Opinion

Bay County, Florida v. United States

  • 112 Fed. Cl. 195
  • 2013 U.S. Claims LEXIS 1070
  • 2013 WL 4083364
Court
United States Court of Federal Claims
Filed
Aug 14, 2013
Status
Published
Author
Lettow
On the bench
Lettow
Cited by
7 cases
Authority
More cited than 61.1%

The opinion

In the United States Court of Federal Claims

No. 11-157C

(Filed: August 14, 2013)

**********************************

) Alleged partial breach of contracts for

BAY COUNTY, FLORIDA, ) utility services provided by Bay County to

) Tyndall Air Force Base; Bay County as an

Plaintiff, ) independent regulatory body; DFARS §

) 241.101; invocation of the Christian

v. ) doctrine; applicability of FAR § 54.241-7

) rather than § 54.241-8; partial summary

UNITED STATES, ) judgment

)

Defendant. )

)

**********************************

George R. Mead, II, Moore, Hill & Westmoreland, Pensacola, Florida, for plaintiff. With

him on the briefs was Charles F. Beall, Jr., Moore, Hill & Westmoreland, Pensacola, Florida.

Antonia R. Soares, Trial Attorney, Commercial Litigation Branch, Civil Division, United

States Department of Justice, Washington, D.C., for defendant. With her on the briefs were

Stuart F. Delery, Principal Deputy Assistant Attorney General, Jeanne E. Davidson, Director,

and Deborah A. Bynum, Assistant Director, Commercial Litigation Branch, Civil Division,

United States Department of Justice, Washington, D.C. Of counsel was Christopher S. Cole,

Trial Attorney, Commercial Law & Litigation Directorate, Department of the Air Force.

OPINION AND ORDER

LETTOW, Judge.

Bay County, Florida (“Bay County” or “the County”) seeks monetary relief for an alleged

breach of two contracts by which the Air Force (“Air Force” or “the government”) is purchasing

water and sewer services from the County. One of the contracts states that for unregulated utility

services, the Air Force is empowered to approve or reject potential rate changes proposed by the

utility. There is no clause in either contract describing the procedure for addressing rate changes

set by independently regulated utilities. Bay County contends that it acts as an independent

regulator of utility services, and that its rate changes apply to the Air Force. The Air Force

counters that Bay County acts as an unregulated utility, and, as such, the rate-change provision in

one of the contracts is triggered, along with an implied inclusion of the same provision in the

other contract, meaning that acceptance of rate changes by the Air Force is discretionary. Bay

County alleges that as an outcropping of this dispute over the terms of the contracts, the Air

Force has failed to pay contractually mandated utility rates since 2007 and now owes Bay

County the balance of unpaid invoice charges, totaling approximately $850,000.

Pending before the court are Bay County’s and the government’s motions for summary

judgment filed pursuant to Rule 56 of the Rules of the Court of Federal Claims (“RCFC”). The

motions have been fully briefed and a hearing was held on June 5, 2013. The government filed a

post-hearing supplemental submission on June 12, 2013.

BACKGROUND

Bay County is a subdivision of the State of Florida and is empowered by state law to

“[p]rovide and regulate” such utilities as water and sewage for the County. Florida Statutes,

Section 125.01(k)(1); see Compl. ¶¶ 10-11. Acting on that authorization, for some years it has

contracted with Tyndall Air Force Base (“Tyndall” or “the Air Base”) for the provision of such

services to the Air Base, which is located in Bay County. See, e.g., Compl., Ex. 8 (1966 Water

Contract). Unlike certain other military bases in the country, Tyndall contracts directly with Bay

County and purchases utilities at wholesale rates. Compl. ¶¶ 30-31.1

The two contracts at issue are for purchase of sewage and water services, and were

entered in 1985 and 1988, respectively. See First Statement of Undisputed Facts, Ex. C (1985

Sewage Contract) (“Sewage Contract”); Compl., Ex. 7 (1988 Water Contract) (“Water

Contract”). 2 The Water Contract had its genesis in an earlier contract entered in 1966, under

1

Bay County historically has provided potable water to Tyndall Air Base at a “wholesale”

rate which also applies to all of the municipalities in Bay County. See First Statement of

Undisputed Facts, Aff. of Paul Lackemacher (Jan. 30, 2012) ¶¶ 12-16, ECF No. 17-4. “Bay

County’s other wholesale customers are by contract . . . entitled to the lowest rate charged to any

other wholesale customer, including Tyndall.” Aff. of Ashley Stukey (Feb. 8, 2013) ¶ 8, ECF

No. 53-1. Accordingly, the result in this case will have a bearing on the rates charged by Bay

County to all of its municipal customers.

