Court rejected contractor’s good faith and fair dealing claim finding the contract allocated the risks attending to securing the required state permits to the contractor and the government did not affirmatively interfere with the contractor’s dealings with the state agency
How later courts described this case
- Court rejected contractor’s good faith and fair dealing claim finding the contract allocated the risks attending to securing the required state permits to the contractor and the government did not affirmatively interfere with the contractor’s dealings with the state agency
- The government is excused from performance under the sovereign acts defense when the sovereign act renders the government’s performance impossible.
- contract must be read as a whole to harmonize and give meaning to all parts
- explaining the need to consider the contract’s allocation of risks and benefits in considering a claim of breach of the duty of good faith and fair dealing
Written by the judges who cited it.
The opinion
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
Targe Logistic Services Company ) ASBCA No. 63282
)
Under Contract Nos. W91B4N-18-D-2005 )
W91B4N-19-D-0005
W91B4N-19-D-0006
W91B4N-19-D-0008
W91B4N-19-D-0009
W91B4N-19-D-0010
APPEARANCES FOR THE APPELLANT: Enayat Qasimi, Esq.
Shamsi Maqsoudi, Esq.
Whiteford, Taylor & Preston LLP
Washington, DC
APPEARANCES FOR THE GOVERNMENT: Dana J. Chase, Esq.
Army Chief Trial Attorney
Major Brandon P. Mark, JA
Trial Attorney
OPINION BY ADMINISTRATIVE JUDGE TAYLOR
ON THE GOVERNMENT’S MOTION FOR SUMMARY JUDGMENT AND
APPELLANT’S CROSS MOTION FOR PARTIAL SUMMARY JUDGMENT
This appeal involves a claim by Targe Logistic Services Company (TLS or
appellant) for the loss of fuel, delivery equipment, and other assets due to the collapse
of the Government of Islamic Republic of Afghanistan (GIRoA) following the
takeover of the country by the Islamic Emirate of Afghanistan (known as the Taliban).
TLS contends the United States Army (Army or government) is responsible for its
alleged losses because the Army breached several contracts by failing to pay for
delivered and stored fuel (Count I), provide security and access to the facilities
(Count II), breached the covenant of good faith and fair dealing (Count III) and
constructively changed the contracts (Count V). The government filed a motion for
summary judgment contending it is entitled to judgment on this appeal as a matter of
law on those counts since the undisputed facts show that it did not breach or
constructively change the contracts. Moreover, the government asserts the Board
should grant its motion based upon the affirmative defenses of sovereign acts,
third-party actions, assumption of risk and the unambiguous contract terms.
TLS contends disputed material facts exist that prevent the Board from granting
the Army’s summary judgment motion. In addition, TLS filed a cross-motion for
partial summary judgment asserting an entitlement to payment for the fuel stored at the
various facilities and terminals under the commercial termination for convenience
clause since the contracts included a minimum fuel requirement (Count IV). The
Army responded to TLS’s cross-motion contending it is not required to pay for that
fuel since the Taliban confiscated the fuel before the termination for convenience
occurred and the contracts placed the risk of loss on TLS.
For the reasons discussed below, we grant the government’s motion for
summary judgment and deny TLS’s partial cross-motion.
STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
The Contracts
1. The Army awarded Contract Nos. W91B4N18D2005, W91B4N19D0005,
W91B4N19D0006, W91B4N19D0008, W91B4N19D0009 and W91B4N19D0010 (the
contracts) to TLS beginning on October 10, 2018 (R4, tabs 1-6).
2. The contracts were indefinite-delivery, indefinite-quantity (IDIQ) contracts
for the supply and delivery of aviation turbine fuel to Afghan National Defense and
Security Forces (ANDSF) sites throughout Afghanistan (R4, tab 1 at 28). 1 The
contracts required TLS to “provide all personnel, equipment (i.e., required vehicles),
supplies, transportation, tools, materials, supervision, other items, and other ancillary
non-personal services necessary to deliver” the aviation fuel (id. at 28). The fuel was
to be delivered by “mobile cold fueling” into designated Afghan Air Force (AAF) and
Special Mission Wing (SMW) aircraft (id.) Mobile cold fueling was defined as “the
mobile fueling (by truck) of static aircraft with engines not running,” and is also
known as “direct to tail” fueling (id.). The contracts further required TLS to deliver
the fuel on a “Free on Board (FOB) Destination Basis” and to maintain an effective
supply chain to ensure an uninterrupted fuel supply (id. at 28-29). The contractor was
responsible for “all aspects of supply chain management, from acquisition of the
aviation fuel from refineries or pipeline terminals . . . and delivery into aircraft
refueling vehicles at the AAF and SMW locations (id. at 29).” The contracts priced
the fuel by the liter (id. at 3).
1
All six contracts have similar language. For ease of reference, we cite only to
Contract No. W91B4N18D2005. We also note the government’s Rule 4 file is
Bates numbered with a six-digit number preceded by “Army.” Here, we delete
the prefix and the leading zeros.
2
3. The contracts incorporated by reference FAR 52.212-4, CONTRACT
TERMS AND CONDITIONS – COMMERCIAL ITEMS (JAN 2017), which reads in
pertinent part:
(l) Termination for the Government’s convenience. The
Government reserves the right to terminate this contract, or
any part hereof for its sole convenience. In the event of
such termination . . . [Prong 1] the Contractor shall be paid
a percentage of the contract price reflecting the percentage
of the work performed prior to the notice of termination,
plus [Prong 2] reasonable charges the Contractor can
demonstrate . . . have resulted from the termination.
(Id. at 8). The contracts also required TLS to “comply with all applicable
updated/superseded regulations, publications, manuals, and local policies and
procedures identified in this SOW . . . that are incorporated into the resulting contract”
(id. at 29).
Acceptance and Payment
4. The contract’s SOW, Section 6.14, Acceptance, provided:
Until acceptance, risk of loss or damage shall remain with
the Contractor. The ANDSF delivery receiving activity
shall provide written acceptance of the fuel on the delivery
ticket, by certifying the delivery and signing the delivery
ticket to affirm the amount of fuel actually delivered. . . .
Upon signature by the ANDSF delivery activity, the fuel is
accepted, in the amount identified on the delivery ticket.
(Id. at 35)
5. The contract’s SOW, Section 6.15, Invoicing, required the contractor to
submit invoices for payment including certified and signed delivery tickets showing
the amount of fuel delivered into the aircraft (id.).
Security and Facility Access
6. The contract’s SOW, Section 4, SCOPE, provided:
The Government will identify a point of contract (POC)
at contract award that the Contractor shall coordinate with
to work to arrange a potential secure area for refueling
3
vehicles, . . . to obtain required facility access at the exact
site location, and to identify any airport/airfield permits
that are required.
(Id. at 29)
7. The contract’s SOW, Section 13, SECURITY REQUIREMENTS, specified:
13.1. The Contractor shall be responsible for security of
all vehicles, personnel and aviation fuel being transported
under this contract. The Contractor shall provide its own
security IAW all applicable GIRoA laws/regulations and
Department of Defense/CENTCOM/U.S. Forces-
Afghanistan (U.S. FOR-A)/Resolute Support, regulations,
policies, and Fragmentary Orders (FRAGO). . . .
