IN THE UNITED STATES DISTRICT COURT
FOR THE MIDDLE DISTRICT OF PENNSYLVANIA
CATAWISSA TOWNSHIP, No. 4:24-CV-00280
Plaintiff, Chief Judge Brann
v.
MIDLAND ASPHALT MATERIALS,
INC. and LIBERTY MUTUAL
INSURANCE COMPANY,
Defendants.
MEMORANDUM OPINION
MAY 14, 2024
I. BACKGROUND
On January 11, 2024, Plaintiff, Catawissa Township, filed a five-count
complaint against Defendants, Midland Asphalt Materials, Inc. (“Midland”) and
Liberty Mutual Insurance Company (“Liberty Mutual”) in the Court of Common
Pleas of Columbia County.1 Defendants then removed this action on the basis of
diversity jurisdiction.2 Midland and Liberty Mutual each filed a Motion to Dismiss
on February 23, 2024 pursuant to Federal Rule of Civil Procedure 12(b)(6) for
failure to state a claim.3 These motions are now ripe for disposition. For the
reasons that follow, Midland’s motion is granted in part and denied in part, and
Liberty Mutual’s motion is granted.
1 See Doc. 1 (Notice of Removal), Ex. A (Columbia Cnty. Compl.).
2 See Doc. 1 (Notice of Removal).
II. DISCUSSION
A. Motion to Dismiss Standard
Under Federal Rule of Civil Procedure 12(b)(6), courts dismiss a complaint,
in whole or in part, if the plaintiff fails to “state a claim upon which relief can be
granted.” Following the landmark decisions of Bell Atlantic Corp. v. Twombly4 and
Ashcroft v. Iqbal,5 “[t]o survive a motion to dismiss, a complaint must contain
sufficient factual matter, accepted as true, to ‘state a claim to relief that is plausible
on its face.’”6 The United States Court of Appeals for the Third Circuit has
instructed that “[u]nder the pleading regime established by Twombly and Iqbal, a
court reviewing the sufficiency of a complaint must take three steps”: (1) “take
note of the elements the plaintiff must plead to state a claim”; (2) “identify
allegations that, because they are no more than conclusions, are not entitled to the
assumption of truth”; and (3) “assume the[] veracity” of all “well-pleaded factual
allegations” and then “determine whether they plausibly give rise to an entitlement
to relief.”7
When deciding a motion to dismiss, a court generally considers only the
allegations in the complaint, exhibits attached thereto, and facts of public record.8
4 550 U.S. 544 (2007).
5 556 U.S. 662 (2009).
6 Id. at 678 (quoting Twombly, 550 U.S. at 570).
7 Connelly v. Lane Construction Corp., 809 F.3d 780, 787 (3d Cir. 2016) (internal quotations
and citations omitted).
8 Mayer v. Belichick, 605 F.3d 223, 230 (3d Cir. 2010).
Normally, to consider anything beyond those sources, a motion to dismiss must be
converted to a motion for summary judgment.9 But consideration of materials
outside the complaint is not completely barred on a 12(b)(6) motion. Courts may
consider any documents that are integral or explicitly relied upon in the
complaint.10 “However, before materials outside the record may become the basis
for a dismissal, several conditions must be met.”11 “For example, even if a
document is ‘integral’ to the complaint, it must be clear on the record that no
dispute exists regarding the authenticity or accuracy of the document.”12 It must
also be clear that there exists no material disputed issues of fact regarding the
relevance of the document.13 In this matter, this Court finds that these conditions
have been met and will consequently consider Pennsylvania Department of
Transportation (“PennDOT”) Publication 408.
B. Facts Alleged in the Complaint
1. The Parties
Catawissa Township is a “Second Class Township in Columbia County,
Pennsylvania.”14 Midland is incorporated in New York and maintains its principal
9 See Fed. R. Civ. P. 12(d).
10 Schmidt v. Skolas, 770 F.3d 241, 249 (3d Cir. 2014).
11 Faulkner v. Beer, 463 F.3d 130, 134 (2d Cir. 2006).
12 Id.; see also Kaempe v. Myers, 367 F.3d 958, 965 (D.C. Cir. 2004); Alternative Energy, Inc.
v. St. Paul Fire and Marine Ins. Co., 267 F.3d 30, 33 (1st Cir. 2001).
