Atlas Industrial Contractors LLC v. In2Gro Technologies LLC

Court
District Court, S.D. Ohio
Filed
Mar 25, 2021
Cited by
0 cases
Authority
More cited than 28.2%

The opinion

IN THE UNITED STATES DISTRICT COURT

FOR THE SOUTHERN DISTRICT OF OHIO

EASTERN DIVISION

Atlas Industrial Contractors, LLC, :

:

Plaintiff, :

:

v. : Case No. 2:19-cv-2705

:

In2Gro Technologies, : Judge Sarah D. Morrison

: Magistrate Judge Vascura

Defendant. :

:

OPINION & ORDER

In this removed diversity action centered upon a contract dispute, Plaintiff

Atlas Industrial Contractors, LLC (“Atlas”) moves for full summary judgment on its

claims against Defendant In2Grow Technologies, LLC (“I2G”) as well as on I2G’s

counterclaims against Atlas. (ECF No. 99). I2G, in turn, moves for summary

judgment on Atlas’s claims against it. (ECF No. 83.) Additionally, each side moves

for sanctions. (ECF Nos. 102, 103.) All motions are fully briefed. (ECF Nos. 90, 98,

100, 101.) After due consideration, the Court GRANTS in part and DENIES in

part Atlas’ Motion for Summary Judgment (ECF No. 99), GRANTS in part and

DENIES in part I2G’s Motion for Summary Judgment (ECF No. 83), and DENIES

the motions for sanctions. (ECF Nos. 102, 103.)

I. BACKGROUND

A. Parties

Atlas is a Delaware limited liability company with is principal place of

business in Columbus, Ohio. I2G is a Michigan limited liability company with a

principal place of business in Michigan. Members of each are diverse.

Atlas offers commercial and industrial installation services across the

country. (ECF No. 86-4, PageID 1055.) I2G provides “end-to-end design,

installation, integration and maintenance security services for large complex high

value facilities” anywhere in the world. (ECF Nos. 13, PageID 247 at ¶ 6 and 100-1

at ¶ 4.) I2G has a contract with Amazon Web Services (“AWS”) to provide, install,

activate, and maintain security systems at AWS’s data server facility (“Facility”) in

Licking County, Ohio. (ECF No. 86-4, PageID 1059.)

B. Standby Work

Atlas began working on the Facility when it was being built. (ECF No. 86-4,

PageID 1060.) I2G became aware of Atlas after I2G later commenced working at the

site. I2G asked Atlas to provide a quote to install conduit and pull wire for the

security systems I2G was installing at the Facility. Id. Before the parties had a

contract for that work, Amazon asked I2G to ensure Atlas had employees present at

the site at all times to complete any miscellaneous work not covered by individual

contracts. Id. at 1065-6. This work was referred to as “Standby Work.” Standby

Work included, but was not limited to, “locksmithing, relocating motion sensors,

field research of conduits and electronic components, installation of various items,

and even information gathering.” (ECF No. 99, PageID 1551)(citing ECF No. 87-4,

PageID 1246-48.)

Atlas performed some Standby Work in March 2018. Atlas submitted a quote

totaling $69,999 to I2G that same month. I2G, in turn, issued a purchase order for

$69,999 to Atlas. In April 2018, I2G paid $89,999 on the purchase order. (ECF No.

87-1, PageID 1165.)

C. Master Services Agreement and Non-Standby Work

The parties executed a Master Services Agreement (“MSA”) on May 23, 2018,

with I2G as the contractor and Atlas the subcontractor. (ECF No. 2-1.) The contract

governed all projects I2G engaged in with Atlas. Id. at ¶ 1.1. It provided that all

work performed and materials supplied by Atlas must be included in written

purchase orders. The MSA also established that:

● I2G would pay Atlas for the satisfactory performance of work and

supplies contained within the purchase orders “either (1) 10 days following receipt

of payment from [AWS] or (2) Net 30 terms from date of Atlas’s invoice date.” Id. at

¶ ¶ 2.1, 2.2.

● I2G could withhold payment up to 100% of the amount of any disputed

item. Id. at ¶ 2.3.

● I2G had a “reasonable time” to secure payment from AWS for Atlas’s

work before payment was due. Id. at ¶ 2.5.

● Atlas “shall execute a Purchase Order prior to receiving payment for

its Work. Execution of a Purchase Order by [I2G] and [Atlas] is a condition

precedent to [I2G]’s obligation to make any payment to Atlas.” Id. at ¶ 3.2.

● Atlas cannot deviate from the scope of work without a prior written

change order approved by I2G. Id. at ¶ 4.3. I2G would not be responsible for “any

extra labor, materials, or equipment furnished without such written change order.”

Id.

● “If any dispute arises between [I2G] and [Atlas] involving performance

of the Work or any alleged change in the Work, [Atlas] shall notify [I2G] in the form

of a written change order proposal. [Atlas] shall not commence with the work unless

[I2G] provides a new or modified purchase order to account for the additional costs.”

Id. ¶ 10.1.

● Any dispute arising out of or related to the MSA shall first be

mediated. Id. at ¶ 11.1. “Any dispute not resolved by mediation shall be resolved

through arbitration . . . .” Id. at ¶ 11.2.

● The agreement would be governed by the substantive and procedural

laws of Michigan. Id. at ¶ 11.4.

● “This AGREEMENT constitutes the entire agreement between the

parties and supersedes and integrates all prior or contemporaneous written or oral

communications between the parties regarding the subject matter herein.” Id. at ¶

13.7.

Work performed under the MSA is referred to as “Non-Standby Work.”

