Opinion

RGD HOLDING COMPANY, LLC v. PERKINS

Court
District Court, D. New Jersey
Filed
Feb 28, 2022
Cited by
0 cases
Authority
More cited than 25.4%

“The general rule . . . is that a claim for indemnity does not accrue until the indemnitee’s liability is fixed by a judgment against or payment by the indemnitee.”

How later courts described this case

  • “The general rule . . . is that a claim for indemnity does not accrue until the indemnitee’s liability is fixed by a judgment against or payment by the indemnitee.”
  • “[T]he general rule [is] that a cause of action for contribution does not arise until the party seeking contribution has paid, or had a judgment rendered against him or her for, more than his or her fair share of common liability.”
  • “[I]t is well established that new arguments cannot be raised for the first time in reply briefs.”

Written by the judges who cited it.

The opinion

NOT FOR PUBLICATION

UNITED STATES DISTRICT COURT

DISTRICT OF NEW JERSEY

RGD HOLDING COMPANY, LLC, Civil Action No.: 2:21-cv-11602

Plaintiff,

v.

Opinion & Order

MICHAEL PERKINS, et al.,

Defendants.

CECCHI, District Judge.

This matter comes before the Court by way of Defendants Michael Perkins (“Perkins”) and

Tejash Shah’s (“Shah,” or, together with Perkins, “Defendants”) motion for judgment on the

pleadings, pursuant to Federal Rule of Civil Procedure 12(c). ECF No. 5. Plaintiff RGD Holding

Company, LLC (“Plaintiff” or “RGD”) opposed the motion (ECF No. 10), and Defendants replied

(ECF No. 11).

WHEREAS the instant action arises out of litigation related to a real estate dispute

currently pending in the Superior Court of Hudson County, New Jersey, Law Division filed on

October 26, 2016. See Dixon Mills Condo. Assoc., Inc. v. RGD Holding Co., LLC et al., No.

Hudson-L-4277-16 (N.J. Super. Ct. Law Div.) (“Underlying Action”); and

WHEREAS the Underlying Action brought by Dixon Mills Condominium Association,

Inc. alleges that in 2007 RGD and other named defendants in the Underlying Action converted a

rental property in Jersey City, New Jersey into a residential real estate complex comprised of

condominiums named the Residences at Dixon Mills (“the complex”). ECF No. 1-1, Exhibit A at

¶¶ 1, 43, 45. Perkins and Shah are not named defendants in the Underlying Action; and

WHEREAS the Underlying Action alleges that the building complex was governed by a

board of directors, on which RGD sat until May 2013. Id. at ¶ 61. The board was responsible for,

among other things, maintaining, repairing, renovating, and replacing any defects or deficiencies

identified at the complex, as well as managing the complex’s finances. Id. at ¶¶ 42, 66, 86; and

WHEREAS RGD and the other directors allegedly failed to perform their duties.

Specifically, the Underlying Action alleges that RGD and other board members failed to address

various defects and deficiencies throughout the building complex by neglecting to complete or

disclose to unit owners necessary renovations and repairs. Id. at ¶¶ 66–67. Moreover, for work the

board of directors did undertake, it allegedly used $1,000,000 of the building complex’s funds

when the work should have been paid for by RGD and others board members directly. Id. at ¶¶ 42,

85. The Underlying Action also alleges that RGD and the board of directors failed to sufficiently

fund the building complex’s capital reserve fund, impacting its ability to meet its financial

obligations. Id. at ¶¶ 91–101. The Underlying Action brings various claims to recover damages,

including common-law and statutory claims for breach of contract, breach of implied warranties,

breach of fiduciary duties, material misrepresentation, and fraud. See generally id.; and

WHEREAS within six years of the filing of the complaint in the Underlying Action, on

April 6, 2021, RGD initiated a separate action against Perkins and Shah in the Superior Court of

Hudson County, New Jersey, Law Division alleging that Perkins and Shah, as former board

members of the building complex, are also liable for the misconduct alleged in the Underlying

Action. See RGD Holding Co., LLC, v. Perkins et al., No. Hud-L-1350-21 (N.J. Super. Ct. Law

Div.); and

WHEREAS RGD alleges that Perkins and Shah were members of the building complex’s

board of directors with RGD prior to May 2013. ECF No. 1-1 at ¶¶ 14, 23. RGD further alleges

that, as board members, Perkins and Shah approved decisions regarding any deficiencies or defects

at the building complex, as well as approved decisions related to the complex’s capital reserve

fund. Id. at ¶¶ 24–25. Given their alleged participation in board decisions, RGD, in its Complaint,

brings claims for contribution (Count 1) and indemnification (Count 2) against Perkins and Shah

in the event RGD is held liable in the Underlying Action. Id. at ¶¶ 26–34; and

WHEREAS Perkins and Shah removed this action from the Superior Court of Hudson

County, New Jersey, Law Division to this Court on May 20, 2021, pursuant to 28 U.S.C. §§

1332(a)(1) and 1441 et seq. ECF No. 1. After filing their Answer to RGD’s Complaint (ECF No.

3), Defendants filed a motion for judgement on the pleadings on July 15, 2021 (ECF No. 5).

Plaintiff filed an opposition (ECF No. 10), to which Defendants replied (ECF No. 11); and

WHEREAS a party may bring a motion for judgement on the pleadings, pursuant to Fed.

R. Civ. P. 12(c), “[a]fter the pleadings are closed but within such time as not to delay the trial.”

Pleadings are considered closed for purposes of a Rule 12(c) motion when the “complaint and

answer are filed, along with any reply to additional claims asserted in the answer.” Horizon

Healthcare Servs., Inc. v. Allied Nat’l Inc., No. 03-4098, 2007 WL 1101435, at *3 (D.N.J. Apr.