13.2. Delivery Point Security Requirements: Force
protection requirements are in full effect at all times under
this contract. There may be waiting periods outside the
gates of all delivery sites (AAF or SMW). Security
measures change according to perceived threat levels, and
may irregularly affect wait times outside of installation
entry points.
(Id. at 39-40) TLS engaged the Afghanistan Ministry of the Interior National Public
Protection Force for its security (compl. ¶ 26).
8. The contract also included CENTCOM Joint Theater Support Contracting
Command (C-JTSCC) clause 5152.225-5916, MANDATORY ELIGIBILITY FOR
INSTALLATION ACCESS (OCT 2015). That clause provides, in part:
(a) U.S. and Coalition Commanders possess inherent
authority to maintain law and order, provide security, and
impose discipline necessary to protect the inhabitants of
U.S. and/or Coalition installations, U.S. and Coalition
personnel operating outside of installations, and U.S. or
Coalition-funded developmental projects in Afghanistan.
This authority allows commanders to administratively and
physically control access to installations and/or project
sites . . . . A commander’s inherent force protection (FP)
authority is independent of an agency’s contracting
authority, and it may not be superseded by any contractual
term or provision.
4
(R4, tab 1 at 25)
9. The United States Central Command established the overall force protection
requirements in Afghanistan (app. supp. R4, tab 107 at 64). The force protection
requirements concerned security at individual locations including vehicle and
personnel searches (id. at 62-63). Force protection requirements may also include
enforcing waiting periods for access to the facilities (id. at 70-71). Contractors had to
comply with those requirements (id. at 62). Commanders at the individual facilities
could make changes to the force protection posture based on individual threats (id.
at 65).
10. The contract’s SOW Section 20.1., Services, provides:
The Government will provide POC [Point of Contact]
information for each of the locations identified in
Paragraph 9, as well as POCs for each fuel delivery
Contractor with which the Contractor shall coordinate
quality assurance testing as described in Paragraph 6.2.
The KO [Contracting Officer] and COR [Contracting
Officer Representative] will also coordinate and assist the
Contractor in the event of any denial of access to ANDSF
facilities that interferes with contract performance.
(R4, tab 1 at 41)
Risk of Loss
11. The contract’s SOW, Section 14, Risk of Loss, states:
Risk of loss or damage shall remain with the Contractor,
until, and will pass to U.S. Government upon, delivery of
the aviation turbine fuel products into AAF or SMW
aircraft.
14.1. The Contractor bears all risk and responsibility for
loss or damage to equipment and personal injury or death
of its employees, agents or subcontractors, or any member
of the public, if such damage, personal injury or death
arises from or relates to any performance under this
contract.
14.2. The Contractor is solely responsible for obtaining
adequate insurance to cover the risks discussed herein.
5
14.3. The U.S. Government will not reimburse the
Contractor for claims stemming from loss or damage to
product or equipment or personal injury or death of
employees, agents, or subcontractors, or any member of
the public.
(Id. at 40)
12. The contract included C-JTSCC clause 5152.225-5915, CONTRACTOR
ACCOUNTABILITY AND PERSONNEL RECOVERY (JUN 2014). The clause
states, in part:
Contract performance may require work in dangerous or
austere conditions. Except as otherwise provided in the
contract, the contractor accepts the risks associated with
required contract performance in such operations.
(Id. at 24)
Contract Modification
13. The Army modified the contracts in June and July 2020 to implement
minimum fuel reserve and minimum bowser quantity requirement changes, provide
associated firm-fixed price changes, and incorporate an updated narrative to the SOW
implementing the minimum fuel reserve and minimum bowser quantity requirements
(R4, tabs 25-30).
United States Withdrawal from Afghanistan
14. The United States and the Taliban, signed the “Agreement for Bringing
Peace to Afghanistan” in Doha, Qatar on February 29, 2020 (“Doha Agreement”,
available at https://www.state.gov/wp-content/uploads/2020/02/Agreement-For-
Bringing-Peace-to-Afghanistan-02.29.20.pdf).
15. On April 14, 2021, pursuant to the Doha Agreement, President Joseph R.
Biden announced that all remaining United States military personnel would leave
Afghanistan by September 11, 2021, which was later changed to August 31, 2021.
See Special Inspector General for Afghanistan Reconstruction Quarterly Report to the
United States Congress, October 30, 2021, (SIGAR Report) at 3 available
at https://www.sigar.mil/pdf/quarterlyreports/2021-10-30qr.pdf.
16. The U.S. Forces-Afghanistan (USFOR-A) formally began the final phase
of the withdrawal from Afghanistan on May 1, 2021 (id. at 68). TLS provided a series
of Serious Incident Reports (SIR) between August 6 and August 18, 2021, regarding
6
the Taliban takeover of various sites and lost fuel and assets (See, e.g., R4, tab 31).
These reports were informational in nature and did not request any government
response (id.).
17. On August 6, 2021, TLS informed the Army that they were exploring
airlifting fuel into Shorab since the Taliban controlled all the road routes (app. supp.
R4, tab 16 at 2). The next day, the Army’s contracting officer representative asked
TLS whether they could airlift fuel into Shorab since fuel was becoming an urgent
need (id. at 1). The record does not indicate whether TLS airlifted fuel into Shorab,
but apparently, TLS moved a fuel bowser by air from Kabul to Maimana on
August 11, 2021, at the Army’s request (app. supp. R4, tab 129 at 5).
18. On August 15, 2021, Taliban fighters occupied the presidential palace in
Kabul and the GIRoA collapsed (SIGAR Report at 72). The Taliban took over most of
Afghanistan and the ANDSF facilities relevant to these contracts within days (compl.
¶ 4). The Taliban also confiscated all of TLS’ fuel and transportation, storage and
delivery equipment and assets at all the relevant facilities and TLS’s regional fuel
terminals (id.).
Contract Termination and Appeal
19. The government terminated the contracts for convenience on September 2,
2021, with an effective date of September 7, 2021 (R4, tabs 8a, 12). 2
20. On December 28, 2021, TLS provided the government with a termination
settlement proposal (TSP) under FAR 52.212-4(l), the contract’s commercial items
termination for convenience clause (R4, tab 13a). The TSP requested a payment of
$14,189,284.95 consisting of $1,264,767.77 for “On-Base Fuel,” $4,918,980 for
“Terminal Fuel,” $6,980,600 for “Equipment,” $980,000 for “Office,” $26,126 for
“Costs of Preparing TSP” and $44,937.18 for “Improperly Rejected Invoices” (id.
at 20). 3 TLS provided a certification pursuant to DFASRS clause 252.243-7002,
REQUESTS FOR EQUITABLE ADJUSTMENT, with its TSP (id. at 20-21).
