UNITED STATES DISTRICT COURT

EASTERN DISTRICT OF LOUISIANA

LAMAR CONTRACTORS, LLC CIVIL ACTION

VERSUS NO. 20-588

AR-CLAD, INC., GH HORNE SECTION M (3)

ARCHITECTURAL SYSTEMS, LLC

AND CENTRIA, INC.

ORDER & REASONS

Before the Court are motions by defendants AR-Clad, Inc. (“AR-Clad”) and GMHorne

Commercial & Industrial, LLC (“GMHorne”) to dismiss pursuant to Rule 12(b)(6) of the Federal

Rules of Civil Procedure for failure to state a claim upon which relief can be granted, or

alternatively, for summary judgment.1 Plaintiff Lamar Contractors, LLC (“Lamar”) responds in

opposition,2 and the defendants reply in further support of their respective motions.3 Having

considered the parties’ memoranda, the record, and the applicable law, the Court issues this Order

& Reasons granting the motions for summary judgment because Lamar’s claims are perempted

under Louisiana Revised Statute (“La. R.S.”) 9:2772.4

1 R. Docs. 61 & 66.

2 R. Docs. 71 & 72.

3 R. Docs. 76 & 84. Lamar also file surreplies in further opposition to the motions. R. Docs. 82 & 87.

4 Also before the Court is a motion for summary judgment filed by defendant Centria, Inc. (“Centria”). R.

Doc. 65. Lamar alleges that Centria manufactured the metal wall panel system at issue in this litigation and issued

warranties covering defects in its product. R. Doc. 1-2 at 5. Lamar alleges that it made a warranty claim on Centria,

but Centria has refused to fulfill its warranty obligations. Id. Centria argues that it is entitled to summary judgment

because the warranty extends to the owner, St. Charles Parish (the “Parish”), not Lamar, the general contractor, with

whom Centria has no contract. R. Doc. 65-1. Centria further argues that (1) even if Lamar could allege a breach-of-

warranty claim, such a claim fails because Lamar alleges that the problems stem from installation, which is not covered

by Centria’s warranty; (2) there is no defect in the product; and (3) the material defect warranty expired four years

before Lamar made its claim. Id. Centria’s motion was set to be submitted to the Court on July 29, 2021. R. Doc.

65-12. Local Rule 7.5 requires that a memorandum in opposition to a motion be filed no later than eight days before

the noticed submission date, which in this instance was July 21, 2021. Lamar, who is represented by counsel, has not

filed an opposition. Accordingly, because Centria’s motion for summary judgment is unopposed, and it appearing to

I. BACKGROUND

This matter concerns a construction defect. In 2011, the Parish solicited bids for the

construction of the Edward A. Dufresne Community Center (the “Community Center”) to be

constructed in accordance with plans prepared by Sizeler Thompson Brown Architects. The Parish

selected Lamar as the general contractor for the project because it was the lowest responsible and

responsive bidder.5 Lamar signed the contract with the Parish on December 7, 2011.6 As part of

the project, Lamar entered into a written subcontract with AR-Clad to furnish labor and equipment

to install a complete metal wall panel and composite wall panel system.7 Lamar purchased the

metal wall panel system from GMHorne pursuant to a written purchase order agreement.8 Centria

manufactured the wall panel system.9 Lamar and the Parish both signed the certificate of

substantial completion on August 6, 2013, and it was filed into the Parish’s mortgage records on

August 9, 2013.10

On January 22, 2020, Lamar filed this action alleging that the defendants AR-Clad,

GMHorne, and Centria are liable for the cost it will incur to repair leaks in the wall panel system.11

Lamar alleges that in May 2013, leaks were discovered near the panels around the windows in the

Community Center’s gymnasium.12 Lamar’s senior project manager, Steve Louque, emailed

Jacob Scott with AR-Clad and Jason Horne with GMHorne to advise them of the situation.13 Scott

responded that the leaks were coming from windows that needed to be recaulked because AR-Clad

the Court that the motion has merit, it is GRANTED, and Lamar’s claims against Centria are DISMISSED WITH

PREJUDICE.

