Opinion

American Premier Underwriters Inc v. General Electric Company

Court
District Court, S.D. Ohio
Filed
Aug 25, 2020
Cited by
0 cases
Authority
More cited than 28.2%

The opinion

UNITED STATES DISTRICT COURT

SOUTHERN DISTRICT OF OHIO

EASTERN DIVISION

American Premier

Underwriters, Inc.,

Plaintiff,

Case No. 1:05-cv-437

Vv.

Judge Michael H. Watson

General Electric

Company,

Defendant.

OPINION AND ORDER

This cause comes before the Court on Plaintiff American Premier

Underwriters, Inc.’s (“APU”) Trial Brief, ECF No. 178, Defendant Genera! Electric

Company’s (“GE”) Trial Brief, ECF No. 180, and APU’s Reply, ECF No. 181. For

the following reasons, the Court finds that GE is not liable as a former operator of

the Silverliner IV and Jersey Arrow II railcars or the Paoli, Sunnyside, and

Wilmington rail yards.

I. INTRODUCTION

APU is the successor to the Penn Central Transportation Company (“Penn

Central”).' Compl. 23, ECF No. 1. This action arises from contamination at

three rail yards operated by Penn Central prior to April 1, 1976: (1) the Paoli Yard

in Paoli, Pennsylvania; (2) the Sunnyside Yard in Long Island, New York; and (3)

' The Court refers to Pennsylvania Railroad and Penn Central Transportation Company

collectively as “Penn Central.” The former was renamed to the latter after a 1968 merger.

the Wilmington Yard and its related facilities in Wilmington, Delaware. /d. at J 24.

When Penn Central operated these three rail yards (collectively the “Yards’), it

owned and used passenger railcars with transformers designed and

manufactured by GE. /d. at { 25. APU claims these GE railcar transformers

contributed to contaminating the Yards by leaking polychlorinated biphenyls

(“PCBs”). /d. at | 2. APU now seeks to hold GE responsible for portions of the

clean-up and response costs asscciated with those leaks based on its theory that

GE is a “former operator’ of the Yards and related railcars, as that term is defined

by the Comprehensive Environmental Response, Compensation, and Liability

Act of 1980 (“CERCLA”), 42 U.S.C. § 9601, et seq. /d. □□ 911. To understand

this litigation, a brief summary of its previous proceedings is necessary.

In 1992, the United States filed a CERCLA action against Penn Central to

recover response costs related to the contamination at the Paoli Yard. /d. at

{| 63. That case proceeded alongside other CERCLA claims against Penn

Central filed by the Southeastern Pennsylvania Transportation Authority

(“SEPTA”), National Railroad Passenger Corporation (“Amtrak”), and

Consolidated Rail Corporation (“Conrail”) to recover environmental costs incurred

at the Sunnyside and Wilmington Yards. On September 20, 1999, SEPTA,

Amtrak, and Conrail entered into a settlement agreement with the United States

relating to the Paoli Yard; the settling defendants were obligated to pay $500,000

to the United States and $100,000 to Pennsylvania for response costs, and

$850,000 to the United States and Pennsylvania for natural resource damages

Case No. 1:05-cv—437 Page 2 of 26

arising from the contamination at the Paoli Yard. APU SOF No. 22-23, ECF No.

96-2. About five years later, on November 8, 2004, APU, SEPTA, Amtrak, and

Conrail entered into a settlement agreement relating to the contamination of the

Paoli Yard, under which APU paid $23,000,000 to SEPTA and $15,000,000 to

Amtrak.” /d. No. 27, ECF No. 96-3. Ten months after that, in September 2005,

APU and the United States entered a settlement agreement under which APU

paid another $6.4 million for response costs and natural resource damages

related to the Paoli Yard. /d. No. 31-32. APU has also incurred costs related to

CERCLA claims for the Sunnyside and Wilmington Yards. /d. Nos. 51, 56-58.

In June 2005, APU filed this action against GE asserting twenty-three

causes of action under federal! law and the laws of four states seeking to recover

costs expended to remove the PCB contamination at the Yards. After GE moved

to dismiss certain causes of action, the Court dismissed twelve of APU’s claims.

See Opinion & Order, ECF No. 60. Then, in May 2011, after discovery had

closed, APU and GE each moved for summary judgment on various remaining

claims. The case was then reassigned to Judge Barrett, who ruled on those

motions. ECF Nos. 151, 153-55. Judge Barrett subsequently permitted the

parties to move for reconsideration. See ECF No. 157. He later denied APU’s

Motion for Reconsideration. ECF No. 170. This case was then reassigned to the

2 The United States had initially demanded $58,600,000. /d. No. 29.

Case No. 1:05—cv-437 Page 3 of 26

Undersigned, who granted in part and denied in part GE’s Motion for

Reconsideration. ECF No. 175.