2

Bay County filed a Statement of Undisputed Facts in support of its first motion for

summary judgment on January 30, 2012. See ECF No. 17. The government did not respond to

the Statement, nor did it file its own statement of undisputed facts in connection with a cross-

motion for summary judgment. See Def.’s Mot. for Summary Judgment (Jan. 30, 2012), ECF

No. 18. The government did, however, file an extensive documentary appendix with its cross-

motion. Id. Thereafter, because of perceived deficiencies in the record, Bay County’s motion

and the government’s cross-motion were denied without prejudice to renewal. See Order of

Sept. 25, 2012, ECF No. 40; Order of Jan. 15, 2013, ECF No. 45.

Subsequently, the County and the government filed the renewed motions for summary

judgment which are now before the court, and the County filed a Second Statement of

Undisputed Facts in support of its renewed motion. See Second Statement of Undisputed Facts

(Feb. 8, 2013), ECF No. 55. The government again has failed to respond directly to the

assertions of fact in the Second Statement, although, as before, it submitted a lengthy

documentary appendix to its second motion for summary judgment. See App. to Def.’s Renewed

Mot. for Summary Judgment (Jan. 11, 2013), ECF Nos. 44-1 and 44-2. Thus, pursuant to RCFC

56(c)(1) and (e)(2), the court considers facts asserted and supported in the Second Statement to

be undisputed for purposes of the pending cross-motions for summary judgment, to the extent

that they are not specifically contested or challenged by the government in its briefing.

2

which contract Bay County increased its rates fourteen times over fifteen years, without any

apparent acrimony between the parties. Second Statement of Undisputed Facts ¶¶ 22-23. In

1988, the old water contract was superseded by the current contract, which is the one at issue in

this case. See Water Contract. The new Water Contract contained the following “change of

rate” clause:

No increase shall be requested in the contract rate unless the

Contractor has placed into effect a general rate increase to all of his

customers under similar conditions of service. If the Contractor

has placed into effect a general rate decrease, a corresponding

decrease in the contract rate shall be made.

Id. ¶ 3.

The Sewage Contract, made effective in 1985, contains a substantially similar clause

regarding rate changes. Sewage Contract, Additional Provisions ¶ 2(b). That clause is preceded

by an additional restriction on changes of rate, specifying a process of negotiation prior to any

implementation:

At the request of either party to this contract with reasonable cause,

the rates set forth herein shall be renegotiated and the new rates

shall become effective as mutually agreed — provided that any

rates so negotiated shall not be in excess of rates to any other

customer of the Contractor under similar conditions of service.

Id., Additional Provisions ¶ 2(a).

In December 1994, the Federal Acquisition Regulations were amended to create a

regulatory requirement that certain pre-established clauses be included in utility service contracts

such as the water and sewage contracts at issue here. 48 C.F.R. (“FAR”) § 41.501. The new

requirements in the FAR effectively replaced the earlier “change of rates” provision that had

been commonly used, not only in the contracts at issue in this case but in many other contracts

for utility services provided to federal installations.3 The requirements specify that “under the

prescribed conditions,” “[t]he contracting officer shall insert clauses substantially the same as the

clauses listed” in the FAR. FAR § 41.501(d). Two different “change of rate” clauses are

provided, one prescribed for use in connection with regulated services, and the other for

unregulated services. See FAR §§ 41.501(d)(1) and (2). The text of those clauses is found at

FAR §§ 52.241-7 and 52.241-8, respectively. Where regulated services are being supplied, the

The underlying documentation supporting both of Bay County’s Statements is appended

to the First Statement, and was not re-filed with the court, and any citations to those documents

are to those accompanying the First Statement.