5 R. Doc. 1-2 at 3.

6 Id.

7 Id.

8 Id. at 4.

9 Id.

10 R. Doc. 61-3.

11 R. Doc. 1-2.

12 Id. at 4.

13 Id.

had removed the caulking done by the glass subcontractor to install flashing in the jamb and the

metal wall panel system.14 Scott stated that the recaulking was not within AR-Clad’s scope of

work.15 Lamar had the glass subcontractor recaulk the windows, and the leak appeared to stop

temporarily.16 But Lamar alleges that the leaks persisted and were caused by AR-Clad’s failure

“to install proper through wall jamb flash, failure to install foam closures where required under the

contract documents, and failure to properly install sill flash at certain locations and other

components within the metal wall panel system.”17 Lamar claims that neither AR-Clad nor

GMHorne complied with Lamar’s requests “for them to fulfill their contractual and warranty

obligations and make the necessary repairs to stop the leaks coming from the metal wall panel

system.”18 Lamar alleges that defendants refuse to honor their contractual and warranty

obligations to repair the metal wall panel system.19 Lamar claims that it has received a bid

estimating that it will cost $222,520.00 for labor, materials, and equipment to repair the leak.20

Lamar seeks the amount of the estimate plus attorney’s fees and costs.21

II. PENDING MOTION

AR-Clad and GMHorne argue that Lamar’s claims against them are perempted by La. R.S.

9:2772, which provides that any action arising out of an engagement for construction must be

brought no later than five years after the owner’s acceptance of the work is registered in the

mortgage office, whether brought by direct action or for contribution or indemnity or by third-

party practice and whether brought by the owner or by any other person.22 The Parish’s acceptance

14 Id.

15 Id.

16 Id.

17 Id.

18 Id. at 5.

19 Id.

20 Id.

21 Id.

22 R. Docs. 61-2; 66-1.

of the work was filed in its mortgage records on August 9, 2013.23 Thus, argue AR-Clad and

GMHorne, any claims Lamar had against them relating to the construction of the Community

Center were extinguished on August 9, 2018, and Lamar did not file this suit until January 22,

2020, more than seventeen months after its claims ceased to exist.24 GMHorne also argues that

any contractual claims against it are based on a breach of warranty in a contract of sale and are

founded in redhibition, which has a one-year prescriptive period that expired in May 2014, one

year from the date the water leak was discovered.25

In opposition to AR-Clad’s motion, Lamar argues that AR-Clad performed remedial work

on the Community Center in October 2019, and thus, Lamar’s claims against AR-Clad should not

be perempted.26 Specifically, Lamar argues that AR-Clad’s original work, prior to the Parish’s

acceptance of the work, should be considered as a single project together with the 2019 work so

that none of Lamar’s claims related to any portion of AR-Clad’s work are perempted.27 Lamar

argues that this Court should defer ruling on AR-Clad’s motion for summary judgment until after

Lamar has taken Scott’s deposition.28

With respect to GMHorne’s motion, Lamar argues that its claim against GMHorne is not

based upon breach of warranty or redhibition, but rather is for breach of the sales contract due to

late delivery of the wall panel system materials, and thus has a ten-year prescriptive period.29

Specifically, Lamar argues that GMHorne’s failure to deliver the materials timely caused the

window units to be installed prior to the metal wall panel, which is the opposite of what is supposed

23 R. Doc. 61-3.

24 R. Docs. 61-2 at 4-5; 66-1 at 5-10.

25 R. Doc. 66-1 at 10-13.

26 R. Doc. 71 at 8-10.

27 Id.

28 Id. at 9-10. Lamar points out that AR-Clad’s and GMHorne’s Rule 12(b)(6) motions were untimely filed

because they were filed after the defendants had answered. R. Docs. 71 at 4 n. 10; 72 at 4 n. 7. Lamar acknowledges,

however, that the Court can consider the motions under Rule 12(c) as motions for judgment on the pleadings. Id.

29 R. Doc. 72 at 2-3.

to occur, and this resulted in AR-Clad’s deficient installation of the wall panel system, having had

to work around the previously installed window units.30 Lamar further argues that La. R.S. 9:2772

is not applicable to sales contracts like the one it had with GMHorne.31

III. LAW & ANALYSIS

A. Summary Judgment Standard32

Summary judgment is proper “if the pleadings, depositions, answers to interrogatories, and

admissions on file, together with the affidavits, if any, show that there is no genuine issue as to

any material fact and that the moving party is entitled to a judgment as a matter of law.” Celotex

Corp. v. Catrett, 477 U.S. 317, 322 (1986) (quoting Fed. R. Civ. P. 56(c)). “Rule 56(c) mandates

the entry of summary judgment, after adequate time for discovery and upon motion, against a party

who fails to make a showing sufficient to establish the existence of an element essential to that

party’s case, and on which that party will bear the burden of proof at trial.” Id. A party moving

for summary judgment bears the initial burden of demonstrating the basis for summary judgment

and identifying those portions of the record, discovery, and any affidavits supporting the

conclusion that there is no genuine issue of material fact. Id. at 323. If the moving party meets

that burden, then the nonmoving party must use evidence cognizable under Rule 56 to demonstrate

the existence of a genuine issue of material fact. Id. at 324.