As a result of this extensive litigation history, only two claims remain for

trial: (1) APU’s recovery claim for removal costs at the Sunnyside and Wilmington

Yards (Count I), and (2) APU’s contribution claim for settlement payment to the

United States in connection with the Paoli Yard (Count Ill). Although CERCLA’s

removal and contribution claims are separate, United States v. Atl. Research

Corp., 551 U.S. 128, 131 (2007), the parties agree that the threshold issue for

both these remaining claims is whether GE qualifies as a former “operator” of the

relevant facilities. See Joint Mot. to Approve Case Mgmt. Order at 1~2, ECF No.

176. Thus, that is the sole question before the Court, which the parties agreed to

submit to the Court by trial briefs. See ECF Nos. 176-77. Based on those briefs

and the evidence presented in them, the Court makes the following findings of

fact and conclusions of law.

Il. | FINDINGS OF FACT

For most of the twentieth century, Penn Central provided passenger and

freight rail services throughout the United States. Compl. 16, ECF No. 1.

Beginning in 1915, Penn Centra! operated self-propelled multi-unit (“MU”)

passenger railcars powered by electricity at the Paoli Yard in Paoli,

Pennsylvania. APU Brief, Ex. 2 at 2, ECF No. 99-1. in 1928, Penn Central

began commuter services from Philadelphia to the Wilmington Yard in

Case No. 1:05—cv-437 Page 4 of 26

Wilmington, Delaware. /d. at 3. Then, in 1933, Penn Central first operated

electric railcars at the Sunnyside Yard in Queens, New York. /d. at 4.

At those operations, Penn Central provided commuter services via MU

railcars. Evans Dep. 13-15, ECF No. 180-1. The commuter cars were self-

propelled using electricity provided by catenary lines strung above the railroads.

fd. at 14-16. The railcars drew high-voltage alternating currents from the

overhead lines, reduced the current to a lower voltage with an onboard electrical

transformer, and converted the alternating current to a direct current with other

electrical devices. /d. at 16-18. Each transformer was essentially a tank with

various attachments coming out of it. Evans Dep. 31, ECF No. 180-1. To

insulate the substantial heat within the tanks, the transformers were filled with a

fluid called askarel, which contained PCBs. /d. at 26, 33. GE eventually

trademarked its version of askarel as “Pyranol.” /d. at 27.

Depending on the model of the railcar and its transformer, the volume of

Pyranol in a transformer’s sealed tank ranged from 80 to 140 gallons. /d. at 31—

32. The transformers could not function with an insufficient amount of Pyranol

since the internal components would then overheat, which would cause the tank

to explode. /d. at 31, 33-34. Thus, when GE delivered the railcars to Penn

Central, GE had already filled the transformer tanks with Pyranol. GE Ex. 5

(“MacMonagle Dep. II”) at 203, Doc. 180-5. GE mounted the transformers under

the railcars’ cabins, about eight inches to two feet above the railroad (depending

Case No. 1:05—cv—437 Page 5 of 26

on the railcar model). Ex. 101, ECF No. 102-2: Evans Dep. at 20-21, ECF No.

180-1.

As the internal components in a transformer became hot during operation,

the Pyranol expanded, thereby increasing the tank’s internal pressure. Evans

Dep. at 34-35, ECF No. 180-1. GE designed the tank to accommodate

increased pressure, and avoid a potential explosion, by including a pressure

relief valve on the transformers. /d. at 35-37. These devices prevented tank

ruptures by releasing vapor—and sometimes Pyranol—until the tank’s internal

pressure feil to a level that could not potentially rupture the tank. Evans Dep. at

65-74, ECF No. 180-1.

Beginning on July 1, 1965, and continuing until April 1, 1976, Penn Central

and the New Jersey Department of Transportation (‘NJDOT’) entered

agreements, which obligated Penn Central to run and maintain various railcars in

New Jersey, including Jersey Arrow II railcars. APU SOF No. 6, ECF No. 95-2.

On October 11, 1971, SEPTA leased Penn Central 130 Silverliner IV railcars for

use in four Pennsylvania counties and in the City of Philadelphia. /d. Nos. 1, 4,

ECF No. 95-1. On October 14, 1971, GE and NJDOT entered a sales contract

under which GE agreed to “design, construct, test, deliver, and guarantee” 70

Jersey Arrow Il railcars. fd. No. 7, ECF No. 95-2. A few days later, on October

18, 1971, SEPTA and GE executed a contract under which GE agreed to

“design, construct, test, deliver, and guarantee” 144 Silverliner IV railcars for

SEPTA. fd. No. 5, ECF No. 95-1. GE manufactured the Silverliner IV and

Case No. 1:05-cv—437 Page 6 of 26

Jersey Arrow Ii railcars at its plant in Erie, Pennsylvania. MacMonagle Dep. tI at

178, ECF No. 180-5. And GE manufactured those Railcars’ transformers at a

GE plant in Pittsfield, Massachusetts. /d. at 165. In addition to the Railcars’

purchase agreements, GE executed warranty agreements with NJDOT and

SEPTA.

