, games, or equipment available for
activity
“(5) Permitted or licensed activities
“(6) Organized group activities
“(7) School related activities
1
The board’s decision in Nehmzow was appealed to LUBA in Nehmzow v.
Deschutes County, ___ Or LUBA ___ (LUBA No 2019-110, Aug 10, 2020), and,
on judicial review before our court, was decided today. Nehmzow v. Deschutes
County, 308 Or App 533, 479 P3d 340 (2021).
498 Waveseer of Oregon, LLC v. Deschutes County
“(8) Usage (frequency/ regularity/ intensity/ number of
participants) exceeds usual EFU use by 50% or more
“(9) Use observable from neighboring properties
“(10) Youth activities marketed to the public (e.g., website,
social media, published or publicized).”
The board also stated that the analysis contained a
foreseeability component: whether it would be foreseeable to
an applicant who had exercised due diligence that the county
would consider a particular property to be a “youth activ-
ity center.” Applying that analysis to the current case, the
board concluded that the Rhinestone Ranch and the Dodds
Road residence were “youth activity center[s]” because of the
nature of the youth activities conducted on them, because
due diligence would have revealed those activities, and
because, according to the board, it would be foreseeable that
the county would view those properties as “youth activity
center[s]” based on those activities. The board again denied
Waveseer’s application, which again led Waveseer to appeal
to LUBA.
This time, LUBA reversed the denial of Waveseer’s
application outright. Rejecting the county’s contention that
Waveseer had waived the right to raise the issue, LUBA
concluded that the county’s interpretation and application
of the “youth activity center” provision still contravened the
codification requirement of ORS 215.416(8)(a) because an
applicant still could not discern from the terms of the code
itself what would constitute a “youth activity center.” LUBA
explained:
“Under the current DCC, an applicant or opponent can-
not know or predict whether activities on a property within
the separation buffer constitute a youth activity center with
reference to the DCC. The codified phrase ‘youth activity
center’ itself does not reasonably inform an applicant or
opponent what evidence and argument address that crite-
rion. As we pointed out in Waveseer I, the phrase ‘youth
activity center’ is not defined in the DCC, is not listed as
a permitted use in any zone, and is not defined or used in
any state statute or administrative rule. The board’s inter-
pretation and application of the Nehmzow factors demon-
strates that the code itself fails to sufficiently inform inter-
ested parties of the basis on which an application may be
Cite as 308 Or App 494 (2021) 499
approved or denied. That interpretation allows the county
to deny a marijuana production application if the county
finds that activities taking place on a neighboring prop-
erty satisfy one or more of the uncodified Nehmzow factors.
No applicant or opponent could reasonably predict whether
and when the county would determine that youth-oriented
activities constitute a youth activity center because the rel-
evant criteria do not appear in the DCC.”
Because it violated the codification requirement, LUBA con-
cluded that the county could not apply the “youth activity
center” provision to Waveseer’s application to deny it.2
In addition to concluding that the county’s interpre-
tation and application of the term “youth activity center”
was too “amorphous” to satisfy ORS 215.416(8)(a), LUBA also
determined that the county’s interpretation was not a plau-
sible reading of its text and context. Consequently, LUBA
opined, codification problems aside, the county’s interpre-
tation would not be entitled to deference under Siporen v.
City of Medford, 349 Or 247, 243 P3d 776 (2010), and was,
in fact, wrong. In particular, LUBA reasoned that the coun-
ty’s interpretation did not plausibly account for the word
“center” in the context of the code because it does not man-
date that a “youth activity center” involve a place “ ‘built,
constructed, installed, or established’ to serve or facilitate
‘youth activit[ies],’ and, instead, interprets the term as any
place where youth activities occur.” LUBA noted that other
provisions of the Deschutes County Code using the word
“center” appeared to require such separately constructed
or established facilities, and reasoned that it was inconsis-
tent with those other textual references to conclude that a
“youth activity center” did not require such a facility. LUBA
acknowledged that it did not need to reach the issue of the
plausibility of the county’s interpretation of the phrase
2
LUBA also addressed the goal-post standard of ORS 215.427(3), which
requires that an application for a land-use permit be evaluated under the stan-
dards and criteria existing as of the date the application is filed. As we under-
stand LUBA’s ruling, the goal-post rule informs the disposition in a matter in
which a standard has been applied in violation of the ORS 215.416(8)(a) codifi-
cation requirement. If a county erroneously applies uncodified standards, and
its decision is reversed for that reason, the goal-post standard of ORS 215.427(3)
precludes the county from fixing the codification problem in the case at hand
because it would prohibit the county from applying the newly codified standards.
