noting that the First Circuit has “long held that the FCA is subject” to a materiality requirement
How later courts described this case
- noting that the First Circuit has “long held that the FCA is subject” to a materiality requirement
Written by the judges who cited it.
The opinion
United States District Court
District of Massachusetts
)
UNITED STATES OF AMERICA and )
COMMONWEALTH OF MASSACHUSETTS, )
ex rel. FREDERIC P. ZOTOS, )
)
Plaintiffs, ) Civil Action No.
) 19-12002-NMG
v. )
)
TOWN OF HINGHAM et al., )
)
Defendants. )
)
MEMORANDUM AND ORDER
GORTON, J.
Frederic P. Zotos (“Zotos” or “Relator”), an attorney
representing himself, brings this qui tam action on behalf of
the United States of America and the Commonwealth of
Massachusetts under the federal False Claims Act, 31 U.S.C. §§
3729(a)(1)(A)-(C) (“the FCA”), and the Massachusetts False
Claims Act, M.G.L. ch. 12, §§ 5B(a)(1)-(3) (“the MFCA”).
Zotos alleges that the Town of Hingham (“the Town”) and
several of its administrators and officers (collectively, “the
defendants”) violated the FCA and MFCA by: 1) posting speed
limit signs ultra vires; 2) knowingly submitting, or causing to
be submitted, claims for payment which falsely represented that
defendants had complied with all applicable laws and
regulations; and thereby 3) fraudulently inducing the United
States and the Commonwealth to pay millions of dollars for
highway and transportation projects.
Defendants have filed a joint motion to dismiss (Docket No.
21) which is currently pending before the Court. For the
following reasons, the motion will be allowed.
I. Background
A. Prior Litigation
Zotos has been the plaintiff in two previous actions
brought in this Court against the Town and related defendants.
See Zotos v. Town of Hingham, No. 12-11126-JGD, 2013 U.S. Dist.
LEXIS 134123 (D. Mass. Sep. 19, 2013) ("Zotos I"); Zotos v. Town
of Hingham, et al., No. 13-CV-13065-DJC, 2016 U.S. Dist. LEXIS
195835 (D. Mass. March 25, 2016) ("Zotos II"). In both of those
cases, Zotos challenged the legitimacy of certain speed limit
signs posted in the Town of Hingham.
In Zotos I, the district court published a lengthy decision
dismissing the action and the First Circuit Court of Appeals
(“the First Circuit”) affirmed the dismissal. Zotos I, 2013 U.S.
Dist. LEXIS 134123, aff’d, No. 13-2308 (1st Cir. 2015). Zotos
filed Zotos II prior to the First Circuit's decision in Zotos I
and the district court issued a carefully crafted opinion
dismissing that action as well. Zotos II, 2016 U.S. Dist. LEXIS
195835, at *14.
In addition to the lawsuits Zotos filed as a plaintiff, he
has also served as an attorney in two other civil actions in
which the plaintiff, Nicholas Belezos, alleged statutory and
constitutional violations with respect to a speeding ticket
issued by the Town.
In Belezos v. Board of Selectmen of the Town of Hingham,
the Massachusetts Superior Court for Plymouth County allowed the
defendants' motion for judgment on the pleadings which was then
upheld on appeal by the Massachusetts Appeals Court on the
grounds that plaintiff had waived his right to contest the
infraction “at the heart of [the] dispute”. Belezos v. Board of
Selectmen of Hingham, 2017 Mass. App. Unpub. LEXIS 1005, at *3-
4, 92 Mass. App. Ct. 1114 (Mass. App. Ct. 2017). The
Massachusetts Supreme Judicial Court denied plaintiff's
application for further appellate review.
The same plaintiff, again represented by Zotos, brought
substantially similar claims in federal court which, after the
filing of a motion to dismiss and multiple motions for
reconsideration, were dismissed by another session of this Court
because they were barred by the doctrine of claim preclusion.
See Belezos v. Board of Selectmen of Hingham, No. 17-12570-MBB,
2019 U.S. Dist. LEXIS 205938 (D. Mass. Nov. 27, 2019) (“Belozos
II”).