3

The change-of-rate provisions had acquired an interpretive gloss through a decision of

the Federal Circuit in City of Tacoma v. United States, 31 F.3d 1130 (Fed. Cir. 1994).

3

utility is instructed to notify the government of application to and approval by the regulatory

body of any changes in rates or terms and conditions of service, and the government is obligated

to accept the change. FAR § 52.241-7.4 In the case of unregulated services, rate changes may

only be accomplished through negotiation between the utility and the government. FAR §

52.241-8.5

In 1997, Bay County and the Air Force executed a bilateral modification to the Sewage

Contract, conforming various provisions of the original contract to those newly required by the

FAR. See Compl., Ex. 6 (1997 Sewage Contract Amendment). Among the provisions included

in the amendment is one concerning changes in rates, specifically the provision prescribed for

use in contracts with unregulated utility service providers, FAR § 52.241-8. Compl., Ex. 6 at 5.

Whether the Water Contract was also so amended appears to be a mystery to the parties; no such

amendment has been provided to the court. See Hr’g Tr. at 7:19-22 (June 5, 2013)6 (“[O]f

4

The relevant text of the change-of-rate provision in FAR § 52.241-7 states:

This clause applies to the extent services furnished under this contract are

subject to regulation by a regulatory body. The Contractor agrees to

give . . . written notice of (1) the filing of an application for change in

rates or terms and conditions of service concurrently with the filing of the

application and (2) any changes pending with the regulatory body as of the

date of the contract award. Such notice shall fully describe the proposed

change. If, during the term of this contract, the regulatory body having

jurisdiction approves any changes, the Contractor shall forward to the

Contracting Officer a copy of such changes within 15 days after the

effective date thereof. The Contractor agrees to continue furnishing

service under this contract . . . and the [g]overnment agrees to pay for such

service at the higher or lower rates as of the date when such rates are made

effective.

FAR § 52.241-7(a).

5

The relevant text of the change-of-rate provision in FAR § 52.241-8 states:

(a) This clause applies to the extent that services furnished

hereunder are not subject to regulation by a regulatory body.

(b) After ____ [insert date], either party may request a change in

rates or terms and conditions of service, unless otherwise provided

in this contract. Both parties agree to enter in negotiations

concerning such changes upon receipt of a written request detailing

the proposed changes and specifying the reasons for the proposed

changes.

FAR § 52.241-8(a), (b).

6

Further citations to the hearing held on June 5, 2013 will omit the date.

4

course, it’s clear that the 1997 modification as to the [W]ater [C]ontract does not exist. It may

have been destroyed or lost during the squadron reorganization a few years back.”); Def.’s

Renewed Mot. for Summary Judgment (Jan. 11, 2013) (“Def.’s Renewed Mot.”) at 15, ECF No.

44 (“[A] comparable bilateral modification incorporating FAR subpart 52.241-8 into the [W]ater

[C]ontract has not been located.”).

In 2000, Bay County increased the cost of water and notified the Air Force of the

increased rate; the Air Force acceded to the rate increase and paid invoiced amounts in full under

the new rate. See Second Statement of Undisputed Facts ¶ 26. In 2003, the Sewer Contract was

formally amended to reflect a rate increase, to which the Air Force did not object. Id. ¶ 35.

On October 1, 2007, Bay County adopted Resolution No. 2794, by which it increased

wholesale water rates by $0.55 per 1000 gallons and authorized further increases each

subsequent October 1st at three percent (or the percentage change in the Consumer Price Index,

whichever was lower) per year. See Second Statement of Undisputed Facts ¶¶ 26, 27. The Air

Force refused to recognize this rate increase and continued to pay at the previous rate. Id. ¶ 27.

On May 5, 2009, Bay County adopted another resolution, No. 2920, setting a five-year pro forma

rate scheme, effective October 1, 2009. Id. ¶ 28. Resolution No. 2920 and its accompanying

increases were likewise disregarded by the Air Force, which continued to pay the pre-2007 rate

for its water utility services at Tyndall. See id. ¶ 30.

