Opinion

Triangle American Homes v. Samuel B. Harrison

Court
Court of Appeals of Tennessee
Filed
Oct 13, 2011
Status
Published
On the bench
Judge John W. McClarty
Cited by
0 cases
Authority
More cited than 29.2%

The opinion

IN THE COURT OF APPEALS OF TENNESSEE

AT KNOXVILLE

December 14, 2010 Session

TRIANGLE AMERICAN HOMES v. SAMUEL B. HARRISON, ET AL.

Appeal from the Chancery Court for Loudon County

No. 10889 Frank W. Williams, III, Chancellor

No. E2009-01954-COA-R3-CV-FILED-OCTOBER 13, 2011

In this indemnity case, Jere Krieg (“Builder”), through Triangle American Homes, Inc.,

initially filed a complaint for attachment and damages against Samuel and Lauren Harrison

(collectively “the Harrisons”) relating to the construction of a modular home. When the

Harrisons filed a counterclaim, arguing that Builder had failed to perform pursuant to their

contract, Builder brought a third-party complaint against All American Homes of Tennessee,

LLC (“Seller”), alleging that Seller should indemnify Builder. Builder and the Harrisons

entered into a settlement agreement. In the remaining suit for indemnification, Seller argued

that Builder was not entitled to indemnity because the damages and losses sustained by

Builder were a result of Builder’s actions. Following a bench trial, the trial court held that

Builder was entitled to damages in the amount of $45,000 and attorney fees in the amount

of $45,000, for a total award of $90,000. Seller appeals. We modify the award of attorney

fees to $18,084 and affirm the decision of the trial court in all other respects.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court

Affirmed as Modified; Case Remanded

J OHN W. M CC LARTY, J., delivered the opinion of the court, in which H ERSCHEL P. F RANKS,

P.J., and C HARLES D. S USANO, J., joined.

A. Wayne Henry (at trial and on appeal), Loudon, Tennessee, and Stephanie L. Nemeth (on

appeal) and Jason W. Cottrell (at trial), Mishawaka, Indiana, for the appellant, All American

Homes of Tennessee, LLC.

Jack M. Tallent, II, Knoxville, Tennessee, for the appellee, Triangle American Homes, Inc.

OPINION

I. BACKGROUND

In 2003, Builder entered into an agreement with Seller, whereby Builder was allowed

to purchase, install, resell, and service Seller’s modular homes.1 Pursuant to the agreement,

Builder was responsible for “all obligations arising from the excavation and land condition,

backfilling and grading, footings, basement floor, crawlspace, foundation walls, HVAC

system, and any and all additional work and/or material not specifically set forth and agreed

to be provided by [Seller].” Builder also had the option of purchasing additional finishing

services, including an interior and exterior trim out, which were necessary because the areas

where the sections joined, referred to as the marriage line, were not completed. If Builder

purchased an interior trim out, Seller agreed to complete the wall openings at the marriage

line; install doors at the marriage line, base trim, flooring cutbacks at door openings, and

loose light fixtures; adjust the interior and exterior doors; and touch-up the walls. If Builder

purchased an exterior trim out, Seller agreed to install shutters, channels, trim, wood, siding,

corners, blocks, support boards, panels, roofing edges, covers, and windows. If Builder did

not purchase these services, he was responsible for performing these services.

In 2005, the Harrisons visited Builder’s office and displayed interest in purchasing a

modular home. The Harrisons inquired about the Kingston unit, which was composed of two

modules, and Builder subsequently discovered that a previously manufactured Kingston unit

was available. Builder informed them that a Kingston unit that had been built for another

customer was available and told them that if they purchased that unit, they could save money.

Builder did not inform them that the unit was commonly referred to as a yard unit because

it had been manufactured one year ago and had been sitting outside on wood cribbing.