D. Unpaid Invoices

Atlas issued three invoices to I2G for Standby Work in August, October, and

December 2018. (ECF Nos. 87-5, PageID 1301-18 and 99, PageID 1554.) These

invoices, which totaled $139,609.20, also included sums for other, Non-Standby

“work from Atlas not covered by another, specific purchase order.” (ECF Nos. 87-4,

PageID 1223-24 and 99, PageID 1550-51.) Each was dated after the MSA took

effect. I2G did not pay any of the invoices.

Atlas also invoiced I2G for $177,686.50 pursuant to purchase orders for Non-

Standby Work. (ECF No. 99, Page ID 1553.) I2G did not pay that sum either. Atlas

ceased working at the facility in April 2019. Id. at 1554.

E. Redesign Contract and Lien

That same month, AWS accepted bids for a Perimeter Gate Redesign Project

(“Redesign Project”) involving rebuilding entrance gates at three Columbus area

AWS sites. (ECF No. 100-1, ¶ 22.) I2G bid $9,006,393 for the three-gate project and

estimated its profit to be $3,953,796 if selected. Id.

AWS e-mailed I2G twice on June 13, 2019. One stated, “congratulations on

winning the [Redesign] project, we are in the process of authorizing funds.” (ECF

No. 100-1, PageID 1680.) The second stated that purchase orders would be issued in

the next few weeks, “at which time [I2G] will be authorized to invoice for 25% for

the total contract to start ordering parts and begin mobilization.” Id. at 1681. I2G

did not receive a purchase order for the project. (ECF No. 87-1, PageID 1175.)

Atlas initiated the instant suit the same day AWS e-mailed I2G. On June 18,

2019, Atlas filed a mechanic’s lien on the property where the Facility is located

against I2G for $297,295.70, the total for the unpaid Standby and Non-Standby

Work. (ECF No. 99-1, ¶¶ 5-7.) At the end of that month, Matt Swearingen, Atlas’s

project manager estimator, spoke with non-party Perry Moss of Plugout. (ECF No.

86-4, PageID 1053, 1094, 1096.) Plugout is another company that installs security

systems. Id. at 1094. Moss was a salesman at Plugout and a former I2G employee.

(ECF Nos. 86-4, PageID 1094-95 and 18, PageID 292.) Moss asked Swearingen to

provide pricing for installing security systems for one of AWS’s properties in

Columbus. (ECF No. 86-4, PageID 1095.) Swearingen did so.

AWS asked Swearingen for a copy of the lien on June 26, 2019, which he

provided. Id. at 1096-97. The next day, AWS informed I2G that the Redesign

Project would be re-bid as three separate projects (“Rebid Projects”). (ECF No. 87-1,

PageID 1175.) This meant that I2G lost the Redesign Project.

In July 2019, I2G bid for each of the Rebid Projects. Atlas also bid for the

Rebid Projects as both a contractor and as a subcontractor for Plugout. I2G won one

project for which it expected a profit of $352,235. (ECF No. 100-1, ¶ 26.) Plugout

won one bid with Atlas as the subcontractor. (ECF No. 87-4, PageID 1258.)

Atlas executed a release of its lien on December 6, 2019. The release was

recorded on December 23, 2019.

F. Current Litigation

Atlas asserts claims against I2G for breach of contract, unjust enrichment,

declaratory judgment, and for violation of Ohio’s Prompt-Payment Act, R.C.

4113.61. (ECF No. 2.) I2G denies all claims and asserts counterclaims for tortious

interference with business expectancies, tortious interference with a contract,

breach of contract, and civil conspiracy. (ECF Nos. 13, 18.)

II. SUMMARY JUDGMENT MOTIONS

A. Standard of Review

Under Federal Rule of Civil Procedure 56, summary judgment is proper if the

evidentiary materials in the record show that there is “no genuine dispute as to any

material fact and the movant is entitled to judgment as a matter of law.” Fed. R.

Civ. P. 56(a); see Longaberger Co. v. Kolt, 586 F.3d 459, 465 (6th Cir. 2009). The

moving party bears the burden of proving the absence of genuine issues of material

fact and its entitlement to judgment as a matter of law, which may be accomplished

by demonstrating that the nonmoving party lacks evidence to support an essential

element of its case on which it would bear the burden of proof at trial. See Celotex

Corp. v. Catrett, 477 U.S. 317, 322-23 (1986); Walton v. Ford Motor Co., 424 F.3d

481, 485 (6th Cir. 2005).

The “mere existence of some alleged factual dispute between the parties will

not defeat an otherwise properly supported motion for summary judgment; the

requirement is that there be no genuine issue of material fact.” Anderson v. Liberty

Lobby, Inc., 477 U.S. 242, 247-48 (1986) (emphasis in original); see also

Longaberger, 586 F.3d at 465. “Only disputed material facts, those ‘that might affect

the outcome of the suit under the governing law,’ will preclude summary judgment.”

Daugherty v. Sajar Plastics, Inc., 544 F.3d 696, 702 (6th Cir. 2008) (quoting

Anderson, 477 U.S. at 248). Accordingly, the nonmoving party must present

“significant probative evidence” to demonstrate that “there is [more than] some

metaphysical doubt as to the material facts.” Moore v. Philip Morris Cos., Inc., 8

F.3d 335, 340 (6th Cir. 1993).

A district court considering a motion for summary judgment may not weigh

evidence or make credibility determinations. Daugherty, 544 F.3d at 702; Adams v.