On November 29, 2009, and October 27, 2010, the Air Force unilaterally modified the

Water Contract to reflect modest increases over the pre-2007 rate which it had previously been

paying. Second Statement of Undisputed Facts ¶¶ 29, 31. Both increases fell short of the

amounts invoiced by Bay County at the rate which had been set for wholesale customers,

including Tyndall and municipalities in the County. Id. ¶¶ 30-31; see also supra n.1. At the

time of the most recent increase by the Air Force’s unilateral action, the wholesale rate set by

Bay County was $1.79 per 1000 gallons, while the rate the Air Force determined it would pay

was $1.41 per 1000 gallons, leaving a disparity of $0.38 per 1000 gallons. Id. ¶ 31.

With respect to the Sewage Contract, Bay County notified the Air Force of proposed (and

ultimately adopted) rate increases on June 16, 2009. See Def.’s Renewed Mot. at 5. The

government has disputed these increases and declined to pay invoiced amounts reflecting the

higher rates, as it has done with the water rate increases. Id.

After unsuccessfully attempting to recover the amounts allegedly owed by the Air Force

for utility services through a claim to the Air Force’s Contracting Officer,7 Bay County filed suit

in this court on March 14, 2011. A first round of motions for summary judgment was filed in

early 2012, but those motions were dismissed without prejudice on September 25, 2012. The

parties filed renewed motions for summary judgment in January and February 2013, and

7

Bay County filed its certified claim with the Contacting Officer on April 19, 2010.

Second Statement of Undisputed Facts ¶ 42. That claim was denied on January 20, 2011. Id.

¶ 43.

5

briefing, a hearing, and a supplemental submission completed presentation of the cross-motions

to the court.

STANDARD FOR DECISION

Summary judgment is appropriate when the pleadings, affidavits, and evidentiary

materials filed in a case reveal that “there is no genuine dispute as to any material fact and the

movant is entitled to judgment as a matter of law.” RCFC 56(a). A material fact is one “that

might affect the outcome of the suit under the governing law.” Anderson v. Liberty Lobby, Inc.,

477 U.S. 242, 248 (1986). A genuine dispute is one that “may reasonably be resolved in favor of

either party.” Id. at 250. The absence of such genuine disputes must be demonstrated by the

moving party; in this respect, “the inferences to be drawn from the underlying facts . . . must be

viewed in the light most favorable to the party opposing the motion.” Matsushita Elec. Indus.

Co. v. Zenith Radio Corp., 475 U.S. 574, 587-88 (1986) (quoting United States v. Diebold, Inc.,

369 U.S. 654, 655 (1962)); see also Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986). In the

case currently before the court, each party has filed a motion for summary judgment. Because

cross-motions for summary judgment are pending, the court must evaluate each motion on its

own merits and “tak[e] care in each instance to draw all reasonable inferences against the party

whose motion is under consideration.” Mingus Constructors, Inc. v. United States, 812 F.2d

1387, 1391 (Fed. Cir. 1987).

In support of their motions, the parties may cite to “particular parts of materials in the

record, including depositions, documents, electronically stored information, affidavits or

declarations, stipulations . . . , admissions, interrogatory answers, or other materials.” RCFC

56(c)(1)(A). Summary judgment will be granted “[w]here the record taken as a whole could not

lead a rational trier of fact to find for the non-moving party.” Matsushita, 475 U.S. at 587

(quoting First Nat’l Bank of Ariz. v. Cities Serv. Co., 391 U.S. 253, 288 (1968)).

