Opinion

United States v. Tisbury Towing and Transportation Co. Inc.

Court
District Court, D. Massachusetts
Filed
Jul 25, 2019
Cited by
0 cases
Authority
More cited than 22.7%

allowing the Corps to recover for indirect overhead

How later courts described this case

  • allowing the Corps to recover for indirect overhead

Written by the judges who cited it.

The opinion

UNITED STATES DISTRICT COURT

DISTRICT OF MASSACHUSETTS

)

UNITED STATES OF AMERICA, )

)

Plaintiff, )

)

v. )

)

TISBURY TOWING & ) Civil Action No. 16-11857-LTS

TRANSPORTATION, INC., Tug M/V )

THUBAN, its engines, boilers, tackle, etc., )

in rem, and Barge HYDRA 1200, its )

appurtenances, etc., in rem, )

)

Defendants. )

)

FINDINGS OF FACT AND CONCLUSIONS OF LAW

July 25, 2019

SOROKIN, J.

The United States of America has brought an in rem claim against defendant vessels tug

M/V Thuban and barge Hydra 1200, both owned and operated by Tisbury Towing &

Transportation, Inc. (“Tisbury”), for their alleged violation of the Rivers and Harbors Act, 33

U.S.C. § 408, on September 19, 2013 at the New Bedford Hurricane Barrier (“Hurricane

Barrier”) near New Bedford, Massachusetts. The parties stipulate to defendants’ liability and

dispute only the amount of damages. The Court held a bench trial on this claim on June 10–14,

2019, and now “find[s] facts specially and state[s] its conclusions of law separately” herein as

required by Fed. R. Civ. P. 52(a). The Court awards damages on this claim to the United States

as explained herein.

I. FINDINGS OF FACT

The Court makes the following factual findings based on materials submitted by the

parties, the credible testimony offered at the trial, and the Court’s view of the Hurricane Barrier

on June 10, 2019.

The United States Army Corps of Engineers (“the Corps”) owns and maintains the

Hurricane Barrier. Construction of the Hurricane Barrier was completed in 1966. The barrier

consists primarily of two dikes that cross the mouth of the Acushnet River. A 150-foot opening

between the two dikes provides a navigation channel into the harbor. That opening is gated by

two 60-foot steel structures that can be closed at times of anticipated flooding but are typically

open. The steel structures each rest on six steel wheels on which they can turn to close off the

navigation channel. When the gates are open, eight vertical gate guide beams connected by

horizontal trusses face the navigation channel on each side of the Hurricane Barrier. The Corps

numbers these beams, and the beams on the eastern side of the gate that are of particular

relevance to this case are numbered G-5, G-6, and G-7. As of 2013, all but two of the gate guide

beams were original to the Hurricane Barrier’s construction. Ten wooden fenders connect each

pair of gate guide beams to protect the gate from boat impacts, for a total of seventy wooden

fenders.

When the Hurricane Barrier requires maintenance, the Corps inserts rectangular stop

gates into the gate guide beams, creating a pocket that can be drained to allow maintenance on

the gate wheels and steel trusses. The Corps calls this process dewatering. In June 2011, the

Corps performed its most recent periodic inspection on the Hurricane Barrier. Ex. 18. It

performed its most recent dewatering in July 2012, at which time the gate guide beams were

sufficiently intact to enable a successful dewatering.

On the evening of September 19, 2013, the defendant vessels attempted to pass from the

harbor into Buzzards Bay through the Hurricane Barrier’s navigation channel. The barge was

carrying 1,232 tons of crushed blue stone. As the barge passed through the channel, it struck the

eastern portion of the gate at gate guide beam G-6, causing damage to the gate. Two federal

employees observed the allision from the Hurricane Barrier’s operating house, located on the

western side of the gate. The allision was also captured on film by a security camera mounted on

the operating house.