When Builder contacted Seller, he was given a “quick quote sheet,” reflecting the

price for the unit itself and additional options. The quote sheet reflected a total price of

$91,573 for the potential transaction, including delivery, crane setting, and an exterior and

interior trim out of the unit. Approximately two months later, the Harrison gave Builder a

$5,000 deposit for the unit. Shortly thereafter, Builder sent Seller a $2,000 deposit for the

unit. The order was subsequently confirmed in an order sheet, which reflected Seller’s

receipt of Builder’s deposit, the base price for the unit, and the cost for an exterior and

interior trim, delivery, and crane setting of the two modules, with applicable discounts. The

order sheet reflected a total price for the transaction of $72,000, less the deposit, and

1

These homes were composed of separate modules that are manufactured inside Seller’s plant. Once the

modules were manufactured, they were delivered to a permanent foundation, where a crane set each module

in its place. The modules were then secured to the foundation and fastened together.

-2-

instructed Builder that if the unit was not delivered and set within 45 days, then Seller may

charge storage fees. Approximately one week later, Builder and the Harrisons executed a

contract providing for the purchase of the unit and additional site buildings, for a total price

of $173,376. One month later, Builder began work on the foundation.

On September 7, 2005, Seller sent Builder a letter, which provided, in pertinent part,

This letter is to inform you that [the Harrison] unit ha[s] exceeded the 45-day

delivery requirement. We will need to establish a firm delivery date within

five days or the units will become open and available to our builder network.

Please contact our transportation department so we can schedule delivery to

take place in the next thirty days.

These units are sold “as is” and will be delivered and crane set per our

guidelines. No interior or exterior trim out is available for th[is] unit.

Several days before the unit was scheduled to be delivered, Seller sent Builder a “Yard

Inventory Release,” which provided that the purchase price of the unit had been discounted

and that in consideration for the discount, the house was being sold “as is” with only a

Bonded Builders Warranty, not a manufacturer’s warranty as to condition or value. The

document also provided that the fees for delivery and set of the modules at the site location

were in addition to the newly discounted price. Pursuant to the document, Builder agreed to

inform the purchaser that the unit was sold without a manufacturer’s warranty and “perform

all necessary warranty work [and] assume all liability for any warranty work.” Seller told

Builder that they would not deliver the unit until Builder signed the document. Builder

signed the document and returned it to Seller.

On October 3, 2005, Seller attempted to deliver and set the modules. However, the

foundation was not ready, and the crane that had been ordered did not have enough

counterweights. The next day, Larry Lane, Seller’s plant manager, asked Builder to sign a

waiver of responsibility form because he believed the way in which the company driver had

to bring the unit in was “unsafe.” After Builder signed the form, Rodney Sculley, Seller’s

company driver,2 then drove the first module onto the site without incident other than some

“teeter[ing].” However, as he was driving the second module in, the left side of the module

leaned, tipped, and eventually rested on a pear tree in the driveway. Mr. Sculley and others

present had to use a bulldozer to right the module into the proper position. Once the module

was close enough to the foundation, the crane attempted to lift the module. As the crane was

lifting the module, a floor joist broke. The workers discovered that a lag bolt, which

2

Mr. Sculley testified at trial that he believed they used the best pathway to deliver the unit.

-3-

connected the module to attachments on the trailer, had not been removed. The force of the

crane had freed the module from the trailer, tearing the floor joist in the process. After the

modules were set, Builder and his employees began the process of completing the interior

and exterior trim outs and finishing the additional site buildings. Progress was slow, and

Builder had to change the estimated move-in date for the Harrisons a number of times.

The Harrisons were finally scheduled to move into the house on February 10, 2006.

When the Harrisons arrived, Builder was not present. Shane Roberts, one of Builder’s

employees, arrived two hours later. Shortly after Mr. Roberts arrived, Builder called and told

Mr. Roberts to gather the tools and leave the premises because the Harrisons owed Builder

money. Mr. Roberts left without taking the tools. When the Harrisons entered their new

house, they discovered that areas remained unfinished and that projects had not been

completed as they requested. The Harrisons refused to let anyone associated with Builder

return to remedy the problems with the house. A few weeks later, the Harrisons spoke with

one of Seller’s representatives, David Kurth, who told them that the modules should have

been brought in by a different route, that they had bought a yard unit, that the unit was sold

“as is,” and that they did not have the one-year manufacturer’s warranty as they had been

told. However, at some point, Michael Elliot, Seller’s customer service technician, repaired

some of the major drywall issues and delivered some missing windows.

