Opinion

York v. Northrop Grumman Corporation Guidance and Electronics Company Inc.

Court
District Court, W.D. Missouri
Filed
Aug 31, 2022
Cited by
0 cases
Authority
More cited than 24.3%

The opinion

IN THE UNITED STATES DISTRICT COURT FOR THE

WESTERN DISTRICT OF MISSOURI

SOUTHERN DIVISION

DON YORK, et al., )

)

Plaintiffs, )

v. ) No. 21-03251-CV-S-BP

)

NORTHROP GRUMMAN GUIDANCE AND )

ELECTRONICS COMPANY, INC., et al., )

)

Defendants. )

ORDER GRANTING IN PART DEFENDANTS’ MOTION TO DISMISS

Pending is Defendants’ Motion to Dismiss. The Court has considered the parties’ written

arguments and the arguments presented at the hearing on August 23, 2022. As set forth below, the

Motion to Dismiss, (Doc. 47), is GRANTED IN PART.

I. BACKGROUND

This case arises from the operations of Litton Systems Inc., (“Litton”), at its manufacturing

facility in Springfield, Missouri, (“the Site”). According to the Second Amended Complaint,

Litton began manufacturing printed circuit boards at the Site in the 1960s, and part of the process

involved the use of tricholorethyline, (“TCE”), which is a carcinogen.1 Litton’s method for

containing the TCE proved unsuccessful, and in 1982 the State of Missouri filed suit. That suit

was settled, with Litton paying a fine and being required to engage in various efforts to remediate

the contamination. (Doc. 44, ¶ 37.) The settlement also required Litton to construct a network of

monitoring and extracting wells to be placed under the State’s oversight, through the Missouri

1 The Court acknowledges the Second Amended Complaint’s footnote in the Introduction that other contaminants

were released as well. (Doc. 44, ¶ 3 n.1.) But Plaintiffs concede “the focus of this [Second Amended C]omplaint is

on TCE,” id., and the only contamination alleged to exist in their wells is TCE. (Doc. 44, ¶¶ 81, 83.) Thus, while the

footnote indicates (and Plaintiffs contended during the hearing) that contaminants other than TCE are at issue, this

contention is not supported by the remainder of the Second Amended Complaint.

Department of Natural Resources, (“MDNR”). (Doc. 44, ¶ 38.) At the time, there was no

indication that any private wells had been contaminated, although it was understood that

contamination could occur if the TCE was not contained and seepage continued. (See Doc. 44, ¶

36.)

In 1990 or 1991, contamination was discovered on the Site, which was later reported to

MDNR. (Doc. 44-10, ¶¶ 9-11.) This led the State and Litton to enter a Consent Agreement in

1993. (Doc. 44-10, ¶ 12.) As relevant to this suit, the 1993 Consent Agreement provides that

Litton “shall notify the MDNR immediately upon the occurrence of any event, which, in Litton’s

judgment, may threaten human health or the environment” and then provide a written notice

“which explains the event, any action taken to eliminate the threat, and the precautions to avoid

recurrence of a similar event.” (Doc. 47-2, § VII.) Defendants acquired the Site in 2001 and

assumed Litton’s responsibilities under the prior settlements with the State (including the 1993

Consent Agreement).

In 2004, testing conducted by Defendants (at MDNR’s behest, see Doc. 47-4, p. 3) revealed

that a private well had been contaminated with TCE. (Doc. 44, ¶¶ 117-19, 132.) This information

was conveyed to MDNR, (see Doc. 47-3, pp. 25, 327-31),2 but was not publicly announced until

sometime in 2018.3

2 The Court may take judicial notice of documents filed with the State and of public records, so it can consider these

materials when ruling on Defendants’ motion. Plaintiffs object on the ground that judicial notice cannot be used to

resolve disputed facts or to establish that facts contained within the documents are true. (Doc. 50, pp. 15-16.)

However, the Court is not taking judicial notice of these documents to establish the accuracy of the scientific

information contained in them; it is taking judicial notice of these documents to establish what information MDNR

purportedly possessed – which are facts that do not seem to be in dispute.

