“[t]his Court, as well as seven other courts of 25 appeals, has concluded that the automatic stay can operate to prevent an appeal by a debtor when the action or proceeding below 26 was against the debtor”

How later courts described this case

  • “[t]his Court, as well as seven other courts of 25 appeals, has concluded that the automatic stay can operate to prevent an appeal by a debtor when the action or proceeding below 26 was against the debtor”
  • heightened scrutiny for rejection motions involving the 24 protection of national public interest such as public safety, health or welfare (citing In re Old Carco, LLC, 406 B.R. 180, 189 25 (Bankr. S.D.N.Y. 2009
  • stating the debtor must demonstrate that rejection 10 will benefit the estate
  • stating FERC is a creature of statute and only has 23 authority specifically conferred by Congress with no constitutional 24 or common law existence or authority

Written by the judges who cited it.

The opinion

EDWARD J. EMMONS, CLERK of □□ NO

U.S. BANKRUPTCY COURT Ei □□□□

NORTHERN DISTRICT OF CALIFORNIA □□□ a

□□ □□ □□

1 □□□□

Signed and Filed: June 12, 2019 □□□□□□□

2

run, J

Mnf

DENNIS MONTALI

5 U.S. Bankruptcy Judge

6

7 UNITED STATES BANKRUPTCY COURT

8 FOR THE NORTHERN DISTRICT OF CALIFORNIA

9]/In re ) Bankruptcy Case

) No. 19-30088-DM (Lead Case)

10 PG&E CORPORATION; PACIFIC GAS )

AND ELECTRIC COMPANY, ) Chapter 11

11 )

Debtors. ) (Jointly Administered)

12 )

PG&E CORPORATION; PACIFIC GAS ) Adv. Proc. No. 19-03003

13 AND ELECTRIC COMPANY, )

)

14 Plaintiffs, )

)

15|v. )

)

16 || FEDERAL ENERGY REGULATORY )

COMMISSION, )

17 )

Defendant. )

18 )

19 MEMORANDUM REGARDING CERTIFICATION

FOR DIRECT APPEAL TO COURT OF APPEALS

20

21]1. INTRODUCTION

22 This Memorandum Regarding Certification For Direct Appeal To

23||Court Of Appeals is issued concurrently with the court’s

24||Certification For Direct Appeal To Court Of Appeals and is the

||}document required by Fed. R. Bankr. P. 8006(b) and (e)(1).

26 The Amended Declaratory Judgment that is the subject of this

Certification was entered on June 12, 2019 (Dkt. #155). No notice

28 ]/of appeal has been filed yet. This court is the court to make and

- 1 -

1 file the Certification For Direct Appeal. Fed. R. Bankr. P.

2 8006(d).

3 Fed. R. Bankr. P. 8006(e)(1) requires that the court making a

4 certification on its own shall provide in a memorandum accompanying

5 that certification the information required by Fed. R. Bankr. P.

6 8006(f)(2)(A)-(D). That subdivision provides that a request for

7 certification shall include the following:

8 (A) the facts necessary to understand the question presented;

9 (B) the question itself;

10 (C) the relief sought;

11 (D) the reasons why the direct appeal should be allowed,

12 including why a circumstance specified in 28 U.S.C. §

13 158(d)(2)(A)(i)-(iii) applies; and

14 (E) a copy of the judgment, order or decree and any related

15 opinion or memorandum.

16 Attached are copies of the court’s Memorandum Decision On

17 Action For Declaratory And Injunctive Relief (Dkt. #153) filed and

18 entered on June 7, 2019, and the Amended Declaratory Judgment (Dkt.

19 #155), filed and entered on June 12, 2019. The facts necessary to

20 understand the question presented, the question itself, the relief

21 sought, and the reasons why the appeal should be allowed follow.

22 II. FACTS NECESSARY TO UNDERSTAND THE QUESTION PRESENTED

23 On January 29, 2019, PG&E Corporation and its wholly owned

24 subsidiary, Pacific Gas and Electric Company (collectively,

25 “Debtors”) filed voluntary petitions under Chapter 11 of the

26 Bankruptcy Code in this court. They continue as debtors in

27 possession, as no trustees have been appointed. At the time of

28 their filing, their joint cases represented one of the largest

1 bankruptcies in United States history and possibly the largest of a

2 public utility. Their filings appear to have been a result of

3 devastating wildfires in Northern California in 2017 and 2018 that

4 resulted in billions of dollars of claims filed or threatened

5 against them for wrongful death, personal and property damages and

6 numerous other theories of liability. While apparently not a

7 precipitating cause of their bankruptcies, the Debtors have

8 reported in excess of forty-two billion dollars in contractual

9 obligations arising from hundreds of executory contracts to

10 purchase electric power at wholesale from others. These contracts

11 are commonly called Power Purchase Agreements (“PPAs”).

12 California law changed in the fall of 2018 to require

13 companies such as Debtors to give a fifteen-day notice to their

14 creditors prior to filing for bankruptcy relief. They gave that

15 notice on January 14, 2019.

16 On January 18 and 22, 2019, certain counterparties to PPAs

17 commenced two different but similar administrative proceedings

18 before the Federal Energy Regulatory Commission (“FERC”) to deal

19 with the imminent bankruptcy filings by Debtors. In granting their

20 two requests only days later, FERC described their requests as

21 rulings by it that if Debtors file bankruptcy, they “may not

22 abrogate, amend or reject in a bankruptcy proceeding any rates,

23 terms and conditions of its [PPAs]...without first obtaining

24 approval from {FERC}....” NextEra Energy, Inc. v. Pac. Gas and

25 Elec. Co., 166 FERC ¶ 61,049 (2019); Exelon Corp. v. Pac. Gas and

26 Elec. Co., 166 FERC ¶ 61,053 (2019).

27

28

1 On the day they filed bankruptcy, Debtors commenced this

2 adversary proceeding in this court, seeking preliminary injunctive

3 relief. They also sought a declaratory judgment as to their right

4 to reject executory PPA contracts subject to this court’s

5 authority, but not FERC’s. They petitioned FERC on February 25,

6 2019, for rehearing of its two January decisions. On May 1, 2019,

7 FERC denied rehearing. NextEra Energy, Inc. v. Pac. Gas and Elec.

8 Co., 167 FERC ¶ 61,096 (2019).

9 In denying rehearing, FERC ruled that it had “concurrent

10 jurisdiction” with this court and that its approval would be

11 required before either Debtor could reject a PPA as an executory

12 contract.

13 III. QUESTION PRESENTED

14 Does 11 U.S.C. § 365(a) (“Section 365") give the bankruptcy

15 court sole and exclusive authority to grant or deny motions to

16 reject (or assume) executory contracts involving wholesale power

17 contracts such as PPAs, or does FERC have concurrent jurisdiction

18 over such motions such that its approval is also required.

19 IV. RELIEF SOUGHT

20 Debtors sought and received, and FERC and certain PPAs

21 opposed, a declaration by this court that it had sole and exclusive

22 jurisdiction under 28 U.S.C. § 1334(a) and its authority under

23 Section 365 to grant or deny any motions described above. The

24 court assumes that on appeal Debtors will ask for that decision to

25 be affirmed; FERC and the PPAs will be expected to seek reversal.

26 V. REASONS WHY DIRECT APPEAL SHOULD BE ALLOWED

27 In certifying a direct appeal on its own motion, this court is

28 directed to state whether any of the circumstances set forth in

1 subsections (i), (ii), or (iii) of 28 U.S.C. § 158(d)(2)(A) exist.

2 See 28 U.S.C. § 158(d)(2)(B). This court believes all three exist.

3 (i) The judgment involves a question of law as to

which there is no controlling decision of this

4 circuit or of the Supreme Court of the United

States, or involves a matter of public importance.

5

6 The central issue of whether a bankruptcy court alone may

7 grant or deny a motion to reject a PPA as an executory contract, or

8 whether FERC has a say in the question by virtue of its claimed

9 “exclusive jurisdiction,” has not been addressed by any reported

10 Ninth Circuit decision or by the United States Supreme Court. It

11 is very much a matter of public importance. Also of great

12 importance, though not directly related to the rejection issue, are

13 billions of dollars in claims arising from the tragic wildfires

14 that occurred principally in 2017 and 2018 in Northern California

15 for which Debtors bear substantial liability. In some cases that

16 liability is a result of their direct actions and in others because

17 of their strict liability under California’s inverse condemnation

18 laws. These wildfires are the principal publically stated reasons

19 why the Debtors filed bankruptcy.