13 Faulkner, 463 F.3d at 134.
14 Doc. 1 (Notice of Removal), Ex. A (Columbia Cnty. Compl.) ¶ 1.
place of business there.15 Through a bidding process, the Township selected
Midland to perform repair work on McIntyre Road in 2019.16 Finally, Liberty
Mutual is a Massachusetts corporation with a principal place of business in Boston,
Massachusetts; it provided the surety bond required by Plaintiff.17
2. The Proposal
Midland “created a proposal for work to be performed on McIntyre Road for
Catawissa Township” on April 12, 2018.18 To ensure the proper material was
supplied, the Proposal required Midland to provide a bill of lading for each load
delivered, daily material certifications, oil samples, an affidavit showing aggregate
and oil compatibility, and a copy of a PennDOT approved seal coat design.19 An
escalator clause in the Proposal allowed for the price adjustment of bituminous
material as needed.20 Plaintiff was also to receive two weeks’ notice before any
work began, and all work was to be completed in accordance with PennDOT
Publication 408.21 Finally, the Proposal required Midland to perform full depth
reclamation (“FDR”) on the road and to test and submit a laboratory design mix to
the Township three weeks before commencing the repair work.22
15 See id. ¶ 2; Doc. 1 (Notice of Removal), Ex. B (Coleman Decl.) ¶ 3.
16 See id. ¶ 8.
17 See id. ¶ 3.
18 Id. ¶ 7.
19 See Doc. 1 (Notice of Removal), Ex. A (Columbia Cnty. Compl.), Attach. 1 (The Proposal)
at 3-e.
20 See id. at 3-f.
21 See id.
22 See id. at 3-3-a.
3. The Contract
The Catawissa Township Board of Supervisors approved the Proposal on
April 9, 2019 through PennDOT Form MS-944 (“Form MS-944” or “the
Contract”).23 Form MS-944 is divided into two parts.24 Part A describes how to
submit proposals.25 In Part B, the relevant proposal is identified and followed by a
signed contractor’s certification.26 Underneath the signed certification is a page
divider that states: “TO BE EXECUTED ONLY IN THE EVENT THE ABOVE
PROPOSAL IS ACCEPTED.”27 The municipality then signs and dates the form
under this page divider.28
4. The Surety Bond
The Contract required Midland to provide a Performance Bond and Payment
Bond (“the Bond”) “for 100% of the work to Catawissa Township within twenty
days … of receipt of the bid award.”29 On April 18, 2019, Midland provided a
bond issued by Liberty Mutual for $151,111.07 “to guarantee Midland’s
compliance and performance of the terms and conditions of the Contract ….”30 The
23 See Doc. 1 (Notice of Removal), Ex. A (Columbia Cnty. Compl.) ¶ 8.
24 See Doc. 1 (Notice of Removal), Ex. A (Columbia Cnty. Compl.), Attach. 2 (Executed
Contract) at 52-53.
25 See id.
26 See id.
27 Id.
28 See id.
29 Doc. 1 (Notice of Removal), Ex. A (Columbia Cnty. Compl.) ¶ 9.
30 Id.
Bond “irrevocably bound” Liberty Mutual to Catawissa Township “to assure the
completion of the work by Midland under the Proposal and Contract.”31
5. Modifying the Proposal Terms
Pursuant to the escalator clause, “Midland met with Catawissa Township [in
June 2019] to seek a modification of the Proposal” as its “emulsion projections
prohibited it from performing the project for the full length at the agreed upon
price ….”32 Due to this issue, the parties reduced the amount of work to be
performed.33
6. Performance Failures
Catawissa Township alleges several breaches of the Proposal. These failures
are best divided into the following categories: nonperformance of certain tests or
investigations; lack of adequate notice and certifications; and noncompliance with
specific performance metrics.