3 In 2010, the State sued Defendants because contamination spread from the Site, and that suit was settled via a Consent

Decree in 2011. Details about the 2010 suit and the 2011 Consent Decree are not relevant to the issues presently

before the Court, but they were discussed in the Court’s Order addressing Defendants’ Motion to Dismiss directed to

the First Amended Complaint. (Doc. 43, pp. 2-3.) The Court will, however, occasionally use the term “settlements”

to refer to both the 1993 Consent Agreement and the 2011 Consent Decree.

In 2016 or 2017, DNR conducted tests at a tourist attraction known as “Fantastic Caverns”

and discovered TCE vapor had seeped into the cave system. (Doc. 44, ¶ 46.) In 2018, MDNR

began testing wells around the Site and discovered some had been contaminated with TCE.

MDNR then offered free testing to property owners near the Site, which resulted in more positive

tests. (Doc. 44, ¶¶ 47-50.) “Where tests have found TCE in private wells, DNR and Defendants

have scheduled either quarterly or monthly follow ups to continue testing the wells.” (Doc. 44, ¶

52.)

Plaintiffs are individuals who own or lease property in Springfield, Missouri. Don and

Beverly York purchased their property in 2006; their daughter and husband are tenants on the

property. Plaintiffs Jack and Judy Harvey purchased their property “over 20 years ago,” (Doc. 44,

¶ 86), which suggests approximately 2001 or 2002. Plaintiffs learned that their well water was

contaminated with TCE from the Site in 2018, (Doc. 44, ¶¶ 81, 83), which impacts Plaintiffs in a

variety of ways, including by causing health concerns and creating potential difficulty selling the

properties.

The Second Amended Complaint asserts a single count of negligence, but the sole count is

premised on two discrete theories, which allege that Defendants: (1) breached a duty to warn that

TCE had spread into private wells when they learned that fact in 2004, (Doc. 44, ¶¶ 197, 200(1)),

and (2) negligently performed their duties under the Consent Agreement and the Consent Decree,

(Doc. 44, ¶ 200(2)). Additional details about Plaintiffs’ claims will be discussed as necessary in

Part II.4

Defendants seek dismissal, primarily contending that (1) Plaintiffs’ failure to warn claims

are preempted because they conflict with the 1993 Consent Agreement and (2) the negligence

4 Plaintiffs seek certification of four classes, (Doc. 44, ¶ 163-67), but the Court need not discuss this aspect of the

Amended Complaint. The Court similarly does not address the scope of relief to which Plaintiffs might be entitled.

claims should be dismissed because they fail to state a claim for which relief can be granted.

Plaintiffs oppose dismissal. The Court resolves the parties’ arguments below.

II. DISCUSSION

Under Rule 12(b)(6), the Court “must accept as true all of the complaint=s factual

allegations and view them in the light most favorable to the Plaintiff[ ].” Stodghill v. Wellston

School Dist., 512 F.3d 472, 476 (8th Cir. 2008); see also Alexander v. Hedback, 718 F.3d 762, 765

(8th Cir. 2013).

To survive a motion to dismiss, a complaint must contain sufficient factual matter,

accepted as true, to state a claim to relief that is plausible on its face. A claim has

facial plausibility when the plaintiff pleads factual content that allows the court to

draw the reasonable inference that the defendant is liable for the misconduct

alleged. The plausibility standard is not akin to a probability requirement, but it

asks for more than a sheer possibility that a defendant has acted unlawfully. Where

a complaint pleads facts that are merely consistent with a defendant’s liability, it

stops short of the line between possibility and plausibility of entitlement to relief.

Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (quotations and citations omitted). A claim is facially

plausible if it allows the reasonable inference that the defendant is liable for the conduct alleged.

E.g., Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 570 (2007); Horras v. American Capital

Strategies, Ltd., 729 F.3d 798, 801 (8th Cir. 2013). Finally, dismissal based on an affirmative

defense is permissible if the Complaint establishes that the defense exists. E.g., C.H. Robinson

Worldwide, Inc. v. Lobrano, 695 F.3d 758, 763-64 (8th Cir. 2012).

A. Failure to Warn and Conflict Preemption

Defendants argue that CERCLA preempts Plaintiffs’ claims predicated on the alleged

failure to disclose in 2004 that a private well was contaminated with TCE. This is not the first

time the Court has addressed the issue of conflict preemption in this case. The Court discussed

the issue in its Order addressing Defendants’ Motion to Dismiss the First Amended Complaint,

which held that Plaintiffs’ claims as pleaded were preempted but granted Plaintiffs an opportunity

to file a Second Amended Complaint to assert theories that they had discussed at oral argument

but had not clearly pleaded. Specifically, Plaintiffs were granted leave to more clearly state their

failure to warn claim because while it had been alluded to in the Amended Complaint it was not

clearly set forth as an independent theory of liability. (See Doc. 43, pp. 5-6, 15-16.)