B. The Pending Case
1. The Parties
Relator Frederic Zotos is a licensed attorney residing in
Cohasset, Massachusetts. The Town of Hingham is a municipality
located in Massachusetts. The remaining defendants were all
administrators and/or officers of the Town at times relevant to
the complaint: Roger Fernandes was a Town Engineer, Thomas Mayo
was a Town Administrator, Ted Alexiades was a Town
Accountant/Finance Director and Town Administrator, Kevin Paicos
was a Town Administrator and Susan Nickerson was a Town
Accountant.
2. Speed Limit Signs
The complaint includes a lengthy recitation of various
federal and state laws and regulations pertaining to the
establishment of speed limit signs. In particular, the federal
highway administrator has approved a 2009 Manual on Uniform
Traffic Control Devices (“MUTCD”) which sets standards for the
establishment of speed limit signs and advisory speed plaques.
According to other federal regulations, any permanent or
temporary traffic control devices installed as part of a
federal-aid project “shall conform to the MUTCD”. The federal
highway administrator can withhold or withdraw funds for highway
projects from states if they “violate[] or fail[] to comply with
the Federal laws or the regulations . . . with respect to a
project”.
Massachusetts has also enacted several statutes and
regulations with respect to the establishment and maintenance of
traffic signs. For instance, M.G.L. ch. 90, § 18 authorizes the
special regulation of speed limits and the posting of such speed
limit signs on roadways in Massachusetts. Pursuant to M.G.L.
ch. 85, § 2, the Massachusetts Department of Transportation
(“MassDOT”) promulgates various regulatory standards about speed
limits and signs. Those regulations require, inter alia, posted
signage to comply with the MUTDC (as well as the Commonwealth’s
2012 amendments to those standards), explain the kinds of
statutory and special speed limits authorized under M.G.L. ch.
90, §§ 17 and 18, and set out procedures for posting new speed
limit signs and advisory speed plaques.
Zotos avers that, as of March, 2012, the Town posted at
least 26 speed limit signs without following applicable federal
and state regulations for the establishment of those limits.
Furthermore, Zotos alleges that, as of March, 2012, the Town
posted multiple advisory speed plaques in violation of
applicable regulations. He asserts that the Town has enforced
such signs without authority and has ignored traffic studies and
reports which indicate that the selected speed limits are
improper.
3. Chapter 90 Reimbursements
The complaint seeks to connect the Town’s purportedly ultra
vires posting of speed limit signs with certain funds provided
by the federal government and/or the Commonwealth as part of
highway and transportation aid programs. The Commonwealth of
Massachusetts (“the Commonwealth”) provides funding for local
transportation projects pursuant to M.G.L. ch. 90, § 34
(“Chapter 90”). Under Chapter 90, the Commonwealth reimburses
municipalities and other qualifying entities for up to 100% of
the cost of approved projects.
Zotos contends that the Town, in connection with a variety
of Chapter 90 projects, entered into two contracts with the
Commonwealth, submitted 24 separate Chapter 90 Reimbursement
Forms to the District Office of the MassDOT’s Highway Division
and submitted several Chapter 90 Final Reports. The complaint
identifies certifications included in those contracts and
reimbursement forms which defendants signed despite their
alleged failure to comply with regulations pertaining to speed
limit signs.
For instance, in 2007, the Town entered into a ten-year
contract with the Massachusetts Highway Department related to
its work on Chapter 90 projects in which it certified its
current and continuing compliance with “all legal requirements
governing performance of this Contract” whether or not such laws
or requirements were specifically cited. In 2017, the Town
executed a replacement contract in which it again certified that
it would ”comply with all applicable state laws and
regulations”.
Throughout the time period covered by those contracts,
defendants submitted two dozen Chapter 90 Reimbursement Forms to
the District Office of the MassDOT Highway Division. Those
reimbursement requests documented the Town’s qualifying
expenditures on previously approved Chapter 90 projects. The
requests also contained several certifications, namely: 1) a
Municipal Highway Officer’s Certification stating that costs
were incurred “in conformance with the Massachusetts Highway
Department Policies”, 2) an Accounting Officer’s Certification
that the forms submitted by the Town conformed with “all
applicable statutes and regulations” and 3) a Duly Authorized
Municipal Official’s Certification certifying the same.
