Opinion

Western Watersheds Project v. Secretary of the United States Department of the Interior

Court
District Court, D. Oregon
Filed
Dec 4, 2023
Cited by
0 cases
Authority
More cited than 28.8%

discussing the circuit split on whether a district court must or may consider new evidence when reviewing de novo a magistrate judge’s findings and recommendation, and concluding that a district court “has discretion, but is not required” to consider new evidence

How later courts described this case

  • discussing the circuit split on whether a district court must or may consider new evidence when reviewing de novo a magistrate judge’s findings and recommendation, and concluding that a district court “has discretion, but is not required” to consider new evidence
  • discussing the district court’s discretion to consider new arguments raised in objections
  • rejecting the Fourth Circuit’s requirement that a district court must consider new arguments raised in objections to a magistrate judge’s findings and recommendation

Written by the judges who cited it.

The opinion

IN THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF OREGON

WESTERN WATERSHEDS PROJECT, Case No. 2:21-cv-297-HL

et al.,

ORDER

Plaintiffs,

v.

SECRETARY OF THE UNITED STATES

DEPARTMENT OF INTERIOR and

BUREAU OF LAND MANAGEMENT,

Defendants.

Michael H. Simon, District Judge.

United States Magistrate Judge Andrew Hallman issued Findings and Recommendation

(F&R) in this case on November 8, 2022. Judge Hallman recommends that this Court (1) grant

Defendants’ motion to dismiss Plaintiffs’ third claim and the portion of Plaintiffs’ first claim

related to the shortened protest period, and (2) otherwise deny Defendants’ motion to dismiss.

Both Plaintiffs and Defendants filed objections to the F&R. On November 13, 2023, the Court

requested supplemental briefing to obtain any new relevant information or evidence relating to

mootness. For the reasons discussed below, the Court adopts Judge Hallman’s F&R.

STANDARDS

Under the Federal Magistrates Act (Act), the Court may “accept, reject, or modify, in

whole or in part, the findings or recommendations made by the magistrate.” 28 U.S.C.

§ 636(b)(1). If a party objects to a magistrate judge’s findings and recommendations, “the court

shall make a de novo determination of those portions of the report or specified proposed findings

or recommendations to which objection is made.” Id.; Fed. R. Civ. P. 72(b)(3).

For those portions of a magistrate judge’s findings and recommendations to which neither

party has objected, the Act does not prescribe any standard of review. See Thomas v. Arn, 474

U.S. 140, 152 (1985) (“There is no indication that Congress, in enacting [the Act], intended to

require a district judge to review a magistrate’s report to which no objections are filed.”); United

States. v. Reyna-Tapia, 328 F.3d 1114, 1121 (9th Cir. 2003) (en banc) (holding that the court

must review de novo magistrate judge’s findings and recommendations if objection is made, “but

not otherwise”). Although in the absence of objections no review is required, the Act “does not

preclude further review by the district judge[] sua sponte . . . under a de novo or any other

standard.” Thomas, 474 U.S. at 154. Indeed, the Advisory Committee Notes to Fed. R. Civ.

P. 72(b) recommend that “[w]hen no timely objection is filed,” the Court review the magistrate

judge’s recommendations for “clear error on the face of the record.”

BACKGROUND

On January 19, 2021, on his last day in office, then-Secretary of the Interior, David

Bernhardt, issued a decision authorizing the grant of grazing permits to Hammond Ranches, Inc.

(HRI) on four allotments in southeastern Oregon. HRI had previously held grazing permits for

those allotments that BLM declined to renew after two of the ranch owner and operators were

convicted on criminal charges stemming from allegations that they intentionally set fire to public

lands. On January 2, 2019, on his last day in office, then-Secretary of the Interior Ryan Zinke

had issued a decision requiring the issuance of grazing permits to HRI on the four allotments.

This Court declared those permits in violation of the Administrative Procedure Act (APA), and

the permitting process on the subject public lands was continued by the Bureau of Land

Management (BLM). BLM conducted an environmental assessment (EA). During that process,

then-Secretary Bernhardt issued the challenged decision.

Plaintiffs, environmental organizations, filed a complaint on February 25, 2021,

challenging the decision and alleging that Defendants, the current Secretary of the Interior and

BLM, violated the Federal Land Policy and Management Act (FLPMA), the National

Environmental Policy Act (NEPA), the APA, and the Steens Mountain Cooperative Management

and Protection Act of 2000 (Steens Act) in issuing the decision. The current administration

rescinded the decision on February 26, 2021, and initiated a new environmental impact statement

(EIS) process on the project. The government moves to dismiss Plaintiffs’ claims as moot.