On October 5, 2013, the Corps conducted a dive inspection of the damage to the

Hurricane Barrier. During the inspection, divers inspected gate guide beams G-5, G-6, and G-7

on the Hurricane Barrier’s eastern side, which were in the area the barge struck. Gate guide beam

G-6 and its truss connections appeared damaged down to the third truss, while the other two gate

guide beams appeared undamaged. Ex. 5 at US000042–43. All the wooden fenders between gate

guide beams G-5 and G-6 were missing or damaged. Id. As a result, Corps engineer John

Kedzierski proposed replacing gate guide beam G-6 “from the top to Truss III” and replacing all

the wooden fenders. Id.

Accordingly, the Corps solicited bids to repair the damage to the Hurricane Barrier using

specifications that described cutting gate guide beam G-6, welding a replacement portion onto

the intact portion of the beam, and replacing 20 wooden fenders. See Ex. 11. The Corps received

bids for $438,000, $899,000, and $574,000, Ex. 6, and, on April 18, 2014, awarded the contract

to Kovilic Construction Co., Inc. (“Kovilic”), the low bidder, Ex. 7 at 2. On September 26, 2014,

the Corps modified the contract with Kovilic to include the replacement of ten additional wooden

fenders for an additional $111,371. Ex. 8.

On October 14, 2014, defendants’ expert Duncan Mellor personally inspected the

damaged Hurricane Barrier with divers from Northeast Diving Services, Inc., a commercial

diving company. Ex. 209. Mellor and the divers inspected the damage to the Hurricane Barrier,

including the gate guide beams and wooden fenders, both above and below water.

On October 25, 2014, divers working for Kovilic’s subcontractor cut gate guide beam G-

6 at the third truss. See Ex. 13 at US000166–68. After the cut was performed, the lower portion

of the beam—the portion that remained after the portion above the third truss was removed—was

observed to be twisted and therefore still damaged, requiring further repair. See Ex. 76 (showing

the top of the lower portion of gate guide beam G-6 after the cut was made). On December 12,

2014, as a result of the remaining damage, the Corps made a second modification to the contract

with Kovilic to include replacing the lower portion of gate guide beam G-6 for an additional

$261,785. Ex. 9. Kovilic then completed its performance under the twice-modified contract on

April 13, 2015. Ex. 13 at US000424. The Corps paid Kovilic a total of $811,156 for its work on

the Hurricane Barrier, of which $699,785 was for work to repair the damage from the barge

strike and $111,371 was for the unrelated replacement of ten additional wooden fenders. Ex. 22

at US000683.

The Corps uses a system of labor codes to track employee time. In the normal course of

business, employees record their time to various labor codes that correspond to different areas of

work and allow the Corps to allocate employee time to various funding sources. Each individual

employee inputs how they spent their time, and these records are then reviewed and approved by

the employee’s supervisor. All employees receive training on how to input time, and supervisors

receive additional training, including on fiscal law. After the barge struck the Hurricane Barrier,

the Corps established specific labor codes to track the internal labor costs incurred by its

response to the incident. See Ex. 17. Internal labor was used to prepare plans and specifications

for the repair, bid and oversee the contract, and inspect the repairs. Ex. 22 at US000681.

Employees recorded time to these labor codes as the Corps arranged the Hurricane Barrier’s

repair, and those time data were converted to dollar amounts at the Corps’s standard rates, which

include an allocation of other internal Corps costs such as rent and utilities. The total internal

labor costs attributed to repairing the Hurricane Barrier from the barge strike was $131,622.75,

which amount was reviewed for accuracy by the Corps’s supervisory civil engineer John

MacPherson. Ex. 22 at US000683. Along with the $699,785 paid to Kovilic, the total amount the

Corps spent on repairing the Hurricane Barrier was therefore $831,407.75.

II. CONCLUSIONS OF LAW

The Rivers and Harbors Act provides that

it shall not be lawful for any person or persons to . . . injure . . . or in any manner

whatever impair the usefulness of any sea wall, bulkhead, jetty, dike, levee, wharf,

pier, or other work built by the United States . . . for the preservation and

improvement of any of its navigable waters or to prevent floods.