A genuine issue of material fact exists if a reasonable jury could return a verdict for the

nonmoving party. See Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). The substantive

law identifies which facts are material. Id. Material facts are not genuinely disputed when a

rational trier of fact could not find for the nonmoving party upon a review of the record taken as a

30 Id.

31 Id. at 6-7.

32 The Court will consider the motions under the summary judgment standard because the parties presented

evidence outside of the pleadings. See R. Docs. 61, 66, 71, 72.

whole. See Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587 (1986); EEOC

v. Simbaki, Ltd., 767 F.3d 475, 481 (5th Cir. 2014). Unsubstantiated assertions, conclusory

allegations, and merely colorable factual bases are insufficient to defeat a motion for summary

judgment. See Anderson, 477 U.S. at 249-50; Little v. Liquid Air Corp., 37 F.3d 1069, 1075 (5th

Cir. 1994); Hopper v. Frank, 16 F.3d 92, 97 (5th Cir. 1994). In ruling on a summary-judgment

motion, a court may not resolve credibility issues or weigh evidence. See Delta & Pine Land Co.

v. Nationwide Agribusiness Ins. Co., 530 F.3d 395, 398-99 (5th Cir. 2008). Furthermore, a court

must assess the evidence, review the facts, and draw any appropriate inferences based on the

evidence in the light most favorable to the party opposing summary judgment. See Tolan v. Cotton,

572 U.S. 650, 656-57 (2014); Daniels v. City of Arlington, 246 F.3d 500, 502 (5th Cir. 2001). Yet,

a court only draws reasonable inferences in favor of the nonmovant “when there is an actual

controversy, that is, when both parties have submitted evidence of contradictory facts.” Little, 37

F.3d at 1075 (citing Lujan v. Nat’l Wildlife Fed’n, 497 U.S. 871, 888 (1990)).

After the movant demonstrates the absence of a genuine issue of material fact, the

nonmovant must articulate specific facts showing a genuine issue and point to supporting,

competent evidence that may be presented in a form admissible at trial. See Lynch Props., Inc. v.

Potomac Ins. Co., 140 F.3d 622, 625 (5th Cir. 1998); Fed. R. Civ. P. 56(c)(1)(A) & (c)(2). Such

facts must create more than “some metaphysical doubt as to the material facts.” Matsushita, 475

U.S. at 586. When the nonmovant will bear the burden of proof at trial on the dispositive issue,

the moving party may simply point to insufficient admissible evidence to establish an essential

element of the nonmovant’s claim in order to satisfy its summary-judgment burden. See Celotex,

477 U.S. at 322-25; Fed. R. Civ. P. 56(c)(1)(B). Unless there is a genuine issue for trial that could

support a judgment in favor of the nonmovant, summary judgment must be granted. See Little, 37

F.3d at 1075-76.

B. Peremption under La. R.S. 9:2772

Peremption is a period of time fixed by law for the existence of a right, and it may not be

renounced, interrupted, or suspended. L. Enf’t Dist. of Jefferson Par. v. Mapp Constr., LLC, 296

So. 3d 1260, 1263 (La. App. 2020) (citing La. Civ. Code arts. 3458, 3461). “Unless timely

exercised, the right is extinguished upon the expiration of the peremptive period.” Id. (citing La.

Civ. Code art. 3458). Because peremptive statutes are strictly construed against peremption and

in favor of the claim, when there is more than one possible construction, “the one that maintains

enforcement of the claim or action, rather than the one that bars enforcement should be adopted.”

Id. (citing Rando v. Anco Insulations Inc., 16 So. 3d 1065, 1083 (La. 2009)).