DISCUSSION

Judge Hallman set out the following conduct by Defendants as alleged by Plaintiffs to be

illegal:

(1) the Secretary prematurely assuming jurisdiction of the grazing

decision before it became a “case” and improperly shortening the

required protest period before issuing a final grazing decision;

(2) awarding the permit to an unqualified applicant under the Land

Policy Act because the Ranch had a record of permit violations and

other applicants did not; (3) basing the final decision on a flawed

and incomplete EA and related FONSI; (4) failing to ensure the

permit complied with applicable land use plans issued under the

Land Policy Act; and (5) issuing a permit that violates the Steens

Act by not adequately protecting the Steens Management Area and

misinterpreting the Steens Act to include an additional competing

purpose of promoting viable and sustainable grazing operations.

ECF 38 at 15 (citations omitted). Judge Hallman concluded that none of the alleged conduct was

moot under the voluntary cessation doctrine except improperly shortening the required protest

period (part of claim one) and basing the final decision on a flawed and incomplete EA and

related FONSI (claim three). Thus, Judge Hallman concluded that those claims should be

dismissed as moot and all other claims should remain.

The Government objects that these claims should also be dismissed as moot. Plaintiffs

object that claim three should not be dismissed as moot, because Defendants have not shown that

the conduct is not reasonably likely to recur. Plaintiffs also object to the Findings and

Recommendation referring to grazing “rights” rather than “privileges.”

Neither party objects to the portion of the F&R concluding that the “capable of repetition

yet evading review” exception to mootness does not apply. Nor do Plaintiffs object to Judge

Hallman’s conclusion regarding their claim one. The Court therefore reviews those portions of

the F&R for clear error. The Court finds no clear error and adopts those portions of the F&R.

The Court reviews de novo the portions of the F&R objected to by the parties.

A. New Evidence and Arguments

Both parties submit new evidence and argument to this Court that was not presented to

Judge Hallman. It is within this Court’s discretion whether to accept new evidence or argument

submitted with objections. See Jones v. Blanas, 393 F.3d 918, 935 (9th Cir. 2004) (discussing the

district court’s discretion to consider new arguments raised in objections); Brown v. Roe, 279

F.3d 742, 746 (9th Cir. 2002) (rejecting the Fourth Circuit’s requirement that a district court must

consider new arguments raised in objections to a magistrate judge’s findings and

recommendation); United States v. Howell, 231 F.3d 615, 621 (9th Cir. 2000) (discussing the

circuit split on whether a district court must or may consider new evidence when reviewing de

novo a magistrate judge’s findings and recommendation, and concluding that a district court “has

discretion, but is not required” to consider new evidence); see also 28 U.S.C. § 636(b)(1) (stating

that the district court judge “may also receive further evidence”). The Court exercises its

discretion and considers the parties’ new evidence and argument.

B. Defendants’ Objections to the F&R

1. Requirements of the Voluntary Cessation Exception

Defendants first object that the cessation of their conduct was not as a result of this

litigation and thus the voluntary cessation doctrine does not apply. Plaintiffs dispute that conduct

must cease as a result of litigation in the Ninth Circuit. Regardless of the legal requirement in

this circuit, Defendants have not shown that their voluntary conduct was wholly independent of

litigation, considering the history this case.

It is the party asserting mootness who “bears the burden to establish that a once-live case

has become moot. That burden is heavy where . . . the only conceivable basis for a finding of

mootness is [a defendant’s] voluntary conduct.” Rosebrock v. Mathis, 745 F.3d 963, 972 (9th

Cir. 2014) (quotation marks omitted). Defendants’ new evidence includes a declaration and

internal BLM records indicating that BLM employees created an information memorandum

about the allotments on February 16, 2021, and a draft recission decision on February 24, 2021.

This evidence, Defendants argue, shows that the rescission was not in response to the current

litigation, because both the memorandum and draft decision were created before Plaintiffs filed

their complaint on February 25, 2021. Defendants, however, have not submitted the information

memorandum to the Court, and the Court will not assume that the memorandum supports

Defendants’ contention. Defendants did provide a copy of the draft recission decision, which was

created one day before Plaintiffs filed their complaint. ECF 43-5.

Given the circumstances leading up to this case, however, it was readily apparent that

Plaintiffs intended to initiate litigation before they filed their complaint on February 25, 2021.