33 U.S.C. § 408. “[T]he purpose” of the Act “is to provide funds for the replacement and

maintenance of improvements built by the United States . . . through an absolute liability

standard.” United States v. Ohio Valley Co., 510 F.2d 1184, 1188 (7th Cir. 1975). “[T]he penalty

is supposed to attach to the offending act without regard to the question of willfulness or intent,

and without regard to the question of mistake or innocence.” Scow No. 36, New England

Dredging Co. v. United States, 144 F. 932, 933 (1st Cir. 1906). The Act further provides that the

vessels “used or employed in violating” the Act are liable in rem. 33 U.S.C. § 412.

Despite the strict liability standard that attaches in a case of this nature, “[t]he burden of

proof [i]s on the government to establish that the amount claimed [i]s reasonable and that it fairly

reflect[s] the actual costs of repairing the” structure at issue. United States v. Motor Vessel

Gopher State, 614 F.2d 1186, 1188 n.1 (8th Cir. 1980). Because Tisbury concedes its liability,

the parties’ arguments focus on the reasonableness of the government’s claimed damages.

Tisbury advances several arguments that it is not liable to the government for the full amount of

the repair costs, which the Court addresses in turn.

Tisbury first argues that, as a general matter, it is entitled to a depreciation discount on

damages for the repair of the gate guide beam because the government’s repairs left the

Hurricane Barrier in a better condition than immediately before the allision. See Doc. No. 84 at

10; Doc. No. 103 at 2, 5. Tisbury cites no case arising under the Rivers and Harbors Act in which

recovery was limited by the application of depreciation.1 The government contends alternately

that depreciation is a business and tax concept inapplicable to a public work like the Hurricane

Barrier, Doc. No. 87 at 17–18, and that the government is entitled to recover without deductions

for depreciation where the repairs did not extend the life or otherwise increase the value of the

Hurricane Barrier because the replaced part will not be retained when the rest of the Hurricane

Barrier is replaced. Doc. No. 104 at 2. The government also cites no Rivers and Harbors Act case

specifically precluding the application of depreciation.

With respect to the gate guide beam, the government’s evidence demonstrated that the

gate guide beam, at a minimum, would have continued in service until the replacement of the

1 Although Tisbury cites United States v. Motor Vessel Gopher State, 472 F. Supp. 556, 559

(E.D. Mo. 1979), for the proposition that “[t]he government is entitled to have its . . . facility

restored to the condition in which it was prior to the collision but no more,” that case did not

involve depreciation. Rather, the district court reduced its damages award because the

government had failed to meet its burden to demonstrate that “the additional amount claimed

over and above [its] own detailed and itemized estimate of the costs necessary to repair the

damage . . . was necessary, fair and reasonable.” Id. Despite the dictum cited by Tisbury, the case

did not involve a contention that the repairs for which damages were sought improved the

condition of the facility at issue. See id. At any rate, although the amount of the district court’s

award was affirmed on appeal, the Court of Appeals “disagree[d] with the use of the estimate in

ascertaining the award of damages.” Motor Vessel Gopher State, 614 F.2d at 1187.

Hurricane Barrier. The only gate guide beams replaced to date were replaced because of

allisions, not because they wore out. Further, the replaced gate guide beam is plainly an integral

part of the Hurricane Barrier, given that they are required for a successful dewatering of the gate

pocket, a process necessary to the Hurricane Barrier’s continued functioning. Its replacement is

therefore essential to the use of the Hurricane Barrier for the remainder of its useful life.2

Tisbury presented no evidence that its replacement would allow the entire Hurricane Barrier as

currently installed to remain in service longer than it otherwise would have and indeed concedes

that the “expected useful life of the [Hurricane] Barrier after allision-related repairs was the same

as it had been at the time of its acquisition.” Doc. No. 107 ¶ 39. “[W]here . . . repairs do not

extend the useful life of the property as it existed just before the collision, there should be no

deduction for depreciation.” Freeport Sulphur Co. v. S/S Hermosa, 526 F.2d 300, 305–06 (5th

Cir. 1976). Accordingly, Tisbury is not entitled to a reduction in damages for the gate guide

beam because of depreciation.