20 Debtors report that over forty-two billion dollars of

21 wholesale power contracts, via approximately four hundred separate

22 contracts, exist. It is likely that in apparently the largest

23 public utility bankruptcy ever, rejection of contracts of this

24 nature are expected. Rejection will give rise to substantial

25 damage claims because rejection constitutes a breach under current

26 bankruptcy law. How those damage claims will be treated under any

27 Chapter 11 reorganization plan will inevitably be interrelated with

28 how the wildfire related claims will be treated. On top of that

1 are the complications brought by the presence of billions of

2 dollars more of contractual liabilities that Debtors must deal with

3 in their bankruptcies.

4 If FERC has a say in the rejection decision because its

5 authority is upheld as “concurrent” with this court’s, an extremely

6 complicated situation will be rendered all the more complicated and

7 time-consuming, possibly delaying further the ultimate resolution,

8 settlement and payment of those wildfire and contractual claims.

9 (ii) The judgment involves a question of law requiring a

resolution of conflicting decisions.

10

11 There are only three other decisions this court believes have

12 dealt directly with the clash between FERC and the bankruptcy court

13 over this jurisdiction struggle. This court’s recent decision is

14 the only one where the court was presented with pre-bankruptcy FERC

15 decisions that purported to apply to bankruptcies even before they

16 were filed. Once filed, of course, the FERC decisions described

17 above become concrete and actual realities confronting Debtors as

18 they attempt to reorganize.

19 The three reported cases that are similar, and in one case

20 directly in conflict are:

21 In the matter of Mirant Corp., 378 F.3d 511 (5th Cir. 2004);

22 In re Calpine Corp., 337 B.R. 27 (S.D.N.Y. 2006); and In re

23 FirstEnergy Solutions Corp. v. FERC, 2018 WL 2315916 (Bankr. N.D.

24 Ohio May 18, 2018), which is scheduled for oral argument in the

25 Sixth Circuit on June 26, 2019 (Case. No. 18-3788).

26 (iii) Immediate appeal of the judgment may advance the

progress of these cases or proceedings in which the

27 appeal is taken.

28

1 The complexity of these reorganization cases and the vast

2 number of victims of massive torts and the vast number of

3 involuntary and voluntary creditors of other types, including

4 potential claims arising from PPA rejections, and the intense

5 public pressure for a speedy end to these costly bankruptcies, cry

6 out for expeditious resolution of different and substantial legal

7 claims such as these. There are so many “moving parts” in these

8 cases involving political, financial, social and legal problems,

9 that every one of them that can be addressed promptly should be

10 addressed. Debtors and their advisors need to know whether they

11 can utilize the tool of rejection that Congress gave them, subject

12 only to this court’s approval. If FERC’s approval will also be

13 necessary to facilitate their reorganization efforts, they need to

14 know sooner rather than later. The court is encouraged to help

15 with these complex challenges by expediting the appeal of this very

16 critical question.

17 ***END OF MEMORANDUM REGARDING CERTIFICATION

FOR DIRECT APPEAL TO COURT OF APPEALS***

18

19

20

21

22

23

24

25

26

27

28

EDWARD J. EMMONS, CLERK of □□ NO

U.S. BANKRUPTCY COURT Sf □□□□

NORTHERN DISTRICT OF CALIFORNIA 5 te □□□ a

ye 75

1 Qs

Signed and Filed: June 7, 2019 □□□□□□□

2

Mw,

Lp Mnfteke

DENNIS MONTALI

5 U.S. Bankruptcy Judge

6

UNITED STATES BANKRUPTCY COURT

7

NORTHERN DISTRICT OF CALIFORNIA

8

SAN FRANCISCO DIVISION

9

In re ) Bankruptcy Case

10 ) No. 19-30088-DM (Lead Case)

PG&E CORPORATION; PACIFIC GAS )

11] AND ELECTRIC COMPANY, ) Chapter 11

)

12 Debtors. ) (Jointly Administered)

a)

13 || PG&E CORPORATION; PACIFIC GAS ) Adv. Proc. No. 19-03003

AND ELECTRIC COMPANY, )

14 )

Plaintiffs, )

15 )

Vv. )

16 )

FEDERAL ENERGY REGULATORY )

17 || COMMISSION, )

)

18 Defendant. )

a)

19

20 || MEMORANDUM DECISION ON ACTION FOR DECLARATORY AND INJUNCTIVE RELIEI

21]1. INTRODUCTION

22 In its May 1, 2019, Order Denying Rehearing (“the FERC

23 ||/Denial”, the Federal Energy Regulatory Commission (“FERC”) made twe

24|/remarkable statements. First, it said:

25 ‘Wholesale power contracts are not simple run-of-the-mill

contracts between two private parties, rather, these

26 contracts, while privately negotiated, implicate the

public’s interest in the orderly production of plentiful

27 supplies of electricity at just and reasonable rates

28

-1-

1 NextEra Energy, Inc. V. Pac. Gas and Elec. Co., 167 FERC ¶ 61,096

2 (2019) at Para 13.

3 Second, it stated:

4 “To be clear, the [FERC] neither presumes to sit in

judgment of rejection motions nor seeks to arrogate the

5 role of adjudicating bankruptcy proceedings”.

6 Id. at Para. 16.

7 The problem is that the first statement, while true, is

8 completely contrary to the congressionally created authority of the

9 bankruptcy court to approve rejection of nearly every kind of

10 executory contract. This includes “run-of-the-mill” types,

11 whatever that means, or the other kind, including power purchase

12 agreements and others that implicate the public’s interest, but

13 excluding certain types not relevant here.

14 The second problem is that FERC, despite its denial, has

15 chosen to interfere with bankruptcy courts’ decisions. Without

16 statutory or supreme court authority to support its position, it in

17 fact “presumes to sit in judgment” and second-guess - no overrule -

18 decisions of the bankruptcy court.

19 To deal with what it correctly identifies as unsettled law

20 with different court interpretations (one circuit court, one

21 district court and one bankruptcy court now on direct appeal to

22 another circuit court)1 FERC purports to settle the law by

23 announcing its own interpretation of bankruptcy law and decree

24 something found nowhere in the statute it interprets. This is not

25 the way that unsettled law is to be developed. That is the role of

26

27 1 See In the matter of Mirant Corp., 378 F.3d 511 (5th Cir.

2004) (“Mirant”); In re Calpine Corp., 337 B.R. 27 (S.D.N.Y. 2006)

28 (“Calpine”); In re FirstEnergy Solutions Corp. v. FERC, 2018 WL

2315916 (Bankr. N.D. Ohio May 18, 2018) (“FirstEnergy”).

1 the courts.

2 To this court, FERC’s decision was not only unauthorized, but

3 has and continues to have the effect of undermining the function of

4 the bankruptcy court in its role of ensuring that the goals and

5 purposes of bankruptcy law and policy are properly served and

6 properly executed. Despite FERC’s lip service to what it describes

7 as “concurrent jurisdiction” to carry out differing and perhaps

8 competing policies, the effect of its decision guts and renders

9 meaningless the bankruptcy court’s responsibilities in this area of

10 the law.

11 For this reason, FERC must be stopped and the division and

12 balance of power and authority of the two branches of government

13 restored. Accordingly, and for the reasons that follow, the court

14 declares FERC’s decision announcing its concurrent jurisdiction

15 unenforceable in bankruptcy and of no force and effect on the

16 parties before it. If necessary in the future it will enjoin FERC

17 from perpetuating its attempt to exercise power it wholly lacks.

18

19 II. PROCEDURAL BACKGROUND

20 On April 10, 2019, the court held a hearing on Pacific Gas and

21 Electric Company and PG&E Corporation’s (collectively, “Debtors”)

22 Motion For Preliminary Injunction (the “Motion”).2 Debtors were

23 initially seeking a preliminary injunction to prevent FERC from

24 issuing any rulings that would impact rejection of a power purchase

25

26

27

28 2 See, Debtors’ Complaint For Declaratory Judgment And

Preliminary And Permanent Injunctive Relief (“Complaint”), Dkt. #1.

1 agreement (“PPA”) under Section 365 of the Bankruptcy Code3

2 (“Section 365") and to establish that the bankruptcy court has sole

3 authority over Debtors’ rights to reject any of its PPAs.