10, 2007). To prevail, the moving parties must “clearly establish[] that no material issue of fact

remains to be resolved and that [they are] entitled to judgment as a matter of law.” Bayer Chem.

Corp. v. Albermarle Corp., 171 F. App’x 392, 397 (3d Cir. 2006) (quoting Jablonski v. Pan Am.

World Airways, Inc., 863 F.2d 289, 290 (3d Cir. 1988) (internal citations and quotations omitted)).

The Court must consider “the facts presented in the pleadings and the inferences to be drawn

therefrom in the light most favorable to the nonmoving party.” Hrinuk v. Pub. Serv. Elec. & Gas

Co., No. 14-cv-988, 2018 WL 621292, at *1–*2 (D.N.J. Jan. 30, 2018) (quoting Szczurek v. Prof’l

Mgmt. Inc., 627 F. App’x 57, 60 (3d Cir. 2015) (internal citations and quotations omitted)); and

WHEREAS here Defendants argue that Plaintiff’s claims should be dismissed because

they are time barred. Specifically, Defendants argue that, pursuant to N.J.S.A. § 2A:14-1, the

applicable New Jersey statute of limitations is six years and accrued when Defendants allegedly

committed misconduct in their capacity as board members of the building complex, positions they

held at some time before 2013. ECF No. 5-1 at 3–5. As Plaintiff waited until 2021 to file this

action, Defendants argue that more than six years have elapsed since their allegedly wrongful

conduct could have occurred most recently in 2013, and, accordingly, Plaintiff’s action is untimely.

Id.; and

WHEREAS while Plaintiff agrees N.J.S.A. § 2A:14-1 provides that the relevant statute of

limitations is six years, it argues that its claims for indemnification and contribution did not accrue

when Defendants’ alleged misconduct occurred, but rather will accrue when judgment is ultimately

rendered against Plaintiff in the Underlying Action. ECF No. 10 at 4–6. Because no judgment has

been rendered against Plaintiff in the Underlying Action, the statute of limitations has not begun

to run, and Plaintiff’s action is timely. Id.; and

WHEREAS under New Jersey law, a claim for indemnification begins to accrue at the

time judgment is rendered against the defendant for the underlying claim. See Holloway v. State,

593 A.2d 716, 722 (N.J. 1991) (citing McGlone v. Corbi, 279 A.2d 812, 817 (N.J. 1971)); see also

United N.Y. Sandy Hook Pilots Ass’n v. Rodermond Indus., Inc., 394 F.2d 65, 75 (3d Cir. 1968)

(“The general rule . . . is that a claim for indemnity does not accrue until the indemnitee’s liability

is fixed by a judgment against or payment by the indemnitee.”); and

WHEREAS similarly, under New Jersey law, a claim for contribution begins to accrue

“when the plaintiff recovers a judgment against [defendant].” Mettinger v. Globe Slicing Mach.

Co. 709 A.32d 779, 787 (1998) (citing McGlone, 279 A.2d at 817); see also Sea-Land Serv., Inc.

v. United States, 874 F.2d 169, 171 (3d Cir. 1989) (“[T]he general rule [is] that a cause of action

for contribution does not arise until the party seeking contribution has paid, or had a judgment

rendered against him or her for, more than his or her fair share of common liability.”); and

WHEREAS here, no judgment in the Underlying Action has been rendered or recovered

against RGD. ECF No. 10-1. Without such a judgment, the statute of limitations for neither

Plaintiff’s claim for indemnification, nor its claim for contribution has accrued. Accordingly,

Plaintiff’s claims are not barred by the applicable statute of limitations; and

WHEREAS Defendants argue, in the alternative, that, even if Plaintiff’s claims are not

time barred, they are unripe for adjudication because no judgment has been issued in the

Underlying Action. ECF No. 11 at 6. However, that argument is unavailing. New Jersey courts

allow indemnification and contribution claims to be brought before a defendant suffers a judgment

against it. See, e.g., Highland Lakes Country Club & Cmty. Ass’n v. Nicastro, 966 A.2d 1102,

1106–08 (N.J. Super. Ct. App. Div. 2009); see also Szaloczy v. KONE Elevators & Escalators,

No. 20-cv-3815, 2021 WL 2680185, at *7–*8 (D.N.J. June 29, 2021); and

WHEREAS to the extent Defendants argue that Plaintiff’s claims should be dismissed

because Plaintiff cannot establish that Defendants are liable for any underlying conduct to justify

contribution or indemnification (ECF No. 11 at 3–6), the Court need not address that argument at

this time as it is raised for the first time in Defendants’ reply brief. See D’Alessandro v. Bugler

Tobacco Co. et al., No. 05-5051, 2007 WL 130798, at *2 (D.N.J. Jan. 12, 2007) ((“A moving party

may not raise new issues and present new factual materials in a reply brief that it should have

raised in its initial brief.”) (quoting Int’l Raw Materials, Ltd. v. Stauffer Chem Co., 978 F.2d 1318,

1327 n.11 (3d Cir. 1992))); see also Jurista v. Amerinox Processing, Inc., 492 B.R. 779 (D.N.J.

2013) (“[I]t is well established that new arguments cannot be raised for the first time in reply

briefs.”) (footnote and citation omitted).

Accordingly, IT IS on this 28th day of February, 2022;

ORDERED that Defendants’ motion for judgment on the pleadings (ECF No. 5) is

DENIED.

SO ORDERED.

s/ Claire C. Cecchi

CLAIRE C. CECCHI, U.S.D.J.