In the warranty agreements, GE guaranteed that each Silverliner IV and

Jersey Arrow II railcar and its components would contain no “defects in design,

materials, and workmanship[.]” GE Ex. 14 at 12, ECF No. 180-14; GE Ex. 15 at

13, ECF No. 180-15. If 25% of the railcars experienced a particular component

failure, GE was required to recall and repair that component in ail the railcars.

GE Ex. 16 at 1-2, ECF No. 180-16. But GE was not required to perform any

repairs. GE Ex. 14 at 13-14, ECF No. 180-14; GE Ex. 15 at 13-14, ECF No,

180-15. Rather, GE had to pay for them. GE Ex. 14 at 13-14, ECF No. 180-14;

GE Ex. 15 at 13-14, ECF No. 180-15. This reimbursement warranty policy

included any costs Penn Central incurred for labor, fringe benefits, and overhead.

GE Ex. 16 at 1, ECF No. 180-16.

Around June 1974, GE began delivering the Silverliner IV and Jersey

Arrow II railcars to Penn Central on a rolling basis. GE Brief Ex. 2 (“Kennedy

Dep.”) at 97, ECF No. 180-2. Almost immediately, some railcar transformers

suffered serious internal failures, GE Brief Ex. 17, ECF No. 180-17, that were

sometimes accompanied by the release of Pyranol. GE Brief 26, ECF No. 180.

GE investigated the issue and ultimately concluded that the failures were caused

Case No. 1:05—cv—437 Page 7 of 26

by “a randomly occurring core blocking workmanship problem.”? GE Brief Ex. 17

at 1, ECF No. 180-17. GE also concluded that the overall failure rate on the

Railcars with the original design was between 10-20%. GE Brief Ex. 18, ECF

No. 180-18. To remedy the issue, GE designed a modified coil blocking

component that stabilized the tanks’ coils and prevented short-circuiting.

MacMonagle Dep. II at 197, ECF No. 180-5. This tweak solved the issue. Evans

Dep. at 117-18, ECF No. 180-1. But GE only added that component to Railcars’

transformers after they had already malfunctioned. GE Brief Ex. 17, ECF No.

180-17.

After GE delivered the Silverliner IV railcars to Penn Central, GE

established a trailer at the Paoli Yard to house four GE employees that

performed warranty administration and field service support to the Penn Central

employees at the shop. Keefe Dep. at 29-31, ECF No. 180-3. To that end,

when a railcar arrived at the Paoli Yard with a “warranty problem,” a Penn

Central shop foreman would enter the GE trailer and ask one of the four GE

technicians for assistance. Evans Dep. at 163, ECF No. 180-1. Only the Penn

Central shop foreman could request assistance from GE technicians. /d. Upon

doing so, GE technicians assisted Penn Central employees with troubleshooting

the railcars problems, but those technicians were not allowed to give orders to

3 GE, perhaps to put this in terms the Court better understands, describes the problem

as “affectfing] the stability of the components within the transformer tank.” GE Brief 24,

ECF No. 180.

Case No. 1:05—-cv-437 Page 8 of 26

the railroad employees since the GE technicians could only offer technical

support. /d. So, according to the “ground rules,” the Penn Central shop foreman

was in charge, and only he could give commands regarding the maintenance and

repair of the Railcars and their components. /d. For that reason, the GE

technicians never tried to give orders to Penn Central employees but rather just

offered them advice. /d. This hierarchy is consistent with Penn Central's labor

organization at the Paoli Yard, which prohibited any non-Penn Central personnel

from performing mechanical labor on the Railcars. Evans Dep. at 165~167, ECF

No. 180-1. Thus, GE technicians were barred from performing any work on the

Railcars, such as disconnecting wires, removing covers, or “that type of thing.”

ld. For that reason, the four GE technicians at the Paoli Yard never serviced or

repaired any transformers there. Evans Dep. at 229-33, ECF No. 180-1.

The Railcars’ transformers, which were filled with liquid, required repairs

every now and then; but their tanks contained up to 140 gallons of Pyranol, so

they were extremely heavy. APU SOF Ex. 98, ECF No. 102-2; MacMonagle

Dep. 1 147, ECF No. 180-4. To remove and then repair or replace the

transformers, Penn Central employees sometimes drained the transformer tanks

of Pyranol directly onto the railbeds or on other parts of the Yards. Keefe Dep. at

163-65, ECF No. 180-3; D’Antonio Dep. at 31-41, ECF No. 180-11.

in sum, APU asserts that Pyranol leaks occurred when: “(1) the Railcars’

transformers overheated; (2) rocks or debris damaged the transformers while the

Railcars were in service on the main line; (3) fluid volatilized; and (4) the Railcar’s

Case No. 1:05-cv-437 Page 9 of 26

transformers were serviced.” APU’s SOF No. 12, ECF No. 95-3. And the record

indicates that some leaks occurred at the Paoli and Wilmington Yards from the

deliberate wholesale dumping or spraying of fluids drained from the rail car

transformers and from unintended spillage and leakage of fluids from

transformers. /d.

lll. LAW AND ANALYSIS

The threshold issue here is whether GE is a former operator of the Yards

or Railcars. CERCLA defines a former “operator” as anyone “who at the time of

disposal of any hazardous substance . . . operated any facility at which such

hazardous substances were disposed off.]” 42 U.S.C. § 9607(a)(2). APU and

GE agree that some of those elements are supported by the evidence here.