Tisbury further argues that the Corps’s process to solicit bids for the Hurricane Barrier

was flawed because it was limited to certain qualifying entities, resulting in an unreasonably

higher price. Doc. No. 107 ¶ 53. Trial evidence demonstrated that the Corps determined to bid

the repair contract exclusively to small business entities pursuant to the Federal Acquisition

Regulation’s requirement that the agency “set aside any acquisition over $150,000 for small

business participation when there is a reasonable expectation that . . . [o]ffers will be obtained

from at least two responsible small business concerns . . . and . . . [a]ward will be made at fair

market prices.” 48 C.F.R. § 19.502-2(b). Because the Corps had recently procured similar work,

2 In addition, neither before the allision nor since has the Corps seriously considered replacing

the entire Hurricane Barrier.

it knew already that it would be likely to receive two or more bids from small businesses capable

of performing the work.

Tisbury suggested at trial that the Corps’s bidding was nevertheless insufficient because

it failed to “obtain appropriate data . . . on the prices at which the same or similar items have

previously been sold and determine if the data is adequate for evaluating the reasonableness of

the price.” 48 C.F.R. § 15.404-1(b)(1). However, because the Corps received three bids for the

repair, it was entitled to determine that the contract was “based on adequate price competition”

because “[t]wo or more responsible offerors, competing independently, submit priced offers that

satisfy the Government’s expressed requirement and . . . [a]ward w[as] made to the offeror

whose proposal represents the best value . . . and . . . [t]here is no finding that the price of the

otherwise successful offeror is unreasonable.” 48 C.F.R. § 15.403-1(c)(1). More generally,

Tisbury cites no authority for the proposition that the government is not entitled to seek damages

under the Rivers and Harbors Act that correspond to the generally higher prices that accompany

government procurement requirements. The Court finds that the Corps’s procurement process

was reasonable under the circumstances. Accordingly, the government is entitled to recover its

repair costs that result from its standard procurement procedures.

Perhaps most significantly, Tisbury argues that the Corps’s approach to the repair—first

bidding a contract to replace only the top portion of the damaged gate guide beam, then

modifying the contract to replace the entire beam without soliciting new bids—was unreasonable

and inflated the cost of the repair beyond a reasonable level. Doc. No. 103 at 4–5. It also argues

that the government’s recovery is limited by its spoliation of evidence about the lower portion of

the gate guide beam, id. at 9–11, and that the government’s evidence about the condition of the

lower gate guide beam during and after the government’s contractor cut it is inadmissible

hearsay, Doc. No. 105. The Corps’s decisions to award a contract to replace only the upper

portion of the gate guide beam and later to replace the entire beam plainly resulted in a higher

cost than simply first seeking bids to replace the entire beam, given that the stepwise process

required two mobilizations and at least two rounds of production of the replacement beam. The

parties’ dispute is whether those decisions were reasonable.

In an admiralty case, the plaintiff must prove the facts supporting its case by a

preponderance of the evidence. CEH, Inc. v. F/V Seafarer (O.N. 675048), 880 F. Supp. 940, 943

(D.R.I.). Although a strict liability standard governs this Rivers and Harbors Act action, the

government nevertheless bears the burden of establishing the reasonableness of its damages

calculation. Motor Vessel Gopher State, 614 F.2d at 1188 n.1.

In this case, the government elected to call only one expert, its own senior structural

engineer. The Corps’s expert provided no credible evidence that the Corps’s decision was

reasonable under the circumstances given the risk, eventually realized, that replacing only part of

the beam would lead to a need for further repair. Rather, the expert described basing his decision

about the best repair option on a visual inspection of the beam, which he conceded would not

have revealed any induced stress causing by the barge strike. He also described his decision not

to discuss the potential for hidden stress in the beam in his report recommending only partial

replacement, despite his awareness that such stress was a possibility after a barge strike. He

offered no credible opinion that, for example, the likely savings from retaining the lower portion

of the beam was sufficient to outweigh the risk of damage to the remainder of the beam during

the cutting and repair. By contrast, Tisbury’s hired expert testified that the more reasonable

course would have been to replace the entire beam at the outset.