2
The contracting officer’s termination notice stated it was issued in accordance with
FAR Part 49 and FAR 52.249-2. The contracts, however, did not contain those
provisions. Rather, the contracts contained FAR 52.212-4, the terms and
conditions for commercial item contracts. The parties agree the FAR 52.212-4(l)
commercial items termination provisions control the resolution of TLS’s
termination costs (app. resp. at 21-22; gov’t reply at 34-35).
3
Appellant apparently did not include in its claim calculation the costs for preparing
the TSP. The total claimed TSP amount including the costs for preparing the
TSP calculates to $14,215,410.95 and not $14,189,284.95.
7
21. On February 15, 2022, the contracting officer issued a contracting officer’s
final decision (COFD) responding to TLS’ TSP and certified claim (R4, tab 22a). The
contracting officer determined TLS was entitled to be paid for its unpaid invoices in
the amount of $2,201,966.56; disputed invoices in the amount of $44,937.18; and TSP
preparation costs in the amount of $26,126 (id. at 4-5). 4 The contracting officer
further determined TLS was not entitled to be paid for the undelivered on-base fuel,
fuel located at the terminals and the lost equipment since they belonged to TLS and
not the United States at the time of their loss (id. at 5).
22. On May 16, 2022, TLS appealed the contracting officer’s COFD to the
Board. Appellant’s complaint lists five counts: (I) breach of contract for failure to pay
for delivered fuel; (II) breach of contract for failure to provide adequate security and
facility access; (III) breach of implied duties of good faith and fair dealing; (IV) breach
of contract for failure to pay for work completed and reasonable charges upon
termination for convenience; and (V) increased costs resulting from a constructive
change (compl. ¶¶ 74-101).
23. On April 3, 2023, the government filed its motion for summary judgment
requesting the Board deny appellant’s complaint and request a stay of the Board
proceedings (gov’t mot. at 1-2). On April 24, 2023, the Board granted the parties’
joint request to suspend discovery for 90-days. On May 8, 2023, the Board granted the
parties’ joint proposed schedule for briefing and limited discovery on the
government’s motion. On July 5, August 7 and October 16, 2023, the Board granted
the parties’ additional joint requests to further extend the briefing and limited
discovery to allow appellant time to conduct discovery to respond to the motion. On
October 23, 2023, appellant filed its response to the government’s summary judgment
motion and filed a cross-motion for partial summary judgment. The parties filed
additional replies and sur-replies.
DECISION
I. The Parties’ Contentions
TLS claims it is entitled to its costs for the loss of fuel, delivery equipment, and
other assets at various locations throughout Afghanistan due to the collapse of the
GIRoA and takeover by the Taliban because the government breached the contract by
failing to pay for the delivered fuel (compl. ¶¶ 74-79), provide adequate security and
facility access (compl. ¶¶ 80-84) and breached its covenant of good faith and fair
dealing (compl. ¶¶ 85-90). TLS also claims the government constructively changed
4
The record is unclear as to whether the government paid TLS for these allowed
amounts since TLS apparently had trouble establishing a non-Afghan bank
account (R4, tab 24).
8
the contract (compl. ¶¶ 96-101). Finally, appellant asserts the government failed to
pay for the completed work and reasonable charges resulting from the termination for
convenience (compl. ¶¶ 91-95).
The government contends the Board should grant its motion for summary judgment
because the undisputed facts show it did not breach the contract and did not constructively
change the contract (gov’t mot. at 7-8). Moreover, the government asserts the Board
should grant its request for summary judgment based upon its affirmative defenses of
sovereign acts, third-party action, and assumption of risk (id. at 2).
In its response, TLS first opposes the government’s motion asserting there are
many disputed issues of material facts that preclude entry of summary judgment (app.
resp. at 2). TLS next claims the government’s motion should be denied because it has
not had the opportunity to conduct full discovery (id. at 3). Finally, TLS asserts its
own entitlement as a matter of law to be paid for the fuel stored at the various facilities
and terminals and for its equipment under the commercial termination for convenience
clause since the contract included a minimum fuel requirement (id.). The Army
replies that it is not required to pay appellant for the lost fuel and equipment under the
commercial termination for convenience clause since the Taliban took the fuel and
equipment before the termination for convenience occurred and the contract placed the
risk of loss on TLS (gov’t reply at 34-35).
We first address issues raised by the government’s motion for summary
judgment and then appellant’s motion for partial summary judgment on the
termination for convenience costs.
II. Summary Judgment Standard
“Summary judgment is appropriate if there is no genuine issue as to any
material fact and the moving party is entitled to judgment as a matter of law.” First
Commerce Corp. v. United States, 335 F.3d 1373, 1379 (Fed. Cir. 2003); FED. R.
CIV. P. 56(a). A material fact is one that makes a difference in the outcome of the
case. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248-49 (1986). “The moving
party bears the burden of establishing the absence of any genuine issue of material fact
and all significant doubt over factual issues must be resolved in favor of the party
opposing summary judgment.” Mingus Constructors, Inc. v. United States, 812 F.2d
1387, 1390 (Fed. Cir. 1987) (citing United States v. Diebold, Inc., 369 U.S. 654, 655
(1962)).
While the movant must demonstrate there is no “genuine issue for trial,” the
nonmovant must “make a showing sufficient to establish the existence of an element
essential to [its] case and on which [it] will bear the burden of proof at trial. Celotex
Corp. v. Catrett, 477 U.S. 317, 322 (1986). A non-movant seeking to defeat summary
9
judgment by suggesting conflicting facts, “must set forth specific facts showing that
there is a genuine issue for trial.” Liberty Lobby, Inc., 477 U.S. at 248 (quoting First
Nat’l Bank of Ariz. v. Cities Serv. Co., 391 U.S. 253, 288 (1968)). “[M]ere denials or
conclusory statements are insufficient.” SRI Int’l v. Matushita Elec. Corp. of Am.,
775 F.2d 1107, 1116 (Fed. Cir. 1985) (citing Barmag Barmer Maschinenfabrik AG v.
Murata Machinery, Ltd., 731 F.2d 831, 836 (Fed. Cir. 1984)). Finally, the evidence
must be viewed in the light most favorable to the party opposing the motion. Crown
Operations Int’l, Ltd. V. Solutia Inc., 289 F.3d 1367, 1375 (Fed. Cir. 2002).
III. Appellant Has Not Shown A Need For Additional Discovery
Appellant first contends the Board should deny the Army’s summary judgment
motion because the Army failed to provide information and/or documents responsive
to appellant’s discovery requests that appellant needs to respond to the motion (app.
resp. at 14-16). Appellant correctly notes the Federal Rules permit the Board to deny a
motion for summary judgment if the non-movant has not had the opportunity to
conduct necessary discovery. See Board Rule 7(c); Fed. R. Civ. P. 56(d); Dunkin
Donuts of America, Inc. v. Metallurgical Exoproducts Corp., 840 F.2d 917, 919 (Fed.