First, there is no dispute that the Railcars and Yards qualify as separate

“facilities” under CERCLA. And both parties agree that Pyranol, which contains

PCBs and is a “hazardous substance” under CERCLA, was released at the

Yards and from the transformers of some Railcars. The only disagreement

between APU and GE, then, is whether GE operated the Yards or Railcars when

the Pyranol leaks occurred.

The temporal requirement is a straightforward question of fact. The

conduct requirement, on the other hand, is a complicated question of law and

fact.

To begin, in United States v. Bestfoods, the Supreme Court explained that,

to “operate” in the context of CERCLA, one “must manage, direct, or conduct

Case No. 1:05—cv—437 Page 10 of 26

operations specifically related to pollution, that is, operations having to do with

the leakage or disposal of hazardous waste[.]” 524 U.S. 51, 66-67 (1998). In

other words, the Court clarified, “to operate’. . . obviously mean[s] something

more than mechanical activation of pumps and valves, and must be read to

contemplate ‘operation’ as including the exercise of direction over the facility's

activities.” /d. at 71. Two months after Bestfoods, the Sixth Circuit provided the

test to apply when determining whether one qualifies as a CERCLA operator.

United States v. Twp. of Brighton, 153 F.3d 307 (6th Cir. 1998). There, the Sixth

Circuit held that the “actual control” test applies, meaning that “[bJefore one can

be considered an ‘operator’ for CERCLA purposes, one must perform affirmative

acts.” /d. at 314. Thus, the Sixth Circuit found, “[t]he failure to act, even when

coupled with the ability or authority to do so, cannot make an entity into an

operator.” /d.

Under that general framework, APU argues that GE qualifies as an

operator of the Railcars and Yards for three reasons. First, APU contends that

GE operated the Railcars by designing and manufacturing them and, in

particular, their transformers. Second, APU argues that, by administering the

Railcars' warranties at the Yards, GE controlled the Railcars enough to

effectively direct the activities of the Railcars and the Yards. Third, APU asserts

GE controlled the Railcars by implementing its “fail and fix” warranty policy, under

which GE chose to repair rather than replace potentially faulty transformers. For

Case No. 1:05-cv—437 Page 11 of 26

the following reasons, APU’s first and third theories fail as matters of law, and its

second theory fails on the record here.

A. Designing and Manufacturing the Railcars Does Not Make GE an

Operator.

There is no dispute that GE was the general contractor for the building of

the Silverliner IV and Jersey Arrow II railcars, as well as the manufacturer of the

transformers and propulsion system. GE Brief 6, ECF No. 180. APU contends

that this conduct establishes that GE is an operator of the Railcars.* For two

primary reasons, however, APU’s claim fails as a matter of law. First, GE’s

design and manufacture activities are not the types of work that support a finding

that it was an operator under CERCLA. Second, even if those actions could

move the “operator” needle, GE’s design and manufacturing work cannot serve

as the basis for operating the Railcars because APU does not allege that any

leaks occurred at the time GE performed that work. Thus, GE cannot be held

liable as an operator for designing and manufacturing the Railcars.

Again, CERCLA defines former operators as “any person who at the time

of disposal of any hazardous substance . . . operated any facility at which such

hazardous substances were disposed off.]” 42 U.S.C. § 9607(a)(2). APU

contends that GE’s design and manufacture of the Railcars demonstrates its

operator status as those acts related to pollution to the extent that, by including

4 APU also briefly suggests that GE is liable because it invented and patented PCB-

containing Pyranol. APU Brief 18, ECF No. 178. Without further developing that

argument, however, the Court need not analyze it.

Case No. 1:05-cv—437 Page 12 of 26

Pyranol and valve releases as components of the transformers, GE planned for

Pyranol discharges to occur in certain future circumstances. Even if true,

however, CERCLA does not extend liability so broadly as to attach to GE for its

actions that occurred before the release of PCB-containing materials.

