Opinion

Middletown Water Joint Venture LLC v. Borough of Middletown

Court
District Court, M.D. Pennsylvania
Filed
Apr 13, 2020
Cited by
0 cases
Authority
More cited than 29.1%

The opinion

IN THE UNITED STATES DISTRICT COURT

FOR THE MIDDLE DISTRICT OF PENNSYLVANIA

MIDDLETOWN WATER JOINT : CIVIL ACTION NO. 1:19-CV-1402

VENTURE LLC, :

: (Chief Judge Conner)

Petitioner :

:

v. :

:

BOROUGH OF MIDDLETOWN, :

:

Respondent :

MEMORANDUM

Both parties in this case have asked us to enforce an arbitration agreement.

Middletown Water Joint Venture LLC (“Middletown Water”) petitions the court to

confirm an arbitration award that it claims grants it the right to compensation for

certain contractually defined projects. (See Docs. 1, 14). The Borough of

Middletown (“Middletown Borough” or “Borough”) opposes the petition and claims

it has the right to review and approve of, or disapprove of, those same contractually

defined projects. (See Docs. 7, 15). We will deny Middletown Water’s petition.

I. Factual Background & Procedural History

This case arises from a contractual relationship and subsequent arbitration

proceedings between a governmental body and a private contractor. Middletown

Borough is a subdivision of the Commonwealth of Pennsylvania. (Doc. 1 ¶ 9).

Middletown Water is a Delaware limited liability company headquartered in New

York. (Id. ¶ 8). The parties entered into a Municipal Water and Wastewater Utility

System Concession and Lease Agreement (“Concession Agreement” or

“Agreement”) on September 30, 2014. (Id. ¶ 2).

A. Concession Agreement

Under the Concession Agreement, Middletown Water leased Middletown

Borough’s water and sewer systems for a 50-year period. (Doc. 1-2 at 2).1 The

Agreement makes Middletown Water responsible for all capital improvements to

the Borough’s system, including “Major Capital Improvements.” (Id. at 3; Doc. 1-4

at 64). A “Major Capital Improvement” is

(a) any capital improvement required to increase the

treatment capacity of the Wastewater Utility System as

contemplated by Section 3.21, (b) any amount required to

fund a Casualty Cost in excess of net insurance proceeds

under Section 13.3(a) and (c) any other capital

improvement to the Utility System (1) having an estimated

cost in excess of $500,000, Adjusted for Inflation from the

Closing Date to the dale such estimate is made and (2)

which, in the written opinion of an Engineering Firm,

constitutes an expansion to or renewal, replacement or

betterment of the Utility System and has a useful life of at

least five years.

(Doc. 1-4 at 19 (emphasis added)). As described below, Middletown Water may seek

reimbursement for Major Capital Improvements. (See id. at 69, 77).

Section 4.5 of the Concession Agreement, entitled “Major Capital

Improvement Project Implementation,” describes the process that Middletown

Water must undertake before performing Major Capital Improvements. (Id. at

67-70). In the spirit of brevity, we will describe only the processes and related

information relevant to the instant dispute.

1 The Middletown Borough Authority (“Authority”) owns the assets that

make up Borough’s water utility system. (Doc. 1-4 at 1). The Authority leased the

water utility system and its assets to the Borough. (Id.) References to the Authority

in the Concession Agreement are therefore treated as references to the Borough.

For any project fitting the definition of Major Capital Improvement,

Middletown Water must first create a “Major Capital Improvement Conceptual

Design,” which is simply a “basic description” of the Major Capital Improvement.

(Id. at 67). Pursuant to subsection 4.5(a)(iii)—entitled “Review and Approval”—the

Major Capital Improvement Conceptual Design is subject to the review,

commentary, and approval of the Borough. (See id. at 67-68). Middletown Water

must attempt to address the Borough’s comments, resolve those comments, and

thereafter distribute meeting minutes “for Approval by the [Borough].” (Id.) The

Borough then either approves of or disapproves of the minutes. (Id. at 68).

