“[T]he claimed injury cannot merely be possible, speculative[,] or remote.”
How later courts described this case
- “[T]he claimed injury cannot merely be possible, speculative[,] or remote.”
Written by the judges who cited it.
The opinion
NOT FOR PUBLICATION
UNITED STATES DISTRICT COURT
DISTRICT OF NEW JERSEY
HOLTEC INTERNATIONAL, et al.
Civil Action No. 20-12773 (MAS) (DEA)
MEMORANDUM OPINION
TOWNSHIP OF LACEY, et al.
Defendants.
SHIPP, District Judge
This matter comes before the Court upon Plaintiffs Holtec International (“Holtec”), Holtec
Decommissioning International, LLC (“HDI”), and Oyster Creek Environmental Protection,
LLC’s (“OCEP”) (collectively, “Plaintiffs”} Motion for a Temporary Restraining Order. (ECF No.
3.) Defendants Township of Lacey (the “Township”) and Lacey Township Planning Board (the
“Planning Board”) (collectively, “Defendants”) opposed (ECF Nos. 13, 15) and Plaintiffs replied
(ECF No. 18). The Court has carefully considered the parties’ submissions and decides the matter
without oral argument pursuant to Local Civil Rule 78.1. For the reasons set forth herein, Plaintiffs’
Motion is denied.
I. BACKGROUND
Plaintiffs own Oyster Creek Nuclear Power Station (“Oyster Creek”), a shutdown nuclear
power plant in Ocean County, New Jersey.' (Compl. J 1, ECF No. 1.) Oyster Creek is currently
1 OCEP and HDI are both wholly owned subsidiaries of Holtec, (Compl. 1 6.) OCEP is the licensed
owner of Oyster Creek and HDI serves as the plant’s decommissioning operator. (/d. { 7.)
undergoing decommissioning, a “process by which [a] plant is retired from service.” (/d.) The
decommissioning process is regulated by the Nuclear Regulatory Commission (“NRC”)? and
includes the transfer of all spent nuclear fuel from a spent fuel pool to an on-site storage facility
known as the Independent Spent Fuel Storage Installation (“ISFS!”). (/d. §f] 3-4.) In order to
perform the spent fuel campaign, Plaintiffs must first complete a mandatory dry run (i.e., practice
demonstrations). (/d. J 24.)
On July 9, 2020, Plaintiffs submitted a minor site application (the “Application”) to the
Planning Board, essentially seeking to expand the ISFSI area. (/d. {| 12.) The Planning Board,
however, denied the Application on August 24, 2020. (/d. { 18.) Plaintiffs assert that this denial
resulted in the suspension of a three-day dry run scheduled to begin on October 26, 2020.° (Dostal
Aff. 7 11, ECF No. 3-2.)
A. Oyster Creek Background
In January 2018, Exelon Generating Company, LLC (“Exelon”), the previous owner of
Oyster Creek, and the New Jersey Department of Environmental Protection entered into an
Administrative Consent Order (“ACO”) governing the decommissioning of Oyster Creek. (Compl.
2-3; ACO Doc., Ex. D to Compl., ECF No. 1-1.) Among other things, the ACO directed Exelon
to submit a Post-Shutdown Decommissioning Activities Report (“PSDAR”) to the NRC. (ACO
Doc. 1-2.) The ACO also provided that “Exelon will transfer all fuel to the ISFSI as soon as
technically and financially feasible and in accordance with the Facility’s PSDAR.” (/d. at 3.)
2 The NRC is an independent regulatory agency exercising all of the licensing and related
regulatory functions formerly assigned to the Atomic Energy Commission. 42 U.S.C. §§ 5841(f),
5842.
3 Plaintiffs indicate that a dry run related activity at their Camden Facility was scheduled for
September 28 through September 30, 2020. (Dostal Aff. { 11.)