Metiva, 31 F.3d 375, 379 (6th Cir. 1994). Rather, in reviewing a motion for

summary judgment, a court must determine whether “the evidence presents a

sufficient disagreement to require submission to a jury or whether it is so one-sided

that one party must prevail as a matter of law.” Anderson, 477 U.S. at 251-52. The

evidence, all facts, and any inferences that may permissibly be drawn from the facts

must be viewed in the light most favorable to the nonmoving party. Matsushita

Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587 (1986); Eastman Kodak

Co. v. Image Technical Servs., Inc., 504 U.S. 451, 456 (1992). However, “[t]he mere

existence of a scintilla of evidence in support of the plaintiff’s position will be

insufficient; there must be evidence on which the jury could reasonably find for the

plaintiff.” Anderson, 477 U.S. at 252; see Dominguez v. Corr. Med. Servs., 555 F.3d

543, 549 (6th Cir. 2009).

B. Preliminary Matters

Two issues ignored by the parties but addressed by the MSA deserve

mention—arbitration and choice of law.

1. Arbitration

As noted, the MSA has several dispute resolution provisions. Paragraph 11.1,

titled “Mediation,” states “in the event of any dispute arising out of or related to this

AGREEMENT, subsequent purchase order or [Atlas’s] work, [I2G] and [Atlas]

hereby agree to resolve any such dispute first through internal mediation.” (ECF

No. 2-1, PageID 81, ¶ 11.1.) In turn, Paragraph 11.2, titled “Arbitration,” provides

that I2G and Atlas “each acknowledge and agree that any dispute not resolved by

mediation shall be resolved through arbitration administered by the American

Arbitration Association under its Construction Industry Arbitration Rules . . . .” Id.

at ¶ 11.2 (emphasis added). Hence, arbitration about any dispute related to the

MSA is mandatory if mediation fails.

Atlas seeks recovery for work performed at the facility pursuant to the MSA.

Thus, the Complaint clearly pertains to a dispute “arising out of or related to the”

MSA. Neither side indicates whether mediation took place prior to Atlas’s filing of

this suit. But mediation did occur thereafter and was unsuccessful. (ECF No. 84.)

Hence, the MSA’s plain language requires the parties to arbitrate.

Yet, neither side moved to enforce the arbitration provision. While “there is a

strong presumption in favor of enforcing arbitration rights,” O.J. Distrib., Inc. v.

Hornell Brewing Co., 340 F.3d 345, 357 (6th Cir. 2003), “an agreement to arbitrate

may be waived by the actions of a party which are completely inconsistent with any

reliance thereon.” Germany v. River Terminal Ry. Co., 477 F.2d 546, 547 (6th Cir.

1973) (per curiam).

The Court determines that Atlas waived the arbitration provision by filing

the instant suit and that I2G did the same by failing to move to enforce the section.

See O.J. Distrib., Inc., 340 F.3d at 361 (Batchelder, J.)(dissenting)(“The obligation

on the part of the defendant to demand arbitration arises once the defendant is

faced with a properly filed claim.”). Furthermore, the MSA contains a waiver

provision. It states:

all remedies contained in this AGREEMENT are

cumulative and any one remedy is not intended to be in

lieu of any other legal right or remedy afforded [I2G] for

any breach or default of this AGREEMENT. [I2G’s]

failure to enforce in a timely manner any of the remedies

contained in this AGREEMENT shall not act as a waiver

to enforcement of any such remedies, or any other

remedies, at a later date.

Under these circumstances, the Court determines that both sides have waived the

arbitration provision and consideration of the instant motions is proper.

2. Choice of Law

This is a diversity case. As such, “[u]nder the Erie doctrine, federal courts

sitting in diversity apply the substantive law of the forum state and federal

procedural law.” Biegas v. Quickway Carriers, Inc., 573 F.3d 365, 374 (6th Cir.

2009)(citing Erie R. Co. v. Tompkins, 304 U.S. 64 (1938)). But the MSA’s choice of

law provision states that Michigan law, substantive and procedural, will govern any

disputes arising out of or related to the MSA. (ECF No. 2-1, PageID 82, ¶ 11.4).

The choice-of-law rules of Ohio, as the forum state, govern the determination

of whether to enforce the MSA’s selection of Michigan law. Wallace Hardware Co. v.

Abrams, 223 F.3d 382, 391 (6th Cir. 2000). Ohio requires the presence of conflict

before engaging in any choice of law analysis. Akro-Plastics v. Drake Indus., 685

N.E.2d 246, 248 (11th Dist. 1996). “If the two states would use the same rule of law

or would otherwise reach the same result, it is unnecessary to make a choice of law

determination because there is no conflict of law.” Mecanique C.N.C., Inc. v. Durr

Envtl., Inc., 304 F. Supp. 2d 971, 975 (S.D. Ohio 2004)(Marbley, J.). Typically, the

party seeking application of the law of a foreign jurisdiction bears the burden of

establishing conflict. Id. Should it fail to sustain its burden, Ohio law applies. Gouge

v. BAX Global, Inc., 252 F. Supp. 2d 509, 521 (N.D. Ohio 2003)(citation omitted).

Again, both parties fail to address this issue. The Court will not analyze

against itself. Because: (1) the general rule is that the law of the forum shall apply;

(2) both sides utilize Ohio law; and (3) neither side argues for application of

Michigan law, the Court determines that the parties have waived the MSA’s choice

of law provision. Ohio substantive law and federal procedural law will apply to the

Court’s analysis.

C. Summary Judgment Analysis

1. Breach of Contract

Each side sues the other for breach of contract, and each side moves for

judgment on the other’s breach count.

a. Framework

To recover for breach of contract under Ohio law, a breach plaintiff must

prove “the existence of a contract, performance by the plaintiff, breach by the

defendant, and damage or loss to the plaintiff.” Powell v. Grant Med. Ctr., 148 Ohio

App.3d 1, 10, 771 N.E.2d 874 (10th Dist. 2002)(quotation and citation omitted).

Both parties focus on the breach element. “A party breaches a contract if he fails to

perform according to the terms of the contract or acts in a manner that is contrary

to its provisions.” Savedoff v. Access Grp., Inc., 524 F.3d 754, 762 (6th Cir.