i. Nonperformance of Tests and Investigations
Midland did not provide a “laboratory design mix” or perform a Marshall
Design Test before work on the road began.34 Further, it did not “investigate the
traffic and water flow on McIntyre and Quarry Roads” nor did it “provide oil
31 Id. ¶ 11.
32 Id. ¶ 14.
33 See id.
34 Id. ¶¶ 15-17.
samples ….”35 And, finally, Midland did not “perform a 300-foot test strip
demonstrating the FDR process prior to work being performed ….”36
ii. Lack of Adequate Notice and Certifications
Midland was supposed to provide two weeks’ notice before working on the
roads.37 No such notice was given; instead, Midland “arrived unannounced and
began work on McIntyre Road” on June 25, 2019.38 Additionally, the Township
never received the required daily material certifications, a compatibility affidavit,
or load tickets.39
iii. Noncompliance with Performance Metrics
Midland notably did not comply with PennDOT Publication 408 or provide
“an approved PennDOT seal coat design ….”40 These failures contributed to the
company’s inability to “provide a road surface that lasted more than a few months
prior to failure” and “to construct the road in such a way as to avoid premature
road failure.”41
35 Id. ¶¶ 39(d), (h).
36 Id. ¶ 39(k).
37 See id. ¶ 39(l).
38 Id. ¶ 22.
39 Id. ¶¶ 39(f), (g), (i).
40 Id. ¶¶ 39(a), (e).
41 Id. ¶¶ 39(m), (n).
7. Payment and Failure of the Road
Plaintiff “paid Midland in full in two payments on August 2, 2019 and
September 6, 2019.”42 In February 2020, Catawissa Township became aware of the
road’s “failure” and “immediately notified” Midland of this issue.43 Engineers
from the Township and Midland agreed “that the road had failed and required
repairs.”44 The road had an emulsion rate of 1.5% to 1.8%.45 In order to avoid
failure, McIntyre Road actually required an emulsion rate of 3% to 4.5%.46 This
prompted Plaintiff to send “a formal notice of the failure of the reclaimed base and
roadway surface ….”47
C. Analysis
The Township has filed a five-count complaint against the Defendants. In
Counts I through IV, Plaintiff alleges claims against Midland stemming from the
failure of McIntyre Road. Count V is a claim for breach of surety contract solely
alleged against Liberty Mutual. This is a contractual dispute predicated on this
Court’s diversity jurisdiction and brought under Pennsylvania law.48 “In the
absence of authoritative guidance from the Supreme Court of Pennsylvania, the
Court looks to ‘decisions of [Pennsylvania] intermediate appellate courts, of
42 Id. ¶ 24.
43 Id. ¶ 25.
44 Id. ¶ 28.
45 Id. ¶ 30.
46 Id.
47 Id. ¶ 31.
48 See Erie R.R. Co. v. Tompkins, 304 U.S. 64, 78, 58 S. Ct. 817, 82 L.Ed. 1188 (1938).
federal courts interpreting [Pennsylvania] law, and of other state supreme courts
that have addressed the issue ….”49
1. Count I – Breach of the Contract
Under Pennsylvania law, “‘three elements are necessary to plead a cause of
action for breach of contract: (1) the existence of a contract, including its essential
terms[;] (2) a breach of the contract; and[] (3) resultant damages.’”50 Midland
disputes the terms of the contract, Plaintiff’s ability to show any breach, and
causation.
i. Terms of the Contract
Midland contends that the Contract does not incorporate the Proposal it had
previously submitted to the Township as it is not “clear[ly] reference[d]” in the
Contract.51 This argument fails to recognize the critical issue: whether the Proposal
served as an offer that Plaintiff was free to accept.
Courts in Pennsylvania have routinely concluded that “‘a solicitation for bid
proposals is not an offer but only an invitation for parties to submit bids in
response to this request. The submission of the bid is, in fact, the offer which the
49 First Nonprofit Ins. Co. v. Meenan Oil LLC, 462 F. Supp. 3d 537, 540 (E.D. Pa. 2020)
(quoting Spence v. ESAB Grp., Inc., 623 F.3d 212, 216 (3d Cir. 2010)).
50 Doe v. Univ. of the Scis., 961 F.3d 203, 211 (3d Cir. 2020) (quoting Meyer, Darragh,
Buckler, Bebenek & Eck, P.L.L.C. v. Law Firm of Malone Middleman, P.C., 635 Pa. 427, 137
A.3d 1247, 1258 (Pa. 2016)).