On May 21, 2018, Exelon submitted the PSDAR, which included a “description of the
planned decommissioning activities [and] a schedule for their accomplishment.” (Exelon’s
PSDAR 3, Ex. E to Compl., ECF No. 1-1; Compl. 5.) The PSDAR indicates that Exelon selected
the SAFSTOR decommissioning method.* (/d. at 4-5.) Under SAFSTOR, Exelon intended to
commence the transfer of spent fuel to the ISFSI in March 2020 and expected to complete the
transfer in March 2024. (See id. at 8, 12.) According to the PSDAR, Exelon estimated the overall
decommissioning process would be completed by approximately 2078. (/d. at 8.) Exelon also
indicated in the PSDAR that no abnormal environmental issues were expected to result from use
of the SAFSTOR method. (See id. at 22-41.)
Sometime thereafter, Plaintiffs and Exelon entered into an agreement for the sale of Oyster
Creek that was subject to the NRC’s approval. (See Compl. 4 6.) In anticipation of the acquisition,
Plaintiffs submitted a revised PSDAR to the NRC on September 28, 2018. (/d. J 9; Pls.” PSDAR
4, Ex. F to Compl., ECF No. 1-1.) Unlike Exelon, Plaintiffs selected the DECON decommissioning
method.? (Pls.’ PSDAR 4.) Plaintiffs’ PSDAR appears to indicate that they intended to commence
the spent fuel campaign around June 2019 and expected to complete the transfer around June 2023.
(See id. at 17.) According to the PSDAR, Plaintiffs sought to complete the decommissioning
process, except for activities related to the ISFSI, “within approximately eight years of license
4 SAFSTOR is “[a] method of decommissioning in which a nuclear facility is placed and
maintained in a condition that allows the facility to be safely stored and subsequently
decontaminated (deferred decontamination) to levels that permit release for unrestricted use.”
(Exelon’s PSDAR 10.)
5 Plaintiffs PSDAR describes the DECON decommissioning method as follows: “The equipment,
structures, and portions of the facility and site that contain radioactive contaminants are promptly
removed or decontaminated to a level that permits termination of the license shortly after cessation
of operations.” (Pls.” PSDAR 4.)
transfer.” (/d. at 10.) On June 20, 2019, the NRC approved the transfer and Plaintiffs acquired
Oyster Creek shortly thereafter. (Compl. [J 11-12.)
B. Plaintiffs’ Application to the Planning Board
In December 2019, Plaintiffs submitted an initial application to the Planning Board seeking
approval to, among other things, expand the ISFSI pad to accommodate additional storage casks.
(Compl. 7 61; Dec. 2019 Appl., Ex. Q to Compl., ECF No. 1-3.) Plaintiffs assert that they
ultimately withdrew this application after determining that the proposed project was no longer
necessary. (Compl. {9 62-63.) Plaintiffs, however, allegedly performed unauthorized construction
at the site. Consequently, in March 2020, the Township issued a stop construction order to
Plaintiffs for failing to obtain construction permits. (Stop Construction Order Doc. (“SCO”), Ex.
S to Compl., ECF No. 1-3; Compl. § 64.) The order also advised Plaintiffs that they may resume
construction after obtaining the proper permits. (See generally SCO.) By correspondence dated
May 14, 2020, the Township again advised Plaintiffs to obtain the proper permits before
continuing construction at Oyster Creek. (May 14, 2020 Correspondence, Ex. D to Def. Twp.’s
Opp’n Br., ECF No. 15-1.)
After Plaintiffs allegedly continued unauthorized construction, the Township filed a
lawsuit in the Superior Court of New Jersey, Ocean County, Chancery Division,*® seeking to enjoin
Plaintiffs from continuing to undertake such work until they obtained the necessary approvals and
permits. (May 27, 2020 Superior Ct. Compl., Ex. E to Def. Twp.’s Opp’n Br., ECF No. 15-1;
Compl. J 66.) The Superior Court entered an order granting the Township’s requested relief.
(Compl. J 67.) On July 17, 2020, following settlement discussions by the parties, the Superior
6 Twp. of Lacey v. Holtec Int'l, Docket No. OCN-C-76-20.
Court entered a consent order resolving the matter. (/d. | 69; Consent Order, Ex. V to Compl.,
ECF No. 1-3.) The consent order indicated that Plaintiffs would submit a site plan application for
any prior and planned construction at Oyster Creek. (Consent Order { 1.)