Builder filed suit for amount due pursuant to the contract and the retention of its tools,

and when the Harrisons counterclaimed, Builder filed a third-party complaint against Seller.

The Harrisons filed a cost bond into the court in the amount of $23,423.96, and following a

settlement agreement between Builder and the Harrisons, the money was disbursed among

the parties. In exchange for releasing their claims against Builder, the Harrisons paid Builder

$1,400 and retained the rest of the money, less 5 percent of the earned interest that was given

to the Clerk and Master. The trial regarding the suit between Builder and Seller was held

approximately one year later.

At trial, Jim Richards testified that he was Seller’s divisional sales manager of the

Springfield, Tennessee division until his position was eliminated when David Kurth became

the interim general manager. He said that when Builder began working with Seller, Robert

Nordass was the sales representative that handled Builder’s area. Builder purchased four

units from Seller, including three yard units in Spring 2005. Mr. Richards explained that the

yard units Builder purchased came with an interior trim out because the service made the

purchase of the units more attractive and because the units could not be inspected until the

home was being set. In addition to the interior trim out, Builder requested an exterior trim

out. Mr. Richards’s superior approved the transaction with the additional service.

-4-

Mr. Richards asserted that all of Seller’s homes, including yard units, “were sold with

a one-year warranty against manufacturer’s defects and workmanship and materials” in

addition to a Bonded Builders Warranty, that provided warranty coverage for nine years

starting after the one-year warranty expired. He admitted that Builder’s quick quote sheet

did not mention a manufacturer’s warranty but explained that the warranty “would not have

been something that [he] would have brought up because every home had a warranty on it.”

David Kurth testified that when he arrived at the Springfield plant in February 2005,

he attempted to maintain and build the business but that the plant was ultimately closed in

September. He created the yard inventory release forms and established a practice and

procedure for selling the yard units. He asserted that the forms were created before Builder

bought the yard unit in June 2005 but acknowledged that Builder was not asked to sign a

form until after he had placed his order. When asked why the customer service manual did

not differentiate between yard units and other units, Mr. Kurth opined,

It was the intent of the company to never have a yard unit. If the [company]

procedures had been followed, there would be no yard units. It’s because

procedures were overlooked, because they weren’t followed, because the

people at the Tennessee plant before I got there did not follow procedures, that

we ended up with yard units to begin with. So this entire [manual] was written

under the premise that such a thing did not exist. Unfortunately, it did.

He insisted that the portion of the manual that referred to the one-year warranty only applied

to newly constructed homes and that he did not think there was “anything in th[e] manual that

sp[oke] directly to the sale of existing inventory of previously built homes.”

Relative to the yard inventory release that Builder signed, Mr. Kurth stated that when

Builder did not accept delivery within 45 days of the sale, he had the ability to cancel the

original order and keep the deposit. He conceded that if the units had been delivered within

45 days of the June 2005 order, then they would have been obligated to follow the terms of

that document. He acknowledged that such a provision was not included in the original

contract and that the yard inventory release and a receipt form 3 that he also developed were

the only documents evidencing Seller’s ability to cancel the order and keep the deposit. He

admitted that when he told Builder that he had to sign the yard inventory release or risk

forfeiture of the unit, he knew that the foundation for the unit had already been built.

Mr. Kurth testified that while the Harrisons did not receive the one-year

manufacturer’s warranty, they received a Bonded Builders Warranty, which “was an

3

This new receipt was never given to Builder.

-5-

insurance policy of sorts that was available to provide additional coverage for structural

issues for a period of ten years after a builder had constructed” the home. Regarding the

foundation of the home, Mr. Kurth explained that the foundation was

like a tire for a car . . . that can fit many cars as long as the rim of that

particular car accepted that size tire. The foundation is a foundation. And as

long as what is placed on that foundation fits the size and loading requirements

that the foundation was designed to accommodate, any style of home, if you

will, or any appearance of home could be placed on that foundation.

Regarding the trim out services, he said that an interior trim out could be performed in less

than a day and that an exterior trim out of the particular model at issue could take four days.