Cir. 1988). The rule, however, specifically states the nonmovant must show “by
affidavit or declaration that, for specified reasons, it cannot present facts essential to
justify its opposition . . . .” Fed. R. Civ. P. 56(d). “Thus, a party opposing summary
judgment cannot obtain the protection of Rule 56(d) ‘by simply stating that discovery
is incomplete.’” Odyssey International, Inc., ASBCA Nos. 62062, 62279, 21-1 BCA
¶ 37,902 at 184,071 quoting Libertarian Party of N.M. v. Herrera, 506 F.3d 1303,
1308 (10th Cir. 2007). Rather, the party opposing the motion must “state with
specificity how the additional material will rebut the summary judgment motion.”
Libertarian Party of N.M., 506 F.3d 1308-09 citing Ben Ezra, Weinstein & Co. v. Am.
Online Inc., 206 F.3d 980, 987 (10th Cir. 2000). Here, appellant has provided no such
support.
Rather, appellant claims the Army failed to provide it with correspondence
within the Army and between the Army and ANDSF about “security of the facilities,
changes in force protection requirements, threats to facilities, need for continued
delivery of fuel to those facilities as well as what happened to the fuel after TLS’
employees were removed from the facilities” (app. resp. at 15-16). The government
replies those requested documents are “irrelevant for the purposes of the motion for
summary judgment” (gov’t reply at 34). We agree with the government. Any
communications between the Army and GIRoA, or within the Army, will not change
the plain unambiguous contract language or impact the government’s affirmative
defenses. Appellant has failed to show how the additional requested discovery will
lead to facts necessary for its defense of the government’s motion.
10
IV. The Government Did Not Beach the Contract
A. Delivered Fuel
To prevail on a breach of contract claim, TLS must show: (1) a valid contract
between the parties; (2) a government obligation or duty arising out of the contract;
(3) a breach of that duty; and (4) damages caused by that breach. Trident Engineering
& Procurement, P.C., ASBCA Nos. 60541, 62144, 23-1 BCA ¶ 38,351 at 186,235;
Lockheed Martin Integrated Sys., Inc., ASBCA Nos. 59508, 59509, 17-1 BCA
¶ 36,597 at 178,284 citing San Carlos Irrigation & Drainage Dist. v. United States,
877 F.2d 957, 959 (Fed. Cir. 1989).
In Count I of its complaint, TLS alleges the government breached the contracts
by failing to pay for what it refers to as “delivered” fuel (compl. ¶¶ 74-79). This is
somewhat confusing because in the complaint’s prayer for relief, TLS seeks payment
only for pre-positioned fuel stored at the ANDSF facilities and regional terminals
(compl. prayer for relief). TLS apparently seeks to recharacterize this fuel as delivered
fuel despite lacking any evidence of actual delivery.
The government responds it did not breach the contracts because it paid
appellant for all the fuel delivered under the contracts including $2,201,966 for unpaid
verified invoices and $44,937 for rejected invoices (gov’t mot. at 18). 5 The
government admits it did not pay TLS for the on-base and terminal fuel because it had
no duty to pay TLS for those items (id.). Moreover, the government contends it has no
responsibility to pay for those items since their loss resulted from third party actions
(id. at 19).
1. The Contracts Defined “Delivery” To Be Fuel Delivered Into the Aircraft
The contracts incorporated by reference FAR 52.212-4, CONTRACT TERMS
AND CONDITIONS – COMMERCIAL ITEMS (JAN 2017) (SOF ¶ 3). The FAR
52.212-4(i) payment provisions required the government to make payment to TLS for
items that were “accepted” and “delivered” to the destination set forth in the contract.
The contracts specified delivery and acceptance occurred when TLS delivered the fuel
into the aircraft and the ANDSF delivery activity signed off on the delivery ticket
indicating the actual delivered fuel amount (SOF ¶ 4). Based on the plain contract
5
As previously noted, the contracting officer determined these were allowable costs in
his final decision, but the record is unclear whether the government has actually
paid TLS for these allowed costs (SOF ¶ 21).
11
language, fuel that is pre-positioned or stored in a regional terminal has not been
delivered and accepted. 6
TLS does not dispute the government paid it for the fuel delivered into the
designated aircraft but rather contends all the fuel delivered to the ANDSF aircraft
after the Taliban takeover and all the fuel maintained at the facilities and regional
terminals should be “deemed delivered and accepted” (compl. ¶ 45). TLS maintains it
became impossible for it to obtain the confirmation of acceptance and fuel delivery
into the ANDSF aircraft after the Taliban takeover (id.). Moreover, TLS contends all
the fuel should be determined to be delivered and accepted since the contract required
TLS to preposition the fuel to maintain an effective supply chain thereby ensuring an
uninterrupted fuel supply (id). In the alternative, TLS claims delivery of the fuel was
completed and accepted by ANDSF the moment the Taliban took over the facilities
and denied TLS access (compl. ¶ 46).
Appellant has the burden of proof to prove government acceptance. Chloeta
Fire, LLC, ASBCA No. 59211, 15-1 BCA ¶ 36,167 at 176,485. Here, appellant has
presented no evidence that the Afghan government accepted the fuel delivered into any
aircraft after the Taliban takeover or any prepositioned fuel. The government had no
obligation to pay TLS for undelivered fuel.
The parties do not dispute that the Taliban confiscated the undelivered fuel
when it took over the facilities (SOF ¶ 18). The Federal Circuit has long held “absent
fault or negligence or unqualified warranty of the part of its representatives, the
Government is not liable for damages resulting from the action of third parties.”
Oman-Fischbach Int’l (JV) v. Pirie, 276 F.3d 1380, 1385 (Fed. Cir. 2002); see also
Zafer Taahhut Insaat ve Ticaret A.S. v. United States, 833 F.3d 1356, 1364 (Fed. Cir.
2016) (addressing Pakistan’s closure of its border with Afghanistan, delaying
appellant’s delivery of materials, and holding “the U.S. government is not responsible
for the sovereign acts of a foreign nation”); Omran, Inc., ASBCA No. 63414, 24-1
BCA ¶ 38,572 at 187,477 (government not liable for contractor’s loss of construction
equipment since the Taliban’s seizure of that equipment was not foreseeable); Piril
Insaat Tic. Bilgisayar Elek. Buro Donanim Ltd. Sti., ASBCA No. 55605, 08-2 BCA
¶ 34,010 at 168,187 (government not liable for truck damages since the hostile rifle
fire that damaged the truck was not an act of the government). Here, the Taliban, a
third-party, took TLS’s undelivered fuel and equipment. The government is not
responsible for the Taliban’s actions.
6
Similarly, the contracts required TLS to deliver the fuel on “a Free on Board (FOB)
Destination Basis (SOF ¶ 2). FAR 2.101 provides, “F.o.b. destination means
free on board at destination: i.e., the seller or consignor delivers the goods on
seller’s or consignor’s conveyance at destination.” Under the contracts, the
delivery destination was the aircraft (SOF ¶ 2).