4

5 III. PREPETITION EVENTS

6 Debtors announced their intent to file for bankruptcy

7 protection on January 14, 2019. California law mandated a 15-day

8 notice period before filing.4 Various PPA Counterparties5 initiated

9 two administrative actions before FERC against Debtors. They were

10 concerned that Debtors would try to reject PPAs in their

11 forthcoming bankruptcy. As a result, they asked FERC to rule that

12 the bankruptcy court and FERC both must approve rejection of a PPA

13 for rejection to have effect. Promptly thereafter, on January 25

14 and 28, 2019, FERC ruled “that this Commission and the bankruptcy

15 courts have concurrent jurisdiction to review and address the

16 disposition of wholesale power contracts sought to be rejected

17 through bankruptcy.” NextEra Energy, Inc. V. Pac. Gas and Elec.

18 Co., 166 FERC ¶ 61,049 (2019); Exelon Corp. V. Pac. Gas and Elec.

19 Co., 166 FERC ¶ 61,053 (2019) (emphasis added).

20 Debtors had unsuccessfully opposed those attempts and promptly

21 sought relief in this adversary proceeding on the first day they

22 filed for bankruptcy, January 29, 2019.

23 Debtors listed three causes of action in the Complaint: (1)

24

3 Unless otherwise indicated, all chapter, section and rule

25 references are to the Bankruptcy Code, 11 U.S.C. §§ 101-1532, and

to the Federal Rules of Bankruptcy Procedure, Rules 1001-9037.

26

4 Cal. Pub. Util. Code § 854.2.

27

5 For simplicity the court uses this term to describe those

28

entities who proceeded before FERC in January 2019, and those who

later intervened in this adversary proceeding.

1 declaratory relief confirming the bankruptcy court’s exclusive

2 jurisdiction under Section 365; (2) enforcement of the automatic

3 stay under section 362; and (3) a preliminary and permanent

4 injunction under section 105. The second cause of action sought an

5 order stating that FERC could not proceed with any action against

6 Debtors because the automatic stay was in place. The third cause

7 of action, in case the court found the automatic stay did not

8 apply, was for injunctive relief to ensure that FERC would not take

9 any action that would harm Debtors’ rights to reject any of the

10 PPAs.

11

12 IV. POST-PETITION EVENTS

13 On February 25, 2019, Debtors sought rehearing of the two FERC

14 orders. FERC consolidated the requests for rehearing into one final

15 decision and denied the rehearings on May 1, 2019 in the FERC

16 Denial.

17 FERC and several PPA Counterparties moved to withdraw the

18 reference from this court to the district court under 28 U.S.C. §

19 157(d); Debtors opposed the motions. On March 11, 2019, the

20 district court denied the motions to withdraw the reference,

21 ruling this was a core proceeding.6 No party appealed.

22 During the April 10 hearing, the court asked why it could not

23 decide all of the issues presented by the adversary proceeding,

24 particularly because there did not appear to be any material facts

25 in dispute. Promptly after the FERC Denial, the parties filed a

26 stipulation regarding the disposition of this adversary proceeding

27

28 6 See Order Denying the Motions to Withdraw the Reference.

Dkt. #135 at 4.

1 (“the May 3 Stipulation”) (Dkt. No. 149). The May 3 Stipulation

2 stated that the parties were unable to reach agreement on terms of

3 a final judgment and that the court could enter final judgment

4 based upon the current record without any further briefing, oral

5 argument, or other evidence, except for the FERC Denial. This

6 allows this court to enter final judgment at this point.

7 On May 20, 2019, the United States Supreme Court decided

8 Mission Product Holdings, Inc. v. Tempnology, LLC, 587 U.S. ___

9 (2019) (“Tempnology”). The court preserved the right of a

10 trademark licensee to retain the use of the trademark following the

11 licensor’s rejection of the trademark license as an executory

12 contract. The court repeatedly stated basic principles relevant to

13 this case:

14 “Section 365 provides that ‘a debtor’s rejection of

a contract “constitutes a breach of such contract.’”

15

Slip opn,. P.1.

16

“Rejection of a contract--any contract--in bankruptcy

17 operates not as a rescission but as a breach.”

18 Id., at 8.

19 “Rejection ‘constitutes a breach of [an executory]

contract,’ deemed to occur ‘immediately before the date of

20 the filing of the petition’ ... Or said more pithily for

current purposes, a rejection is a breach.’”

21

Id.

22

“Sections 365(a) and (g) speak broadly, to ‘any

23 executory contract[s].’”

24 Id., at 10.

25 The Bankruptcy Code includes several specific provisions

26 important in Chapter 11 reorganization cases where Congress altered

27 those principles in some way. Relevant to Tempnology are

28 intellectual property rights under Section 365(n). Other such

1 provisions are found in Section 365(h)and (i)(purchasers and lessees

2 of real property and timeshare interests). And the trustee is

3 deemed to have assumed (not rejected) obligations for maintenance of

4 capital requirements of a Federal insured depository. Section

5 365(o).

6 Outside of Section 365, rejection of collective bargaining

7 agreements are dealt with great particularity in Section 1113.7

8 From this it is clear that Congress know how to craft special

9 rules for special circumstances.8 Similarly, debtors such as

10 Debtors who are regulated by commissions or other authorities such

11 as FERC must comply with rate change approvals in order to achieve

12 confirmation of Chapter 11 plans. 11. U.S.C. § 1129(a)(6).

13 Tempnology, at a granular level, is about the rights of parties

14 to a trademark license rejected in bankruptcy.9 But on a macro

15 level, it says much about policy decisions that influence the

16 outcome here. Consider the following messages from the opinion:

17 “Today we hold that both Section 365's text and

fundamental principles of bankruptcy law command the

18 ...rejection as breach approach.”

19 Slip opn, p. 8 (emphasis added).

20

21

22 7 There is also specific attention to the duties of a trustee

23 in Chapter 7 found in Sections 765 and 766 not relevant here.

24

8 See Tempnology, at Slip opn. P. 12; and Mirant at 521:

“Section 365, along with other Bankruptcy Code sections, details a

25 number of specific limitations on and exception to the § 365(a)

general rejection authority . . . .”

26 9 The decision aligns the rights of a counterparty to a

27 rejected trademark license to the rights of similarly situtated

parties to copyright and patent licenses, etc. Upon rejection -

28 breach - they retain the option of keeping the entitlements that

they bargained for, viz., the continued use of the intellectual

property licensed to them.

1 And referring in contrast to a trustee’s avoidance powers that

2 can be invoked in only narrow circumstances, the court added:

3 “...unlike the power of rejection, which may be exercised

for any plausible reason.”

4

Id. (emphasis added).

5

The opinion describes in detail the exceptions (referred to in

6

Mirant) added to Section 365 over several decades to address what

7

and how Congress dealt with specific problems that arose for various

8

reasons, including judicial interpretations. That includes the 1988

9

amendments to deal with Lubrizol Enterprises v. Richmond Metal

10

Finishers, 756 F.2d 1043 (4th Cir. 1985)) and protect the rights of

11

some, but not all counterparties to rejected intellectual property

12

licenses. All of them deal with various remedies to protect

13

counterparties’ rights. Nothing in the opinion has any bearing on

14

what FERC seeks in these bankruptcy cases, with one exception. That

15

is, as the supreme court pointed out:

16

“...Section 365 does not grant the debtor an exception

17 from all of the burdens that generally applicable law – whether

involving contracts of trademarks – impose on property owners.

18 See 28 U.S.C. § 959(b)(requiring a trustee to manage the estate

in accordance with applicable law).”

19

Slip opn, at 16.

20

21 V. DISCUSSION

22 What remains following the May 3, 2019 Stipulation is Debtors’

23 request for a declaratory judgment pursuant to 28 U.S.C. § 2201

24 confirming the court’s exclusive jurisdiction over their right to

25 reject any PPA under Section 365, and further declaring that FERC

26 does not have “concurrent jurisdiction” to grant or deny Debtors’

27 rejection of any of their PPAs.

28 The enforcement of the automatic stay (Complaint, Court Two) is

1 not an issue because there has been no violation of the stay. The

2 two FERC orders that prompted this adversary proceeding were in

3 response to proceedings brought against Debtors prior to

4 bankruptcy.10 Debtors have not filed a single motion to reject, so

5 there is no reason to imagine why FERC would take any action.