51 Fegley Real Estate, LLC v. Boyle Constr., Inc., No. 2009-C-4007, 2011 Pa. Dist. & Cnty.
Dec. LEXIS 366, at *4 (Lehigh Cnty. Ct. of Common Pleas) (quoting Standard Bent Glass
Corp. v. Glassrobots Oy, 333 F.3d 440, 447 (3d Cir. 2003)).
contracting agency is free to accept or reject.’”52 This view is consistent with the
discussion of public construction contracts in the Restatement (Second) of
Contracts.53 The structure of Form MS-944 also aligns with the three-steps of
forming a contract through an auction process. Part A is the Township’s initial
request for offers.54 Part B first memorializes Midland’s submission of its offer to
Catawissa Township.55 Then, below the page divider, Plaintiff accepts that offer.56
Accordingly, I conclude that the Proposal operated as an offer which Plaintiff
accepted through Form MS-944; the terms of the Proposal are an appropriate basis
for this breach of contract claim.
The course of performance of this contract reinforces this determination.
“[T]he Supreme Court of Pennsylvania has recognized that the ‘course of
performance is always relevant in interpreting a writing.’”57 “As the
[Pennsylvania] Supreme Court explained, ‘[t]he parties to an agreement know best
52 Yurcho v. Hazleton Area Sch. Dist., No. 1430 C.D. 2011, 2012 Pa. Commw. Unpub. LEXIS
821, at *22-23 (Pa. Commw. Ct. 2012) (quoting Nat’l Constr. Servs. V. Phila. Reg’l Port
Auth., 789 A.2d 306, 309 (Pa. Commw. Ct. 2001)).
53 See RESTATEMENT (SECOND) OF CONTRACTS § 28, cmt. c (1981) (“Governmental agencies …
often advertise for bids from construction contractors prepared to undertake the building of a
building or other structure … The rule in such cases is much like that governing auctions –
unless a contrary intention is manifested, the advertisement is not an offer but a request for
offers; bidders on both prime contract and subcontract make offers when they submit bids;
and all bids may be rejected ….”). “Pennsylvania courts regularly employ the Restatement
(Second) of Contracts when resolving contract disputes.” Hart v. Arnold, 2005 PA Super
328, 884 A.2d 316, 333 (Pa. Super. 2005), appeal denied, 587 Pa. 695, 897 A.2d 458 (Pa.
2006).
54 See RESTATEMENT (SECOND) OF CONTRACTS § 28, cmt. c (1981).
55 See id.
56 See id.
57 Norfolk Southern Ry. v. Pittsburgh & W. Va. R.R., 101 F. Supp. 3d 497, 525 (W.D. Pa. 2015)
(quoting Atl. Richfield Co. v. Razumic, 480 Pa. 366, 390 A.2d 736, 741 n.6 (Pa. 1978)).
what they meant, and their action under it is often the strongest evidence of their
meaning.’”58 The Third Circuit has similarly “observed that ‘[a] court always may
consider the course of performance as evidence of the intent of the parties.’”59
Notably, “Midland met with Catawissa Township to seek a modification of
the Proposal pursuant to the Escalator Clause” in June 2019. This escalator clause
is not mentioned in what Midland asserts is the only operative document: the
signed and executed version of Form MS-944. This behavior suggests that the
parties did in fact intend to be bound by the terms of the Proposal.
ii. Breach of the Terms and Causation
Since I have determined that the terms of the Proposal are binding on
Midland for purposes of this motion, Plaintiff has also appropriately identified
various breaches of the contract.60 For this reason, I will now address Midland’s
causation argument.
“In order to prevail on a breach of contract claim in Pennsylvania, a plaintiff
must show not only damages, but also ‘a causal connection between the breach and
the loss.’” 61 As alleged, Plaintiff contends that “[a]s a direct and proximate result
of Midland’s material breach of the Contract, [it] has suffered damages in excess
of $150,000.00 ….” Other courts in this Circuit have found similar language
58 Id.
59 Id. at 526 (quoting In re Old Summit Mfg., LLC, 523 F.3d 134, 137-38 (3d Cir. 2008)).
60 See Doc. 1 (Notice of Removal), Ex. A (Columbia Cnty. Compl.) ¶ 39.
61 Enslin v. Coca-Cola Co., 739 F. App’x 91, 95 (3d Cir. 2018) (quoting Logan v. Mirror
Printing Co. of Altoona, Pa., 410 Pa. Super. 446, 600 A.2d 225, 226 (Pa. Super. Ct. 1991)).