12
2. The Contracts Allocated the Risk of Loss to TLS
The commercial items clause further provided:
(j) Risk of loss. Unless the contract specifically provides
otherwise, risk of loss or damage to the supplies provided
under this contract shall remain with the Contractor until,
and shall pass to the Government upon: . . .
(2) Delivery of the supplies to the Government at the
destination specified in the contract, if transportation is
f.o.b. destination.
FAR 52.212-4(j)(2)
Here, the contract specified fuel delivery occurred when TLS pumped the fuel
into the aircraft (SOF ¶ 2). Accordingly, FAR 52.212-4(j)(2) placed the risk of loss on
appellant until it delivered the fuel. See KAL M.E.I. Manufacturing & Trade Ltd.,
ASBCA Nos. 44367, 45531, 45532, 94-1 BCA ¶ 26,582 at 132,258 (risk of loss
remained with the contractor until delivery of the supplies to the government at the
destination on a contract with a f.o.b. destination clause); Donaldson Enterprises, Inc.,
ASBCA No. 57927, 13-1 BCA ¶ 35,368 at 173,562 (finding FAR 52.212-4(j)(2)
expressly placed the risk of loss on the contractor up until the time the bailed rock was
redelivered to the government).
Similarly, the contract’s SOW also clearly specified the risk of loss would
remain with the contractor until acceptance. SOW Section 6.14, Acceptance, stated that
“[u]ntil acceptance, risk of loss or damage shall remain with the Contractor” (SOF ¶ 4).
In addition, SOW Section 14, Risk of Loss, provided, “[r]isk of loss or damage shall
remain with the Contractor, until, and will pass to U.S. Government upon, delivery of
the aviation turbine fuel products into AAF or SMW aircraft” (SOF ¶ 11).
TLS contends these contractual risk of loss provisions do not apply in this case
because they are limited to those losses occurring during contract performance, “e.g.,
from issues involving TLS’ transportation, storage or handling of the fuel” (app. resp.
at 18). TLS argues the parties intended the risk of loss provisions “to make sure that TLS
took the necessary measures to get fuel from its origins to the relevant facilities and
terminals to prevent Army paying for fuel damaged or pilfered along the way to the
relevant facilities” (id.). TLS points to SOW Section 14.1 to support its contention (id.).
SOW Section 14.1 provides TLS would bear “all risk and responsibility for loss or
damage to equipment and personal injury or death . . . if such damage, personal injury or
death arises from or relates to any performance under this contract” (SOF ¶ 11). TLS
13
maintains the fuel and equipment losses in this case did not occur during contract
performance but rather from their seizure by the Taliban (app. resp. at 18). TLS’s
interpretation of this contract loss provision is not supported by the contract’s plain
language.
SOW Section 14.1 addresses the loss or damage to equipment and personal
injury or death but not loss of fuel (SOF ¶ 11). When read as a whole, Section 14
clearly places the risk of loss of fuel on the contractor until delivery. McAbee
Construction, Inc. v. United States, 97 F.3d 1431, 1434-35 (Fed. Cir. 1996) (contract
must be read as a whole to harmonize and give meaning to all parts). The initial
language in SOW Section 14 states, “[r]isk of loss. . . shall remain with the Contractor,
until . . . delivery of the aviation turbine fuel products into AAF or SMW aircraft”
(SOF ¶ 11). SOW Section 14.2 places the responsibility upon the contractor to obtain
adequate insurance to cover the risk of loss (id.). Further, SOW Section 14.3 states
that the United States will not pay the contractor for claims stemming from loss or
damage to product or equipment (id.).
Finally, the contracts’ SOW specifically notified TLS that it may be required to
perform the contract “in dangerous or austere conditions” and that it was accepting
“the risks associated with the required contract performance in such operations”
(SOF ¶ 12). TLS had clear notice that it was performing the contract in a dangerous
environment that could result in the loss of both fuel and equipment due to hostile
action. TLS accepted that risk upon contract award. Omran, Inc., 24-1 BCA ¶ 38,572
at 187,477 (contractor accepted potential loss of its equipment and materials to the
Taliban at contract award).
TLS has failed to present sufficient evidence upon which a reasonable
factfinder could find that there are material facts in dispute that the government
breached the contract by failing to pay TLS for fuel delivered to aircraft after the
Taliban takeover, the pre-positioned fuel stored at the applicable facilities and the fuel
held in the regional terminals. The government is entitled to summary judgment on
this issue.
B. Security and Access
In Count II of its complaint, TLS alleges the government breached the contract
by failing to provide adequate security and facility access (compl. ¶¶ 80-84).
1. The Government Had No Contractual Duty To Provide Security
TLS contends the government breached its duty of providing a secure area when
it allowed the Taliban to take over the facilities and equipment (compl. ¶¶ 81-82).
14
Appellant first asserts a material factual dispute exists concerning the Army’s
obligation to provide security (app. resp. at 2). 7 Appellant, however, does not cite to
any specific material disputed facts but largely relies upon legal arguments interpreting
the various contractual provisions. The interpretation of a government contract is a
question of law not fact. Triple Canopy, Inc. v. Sec’y of Air Force, 14 F.4th 1332,
1338 (Fed. Cir. 2021).
The contracts’ SOW Section 13.1, SECURITY REQUIREMENTS, placed on
TLS the responsibility “for security of all vehicles, personnel and aviation fuel being
transported under this contract” (SOF ¶ 7). That provision further required TLS to
provide its own security in accordance with all applicable GIRoA and United States
laws, regulations, and orders (id.). TLS engaged the Afghanistan Ministry of the
Interior National Public Protection Force for its security (id.).
TLS contends these security requirements placed the security responsibility upon
it only during the transportation of the fuel to the relevant facilities (app. resp. at 5).
TLS claims the facilities were the delivery point (id.). Once the fuel arrived at the
facilities, TLS maintains the security obligation passed to the government (id.). TLS
points to SOW Section 13.2 in support of this contention (id.). That provision, entitled
“Delivery Point Security,” indicated force protection requirements were in effect under
the contract and there could be waiting periods outside the facility gates (SOF ¶ 7.).
TLS contends that since the Army established the overall force protection requirements,
the Army warranted the facilities would be a secure area (app. resp. at 5). TLS
misreads the security provisions.
The contracts specify the contractual delivery point is delivery of the fuel into
the aircraft and not delivery to the facilities (SOF ¶ 2). As previously discussed, TLS
remained the responsible party until it delivered the fuel into the aircraft. Likewise,
TLS’s transportation obligations continued until it physically delivered the fuel into
the aircraft.
SOW Section 13.2 does not alter TLS’s contractual responsibilities. That
provision simply states force protection requirements were in effect. TLS correctly
notes the Army established the overall force protection requirements in Afghanistan
(SOF ¶ 9). The force protection requirements included setting out the procedures for
entering and exiting facilities (id.). Local commanders at individual facilities could
modify the force protection posture based upon individual threats at their locations
7
Confusingly, appellant in the next sentence contends the “[u]ndisputed facts prove”
the army had a contractual obligation “to provide adequate security to TLS and
its personal and equipment at the facilities” (app. resp. at 2).