Approval of the minutes amounts to approval of the Major Capital Improvement

Conceptual Design. (Id.)

After the Major Capital Improvement Conceptual Design is approved,

Middletown Water must submit a report called a “Major Capital Improvement

Substantially Complete Design.” (Id.) This report must include “detailed,

substantially complete engineering drawings, plans, specifications and technical

documents to show the character, detail and scope of the work and services to be

performed with respect to the Major Capital Improvement.” (Id.) This report is

also subject to Borough review, comment, and approval pursuant to subsection

4.5(b)(iv), entitled “Review and Approval.” (Id. at 68-69). The approval process for

this report is similar to that applied to the Major Capital Improvement Conceptual

Design. (Id.) After receiving approval of the Major Capital Improvement

Substantially Complete Design, Middletown Water may take the necessary steps to

begin construction. (Id. at 69-70).

Section 7.1(f) allows Middletown Water to seek a “Capital Cost Recovery

Charge” for Major Capital Improvements. (Id.; see also id. at 77). A “Capital Cost

Recovery Charge” is a reimbursement and consists of: (i) the amount of principal

and debt incurred to finance the Major Capital Improvement; and (ii) the return on

equity contributed to pay capital costs associated with the Major Capital

Improvement, equal to a standardized return. (Id. at 7). To impose a Capital Cost

Recovery Charge, Middletown Water must submit a financial report regarding

implementation of the Major Capital Improvement. (Id. at 77). The report is then

reviewed by and “subject to the Approval of the [Borough].” (Id.) The Borough

may not “unreasonably condition[], delay[] or withh[o]ld” approval of Middletown

Water’s report. (Id.) Middletown Water retains “sole and absolute discretion” to

begin construction on a Major Capital Improvement before a Capital Cost Recovery

Charge is approved. (Id. at 69-70). Its decision to do so, however, “shall not alter or

amend the obligations of the Parties to agree upon and the Authority to permit the

imposition of the Capital Cost Recovery Charge for the Major Capital

Improvement.” (Id.)

B. Arbitration

Article 19 of the Concession Agreement provides that “[a]ny dispute arising

out of, relating to, or in connection with this Agreement” shall be resolved through

a combination of informal dispute resolution, mediation, and arbitration. (Id.

at 136-41). While performing under the Agreement, the parties disagreed about

whether certain capital improvements—specifically, “Water Main Replacement

Work”—qualified as Major Capital Improvements for which Capital Cost Recovery

Charges could be imposed. (Doc. 1-2 at 4). Following failed negotiations, the

parties sought arbitration. (Id. at 9). After several days of hearings, the arbitration

panel issued its final award in July 2019. (Id. at 9-16).

1. Arbitration Panel’s Final Award

As relevant here, the arbitration panel was tasked with deciding whether

“Water Main Replacement Work constitutes a Major Capital Improvement under

the terms of the Concession Agreement, and [whether] the [Middletown Water] is

entitled to impose Capital Cost Recovery Charges for Water Main Replacement

Work.” (Id. at 17). “Water Main Replacement Work” involves annual replacement

of 2,500 linear feet of water mains. (Id. at 4). The panel concluded: (a) that Water

Main Replacement Work is a Major Capital Improvement under the Concession

Agreement; and (b) that Middletown Water is entitled to impose and recover

Capital Cost Recovery Charges for Water Main Replacement Work. (Id. at 17, 22,

52). Critical here is the panel’s holding in Paragraph 1(e) of Section XII of the

award:

[Middletown Borough] is enjoined from taking any action

to oppose, frustrate, dispute, object to or interfere with

[Middletown Water’s] recovery of any Capital Cost

Recovery Charges due for the Water Main Replacement

Work it has performed or will perform in the future when

such work otherwise meets the requirements of clause

(c) of the definition of Major Capital Improvement in the

Concession Agreement.

(Id. at 52-53).