This necessarily is a suit for partial breach of contract because the Water Contract and

Sewage Contract continue in effect. “If the injured party elects to or is required to await the

balance of the other party’s performance under the contract, his claim is said . . . to be one for

damages for partial breach [rather than for a total breach].” Restatement (Second) of Contracts §

236 cmt. b (1981); see also Indiana Mich. Power Co. v. United States, 422 F.3d 1369, 1374

(Fed. Cir. 2005) (applying Restatement (Second) of Contracts § 236)). In essence, “[a] partial

breach is ‘[a] claim for damages . . . based on only part of the injured party’s remaining rights to

performance.” Indiana Mich., 422 F.3d at 1374 (quoting Restatement (Second) of Contracts §

236(2)). “[W]here there has been no repudiation [e.g., no total breach], the plaintiff can recover

damages for his injury only to the date of the writ. . . . [H]e must treat the breach as only

‘partial.’” 10 Arthur L. Corbin, Corbin on Contracts § 956 (interim ed. 2007). Bay County’s

claim is premised upon the Air Force’s partial breach of the Water Contract and Sewage

Contract. If Bay County prevails, its damages will be limited to those incurred prior to the date

of suit. Indiana Mich., 422 F.3d at 1376. To succeed in its suit for partial breach of contract,

Bay County must establish the four elements of breach: “(1) a valid contract between the parties,

(2) an obligation or duty arising under the contract, (3) a breach of that duty, and (4) damages

caused by the breach.” Steinberg v. United States, 90 Fed. Cl. 435, 444 (2009) (citing San

Carlos Irrigation & Drainage Dist. v. United States, 877 F.2d 957, 959 (Fed. Cir. 1989)).

6

ANALYSIS

The parties are generally in agreement as to the factual underpinnings of the case.

Neither side contests the fact that express contracts were formed between Bay County and

Tyndall for the utility services at issue. There is no dispute over whether Bay County approved

and gave notice to Tyndall of its rate changes as they were adopted. They also agree that

Tyndall has refused to pay the invoiced amounts in full since 2007. The parties disagree as to

their respective duties regarding determining, approving, or paying changed rates. The dispute

turns on (1) whether Bay County is an independent regulatory body and governed by FAR §

54.241-7, or a non-independent regulatory body as in FAR § 54.241-8; and (2) if Bay County’s

utilities are independently regulated, whether the inclusion of FAR § 54.241-8 in the sewage

contract is sufficient to negate or waive Bay County’s change-of-rate privileges as an

independently regulated utility. The second issue need only be reached if the first issue is

resolved in Bay County’s favor.

Bay County contends that its utilities are independently regulated and looks to FAR

§ 54.241-7 to argue that it is entitled to set rates free from any obligation to negotiate rates with

Tyndall. See Pl.’s Second Mot. for Summary Judgment (Feb. 8, 2013) (“Pl.’s Renewed Mot.”) at

2-4, ECF No. 54. The government counters that Bay County does not qualify as an independent

regulatory body, and consequently any changes of rate must be agreed by the Air Force to be

valid, obviating any claims of breach on the part of the government for failing to pay in full rates

it had not accepted. Def.’s Renewed Mot. at 7.

A. Bay County’s Status

The Defense Federal Acquisition Regulation Supplement (“DFARS”) applies and

contains an explicit definition of the contested terms:

Independent regulatory body means the Federal Energy Regulatory

Commission [(“FERC”)], a state-wide agency, or an agency with

less than state-wide jurisdiction when operating pursuant to state

authority. The body has the power to fix, establish, or control the

rates and services of utility suppliers.

Non[-]independent regulatory body means a body that regulates a

utility supplier which is owned or operated by the same entity that

created the regulatory body, e.g., a municipal utility.

48 C.F.R. (“DFARS”) § 241.101. Bay County is neither FERC nor a state-wide agency. See

Fla. Const. art 8 § 1. Therefore, if Bay County is to be considered an independent regulatory

body, it must satisfy the third criterion or fail in its suit. Bay County must show that it is an

agency with less than state-wide jurisdiction operating pursuant to state authority.

Bay County is a Florida county, and under Florida law it is considered both an agency of

the state and an independent local actor, depending upon the type of action involved. See Amos

v. Mathews, 126 So. 308, 321 (Fla. 1930) (“[T]heir existence as local entities for local purposes

7

as well as their existence as legal political divisions of the state is recognized by the Constitution.