The Court adopts its prior discussion about CERCLA preemption, (Doc. 43, pp. 7-12), in

full and sets forth only a summary here. CERCLA encourages a responsible party to enter an

agreement with the federal or state government to resolve the method for addressing a release of

environmental contaminants. Such an agreement has the effect of federal law, and state laws

(including state claims) that conflict with the agreement are preempted. The preemptive effect of

such a settlement means that the settling party cannot be sued to require it to do something other

than what is required by the settlement, nor can it be subjected to suit because the response called

for by the settlement is inadequate. Therefore, claims for damages resulting from (1) actions

required by a consent decree or (2) the failure to do more than is required/permitted by the

settlement are also preempted.

This feature of CERCLA derives from 42 U.S.C. § 9622(e)(6), which provides that once

an administrative order or consent decree is entered, “no potentially responsible party may

undertake any remedial action” that is not authorized by the order or decree.5 Courts uniformly

interpret this provision as prohibiting the settling party from taking any remedial action not

specified in the order or decree and hold that conflicting state claims are preempted. After

5 Defendants contend the 1993 Consent Agreement is an “administrative order” within the meaning of § 9622(e)(6).

(Doc. 47-1, p. 12.) Plaintiffs did not argue otherwise in their written arguments, but changed their position at the

hearing. The Court need not resolve the issue at this time. If it is not an “administrative order,” then § 9622(e)(6)

does not apply and Plaintiffs’ claims cannot be preempted; if it is an “administrative order,” the analysis in this Order

explains why Plaintiffs’ are not preempted.

discussing cases construing and applying § 9622(e)(6), the Court concluded (and adheres to the

conclusion) that Plaintiffs’ claims are preempted to the extent that they seek:

1. equitable relief requiring Defendants to undertake “remedial actions” different from or in

addition to those set forth in the settlements,

2. damages because Defendants failed to undertake “remedial actions” that were not required

by the settlements, or

3. damages because Defendants did something required by the settlements, so long as there

is not also a claim that Defendants performed that task improperly or negligently.

On the other hand, Plaintiffs’ claims are not preempted to the extent that they:

1. allege that Defendants negligently performed the tasks required by the settlements, or

2. arise from Defendants’ actions that were not required by the settlements.

The question now before the Court is whether publicly reporting the discovery of TCE in

a private well in 2004 constituted a “remedial action” within the meaning of § 9622(e)(6). The

Court concludes that public announcements and warnings are not “remedial actions” as defined by

CERCLA, so § 9622(e)(6) does not preempt claims based on the failure to make a public

announcement or warning.

As stated earlier, 42 U.S.C. § 9622(e)(6) provides that once an administrative order or

consent decree is entered, “no potentially responsible party may undertake any remedial action”

that is not authorized by the order or decree. The phrase “remedial action” is statutorily defined.

The definition begins by stating that the phrase means “permanent remed[ies]” and “removal

actions” designed “to prevent or minimize the release of hazardous substances so that they do not

migrate to cause substantial danger to present or future public health or welfare or the

environment.” 42 U.S.C. § 9601(24). The definition then sets forth a lengthy list of examples,

and the listed items constitute means for storing, cleaning, removing, or preventing the spread of

contamination. Thus, for instance, if an order or decree required a particular plan or method for

“storage” or “confinement” of hazardous waste, the specified plan would constitute “remedial

action” and the responsible party could not be held liable for using that plan or method or for

failing to use a different plan or method. However, nothing in the definition of “remedial action”

can be described as including public announcements about new discoveries of the spread of

hazardous waste.

Defendants emphasize that the 1993 Consent Agreement dictates what Defendants were to

do if new information (such as TCE’s presence in private wells) was discovered: they were to

notify MDNR. However, the fact that the 1993 Consent Agreement addressed the issue does not

make those aspects of the settlement “remedial action” as defined in the statute.