That same month, Plaintiffs submitted the Application to the Planning Board in which they
described the project as “includ[ing] the filling of a hole where a concrete pad was originally
supposed to be constructed for spent fuel storage installation expansion.” (July 2020 Appl., Ex. G
to Compl., ECF No. 1-1.) The Planning Board held two hearings on the Application in August
2020 and, following the second hearing, denied the Application. (Compl. {J 74-75, 105.)
On September 14, 2020, the Planning Board adopted Resolution 20-SP-07 (the
“Resolution”) denying Plaintiff’s Application. (See generally Resolution Doc., Ex. Y to Compl.,
ECF No. 1-3.) In support of denying the Application, the Resolution provides in part that Plaintiffs
“mischaracterized the nature of the [A]pplication as a proposed temporary spent nuclear fuel
storage site” because Plaintiffs ‘provided absolutely no representation as to how many decades or
even centuries the ‘temporary’ storage will last.” (Resolution Doc. 163.) The Resolution also
provides that Plaintiffs “made numerous inconsistent, self-serving, misleading and non-credible
statements during [their] presentation.” (/d. at 164.) Consequently, the Township informed
Plaintiffs that they could not proceed with the dry run due to the Planning Board’s denial of the
Application.’ (Compl. J 79; Sept. 1, 2020 Correspondence, Ex. P to Compl., ECF No. 1-3.)
’ Plaintiffs and the Township direct the Court to a provision in the July 2020 consent order in
support of their respective positions regarding whether the dry run was contingent on Plaintiffs
obtaining the proper approvals and permits. The provision provides, in relevant part:
6. In the event the [Application] is approved by the Planning Board,
[Plaintiffs] shall apply for construction permits to use the Cask
Transfer Pit (“CTP’’) for its spent fuel transfer campaign. No new
construction may take place until a construction permit is issued,
and [Plaintiffs] have applied for permits and received the proper
C. Procedural History
On September 16, 2020, Plaintiffs filed a lawsuit against the Planning Board in the Superior
Court of New Jersey, challenging the Planning Board’s decision.*® (Sept. 2020 Superior Ct. Compl.,
Ex. 1 to Def. Planning Bd.’s Opp’n Br., ECF No. 13-1.) That same day, Plaintiffs filed the instant
two-count Complaint alleging: (1) federal preemption—specifically, that the Planning Board
improperly based its decision “solely on radiological safety concerns” because such concerns “are
within the exclusive province of the NRC” pursuant to the Atomic Energy Act, 42 U.S.C. § 2011
et seqg.—{Compl. ff 81-88); and (2) constitutional deprivation (id. fj 89-108).
On September 17, 2020, Plaintiffs filed the instant Motion, seeking to enjoin Defendants
from preventing the scheduled dry run and spent fuel campaign. (ECF No. 3.)
II. LEGAL STANDARD
“Preliminary injunctive relief is an extraordinary remedy and should be granted only in
limited circumstances.” Kos Pharms., Inc. v. Andrx Corp., 369 F.3d 700, 708 (3d Cir. 2004)
(internal quotation marks and citation omitted), This remedy should be granted only if Plaintiffs
establish that: (1) “they are likely to succeed on the merits of their claims”; (2) “they are likely to
suffer irreparable harm without relief’; (3) “the balance of harm favors them”; and (4) “relief □□ in
inspection. . . . It is understood that the CTP will NOT be used to
execute the spent fuel program, until [Plaintiffs] receive site plan
approval and construction permits. The Township agrees that the
performance of the NRC regulated dry runs may begin as scheduled
in September 2020 even if permits and the Certificate of Approval
are not issued at that time, however the spent fuel campaign shall
not begin until permits are issued. The Township agrees to work
with [Plaintiffs] to not impact this schedule, and to ensure that any
approvals will not be unreasonably withheld or delayed.