. . . While the county is an agency of the state, it is also under our Constitution, to some extent

at least, an autonomous, self-governing, political entity with respect to exclusively local

affairs.”). Florida counties act as agencies of the state when they perform acts delegated to them

by the state, e.g., assessing and imposing taxes for county purposes. See Whitney v.

Hillsborough Cnty., 127 So. 486, 493 (Fla. 1930) (“The delegation of the power [to collect

county taxes] under such circumstances is tantamount to the state empowering, not a mere

statutory board possessing no governmental status, but a constitutionally recognized

governmental agency to act for it in matters of local taxation.”); Collier Cnty. v. State, 733 So. 2d

1012, 1019 (Fla. 1999) (“[T]he [c]ounty has no inherent power to tax, but obtains that authority

only from the constitution and general law.”).

When Bay County acts to regulate its utility rates, it is exercising a power delegated to it

by the State of Florida, as contrasted to an inherent power over exclusively local affairs:

Any of the several counties of the state which may hereafter come

under the provisions of this chapter as hereinafter provided is

hereby authorized and empowered . . . (3) To fix and collect rates,

fees and other charges for the service and facilities furnished by

any such water supply system or water system improvements and

sewage disposal system or sewer improvements and to fix and

collect charges for making connections with the water system of

the county.

Fla. Stat., tit. 11, ch. 153.03 (emphasis added); see also Fla. Stat., tit. 11, ch. 125.01(1) (“The

legislative and governing body of a county shall have the power to . . . [p]rovide and regulate

waste and sewage collection and disposal [and] water and alternative water supplies.”)

(emphasis added).

The government contends that Bay County must be a non-independent regulatory body

because “its utilities are owned and operated by the very same entity that establishes their rates

— namely, the Bay County Board of County Commissioners.” Def.’s Renewed Mot. at 22. It

presses the proposition that “[t]o come within the definition of an ‘independent regulatory body,’

Bay County, as regulator[,] would have to be independent from Bay County as utility supplier.”

Def.’s Reply in Support of its Renewed Mot. for Summary Judgment and Response to Pl.’s

Cross-Mot. for Summary Judgment (Apr. 25, 2013) (“Def.’s Reply”) at 2, ECF No. 64. This

argument by the government is based upon the broad purposes of the FAR and DFARS and does

not comport with a plain reading of DFARS § 241.101. “[B]road purposes” do not trump

specific and plain regulatory language. See Board of Governors of the Fed. Reserve Sys. v.

Dimension Fin. Corp., 474 U.S. 361, 373 (1986) (refusing to accept an argument based upon

“[a]pplication of ‘broad purposes’ of legislation at the expense of specific provisions”). Instead,

“[i]f the [regulation] is clear and unambiguous, ‘that is the end of the matter.’” Id. at 368

(quoting Chevron U.S.A. Inc. v. Natural Resources Def. Council, Inc., 467 U.S. 837, 842-43

(1984)). To be a non-independent regulatory body, Bay County would have to “regulate[] a

utility supplier which is owned or operated by the same entity that created the regulatory body.”

FAR § 241.101. Definitionally, the relevant relationship is not between the owner or operator of

8

the utility and its regulator, but rather between the owner or operator and the entity which

created the regulator. In the present case, Bay County owns, operates and regulates the utility,

but was itself created by the State of Florida and, specifically, was created as a regulator by the

State of Florida. In sum, Bay County is an independent regulatory body under the definitions in

the DFARS because the County has less than statewide regulatory jurisdiction but exercises that

regulatory jurisdiction “pursuant to state authority.” DFARS § 241.01.

B. Negation of Independent Regulatory Privileges

The government argues that, regardless of Bay County’s classification under the criteria

in the DFARS, Bay County effectively conceded its status as a non-independent regulatory body

by accepting the terms of the original Sewage Contract and the subsequent bilateral modification

incorporating FAR § 52.241-8 in 1997. Def.’s Renewed Mot. at 15.8 As a result of this asserted

concession and waiver, the government contends that Bay County is bound by the change-of-rate

clause set out in FAR § 52.241-8, and must accede to negotiation and approval by the Air Force

prior to raising its utility rates on either contract. Bay County, in turn, submits that such an

arrangement would violate Florida law, and thus could not be a reasonable interpretation of the

contract. Pl.’s Renewed Mot. at 10-11 (citing Fla. Stat., tit. 11, ch. 153.11 (specifying rate-

setting procedures by which the county commission revises rates absent negotiation)). The court

need not reach the question of whether Bay County could legally have contracted as an

unregulated utility because the government’s contention that Bay County actually contracted

away its status as an independent regulatory body is unavailing.