Acknowledging this defect, APU points to the multi-factor test of operator

liability proposed in the Brighton concurrence, which weighed, among other

things, an alleged operator's role in designing a facility and its expertise and

knowledge of the dangers of a facility. APU Reply at 4, 7 (citing Brighton, 153

F.3d at 327 (Moore, J., concurring)). While the Court previously found these

factors to be “instructive,” Op. & Order 12 n.5, ECF No. 154, they are of course

not binding.* See Maryland v. Wilson, 519 U.S. 408, 412-13 (1997). Meanwhile,

the majority opinion in Brighton—which is binding—requires that an operator

“actually control” the relevant facility. Brighton, 153 F.3d at 314. That is,

“[b]efore one can be considered an ‘operator’ for CERCLA purposes, one must

perform affirmative acts” to control the facility, id., “at the time of disposal of any

hazardous substances[.]” 42 U.S.C. § 9607(a)(2). As a matter of law, then, the

fact that GE designed and manufactured facilities that later released hazardous

substances cannot create operator status.

APU disagrees and argues that, as a matter of law, GE’s design and

manufacture of the transformers is sufficient to establish operator liability

5 APU does not suggest otherwise.

Case No. 1:05-cv—437 Page 13 of 26

because the relevant product contained hazardous substances. APU offers two

cases for support.

Relying on Nu-West Mining Inc. v. United States, 768 F. Supp. 2d 1082 (D.

Idaho 2011), APU argues that operator liability can attach to the designer-

manufacturer of a CERCLA facility. For several reasons, though, that case is

inapposite. For one, the Nu-West Mining court applied a standard for operator

liability that differs from the one that applies here. /d. at 1089. There, the court

relied on the Ninth Circuit's “authority to control” standard. /d. (quoting Kaiser

Alum. & Chem. Corp. v. Catellus Dev. Corp., 976 F.2d 1338, 1341-42 (9th Cir.

1992)). Whatever the rule may be in the Ninth Circuit, the Sixth Circuit requires a

CERCLA operator to exercise “actual control” over the facility that released the

contamination.

Moreover, in Nu-West Mining, the defendant was the federal government,

which had substantial control over the facilities—four hazardous waste dumps—

by exerting its regulatory authority and contractual final-approval authority over

the plaintiff to relocate, redesign, and (after the dumps were built) modify the four

hazardous waste dumps. /d. at 1090-91. The government also continued to

inspect the facilities “to ensure compliance with the mining plans and waste

disposal guidelines.” /d. at 1090. After those inspections, the government

ordered the plaintiff to modify the facilities’ structures and to stop dumping

hazardous waste in certain areas, “among other decisions affecting the waste

dump.” /d. In this way, the government controlled how much, where, and the

Case No. 1:05—cv—437 Page 14 of 26

methods by which waste could be handled by the plaintiff. fo. When the

government later argued that it was not an operator under CERCLA but instead a

typical “regulator,” the court rejected that argument because, ultimately, the

government “was a very active participant in designing and locating the waste

dumps, in inspecting mining operations, and in ensuring compliance with all rules

and plans.” /d. at 1090-91.

Finally, in Nu-West Mining, the CERCLA facility the government designed,

built, and monitored was a hazardous waste dump, and so, that facility was

intentionally designed for the purpose of polluting. In contrast, GE designed,

manufactured, and tested the Railcars—i.e., transportation vehicles, not waste

dumps—and then delivered those Railcars to Penn Central for its commuter

operations. After delivery, GE did not maintain rights to inspect the Railcars, did

not have any control over how or where Penn Ceniral operated the Railcars, and

did not order Penn Central to operate the Railcars in compliance with any

environmental regulations (more on all that later). Accordingly, unlike the

defendant in Nu-West, GE’s design and manufacture of the Railcars were not

“specifically related to” activities involving the disposal of hazardous waste, and

so GE did not participate in designing and manufacturing a facility designed

specifically for the purpose of dumping hazardous materials.

Next, APU relies on GenCorp, Inc. v. Olin Corp., 390 F.3d 433 (6th Cir.

2004), arguing that, there, the Sixth Circuit found the defendant was an arranger

and operator under CERCLA for participating in a joint committee that approved

Case No. 1:05-cv-437 Page 15 of 26

the design plans for the facility, as well as other projects. /d. at 449. True

enough, the GenCorp court rejected the defendant's argument that arranger and

operator liability did not attach because it had not directly engaged in disposal

activities. Still, GenCorp does not help APU much as the Sixth Circuit in that

case did not focus on the fact that the defendant had participated in the design

and construction of the facility to find that those activities established the

defendant was an operator. /d. at 449. Rather, the Sixth Circuit pointed out that,

based on the defendant’s “active interest in the facility-—as evidenced by its

option to buy the plant and its contribution of one haif of the facility’s construction

costs—and “equal representation” on the committee that oversaw the

construction, operation, and management of the facility, the defendant had

substantially controlled the facility as to justify operator/arranger liability. /d. at

449 (emphasis in original). Put differently, the defendant’s role on the committee

(which included overseeing the facility’s design and construction, among other

things), demonstrated the substantial degree of control that the defendant

exerted over the entire facility.

Thus, GenCorp does not support APU’s argument that, inter alia, operator

liability attaches to one who designs and manufactures a vehicle that later emits

a hazardous substance. Rather, GenCorp focuses on whether a party actually

controlled the operations specifically related to the disposal of hazardous

substances at the time of those disposals. /d. at 447-49.

