first citing Spiegel v. City of Houston, 636 F.2d 997 (5th Cir. 1981); and then citing Parker v. Dunlop, 517 F.2d 785, 787 (5th Cir. 1975)
How later courts described this case
- first citing Spiegel v. City of Houston, 636 F.2d 997 (5th Cir. 1981); and then citing Parker v. Dunlop, 517 F.2d 785, 787 (5th Cir. 1975)
- first citing Canal Authority of the State of Florida v. Callaway, 489 F.2d 567 (5th Cir. 1974); and then citing Mississippi Power and Light Co. v. United Gas Pipeline, 760 F.2d 618, 621 (5th Cir. 1985)
Written by the judges who cited it.
The opinion
UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF LOUISIANA
DR. AMMAR MEKARI, ET AL. CIVIL ACTION
VERSUS NO. 23-5362
ACCESS RESTORATION US, INC., ET SECTION “B”(2)
AL.
ORDER AND REASONS
Before the Court is a Motion for Temporary Restraining Order
(Rec. Doc. 4) filed by Plaintiffs Dr. Ammar Mekari (“Dr. Mekari”),
Kingman Holdings, LLC (“Kingman”), and Mekari Laser Dentistry,
LLC, (“Mekari Dentistry”) (collectively, “Plaintiffs”). Defendants
Access Restoration Services, US, Inc. (“ARS”), Global Services,
Inc. (“GES”), and ARS/Global Emergency Management, Inc.
(collectively, “Defendants”), have filed an Opposition (Rec. Doc.
10), and Plaintiffs have filed a Reply in Support (Rec. Doc. 14).
For the following reasons, the Motion for Temporary
Restraining Order is DENIED.
BACKGROUND
Plaintiff Dr. Mekari1 and Defendant ARS entered into a
contract (the “Contract”)2 for the purpose of having Defendant ARS
1 Plaintiff Dr. Mekari is the sole member of Plaintiffs Kingman and Mekari
Dentistry, both juridical entities. Rec. Doc. 15 at 2. Plaintiff Kingman owns
the Metairie Property, id. at 3, and upon information and belief, the Metairie
Property is Plaintiff Mekari Dentistry’s principal place of business, see Rec.
Doc. 4-4 at 1.
2 The Contract was executed on September 11, 2021. See Rec. Doc. 4-4 at 7-20;
Rec. Doc. 10-1. Plaintiff Dr. Mekari is the signatory; however, it is unclear
perform restoration services on Plaintiffs’ property located in
Metairie, Louisiana (the “Metairie Property”),3 after it was
damaged by Hurricane Ida. See Rec. Doc. 4-4 at 7-20; Rec. Doc.
10-1. The Contract contains a “DISPUTE RESOLUTION” clause
providing that Plaintiff Dr. Mekari4 and Defendant ARS “agree to
and consent that any controversy or claim arising out of, or
relating to this contract, or the breach thereof, shall be settled
by arbitration administered by the American Arbitration
Association, under the Construction Industry Arbitration Rules.”
Rec. Doc. 4-4 at 8; Rec. Doc. 10-1 at 2.
After Defendant ARS completed the restoration work on the
Metairie Property, a dispute arose regarding an unpaid invoice
related to Defendant ARS’s restoration work.5 In response to this
dispute and in accordance with the dispute resolution clause
outlined in the Contract, Defendant ARS initiated an arbitration
proceeding through the American Arbitration Association against
Plaintiffs Dr. Mekari and Mekari Dentistry for breach of the
whether Plaintiff Dr. Mekari signed individually and on behalf of both
Plaintiffs Kingsman and Mekari Dentistry, or individually and on behalf of only
Plaintiff Kingsman or only Plaintiff Mekari Dentistry.
3 The Metairie Property’s precise address is 4500 York Street Metairie, LA
70001.