Before filing their complaint, Plaintiffs had (1) communicated in January 2021 to Defendants

their belief that the challenged decision was unlawful, (2) communicated in January 2021 to

Defendants that they reserved the right to take legal action in response to the unlawful decision,

and (3) sued Defendants over an earlier decision granting grazing privileges to HRI for the same

allotments in 2019. ECF 50-7 at 2-3; W. Watersheds Project v. Bernhardt, 428 F. Supp. 3d 327

(D. Or. 2019). Although the Court recognizes that Defendants’ proffered reasons for the

rescission—the change in administration on January 20, 2021, and the new administration’s

realization that the previous process was flawed—also likely contributed to Defendants’ choice

to rescind their earlier decision, these reasons do not establish that the rescission was

independent of the litigation.

2. Whether Defendants Show Some Conduct Is Not Reasonably Likely to Recur

Defendants next object to the portion of Judge Hallman’s F&R concluding that

Defendants have not shown that some of the challenged conduct is not reasonably likely to recur.

Defendants rely primarily on the fact that they have rescinded the challenged decision,

withdrawn the Finding of No Significant Impact, and begun to prepare a new EIS that will

“necessarily reexamine” the issues raised by Plaintiffs. ECF 43 at 11. Defendants previously

made these arguments in the briefing they submitted to Judge Hallman. ECF 21, ECF 25.

In its supplemental brief, the Government asserts that in the new EIS process, the

government has obtained new information relating to “Plaintiffs’ claims under FLPMA, the

Sage-Grouse Amendments, and the Steens Act, including new Habitat Assessment Framework

Reports for sage-grouse habitat within the Bridge Creek Area; Updated Land Health Assessment

Evaluation, and Determinations for all four allotments within the Bridge Creek Area; and new

carrying capacity analyses and use areas for each alternative evaluated.” The government argues

that through the new EIS, the government will make a new final agency decision that will be

subject to its own judicial review process, and that will be the mechanism by which Plaintiffs can

challenge Defendants’ decision if Plaintiffs disagree with it, not by a continuation of this lawsuit

challenging the previous agency decision.

The Court understands Defendants’ point that the new EIS process will result in a final

agency decision that may be subject to its own legal challenge. That, however, does not

necessarily mean that Plaintiffs’ claims in this lawsuit are moot. As Judge Hallman described,

the conduct he identified has not been disavowed in a manner demonstrating that it is not

reasonably likely to recur.

The Court agrees with the portion of the F&R finding that Defendants fail to show that “it

is absolutely clear that” the complained-of conduct related to Plaintiffs’ second, fourth, and fifth

claims for relief, as well as the conduct related to Plaintiffs’ first claim for relief other than the

shortened protest period, is “not reasonably . . . expected to recur.” W. Virginia, 142 S. Ct.

at 2607. Defendants’ new evidence similarly does not demonstrate that the challenged conduct is

unlikely to recur. Accordingly, the Court adopts the portion of the F&R concluding that

Plaintiffs’ first claim for relief—except as related to the shortened protest period—and their

second, fourth, and fifth claims for relief are not moot.

C. Plaintiffs’ Objections to the F&R

1. General Mootness Standards

Plaintiffs object to the F&R’s statement of the applicable law, arguing that it

“erroneously states the mootness doctrine applicable in this case” by incorporating case law that

addresses only standing or other doctrines. ECF 44 at 20. Plaintiffs argue that, because the

“central question[] for deciding” the motion to dismiss is whether Defendants have met their

burden under the voluntary cessation standard, Judge Hallman erred in including “General

Mootness Standards” in his F&R. Id. at 23.

Judge Hallman did not err in discussing the doctrine of standing in his general mootness

standards, as the two doctrines are interrelated. As this Court has stated, “[w]hether standing and

the other requirements for a live case or controversy exists throughout the entirety of a case is

considered under the doctrine of mootness.” Wolfe v. City of Portland, 566 F. Supp 3d 1069,

1081 (D. Or. 2021). Although this Court has also clarified that “[t]he doctrine of mootness is

more complex, however, than simply ‘standing set in a time frame’ because it has exceptions that

do not apply to standing and because there may be circumstances in which certain factors are

viewed more flexibly in considering mootness than they would be in considering standing,” id.

at 1082, it was not error to first describe the general standards of mootness, before describing the

voluntary cessation exception. Judge Hallman recognized that the voluntary cessation exception

was the “correct[] focus” for the parties’ arguments related to the motion to dismiss. The Court

adopts the portion of Judge Hallman’s F&R describing the general standards of mootness.