Case No. 1:05-cv—437 Page 16 of 26

Indeed, it is well established that simply designing and building a facility

that subsequently leaks hazardous substances into the environment does not

establish or otherwise support a finding of operator liability under CERCLA,

Judge Easterbrook’s opinion in Edward Hines Lumber Co. v. Vulcan Materials

Co., 861 F.2d 155 (7th Cir. 1988), best illustrates this point. There, the Seventh

Circuit explained that, because operator liability attaches only to those who

control the relevant facilities at the time of the disposals, CERCLA “does not fix

liability on slipshod architects, clumsy engineers, poor construction contractors,

or negligent suppliers of on-the-job training—and the fact that [the defendant}

might [be] all four rolled into one does not change matters.” Edward Hines, 861

F.2d 155, 157 (7th Cir. 1988). This is true, the Edward Hines court found, even

when-—after the initial transaction—the designer-manufacturer-seller trains the

operator-buyer to use the machinery, reserves the right to inspect ongoing

operations, and furnishes the toxic materials. /d. at 156-57. And so, assuming

as true APU’s claims that GE negligently designed and manufactured poorly

constructed railcars and transformers, CERCLA does not impose operator

liability on such actors. Accordingly, APU cannot hold GE liable as an operator

for designing and manufacturing the Silverliner IV and Jersey Arrow II railcars.

B. Administering the Railcars’ Warranties at the Yards Does Not Make GE

an Operator.

Next, APU contends that GE is a CERCLA operator of the Railcars and

Yards for leading the Railcars’ maintenance and repair processes and ultimately

Case No. 1:05-cv—437 Page 17 of 26

“bec[oming] ingrained in the day-to-day operations at the [Yards].” APU Brief 7,

ECF No. 178. GE disagrees with that characterization of its post-sale activities,

arguing that there is no evidence regarding whether GE personnel engaged in

any on-site activities at the Sunnyside and Wilmington Yards, and that, to the

extent GE had personnel stationed at the Paoli Yard, those technicians merely

administered the Railcars’ warranties, which does not involve the type of

“direction” or “control” necessary to establish that GE is an operator under

CERCLA. The question, then, is whether GE’s post-sale activities at the Yards

involved managing, directing, or conducting the Railcars and Yards.

As an initial matter, though, GE correctly points out that the record is

mostly absent of evidence that GE engaged in any activities at the Sunnyside

and Wilmington Yards.

Regarding the Sunnyside Yard, Evans, a former Penn Central employee,

testified that he had no knowledge about whether GE had a trailer there. Evans

Dep. at 161, ECF No. 130. A former GE engineer, MacMonagle, testified that he

was not certain whether GE had a trailer at the Sunnyside Yard, but he believed

it did. MacMonagle Dep. at 55, ECF No. 137. And Keefe, a GE field engineer,

testified that GE had an office building or a part of an office building at the

Sunnyside Yard from 1970 to around 1975, but he did not elaborate beyond that.

Keefe Dep. at 40, ECF No. 132. Under the “actual control” standard required by

Brighton, GE’s presence at a facility undoubtedly does not establish that it

operated that facility. Simply put, “existence” does not amount to “actual control.”

Case No. 1:05-cv—437 Page 18 of 26

Thus, APU has not established that GE operated the Sunnyside Yard.

By the same token, there is sparse evidence to illustrate what, if any,

activities GE performed at the Wilmington Yard. Keefe testified that GE had a

“commissioning site” there in the early 1970s. Keefe Dep. at 13-22, ECF No.

132. He explained that GE handled warranty support for another set of railcars

(not the Silverliner IV or Jersey Arrow II Railcars) at its Wilmington Yard site,

primarily “diagnosing whether the thing was functioning or defective.” /d. at 22.

Further, to the extent Evans testified that GE had a presence at the Wilmington

Yard in the mid-1970s, he explained that it was because GE delivered the

Silverliner IV cars to SEPTA there. Evans Dep. at 160-61, ECF No. 130.

Neither Evans nor Keefe explained in any detail, however, the work that GE

performed at the Wilmington Yard. Again, without evidence establishing that GE

maintained control over the Wilmington Yard’s operations, APU has not shown

that operator liability should attach to GE for simply diagnosing and delivering

railcars there.

That leaves the Paoli Yard. The parties do not dispute that, there, GE had

a shop—better described as “a small work trailer’—from 1974 to 1978, and that

four GE technicians administered the Silverliner IV railcars’ warranties and taught

the Penn Central employees about how to troubleshoot and repair those railcars.

id. at 155-58. But GE and APU disagree about whether those activities establish

that GE operated the Railcars and the Paoli Yard. Two witnesses, one testifying

on behalf of each party, explained the breakdown of duties at the Paoli Yard.