Builder testified that he was interested in contracting with Seller because he wanted

to develop a construction training program. He thought entering the modular home business

would allow him to mentor his trainees as they completed specific, “individual tasks”

because the home was already partially constructed by the manufacturer. He chose to

contract with Seller because they offered services like completing the trim outs.

Relative to his agreement with Seller, Builder told Mr. Richards that he thought he

could resell three yards units. Builder asked Mr. Richards if Seller could include the crane

setting and the interior and exterior trim outs because he did not want his trainees to complete

those services. After Builder negotiated for the units, he secured a contract with the

Harrisons and sent Seller a deposit for the units. He asserted that the foundation for the

Harrison home was ready in September.

When Builder contacted Seller to set a delivery date, he was given the yard inventory

release and told that if he did not sign the release, he would not receive the unit. At first, he

made changes to the document and faxed the release back to Seller. He admitted that after

Seller changed a few of the provisions, he signed the revised release but asserted that he had

to sign the release to ensure delivery of the unit. He admitted that he could have cancelled

the contract with the Harrisons but explained that he could not just order another unit because

the plumbing and foundation had already been set for that particular unit and because Seller

was in the process of shutting down the plant. Prior to the delivery of the units, he had a dirt

road built for the trailers to cross a small ravine. When the delivery crew arrived, he was

presented with another document, the waiver of liability form, and told that he had to sign

the document before they would deliver the units.

Builder acknowledged that Seller performed their crane setting obligations but said

that they did not complete the interior and exterior trim out. He claimed that when Seller’s

-6-

crew was raising the roof, they did not “put the proper protection underneath it,” causing

damage to the roof. Also, the crew did not adjust the posts where the house was set, and the

shingles on the roof were damaged. Builder testified that he completed the tasks that Seller

had agreed to complete and that he also had to fix several of Seller’s mistakes. He said that

progress was slow because he did not have a proper crew.

Relative to his indemnity claim, Builder introduced a document, providing that he had

suffered damages in the amount of $140,196.01, including his loss from the settlement

agreement with the Harrisons, the additional work that he had to perform to complete the

construction of the house when Seller refused to perform the trim outs, the reflective salaries

he had to pay his employees to complete the work, and the cost of the repairs that he

performed. He asserted that he also had to pay $2,500 for the crane setting of the modules

and that he never received the rebate that was discussed when he ordered the unit.

Susan McCullough testified that she had worked for Seller as a sales manager and that

Mr. Richards was her supervisor. She asserted that all homes, including yard units, came

with two warranties – a one-year warranty and a warranty that covered years two through ten.

When shown a quote sheet for a yard unit, she acknowledged that the sheet reflected that the

house was sold “as is” but explained that the term meant that builders could not change the

existing cabinetry, floor covering colors, carpet colors, or tub and commode colors.

Likewise, Mr. Lane said that the yard units were sold “as is,” meaning that they would not

change or fix anything, other than to remove mold. However, he insisted that in 2005, the

company no longer offered the trim outs as a service and that the “guys who were on the trim

out crew were moved to other sections.”

Mr. Nordass testified that prior to the time that any of the yard units were sold, Seller

stopped offering the trim outs as a service. He asserted that once a builder placed a deposit

on a yard unit, he or she had 45 days to schedule delivery or the unit became “open” and

could be sold to another builder. He spoke with Builder directly after Builder continued to

suggest that the unit was purchased with an interior and exterior trim out and a warranty. He

insisted that he told Builder that the trim out services were not an option and that the unit

came without a warranty. He opined that Seller had never offered the one-year

manufacturer’s warranty for the yard units. Connie Traughber, Seller’s service manager,

confirmed Mr. Nordass’s testimony regarding the trim out services.