For these reasons, the Court is unable to conclude on the evidence presented that the

Corps’s approach to repairing the gate guide beam was reasonable under the circumstances such

that Tisbury is required to pay the full amount of damages sought. The Court therefore declines

to award the cost of the contract modification to replace the entire beam. The Court finds that the

Corps has established that it would have been reasonable to make one procurement to replace the

entire gate guide beam, the cost of which would have been at least as much as the Corps’s

contract to replace the top portion. However, no evidence was presented about the likely cost to

the Corps of simply bidding the replacement of the entire beam, and the Court cannot conclude

on the present record what that cost would likely have been. The Court therefore awards only the

amount of the first contract, subject to the further provisions of this opinion.3

Tisbury also objects that the government failed to prove that all of the wooden fenders

were present at the time of the allision such that Tisbury is responsible for the cost of replacing

all that were missing after the allision and that the Corps’s actions caused spoliation of relevant

action. Doc. No. 103 at 2–4. Tisbury argues that the “number of [fenders] for which recovery

may be considered reasonable is limited to ten,” five on each side of the replaced gate guide

beam. Id. at 2. As with the gate guide beam, Tisbury also argues that damages to the wooden

fenders should be reduced for depreciation because the fenders were not new. Id. at 4.

Eight fenders above the waterline are plainly visible before the allision in the video

recording of the allision. The government’s evidence demonstrated that eight missing wooden

3 Tisbury has also argued that the government’s actions resulted in spoliation of evidence about

the condition of the lower portion of the gate guide beam and that the government’s evidence

about the condition of the beam during and immediately after it was cut was inadmissible as

hearsay. However, given the Court’s ruling, evidence about the condition of the lower half of the

beam is irrelevant, and the Court need not resolve those arguments. Accordingly, Tisbury’s

motions in limine, Doc. No. 90, Doc. No. 105, are DENIED as moot.

fenders, of the seventy fenders on each side of the Hurricane Barrier, had been replaced around

July 2012 as part of maintenance performed with the Hurricane Barrier’s dewatering, at which

point all of the fenders were present. See Ex. 25 at US000699. The government also described

the wooden fenders as “sacrificial,” intended to fend off vessels that rubbed against them,

thereby protecting the gate guide beams behind the fenders, but to break upon an allision with a

vessel as heavy as a loaded barge. The government’s expert also testified that a barge strike

would destroy fenders whether they were new or old. The government’s October 4, 2013,

inspection of the Hurricane Barrier showed that all of the wooden fenders at the location of the

barge strike were missing and that six of the twelve fenders that were similarly situated between

gate guide beams but not involved in the allision were missing. Ex. 27. Finally, Tisbury’s expert

opined that, at the time of its October 2014 inspection, the extent of marine growth on the gate

guide beams, where the fenders would have prevented such growth, meant that the fenders had

been absent for more than the 13 months since the allision.

Given the totality of these circumstances, in which wooden fenders clearly go missing

without immediate replacement, the Court finds that the government has not demonstrated by a

preponderance of the evidence that more than ten wooden fenders were present at the time of the

allision. However, by the same turn, the evidence that some fenders were already missing

demonstrates that that the Corps would not have replaced the wooden fenders except because of

the allision. Accordingly, the cost to replace them is entirely additive to the Corps’s maintenance

costs had the allision not occurred. Because the Corps is therefore no better off for having

replaced the wooden timbers as part of the allision repair, Tisbury is not entitled to a reduction in

the amount of damages for depreciation of the wooden fenders.