2008)(citation omitted).

“A court’s primary objective in interpreting a written contract is to ascertain

the intent of the parties as expressed in the terms of the agreement.” Aero

Fulfillment Servs. Corp. v. Oracle Corp., 186 F. Supp. 3d 764, 771 (S.D. Ohio

2016)(citation and quotation omitted). “Generally, contracts should be construed in

a manner to give effect to the intentions of the parties.” Hamilton Ins. Servs. v.

Nationwide Ins. Cos., 86 Ohio St. 3d 270, 273, 714 N.E.2d 898, 900 (1999). “If a

contract is clear and unambiguous, then its interpretation is a matter of law and

there is no issue of fact to be determined.” Inland Refuse Transfer Co. v. Browning-

Ferris Indus. of Ohio, Inc., 15 Ohio St. 3d 321, 322, 74 N.E.2d 271, 272 (1984).

b. Atlas’s Breach of Contract Count

Although Atlas’s Complaint seemingly asserts a claim for breach of contract

for the Standby Work, Atlas’s filings establish that this count is limited to the Non-

Standby Work. See ECF No. 99, PageID 1567-8. Specifically, Atlas alleges that it

performed work after the MSA was executed pursuant to valid purchase orders

under the MSA in the total amount of $177,686.50 and that I2G breached the MSA

by failing to pay Atlas that sum. (ECF No. 99, PageID 1566.)

I2G concedes that Atlas performed the Non-Standby work. I2G admits that

the work was performed pursuant to purchase orders in accordance with the MSA.

I2G concedes that it did not pay the invoiced amount. I2G does not contest the sum

being sought. Under these facts, I2G’s non-payment for the Non-Standby Work

certainly equates to a failure perform according to the terms of the MSA.

Regardless, I2G argues its non-performance was excused because Atlas

breached the MSA first by issuing invoices for Standby Work performed without

purchase orders after the MSA. (ECF No. 83, PageID 926.) “When one party fails to

perform [its] duties under the contract, without legal excuse, he has breached the

contract, and the duties of the non-breaching party are suspended.” Violante v.

Quadland Corp., 1997 Ohio App. LEXIS 3672, at *15 (11th Dist. Aug.

15, 1997)(citation omitted). In essence, I2G raises an affirmative defense of prior

material breach of contract in response to Atlas’s breach of contract count. (ECF No.

13, PageID 245, ¶ 2.) See also Olentangy Condo. Ass’n v. Lusk, 10th Dist. Franklin

No. 09AP-568, 2010-Ohio-1023, ¶ 29 (describing appellant’s defense of breach of

contract as an affirmative defense).

Affirmative defenses “represent a substantive or independent matter which

the defendant claims exempts him from liability even if it is conceded that the facts

claimed by the [plaintiff] are true . . . .” State v. Poole, 33 Ohio St. 2d 18, 19, 294

N.E.2d 888, 889 (1973). “[T]he burden of proving an affirmative defense rests with

the party raising the defense.” Nationstar Mortg., LLC v. Mielcarek, 9th Dist.

Lorain No. 15CA10748, 2016-Ohio-60, ¶ 11. So, I2G has the burden of proving that

Atlas breached the MSA by billing for the Standby Work performed after the MSA’s

execution.

Atlas’s alleged breach must be material to excuse I2G’s non-performance.

A failure to perform a promise that is nominal, trifling,

technical, or slight does not excuse performance under the

contract by the nonbreaching party. In other words, [a]

breach of a portion of the terms of a contract does not

discharge the obligations of the parties to the contract,

unless performance of those terms is essential to the

purpose of the agreement.

H&H Glass, Inc. v. Empire Bldg. Co., LLC, 1st Dist. Hamilton Nos. C-150059, C-

150227, 2016-Ohio-3029, ¶ 7 (internal quotations and citations omitted). “Whether a

party’s failure was ‘essential to the purpose’ of the agreement-meaning whether a

breach was ‘material’—is a question of fact.” Id. (quoting O’Brien v. Ohio State

Univ., 10th Dist. Franklin No. 06AP-946, 2007-Ohio-4833, ¶11). This involves “an

examination of the parties’ injuries, whether and how much the injured parties

would or could have been compensated, and whether the parties acted in good

faith.” O’Brien, 2007-Ohio-4833, ¶11.

Despite having the burden of proof to show that Atlas’s post-MSA billing for

Standby Work was a material breach of the MSA, I2G fails to discuss this

requirement. Simply calling Atlas’s conduct a “material breach” does not make it so.

The Court will not perform I2G’s job. Because I2G fails to fulfill its burden of proof,

its affirmative defense is insufficient to excuse I2G’s admitted non-payment for the

Non-Standby invoices and its motion for summary judgment on this count is

DENIED. (ECF No. 18.) Furthermore, Atlas has established that there is no

genuine dispute of material fact as to all material elements of its breach claim. So,

the Court GRANTS Atlas summary judgment on its breach of contract claim for

Non-Standby Work in the amount of $177,686.50. (ECF No. 99, PageID 1566.)

Perhaps anticipating this result, I2G says that Atlas failed to mitigate its

damages by refusing “to accept payment for non-Standby PO invoices prior to

initiating this action.” (ECF No. 83, PageID 921.) It makes no argument and

provides no evidence in support of this statement. Rule 408 provides “[e]vidence of

the following is not admissible—on behalf of any party—either to prove or disprove

the validity or amount of a disputed claim . . . : (1) furnishing, promising, or

offering—or accepting, promising to accept, or offering to accept—a valuable

consideration in compromising or attempting to compromise the claim; . . . .” I2G’s

cited deposition testimony in support of its failure to mitigate contention is less

than clear as to who made the offer, to whom the offer was made, when the offer

was made, and whether the offer is an inadmissible offer to compromise under Fed.