Finally, the Town submitted multiple Chapter 90 Final
Reports that each included a joint certification by the
Municipal Highway Officer, Accounting Officer and Duly
Authorized Municipal Official “that the Municipality has
complied with all applicable statutes and regulations” while
incurring the project costs for which it sought reimbursement.
In July, 2012, Zotos sent a letter to Richard Davey, the
Secretary of Transportation and Chief Executive Officer of the
MassDOT. Zotos requested that, inter alia, the MassDOT withhold
or withdraw funds provided to the Town under Chapter 90 because
it had posted unauthorized speed limit signs. He also asked
that the MassDOT dispatch personnel to Hingham to take down
those signs. After the MassDOT rejected his request through its
General Counsel, Zotos wrote a second letter to the MassDOT
stating that he thought its response was inadequate.
According to the complaint, defendants have fraudulently
induced the Commonwealth to pay about $7.3 million of Chapter 90
funds to the Town by submitting reimbursement requests
containing false representations about their regulatory
compliance.
4. Federal-Aid Highway Program Reimbursements
Zotos also avers that defendants caused the Commonwealth to
submit false claims to the Federal Highway Administration
(“FHWA”) with respect to projects administered under the
Federal-Aid Highway Program (“FAHP”). According to the
complaint, the federal government typically reimburses states
for FAHP projects as follows: 1) the FHWA notifies states about
the balance of available funds; 2) states make formal requests
and begin projects (e.g. by engaging various contractors to work
on those projects); 3) contractors work on the approved projects
and bill the states; 4) states, having incurred the cost of
paying such bills, send vouchers for payment to the FHWA; and 5)
the FHWA certifies those claims and submits them to the Treasury
which disburses funds to the state.
Relator claims that states now submit vouchers for payment
electronically through the Rapid Approval and State Payment
System (“RASPS”) which replaced a “legacy” system that used a
specific form, FHWA Form PR-20. He submits that Form PR-20
included a certification, to be signed by an authorized official
of the state highway agency, stating that:
[c]ost [sic] shown in this voucher have been incurred
in accordance with terms of project agreements;
applicable State and Federal laws or regulations; and
that no claim has previously been submitted for costs
claimed.
The complaint describes two FAHP projects that began in
Hingham in 2018. MassDOT/Federal-Aid Project No. 600518 was
scheduled to begin in 2018 and be completed by 2020 (“Project
No. 600518”). It was intended to improve several intersections,
install a new traffic signal system and make other improvements
for drivers, bicyclists and pedestrians. MassDOT purportedly
submitted 19 invoices, including 76 vouchers for payment, via
RASPS for work done in connection with the project and received
about $425,000 in funds from the federal government.
MassDOT/Federal-Aid Project No. 607309 was also scheduled
to begin in 2018 and be completed by 2020 (“Project No. 607309”
and, collectively with Project No. 600518, “the 2018 Hingham
projects”). It was designed to address safety and capacity
issues at ramps by introducing additional traffic signals and
making other improvements. MassDOT is alleged to have submitted
45 invoices, including 221 vouchers for payment, via RASPS for
work done in connection with the project and received about
$2,885,000 in funds from the federal government.
In total, therefore, the complaint alleges that the MassDOT
submitted, and received payment for, about $3.3 million in
claims to the federal government for the 2018 Hingham projects.
II. Motion to Dismiss
A. Legal Standard
To survive a motion to dismiss under Fed. R. Civ. P.
12(b)(6), the subject pleading must contain sufficient factual
matter to state a claim for relief that is actionable as a
matter of law and “plausible on its face.” Ashcroft v. Iqbal,
556 U.S. 662, 678 (2009) (quoting Bell Atl. Corp. v. Twombly,
550 U.S. 544, 570 (2007)). A claim is facially plausible if,
after accepting as true all non-conclusory factual allegations,
the court can draw the reasonable inference that the defendant
is liable for the misconduct alleged. Ocasio-Hernandez v.