Case No. 1:05-cv-437 Page 19 of 26

Evans was a Penn Central shop foreman there in the 1970s. Keefe was a GE

technician at the Paoli Yard’s shop around the same time. Their testimony is

consistent.

Evans averred that at the Paoli, Wilmington, and Sunnyside Yards, Penn

Central’s Transportation Department managed the train schedules, staffing,

equipment, and railcar inventory. /d. at 43, 241-44. And a Penn Central

engineer “drove” the Railcars. /d. at 241. Meanwhile, Penn Central's Mechanical

Department (of which he was a part), performed any maintenance and repairs on

the Railcars. /d. at 241-45. Both Evans and Keefe also explained that the GE

technicians at the Paoli Yard merely trained and assisted the Penn Central

employees, who then maintained and repaired the Railcars. /d. at 152-53; Keefe

Dep. 31-32, ECF No. 132. Keefe described the duties of the GE technicians

working at the Paoli Yard as follows:

In broad terms we were warranty administrators, but under the

heading of warranty administrators you trained, you assisted with

troubleshooting, administrative functions of doing failure analysis,

determining whether it was legitimate equipment failure, whether the

equipment was abused. It was a multifunctional job because there

were times where | even dispatched people to go out and ride the

equipment to find out what the railroad was complaining about. That

was essentially it.

Keefe Dep. 31-32, ECF No. 132.

Evans’ testimony substantiates Keefe’s and further explains that the GE

technicians could only offer advice to Penn Central employees about identifying a

Railcar’s issues. In other words, the GE technicians were only allowed to

Case No. 1:05-cv—437 Page 20 of 26

recommend methods to repair a Railcar’s problems, given that Penn Central's

shop foreman had exc/usive authority over the railroad employees’ actions as

they performed maintenance and repairs on the Railcars. Evans Dep. 162-63,

ECF No. 130. Here is how Evans explained the division of authority for the Paoli

Yard’s maintenance operations:

Q: Now, was there a particular protocol that needed to be followed

when Paoli employees of Penn Central communicated with the

guys in the GE trailer? | mean, did they have to go through a

particular supervisor, or could kind of anyone walk in and talk

to the guys?

A: | The shop manager handled that, the manager of the shop.

Q: So that would have been the position you had?

A: My position, or somebody under me in a management position,

would say, | need some assistance on such-and-such a project,

or tell them that a car’s coming in, it’s got a warranty problem.

Q: So essentially it had to be authorized by the shop foreman?

A: Yes.

Q: Were the GE employees who staffed the trailer allowed to give

orders to the railroad employees?

A: No.

Q: What would have happened if they had tried to give orders to

the railroad employees?

A: They did — they didn’t try to give orders to the railroad

employees because they knew the ground rules when they

came there. They were the technicians, and... . if any orders

were to be given out, it would be given out by the [the railroad’s]

foreman.

Case No. 1:05-cv-437 Page 21 of 26

id. Not only this, but Penn Central’s union labor rules required that Penn Central

employees actually repair and perform maintenance on the Railcars. /d. at 167—

68.

And the purchase agreemenis under which GE sold the Railcars clearly

state that GE was a contractor. Unlike the defendant in GenCorp, GE had no

interest in the facility (i.e., had no right to share in the profits and was not

required to contribute to the operational losses, or any other operational

expense, beyond those called for in the warranty agreement). Notably, APU has

not presented any cases in which a court has held a party liable for administering

its warranty obligations. And APU has not explained how administering the

Railcars’ warranties amounts to operating the railcars. To the contrary, replacing

parts of the Railcars in accordance with the warranty agreement at an off-site

location suggests that the Railcars were not operating during those activities.

Plus, according to Evans, in any instance where a transformer was leaking, GE

employees were not around to provide advice about fixing the unit. /d. at 236.

Consistent with the Warranty Agreements, GE presents a document that

lists the activities that the GE warranty administrators performed:

a.) On-the-job training of the railroad personnel

b.) Technical assistance to railroad personnel

c.) Assistance with troubleshooting the Railcars when:

i. a Railcar’s problems were complex or beyond the capability

of the Penn Central personnel to diagnose and correct

Case No. 1:05—cv—437 Page 22 of 26

li. GE personnel had not yet taught Penn Central personnel the

necessary troubleshooting methods in formal or on-the-job

training

ii. a Railcar had a repeated issue and Penn Ceniral personnel

were unable to diagnose and correct the problem

d.) Administering the warranty

GE Brief, Ex. 22 at 2, ECF No. 180-22. That document also states that “GE can

not perform routine troubleshooting of [RailJcars or try to run the [Penn Central]

maintenance facilities.” /d.

Based on this procedure, then, GE did not know about any problems with a

Railcar’s transformer until after Penn Central had tried and failed to fix the

transformer or Penn Central had otherwise sought a GE employee's technical

guidance.