(Consent Order J 6; Compl. J§ 71, 79; Def. Twp.’s Opp’n Br. 4-5.)
8 Holtec Decommissioning Int'l v. Twp. of Lacey Planning Bd., Docket No. OCN-L-2165-20.
the public interest.” /ssa v. Sch. Dist. of Lancaster, 847 F.3d 121, 131 (3d Cir. 2017) (citation
omitted). Plaintiffs “must meet the threshold for the first two ‘most critical’ factors”—likely to
succeed on the merits and likely to suffer irreparable harm. Reilly v. City of Harrisburg, 858 F.3d
173, 179 (3d Cir. 2017), as amended (June 26, 2017). “If these gateway factors are met, a court
then considers the remaining two factors and determines in its sound discretion if all four factors,
taken together, balance in favor of granting the requested preliminary relief.” /d.
Ill. DISCUSSION
A. Irreparable Harm
1. Parties’ Positions
In support of their Motion, Plaintiffs submit the Affidavit of Jeffrey P. Dostal (“Dostal”),
HDI’s Site Vice President. (Dostal Aff., ECF No. 3-2.) There, Dostal recounts much of the facts
and allegations set forth above. (See id. {| 3-15.) Dostal asserts that the dry run “is essential to the
decommissioning process and essential to the safety of the community.” (/d. 4 16.) Dostal notes
that the “dry run procedure and subsequent spent fuel campaign include a tremendous commitment
of time, equipment, and personnel.” (/d. J 17.) Finally, Dostal contends that Defendants’ actions
carry a “potential” to adversely “impact and delay” the spent fuel campaign, which “severely
jeopardizes ([Plaintiffs’] agreement and obligations concerning the Oyster Creek
decommissioning.” (/d. 18.)
In their Moving Brief, Plaintiffs present two arguments in support of irreparable harm: (1)
“they cannot advance decommissioning Oyster Creek and/or the spent nuclear fuel transfer
campaign” in accordance with their revised PSDAR (Pls.’ Moving Br. 33); and (2) they are
“CunjJable to comply with the ACO” provision providing for the transfer of all nuclear fuel to the
ISFSI “as soon as technically and financially feasible and in accordance with the Facility’s
PSDAR” (id. at 34). Such noncompliance, Plaintiffs argue, “may . . . expose[] [them] to
assessments under the ACO that are tied to timely performance.” (/d.) In opposition, Defendants
contend that Plaintiffs’ alleged injury is financial in nature and, therefore, ultimately compensable.
(Def. Planning Bd.’s Opp’n Br. 16, ECF No. 13; Def. Twp.’s Opp’n Br. 16-18, ECF No. 15.)
Moreover, Defendants assert that Plaintiffs created the alleged injury by, among other things,
prematurely scheduling the dry run without first obtaining the proper permits and approvals. (Def.
Planning Bd.’s Opp’n Br. 3-4, 16; Def. Twp.’s Opp’n Br. 17.)
In reply, Plaintiffs seem to argue that delaying the dry run could result in irreparable harm
to the public’s safety. (See Pls.’ Reply Br. 8-9, ECF No. 18; Dostal Suppl. Aff. 4, ECF No. 18-
2.) In support, Plaintiffs rely on a Supplemental Affidavit from Dostal, who asserts that the spent
fuel pool at Oyster Creek has a “structural safety concern in that a crack could propagate due to
the external temperature,” which “could cause leaking” and “result[] in contamination spreading.”
(Dostal Suppl. Aff. | 7.) Dostal also asserts that “[a]n impact accident or terrorist attack that
damages a spent fuel pool could result in a partial or complete loss of water coolant,” which can
result in “the release of radioactive constituents to the environment.” (/d. { 8.) As an example,
Dostal points to the Fukushima Plant nuclear accident of 2011 where the plant’s spent fuel pool
lost water coolant “[a]s a result of an earthquake and tsunami.” (/d. 11; Pls.’ Moving Br. 9.)