Two well-qualified enigineers, James Quarve and Todd Duncan, testified regarding

their inspection of the Harrison home. Mr. Quarve noticed nail pops, which were caused by

either moisture in the wood or by the setting of the unit as it was picked up and placed on the

foundation. He examined the floor joist that had been split and repaired by placing another

piece of lumber beside the broken joist. He asserted that in addition to the broken floor joist,

-7-

there could have been other damage to the home that occurred when one of the modules

remained attached to the trailer as the crane attempted to lift that module. Mr. Duncan

observed cracks in the walls, nail pops, high spots on the main floor, caused by improper

placement of a post and improper measurement of studs that composed a wall under the

stairs. Mr. Duncan opined that these high spots could cause cracks in the Sheetrock and

could affect the operation of windows and doors. He found that one half of the marriage wall

was unsupported because of the placement of the stud wall.

Mr. Harrison said that Builder’s employees, Bob Campbell and Mr. Campbell’s son,

began construction of the foundation in August 2005 but that Mr. Campbell stopped working

for Builder “not long after the house was set.” He stated that Builder brought other workers

to work on the house once Mr. Campbell quit. He eventually told Builder he thought the

construction was progressing “at a very slow pace.” He thought if Builder had an actual

crew, the house would have been ready within the first projected time frame given the

adequate weather for the first three to four months of construction. Likewise, Mrs. Harrison

asserted that Builder kept changing their move-in date, and when they finally moved in,

Builder was not present and had not finished the items he had promised to finish.

Mr. Harrison asserted that while Seller was responsible for delivering and setting the

modules, Builder was responsible for constructing the foundation, the garage, the breezeway,

the driveway, and the second story of the house. Mr. Harrison found numerous problems

with the house itself, the attic, the garage, and the breezeway. Relative to the problems with

the outside of the house, Mr. Harrison opined that the shingles were broken in certain areas,

that there were two ridge lines that ran across the back of the house, that siding had come off

the house and had not been properly cut, that there were two different colors and textures of

siding on the house, and that the sewer system had not been properly vented through the roof.

Relative to the problems within the house, he testified that there was mold in the master

bedroom, that some of the kitchen cabinets were damaged, that the kitchen window did not

work, that the lights above the kitchen sink were not centered, that insulation had not been

installed in some places and was improperly installed in other places, that panels of

Sheetrock had separated, that numerous nail heads and screws had popped through the

Sheetrock upstairs, that there were stress cracks around all of the windows and doors, and

that the basement leaked. Relative to the problems with the second story, he said that the

upstairs windows did not work, that the plumbing in the upstairs bathroom was faulty and

ultimately ruined the ceiling in the first-floor living area of the house, and that the floor

trusses on the second floor appeared to have protruded through the ceiling of the main living

area. Relative to problems with the garage, he believed that the attic in the garage was not

installed properly, the garage floor was sunk in the middle and cracked all the way around,

and that the back wall in the garage was leaning. When he told Builder about all of these

issues, Builder promised to “deal” with Seller. Mr. Harrison claimed that the majority of his

-8-

problems were with the construction of the site, not the modules and that he did not believe

Seller was really at fault. He said that Builder initially told them that they would receive a

warranty from Seller and that he would also provide a warranty that would “match or exceed”

Seller’s warranty. He said that Builder never told them that they were purchasing the unit

“as is.”

James Deatherage, a partner in the forensic engineering firm of Construction

Engineering Associates, testified that he inspected the modular home built for the Harrisons

and drafted a report detailing the repairs that needed to be made and the cost of the repairs,

totaling $84,061.91. He first visited the home in March 2006 and found “nail pops, water

intrusion areas, framing issues, and foundation issues in the basement area.” He also

inspected the garage, exterior siding, trim, and soffits. He visited the house again in

November 2006 for a subsequent inspection before finalizing his report. His report detailed

repairs needed for the garage and the interior and exterior of the house and the work that had

not been completed by Builder. He believed that the repairs did not relate to the

manufactured portion of the home but that some of the repairs related to the damage that

occurred when the unit turned on its side during delivery. He explained that when the unit

tipped and leaned into the tree and was then subsequently lifted back to its position on the

trailer, the unit underwent residual stresses that caused nail pops and the inoperable windows.

He opined that the subsequent breaking of the lag bolt that attached the second module to the

connectors on the trailer would not have caused any damage, other than the break in the floor

joist in the kitchen area. He doubted that the crane operator would have noticed the event.