In reaching its conclusion, the panel thought the Concession Agreement’s

terms were unambiguous. (Id. at 20-22). It nonetheless supported its holding by

reference to certain extracontractual evidence confirming that Water Main

Replacement Work constitutes a Major Capital Improvement. (Id. at 22-27).

2. Arbitration Panel’s “Clarification of Award”

After the final award was issued, Middletown Borough timely filed an

application for clarification of award. (See Doc. 15-2). The Borough specifically

requested clarification of Paragraph 1(e)’s injunctive language that prohibits it from

interfering with Middletown Water’s ability to recover Capital Cost Recovery

Charges. (Doc. 15-2 at 1-2; Doc. 1-3 at 1). The panel responded in its Disposition of

Application for Clarification of Award that “the intent of its award is clear.” (Doc. 1-

3 at 1). It nonetheless stated that

Paragraph 1(e) of Section XII of the Award is not

intended to alter or modify any terms or provisions of the

Concession Agreement, and in particular, is not intended

to detract or require the Parties to deviate from either the

procedures set forth in Section 4.5 of the Concession

Agreement entitled Major Capital Improvement Project

Implementation, or the procedures set forth in Section

7.1(f) of the Concession Agreement for the imposition of a

Capital Cost Recovery Charge for Major Capital

Improvements.

(Id. at 1-2). Middletown Borough has not submitted a motion to vacate, modify, or

correct the panel’s award. (Doc. 1 ¶ 6; Doc. 15 at 12).

C. Procedural History

The underlying arbitration proceeding in this case commenced on March 20,

2018, and the panel issued its final award on July 10, 2019. Middletown Water then

filed a petition to confirm the arbitration award in this court. Middletown Borough

answered that petition and Middletown Water filed its motion for judgment on the

pleadings shortly thereafter. The motion is fully briefed and ripe for disposition.

II. Legal Standard

A motion for judgment on the pleadings is the procedural hybrid of a motion

to dismiss and a motion for summary judgment. Westport Ins. Corp. v. Black, Davis

& Shue Agency, Inc., 513 F. Supp. 2d 157, 162 (M.D. Pa. 2007). Rule 12(c) of the

Federal Rules of Civil Procedure provides: “After the pleadings are closed—but

early enough not to delay trial—a party may move for judgment on the pleadings.”

FED. R. CIV. P. 12(c). To succeed on a Rule 12(c) motion, the movant must clearly

establish that no material issue of fact remains to be resolved and that the movant

“is entitled to judgment as a matter of law.” Sikirica v. Nationwide Ins. Co., 416

F.3d 214, 220 (3d Cir. 2005); see 5C CHARLES ALAN WRIGHT ET AL., FEDERAL

PRACTICE AND PROCEDURE § 1368 (3d ed. 2015). A Rule 12(c) motion for judgment on

the pleadings is decided under a standard similar to a Rule 12(b)(6) motion to

dismiss. See Zimmerman v. Corbett, 873 F.3d 414, 417 (3d Cir. 2017). That is,

judgment on the pleadings should be granted only when, accepting as true the facts

alleged by the nonmovant and drawing “all reasonable inferences” in that party’s

favor, the movant is entitled to judgment as a matter of law. See id. (citation

omitted).

III. Discussion

In its motion for judgment on the pleadings, Middletown Water seeks

enforcement of the arbitration panel’s final award. It specifically asks that we

enjoin Middletown Borough from rejecting Capital Cost Recovery Charges for

Water Main Replacement Work. Middletown Water additionally claims that

Middletown Borough is wrongfully attempting to amend the award outside the 30-

day limitations period. Middletown Borough rejoins that it is not seeking to modify

or vacate the award but is instead also asking us to enforce it. The Borough asks

that we read the award in light of the panel’s clarification, which it argues

preserved various review and approval procedures. For the reasons described

below, we agree with the Borough.

A federal court sitting in diversity, like here, applies state substantive law.