sufficient to allege a causal connection between the relevant breach and damages.62
This conclusion is supported by the stated purpose of various terms of the
Contract: to ensure that the proper materials were used.63 Despite Midland’s
suggestion to the contrary, the Township has also adequately shown how the
breaches caused its damages. The various alleged breaches contributed to
Midland’s inability “to provide a road surface that lasted more than a few months
prior to failure.”64 That then required Catawissa Township to “remedy the issues
caused by Midland’s defective performance ….”65
2. Count II – Breach of Express Warranty
“To sustain a claim for breach of express warranty, a plaintiff must generally
establish: ‘(1) defendants breached or failed to meet its warranty promise, (2) the
breach was the proximate cause of the harm, and (3) there were ensuing
damages.’”66 “Where a contract contains an express warranty to remedy defects
due to faulty workmanship or materials appearing within the specified time, [that
party] is responsible for defects resulting from such causes which appear within the
warranty period and is required to make good [its] warranty according to its terms
62 See e.g., Jazz Pharms., Inc. v. Synchrony Grp., LLC, 343 F. Supp. 3d 434 (E.D. Pa. 2018).
63 See Doc. 1 (Notice of Removal), Ex. A (Columbia Cnty. Compl.), Attach. 1 (The Proposal)
at 3-e.
64 Doc. 1 (Notice of Removal), Ex. A (Columbia Cnty. Compl.) ¶ 39.
65 Id. ¶ 34.
66 Dietrick v. Barnett Outdoors, LLC, No. 3:20-CV-215, 2021 U.S. Dist. LEXIS 188839, 2021
WL 4494631, at *6 (M.D. Pa. Sept. 30, 2021) (Mariani, J.) (quoting Stevens v. C.R. Bard,
Inc., No. 17-cv-1388, 2018 U.S. Dist. LEXIS 17536, 2018 WL 692097 (W.D. Pa. 2018)).
….”67 “In addition, accepting a completed project does not waive imperfections in
the construction and workmanship that are inherently latent and could not have
been revealed upon reasonable inspection.”68
In support of this claim, Plaintiff identified three possible express
warranties: Midland’s responsibility for maintaining the road for a year as
expressed in the Final Completion Certificate;69 PennDOT Publication 408 Section
105.12;70 and PennDOT Publication 408 Section 107.16(b).71
As to Midland’s obligation to repair the road for a year, I note that the Final
Completion Certificate is unsigned. Assuming for purposes of this motion, without
67 Buddy’s Plant Plus Corp. v. CentiMark Corp., Civil Action No. 10-670 2013 U.S. Dist.
LEXIS 6373, 2013 WL 169697, at *31 (W.D. Pa. Jan. 16, 2013), aff’d 604 F. App’x 134
(quoting Brandywine Area Joint Sch. Auth. v. Van Cor, Inc., 57 Pa. D. & C.2d 606, 616
(Chester Cnty. Ct. of Common Pleas 1971)).
68 Id. (citing Abram Singer Sons, Inc. v. DeStefano, 17 Pa. D. & C.2d 146 (Montgomery Cnty.
Ct. of Common Pleas 1971)).
69 In the Final Completion Certificate, it states “The Contractor is responsible for maintenance
of permanent pavement repairs for a period of one year from this date.” See Doc. 1 (Notice of
Removal), Ex. A (Columbia Cnty. Compl.), Attach. 1 (The Proposal) at 36.
70 See PENNSYLVANIA DEPARTMENT OF TRANSPORTATION, SPECIFICATIONS, PUB 408/2016
(Change 6) § 105.12, Defective Work and Material (Apr. 5, 2019) (“If any work and/or
material does not meet the requirements of the plans and specifications, or is not within
reasonably close conformity, as determined by the Representative, such work and/or material
will be declared defective. Unless otherwise specified, repair, as directed, or remove and
replace defective work and/or material at no expense to the Department.”).