Fortuno-Burset, 640 F.3d 1, 12 (1st Cir. 2011).
When rendering that determination, a court may consider
certain categories of documents extrinsic to the complaint
“without converting a motion to dismiss into a motion for
summary judgment.” Freeman v. Town of Hudson, 714 F.3d 29, 36
(1st Cir. 2013) (citing Watterson v. Page, 987 F.2d 1, 3 (1st
Cir. 1993)). For instance, a court may consider documents of
undisputed authenticity, official public records, documents
central to a plaintiff’s claim and documents that were
sufficiently referred to in the complaint. Watterson, 987 F.2d
at 3.
A court may not disregard properly pled factual allegations
in the complaint even if actual proof of those facts is
improbable. Ocasio-Hernandez, 640 F.3d at 12. Rather, the
court’s inquiry must focus on the reasonableness of the
inference of liability that the plaintiff is asking the court to
draw. Id. at 13.
B. Application
1. Claim Preclusion and Issue Preclusion
As an initial matter, defendants contend that the doctrines
of issue preclusion and claim preclusion bar Relator from
bringing this qui tam action. They point to the extensive
litigation that Zotos has initiated or in which he has been
involved with respect to the Town’s authority to post and
enforce speed limit signs. According to defendants, state and
federal courts have repeatedly held that the Town did not post
such signs ultra vires.
The Court recognizes that claims similar to those asserted
by Zotos in this case have been heard and rejected by other
courts but it acknowledges Zotos’ response that this case is
different because he has filed it on behalf of the federal
government and the Commonwealth as well as on his own behalf.
Thus, the United States and the Commonwealth purportedly remain
“real part[ies] in interest” with a viable financial stake in
this action even though they have not intervened and are not
parties. U.S. ex rel. Eisenstein v. City of New York, New York,
556 U.S. 928, 934–35 (2009). According to Zotos, the presence
of those real governmental parties in interest prevents the
application of claim and/or issue preclusion here.
Neither Relator nor defendants cite First Circuit caselaw
in direct support of their respective positions. The Seventh
Circuit Court of Appeals, however, has addressed a similar issue
and held that
the resolution of personal employment litigation does
not preclude a qui tam action, in which the relator
acts as a representative of the public. The special
status of the United States counsels against reflexive
transfer of rules of preclusion from private to public
litigation.
United States ex rel. Lusby v. Rolls-Royce Corp., 570 F.3d 849,
852 (7th Cir. 2009); see also United States ex rel. Sorenson v.
Wadsworth Bros. Constr. Co., 2019 U.S. Dist. LEXIS 95329, at *5-
7 (D. Utah June 5, 2019) (holding that the presence of the
federal government as a real party in interest in a qui tam
action cannot “be ignored for purposes of collateral estoppel”).
The Court finds, therefore, that neither claim nor issue
preclusion bar this action.
2. Federal and State False Claims Acts
Defendants next contend that Zotos has failed to plead a
violation of the FCA or MFCA because he has not demonstrated the
materiality of the alleged misrepresentations or the scienter of
the defendants. Defendants also suggest that Relator’s claims
are deficient under the heightened pleading requirements of Fed.
R. Civ. P. 9(b). For the reasons stated below, the Court
concludes that Relator’s claims are inadequate under both the
FCA and the MFCA.
a. Materiality
The United States Supreme Court has held that, in order to
be actionable under the FCA,
a misrepresentation about compliance with a statutory,
regulatory, or contractual requirement must be
material to the Government’s payment decision[.]
Universal Health Servs. v. United States ex rel. Escobar, 579
U.S. 176, 192 (2016) (Escobar I); see also U.S. ex rel. Loughren
v. Unum Grp., 613 F.3d 300, 307 (1st Cir. 2010) (noting that the
First Circuit has “long held that the FCA is subject” to a
materiality requirement).