15
(id.). Contrary to TLS’ conclusion, those requirements did not warrant that the
United States guaranteed the security for any facility.
TLS also claims the government breached its contractual security obligations by
failing to provide adequate information and warning about the Taliban takeover (app.
resp. at 6). TLS contends SOW provision 13.2 imposed upon the Army a requirement to
notify it of imminent threats (id.). TLS claims it could have taken action to mitigate its
damages if the government had notified it of the Taliban threat (id.). The government
correctly notes this provision contains no such explicit or implicit notification
requirement (gov’t reply at 28).
The contract terms clearly placed the security responsibility upon TLS and not
the government. We conclude the government did not breach the contract by failing to
provide adequate security because no such contractual duty existed.
2. The Government Had No Contractual Duty To Provide Access
TLS also contends the government breached its contractual duty of providing it
access to the relevant facilities (compl. ¶ 81). Appellant again first contends a material
factual dispute exists concerning the Army’s failure to provide TLS access but does
not cite to any specific disputed facts in the record (app. resp. at 6-7). Appellant
instead asserts the contract’s SOW sections 4 and 20.1 placed an obligation upon the
government to provide TLS access to the facilities (id. at 6). Similar to the security
question, whether the contracts required the government to provide TLS access to the
facilities is a legal question dependent upon the contract terms.
The contracts’ SOW Section 4 required the government to identify a contact
person for TLS to coordinate with to, among other things, obtain the required facility
access (SOF ¶ 6). That provision did not guarantee facility access. Similarly,
Section 20.1 indicated the government would coordinate and assist TLS in the event of
any access denial to the facilities that interfered with contract performance (SOF ¶ 10).
This section likewise did not guarantee access.
The contracts also included C-JTSCC 5152.225-5916, MANDATORY
ELIGIBILITY FOR INSTALLATION ACCESS (OCT 2015) (SOF ¶ 8). That clause
specifically notified TLS that the installation commander had the inherent authority to
control installation access (id.). The clause further notified TLS that the commander’s
authority was independent from the government’s contractual authority (id.). “A
determination of installation access is a matter of inherent command authority and is
not at the discretion of the contracting officer or this Board.” Sang Kash Company,
ASBCA No. 60532, 19-1 BCA ¶ 37,373 at 181,703 (refusing to question a military
commander’s revocation of base access). The installation commander’s decisions to
16
limit TLS’ employees’ access to some of the facilities did not result in a government
contract breach.
3. Sovereign Acts Defense
Even if the government had breached a contractual obligation to provide
security or access to the facilities, the government correctly notes the sovereign acts
defense would prevent any recovery (gov’t mot. at 8-10). “The sovereign acts doctrine
provides that ‘the United States when sued as a contractor cannot be held liable for an
obstruction to the performance of the particular contract resulting from its public and
general acts as a sovereign.’” Conner Bros. Constr. Co. v. Geren, 550 F.3d 1368,
1371 (Fed. Cir. 2008) (quoting Horowitz v. United States, 267 U.S. 458, 461 (1925).
The United States’ withdrawal of its troops from Afghanistan made it impossible for
the government to meet any contractual obligation to provide TLS security and access
to the ANDSF facilities. Casitas Municipal Water Dist. v. United States, 543 F.3d
1276, 1287 (Fed. Cir. 2008) (The government is excused from performance under the
sovereign acts defense when the sovereign act renders the government’s performance
impossible.) As such, the sovereign acts defense would excuse the government from
any contractual breach if such a breach existed.
In this case, appellant does not dispute the United States decision to enter into
the Doha Agreement with the Taliban and its decision to withdraw troops from
Afghanistan were sovereign acts (app. resp. at 16). Appellant contends, however, that
the Army’s failure to provide security or TLS employee’s access to the facilities both
were a breach of the Army’s express contractual obligations and not subject to the
sovereign acts defense (id. at 16-17). As discussed above, we conclude the Army had
no contractual obligation to provide security or facility access to appellant. As such,
application of the sovereign acts doctrine is not necessary since it requires that “the
government acting as a contractor must have breached the contract.” StructSure
Projects, Inc., ASBCA No. 62927, 23-1 BCA ¶ 38,416 at 186,680.
C. Duty of Good Faith and Fair Dealing
In Count III of its complaint, TLS alleges the government breached its implied
duty of good faith and fair dealing (compl. ¶¶ 85-90). The doctrine of good faith and
fair dealing prohibits “interference with or failure to cooperate in the other party’s
performance.” Labatte v. United States, 899 F.3d 1373, 1379 (Fed. Cir. 2018)
(quoting Restatement (Second) of Contracts § 205 cmt. d (1981)). Pursuant to this
implicit duty, each party’s obligations “include the duty not to interfere with the other
party’s performance and not to act so as to destroy the reasonable expectations of the
other party regarding the fruits of the contract.” Metcalf Construction Company, Inc.,
742 F.3d 984 at 991 (Fed. Cir. 2014) (quoting Centex Corp. v. United States, 395 F.3d
1283, 1304 (Fed. Cir. 2005). The duty is “keyed to the obligations and opportunities
17
established in the contract.” Lakeshore Engineering Services, Inc. v. United States,
748 F.3d 1341, 1349 (Fed. Cir. 2014). See also Metcalf, 742 F.3d at 991-92
(explaining the need to consider the contract’s allocation of risks and benefits in
considering a claim of breach of the duty of good faith and fair dealing). The implied
duty of good faith and fair dealing does not “expand a party’s contractual duties
beyond those in the express contract or create duties inconsistent with the contract’s
provisions.” Precision Pine & Timber, Inc., v. United States, 596 F.3d 817, 831 (Fed.
Cir. 2010).
Appellant contends the government breached its duty of good faith and fair
dealing by failing to provide it with information on the deteriorating security situation
in Afghanistan and by its failure to provide direction in response to the various
submitted SIRs (compl. ¶ 87). Appellant also contends the government breached its
duty by failing to cooperate with TLS in safeguarding the fuel (compl. ¶ 88). Appellant
alleges these failures prevented TLS from taking the necessary actions to mitigate its
losses (compl. ¶ 87). In addition, TLS asserts the Board should deny the government’s
motion since a material factual dispute exists concerning the Army’s failure to meet its
duty of good faith and fair dealing under the contracts (app. resp. at 11).
In its summary judgment motion, the government argues appellant cannot
establish any facts to support a breach of the duty of good faith and fair dealing (gov’t
mot. at 19). The government contends it had no contractual duty to notify TLS of the
deteriorating security situation and respond to TLS’ SIRs (id. at 20-21). The
government points out the contracts did not require TLS to submit the SIRs, and TLS
submitted those reports solely for informational purposes to notify the government
when certain facilities were attacked and captured by the Taliban (id. at 20-22). The
reports did not request the government take any actions (SOF ¶ 16). The government
also contends TLS has provided no evidence indicating the government intentionally
withheld security information from TLS that hindered its contract performance (gov’t
mot. at 21).