71 See id. at § 107.16(b), Responsibility for Latent Defects (“The Representative will determine
if a defect is a latent defect. The Contractor and the Surety continue to be liable for all latent
defects; however, the Surety is liable only until the performance bond is released.
Satisfactorily repair or correct latent defects at no expense to the Department. If defects
cannot be satisfactorily repaired or corrected, provide reimbursement for any expenses or
damages incurred by the State because of latent defects. Failure to satisfactorily correct latent
defects, or to reimburse the State for expenses or damages incurred as a result of latent
defects, will be considered sufficient cause to suspend or remove prequalification, according
to 67 PA Code Chapter 457, regulations governing prequalification of prospective bidders,
provided that any adjudication regarding such latent defects is final.”).
deciding that this precludes Plaintiff from relying on it as an express warranty, the
Township has nonetheless adequately pled this claim. The Contract explicitly
incorporates by reference PennDOT Publication 408. Therefore, Plaintiff has
“referred to the warranty … and cited specific examples of” Midland’s “failure to
construct” and repair the road in accordance with the express warranties.72 These
examples include: the determination of the emulsion rate in May 2020; the failure
to provide a PennDOT approved seal coat design; the failure to perform a test strip
demonstrating the FDR process; and the failure to provide an approved FDR mix
design prior to commencing work on the road.73
Midland again challenges Plaintiff’s ability to demonstrate causation. It
contends that the “Township says only that Midland declined to repair the road or
refund its money ….”74 “[R]ather than attempting to ‘show’ how Midland caused
its injury, … the Township simply says that it did so.”75 In making this argument,
Midland does not persuasively consider the impact of incorporating Paragraphs 1
through 41 of the Complaint into this cause of action. The deficiencies in materials
and processes alleged in those paragraphs contributed to the failure of the road and
the latent defect at issue. While this claim may ultimately prove to be duplicative,
for now it is appropriate to allow it to proceed.
72 Roberts v. NVR, Inc., Civil Action No. 15-489, 2015 U.S. Dist. LEXIS 76795, 2015 WL
3745178, at *8 (W.D. Pa. June 15, 2015).
73 See Doc. 1 (Notice of Removal), Ex. A (Columbia Cnty. Compl.) ¶¶ 30, 39.
74 Doc. 9 (Brief in Support of Midland’s Motion to Dismiss) at 13.
75 Id.
3. Count III – Breach of Implied Warranty
For a claim for a breach of an implied warranty, the Township must show
“‘1) the existence of the implied warranty; 2) breach of the implied warranty; 3) a
causal connection between the defendant’s breach and the plaintiff’s injury or
damage; and 4) the extent of loss proximately caused by the defendant’s
breach.’”76 Both federal and state courts in Pennsylvania have “previously
recognized on several occasions that all service contracts—not just residential
construction contracts—may include an implied warranty that services will be
performed in a reasonable and workmanlike manner.”77
First, Midland contends that “the Township does not allege how Midland
allegedly failed to perform [the] services in a way that breached the implied
warranty.”78 In making this argument, Midland does not seriously consider the
significance of incorporating the prior allegations into this claim; instead, it
dismisses these allegations after a cursory discussion.79 But these earlier
allegations in fact establish “how” the implied warranty of workmanship has been
violated: through Midland’s allegedly inadequate performance and improper use of
76 State Farm Fire & Cas. Co. v. Waterbury Kitchen and Bath, Inc., No. 22-447, 2023 U.S.
Dist. LEXIS 151546, 2023 WL 5538048, at *2 (E.D. Pa. Aug. 25, 2023) (quoting Byrd v.
Essex Silverline Corp., No. 04-cv-4827, 2008 WL 81887, at *3 (E.D. Pa. Jan. 8, 2008))
(emphasis removed).
77 Delaware, Lackawaxen and Stourbridge R.R. Co. v. Star Trak, Inc., No. 3:18-CV-0480, 2018
U.S. Dist. LEXIS 183035, 2018 WL 5296292, at *3 (M.D. Pa. Oct. 25, 2018) (Saporito, Jr.
M.J.) (collecting cases).