The government argues that Bay County waived its potential status as an independent

regulatory body by including FAR § 54.241-8 in the Sewage Contract — ignoring the limitation

of Subsection (a) on application, viz., “[t]his clause applies to the extent that services furnished

hereunder are not subject to regulation by a regulatory body.” FAR § 52.241-8(a); see Hr’g Tr.

11:11 to 12:1. Pointing to the principle that this court must avoid contract interpretations that

render the FAR or contract terms superfluous, the government contends that the only way to give

meaning to the Sewage Contract is to treat Bay County as a non-independent regulatory body.

Hr’g Tr. 11:13 to 15:3. In making this argument, the government implicitly urges that a

contractual provision that is inapplicable by its own terms must take precedence over the FAR’s

requirements. The court cannot accede to such a proposition.

When a contract subject to the FAR incorporates improper terms of the FAR, the correct

provisions of the FAR control. See S.J. Amoroso Const. Co. v. United States, 12 F.3d 1072,

1075 (Fed. Cir. 1993); G.L. Christian & Assocs. v. United States, 312 F.2d 418, 426 (Ct. Cl.

8

As the government puts it, “Bay County’s status as a ‘non[-]independent regulatory

body’ is a settled issue.” Def.’s Renewed Mot. at 15 (heading; capitals omitted); Def.’s Reply at

3 (same).

Although the government admits that no corresponding modification to the Water

Contract has been located, it contends that such a modification must exist because “it would be

irrational to conclude that the parties contemplated that Bay County’s status as a non-

independent regulatory body as reflected in the . . . [S]ewer [C]ontract . . . would not apply to the

[W]ater [C]ontract.” Def.’s Renewed Mot. at 15.

9

1963), mot. for rehearing and reargument denied, 320 F.2d 345 (Ct. Cl. 1963). “Under the so-

called Christian doctrine, a mandatory contract clause that expresses a significant or deeply

ingrained strand of procurement policy is considered to be included in a contract by operation of

law.” S.J. Amoroso, 12 F.3d at 1075. In S.J. Amoroso, as here, an improper clause was

substituted for a proper clause. Id. As S.J. Amoroso held, “[a]pplication of the Christian

doctrine turns not on whether the clause was intentionally or inadvertently omitted, but on

whether procurement policies are being ‘avoided or evaded (deliberately or negligently) by lesser

officials.’” Id. (citing G.L. Christian & Assocs., 320 F.2d at 351). The proper clause was

consequently given effect. Id. at 1077.

In this instance, inclusion of the clause prescribed for unregulated utilities constitutes

such an impermissible deviation. See FAR § 1.401 (“Deviation means . . . [t]he omission of any

solicitation provision or contract clause when its prescription requires its use . . . [or] [t]he use of

a solicitation provision or contract clause . . . if such use is inconsistent with the intent, principle,

or substance of the prescription or related coverage on the subject matter in the FAR.”). The text

of the FAR is unambiguous in its requirement for inclusion of the proper change of rate clause:

“The contracting officer shall insert clauses substantially the same as the clauses listed below in

solicitations and contracts under the prescribed conditions.” FAR § 41.501(d) (emphasis added).

The prescribed condition for inclusion of FAR § 52.241-7 is that the utility services “are subject

to a regulatory body.” Id. As established supra, Bay County qualifies as an independent

regulatory body, and as such, FAR § 52.241-7 is a required term of the utility contract.

Correspondingly, FAR § 52.241-8 is inappropriate. Although deviations may be authorized by

the agency head for individual contract actions, such a deviation must be documented and

justified in the contract file. FAR § 1.403. No such documentation or justification is present

here.