6 This is a matter of first impression: Is an order issued by a

7 Federal agency purporting to affect (arrogate) a decision by a

8 bankruptcy court in a future bankruptcy case binding on that

9 bankruptcy court or the parties before it?

10 Here are the different ways courts have dealt with this issue

11 in the only reported decisions. None began with FERC issuing orders

12 before the bankruptcy cases were filed as it did here. In Mirant,

13 the court of appeals adhered to the theory the court applies here.

14 Instead of applying the “business judgment” test, the court

15 remanded, stating:

16 “Therefore, upon remand, the district court should

consider applying a more rigorous standard to the

17 rejection of the [subject contract]. If the district

court decides that a more rigorous standard is

18 required, then it might adopt a standard by which it

would authorize rejection of an executory power

19 contract only if the debtor can show that it "burdens

the estate, [] that, after careful scrutiny, the

20 equities balance in favor of rejecting" that power

21

22 10 The Debtors sought rehearing by FERC after bankruptcy but

without seeking relief from the automatic stay in this court. FERC

23 did not mention that in the FERC Denial nor have the parties done

so here. The court expresses no opinion whether such relief should

24 have been requested. See Parker v. Bain, 68 F.3d 1131, 1135-36 (9th

Cir. 1995) (“[t]his Court, as well as seven other courts of

25 appeals, has concluded that the automatic stay can operate to

prevent an appeal by a debtor when the action or proceeding below

26 was against the debtor”); Ingersoll-Rand Fin. Corp. v. Miller

Mining Co., Inc. 817 F.2d 1424, 1426 (9th Cir. 1987)(“section 362

27 should be read to stay all appeals in proceedings that were

originally brought against the debtor, regardless of whether the

28 debtor is the appellant or appellee”).

1 contract, and that rejection of the contract would

further the Chapter 11 goal of permitting the

2 successful rehabilitation of debtors.”

3

Mirant, 378 F.3d at 525 (emphasis added).11

4

The district court in Calpine accepted the argument advanced by

5

FERC here. One day before Calpine’s bankruptcy, PPA counterparties

6

(including Pacific Gas and Electric Company) commenced a proceeding

7

before FERC to obtain an order requiring Calpine to continue to

8

perform under PPAs. The district court, after several interim

9

steps, concluded that it lacked subject matter jurisdiction over the

10

motions to reject the energy contracts before it. Calpine at 39.

11

Finally, the FirstEnergy court ruled as follows:

12

“This Court holds that rejection, including the

13 attendant cessation of performance, does not intrude

on FERC's jurisdiction over filed rates. If

14 Plaintiffs were solvent and simply stopped making

payments ... the counterparties could not reasonably

15 argue that [the debtors] had somehow modified or

abrogated those agreements; they would seek damages

16 for the breaches of those contracts .... Those

breaches would lead to claims. If the Plaintiffs then

17 filed bankruptcy, the claims would become claims

against the estate. Treatment of those claims are

18 governed by the Bankruptcy Code, including the

confirmation of a reorganization plan in ....”

19

In re FirstEnergy Solutions Corp. (Bankr. N.D. Ohio, May 18, 2018,

20

No. 18-50757) 2018 WL 2315916, at *17.12

21

FirstEnergy discusses at length the applicability, vel non, of

22

the police power exception of Section 362(b)(4) and the merits of a

23

request for injunctive relief. While this court agrees generally

24

25

11 This court believes that this test is subsumed within the

26 good faith and business judgment tests that are implicit in

rejection decisions, as in Part G, 3.

27

12 Before long the Sixth Circuit is expected to weigh in, as

28 the appeal is scheduled for oral argument there on June 26, 2019

(Case. No. 18-3788).

1 with its analysis of the court’s exclusive jurisdiction to apply

2 Section 365 without any concurrent involvement by FERC, the decision

3 here in Count One is dispositive, an option not presented to that

4 court.

5 This “unsettled” law should develop this way, through judicial

6 analysis and decision, and not by fiat or decree as FERC has

7 attempted in this case.13

8 A. Case and Controversy; Standing

9 FERC and the PPA Counterparties question whether there is a

10 pending case or controversy and question Debtors’ standing. They

11 ask that this adversary proceeding be dismissed.

12 To establish standing, a plaintiff must establish injury,

13 causation and redressability. Injury requires a plaintiff to show

14 that it

15 “Has sustained or is immediately in danger of

sustaining some direct injury as the result of the

16 challenged official conduct and the injury or threat

of injury must be both real and immediate, not

17 conjectural or hypothetical.”

18 City of Los Angeles v. Lyons, 461 U.S. 95, 101-02 (1983).

19 The United States Supreme Court has ruled that “where

20 threatened action by government is concerned, we do not require a

21 plaintiff to expose himself to liability before bringing suit to

22 challenge the basis for the threat.” MedImmune, Inc. v. Genentech,

23 Inc., 549 U.S. 118, 128-29 (2007) (emphasis in original).

24 The PPA Counterparties rushed to FERC and instituted an

25

26 13 In re Boston Generating, LLC 2010 WL 4616243 (S.D.N.Y. 2010)

is not on this short list because it was disposed of by consent of

27 the parties. Nor is NRG Power Marketing v. Blumenthal (In re NRG

Energy, Inc.), WL 21507685, (S.D.N.Y., 2003) that involved a race-

28 for-jurisdiction dispute where FERC obtained an order for

performance of a contract while a motion to reject was pending.

1 expedited proceeding before Debtors were able to file bankruptcy.

2 It was they, not Debtors, who initiated the controversy, and FERC’s

3 disposition, that has caused Debtors to need this declaratory

4 relief.

5 Here, there is a threatened injury that is certainly impending.

6 While it is true that Debtors have not yet moved to reject any PPAs,

7 they have been under pressure from various sources to move these

8 complex cases along and deal with billions of dollars of wildfire

9 claims and billions of dollars of contractual liabilities. Already

10 the court has granted in part but denied in part their request to

11 extend plan exclusivity under Section 1121(d). This has been with

12 opposition from the two official creditors’ committees and the

13 Governor of California pressing for a prompt and viable

14 reorganization. If and when either Debtor moves to reject any PPAs

15 they need to know promptly whether this court will grant or deny

16 such requests. If they are forced to seek a second and possibly

17 dispositive decision from FERC based on FERC’s stated policy goals,

18 and not just those found in the Bankruptcy Code, there could be a

19 real and significant impact on the reorganization effort and the

20 millions of Northen Californians adversely affected by it. Under

21 these circumstances there can be no doubt that Debtors have standing

22 right now to invoke this court’s authority and jurisdiction to

23 facilitate these reorganization efforts.

24 If FERC’s view prevails, it could effectively veto the court’s

25 decision to permit rejection under the business judgment test.

26 Instead, it would permit rejection only if the affected rate is no

27 longer just and reasonable and as long as the abrogation or

28 modification is necessary to protect the public

1 interest.14 This means a PPA Counterparty who is unable to persuade

2 the bankruptcy court to deny rejection, but able to persuade FERC to

3 do so, will be left with its “bankruptcy-rejected” contact (treated

4 as breached, resulting in a pre-petition claim) in place, fully

5 enforceable, the same as an assumed executory contract. In other

6 words, the reorganization goals will be replaced by FERC’s public

7 policy goals, giving the PPA Counterparty the same treatment as

8 post-petition administrative claim to be paid in full. This is a

9 quintessential controversy - the clash of two competing policies and

10 goals.

11 Ripeness is determined at the time the complaint is filed.

12 Sierra Club v. Dombeck, 161 F. Supp. 2d 1052, 1061 (D. Ariz. (2001),

13 dismissed, 55 F. App’x 411 (9th Cir. 2002). Ripeness has a

14 constitutional and prudential component. “The constitutional

15 ripeness of a declaratory judgment action depends upon whether the

16 facts alleged . . . show that there is a substantial controversy,

17 between parties having adverse legal interest, of sufficient

18 immediacy . . . warrant the issuance of a declaratory judgment.”

19 United States v. Braren, 338 F.3d 971, 975 (9th Cir. 2003).

20 Prudential ripeness requires the fitness of issues for judicial

21 decision and the hardship to the parties if the court withholds

22 consideration. Braren, 338 F.3d at 975.