78 Doc. 9 (Brief in Support of Midland’s Motion to Dismiss) at 14-15.
79 See Doc. 13 (Reply Brief in Support of Midland’s Motion to Dismiss) at 7-8.
materials. As with the other causes of action where causation has been challenged,
the identified deficiencies allegedly caused the road’s failure. Again, this cause of
action may ultimately prove to be duplicative. However, at this stage of the
proceeding, it is appropriate to allow it to proceed.
4. Count IV – Unjust Enrichment
“To state an unjust enrichment claim, a plaintiff must allege: (1) benefits
conferred on the defendant by the plaintiff; (2) appreciation of such benefits by the
defendant and (3) acceptance and retention of such benefits under such
circumstances that it would be inequitable for the defendant to retain the benefit
without payment of value.”80 But unjust enrichment is “inapplicable when the
relationship between parties is founded on a written agreement or express
contract.”81 When the unjust enrichment claim “concerns conduct outside the scope
of the original agreement or contract,” a plaintiff is allowed to plead such a claim
in the alternative.82
Based on my earlier determinations, the terms of the contract fully govern
the relationship between Plaintiff and Midland. As a result, dismissal of this claim
is appropriate, but I do so without prejudice.
80 Bordoni v. Chase Home Fin. LLC, 374 F. Supp. 3d 378, 388 (E.D. Pa. 2019) (citing Mitchell
v. Moore, 1999 PA Super 77, 729 A.2d 1200, 1203 (Pa. Super. 1999)).
81 Id. (quoting Benefit Tr. Life Ins. Co. v. Union Nat. Bank of Pittsburgh, 776 F.2d 1174, 1177
(3d Cir. 1985)).
82 Kraus Indus. v. Moore, Civil Action No. 06-00542, 2007 U.S. Dist. LEXIS 68869, 2007 WL
2744194, at *8 (W.D. Pa. Sept. 18, 2007) (citing Hershey Foods Corp. v. Ralph Chapek, Inc.,
828 F.2d 989, 999 (3d Cir. 1987)).
5. Count V – Punitive Damages for Breach of Suretyship
Finally, Liberty Mutual seeks dismissal of Plaintiff’s demand for punitive
damages. Punitive damages are not available under Pennsylvania law when based
solely on a breach of contract.83 Instead, “‘[o]nly where the person who breaks a
contract also breaches some duty imposed by society will compensatory or
punitive damages be imposed against the wrongdoer in order to punish the
wrongful act and in order to serve as a deterrent.’”84 Since no breach of a societal
duty has been alleged, dismissal of this claim for punitive damages is appropriate.
Dismissal of this request shall be without prejudice solely to allow Plaintiff the
opportunity to allege a breach of a societal duty. It is currently futile for the
Township to bring a claim under 42 Pa. C.S. § 8371.85 Should the Pennsylvania
Supreme Court eventually disagree with this conclusion, Catawissa Township may
file a motion for reconsideration at that time.
III. CONCLUSION
For the reasons above, Midland’s motion to dismiss is granted in part and
denied in part; Liberty Mutual’s motion to dismiss is granted.
83 See e.g., McShea v. City of Phila., 995 A.2d 334, 340 n. 5 (Pa. 2010); Nicholas v. Penn. State
Univ., 227 F.3d 133, 147 (3d Cir. 2000).
84 Judge v. Shikellamy Sch. Dist., 135 F. Supp. 3d 284, 299 (M.D. Pa. 2015) (quoting Daniel
Adams Associates v. Rimbach Publishing Inc., 287 Pa. Super. 74, 429 A.2d 726, 728 (Pa.
Super. 1981)).
85 See East Steel Constructors, Inc. v. Int’l Fid. Ins. Co., 2022 PA Super 149, 282 A.3d 827,
965 (Pa Super. Ct. 2022) (“Section 8371 does not apply to suretyships ….”).
Plaintiff is granted to leave amend. “The Federal Rules of Civil Procedure
do not address the situation in which a deficiency in a complaint could be cured by
amendment but leave to amend is not sought.”86 But the law in the Third Circuit is
clear that leave to amend should be “freely given” regardless of whether leave is
specifically requested.87 As such, Plaintiff will be given fourteen days from today’s
date to file an amended complaint.
An appropriate Order follows.
BY THE COURT:
s/ Matthew W. Brann
Matthew W. Brann
Chief United States District Judge