R. Evid. 408. (ECF No. 86-2, PageID 1004.) The cites to not establish a failure to

mitigate damages. For this reason, the Court finds I2G’s failure to mitigate

argument unavailing.

c. I2G’s Breach of Contract Counterclaim

I2G asserts that Atlas breached the MSA by issuing the invoices for the

Standby Work and by not returning I2G’s $20,000 overpayment on the original

$69,999 Standby Work invoice. (ECF No. 13, PageID 252, ¶¶ 47-51.) Atlas argues no

breach occurred such that judgment in its favor on this count is proper. (ECF Nos.

99, PageID 1565.)

I2G, as the party asserting breach, must prove that Atlas’s post-MSA

issuance of the Standby Work invoices was a material breach of the MSA. H&H

Glass, Inc., 2016-Ohio-3029, ¶ 7 (internal quotations and citations omitted). I2G

makes no effort to satisfy this burden. Moreover, I2G fails to develop its

overpayment argument.

The Court will not fill those voids. I2G fails to sustain its Fed. R. Civ. P. 56

burden in response to Atlas’s properly argued Motion for Summary Judgment on

I2G’s breach of contract counterclaim. Accordingly, the Court GRANTS Atlas’s

motion for judgment on this count. (ECF No. 99.) This holding negates the need to

address Atlas’s alternative double-recovery argument. Id. at 1558-59.

2. Prompt-Payment Act

Both sides move for judgment on Atlas’s Prompt-Payment Act claim. For this

count, Atlas asserts that I2G’s failure to pay for the Non-Standby work entitles

Atlas to damages available under R.C. 4113.61. (ECF Nos. 2, PageID 68, ¶¶ 36-40

and 90, PageID 1324 and 99, PageID 1566.) I2G counters that Atlas’s inability to

establish that AWS paid I2G for the specific Non-Standby Work in focus and Atlas’s

refusal to accept payment from I2G for the Non-Standby Work warrant judgment in

I2G’s favor for this count. (ECF Nos. 83, PageID 915, 928 and 98, PageID 1525 and

100, PageID 1633.)

The Prompt-Payment Act “essentially requires a contractor to timely pay its

subcontractor or materialmen undisputed amounts under a contract and sets forth

penalties for noncompliance.” Masiongale Elec.-Mech., Inc. v. Constr. One, Inc., 102

Ohio St. 3d 1, 3, 2004-Ohio-1748, ¶ 10. Revised Code § 4113.61(A)(1) provides:

(A) (1) If a subcontractor or material supplier submits an

application or request for payment or an invoice for

materials to a contractor in sufficient time to allow the

contractor to include the application, request, or invoice in

the contractor’s own pay request submitted to an owner,

the contractor, within ten calendar days after receipt of

payment from the owner for improvements to property,

shall pay to the:

(a) Subcontractor, an amount that is equal to the

percentage of completion of the subcontractor’s contract

allowed by the owner for the amount of labor or work

performed;

(b) Material supplier, an amount that is equal to all or

that portion of the invoice for materials which represents

the materials furnished by the material supplier.

The contractor may reduce the amount paid by any

retainage provision contained in the contract, invoice, or

purchase order between the contractor and the

subcontractor or material supplier, and may withhold

amounts that may be necessary to resolve disputed liens

or claims involving the work or labor performed or

material furnished by the subcontractor or material

supplier.

If the contractor fails to comply with division (A)(1)

of this section, the contractor shall pay the subcontractor

or material supplier, in addition to the payment due,

interest in the amount of eighteen per cent per annum of

the payment due, beginning on the eleventh day following

the receipt of payment from the owner and ending on the

date of full payment of the payment due plus interest to

the subcontractor or material supplier.

To summarize, the Prompt-Payment Act establishes that “if a subcontractor makes

a timely request for payment, a contractor must pay the subcontractor in proportion

to the work completed within ten calendar days of receiving payment from the

owner.” Masiongale Elec.-Mech., Inc., 102 Ohio St. 3d at 4. The Act enables a

contractor to withhold amounts disputed about “work or labor performed or

material furnished by the subcontractor.” R.C. § 4113.61(A).

“A subcontractor also may file a civil action to recover the amount due and

the statutory interest.” Masiongale Elec.-Mech., Inc. 102 Ohio St. 3d at 4 (citing R.C.

4113.61(B)(1)). If the contractor violates the Act, the subcontractor is entitled to

eighteen percent interest per annum plus reasonable attorney’s fees and court costs

incurred in pursuing the claim. R.C. § § 4113.61(B)(1) and (B)(3).

There is no dispute about the work performed or materials provided by Atlas

for the Non-Standby Work. There is no dispute about the total due for those

services. Instead, I2G argues that, under the Prompt Pay Act, it does not have to

pay Atlas for the Non-Standby Work because AWS has not paid I2G for the Non-

Standby Work. Atlas does not contest I2G’s interpretation of the statute to the

effect that AWS must pay I2G for the Non-Standby Work before I2G becomes

obligated to pay Atlas. So the issue is whether Atlas has proven that AWS paid I2G

for the Non-Standby Work.

Atlas points to invoices I2G sent to AWS that are marked “paid” as proof that

AWS paid I2G for the Non-Standby Work. (ECF No. 97.) Atlas states those invoices

total $1,811,961.45 and intones that because that sum is greater than the

undisputed Non-Standby Work total of $177,686.50, AWS has paid I2G for the Non-

Standby Work. (ECF No. 90, PageID 1321.) However, the invoices are generic in

nature and do not specify that they are for the Non-Standby Work. Additionally,

some of the invoices pre-date the MSA. Moreover, Matthew Van Haaren, I2G’s

President, testified that AWS has not paid I2G for all of the Non-Standby Work.