23 Here, constitutional ripeness is met because there is a

24 substantial controversy between FERC and Debtors. The parties have

25 adverse legal interests that are immediate because Debtors cannot

26 proceed with rejecting contracts subject to this court’s

27

28

14 FERC Denial, Para. 13.

1 authorization under the cloud of FERC’s adverse position.

2 Accordingly, constitutional ripeness is met.

3 The first element of prudential ripeness requires the claim to

4 be primarily legal and does not require any further factual

5 development. Braren, 338 F.3d at 975. Here, the concurrent

6 jurisdiction issue with FERC needs no factual determination or

7 development. The second element of prudential ripeness focuses on

8 the hardship to the parties. Debtors face an immediate hardship

9 for the reasons stated above.

10 The requirements for prudential ripeness are met. As a result,

11 FERC’s and the PPA Counterparties’ arguments involving ripeness lack

12 merit and must fail.

13 B. Sovereign Immunity

14 FERC contends that the United States has not waived sovereign

15 immunity so the adversary proceeding should be dismissed. However,

16 Section 106(a) abrogates sovereign immunity for governmental

17 entities under several sections of the Bankruptcy Code. In re DBSI,

18 Inc., 869 F.3d 1004, 1013 (9th Cir. 2017). Section 365 is one of

19 the enumerated sections. FERC’s sovereign immunity argument lacks

20 merit.

21 C. Non-Consent to Final Judgment

22 FERC and the PPA Counterparties both declined to consent to

23 final judgment in this adversary proceeding in their respective

24 oppositions to the motion for preliminary injunction. Bankruptcy

25 courts may enter appropriate orders and judgments in core

26 proceedings. In non-core proceedings, a bankruptcy court must only

27 submit proposed findings of fact and conclusions of law to the

28 district court for de novo review. Fed. R. Bankr. P. 9033.

1 Here, the focus of the adversary proceeding is on Section 365.

2 Motions to reject are core proceedings under 28 U.S.C. §

3 157(b)(2)(A). In re Turbowind, Inc., 42 B.R. 579, 583 (Bankr. S.D.

4 Cal. 1984). The district court has ruled so here. See, also, the

5 May 1 Stipulation. This court can and will issue a final judgment

6 regardless of FERC’s and the PPA Counterparties’ non-consent.

7 For the same reason, the court will deny the PPA

8 Counterparties’ request for abstention under In re Tucson Estates,

9 912 F. 2d 1162 (9th Cir. 1990).

10 D. Judicial Estoppel

11 FERC asserts that judicial estoppel prevents the Debtors from

12 arguing that this court has exclusive jurisdiction over motions to

13 reject due to a prior case where they made arguments to the

14 contrary. The purpose of the doctrine is to protect the integrity

15 of the judicial process. The doctrine is invoked when a party makes

16 a representation to a court, that court accepts it, rules in the

17 party’s favor, and then the party makes a contrary argument on that

18 same position to the same court or a different court.

19 First, a party’s later position must be clearly

inconsistent with its earlier position. Second, courts

20 regularly inquire whether the party has succeeded in

persuading a court to accept that party’s earlier

21 position, so that judicial acceptance of an inconsistent

position in a later proceeding would create the perception

22 that either the first or the second court was misled. A

third consideration is whether the part seeking to assert

23 an inconsistent position would derive an unfair advantage

or impose an unfair detriment on the opposing party if not

24 estopped.

25 Ah Quin v. Cty. of Kauai Dep’t of Transp. 733 F.3d 267, 270 (9th

26 Cir. 2013) (supporting citations omitted).

27

FERC argues this occurred in In re Calpine Corp. Case N. 05-

28

10861, Dkt. #15 (S.D.N.Y. Jan. 19, 2006). While this may be so,

1 judicial estoppel may not be invoked where jurisdiction is at issue.

2 Many courts have found that where a party is arguing contrary

3 positions on subject matter jurisdiction, judicial estoppel will not

4 be applicable. Bonzel v. Pfizer, Inc., 439 F.3d 1358, 1363

5 (Fed.Cir.2006); E-Pass Techs. v. Moses & Singer, LLP, 2011 WL

6 5357912, at *7 (N.D. Cal. Nov. 4, 2011). In Bonzel, the plaintiff

7 had previously successfully argued for remand before the Federal

8 Circuit because there was no substantial patent law question. Then,

9 after that action was dismissed, the plaintiff brought another

10 lawsuit claiming federal patent jurisdiction. The court declined to

11 apply judicial estoppel and noted “it was questionable whether

12 estoppel could even apply to jurisdictional question.” E-Pass

13 Techs, 2011 WL 5357912 at *7-8 (citing Bonzel, 439 F.3d at 1363).

14 Here, Debtors’ assertion of different positions does not

15 warrant the application of judicial estoppel. The primary focus of

16 this lawsuit is this court’s exclusive jurisdiction under 28 U.S.C.

17 § 1334(a) and whether it alone or FERC concurrently has authority

18 under Section 365. This is the first and only time the Debtors have

19 been forced to defend the authority of their “home” court. No such

20 issue has confronted them before.

21 More importantly, Debtors are now debtors-in-possession under

22 the Bankruptcy Code. Accordingly, they are given substantial

23 rights, duties and powers under numerous sections, including

24 Sections 1107 that import the duties of a trustee in Section 1106.

25 It is a fundamental principle of bankruptcy law that a Chapter 11

26 trustee or debtor-n-possession is considered a new legal entity and

27 as such, has the power to assume or reject most executory contracts

28 under Section 365. It would be inconsistent to this grant of power

1 to inhibit the authority and powers of Debtors because of conduct

2 they took in their individual capacities in which they acted as

3 counterparties to a bankruptcy debtor who was acting adverse to them

4 prior to their bankruptcy cases.

5 In addition, while FERC is not bound by the principle of

6 judicial estoppel, it has reversed its own position on the issue of

7 concurrent jurisdiction. In 2006, FERC announced it would follow

8 the Fifth Circuit in Mirant, which stated that a debtor can reject a

9 PPA that is filed with FERC, without concurrent approval of the

10 rejection by FERC. However, the FERC Denial states that after the

11 Calpine court ruled contrary to Mirant, FERC was no longer obligated

12 to follow the prior reasoning.15

13 Accordingly, it is only fair to let Debtors, as Debtors-in-

14 Possession, use all the tools Congress has provided which they did

15 not have prior to their bankruptcy. Judicial estoppel does not

16 prevent the court from deciding the merits of the case.

17 E. Automatic Stay

18 In the Complaint, Debtors are seeking an order “pursuant to

19 section 362 of the Bankruptcy Code . . . enforcing the automatic

20 stay as to any FERC Action.”

21 The automatic stay went into effect on the day of the

22 bankruptcy. Debtors petitioned for rehearing after bankruptcy and

23 FERC responded with the FERC Denial. The central issue addressed by

24 FERC in denying rehearing is the same that was decided in the two

25 January, 2019, rulings. No party raised the issue of the automatic

26 stay (see footnote 10) so the court does not infer that the stay was

27

28 15 California Electricity Oversight Board v. Calpine Energy

Services, L.P. (CEOB), 114 FERC ¶ 61,003 at ¶ 11.

1 violated or the FERC Denial is void. Nothing else has been brought

2 to the court’s attention to show the stay has been violated by any

3 party. If a violation of the stay does occur in the future, either

4 Debtor may move for contempt under Rule 9020. As the automatic stay

5 is already in place, no further order is necessary. Because the

6 court is granting Debtors’ request for a Declaratory Judgment

7 (discussed, infra) there is no need to debate and decide whether or

8 nor FERC could act within any Section 362(b)(4) exception. Count

9 Two of the Complaint will be DISMISSED.

10 F. There Is No Need for an Injunction under Section 105(a)

11 A party seeking a preliminary injunction under § 105(a) must

12 show:

13 (1) a strong likelihood of success on the merits, (2) the

possibility of irreparable injury to plaintiff if

14 preliminary relief is not granted, (3) a balance of

hardships favoring the plaintiff, and (4) advancement of

15 the public interest (in certain cases). Alternatively, a

court may grant the injunction if the plaintiff

16 demonstrates either a combination of probable success on

the merits and the possibility of irreparable injury or

17 that serious question are raised and the balance of

hardships tips sharply in his favor.

18

19 In re Excel Innovations, Inc., 502 F.3d 1086, 1093 (9th Cir. 2007).

20 In addition, likelihood of success in reorganization must also

21 be proven. Excel, 502 F.3d at 1095.