4 See supra notes 1-2.
5 Approximately a month after the Contract was executed, Defendant ARS completed
the restoration work on the Metairie Property and sent Plaintiffs Dr. Mekari
and Mekari Dentistry an invoice for Defendant ARS’ services, labor, and
materials; the principal amount on the invoice is $347,563.29. This invoice is
still outstanding.
Contract, seeking to recover the outstanding invoice. Rec. Doc. 10
at 2-3 n.8 (citing Rec. Doc. 4-4). This arbitration proceeding is
currently on-going; a scheduling order has been issued,6 the
discovery deadline has passed,7 and a final arbitration hearing is
set for November 9, 2023. See Rec. Doc. 10-2.
In the present Motion, Plaintiffs Dr. Mekari, Kingsman, and
Mekari Dentistry are seeking a temporary restraining order to
enjoin enforcement of the dispute resolution clause in the
Contract. In simpler terms, Plaintiffs are requesting this Court
to halt the on-going arbitration proceeding. The basis for this
request stems from Plaintiffs’ assertion that the Contract, which
contains the dispute resolution clause, is absolutely null due to
fraud. To fully grasp Plaintiffs’ position, it is necessary to
recount the events leading up to the execution of the Contract
between Plaintiff Dr. Mekari and Defendant ARS.
Following the landfall of Hurricane Ida in Louisiana and the
subsequent damage to the Metairie Property, Plaintiffs retained
the services of the law firm McClenny, Moseley, and Associates
(“MMA”) to represent them in their insurance claim against the
Metairie Property’s insurer. Rec. Doc. 4-1 at 1-2. MMA advised
that Plaintiffs enter into the Contract with Defendant ARS. Id. at
6 Plaintiff Dr. Mekari, individually and on behalf of Plaintiff Mekari Dentistry,
participated in the arbitration’s preliminary hearing. Rec. Doc. 10-2 at 1.
7 All discovery was to be completed by September 15, 2023. Id. at 2. Plaintiffs
Dr. Mekari and Mekari Dentistry have not participated in discovery in the
arbitration proceeding.
2. It later came to light that MMA and Defendant ARS had an existing
contractual arrangement. After Hurricane Ida, MMA and Defendant
ARS entered into a financing and investment agreement. See Rec.
Doc. 4-3 at 2. Under this agreement, Defendant ARS committed to
providing MMA with a loan of $3,000,000.00 to fund litigation that
MMA was pursuing on behalf of its clients in claims against their
respective insurers related to Hurricane Ida damage. Id. In return
for Defendant ARS’s $3,000,000.00 investment, as Plaintiffs tell
it, MMA “would kickback clients/insureds to [Defendant] ARS.” Rec.
Doc. 4-1 at 2. Consequently, Plaintiffs argue that the Contract,
“was based in fraud as Plaintiff [Dr. Mekari] was forced, coerced,
and misled as to the true nature of the [C]ontract and the prior
illegal relationship between MMA” and Defendant ARS. Id. As a
result, Plaintiffs contend that the Contract is absolutely null
and thus, never legally existed. And if the Contract containing
the dispute resolution clause never existed, Plaintiffs pose the
question: “then how or why is [it] relevant what the American
Arbitration Association has to say?” Rec. Doc. 14 at 2.
LEGAL STANDARD
Under Federal Rule of Civil Procedure 65 and Fifth Circuit
authority, a temporary restraining order is available only where
the mover proves all four of the following elements: (1) a
substantial likelihood of success on the merits; (2) a substantial
threat that failure to grant the injunction will result in
irreparable injury; (3) that the threatened injury outweighs any
damage that the injunction may cause the opposing party; and (4)
that the injunction will not disserve the public interest. See,
e.g., Clark v. Prichard, 812 F.2d 991, 993 (5th Cir. 1987) (first
citing Canal Authority of the State of Florida v. Callaway, 489
F.2d 567 (5th Cir. 1974); and then citing Mississippi Power and
Light Co. v. United Gas Pipeline, 760 F.2d 618, 621 (5th Cir.
1985)).