(ECF No. 86-2, PageID 997, 1003.) Atlas does not respond to any of these points or

provide any evidence as to what Non-Standby Work was paid to I2G.

Consequently, Atlas fails to satisfy its Rule 56 burden as to whether AWS

paid I2G for the Non-Standby Work. I2G’s properly supported Motion for Summary

Judgment (ECF No. 83) on Atlas’s Prompt-Payment Act claim is GRANTED and

Atlas’s Motion for Summary Judgment (ECF No. 99) on the same claim is

DENIED. Discussion of I2G’s additional argument that this claim is subject to

judgment on equitable grounds is unnecessary.

3. Unjust Enrichment

Atlas’s unjust enrichment argument is limited to the Standby Work. (ECF

Nos. 90, PageID 1320 and 99, PageID 1568.) Both parties seek judgment on this

count.

Atlas must prove three elements to prevail on this claim: “(1) [a] benefit

conferred by a plaintiff upon a defendant; (2) knowledge by the defendant of the

benefit; and (3) retention of the benefit by the defendant under circumstances where

it would be unjust to do so without payment.” Hambleton v. R.G. Barry Corp., 12

Ohio St. 3d 179, 183, 465 N.E.2d 1298 (1984). Recovery under this theory is

precluded, however, if an express contract between the parties covering the same

subject exists. Ruggles v. Bulkmatic Transp. Co., No. C2-03-617, 2004 U.S. Dist.

LEXIS 30588, at *15 (S.D. Ohio June 23, 2004)(Graham, J.)(citing cases). It is under

that exception that I2G seeks judgment.

The parties dispute whether the MSA covers the Standby Work. Arguing in

the affirmative is I2G. Pursuing the negative, Atlas counters that the parties had

no written contract covering the Standby Work. (ECF No. 99, PageID 1568.)

The Court concludes that the MSA covers the Standby Work. The Standby

Work pertained to work at the Facility. The MSA states that it serves “as a master

agreement for all projects for which [I2G] may engage [Atlas].” (ECF No. 2-1,

PageID 72, ¶ 1.1)(emphasis added).) The contract provides “the parties agree that

this AGREEMENT, without further acknowledgement, signature, or agreement will

govern all projects for [sic] unless a separate project specific contract is issued by

[I2G].” Id. Importantly, the MSA includes an integration clause. That clause

pertinently provides:

This AGREEMENT constitutes the entire agreement

between the parties and supersedes and integrates all

prior or contemporaneous written or oral communications

between the parties regarding the subject matter herein.

Any additions, amendments, modifications, deletions,

additions or changes to this AGREEMENT shall be made

in writing and shall not be binding unless the same are

signed by a duly authorized representative of each party.

Id. ¶ 13.7 (emphasis added). From this, it is clear that the MSA governs the

Standby Work performed after the MSA’s execution. Atlas concedes as much by not

addressing the integration clause.

Because the MSA covers the post-MSA Standby Work, Atlas’s unjust

enrichment claim fails under Ruggles. The Court GRANTS I2G’s Motion for

Summary Judgment (ECF No. 83) on this count and DENIES Atlas’s motion (ECF

No. 99) on this count.

4. Declaratory Judgment

Atlas seeks a declaratory judgment that “Atlas and [I2G] entered into a

binding agreement for the Standby Work and [I2G] breached that agreement by

failing to pay Atlas.” (ECF No. 99, PageID 1568.) I2G moves for judgment on this

count, but Atlas fails to respond or to even address the claim in sufficient detail

anywhere in its briefings.

“‘When a plaintiff asserts a claim in a complaint but then fails to delineate

that claim in [its] brief in opposition to summary judgment, that claim is deemed

abandoned.’” Chic Promotions, Inc. v. Jewelers Mut. Ins. Co., No. 1:07cv417, 2009

U.S. Dist. LEXIS 87930, at *5-6 (S.D. Ohio Sep. 24, 2009)(Barrett, J.)(quoting

E.E.O.C. v. Home Depot U.S.A., Inc., No. 4:07CV0143, 2009 U.S. Dist. LEXIS 11596,

2009 WL 395835, *17 (N.D. Ohio Feb. 17, 2009)). Consequently, I2G’s Motion for

Summary Judgment on Atlas’s declaratory judgment count is GRANTED. (ECF

No. 83.)

5. Remaining Counterclaims

I2G additionally asserts counterclaims for tortious interference with contract,

“tortious interference with business expectancies,” and civil conspiracy. (ECF No.

18, PageID 298-300.) Atlas seeks judgment on each. (ECF No. 99.)

a. Tortious Interference

“Courts frequently use common language when discussing what are actually

two distinct claims, tortious interference with business relationships and tortious

interference with contract rights.” Franklin Tractor Sales v. New Holland N. Am.,

106 F. App’x 342, 344 n.1 (6th Cir. 2004). “They differ only in that the former tort

does not require proof of a contractual relationship.” Super Sulky, Inc. v. United

States Trotting Ass’n, 174 F.3d 733, 741 (6th Cir. 1999).

i. Tortious Interference with Contract

I2G alleges that Atlas tortiously interfered with I2G’s Redesign Contract

with AWS by (1) filing the lien and (2) e-mailing AWS after the lien was filed to ask

if AWS had paid I2G for Atlas’s Non-Standby work. (ECF No. 100, PageID 1622-23.)

Atlas asserts judgment in its favor is proper on this count because I2G never had a

contract with AWS for the Redesign work. (ECF No. 99, PageID 1563.)