2. Claim Three

Plaintiffs argue that their third claim for relief, which alleges that the Secretary violated

NEPA and the APA by basing the January 19th decision on a flawed and inadequate EA, is not

moot. Although Defendants have initiated an EIS, no new NEPA analysis has yet superseded the

challenged EA. Defendants have not withdrawn the problematic EA and Allotment Management

Plan (AMP), nor have they conceded the alleged defects in these documents. The only error

Defendants have conceded is the shortened protest period before the Secretary’s January 19th

decision. By neither withdrawing nor acknowledging the flaws in the EA and AMP, Plaintiffs

argue that Defendants are “leaving the door open to issue an identical or substantially similar

decision at any time.” ECF 44 at 21.

A defendant’s admission that its conduct was unlawful weighs in favor of a finding of

mootness as to that complained-of conduct. See, e.g., Forest Guardians v. United States Forest

Service, 329 F.3d 1089, 1095 (9th Cir. 2003) (holding that defendants met the heavy burden of

showing that their voluntary conduct mooted the case where defendants admitted the challenged

conduct was unlawful, because “[i]t is unreasonable to think that the [defendant] would return to

conduct it has admitted to this court is [unlawful]”). Assurances from the government that

challenged conduct will not recur also weigh in favor of finding mootness based on voluntary

cessation. Brach, 38 F.4th at 13 (holding that voluntary cessation mooted the case, in part

because the defendant had “unequivocally renounced” the challenged conduct). The Court must

also consider, however, “whether the government’s new position ‘could be easily abandoned or

altered in the future.’” Fikre, 904 F.3d at 1038.

Regarding the EIS causing Plaintiffs’ third claim to be moot, the government has

completed public scoping and is working toward a first draft. Although initially it was estimated

that a first draft would be completed by September 2023, it is now expected to be completed in

June 2024. Despite the delay, the government has continued to expend resources and move

forward on the EIS. The Court, however, has some concerns, given the history of this case and

the delays shown thus far. Defendants have not yet completed an EIS, nor have they admitted

that it was unlawful to issue the challenged decision without completing an EIS. Defendants also

have not demonstrated that there are “procedural safeguards insulating [their decision to

complete an EIS] from arbitrary reversal.” Fikre, 904 F.3d at 1038. Thus, this claim is dismissed

without prejudice. If it appears that the government’s current course of action is going to be

“easily abandoned or altered in the future,” id., then Plaintiffs may seek leave to reassert this

claim.

Plaintiffs’ alleged NEPA violations, including failure to consider alternatives, failure to

take a “hard look” at impacts of the action, failure to analyze the alternative actually adopted,

and failure to disclose the effects of the alternative adopted, ECF 1 ¶ 135(b)-(g), will all be part

of the EIS. To the extent Plaintiffs are dissatisfied with the agency’s new final decision after it is

issued, that would be an issue for a future challenge against the EIS, unless Plaintiffs are given

leave to reassert their EA claim as discussed above.

3. The Term “Grazing Rights”

Plaintiffs object to Judge Hallman’s reference to “grazing rights” in his F&R. They ask

the Court to modify the F&R to recognize that a permit to graze livestock on public lands creates

only a regulated privilege, not a right. Defendants do not respond to this objection.

The statute authorizing grazing permits discusses “grazing privileges” and states that

such permits do not create any “rights.” 43 U.S.C. § 315b. Courts, however, including the U.S.

Supreme Court, have used the terms “grazing rights” and “grazing privileges” somewhat

interchangeably. See, e.g., Pub. Lands Council v. Babbitt, 529 U.S. 728, 735 (2000) (referring to

grazing privileges); United States v. Fuller, 409 U.S. 488, 495 (1973) (J. Powell, dissent)

(referring to grazing rights); Corrigan v. Haaland, 12 F.4th 901, 911 (9th Cir. 2021), cert.

denied, 142 S. Ct. 901 (2022) (referring to grazing privileges); United States v. Est. of Hage, 810

F.3d 712, 718 n.2 (9th Cir. 2016) (referring to grazing rights). Nonetheless, because the

government did not respond or object to this request by Plaintiffs, the Court hereby modifies the

F&R to clarify that a permit to graze livestock on public lands grants a recipient grazing

privileges and does not create any right in the lands.

CONCLUSION

The Court ADOPTS Judge Hallman’s F&R (ECF 38), as clarified and modified in this

Order. Accordingly, the Court GRANTS IN PART Defendants’ motion to dismiss (ECF 21) as

to the portion of Plaintiffs’ first claim for relief based on the shortened protest period and as to

Plaintiffs’ third claim for relief. The Court otherwise DENIES Defendants’ motion to dismiss.

IT IS SO ORDERED.

DATED this 4th day of December, 2023.

/s/ Michael H. Simon

Michael H. Simon

United States District Judge

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.