The MFCA also requires proof that an alleged
misrepresentation was material to the government’s decision. See
Commonwealth ex rel. Minarik v. Tresca Bros. Concrete, Sand &
Gravel, Inc., 1784-CV-02608-BLS2, 2021 Mass. Super. LEXIS 5, at
*6 (Jan. 25, 2021); see also United States ex rel. Martino-
Fleming v. S. Bay Mental Health Centers, 540 F. Supp. 3d 103,
116, n.5 (D. Mass. May 19, 2021) (explaining that courts rely on
FCA caselaw to interpret the MFCA).
The materiality standard is “rigorous” and “demanding”.
Escobar I, 579 U.S. at 192, 194. The FCA is not:
a vehicle for punishing garden-variety breaches of
contract or regulatory violations. A
misrepresentation cannot be deemed material merely
because the Government designates compliance with a
particular statutory, regulatory, or contractual
requirement as a condition of payment. Nor is it
sufficient for a finding of materiality that the
Government would have the option to decline to pay if
it knew of the defendant’s noncompliance.
Id. at 194.
A misrepresentation about compliance with statutory,
regulatory or contractual requirements is material only if: 1)
it likely would be important to a reasonable recipient in
“determining his choice of action” or 2) if the defendant knew
it would actually be important to the choice of action of a
particular recipient. Escobar I, 579 U.S. at 193 (citation
omitted). The First Circuit has held that the touchstone of
that inquiry is whether the misrepresentation “is sufficiently
important to influence the behavior of the recipient.” United
States ex rel. Escobar v. Universal Health Servs., Inc., 842
F.3d 103, 110 (1st Cir. 2016) (“Escobar II”) (citation omitted).
Courts assess the materiality of such a misrepresentation
pursuant to a holistic analysis that includes three primary
factors, none of which is dispositive: 1) whether the government
expressly identified compliance with particular requirements as
a condition of payment, 2) whether the government nevertheless
paid a claim despite knowing that those requirements were
violated and 3) whether the noncompliance in question is “minor
and insubstantial” or goes to “the very essence of the bargain”.
See Escobar I, 579 U.S. at 193-195, 193 n.5.
In this case, Relator alleges that defendants certified (or
caused to be certified) their compliance with all applicable
laws and regulations in connection with certain contracts and
reimbursement forms despite their failure to comply with
regulations pertaining to the establishment and maintenance of
speed limit signs in the Town of Hingham. He asserts that
compliance, or lack thereof, with regulations is “the textbook
example” of a material misrepresentation. Zotos concludes that
it is “hard to imagine” that the federal government would have
paid the Commonwealth, or that the Commonwealth would have paid
the Town, but for the purportedly misleading certifications.
According to Relator, there is an actionable
misrepresentation in this case because: 1) defendants did not
comply with certain regulations, 2) they nevertheless submitted
broad certifications which attested to their compliance with all
applicable regulations and 3) those certifications were a
prerequisite to the payment of funds. That expansive framing of
materiality, however, has been specifically rejected by the
United States Supreme Court:
[I]f the Government required contractors to aver their
compliance with the entire U.S. Code and Code of
Federal Regulations, then under this view, failing to
mention noncompliance with any of those requirements
would always be material. The False Claims Act does
not adopt such an extraordinarily expansive view of
liability.
Id. at 196.
In evaluating the materiality of defendants’ alleged
misrepresentations in the case at bar, therefore, the Court
rejects Relator’s expansive and conclusory theory of liability
and instead considers the alleged misrepresentations under the
holistic analysis established by the Supreme Court in Escobar I.
i. Contracts and Reimbursement
Requests Related to the Commonwealth’s
Program
As described above, Zotos asserts that defendants made
material misrepresentations in contracts and reimbursement
request forms that they submitted to the Commonwealth with
respect to Chapter 90 projects. Even assuming that the
defendants posted unauthorized speed limit signs, and assuming
that such misconduct was within the scope of the certifications
at issue, the Court concludes that defendants’ purported
misrepresentations were not material.
Although the certifications submitted to the Commonwealth
may have been a prerequisite for the Town receiving
reimbursements, those certifications do not expressly identify
any specific laws or regulations pertaining to speed limit
signs. And even if particular provisions had been expressly
identified, the alleged noncompliance of defendants was, in any
event, “minor [and] insubstantial”. Escobar I, 579 U.S. at 194.