22 Given the parties’ consent in the May 3 Stipulation, to either

23 grant or denial of the Debtors’ request for declaratory relief as to

24 the effect of FERC’s ruling, there is no need for a separate

25 injunction. Declaratory relief on the First Claim will provide the

26 basis for FERC not having the authority to pursue any type of action

27 that supports concurrent jurisdiction over a motion to reject any

28 PPA. There is no need to enjoin anyone or any action now. Count

1 Three of the Complaint will be DISMISSED.

2 G. Basis for Declaratory Judgment

3 Countless courts have noted and accepted the broad scope of

4 FERC’s statutory jurisdiction over rates, terms and conditions of

5 wholesale electricity sales and power contracts, including changes

6 to those contracts. That authority has led to the evolution and

7 development of the filed-rate doctrine that provides that a party

8 may claim no rate as a legal right other than the filed rate,

9 whether fixed or accepted by FERC. Not even a court may authorize

10 other terms. All of this is black-letter law that is not in doubt

11 here. The briefs before the court are replete with citations that

12 do not need to be repeated.

13 Thus, because all the parties agree that the Federal Power Act

14 (“FPA”) means what it says, and FERC can do what it usually does, no

15 purpose would be served by discussing further the filed-rate

16 doctrine or FERC’s exclusive jurisdiction over rates and related

17 matters.

18 1. This is not an improper attack on FERC’s January 25 and 28,

2019, rulings nor on the FERC Denial.

19

Imagine the absurdity of the exclusive appeal route espoused by

20

FERC and the PPA Counterparties. Kafka might have designed it:

21

Parties not in bankruptcy are subjected to an involuntary

22 process by their opponents before a non-judicial,

administrative body.

23

Just a few days later they are told by that body that if

24 they file bankruptcy, one of the basic and critically

important tools placed there by Congress and available

25 only in bankruptcy will be unavailable.

26 And if they don’t like it, they’ll have to appeal via a

procedure outside of the bankruptcy system with its

27 exclusive subject-matter jurisdiction.

28 One day later they file bankruptcy, where myriad rights

and duties (and obligations) come in to play and a

1 bankruptcy court, experienced in bankruptcy matters, is

there to preside.

2

Now that bankruptcy is a reality and not an intention, the

3 agency repeats its prior ruling, that it has concurrent

jurisdiction with the bankruptcy court, but that court

4 will not be available to vindicate one of their

fundamental and critical bankruptcy rights.

5

Their first recourse to an Article III court after all that

6 is via appeal.

7 This process is unfair and should not be tolerated.

8 The FPA contains a provision dealing with the appeal of a

9 decision from FERC. First, the losing party must request a

10 rehearing before FERC. Second, a further appeal can be pursued in a

11 circuit court of appeals. 16 U.S.C. § 825l. The FPA provides the

12 only method for judicial review of rulings regarding the broad reach

13 of FERC’s exclusive jurisdiction over matters dealing with rates,

14 terms and conditions of wholesale power contracts and the panoply of

15 matters falling within the filed rated doctrine.

16 After the January 25 and 28, 2019 FERC orders, Debtors sought

17 rehearing. But in between they filed bankruptcy and immediately

18 filed this adversary proceeding challenging the fundamental assault

19 on the bankruptcy court’s exclusive jurisdiction.16 FERC and the

20 PPA Counterparties argue Debtors are trying an improper collateral

21 attack on FERC’s orders.

22 Although departure from that procedure just summarized is

23 normally unassailable, “judicial intervention is authorized when an

24 agency acts in ‘brazen defiance’ of its statutory authorization.”

25 Philip Morris, Inc. v. Block, 755 F.2d 368, 369 (4th Cir. 1985)

26

27 16 Had they not initiated this adversary proceeding, Debtors’

only recourse would have been to prosecute their attempt at a

28 successful rehearing; had FERC changed its position, this

proceeding might have been rendered moot.

1 (citation omitted). “An ultra vires act of an administrative agency

2 is either void or voidable.” Sierra Club v. Watt, 608 F. Supp. 305,

3 341 (E.D. Cal. 1985). Ultra vires acts occur when an agency acts

4 outside of “its statutory authorization.” Phillip Morris, 755 F.2d

5 at 370.

6 “FERC is a creature of statute, having no constitutional or

7 common law existence or authority, but only those authorities

8 conferred upon it by Congress.” Atl. City Elec. Co. v. F.E.R.C., 295

9 F.3d 1, 8 (D.C. Cir. 2002). See, also, Civil Aeronautics Bd. v.

10 Delta Air Lines, Inc., 367 U.S. 316, 322 (1961) (finding that an

11 agency “is entirely a creature of Congress” and “the determinative

12 question” is not what “[it] thinks it should do but what Congress

13 has said it can do.”).

14 FERC has acted outside of its statutory authority. Its

15 decisions before bankruptcy were advisory in nature, have no impact

16 on anyone; once the bankruptcy cases were filed they presented an

17 immediate conflict with the Bankruptcy Code and can be challenged

18 and dealt with in this court.

19 In addition, the United States Supreme Court has stated that

20 courts have the ultimate decision-making authority when analyzing

21 provisions governing a federal agency. While the courts can defer

22 to the regulatory agency involved, the final decision is for the

23 court alone to make. See Gordon v. New York Stock Exch., Inc., 422

24 U.S. 659, 686 (1975)(dealing with the court ruling on matters

25 involving the Securities Exchange Act and the Securities Exchange

26 Commission).

27 Nothing in the FPA or the Bankruptcy Code grants FERC

28 concurrent jurisdiction with this court over Section 365 motions to

1 reject executory contracts covering federal power matters.17 The

2 issue here is Section 365 and not any of the permutations and

3 applications of the filed rate doctrine. This is the only issue

4 before this court, and there is nothing collateral or indirect about

5 the attack. It is direct because it goes to the precise bankruptcy

6 issue of exclusive authority under 28 U.S.C. § 1334(a). This court

7 is not considering the FPA or reviewing any FERC decisions regarding

8 any matter within its exclusive jurisdiction. The rejection of an

9 executory contract is solely within the power of the bankruptcy

10 court, a core matter exclusively this court’s responsibility. 28

11 U.S.C. § 157(b)(2).

12 The Bankruptcy Code is the proper and only authority to apply

13 and not any aspect of the FPA. FERC did not draw on any specific

14 provision of that law to reach its ultimate conclusion, nor does

15 this court. The beginning and end of the analysis is in the

16 Bankruptcy Code.

17 2. FERC Acted in Excess of its Statutory Authority.

18 The court disagrees with FERC’s view that were it to authorize

19 rejection of a PPA, that authorization would not be “a license to

20 cease or modify performance in whatever manner [Debtors] wish[es].”

21 FERC Denial, Para. 16 (emphasis added).

22 To the contrary, authorization of rejection under Section 365

23 is authorization to breach - to cease...performance leaving the

24 affected PPA Counterparty with a claim for damages as of the

25 petition date. Tempnology, supra.

26 FERC makes the bold and unfounded statement that:

27

28

17 Mirant, 378 F. 3rd at 521.

1 “Performance under [the rejected PPA] remains subject to

[FERC’s] review to determine whether any cessation or

2 modification of performance is just and reasonable and not

unduly discriminatory or preferential under the FPA.”

3

FERC Denial, Para. 16.

4

The statement is wrong as a matter of law and is unenforceable

5

in these cases. A court “owe[s] an agency’s interpretation of the

6

law no deference” where, as here, the “statutory provisions before

7

[it] deliver unmistakable commands. SAS Inst, Inc. Iancu, 138 S.

8

Ct. 1348, 1358 (2018). It would render meaningless the bankruptcy

9

court’s authority and responsibility to authorize rejection under

10

the business judgment test.

11

Section 365’s lack of an exception for FERC simply means that

12

FERC has no jurisdiction over the rejection of contracts. See FCC

13

v. NextWave Pers. Commc’ns, Inc., 537 U.S. 293, 302 (2003) (“[W]here

14

Congress has intended to provide regulatory exceptions to the

15

Bankruptcy Code, it has done so clearly and expressly.”

16

In re Gruntz, 202 F.3d 1074, 1082 (9th Cir. 2000), is a seminal

17

Ninth Circuit decision that a state court’s determination as to

18

applicability of the automatic stay or actions that are done in

19

violation of the automatic stay are void.