In the event one of the Railcars had a problem, Penn Central had the

ability to initiate a claim. GE Brief Ex. 16 at9, ECF No. 180-16. If Penn Central

initiated a claim, it could elect one of three options: (1) exchange the failed unit

for a new one, (2) have GE rebuild the failed unit, or (3) pursue a “limited repair

and return” option. /d. at 10-11. If Penn Central chose either the second or third

option, a GE technician would decide to either pay Penn Central to perform the

work or elect for GE to perform the work itself ata GE shop elsewhere. /d. The

on-site GE employees never actually physically repaired or serviced the

equipment. Evans Dep. at 232, ECF No. 180-1. And if a Penn Central employee

Case No. 1:05—cv—437 Page 23 of 26

or supervisor disagreed with a GE employee’s advice, the Penn Central

employees were free to disregard it. fd. 235.

APU points to Exxon Mobil Corp. v. United States, 108 F. Supp. 3d 486

(S.D. Texas 2015) for the proposition that an entity can be held liable as a former

CERCLA operator if that entity approved designs for a facility, permanently

stationed personnel there, and played a substantial role in day-to-day operations

of the facility. In Exxon, the plaintiff moved for summary judgment to determine

the government's culpability under CERCLA for its involvement at two different

types of facilities: refineries and plants. As to the plants, the court concluded that

the government, which had already admitted CERCLA liability as an owner of

those facilities, was also an operator under CERCLA because the government

had a substantial presence at the facility and final approval for, among other

things, expenditures exceeding $1,000; the disposal of waste; additions and

alterations to the plant; and increasing Exxon employees’ salaries and benefits.

fd. at 531. GE had no such control at the Paoli Yard. Plus, the extent of GE’s

presence at the Paoli Yard—a four-employee work trailer—pales in comparison

to the government's operations at the plants in Exxon. There, at just one of the

plants, the government “featured military barracks, a mess hall, air raid shelters,

high-security perimeter fencing, and four guard watchtowers.” Exxon, 108 F.

Supp. 3d at 532. The Exxon court thus concluded that the plant “resembled a

United States Army base more than a chemical plant.” /d, And so, Exxon does

not alter the Court's analysis of GE’s work trailer here.

Case No. 1:05—cv—437 Page 24 of 26

The Exxon court’s analysis of the refineries in that case provide even more

support that GE was not an operator in this case. That court concluded that the

government was not a former operator because—although the government

Stationed at least one employee at one of the refineries to ensure product quality

and coordinate shipping—there was no evidence that the government was

involved in the refineries’ daily management or waste disposal practices. /d. at

526. Notably, the Exxon court emphasized, the government was not authorized

to hire, fire, or in any way manage Exxon’s refinery employees. fd. Without such

control, and even though the government understood the potential for harmful

pollution at the facilities, the government did not operate those facilities. /d. at

529.

Similarly here, GE had no control over Penn Central’s employees and

certainly not over the entire Paoli Yard. Rather, as explained above, the GE

technicians could only recommend troubleshooting and repair advice. in

contrast, Penn Central's Transportation Department determined the staffing

decisions, equipment to be used, services to be offered, commuter schedules,

and railcar inventory. Evans Dep. 240-42, ECF No. 180-1. And Penn Central's

Mechanical Department performed all hands-on maintenance and repairs. /d. at

232. Meanwhile, GE technicians proposed maintenance schedules for the

Railcars, which Penn Central generally accepted and followed. /d. at 244.

Similarly, GE technicians could recommend—but not order—that Penn Central

remove a malfunctioning Railcar. /d. at 245,

Case No. 1:05-cv-437 Page 25 of 26

GE’s advisory role in the Railcars’ operation, as opposed to a management

or control position, leads to the conclusion that GE did not operate the Paoli Yard

or the Railcars.

C. The “Fail And Fix” Policy Does Not Render GE a CERCLA Operator.

Finally, APU contends that GE operated the Railcars by implementing a

“fail and fix” policy, which refers to GE’s decision not to proactively recall and

replace transformers under warranty that had not failed but also could not be

definitely declared defect-free. But even under APU's characterization, as GE

points cut, that policy would amount to a failure to exercise control over the

Railcars, which cannot be the basis for operator liability. See Brighton, 153 F.3d

at 314 (“Before one can be considered an ‘operator’ for CERCLA purposes, one

must perform affirmative acts. The failure to act, even when coupled with the

ability or authority to do so, cannot make an entity into an operator.”). Thus,

APU’s argument relating to GE's “fail and fix” policy fails as a matter of law.

IV. CONCLUSION

For these reasons, the Court finds that the record evidence establishes

that GE is not a CERCLA operator of the Paoli, Sunnyside, or Wilmington Yards,

or the Silverliner IV or Jersey Arrow II railcars. Therefore, the Court DIRECTS

the Clerk to enter judgment in favor of GE and TERMINATE this case.

IT IS SO ORDERED. : □ if / bon

ICHAEL H. WATSON, JUDGE é

UNITED STATES DISTRICT COURT

Case No. 1:05—-cv-437 Page 26 of 26

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.