On cross-examination, Mr. Deatherage said that the twisting that occurred when the

unit fell into the tree would have been ten times more than the twisting that could have

occurred when the lag bolt was improperly removed. He admitted that improper shingling

of the entire house was not part of the stick built portion but was part of the manufactured

portion of the house. He explained that the damage to the shingles was attributed to the long-

term bending that occurred while the unit sat outside. He stated that the quality of the siding

was “unacceptable from a construction standpoint” and that repairs needed to be made to the

siding and the facia metal. He said that the crown molding and the plumbing in the upstairs

needed to be repaired and that a downstairs column needed to be reinstalled.

Following the conclusion of the trial and the above presented testimony, the trial court

found that Builder had “contracted for and was offered exterior and interior trim out” and

that the unit came with a one-year manufacturer’s warranty, despite Seller’s protests that yard

units did not include such a warranty. The court stated that it did not believe that there was

any distinction, for warranty purposes, between a newly manufactured unit and a yard unit.

The court explained that the yard inventory release form did not remove the warranty because

the form was drafted by Mr. Kurth in the hopes of minimizing Seller’s liability and signed

-9-

after Builder had already bought the unit and because Builder signed the form under duress.

The court found that the problems that occurred during delivery were attributed to Seller and

that the waiver of responsibility form did not remove Seller’s liability. The court awarded

Builder with $45,000, explaining that the amount covered the sum paid to the Harrisons

pursuant to the settlement agreement and Builder’s lost profit from the sale and construction

of the modular home resulting from Seller’s breach of contract. The court then awarded

Builder with $45,000 in attorney fees, reflecting attorney fees accrued in his defense of the

Harrison counterclaim and in his pursuit of the indemnity claim against Seller.

II. ISSUES

We consolidate and restate the issues raised by Seller as follows:

A. Whether the trial court erred in holding that Builder was entitled to

indemnification from Seller.

B. Whether the trial court erred in awarding Builder with attorney fees

pursuant to the contract between Builder and Seller.

III. STANDARD OF REVIEW

On appeal, we review the decision of a trial court sitting without a jury de novo upon

the record, accompanied by a presumption of correctness of the trial court’s findings of fact,

unless the preponderance of the evidence is otherwise. Tenn. R. App. P. 13(d); Bogan v.

Bogan, 60 S.W.3d 721, 727 (Tenn. 2001). A trial court’s conclusions of law are subject to

a de novo review with no presumption of correctness. Blackburn v. Blackburn, 270 S.W.3d

42, 47 (Tenn. 2008); Union Carbide Corp. v. Huddleston, 854 S.W.2d 87, 91 (Tenn. 1993).

Mixed questions of law and fact are reviewed de novo with no presumption of correctness;

however, appellate courts have “great latitude to determine whether findings as to mixed

questions of fact and law made by the trial court are sustained by probative evidence on

appeal.” Aaron v. Aaron, 909 S.W.2d 408, 410 (Tenn. 1995).

IV. DISCUSSION

A.

Seller contends that Builder is not entitled to indemnification because Builder did not

sustain a loss but actually received money as a result of the settlement with the Harrisons.

Seller also asserts that Builder cannot recover from Seller because Builder was at fault for

the problems with the Harrison house, as evidenced by the Harrison complaint. Builder

-10-

responds that he suffered an actual loss through his settlement with the Harrisons because

less the $1400 he received, he did not receive the balance due pursuant to his contract and

because he had to forego recovery of the additional funds he expended, which were in excess

of $100,000. Builder also asserts that his losses were not a result of his own wrongful

conduct because some of the claims raised by the Harrisons resulted from Seller’s

negligence, actions, breach of contract, and breach of warranty as the manufacturer of the

modules.

“The right to indemnity rests upon the principle that everyone is responsible for the

consequences of his own wrong, and, if another person has been compelled to pay the

damages which the wrongdoer should have paid, the latter becomes liable to the former.”

Southern Coal & Coke Co. v. Beech Grove Min. Co., 381 S.W.2d 299, 302 (Tenn. Ct. App.