20

In sum, bankruptcy courts have the ultimate authority

21 to determine the scope of the automatic stay imposed

by 11 U.S.C. § 362(a), subject to federal appellate

22 review. A state court does not have the power to

modify or dissolve the automatic stay. Accordingly,

23 the Rooker-Feldman doctrine does not render a state

court judgment modifying the automatic stay binding

24 on a bankruptcy court. Thus, if it proceeds without

obtaining bankruptcy court permission, a state court

25 risks having its final judgment declared void.

26 Id., at 1037.

27 The Ninth Circuit upheld a state court’s determination that a

28 criminal prosecution did not violate the automatic stay. Considered

1 narrowly, the decision has little bearing on this case because FERC

2 is not a state court, it did not involve a criminal matter, it did

3 not interpret the automatic stay, and at present there is no

4 automatic stay issue pending. But considered broadly, and

5 considering that the FERC Denial came after bankruptcy when the

6 automatic stay went into effect, Gruntz very much applies. It

7 warns that an interpretation of the Bankruptcy Code and the court’s

8 exclusive jurisdiction over core matters by another body that is in

9 excess of its own jurisdiction, to be binding on the bankruptcy

10 court, must be correct.

11 Before Debtors filed bankruptcy FERC made its January 25 and

12 28, 2019 rulings against them. Those rulings were at best toothless

13 advisory opinions that had no effect on anyone, especially debtors

14 contemplating but not then having filed bankruptcy. Obviously there

15 was no automatic stay in effect or even in existence. Equally

16 obviously, Gruntz was if no concern. All that changed on January

17 29, 2019. The Debtors’ reorganizations were immediately impacted by

18 the cloud of FERC’s assertion of concurrent jurisdiction and its

19 presumption that it could override a bankruptcy court’s PPA

20 executory contract rejection decision based upon policies embodied

21 in the FPA, principally protection of the public interest.

22 Now that FERC has issued its FERC Denial, the full impact of

23 Gruntz’s reasoning applies. Section 365(a) and 28 U.S.C. § 1334,

24 taken together, clearly lead to the inescapable conclusion that only

25 the bankruptcy court can decide whether a motion to reject should be

26 granted or denied, and under what standards.

27 The United States Supreme Court stated that Congress knew how

28 to grant exceptions to the power to reject executory contracts and

1 PPAs governed by the FPA were not included. N.L.R.B. v. Bildisco &

2 Bildisco, 465 U.S. 513, 523 (1984). Tempnology, supra, footnote 8

3 and accompanying text. The right to reject is qualified for many

4 exceptions under §§ 365(h), (i), (n), and (o). FERC and the FPA are

5 not mentioned in any exceptions. Section 365’s lack of an exception

6 for FERC simply means that FERC has no jurisdiction over the

7 rejection of contracts. See FCC v. NextWave Pers. Commc’ns, Inc.,

8 537 U.S. 293, 302 (2003) (“[W]here Congress has intended to provide

9 regulatory exceptions to the Bankruptcy Code, it has done so clearly

10 and expressly.”

11 As a result, if an executory contract does not fall into the

12 exceptions set forth by Congress in the Bankruptcy Code, only the

13 Bankruptcy Court can issue a ruling on rejection. The reasoning of

14 Gruntz is directly applicable, just as the Bankruptcy Court was

15 permitted to void a state court order that was issued in violation

16 of the Bankruptcy Code. This court can declare FERC’s attempt to

17 interpret and apply the Bankruptcy void.

18 In addition and apart from Gruntz and the automatic stay, case

19 law rejects any attempt by FERC to expand its jurisdiction to those

20 matters not governed by the FPA. Hunter v. FERC, 711 F.3d 155, 159

21 (D.C. Cir. 2013); Atl. City Elec. Co. v. F.E.R.C., 295 F.3d 1, 8

22 (D.C. Cir. 2002) (stating FERC is a creature of statute and only has

23 authority specifically conferred by Congress with no constitutional

24 or common law existence or authority). The court in Hunter found

25 that FERC failed to meet its burden to show a repeal by implication.

26 FERC argued that the FPA superseded a particular section of the

27 Commodity Exchange Act, which is implemented by the Commodity

28 Futures Trading Commission. Hunter, 711 F.3d at 160. Any order

1 issued by FERC stating concurrent jurisdiction is therefore void, as

2 it attempts to divest jurisdiction from the bankruptcy court that

3 was set forth by Congress.

4 The court’s “virtually unflagging obligation . . . to exercise

5 the jurisdiction given [it],” Colorado River Water Conservation

6 Dist. v. United States, 424 U.S. 800, 817 (1976), compels the

7 conclusion that it should hold that FERC’s orders are prospectively

8 void because they conflict with a core proceeding solely delegated

9 to this court. The United States Supreme Court referred to its

10 “original and exclusive” jurisdiction over disputes between the

11 States, 28 U.S.C. § 1251(a), adding “the description of our

12 jurisdiction as ‘exclusive’ necessarily denies jurisdiction of such

13 cases to any other federal court.” Mississippi v. Louisiana, 506

14 U.S. 73, 77–78 (1992). In 28 U.S.C. § 1344(a) Congress gave

15 exclusive jurisdiction over bankruptcy cases to this court (via a

16 referral from the district court). There is no reason why this

17 bankruptcy court should not apply exclusive jurisdiction in the same

18 way.

19 In sum, the three FERC decisions discussed here were not the

20 actions of a power regulator carrying out its statutory duties to

21 police rates, terms and conditions of power contracts, and enforcing

22 the filed-rate doctrine. To be blunt, they were unauthorized acts

23 of the power regulator executing a power play (to use a hockey term)

24 to curtail the role of the court acting within its authorized and

25 exclusive role in these bankruptcy cases. Those decisions can not

26 be applied or honored here.

27 3. Proper standard for rejection of executory contracts

28 To determine whether the Bankruptcy Court should approve the

1 rejection of an executory contract under Section 365, the business

2 judgment rule must be applied. In re Pomona Valley Med. Grp., Inc.,

3 476 F.3d 665, 670 (9th Cir. 2007). “[I]n evaluating the rejection

4 decision, the bankruptcy court should presume that the debtor-in-

5 possession acted prudently, on an informed basis, in good faith, and

6 in the honest belief that the action taken was in the best interests

7 of the bankruptcy estate.” Pomona Valley, 476 F.3d at 670; In re At

8 Home Corp., 292 B.R. 195, 199 (N.D. Cal. 2003), aff'd, 392 F.3d 1064

9 (9th Cir. 2004) (stating the debtor must demonstrate that rejection

10 will benefit the estate). This can include eliminating an executory

11 contract that has become burdensome or where prompt elimination will

12 positively impact the debtor’s ability to improve its financial

13 condition. 9C Am. Jur. 2d Bankruptcy § 2311. Further, the debtor’s

14 decision to reject cannot be based on “a gross abuse of debtor’s

15 business discretion.” Id.

16 A primary issue in this determination is whether the rejection

17 would benefit general unsecured creditors, which requires a

18 balancing of interests. In re Chi-Feng Huang, 23 B.R. 798, 801

19 (B.A.P. 9th Cir. 1982); In re Turbowind, Inc., 42 B.R. 579, 584

20 (Bankr. S.D. Cal. 1984). If rejection would lead to a third party

21 benefitting substantially at the expense of unsecured creditors, the

22 rejection cannot be approved. Chi-Feng Huang, 23 B.R. at 801.

23 A district court denied a debtor’s motion to reject where it

24 found that debtor was trying to “create” a business rather than

25 preserve one, and that debtor had filed bankruptcy solely to reject

26 that contract. The court found that these facts meant the debtor

27 was not exercising business judgment or operating in good faith. In

28 re S. California Sound Sys., Inc., 69 B.R. 893, 898 (Bankr. S.D.

1 Cal. 1987). Rejection is precluded where bankruptcy is filed with

2 the sole purpose of trying to reject. In re Safakish, No. 18-50769

3 MEH, 2018 WL 5621783, at *6 (Bankr. N.D. Cal. Oct. 29, 2018).

4 Disproportionate damage to the aggrieved party is a ground to

5 disapprove rejection. In re Monarch Tool & Mfg. Co., 114 B.R. 134,

6 137 (Bankr. S.D. Ohio 1990). Unfairness to the aggrieved party is

7 not enough, however. See In re Chi-Feng Huang, 23 B.R. 798, 801

8 (B.A.P. 9th Cir. 1982) (stating that the primary issue is whether

9 rejection would benefit the general unsecured creditors).