2. Plaintiffs Fail to Establish They are Likely to Suffer Irreparable
Harm Absent Relief
To demonstrate irreparable harm, “a plaintiff has the burden of proving a clear showing of
immediate irreparable injury.” ECRI v. McGraw-Hill, Inc., 809 F.2d 223, 226 (3d Cir. 1987)
(internal quotation marks and citation omitted). Merely “[{ejstablishing a risk of irreparable harm
is not enough [to warrant a preliminary injunction].” /d.; see also Laidlaw, Inc. v. Student Transp.
of Am., 20 F. Supp. 2d 727, 766 (D.N.J. 1998) (“[T]he claimed injury cannot merely be possible,
speculative[,] or remote.”). “[T]he injury created by a failure to issue the requested injunction must
be of a peculiar nature, so that compensation in money cannot atone for it.” Acierno v. New Castle
Cnty., 40 F.3d 645, 653 (3d Cir. 1994) (internal quotation marks and citation omitted),
Here, the Court finds that Plaintiffs fall short of establishing a clear showing of immediate
irreparable harm. As Defendants note, Plaintiffs’ alleged injury appears to be self-created and
strictly financial in nature. That is, Plaintiffs seem to have prematurely scheduled the dry run
without first obtaining the proper permits and now, as Plaintiffs acknowledge, they potentially face
assessments under the ACO. (Pis.’ Moving Br. 34.) Moreover, the ACO itself sets no definite
schedule but rather merely provides that the spent fuel campaign should be completed “as soon as
technically and financially feasible.” (ACO Doc. 4.) Plaintiffs’ allegations, therefore, present no
more than a mere speculation of financial harm. Even if Plaintiffs had alleged a sufficiently
concrete financial injury, however, their argument would still fail because a “purely economic”
injury is ultimately compensable and therefore generally does not constitute irreparable harm.
Morton v. Beyer, 822 F.2d 364, 372 (3d Cir. 1987).
Plaintiffs also make an unavailing conclusory assertion that, because the “emergent
concerns related to radiological safety are certainly of a peculiar nature,” the harm is not
compensable. (Pls. Reply Br. 9.) While it is true that an environmental injury can constitute
irreparable harm, Amoco Production Company v. Village of Gambell, 480 U.S. 531, 545 (1987),
there are no facts set forth from which the Court could conclude that such injury is sufficiently
“likely” or “imminent.” Plaintiffs’ only evidence comes from Dostal’s Supplemental Affidavit in
which he “expand[s]” on his previous submission and posits that the spent fuel pool has structural
safety concems that may cause a leak and that radioactive constituents may be released if an
incident causes sufficient loss of water coolant. (Dostal Suppl. Aff. ff 3, 7-9.) This self-serving
statement, based primarily on the Fukushima incident that resulted from natural phenomena
unheard of in this state, and submitted for the first time in reply does not establish a sufficient
likelihood of environmental harm. Notably, Plaintiffs elected to change the decommissioning
method from SAFSTOR—in which Exelon reported that no abnormal environmental issues were
expected to result from the approximately sixty-year decommissioning process—to DECON.
(Compl. { 9.) Plaintiffs, therefore, cannot persuasively claim that postposing the dry run would
likely result in irreparable harm. The Court, accordingly, finds that Plaintiffs fail to establish a
likelihood of imminent irreparable harm.’
B. Younger Abstention
The Planning Board also argues that, due to the ongoing state court proceeding, this Court
should abstain from adjudicating this matter under Younger v. Harris, 401 U.S, 37 (1971). (See
Def, Planning Bd.’s Opp’n Br. 15 (citing Addiction Specialists, Inc. v. Twp. af Hampton, 411 F.3d
399, 408 (3d Cir. 2005) (discussing Younger abstention))}.) In response, Plaintiffs assert that they
are not seeking to overturn the Planning Board’s decision as in the pending state court action. (Pls.’
Reply Br. 16.) Rather, Plaintiffs assert they “are requesting that this Court, on the basis of federal
preemption, find that” Defendants are “frustrating the operation of a federally regulated facility
and the spent fuel transfer process with no jurisdiction to do so.” (/d.)