La. R.S. 9:2772 imposes a five-year peremptive period for actions arising out of a

construction or design project. The statute provides in pertinent part:

A. Except as otherwise provided in this Subsection, no action, whether ex

contractu, ex delicto, or otherwise, including but not limited to an action for

failure to warn, to recover on a contract, or to recover damages, or otherwise

arising out of an engagement of planning, construction, design, or building

immovable or movable property which may include, without limitation,

consultation, planning, designs, drawings, specification, investigation,

evaluation, measuring, or administration related to any building, construction,

demolition, or work, shall be brought against any person performing or

furnishing land surveying services, as such term is defined in R.S. 37:682,

including but not limited to those services preparatory to construction, or

against any person performing or furnishing the design, planning, supervision,

inspection, or observation of construction or the construction of immovables, or

improvement to immovable property, including but not limited to a residential

building contractor as defined in R.S. 37:2150.1:

(1)(a) More than five years after the date of registry in the mortgage office of

acceptance of the work by owner.

. . . .

B. (1) The causes which are perempted within the time described above include

any action:

(a) For any deficiency in the performing or furnishing of land surveying

services, as such term is defined in R.S. 37:682, including but not limited to

those preparatory to construction or in the design, planning, inspection, or

observation of construction, or in the construction of any improvement to

immovable property, including but not limited to any services provided by

a residential building contractor as defined in R.S. 37:2150.1(9).

(b) For damage to property, movable or immovable, arising out of any such

deficiency.

. . . .

(3) Except as otherwise provided in Subsection A of this Section, this

peremptive period shall extend to every demand, whether brought by direct

action or for contribution or indemnity or by third-party practice, and whether

brought by the owner or by any other person.

. . . .

La. R.S. 9:2772 (emphasis added).

The date of registry of acceptance, not the discovery of the defect, is the trigger for the

statute’s five-year peremptive period. Koerner v. Vigilant Ins. Co., 2017 WL 4682295, at *4 (E.D.

La. Oct. 18, 2017) (quoting Burkart v. Williamson, 29 So. 3d 635, 639 (La. App. 2009)).

Moreover, the peremptive period is not interrupted by “any repairs or promises to repair alleged

to have been made.” Id. (quoting Lasseigne v. Schouest & Sons, Builders, 563 So. 2d 371, 373

(La. App. 1990)).

Here, it is clear that the five-year peremptive period has lapsed with respect to Lamar’s

claims against AR-Clad. All of Lamar’s claims against AR-Clad arise from a construction

contract, namely, AR-Clad’s installation of the metal wall panel system. The Parish’s acceptance

of the work was filed into the mortgage records in August 2013, and Lamar filed this action more

than five years later in January 2020. Thus, Lamar’s claims are perempted on the face of the

complaint.

Lamar’s argument that AR-Clad performed work in 2019 and that such work should be

construed as part of the same project as the 2013 work, so that neither is perempted, is off the

mark. First, there is no evidence that AR-Clad performed any work after 2014. In his affidavit,

Scott states that AR-Clad performed warranty work in 2014 and has not performed any work on

the building since then.33 This evidence is uncontroverted. Lamar attaches to its opposition an

email from Scott to Chase Lacombe of Lamar discussing an inspection Scott performed on the

Community Center in 2019 and repair work that AR-Clad might do.34 There is no indication that

AR-Clad performed the work discussed. Moreover, even if AR-Clad had performed work after

the peremption period, it would not revive Lamar’s perempted claims related to AR-Clad’s original

work. See Koerner, 2017 WL 4682295, at *5-6 (repair work performed after the peremptive period

expired on the original work was considered a new job and claims related to that repair work were

not perempted whereas claims related to the original work were). All the claims in Lamar’s

complaint against AR-Clad relate to AR-Clad’s original work and work prior to 2014, and thus are

perempted. Therefore, AR-Clad’s motion for summary judgment is granted, and Lamar’s claims

against it are dismissed with prejudice.

The analysis differs with respect to Lamar’s claims against GMHorne. Lamar argues that

its claims against GMHorne are based on breach of a sales contract due to late delivery. “La. R.S.

9:2772 applies only to contracts to build, and not contracts of sale.” L. Enf’t Dist., 296 So. 3d at

1266. To determine whether a contract is a construction contract or a contract of sale, “Louisiana

courts generally weigh the economics of the situation to determine whether the primary obligation

is ‘to give’ (sales contract) or ‘to do’ (construction contract).” Harvey v. Mosaic Fertilizer, LLC,

33 R. Doc. 61-4 at 2.

34 R. Doc. 71-2. The Court recognizes that AR-Clad contests the admissibility of the referenced email but

will consider it anyway in evaluating the motion for summary judgment.