We have previously held “[w]here the failure to take some positive action is
alleged as a breach of the duty of cooperation, it must be shown that the action was
necessary for performance of the contract, and the Government unreasonably failed to
take the action.” Envtl. Safety Consultants, Inc., ASBCA No. 47498, 00-1 BCA
¶ 30,826 at 152,145. TLS alleges the government failed to notify it of the deteriorating
security situation in Afghanistan and failed to respond to the SIRs. Those actions,
however, even if true, did not impact TLS’ ability to perform the contract. TLS
appears to have submitted the SIRs for purely informational purposes to tell the
government which facilities had fallen to the Taliban and the amount of lost fuel and
equipment (SOF ¶ 16). The SIRs did not request any government action (id.).
18
Moreover, the implied duty of good faith and fair dealing does not make the
government responsible for third-party actions. Olympus Corp. v. United States,
98 F.3d 1314, 1318 (Fed. Cir. 1996) (“While interference by the government with a
contractor’s access to the work site may constitute a breach of the government’s duty
to cooperate, the government is not responsible for third-party actions such as labor
strikes that delay a contractor’s performance, absent a specific contractual provision.”)
Here, the Taliban’s actions, and not any action or inaction by the government,
prevented TLS from performing the contracts.
When the government is accused of breaching the duty of good faith and fair
dealing, the Board will examine the reasonableness of the government’s actions,
considering all the circumstances. SIA Construction, Inc., ASBCA No. 57693,
14-1 BCA ¶ 35,762 at 174,986. Ordinarily, issues requiring a determination of
whether a parties’ actions were reasonable cannot be disposed of by summary
judgment (id.). In this case, however, appellant has identified no material facts
indicating the government’s actions or inactions prevented TLS from performing its
contractual duties. See Grow Life General Trading, LLC, ASBCA Nos. 60398, 60467,
60887, 19-1 BCA ¶ 37,361 at 181,676 (An allegation the government breached its
implied duty of good faith and fair dealing lacked merit because there was no evidence
the government prevented the contractor from performing its duties). Under these
circumstances, we conclude the government’s actions were reasonable.
As previously discussed, the contract itself allocated the risk of operating in a
hostile environment to TLS. Whether the government failed to provide TLS with
direction in response to the SIRs or updates on the pending security situation did not
frustrate TLS’s ability to perform the contract. See Bell/Heery, a Joint Venture v.
United States, 739 F.3d 1324, 1335 (Fed. Cir. 2014) (Court rejected contractor’s good
faith and fair dealing claim finding the contract allocated the risks attending to
securing the required state permits to the contractor and the government did not
affirmatively interfere with the contractor’s dealings with the state agency); JAAAT
Technical Services, LLC., ASBCA No. 62373, 22-1 BCA ¶ 38,086 at 184,965
(rejecting contractors’ breach of the duty of good faith and fair dealing claim since it
would impose upon the government a duty inconsistent with the contract provisions).
Accordingly, based on the record, the government is entitled to summary judgment on
this issue.
V. Constructive Change
In addition to its contract breach claims, TLS contends in Count V of its
complaint that the government constructively changed the contracts (compl. ¶¶ 96-101).
Appellant alleges the Army constructively changed the contract when the government
and ANDSF denied TLS access to the relevant facilities, and the government and/or
ANDSF took control of TLS’s facilities, fuel and equipment thereby abandoning the
19
contractual fuel delivery and acceptance procedures (compl. ¶ 99). Appellant also
alleges the government constructively changed the contracts when it failed to secure the
facilities, fuel, and equipment (compl. ¶ 100).
In its motion, the government contends appellant is not entitled to an equitable
adjustment due to a constructive change because appellant did not perform any work
beyond the contract requirements and the government did not order, expressly or
impliedly, any additional work (gov’t mot. at 23-24). In its response to the
government’s motion, appellant further suggests the government changed the contract
by requiring fuel delivery by air on at least one occasion (app. resp. at 9).
To recover for a constructive change, a contractor must prove (1) it performed
work beyond the contract requirements; and (2) the government expressly or impliedly
ordered the additional work. Bell/Heery, 739 F.3d at 1335; ANHAM FZCO, LLC,
ASBCA No. 58999, 20-1 BCA ¶ 37,745 at 183,186. The contracts required TLS to
deliver fuel into the aircraft (SOF ¶ 2). Appellant first suggests material factual
disputes exist with regards to the constructive change as to (1) whether the Army
provided the necessary security and/or access to the facilities; (2) the Army’s
continued requirement for appellant to provide the fuel despite the deteriorating
security situation; and (3) the Army’s requirement for TLS to deliver fuel and
equipment by air to some facilities (app. resp. at 8-9).
With regards to appellant’s first two contentions, the government correctly
points out that even if true, they would not constitute constructive changes because
appellant performed no additional work beyond the contracts’ requirements (gov’t
mot. at 23). Appellant admits that its claim amounts result from its total loss of the
fuel reserves and equipment and assets used to transport, store, and deliver the fuel and
not increased costs resulting from work performed beyond the contracts’ requirements
(compl. ¶ 36).
Appellant further suggests the Army somehow constructively changed the
contracts’ requirements when ANDSF changed the fuel delivery and acceptance
procedures following the Taliban takeover (app. resp. at 10). It is well established that
interference by a foreign government is not a constructive change. Kellogg Brown &
Root Servs., ASBCA No. 59385, 20-1 BCA ¶ 37,656 at 182,832. Moreover, to prevail
on its constructive change claim, TLS must show an authorized government
representative required or compelled it to perform work beyond the contracts’
requirements. Environmental Chemical Corporation, ASBCA Nos. 59280, 60760,
22-1 BCA ¶ 38,166 at 185,361. Appellant has not identified any explicit or implicit
government action that required it to perform work beyond the contracts’
requirements.
20
Finally, appellant suggests that on at least one occasion, the government
constructively changed the contracts’ by requiring TLS to provide air transport to
deliver fuel and equipment to some facilities (app. resp. at 9). Appellant cites to an
email in which the Army contracting officer representative asks TLS whether they can
do an air cargo lift since fuel is becoming an urgent need (SOF ¶ 17). While the
record is unclear as to whether TLS airlifted any fuel into Shorab, the evidence
suggests TLS moved another bowser by air allegedly at the Army’s request (id.).
Even if the Army requested TLS move a fuel bowser by air, however, that
request would not have been a constructive change to the contracts. The contracts
required TLS to provide all the necessary transportation to deliver the fuel into the
aircraft on a FOB destination basis (SOF ¶ 2). The contract did not specify how TLS
should transport that fuel to the facilities. An Army request to TLS to deliver fuel by
air to the facilities would not be a change to the contracts’ requirements.
TLS did not perform work beyond the contracts’ requirements. Moreover, we
find no evidence that the government either expressly or impliedly ordered any
additional work. Accordingly, the government is entitled to summary judgment on
this issue.