Tortious interference with a contract requires proof of the following elements:

(1) the existence of a contract; (2) the wrongdoer’s knowledge of the contract; (3) the

wrongdoer’s intentional procurement of the contract’s breach; (4) lack of

justification or privilege; and (5) resulting damages. See Fred Siegel Co. v. Arter &

Hadden, 85 Ohio St. 3d 171, 171-72, 707 N.E.2d 853, 855 (1999); Kenty v.

Transamerica Premium Ins. Co., 72 Ohio St. 3d 415, 416, 650 N.E. 2d 863, 864

(1995). Here, the dispute centers upon the existence of a contract aspect.

Atlas maintains that I2G did not have a contract for the Redesign work

because AWS’s June 2019 e-mails to I2G about the Redesign work “lack[] sufficient

terms to constitute an enforceable contract” and because AWS never sent, and I2G

never received, a purchase order for the Redesign Contract. (ECF No. 99, PageID

1563.) Hence, according to Atlas, because the alleged Redesign Contract lacks

essential terms, I2G cannot establish the first element of its claim for tortious

interference with a contract. Id.

I2G responds that its course of dealing with Amazon included e-mail

notifications from AWS when I2G won project bids for AWS’s projects. Van Haaren

describes how AWS notified I2G of bids awarded to I2G as follows:

a. AWS issues a Request for Proposal (RFP) and invites

companies to bid on a particular project.

b. I2G submits a bid on any RFP that falls into its

business scope.

c. If I2G wins the bid, Amazon issues an e-mail notifying

I2G of the winning bid. This serves as AWS’ authorization

for work.

d. A few days to two week later, AWS issues a PO.

e. Prior to the issuance of the formal PO, I2G begins

mobilizing in order to begin working promptly when the

PO is formally issued.

f. I2G submits invoices to AWS as work is completed.

(ECF No. 100-1, PageID 1638, ¶ 11.)

I2G’s response misconstrues Atlas’s argument. Atlas does not contest

acceptance. Instead, Atlas takes issue with the essential elements of the purported

contract being missing. Its approach is successful. Acceptance is but one element of

contract formation; I2G’s failure to establish the others is fatal to its claim. “To

prove the existence of a contract, a party must establish the essential elements of a

contract: an offer, an acceptance, a meeting of the minds, an exchange of

consideration, and certainty as to the essential terms of the contract.” Nilavar v.

Osborn, 127 Ohio App. 3d 1, 11, 711 N.E.2d 726 (1998). “In order to declare the

existence of a contract, both parties to the contract must consent to its terms * * *;

there must be a meeting of the minds of both parties * * *; and the contract must be

definite and certain.” Episcopal Retirement Homes, Inc. v. Ohio Dept. of Indus.

Relations, 61 Ohio St. 3d 366, 369, 575 N.E.2d 134 (1991).

Hence, I2G fails to prove, at a minimum, any exchange of consideration or

certainty as to the essential terms of any contract with AWS for the Redesign work

and the Court GRANTS Atlas’s Motion for Summary Judgment on I2G’s tortious

interference with contract counterclaim. (ECF No. 99.)

ii. Tortious Interference with a Business Relationship

I2G properly re-frames its tortious interference with a business expectancy

counterclaim as one for tortious interference with a business relationship in its

opposition to Atlas’s Motion for Summary Judgment. (ECF No. 100, PageID 1624.)

I2G argues that Atlas tortiously interfered with I2G’s relationship with Amazon by

filing the lien and by inquiring with Amazon about payment for Atlas’s Non-

Standby work. Id., PageID 1622-23. Atlas seeks judgment on this claim.

Elements for this count mimic those of tortious interference with contract,

but this tort “occurs when the result of the improper interference is not a breach of

contract, but the refusal of a third party to enter into or continue a business

relationship with the plaintiff.” Franklin Tractor Sales v. New Holland N. Am., 106

F. App’x 342, 344 n.1 (6th Cir. 2004)(citing A & B-Abell Elevator Co. v.

Columbus/Cent. Ohio Bldg. & Constr. Trades Council, 73 Ohio St. 3d 1, 14, 651

N.E.2d 1283, 1294 (1995)).

“‘A tortious interference action . . . requires a showing that [the defendant’s]

actions induced or caused a third party to discontinue a business relationship with

[the plaintiff].’” Wilkey v. Hull, 366 F. App’x 634, 638 (6th Cir. 2010)(quoting Smith

v. Ameriflora 1992, Inc., 96 Ohio App. 3d 179, 644 N.E.2d 1038, 1044 (Ohio Ct. App.

10th Dist. 1994)). As Atlas correctly contends, the Rebid Contract happened after

the lien was filed and the e-mail was sent. (ECF No. 100, PageID 1625.) I2G admits

that it did get one of the Rebid Contracts and that its business relationship with

AWS continues through other projects. (ECF No. 87-1, Page ID 1177.) Thus, Atlas

did not improperly interfere with I2G’s business relationship by filing the lien or by

corresponding with AWS about payment for Atlas’s services. Atlas’s Motion for

Summary Judgment on I2G’s tortious interference with business relationship

counterclaim is GRANTED. (ECF No. 99.)

b. Civil Conspiracy

Lastly, I2G asserts that Atlas engaged in a civil conspiracy with non-parties

Plugout and Moss to harm I2G’s business relationships with AWS. (ECF No. 18,

PageID 300, ¶ 78.) Atlas argues this counterclaim is subject to judgment because

I2G fails to prove that Atlas committed an underlying unlawful act. (ECF No. 99,

PageID 1564-65.)