Erie R.R. v. Tompkins, 304 U.S. 64, 78-80 (1938).2 Under Pennsylvania law, which

governs the applicable limitations period, (see Doc. 1-4 at 145), the court “shall

confirm an award” unless there is a timely motion to vacate, modify, or correct the

award, 42 PA. CONS. STAT. § 7313. A motion to vacate, modify, or correct the award

must be filed within 30 days after the award is made. Id. § 7342(b). This limitations

period applies to both common law and statutory arbitration. See Moscatiello v.

Hilliard, 939 A.2d 325, 327 (Pa. 2007) (citations omitted).

The Commonwealth’s 30-day limitations period is strictly enforced. See Serv.

Emp. Int’l Union, Local No. 36, AFL-CIO v. Office Ctr. Servs., Inc., 670 F.2d 404, 412

2 In resolving arbitration disputes, courts sitting in diversity must determine

whether the dispute is governed by the Federal Arbitration Act or state law. See

State Farm Mut. Auto. Ins. Co. v. Coviello, 233 F.3d 710, 713 n.1 (3d Cir. 2000)

(citations omitted). Federal law applies if the arbitration agreement implicates

interstate commerce. Id. (citation omitted). We need not make this determination,

however, because the parties agreed to a valid choice-of-law provision and do not

dispute that Pennsylvania law applies. (Doc. 1-4 at 145). In any event, “there is no

meaningful difference between federal and Pennsylvania law when reviewing the

scope of an arbitration clause.” Coviello, 233 F.3d at 713 n.1.

(3d Cir. 1982). The Third Circuit has explained that a defendant must raise all

“important defenses to an arbitration award . . . within the period prescribed for

actions to vacate rather than wait to raise them as defenses in a confirmation

proceeding.” Id. This rule consequently prohibits untimely defenses that

“challenge[] the underlying validity of the arbitration proceeding and award.” Id.

Middletown Borough concedes that it did not file a motion to vacate, modify, or

correct the panel’s award. (Doc. 1 ¶ 6; Doc. 7 ¶ 1).

We conclude that Middletown Borough is not required to forego the review-

and-approval processes established in the Concession Agreement and blindly

compensate Middletown Water for Water Main Replacement Work. As an initial

matter, we note that Middletown Water relies heavily on the panel’s seemingly

absolute use of the word “recovery”—specifically, its statement that the Borough “is

enjoined from taking any action to oppose, frustrate, dispute, object to or interfere

with [Middletown Water’s] recovery of any Capital Cost Recovery Charges due for

the Water Main Replacement Work.” (See generally Doc. 14). This word choice,

says Middletown Water, suggests that the panel vitiated the Borough’s right to

approve of Capital Cost Recovery Charges for Water Main Replacement Work. (See

id. at 8-9). The final award does authorize Middletown Water to recover Capital

Cost Recovery Charges for Water Main Replacement Work. (Doc. 1-2 at 52). It also

prohibits the Borough from hindering that recovery. (Id. at 52-53). But this

prohibition applies only to Capital Cost Recovery Charges that are “due” from

system customers. (Id. at 52). Under the Concession Agreement’s plain terms,

Capital Cost Recovery Charges do not become due until they have been approved

by the Borough. (See id. at 69, 77). The panel’s award was therefore not as absolute

as Middletown Water claims.

Several other reasons support this reading. First, the panel’s focus,

reasoning, and conclusion confirm that its award did not eliminate the Concession

Agreement’s review and approval provisions. The panel addressed a narrow

question: Whether “Water Main Replacement Work constitutes a Major Capital

Improvement under the terms of the Concession Agreement, and [whether]

[Middletown Water] is entitled to impose Capital Cost Recovery Charges for Water

Main Replacement Work.” (Id. at 17). The panel answered that question in the

affirmative. (Id. at 17-27). Its award focused on the threshold inquiry of whether

this type of work constitutes a Major Capital Improvement; it did not discuss the

process by which Capital Cost Recovery Charges are reviewed and approved by

Middletown Borough. As described above, Capital Cost Recovery Charges must go

through an approval process to become “due.” Supra at pp. 2-4. All this is to say

that Middletown Water is entitled to impose Capital Cost Recovery Charges, but its

ability to ultimately recover those charges is dependent upon the Borough’s

approval and charges becoming due.