500 Waveseer of Oregon, LLC v. Deschutes County
“youth activity center” but did so based on its view that the
issue was likely to arise again.
Finally, having concluded that the county’s inter-
pretation of the term “youth activity center” violated the cod-
ification requirement and could not be applied to Waveseer’s
application, LUBA reversed the board’s denial of Waveseer’s
application outright and ordered the county to approve it.
The county petitioned us for judicial review of
LUBA’s decision. It raises four assignments of error. In its
first assignment of error, the county contends that LUBA
erred when it determined that the county’s interpretation
of the term “youth activity center” was implausible and not
entitled to deference under Siporen. In its second assign-
ment of error, the county asserts that LUBA erred in deter-
mining that the county’s interpretation and application of
the term “youth activity center” violated the codification
requirement. In its third assignment of error, the county
contends that LUBA erred by entertaining Waveseer’s argu-
ments regarding the codification requirement to the extent
that Waveseer did not raise those arguments to LUBA in its
initial appeal. Finally, in its fourth assignment, the county
contends that LUBA erred in reversing its decision outright
under ORS 197.835(10)(a)(A). As mentioned, our review is to
determine whether LUBA’s order is “unlawful in substance
or procedure.” ORS 197.850(9)(a).
We start with the primary basis for LUBA’s disposi-
tion, and the one addressed in the county’s second and third
assignments of error: that the county’s interpretation of the
“youth activity center” criterion in DCC 18.116.330(B)(7)(a)
violates the codification requirement of ORS 215.416(8)(a).
As an initial matter, we reject the county’s conten-
tion that LUBA erred in considering the arguments on that
point because Waveseer had not raised them in its initial
appeal. The county, to be sure, is correct that Waveseer’s
failure to raise those arguments initially has meant that
the county had to expend time and effort in resolving this
matter that could have been spared had Waveseer made
those arguments initially. But the county has identified no
source of law that would permit us to conclude that LUBA’s
procedural choice to consider those arguments is one that
Cite as 308 Or App 494 (2021) 501
is “unlawful,” so as to permit us to conclude that LUBA’s
order was “unlawful in * * * procedure” to the extent LUBA
decided to consider arguments that were not raised in the
initial appeal but could have been. ORS 197.850(9)(a).
As for the merits of LUBA’s determination, we con-
clude that it is legally correct. ORS 215.416(8)(a) states:
“Approval or denial of a permit application shall be
based on standards and criteria which shall be set forth
in the zoning ordinance or other appropriate ordinance or
regulation of the county and which shall relate approval or
denial of a permit application to the zoning ordinance and
comprehensive plan for the area in which the proposed use
of land would occur and to the zoning ordinance and com-
prehensive plan for the county as a whole.”
We have recognized that the nearly identically worded pro-
vision applicable to land use decisions by cities is satisfied
if the applicable code “contains provisions that can reason-
ably be interpreted and explained as embodying the stan-
dards and criteria applicable to the particular decision.”
BCT Partnership v. City of Portland, 130 Or App 271, 276,
881 P2d 176 (1994). The key is that the standards must be
ascertainable from the terms of the local government’s leg-
islation. Zirker v. City of Bend, 233 Or App 601, 610, 227
P3d 1174, rev den, 348 Or 415 (2010). In other words, ORS
215.416(8)(a) generally does not permit a county to develop
land use approval standards and criteria through quasi-
adjudicative decision-making; the standards must be rea-
sonably discernible from provisions of the code itself. See id.
As we recently explained,
“[i]n plain terms, ORS 215.416(8)(a) requires that a deci-
sion on a permit application be based on ‘standards and
criteria which shall be set forth in the zoning ordinance
or other appropriate ordinance or regulation of the county.’
The planning director’s interpretation was not something
set forth in the zoning ordinance or other appropriate ordi-
nance or regulation of the county. Therefore, we agree with
LUBA’s conclusion that the planning director’s similar use
determination was only an interpretation of a criterion and
not a criterion itself.”
Jones v. Willamette United Football Club, 307 Or App 502,
514, 479 P3d 326 (2020).
502 Waveseer of Oregon, LLC v. Deschutes County
True, we must acknowledge, it may often be a close
call whether a local government has, in effect, promulgated
new approval standards and criteria through the process of
adjudication, and not merely refined by interpretation exist-
ing codified standards and criteria. Detecting the precise
point at which an act of interpretation becomes an act of
legislation can hardly be said to be a science.