Defendants direct the Court to several cases that purportedly support their position that

warnings and announcements are within the scope of CERCLA preemption, but the Court

concludes that they do not support that position.6 They rely on Bethas v. Midland Refining Co.,

2000 WL 1920035 (D. Kan. Dec. 15, 2000), but the case does not address (or even cite) § 9601(24)

or § 9622. The plaintiff in that case sued, among others, the federal government for failing to issue

a public warning. The court concluded that the government’s decision whether to issue a warning

6 For their part, Plaintiffs cite Chestnut v. AVX Corp., 2009 WL 10678827 (D.S.C. Mar. 25, 2009), but that case only

addressed the nature of CERCLA preemption and not its scope. The issue decided was whether an assertion of

CERCLA preemption caused the case to arise under federal law such that jurisdiction could be based on 28 U.S.C. §

1331. (The parties were not of diverse citizenship, so jurisdiction could not lie under 28 U.S.C. § 1332, as it does in

the present case.) In that case the court simply held CERCLA did not preempt the field and CERCLA’s conflict

preemption was only a defense – and as a defense, the preemption argument did not appear in the well-pleaded

complaint so it did not provide a basis for jurisdiction. Chestnut, 2009 WL 10678827, at *4-5; see also Caterpillar

Inc. v. Williams, 482 U.S. 386, 393 (1987) (“Thus, it is now settled law that a case may not be removed to federal

court on the basis of a federal defense, including the defense of pre-emption, even if the defense is anticipated in the

plaintiff's complaint, and even if both parties concede that the federal defense is the only question truly at issue.”).

is a discretionary function and thus cannot form the basis for a claim under Federal Tort Claims

Act; preemption was not discussed. Bethas, 2000 WL 1920035, at *2-3.

Defendants also rely on Salerno v. City of Niagara Falls, 2020 WL 5814406 (W.D.N.Y.

Sep. 30, 2020), aff’d, 2021 WL 4592138 (2d Cir Oct. 6, 2021), which (1) mentioned only in passing

the plaintiffs’ claim based on “repeated failures to alert the public at large” and (2) did not discuss

§ 9601(24). Salerno, 2020 WL 5814406, at *6. In affirming the decision, the Second Circuit also

did not discuss § 9601(24) and did not mention the failure to warn claim. Further investigation

reveals there was no specific discussion of the failure to warn claim in the plaintiffs’ submissions

to either the District Court or the Second Circuit, much less any discussion about whether warnings

constitute “remedial actions” within the meaning of CERCLA.

Finally, Defendants point to the underlying complaint in Bartlett v. Honeywell Int’l, Inc.,

260 F. Supp. 3d 231 (N.D.N.Y. 2017), aff’d, 737 Fed. App’x 543 (2d Cir. 2018), which was

dismissed on preemption grounds. But, while the Amended Complaint in that case included

allegations about the defendants’ failure to disclose certain information, none of the three counts

asserted in the Amended Complaint were based on those facts. Moreover, the District Court’s

description of the claims analyzed in its decision does not include a failure to warn claim. Bartlett,

260 F. Supp. 3d at 238-39. Therefore, Bartlett did not address the issue presently before the Court.

Defendants also point to EPA regulations addressing community relations and

communications with the public. 40 C.F.R. § 300.430(c). As Defendants concede, however, the

EPA cannot expand the scope of the preemption set by Congress when it passed § 9622(e)(6) or

declare actions as “remedial” if they do not satisfy the definition in § 9601(24). During the hearing,

Defendants contended the EPA intended § 300.430(c) to interpret the phrase “remedial action.”

The Court does not believe this to be the case for several reasons. First, Congress defined remedial

activity when it passed § 9601(24). Second, § 300.430(c) focuses on the community relation

requirements created elsewhere in the regulation and contains no language suggesting it is

interpreting § 9601(24) or § 9622(e)(6). Third, even if the EPA intended to interpret the phrase

“remedial action,” it could not do so in a manner that is inconsistent with § 9601(24). Community

announcements and warnings do not fall within Congress’s definition in that they are not actions

intended “to prevent or minimize the release of hazardous substances so that they do not migrate”

and are not similar to any of the examples Congress enumerated. The Court does not believe the

EPA could interpret § 9601(24) to include actions that are not described by Congress’s definition

or that are not like the examples Congress listed. The 1993 Consent Agreement’s requirement that

Defendants notify MDNR is thus a floor, not a ceiling; it required Defendants to notify MDNR but

did not preclude Defendants from reporting to MDNR and making a public announcement, so §

9622(e)(6) does not preempt a failure to warn claim.