Second, the panel’s clarification makes clear that its final award maintained

the Concession Agreement’s review and approval procedures. Middletown

Borough timely asked the panel to elaborate on the scope of the prohibitive

language in Paragraph 1(e) of the award. (Doc. 1-2 at 52-53; Doc. 15-3 at 1). The

panel responded in no uncertain terms: “[T]he Award is not intended to alter or

modify any terms or provisions of the Concession Agreement, and in particular, is

not intended to detract or require the Parties to deviate from either the procedures

set forth in Section 4.5 . . . or the procedures set forth in Section 7.1(f).” (Doc. 1-3

at 1-2). Those sections describe the Borough’s rights to review and approve

Middletown Water’s proposed Capital Cost Recovery Charges and associated

submissions. The panel thus preserved the process described in the Concession

Agreement.

Third, and lastly, Middletown Borough’s so-called “defense” (i.e., its different

reading of the panel’s final award) is not the sort that must be raised in a motion to

vacate, modify, or correct within 30 days. Middletown Water cites two

distinguishable cases—Service Employees International Union, Local No. 36, AFL-

CIO v. Office Center Services, Inc., 670 F.2d 404 (3d Cir. 1982), and SEIU Healthcare

Pennsylvania v. Regional Hospital of Scranton, No. 3:13-CV-02669, 2015 WL 150069

(M.D. Pa. Jan. 12, 2015)—in support of its argument that Middletown Borough is

attempting to submit a disguised motion to vacate, modify, or correct the award

beyond the permitted time period. (See Doc. 14 at 10). In both Office Center

Services and SEIU, the party opposing confirmation of the arbitration award

sought to nullify or invalidate the award after the applicable deadline. The

respondent in Office Center Services untimely attempted to bring a due process

claim, among others, to challenge the arbiters’ findings and conclusions, and

declare the arbiters’ award unenforceable. See Office Ctr. Servs., 670 F.2d at 406

n.5. The respondent in SEIU similarly tried to attack the arbiters’ award on the

theory that it was unenforceable. SEIU, 2015 WL 150069, at *11. In both cases, the

court correctly rejected the untimely requests. Middletown Borough is not

“challeng[ing] the underlying validity of the arbitration proceeding and award.”

Office Ctr. Servs., 670 F.2d at 412. It is asking us to enforce the award according to

its understanding of the award’s scope. We thus reject Middletown Water’s

argument that the Borough is advancing an improper request to vacate, modify, or

correct the panel’s award.

IV. Conclusion

We conclude that the arbitration award does not exempt Middletown Water’s

Water Main Replacement Work from the procedures described in Sections 4.5 and

7.1(f) of the Concession Agreement regarding review and approval of Capital Cost

Recovery Charges. We emphasize, however, that under the terms of those sections,

the Borough may not “unreasonably condition[], delay[] or with[o]ld” its review and

approval of the Middletown Water’s relevant submissions. (Doc. 1-4 at 77).3 For

3 We make one final point of clarification. Middletown Water asks that we

enjoin Middletown Borough from preventing its recovery of “any Capital Recovery

Charges due for any Major Capital Improvements.” (Doc. 1 at 18 (emphasis added)).

Strangely, Middletown Borough also includes this expansive language in its

proposed judgment. (Doc. 7 at 5). The final award did not make such a far-reaching

holding. It applies only to Middletown Water’s right to recover “Capital Cost

Recovery Charges due for the Water Main Replacement Work.” (Doc. 1-2 at 52).

these reasons, we will deny Middletown Water’s motion (Doc. 13) for judgment on

the pleadings. An appropriate order shall issue.

/S/ CHRISTOPHER C. CONNER

Christopher C. Conner, Chief Judge

United States District Court

Middle District of Pennsylvania

Dated: April 13, 2020

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.