10 The parties that are impacted will receive an unsecured claim

11 for damages in the full amount of the rate listed in the PPAs.

12 Creation an administrative priority claim, which means placement

13 ahead of all unsecured creditors, will happen if FERC successfully

14 orders performance under a rejected PPA. That would be inconsistent

15 with the Bankruptcy Code’s treatment of such a rejected claim. As

16 noted, “a priority scheme dictating the order in which various

17 creditors’ claims will be satisfied in the course of bankruptcy

18 proceedings.” In re Holly Marine Towing, Inc., 669 F.3d 796, 800

19 (7th Cir. 2012).

20 That said, the court will not ignore what others have said

21 about public interest and the need to take it into account while at

22 the same time paying careful attention on the reorganization goals:

23 “If the district court decides that a more rigorous

standard is required, then it might adopt a standard

24 by which it would authorize rejection of an executory

power contract only if the debtor can show that it

25 “burdens the estate, [ ] that, after careful

scrutiny, the equities balance in favor of rejecting”

26 that power contract, and that rejection of the

contract would further the Chapter 11 goal of

27 permitting the successful rehabilitation of debtors.

See Bildisco, 465 U.S. at 526–27, 104 S.Ct. 1188.

28 When considering these issues, the courts should

carefully scrutinize the impact of rejection upon the

1 public interest and should, inter alia, ensure that

rejection does not cause any disruption in the supply

2 of electricity to other public utilities or to

consumers. Cf. id. at 527, 104 S.Ct. 1188. (requiring

3 the bankruptcy court to balance the interests of the

debtor, the creditors and the employees when

4 determining what constitutes a successful

rehabilitation).”

5

Mirant, at 525.18

6

Public policy does not need to be considered when applying the

7

business judgment rule every time a federal statute is implicated.

8

“Congress did not intend the Code to be a shield

9 behind which a debtor in possession might engage in

conduct that would be improper in a non-bankruptcy

10 context. Indeed, as a fiduciary holding its estate

in trust and responsible to the court, a debtor in

11 possession must administer its case and conduct its

business in a fashion amendable to the scrutiny to be

12 expected from creditor and court oversight.”

13

In re Pilgrim's Pride Corp., 403 B.R. 413, 424 (Bankr. N.D. Tex.

14

2009).

15

The business judgment standard in regular rejection is more

16

deferential than that given to contracts that are in the “public

17

interest.”19 But public interest may need to be considered in the

18

context of a specific rejection of a specific PPA. That outcome

19

will be fact-driven based on the particular motion to reject and the

20

responses of the opposing party. That is for another day.

21

22

23 18 In re Caribbean Petroleum Corp., 444 B.R. 263, 269 (Bankr.

Del 2010)(heightened scrutiny for rejection motions involving the

24 protection of national public interest such as public safety,

health or welfare (citing In re Old Carco, LLC, 406 B.R. 180, 189

25 (Bankr. S.D.N.Y. 2009).

26 19 Cf., In re Old Carco LLC, supra stating that the statutes

there were enacted by state legislatures, not Congress, so they

27 were protecting the public interest of the states rather than the

national public interest and did not deny the rejection motion in

28 the name of public interest.

1

2 VI. DISPOSITION

3 Debtors are entitled to this court’s declaratory judgment that

4 (1) FERC does not have concurrent jurisdiction over its decision to

5 permit Debtors to reject (or assume) executory contracts under

6 Section 365; and (2) that the FERC Denial and its two prior rulings

7 described above are of no force and effect and are not binding on

8 Debtors in these cases.20

9 Nothing will happen here until either of the Debtors moves to

10 reject an executory PPA and the affected counterparty opposes that

11 motion. At that time the court will consider the merits of any such

12 motion and if consideration implicates public policy interests as

13 well as reorganization goals, those interests can be considered as

14 part of the higher standard for the rejection decision. It may well

15 be that a particular motion seeks rejection of a contractual

16 obligation of the debtor to purchase energy in the future. That

17 likely will involve little if any public interests; on the other

18 hand rejection of a PPA based on some other rights and obligations

19 may trigger a more concrete and demonstrable consequence that may

20 tip the balance the other way. Either way, or whatever set of facts

21 apply, this court can make the assessment consistent with the

22 principles expressed here. There is no need or right for a second

23 inquiry by a separate non-judicial body to be involved. This court

24 will exercise its exclusive jurisdiction as Congress directed.

25 The automatic stay still applies the same way it did on January

26 29, 2019, when these cases were commenced. If more relief is

27

28 20 The court takes no position as to what happens if Debtors

appeal the FERC Denial to a court of appeal.

1 needed, the court’s specific and inherent injunctive powers are

2 available.

3 The motion of the Official Committee of Unsecured Creditors is

4 GRANTED. If there is no appeal that grant is of no consequence; if

5 there is an appeal, the committee’s views should be considered.

6 Concurrent with this Memorandum Decision the court is issuing

7 its Declaratory Judgment. In a few days it will issue a

8 Certification for Direct Appeal.

9

10 * * * END OF MEMORANDUM DECISION * * *

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

EDWARD J. EMMONS, CLERK 13 □□ \o.

U.S. BANKRUPTCY COURT Sf SSF &

NORTHERN DISTRICT OF CALIFORNIA 5 ay a

□□ 75

1 □ US □□

Signed and Filed: June 12, 2019 □□□□□□□

2

Lp Mnfteke

DENNIS MONTALI

5 U.S. Bankruptcy Judge

6

7 UNITED STATES BANKRUPTCY COURT

8 FOR THE NORTHERN DISTRICT OF CALIFORNIA

9]/In re ) Bankruptcy Case

) No. 19-30088-DM (Lead Case)

10 PG&E CORPORATION; PACIFIC GAS )

AND ELECTRIC COMPANY, ) Chapter 11

11 )

Debtors. ) (Jointly Administered)

12 )

PG&E CORPORATION; PACIFIC GAS ) Adv. Proc. No. 19-03003

13 AND ELECTRIC COMPANY, )

)

14 Plaintiffs, )

)

15|v. )

)

16 || FEDERAL ENERGY REGULATORY )

COMMISSION, )

17 )

Defendant. )

18 )

19 AMENDED DECLARATORY JUDGMENT

20 For the reasons set forth in the Memorandum Decision on Actior

21]||/For Declaratory and Injunctive Relief filed and entered on June 7,

2019,

23 IT IS HEREBY ORDERED, ADJUDGED AND DECREED AS FOLLOWS:

24 1. This court confirms its original and exclusive

25 jurisdiction over Debtors’ cases under 11 U.S.C. § 1334(a) and

||/Debtors’ rights to assume or reject executory contracts under 11

27/U.S.C. 8§ 365, as core proceedings under 28 U.S.C. 157(b)(2).

28

- 1 -

1 2. Included in the foregoing paragraph are power purchase

2 contracts between and among either or both Debtors and

3 counterparties to any such contracts.1

4 3. The Federal Energy Regulatory Commission does not have

5 concurrent jurisdiction, or any jurisdiction, over the

6 determination of whether any rejections of power purchase contracts

7 by either Debtor should be authorized.

8 4. Debtors do not need approval from the Federal Energy

9 Regulatory Commission to reject any of their power purchase

10 contracts.

11 5. Any determinations of the Federal Energy Regulatory

12 Commission contrary to the provisions of Paragraph 3 and 4 above

13 are void, of no force and effect and not binding on this court or

14 either Debtor. Such determinations include, but are not limited

15 to, NextEra Energy, Inc. v. Pac. Gas and Elec. Co., 167 FERC ¶

16 61,096 (2019) at para. 13, NextEra Energy, Inc. v. Pac. Gas and

17 Elec. Co., 166 FERC ¶ 61,049 (2019); Exelon Corp. v. Pac. Gas and

18 Elec. Co., 166 FERC ¶ 61,053.

19 6. This Amended Declaratory Judgment is the court’s Final

20 Judgment concluding this adversary proceeding.

21 ***END OF AMENDED DECLARATORY JUDGMENT***

22

23

24

25

26

27

1 Many of these counterparties have intervened as defendants

28 in this adversary proceeding and have stipulated to entry of a

final judgment by this court. See Stipulation re Procedure for

Disposition of Adversary Proceeding at Docket. No. 149, ¶¶ 2-3.