2009 WL 3112144, at *3 (E.D. La. Sept. 25, 2009) (quoting Harris v. Black Clawson Co., 961

F.2d 547, 553 (5th Cir. 1992)). As stated in Law Enforcement District of Jefferson Parish,

There are three major factors in determining whether a contract is a contract of sale

or a contract to build or to work by the job. First, in a contract to build, the

“purchaser” has some control over the specifications of the object. Second, the

negotiations in a contract to build take place before the object is constructed.

Lastly, and most importantly, a building contract contemplates not only that the

builder will furnish the materials, but that he will also furnish his skill and labor in

order to build the desired object.

296 So. 3d at 1267-68 (quotation and citation omitted). “Thus, as a matter of law, the performance

of a custom design and manufacturing can be sufficient to establish that a contract’s primary

obligation is ‘to do’ rather than ‘to give.’” ConstructionSouth, Inc. v. Fire Windows & Doors,

Inc., 2013 WL 3242728, at *3 (E.D. La. June 25, 2013).

In the case at bar, Lamar’s contract with GMHorne was a construction contract, having a

primary obligation “to do,” rather than simply a sales contract, having a primary obligation “to

give.” As evidenced by Lamar’s own Rule 26 disclosures, the contract required GMHorne to

create shop drawings to design metal wall components unique to the Community Center project.35

These shop drawings were submitted to Lamar for review and approval of the architect, and then

upon approval, sent to Centria to fabricate the metal wall components.36 In other words, GM

Horne was not simply supplying to Lamar products off the shelf. A significant portion of

GMHorne’s work included design skills and the products were not prefabricated but rather built

according to GMHorne’s design. Thus, Lamar’s claims against GMHorne arise out of a

construction contract that is subject to La. R.S. 9:2772, and its claims against GMHorne are

perempted.

35 R. Docs. 66-3; 66-4; 66-5.

36 R. Doc. 66-5.

In this diversity case, the decision of the Louisiana appellate court in Law Enforcement

District of Jefferson Parish is instructive. In that case, the Law Enforcement District of Jefferson

Parish (the “District”) entered into a contract with MAPP Construction, LLC (“MAPP”) to build

a new crime laboratory. 296 So. 3d at 1261. MAPP subcontracted with GMHorne to supply and

install a wall panel system manufactured by Centria. Id. at 1261-62. GMHorne then contracted

with Centria to furnish the materials. Id. at 1262. The litigation arose because the wall panel

system leaked. Id. MAPP sued GMHorne, which in turn sued Centria. Id. Centria filed an

exception arguing that GMHorne’s claims against it arose from a construction contract and were

thus perempted by La. R.S. 9:2772. GMHorne naturally argued that it had a sales contract with

Centria that was subject to a ten-year liberative prescriptive period. Id. After examining the scope

of work Centria undertook to construct wall panels specifically for the District’s project, the

appellate court affirmed the trial court’s legal conclusion that GMHorne’s contract with Centria

was a construction contract, rather than a sales contract, because Centria had provided design

services and did not simply sell an off-the-shelf product to GMHorne. Id. at 1263-70 (upholding

exception of peremption under La. R.S. 9:2772). The same result follows for the case at bar where

the contract at issue called for GMHorne to design components of the wall panel system

specifically for the Community Center. Therefore, Lamar’s claims against GMHorne are also

perempted under La. R.S. 9:2772.

IV. CONCLUSION

Accordingly, for the foregoing reasons,

IT IS ORDERED that AR-Clad’s motion for summary judgment (R. Doc. 61) is

GRANTED, and Lamar’s claims against it are DISMISSED WITH PREJUDICE.

IT IS FURTHER ORDERED that GMHorne’s motion for summary judgment (R. Doc. 66)

is GRANTED, and Lamar’s claims against it are DISMISSED WITH PREJUDICE.

IT IS FURTHER ORDERED that Centria’s motion for summary judgment (R. Doc. 65) is

GRANTED, and Lamar’s claims against it are DISMISSED WITH PREJUDICE.

New Orleans, Louisiana, this 10th day of August, 2021.

________________________________

BARRY W. ASHE

UNITED STATES DISTRICT JUDGE