Here, though, the county’s interpretation and appli-
cation of the phrase “youth activity center” to involve a
case-by-case 10-factor checklist analysis is not in any way
signaled by the provisions of the Deschutes County Code.
Simply put, as LUBA recognized, no one could tell by read-
ing the Deschutes County Code what is likely to be deemed
a “youth activity center,” and the case-by-case approach con-
templated by the county under the unweighted Nehmzow fac-
tors does not improve matters. The case-by-case approach as
articulated by the county appears largely discretionary and
standardless at this juncture, and, in all events, nothing in
the provisions of the code signals the notion of a 10-factor
analysis, let alone the particular 10 factors identified by the
county as relevant. Under those circumstances, LUBA was
correct to conclude that the county’s interpretation of the
“youth activity center” criterion in DCC 18.116.330(B)(7)(a)
violates the codification requirement of ORS 215.416(8)(a).
We next turn to the issue of disposition, raised in
the county’s fourth assignment of error. The county con-
tends that LUBA erred in reversing outright and order-
ing the county to approve Waveseer’s application under
ORS 197.835(10)(a). In the county’s view, a remand was the
appropriate disposition. The county’s arguments on this
point largely focus on the fact that, in its view, it was not put
on notice of this possibility by the arguments in Waveseer’s
briefing to LUBA, and on the fact that this outcome will
subject it to attorney fees. We can see how LUBA’s disposi-
tion may have come as a surprise to the county, particularly
after LUBA’s previous remand to the board. That remand
would have suggested to the county the reasonable possibil-
ity that it could interpret and apply the “youth activity cen-
ter” criterion to deny Waveseer’s application in a way that
comported with ORS 215.416(8)(a). Ultimately, though, the
county’s arguments do not demonstrate any error by LUBA
Cite as 308 Or App 494 (2021) 503
in its choice of disposition. In particular, the county does not
posit to us any way in which it could interpret and apply the
“youth activity center” criterion to deny Waveseer’s applica-
tion, even if there might be plausible interpretations of that
criterion that would not contravene the codification require-
ment of ORS 215.416(8)(a). For those reasons, we reject the
county’s fourth assignment of error.
Finally, we address briefly the county’s argument in
its first assignment of error—that LUBA erred when it deter-
mined that the county’s interpretation of the phrase “youth
activity center” in DCC 18.116.330(B)(7)(a) is not plausible,
given the text and context of that provision. We ultimately
do not resolve the issue because resolution of the question
will not alter the outcome of this appeal. Regardless of
whether the county’s interpretation of the phrase is a plau-
sible one, it represents an interpretation and application of
the county code that contravenes the codification require-
ment. That, combined with the fact that the county has not
identified for us an alternative plausible interpretation that
would both (1) comport with the codification requirement
and (2) allow for the denial of Waveseer’s application means
that the county has not demonstrated that LUBA’s disposi-
tion of this matter was unlawful in substance so as to entitle
the county to a reversal.
We nevertheless note for the record that our opinion
should not be understood as an affirmance of LUBA’s rul-
ing on the plausibility of the county’s interpretation of the
phrase “youth activity center.” LUBA’s analysis on that point
focused on one common definition of the word “center,” but the
county’s (inadequately codified) interpretation is consistent
with another common definition of the word “center.” As the
dictionary and ordinary usage make clear, the word center
can be synonymous with hub: “a point, area, person, or thing
that is most important or pivotal in relation to an indicated
activity, interest, or condition * * * < a railroad ~>.” Webster’s
Third New Int’l Dictionary 362 (unabridged ed 2002). That
common understanding of the word “center” would appear
to track the county’s reading of the phrase to encompass
a “point” or “area” that is “important or pivotal in relation
to” the activities of youth, as well as the context of the rule
in which the county has employed the term “youth activity
504 Waveseer of Oregon, LLC v. Deschutes County
center”—a rule on its face aimed at distancing marijuana
production from places where youth regularly congregate.
That is an objective that might be undermined by LUBA’s
interpretive approach, which appears to be focused on the
facility-based definition of the word “center.” Although some
places where youth congregate for activities might involve
facilities (like the schools or child care centers mentioned
in other provisions of DCC 18.116.330(B)(7)(a)), other places
where youth congregate for activities might not (like the
national monuments and state parks mentioned in a dif-
ferent provision of DCC 18.116.330(B)(7)(a)). Thus, LUBA’s
conclusion that the county implausibly interpreted its code
is subject to question. We leave that question for another
day, which may not come. When the county either amends
its code or narrows its interpretation of it to address the
codification issue, that process might well and finally inter
the issue.
Affirmed.