However, to reduce the damages award for the ten wooden fenders not shown to be

present at the time of the allision, the Court must determine the cost the Corps paid to replace

those fenders. Kovilic’s bid for the barge strike repair work showed a price of $7,500 to replace

each fender above the mean low water line and $11,750 for each fender beneath the mean low

water line. Ex. 6. However, at trial, the Corps’s contracting officer testified that the rates shown

for bids’ individual line items have little significance because a contract is awarded only on the

lowest total price for a given solicitation and that, as a result, individual line items frequently

vary widely based on each bidder’s accounting system. For example, Tisbury pointed at trial to

the contract that the Corps awarded for the July 2012 dewatering as evidence that the costs to

repair the damage from the barge strike were unreasonable. That contract had a line item cost of

$2,500 per wooden fender. Ex. 25 at US000699. The Court finds that the higher cost per wooden

fender in the barge strike repair contract likely resulted from the nature of the mobilization

required by the gate guide beam repair, which was necessary regardless of the wooden fender

replacement. Accordingly, the Court reduces the Corps’s damages award by only $2,500 per

each of the ten wooden fenders not shown to be present at the time of the allision.

Tisbury also objects to the Corps’s calculation of its internal operating costs that resulted

from the allision. It argues that the Corps improperly allocated “rent, utilities, and administrative

costs unrelated to the allision.” Doc. No. 103 at 8. Trial testimony of Corps employees, however,

explained that the Corps tracked its allision response costs using internal labor codes and then

allocated other internal overhead at standard rates. These rates are reasonable, and their

composition, including fixed costs such as rent and utilities, accords with “the definition of

overhead, which requires only an indirect connection by definition” and allows recovery for

“general operating expenses.” United States v. Capital Sand Co., 466 F.3d 655, 658–59 (8th Cir.

2006) (allowing the Corps to recover for indirect overhead). Accordingly, the Court credits the

Corps’s calculation of its internal costs from the allision. See Ex. 22 at US000683. However, the

Court reduces the damages for overhead for those portions of the damages reduced as described

above, proportionally to their dollar amounts.

The government also seeks prejudgment interest on its damages. Doc. No. 87 at 18–19.

“Prejudgment interest on admiralty claims is generally allowed on claims for prejudgment

economic harm as compensation for the use of funds to which the plaintiff was ultimately judged

entitled, but which the defendant had the use of prior to judgment.” Borges v. Our Lady of the

Sea Corp., 935 F.2d 436, 444 (1st Cir. 1991) (citations and internal quotations omitted). Because

nearly six years have passed since the allision, the government “is entitled to the income which

the monetary damages would have earned, and that should be measured by interest on short-

term, risk free obligations.” City of Bos. v. S.S. Texaco Texas, 773 F.2d 1396, 1401 (1st Cir.

1985). Although a plaintiff “may lose his right to prejudgment interest if exceptional

circumstances make an award of interest inequitable,” Nevor v. Moneypenny Holdings, LLC,

842 F.3d 113, 124 (1st Cir. 2016) (citations and internal quotations omitted), no such

circumstances exist here. Tisbury did not oppose an award of prejudgment interest either in its

briefing or at trial. The Court therefore awards prejudgment interest running from April 13,

2015, the date on which repairs were completed, see Ex. 13 at US000424, compounded quarterly

at the prevailing Treasury bill rate.

IV. CONCLUSION

The Court awards damages to the United States in the amount of $490,681.28 plus

prejudgment interest. This amount includes $438,000 for the first contract awarded to Kovilic to

repair the Hurricane Barrier, less a $25,000 reduction for the ten wooden fenders not shown to be

present at the time of the allision, for an adjusted amount of $413,000. Because this amount is

40.98 percent less than the amount the Corps spent to repair the Hurricane Barrier, the Court

awards the same proportion of the Corps’s internal overhead costs, or $77,681.28. The total

award is therefore $490,681.28 plus prejudgment interest.

By August 1, 2019, the government shall, after conferring with the defendant, submit a

proposed form of judgment that includes a calculation of prejudgment interest on the amount

awarded herein as described above.

SO ORDERED.

/s/ Leo T. Sorokin

Leo T. Sorokin

United States District Judge

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.