As an alternative argument, Defendants contend a failure to warn claim is not viable

because they immediately notified MDNR that TCE was discovered in a private well. But they

cite no statute supporting this argument, and the cases they cite do not hold that a failure to warn

claim is not viable if the responsible party notified government officials. Defendants rely heavily

on Kirk v. Schaeffler Group USA, Inc., 887 F.3d 376 (8th Cir. 2018), which, inter alia, affirmed

liability for a responsible party based on a failure to warn theory. In that discussion the Eighth

Circuit stated: “Though [defendant] FAG Bearings argued that it had no knowledge of off-site

contamination . . . there was evidence that [it] knew of on-site TCE contamination before the

agencies did, and failed to warn the surrounding communities of potential risk.” 887 F.3d at 393.

However, neither this statement nor anything else in the opinion holds that a government agency’s

knowledge of contamination precludes an action against the responsible party for failure to warn.

In context (and as confirmed by the briefs submitted to the Eighth Circuit), this comment was

addressing FAG Bearings’ argument that it could not be liable for a failure to warn because

government agencies had already told the public about the TCE contamination so the public

already had the information the plaintiffs’ alleged FAG Bearings should have provided to them.

It was in this context that FAG Bearings’ knowledge of the contamination before the government’s

announcement was relevant; the Eighth Circuit did not hold that mere knowledge by the

government was legally sufficient to terminate FAG Bearings’ liability for failing to warn.7

Claims based on the choice of “remedial actions” set forth in administrative orders and

consent decrees are preempted by CERCLA. However, notifying the public that contamination

exists is not a “remedial action” within the meaning of CERCLA’s preemption provision.

Therefore, Plaintiffs’ claims based on Defendants’ failure to warn the public that TCE was found

in private wells in 2004 is not preempted.8

7 Defendants also contend that in Cavallo v. Star Enterprises, 100 F.3d 1150 (4th Cir. 1996), cert. denied, 522 U.S.

1044 (1998), “the Fourth Circuit allowed failure to warn claims to proceed only to the extent the defendant ‘tortiously

failed to notify the EPA.’” (Doc. 47-1, p. 16 (quoting Cavallo, 100 F.3d at 1157)). But this takes the quote from

Cavallo out of context; in that passage the Fourth Circuit was addressing a different claim and stated that claims

predicated on venting of petroleum tanks were “actionable if Star tortiously failed to notify the EPA of the releases

. . . .” Cavallo, 100 F.3d at 1157. Elsewhere, in addressing the plaintiffs’ failure to warn claim, Cavallo provides

support for Plaintiffs’ position here, stating that “failure by Star to notify the Cavallos of petroleum releases may

support their claims if the . . . failures to notify were not authorized or approved by the EPA.” Id. The Fourth Circuit

remanded the case and, in so doing, reconfirmed “the fact that allegedly tortious conduct occurred within the temporal

and subject-matter scope of an EPA Order does not necessarily compel preemption claim based on that conduct.” Id.

The case was remanded so the district court could determine, inter alia, whether anything in the EPA Order (1) forbade

the defendant from notifying the plaintiffs about the releases or (2) authorized the defendant to refrain from notifying

the plaintiffs about the releases. Consistent with Cavallo, the Court’s conclusion in this case might be different if the

settlements prohibited Defendants from telling the public they discovered TCE in private wells or authorized

Defendants to keep such discoveries a secret – but this is not the case.

8 As an alternative to their preemption argument, Defendants argue that they had no duty to warn because they had no

reason to believe that the discovery of TCE in the private well in 2004 meant that the wells on Plaintiffs’ property

were contaminated. (Doc. 47-1, p.17.) However, the Second Amended Complaint alleges facts that suggest

Defendants should have known of the possibility, particularly given that Plaintiffs’ properties are closer to the Site

than the well where TCE was found. (See, e.g., Doc. 44, ¶¶ 69, 75, 80, 119, 199.)