1963). “Indemnity obligations are either express or implied. Express indemnity obligations

arise from the contracts between the parties, and implied indemnity obligations, whether

called equitable or contractual, are imposed by law without the consent or the agreement of

the parties.” Winter v. Smith, 914 S.W.2d 527, 541-42 (Tenn. Ct. App. 1995).

“Indemnification issues arise frequently in construction litigation.” Id. at 542. Moreover,

“[t]heir impact can be significant because indemnification shifts the entire burden of loss or

responsibility.” Id.

Citing Stiver Mktg., Inc. v. Performance Bus. Forms, Inc., No. 01-A-019108CH00276,

1991 WL 254564, at *4 (Tenn. Ct. App. Dec. 4, 1991), Seller asserts that Builder cannot

recover because he never suffered a loss. While we acknowledge that “[g]enerally, the right

to sue for indemnity for damages resulting from the negligence, misfeasance, or malfeasance

of another accrues only when payment has been legally made by the indemnitee,” we believe

that the loss sustained in this case occurred in the form of the settlement between Builder and

the Harrisons. Id. Indeed, the loss may take the form of “payment, settlement, or through

the injured party’s obtaining an enforceable judgment.” Id.

In this case, Builder sustained a loss in the amount of $22,023.96, reflecting the

amount the Harrisons retained less the amount given to Builder pursuant to the settlement

agreement between Builder and the Harrisons. Additionally, the indemnity provision at issue

here provides, in pertinent part,

Seller will defend, indemnify and hold Builder harmless from and against any

claim by the purchaser or occupant of a home, to the extent such claim is based

on a failure of the home to meet the specifications of the order placed with and

accepted by Seller, and to the extent such claim is based upon an alleged

breach of Seller’s warranty. . . . Each party’s indemnity shall include . . . any

-11-

costs or expenses reasonably incurred to perform the other party’s obligations

if that party fails or refuses to perform them without good cause.

(Emphasis added).

Pursuant to the contract in the form of the order between the parties, Seller agreed to

perform the interior and exterior trim out. Seller refused to perform this service, and Builder

was tasked with performing the service. Builder was also tasked with repairing the damage

resulting from Seller’s delivery of the modules. Indeed, the second module was damaged as

Seller delivered the module to the foundation and as the module was lifted from the trailer.

While testimony at trial indicated that Seller repaired some of the major drywall issues

caused by the delivery and setting of the modules, no testimony was presented that Seller

adequately repaired the damage resulting from its failure to meet the specifications of the

order and its failure to perform pursuant to the one-year manufacturer’s warranty. Like the

trial court, we believe the unit came with a one-year manufacturer’s warranty and that Seller

refused to perform the services implicated by the warranty and the services contracted for in

the order. We also believe that the subsequent attempt by Seller to amend the order by

changing the terms and removing the warranty shortly before the unit was to be delivered was

ineffective and that the waiver of responsibility form that was presented at delivery was also

ineffective. With the above considerations in mind, we conclude that Builder was entitled

to indemnification from Seller and that an award of $45,000 was sufficient and appropriate

to cover the loss sustained by Builder in the settlement agreement with the Harrisons and the

costs and expenses incurred to perform Seller’s obligations after Seller refused to perform

its obligations without good cause.

B.

Seller contends that the contract does not require payment of attorney fees when

Builder was at fault for the problems with the Harrison home. Seller alternatively asserts that

pursuant to the language in the contract, Builder is only entitled to recover attorney fees

relating to his defense of the Harrison counterclaim and is not entitled to recover any attorney

fees relating to his pursuit of the indemnity cause of action. Builder responds that he is

entitled to the amount of attorney fees awarded pursuant to the express provisions of the

contract. Builder alternatively responds that if he is not entitled to the full amount of attorney

fees awarded, he is “clearly” entitled to the attorney fees accrued as a result of his defense

against the Harrison counterclaim.