Accordingly, the Christian doctrine applies and binds the contracting parties to the

mandatory contractual term. See G.L. Christian & Assocs., 312 F.2d at 426 (“We are not, and

should not be, slow to find the standard [regulation-mandated] article incorporated, as a matter of

law, into plaintiff’s contract if the [r]egulations can fairly be read as permitting that

interpretation.”). “Such regulations are law, binding on the contract parties” when otherwise

applicable to the contract, Dravo Corp. v. United States, 480 F.2d 1331, 1333 (Ct. Cl. 1973), and

“need not be physically incorporated into the contract,” First Nat’l Bank of Louisa, Ky. v. United

States, 6 Cl. Ct. 241, 244 (1984) (citing Hills Transp. Co. v. United States, 492 F.2d 1394, 1396

(Ct. Cl. 1974)); see also Bethlehem Steel Corp. v. United States, 423 F.2d 300, 305 (Ct. Cl. 1970)

(holding that the regulation need not be in effect when the contract was awarded so long as

adoption of the regulation was remedial and intended to afford safeguards to the contractor). The

court determines as a matter of law that the clause pertaining to independently regulated utilities,

FAR § 52.241-7, is incorporated into the contract in place of the improper clause, FAR § 52.241-

8, which is physically present.9

9

FAR § 52.241-8 would in any event not control the utility service contracts in this case

because the provision is conditional and the condition is not triggered. See FAR § 5.241-8(a)

(“This clause applies to the extent that services furnished hereunder are not subject to regulation

by a regulatory body.”).

10

In sum, the physical presence of FAR § 52.241-8 in the Sewage Contract (and its inferred

presence in the Water Contract) does not negate Bay County’s actual status as an independent

regulatory body. The Sewage Contract and Water Contract incorporated FAR § 52.241-7 as a

matter of law, and nothing in the parties’ contractual implementation would permit the

substitution of FAR § 52.241-8. On the record at hand, Bay County has adhered to the

requirements of FAR § 52.241-7 and Florida law in setting and revising its utility rates. The Air

Force’s unilateral modifications of the Water Contract in 2009 and 2010, see supra p. 5, are

invalid and cannot be given effect.

CONCLUSION

There are no genuine issues of material fact in this case which preclude summary

judgment. Bay County, through its state-delegated regulatory power, approved and gave notice

to the government of utility rate increases. The FAR and DFARS explicitly permit Bay County,

as an independent regulatory body, to revise rates without resorting to negotiation with Tyndall

Air Force Base. In light of the Air Force’s admitted refusal to remit all of the invoiced amounts

under these legally enforceable rates, no rational trier of fact could find in the government’s

favor. Accordingly, the government’s renewed motion for summary judgment is DENIED, and

the plaintiff’s renewed motion for summary judgment is GRANTED as to liability.

Bay County has requested relief in the form of damages “for the balance of unpaid

invoiced charges certified in its Claim, and accruing thereafter.” Compl. ¶ 40. Because the

breach is partial and continuing, its damages are limited to those incurred prior to filing suit in

this court. Indiana Mich., 422 F.3d at 1376. The parties have neither briefed nor stipulated to

the particular amount of damages accrued during the pertinent time period. Consequently, the

determination of damages is reserved for further proceedings.10

The court requests that the parties confer and then provide a joint status report on or

before September 10, 2013, setting out a proposed plan and schedule for further proceedings

related to damages.

It is so ORDERED.

s/ Charles F. Lettow

Charles F. Lettow

Judge

10

Pursuant to the Contract Disputes Act, Bay County will be entitled to interest on the

final amount, commencing from the date of the Air Force Contracting Officer’s receipt of Bay

County’s certified claim for amounts due under these contracts. See 41 U.S.C. § 7109(a)(1).

Bay County retains the right to sue again at a later date for damages related to this same breach

which are not encompassed by the result in this action. See Indiana Mich., 422 F.3d at 1378

(citing Restatement (Second) of Judgments, § 26 (1982)).

11