Federal district courts have a “virtually unflagging obligation” to adjudicate claims within
its jurisdiction. Deakins v. Monaghan, 484 U.S. 193, 203 (1988). “Although the general rule is that
the pendency of a state court proceeding is not a reason for a federal court to decline to exercise
Because the Court concludes that Plaintiffs fail to demonstrate irreparable harm, it does not
address the likelihood of Plaintiffs’ success on the merits of their claim. See Morton, 822 F.2d at
367 (“To obtain a preliminary injunction, the moving party must demonstrate both a likelihood of
success on the merits and the probability of irreparable harm if relief is not granted.”).
10
jurisdiction established by Congress, an exception to that rule is Younger abstention.” Yang v. Tsui,
416 F.3d 199, 201 (3d Cir. 2005) (citation omitted). Under the Younger abstention doctrine, “[a]
federal district court has discretion to abstain from exercising jurisdiction over a particular claim
where resolution of that claim in federal court would offend principles of comity by interfering
with an ongoing state proceeding.” Kendall v. Russell, 572 F.3d 126, 131 (3d Cir. 2009) (citing
Addiction Specialists, 441 F.3d at 408).
In Sprint Communications, Inc. v. Jacobs, the Supreme Court held that Younger abstention
is limited to “three exceptional categories[:]” (1) “state criminal prosecutions”; (2) “civil
enforcement proceedings”; and (3) “civil proceedings involving certain orders that are uniquely in
furtherance of the state courts’ ability to perform their judicial functions.” 571 U.S. 69, 73, 79
(2013) (citation omitted). In doing so, the Supreme Court rejected the Eighth Circuit’s
interpretation of Younger that was based on its previous decision in Middlesex County Ethics
Committee v. Garden State Bar Ass'n, 457 U.S. 423 (1982). Sprint Comme'ns, 571 U.S. at 81.
Specifically, the Supreme Court rejected the notion that Younger abstention is warranted
“whenever [the following] three conditions are met: [t]here is (1) an ongoing state judicial
proceeding; which (2) implicates important state interests, and (3) . . . provide[s] an adequate
opportunity to raise [federal] challenges.” /d. (third and fourth alterations in original) {internal
quotation marks and citation omitted). The Supreme Court stated that these conditions were “not
dispositive” but “were, instead, additional factors appropriately considered by the federal court
before invoking Younger.” Jd. (emphasis in original). The Supreme Court warned that “{dJivorced
from their quasi-criminal context, the three Middlesex conditions would extend Younger to
virtually all parallel state and federal proceedings, at least where a party could identify a plausibly
important state interest.” /d. This result, the Supreme Court noted, “is irreconcilable with □□□□□
Il
dominant instruction that, even in the presence of parallel state proceedings, abstention from the
exercise of federal jurisdiction is the exception, not the rule.” /d. at 81-82 (internal quotation marks
and citation omitted).
Here, the pending state court proceeding does not fall under any of the three categories
delineated by the Supreme Court in Sprint. That is, the state court action is neither a criminal
proceeding nor a civil enforcement proceeding. See id. at 79-80 (noting that civil enforcement
actions are “akin to a criminal prosecution” where “a state actor is routinely a party to the state
proceeding and often initiates the action”; the proceedings “are characteristically initiated to
sanction” a party “for some wrongful act”; and “[i]nvestigations are commonly involved, often
culminating in the filing of a formal complaint or charges.”). Moreover, the state court action does
not fall under the third category relating to the “state courts’ ability to perform their judicial
functions,” which has been applied to proceedings for “civil contempt order[s]” and “posting
bond{s] pending appeal.” /d. at 79. The Court, therefore, finds that Younger abstention is
inappropriate.
IV. CONCLUSION
For the reasons set forth above, Plaintiffs’ Motion for a Temporary Restraining Order is
denied. In addition, the Planning Board’s abstention request is denied. The Court will enter an
Order consistent with this Memorandum Opinion.
ftALef
MICHAEL A. SHIPP
UNITED STATES DISTRICT JUDGE
12