B. Negligent Implementation of the Remedial Actions

As stated earlier, § 9622(e)(6) would not preempt a claim alleging that Defendants

negligently performed the remedial actions required in the settlements, and Plaintiffs have

attempted to plead such a claim. Defendants argue that this theory should be dismissed for failure

to state a claim, and the Court agrees that the Second Amended Complaint does not allege that (1)

Defendants breached any duties or that (2) any supposed breaches proximately caused Plaintiffs’

damage.9

“In any action for negligence, a plaintiff must establish the defendant owed a duty of care

to the plaintiff, the defendant breached that duty, and the defendant’s breach proximately caused

the plaintiff’s injury.” Wieland v. Owner-Operator Servs., Inc., 540 S.W.3d 845, 848 (Mo. 2018)

(en banc). The Second Amended Complaint alleges that Defendants’ settlements and agreements

with the State imposed a duty of care, and one of the duties imposed was to “perform all work

required . . . in accordance with all local, state, and federal laws and regulations . . . .” (Doc. 44, ¶

153 (quoting Doc. 28-2, ¶ 47-2) (emphasis supplied); see also Doc. 47-2, § III.C (similar provision

in 1993 Consent Agreement).) Plaintiffs further allege Defendants breached their duty to perform

all work in accordance with applicable laws, as demonstrated by the fact that on several occasions

MDNR advised that various “effluent limitations” had been exceeded. (Doc. 44, ¶ 154.) However,

the mere fact that limits were violated does not plausibly demonstrate the limits were violated

because Defendants negligently performed the remedial work required by the settlements (and the

Second Amended Complaint does not identify any aspect of the remedial work that was performed

negligently). The settlements did not serve as guarantees that the contamination would be

9 Defendants also argue that this claim should be dismissed because, in allowing Plaintiffs to file a Second Amended

Complaint, the Court did not specifically give Plaintiffs permission to re-plead this claim. However, the Court declines

to dismiss this aspect of the negligence claim based on a lack of permission from the Court.

contained, and Defendants cannot be liable simply because their non-negligent performance of the

remedial work required by the settlements was insufficient to prevent additional discharges that

exceeded the effluent limitations. To hold otherwise would effectively eviscerate the preemption

created by § 9622(e)(6).10

In addition, the Second Amended Complaint does not contain facts making it plausible that

the violations set forth in paragraph 154 were the cause (much less the proximate cause) of the

injuries Plaintiffs assert. Defendants argue, (Doc. 47-1, pp. 18-19), that the violations identified

in the Second Amended Complaint did not involve TCE or private wells. Plaintiffs do not dispute

the point and instead contend it does not matter because these violations demonstrate “general

recklessness on Defendants’ behalf [that] allowed contaminant concentrations to leave the Site.”

(Doc. 50, p. 14.) But the paragraphs Plaintiffs identify as supporting proximate cause, (see Doc.

50 p. 14), all (1) specifically relate to TCE, (Doc. 44, ¶¶ 119, 133-40) or (2) assert the legal

conclusion (to which no deference is owed under Rule 12(b)(6)) that Defendants’ actions were the

proximate cause of Plaintiffs’ injuries, (Doc. 44, ¶ 183, 201). And significantly, nothing about the

violations makes it plausible that the violations Plaintiffs specified in paragraph 154 are related to

the presence of TCE in Plaintiffs’ wells or on Plaintiffs’ property. To the contrary: the fact that

none of the violations involved TCE might suggest the opposite.11

III. CONCLUSION

The Motion to Dismiss, (Doc. 47), is GRANTED IN PART and Plaintiffs’ negligence

claims are dismissed to the extent that they are based on Defendants’ negligent performance of

10 The Court also does not agree with Plaintiffs that the fact effluent limits were exceeded, without more, sufficiently

states the claim and allows them to engage in discovery to explore whether Defendants’ negligent conduct caused the

limits to be exceeded. A viable claim must be alleged before discovery is permitted.

11 Plaintiffs also point to two violations for which details are presently unknown. (Doc. 50, p. 14 (citing Doc. 44, ¶¶

155-56).) However, the mere existence of violations does not make it plausible that those violations are examples of

negligent conduct by Defendants or were the proximate cause of contamination on Plaintiffs’ properties.

duties under the settlements. However, the Motion to Dismiss is DENIED to the extent that

Plaintiffs’ negligence claims are predicated on Defendants’ failure to warn the public that TCE

was discovered in private wells.

IT IS SO ORDERED.

/s/ Beth Phillips

BETH PHILLIPS, CHIEF JUDGE

DATE: August 31, 2022 UNITED STATES DISTRICT COURT

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.