The “essence of the bargain” pursuant to which the Town received
Chapter 90 funds was that the Town incurred costs in connection
with actual work done on approved projects and that the
Commonwealth reimbursed those costs. Id. at 193, n.5. The
complaint does not allege that the Town failed to carry out the
work or incur the costs for which it submitted reimbursement
requests.
Furthermore, Zotos claims that he alerted the MassDOT about
defendants’ posting and maintenance of purportedly ultra vires
speed limit signs in July, 2012. The Commonwealth denied
Relator’s request to withhold funds from the Town and, in the
aftermath of that correspondence, continued to appropriate
Chapter 90 funding to the Town. That funding in spite of
defendants’ alleged violations is “strong evidence” that the
requirements were not material to the Commonwealth’s decision-
making. Escobar I, 579 U.S. at 195.
This Court concludes that defendants’ alleged
misrepresentations to the Commonwealth about their compliance
with regulations on speed limit signs were not therefore
material under the holistic and demanding standard articulated
in Escobar I.
ii. Invoices and Vouchers Related to
the Federal-Aid Highway Program
A similar analysis applies to Relator’s allegation that
defendants caused the MassDOT to submit misleading invoices and
vouchers to the federal government in connection with the 2018
Hingham projects.
It is unclear from the complaint whether the MassDOT
actually submitted any signed copies of Form PR-20, including
certifications, in connection with either of the 2018 Hingham
projects. To the contrary, Relator has merely alleged that Form
PR-20 was used at some point, that the MassDOT submitted some
vouchers for reimbursement to the federal government in
connection with the 2018 Hingham projects (with or without Form
PR-20) and that defendants’ alleged misconduct would have
rendered the certification on Form PR-20 false.
That juxtaposition of defendants’ alleged misconduct, the
certification included on Form PR-20 and the federal funding of
the pertinent projects supports, at most, a speculative
inference that defendants may have caused the MassDOT to submit
a false statement to the FHWA. In United States ex. rel. Kelly
v. Novartis Pharms. Corp., the First Circuit explained that
“evidence and arguments [which] proceed more by insinuation” are
too speculative to support a claim that defendants caused a
third-party to submit false claims. 827 F.3d 5, 14-15 (1st Cir.
2016) (citing United States ex rel. Rost v. Pfizer, Inc., 507
F.3d 720, 733 (1st Cir. 2007)). Thus, the complaint here does
not allege defendants’ purported fraud with the requisite level
of specificity. Id. at 13-14 (holding that allegations of
“illegal conduct alone” and/or “that a fraudulent claim was
presumably submitted” are insufficient).
Even if the complaint had adequately alleged that
defendants caused the MassDOT to submit misleading
certifications to the federal government, the purported
misrepresentations about defendants’ compliance with speed limit
sign regulations would not be material. First, there is no
express indication on Form PR-20 that compliance with
regulations related to the establishment of speed limit signs
was necessary for federal funding. Furthermore, by 2018,
Relator had publicly initiated several lawsuits with respect to
defendants’ alleged noncompliance but the federal government
nevertheless provided funding for the 2018 Hingham projects.
Finally, the “essence” of the FAHP funding bargain was that
the MassDOT incurred permissible costs on FAHP projects that
were duly reimbursed. Escobar I, 579 U.S. at 193 n.5. There are
no allegations in the complaint to suggest that work on approved
projects was falsified or that duplicate costs were claimed.
One cannot infer from the complaint that misrepresentations, if
any, about defendants’ compliance with regulations on speed
limit signs were “sufficiently important” to affect the federal
government’s funding decisions about the 2018 Hingham projects.
Escobar II, 842 F.3d at 110.
ORDER
For the foregoing reasons, defendants’ motion to dismiss
(Docket No. 21) is ALLOWED.
So ordered.
_/s/ Nathaniel M. Gorton____
Nathaniel M. Gorton
United States District Judge
Dated: July 21, 2023