“An underlying unlawful act is required before a civil conspiracy claim can

succeed.” Williams v. Aetna Fin. Co., 83 Ohio St. 3d 464, 475, 700 N.E.2d 859, 868

(1998). I2G predicates this counterclaim on Atlas’s alleged tortious interference

with I2G’s business relationship with AWS and on Atlas’s alleged interference with

I2G’s purported Redesign Contract with AWS. (ECF Nos. 18, PageID 300, ¶ 78 and

100, PageID 1629.) Because the Court grants summary judgment in favor of Atlas

on both of I2G’s tortious interference claims, I2G’s civil conspiracy claim necessarily

fails. Atlas’s Motion for Summary Judgment on I2G’s civil conspiracy claim is

GRANTED. (ECF No. 99.)

III. MOTIONS FOR SANCTIONS

The final dispute before the Court involves each party’s request for sanctions

against the other. (ECF Nos. 102, 103.) Both requests are denied.

A. Atlas’s Motion for Sanctions

Atlas seeks an order of sanctions against I2G, its counsel, and counsel’s law

firm pursuant to 28 U.S.C. § 1927 and Fed. R. Civ. P. 11(b). (ECF No. 102, PageID

1800.) Atlas also wants its attorney’s fees, costs and expenses “incurred in

responding to the [sic] and defending against the Counterclaim and Amended

Counterclaim,” as well any other relief that the Court deems just. Id., PageID 1813.

Section 1927 states:

[a]ny attorney or other person admitted to conduct cases

in any court of the United States or any Territory thereof

who so multiplies the proceedings in any case

unreasonably and vexatiously may be required by the

court to satisfy personally the excess costs, expenses, and

attorneys’ fees reasonably incurred because of such

conduct.

28 U.S.C. § 1927. Rule 11(b) declares:

(b) Representations to the Court. By presenting to the

court a pleading, written motion, or other paper—whether

by signing, filing, submitting, or later advocating it—an

attorney or unrepresented party certifies that to the best

of the person’s knowledge, information, and belief, formed

after an inquiry reasonable under the circumstances:

(1) it is not being presented for any improper purpose,

such as to harass, cause unnecessary delay, or needlessly

increase the cost of litigation;

(2) the claims, defenses, and other legal contentions are

warranted by existing law or by a nonfrivolous argument

for extending, modifying, or reversing existing law or for

establishing new law;

(3) the factual contentions have evidentiary support or, if

specifically so identified, will likely have evidentiary

support after a reasonable opportunity for further

investigation or discovery; and

(4) the denials of factual contentions are warranted on the

evidence or, if specifically so identified, are reasonably

based on belief or a lack of information.

Atlas focuses on Rule 11. According to the Sixth Circuit, Rule 11 sanctions are

proper if “a reasonable inquiry discloses the pleading, motion, or paper is (1) not

well grounded in fact, (2) not warranted by existing law or a good faith argument for

the extension, modification or reversal of existing law, or (3) interposed for any

improper purpose such as harassment or delay.” Herron v. Jupiter Transp. Co., 858

F.2d 332, 335 (6th Cir. 1988)(quotation and citation omitted). “Rule 11 motions are

measured against an objective standard of reasonableness under the

circumstances.” Gibson v. Solideal USA, Inc., 489 F. App’x 24, 29 (6th Cir.

2012)(quotation and citation omitted).

Atlas argues that I2G violated Rule 11(b) by asserting its “meritless”

counterclaims and by seeking recovery for same despite having already recovered a

judgment in another lawsuit “for the exact same harm [I2G] claims Atlas caused by

filing” the lien. (ECF No. 102, PageID 1801.) Sanctions under Rule11(c) are

therefore warranted, Atlas continues.

Atlas’s present contentions are nothing more than a repeat of its arguments

supporting its own Motion for Summary Judgment and opposing I2G’s Motion for

Summary Judgment. Having conducted a reasonable inquiry of those contentions,

the Court determines that none of the Herron grounds for assessing sanctions are

present. I2G’s pursuing its counterclaims is not so objectively unreasonable as to

require a sanctions award here. Atlas’s Motion for Sanctions (ECF No. 102) is

DENIED.

B. I2G’s Request for Sanctions

I2G argues that Atlas’s Motion for Sanctions is baseless such that the Court

should award I2G its attorney’s fees and expenses in opposing it. (ECF No. 103.)

Rule 11 requires that “[a] motion for sanctions must be made separately from any

other motion and must describe the specific conduct that allegedly violates Rule

11(b).” Fed R. Civ. P. 11(c)(2). I2G pursues sanctions via its opposition, not a

motion. Accordingly, I2G does not meet the procedural requirements that justify

consideration of its request. See Wayne Watson Enters., LLC v. City of Cambridge,

No. 2:15-CV-02679, 2018 U.S. Dist. LEXIS 54785, at *8-9 (S.D. Ohio Mar. 30,

2018)(Marbley, J.). I2G’s request for sanctions is DENIED. (ECF No. 103.)

IV. CONCLUSION

Atlas’s Motion for Summary Judgment (ECF No. 99) is GRANTED in part

and DENIED in part.

Judgment shall be entered in Atlas’s favor for its breach of contract claim for

the Non-Standby Work in the amount of $177,686.50.

Judgment shall be entered in Atlas’s favor for all of I2G’s counterclaims.

I2G’s Motion for Summary Judgment (ECF No. 83) is GRANTED in part and

DENIED in part.

Judgment shall be entered in favor of I2G on Atlas’s Prompt-Payment Act,

unjust enrichment, and declaratory judgment claims.

Atlas’s Motion for Sanctions (ECF No. 102) is DENIED.

I2G’s request for sanctions (ECF No. 103) is DENIED.

The Clerk shall enter Judgment accordingly and shall terminate this case

from the Court’s docket.

IT IS SO ORDERED.

/s/ Sarah D. Morrison

SARAH D. MORRISON

UNITED STATES DISTRICT JUDGE