LAW AND ANALYSIS
The Court first considers whether Plaintiffs have carried the
burden of showing element two - a substantial threat of irreparable
injury. “An injury is ‘irreparable’ only if it cannot be undone
through monetary remedies.” Deerfield Medical Center v. City of
Deerfield Beach, 661 F.2d 328, 338 (5th Cir. 1981) (first citing
Spiegel v. City of Houston, 636 F.2d 997 (5th Cir. 1981); and then
citing Parker v. Dunlop, 517 F.2d 785, 787 (5th Cir. 1975)).
Plaintiffs assert they are suffering irreparable injury by
“accruing costs in arbitration which are an unnecessary expense”
where the Contract is an absolute nullity. Rec. Doc. 4-1 at 3. In
response, Defendants argue that Plaintiffs’ admission that their
irreparable injury is expenses they will incur in the arbitration
proceeding is “fatal” to their Motion. Rec. Doc. 10 at 5. We agree.
Defendants cite City of Meridian, Miss. V. Algernon Blair,
Inc., where the Fifth Circuit stated that the “expense of
inappropriate arbitration” does “not constitute irreparable harm.”
Rec. Doc. 10 at 4 (citing City of Meridian, Miss. V. Algernon
Blair, Inc.,721 F.2d 525, 529 (5th Cir. 1983)). Plaintiffs aver
that City of Meridian is distinguishable because in that case,
there was a genuine contract dispute regarding the scope of the
work; whereas in this case, Plaintiffs argue the contract does not
exist whatsoever because it is absolutely null due to fraud. Rec.
Doc. 14 at 2. The argued distinction, however, does not make a
material difference in the reasoning and result.
Plaintiffs’ argument does not change the principle that an
injury which can be undone through monetary remedies is not
“irreparable.” Additionally, Plaintiffs’ argument that the
Contract is absolutely null due to fraud is a defense to Defendant
ARS’s breach of contract claim in the arbitration proceeding.
Plaintiffs have provided no reason why this defense cannot be
raised before the American Arbitration Association. Nor has this
Court found one. This Court has, however, found evidence that
Plaintiffs would have an opportunity to present its defense to the
arbitrator,8 “and to the courts if there was an unfavorable
8 For instance, under the American Arbitration Association’s Construction
Industry Arbitration Rules-which govern the parties’ arbitration proceeding-
“[t]he arbitrator shall have the power to determine the existence or validity
of a contract of which an arbitration clause forms a part. Such an arbitration
clause shall be treated as an agreement independent of the other terms of the
decision. If a legal challenge proved successful, [Plaintiffs]
obviously would not be bound by the finding or conclusions of the
arbitrator[,]” City of Meridian, 721 F.2d at 529.
The Court finds that Plaintiffs have not made a showing of
irreparable injury sufficient to merit issuance of the
“extraordinary” and “rarely issued” relief of a temporary
restraining order. Treen v. Brown, No. 10-3359, 2010 WL 4027714,
at *1 (E.D. La. Oct. 13, 2010). Thus, it is unnecessary to consider
the other factors for issuance of a temporary restraining order.
CONCLUSION
For the foregoing reasons, Plaintiffs’ Motion for Temporary
Restraining Order (Rec. Doc. 4) is DENIED.
IT IS FURTHER ORDERED that Defendants’ ex parte Motion for
Leave to File Opposition to Plaintiffs’ Motion for Temporary
Restraining Order (Rec. Doc. 6) is DISMISSED as MOOT.
IT IS FURTHER ORDERED that Plaintiff’s Motion to Reassign the
Submission Date for its Motion for Preliminary Injunction (Rec.
Doc. 9) in the above-captioned matter is DISMISSED as MOOT.
New Orleans, Louisiana this 13th day of October, 2023
___________________________________
SENIOR UNITED STATES DISTRICT JUDGE
contract.” AAA Constr. Indus. Arb. Rules and Mediation Proc. Rule 9(b) (2015),
https://www.adr.org/Rules.