Tennessee follows the American Rule which provides that “litigants pay their own

attorney’s fees absent a statute or an agreement providing otherwise.” State v. Brown &

Williamson Tobacco Corp., 18 S.W.3d 186, 194 (Tenn. 2000); accord Taylor v. Fezell, 158

-12-

S.W.3d 352, 359 (Tenn. 2005). “Under the American [R]ule, a party in a civil action may

recover attorney fees only if: (1) a contractual or statutory provision creates a right to recover

attorney fees; or (2) some other recognized exception to the American [R]ule applies,

allowing for recovery of such fees in a particular case.” Cracker Barrel Old Country Store,

Inc. v. Epperson, 284 S.W.3d 303, 308 (Tenn. 2009) (citing Taylor, 158 S.W.3d at 359; John

Kohl & Co. v. Dearborn & Ewing, 977 S.W.2d 528, 534 (Tenn. 1998)). “[A]s a general

principle, the American [R]ule reflects the idea that public policy is best served by litigants

bearing their own legal fees regardless of the outcome of the case.” House v. Estate of

Edmondson, 245 S.W.3d 372, 377 (Tenn. 2008).

As relevant to this case, attorney fees “are recoverable under an express indemnity

contract if the language of the agreement is broad enough to cover such expenditures.”

Pullman Standard, Inc. v. Abex Corp., 693 S.W.2d 336, 338 (Tenn. 1985). However,

recovery under an implied indemnity theory also includes attorney fees and “other litigation

costs which have been incurred by the indemnitee in litigation with a third party.” Id. at 338.

This case involved an express indemnity contract that included an attorney fees provision.

Consequently, we must determine whether the provision in the contract was broad enough

to include the trial court’s award of attorney fees. The cardinal rule of contract interpretation

is that the court “must attempt to ascertain and give effect to the intent of the parties.”

Christenberry v. Tipton, 160 S.W.3d 487, 494 (Tenn. 2005). In attempting to ascertain the

intent of the parties, the court must examine the language of the contract, giving each word

its usual, natural, and ordinary meaning. See Wilson v. Moore, 929 S.W.2d 367, 373 (Tenn.

Ct. App. 1996). The “court’s initial task in construing a contract is to determine whether the

language of the contract is ambiguous.” Planters Gin Co. v. Fed. Compress & Warehouse

Co., 78 S.W.3d 885, 889-90 (Tenn. 2002). Where the language of a contract is clear and

unambiguous, its literal meaning controls the outcome of the dispute. Id. at 890.

The provision for attorney fees provides, in pertinent part,

Seller will defend, indemnify and hold Builder harmless from and against any

claim by the purchaser or occupant of a home, to the extent such claim is based

on a failure of the home to meet the specifications of the order placed with and

accepted by Seller, and to the extent such claim is based upon an alleged

breach of Seller’s warranty. . . . Each party’s indemnity shall include

reasonable attorney’s fees to defend against such a claim, and any costs or

expenses reasonably incurred to perform the other party’s obligations if that

party fails or refuses to perform them without good cause.

(Emphasis added). A literal reading of the provision reflects that the parties clearly and

unambiguously contracted for an award of attorney fees accrued as a result of Builder’s

-13-

defense against a third-party claim. Thus, this provision supported an award of attorney fees

accrued as a result of Builder’s defense against the Harrison counterclaim after Seller refused

to perform pursuant to the contract and refused to honor its one-year manufacturer’s

warranty. This provision did not support an award of attorney fees accrued as a result of the

suit between Builder and Seller. While Builder attempts to use the “costs and expenses”

portion of the sentence to argue that he was entitled to attorney fees relating to his suit

against Seller, we do not believe that the clear and unambiguous language of the provision

is broad enough to include an award of attorney fees under those circumstances. The drafter

of the contract clearly separated the award of attorney fees from the award of costs and

expenses incurred to perform the other party’s obligations. Any other reading of the contract

would ignore the literal meaning of the provision. Accordingly, we conclude that Builder’s

award of attorney fees should be reduced to the amount of $18,084, which reflects Builder’s

claim for attorney fees accrued in its defense of the Harrison counterclaim. The judgment

of the trial court should be modified to reflect that amount.

V. CONCLUSION

The judgment of the trial court is affirmed as modified, and the cause is remanded for

such further proceedings as may be necessary. Costs of this appeal are taxed to the appellant,

All American Homes of Tennessee, LLC.

______________________________________

JOHN W. McCLARTY, JUDGE

-14-

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.