VI. Termination for Convenience Costs
TLS also filed a cross-motion for partial summary judgment claiming it is entitled
to receive compensation as part of its termination for convenience settlement costs for its
lost fuel reserves and equipment (app. resp. at 20-22). 8 TLS claims the contracts
required it to maintain a fuel reserve and equipment at each of the specified facilities and
at the regional terminals to ensure an uninterrupted fuel supply (id. at 20-21). TLS
further alleges the government did not give it the opportunity to remove the fuel and
equipment before the Taliban takeover (id. at 22). As such, TLS claims the fuel reserves
and equipment at the facilities and regional terminals should be considered as part of its
completed work under the contracts (id. at 21-22).
The government responds it is not responsible for paying appellant for any of
its lost stored fuel or equipment costs as part of the termination settlement since the
Taliban seized those items prior to the termination and appellant bore that risk of loss
(gov’t reply at 35). The government contends those losses resulted from the actions of
a third-party and not the termination (id.).
The contracts incorporated the commercial termination clause at FAR 52.212-
4(l) (SOF ¶ 3). Our previous decisions have analyzed this clause as providing for
8
The Board notes the government has not filed a cross-motion for summary judgment
on the termination for convenience issue.
21
reimbursement under two prongs: the first prong being for the percentage of work
performed prior to the termination notice and the second prong for costs resulting from
the termination including settlement costs. See SWR, Inc., ASBCA No. 56708,
15-1 BCA ¶ 35,832 at 175,223-24; Zahra Rose Construction, ASBCA No. 62732,
22-1 BCA ¶ 38,111 at 185,111.
Under the first prong, TLS is limited to recovering the price of the delivered
fuel prior to the termination as the work performed under the contracts. See Hermes
Consolidated, Inc., d/b/a Wyoming Refining Co., ASBCA Nos. 52308, 52309,
02-1 BCA ¶ 31,767 at 156,899 (recovery limited to the price of fuel delivered plus
“reasonable charges” under a fuel supply contract because the termination for
convenience clause permitted the government to terminate any portion of the
guaranteed minimum quantity and be responsible only for the price of delivered fuel);
ACLR, LLC v. United States, 157 Fed. Cl. 324, 333 (2021) (prong one looks to the
amount of payment the contractor is entitled to be paid under the terms of the
contract). Under the contracts, the government was responsible for paying TLS for
delivered fuel (SOF ¶ 4). The government paid TLS for that fuel (SOF ¶ 21). As
such, TLS summary judgment motion seeking a determination that its fuel reserves
and equipment at the facilities and regional terminals be considered as part of its
completed work under the contracts is denied.
The commercial termination for convenience clause, however, also provides
recovery for any reasonable expenses resulting from the termination including costs
incurred in preparing to perform the contracts. See SWR, Inc., 15-1 BCA ¶ 35,832
at 175,227-28 (contractor entitled to recover a deposit for fabric structures made prior
to the termination for convenience while preparing to perform the contract); Zahra
Rose Construction, 22-1 BCA ¶ 38,111 at 185,111 (contractor entitled to recover its
costs incurred in leasing fuel trucks in preparation for performing the contract). As we
explained in SWR, FAR 52.212-4(l) provides for the “recovery of those charges
incurred that ‘do not relate to work completed’ but should be reimbursed to fairly
compensate the contractor whose contract has been terminated.” SWR, 15-1 BCA
¶ 35,832 at 175,223. This principle is consistent with the overall purpose of a
termination for convenience settlement which is to fairly compensate the contractor
and to make the contractor whole for the costs incurred in connection with the
terminated work. Id. (citing Nicon, Inc. v. United States, 331 F.3d 878, 885 (Fed. Cir.
2003). “A contractor is not supposed to suffer as the result of a termination for
convenience of the Government, nor to underwrite the Government’s decision to
terminate.” Jacobs Engineering Group, Inc. v. United States, 434 F.3d 1378. 1381
(Fed. Cir. 2006) (quoting Kasler Electric Co., DOT CAB 1425, 84-2 BCA ¶17,374
at 86,566-67).
The Army contends TLS is not entitled to any payment for the lost fuel reserves
and equipment under the termination for convenience since the Taliban seized those
22
items shortly prior to the termination and TLS bore the risk of loss (gov’t reply br.
at 35). TLS, however, incurred the costs to preposition the undelivered fuel and
equipment in preparing to perform the contracts prior to the Taliban’s seizure. The
contracts required TLS to maintain minimum fuel reserves and bowser quantities to
ensure an uninterrupted fuel supply to meet the required fuel deliveries (SOF ¶¶ 2, 13).
TLS may be entitled to recover those costs under the commercial termination for
convenience clause as costs reasonably incurred in preparing to perform the contracts. 9
The existing record, however, is unclear as to whether TLS could have taken any
actions to avoid the loss and thereby mitigate the costs. Zahra Rose Construction,
22-1 BCA ¶ 38,111 at 185,111 (avoidance of additional cost is a duty of a terminated
contractor). The record is also unclear as to whether TLS obtained the required
insurance that may offset some of its claimed termination costs. Accordingly, we
conclude that the record needs to be further developed on this issue and thus, summary
judgment is not appropriate at this time. See Conquistador Dorado JV, ASBCA
No. 60042 et al., 20-1 BCA ¶ 37,628 (summary judgment not appropriate when record
needs further development).
TLS bears the burden of proving its recovery of the government’s refusal to pay
its claimed termination settlement costs. SWR, 15-1 BCA ¶ 35,832 at 175,229 (citing,
Lisbon Contractors, Inc. v. United States, 828 F.2d 759, 767 (Fed. Cir. 1987). That
proof should be of “sufficient certainty so that the determination of the amount of the
damages will be more than mere speculation.” Lisbon Contractors, Inc., 828 F.2d
at 767 (Fed. Cir. 1987).
9
To be clear, we make no determination currently on TLS’s claim for termination
costs under FAR 52.212-4(l) prong two.
23
CONCLUSION
For the reasons set forth above, the government’s motion for summary
judgment on appellant’s breach of contract contentions (Counts I, II, III) is granted. In
addition, the government’s motion for summary judgment on appellant’s constructive
change allegation (Count V) is granted. Appellant’s cross-motion for partial summary
judgment on the termination for convenience costs (Count IV) is denied. Thus, this
decision does not resolve the entire appeal as TLS’ entitlement to additional
termination settlement costs, if any, will be addressed in further proceedings.
Dated: August 12, 2024
ARTHUR M. TAYLOR
Administrative Judge
Armed Services Board
of Contract Appeals
I concur I concur
OWEN C. WILSON MICHAEL N. O’CONNELL
Administrative Judge Administrative Judge
Acting Chairman Vice Chairman
Armed Services Board Armed Services Board
of Contract Appeals of Contract Appeals
24
I certify that the foregoing is a true copy of the Opinion and Decision of the
Armed Services Board of Contract Appeals in ASBCA No. 63282, Appeal of Targe
Logistic Services Company, rendered in conformance with the Board’s Charter.
Dated: August 12, 2024
PAULLA K. GATES-LEWIS
Recorder, Armed Services
Board of Contract Appeals