Opinion

SH Marathon, Ltd. v. Homesite Insurance Company

Court
District Court, S.D. Florida
Filed
Apr 7, 2021
Cited by
0 cases
Authority
More cited than 20.1%

The opinion

UNITED STATES DISTRICT COURT

SOUTHERN DISTRICT OF FLORIDA

KEY WEST DIVISION

CASE NO. 4:19-cv-10173-JLK

SH MARATHON, LTD., a limited

partnership

Plaintiff,

v.

HOMESITE INSURANCE COMPANY,

a corporation

Defendant.

_____________________________________/

ORDER GRANTING DEFENDANT’S MOTION FOR SUMMARY JUDGMENT

THIS CAUSE comes before the Court upon Defendant’s Motion for Summary Judgment

(the “Motion”) (DE 19), filed December 4, 2020. The Court has additionally considered Plaintiff’s

Response (DE 23) filed on January 4, 2021, and Defendant’s Reply (DE 29) filed on January 25,

2021.

I. BACKGROUND

The following facts are undisputed:

On June 19, 2017, Homesite Insurance Company (“Defendant”) issued a Standard Flood

Insurance Policy (“SFIP”) to SH Marathon (“Plaintiff”). Mot. at 6 ¶ 1. On September 10-11, 2017,

Hurricane Irma damaged the Plaintiff’s property. Id. at ¶ 2. On September 20, 2017, Plaintiff

submitted a claim to Defendant under its flood insurance policy for damages from the hurricane.

Id.

On October 5, 2017, Jason Dawsey, Defendant’s adjuster, mistakenly inspected the wrong

property at an incorrect address supplied by Richard West, Plaintiff’s public adjuster. Id. ¶ 4.

Dawsey took photos of the address, documented that there was no damage and recommended

closing the claim without payment. Mot. at 7 ¶ 5. Dawsey, testified: “. . . the public adjuster gave

me the wrong address, so this file should not have been closed without pay. It should have been

inspected with a public adjuster. . . .” Resp. Ex. 1 at 23:4–6, DE 23-1.

On October 11, 2017, Dawsey and West (adjusters for both parties) conducted a joint

inspection of the correct property. Mot. at 8 ¶ 11. After the inspection, Dawsey prepared several

estimates for building damages and continued to adjust the claim. Id. at 9 ¶ 12. On October 12,

2017, Defendant issued a letter to the Plaintiff denying its claim on the grounds of lack of damage.

Id. at 7 ¶ 6; see also DE 19-2. Plaintiff received the October 12, 2017 denial letter, retained counsel,

and notified Defendant of the alleged mistake. Id. at 7–8 ¶ 8.

On September 6, 2018, Defendant received Plaintiff’s request for additional payment

supported by a Proof of Loss dated August 30, 2018. Mot at 8 ¶ 9. On October 26, 2018, Defendant

rejected Plaintiff’s Proof of Loss and request for additional payment and reiterated its previous

denial of Plaintiff’s original flood claim. Id. ¶ 10. On September 6, 2019, Defendant issued a check

based on its adjuster’s estimate and mailed it to Plaintiff. Id. at 9 ¶ 14. The check has not been

cashed. Mot at 9 ¶ 14. On September 25, 2019, Plaintiff filed its Complaint alleging breach of its

Flood Policy and nonpayment of claims. Id. ¶ 15.

II. LEGAL STANDARD

Summary judgment is appropriate where there is “no genuine issue as to any material fact

and [] the moving party is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a); Anderson

v. Liberty Lobby, Inc., 477 U.S. 242, 247–48 (1986). An issue is genuine if a reasonable jury could

return a verdict for the nonmoving party. Mize v. Jefferson City Bd. of Educ., 93 F.3d 739, 742

2

(11th Cir. 1996). A fact is material if it may affect the outcome of the case under the applicable

substantive law. Allen v. Tyson Foods, Inc., 121 F.3d 642, 646 (11th Cir. 1997).

If a reasonable fact finder could draw more than one inference from the facts, creating a

genuine issue of material fact, summary judgment should not be granted. Samples ex rel. Samples

v. City of Atlanta, 846 F.2d 1328, 1330 (11th Cir. 1988). The moving party has the burden of

establishing both the absence of a genuine issue of material fact and that it is entitled to judgment

as a matter of law. See Matsushita Elec. Indus. Co., Ltd. v. Zenith Radio Corp., 475 U.S. 574,

586–87 (1986). On a motion for summary judgment, the court views the evidence and all

reasonable inferences in the light most favorable to the non-moving party. Davis v. Williams, 451

F.3d 759, 763 (11th Cir. 2006).

III. DISCUSSION

Defendant argues that Plaintiff’s lawsuit is barred by the SFIP Statute of Limitations. See

Mot. Specifically, Defendant argues that it issued a denial letter to Plaintiff dated October 12, 2017

which explicitly pointed out the one-year time limitation to file a lawsuit and thus triggered the

commencement of the statute of limitations which would expire on October 12, 2018. Id. at 12–

13. Plaintiff did not file the instant suit until September 25, 2019, almost two (2) years after the

October 12, 2017 denial letter. Id. at 13; See Compl.

In its Response, Plaintiff argues that its suit is not barred because the limitations period

commences when the Plaintiff has a complete and present cause of action. See Resp. Specifically,

Plaintiff argues that Defendant’s first denial letter, dated October 12, 2017, did not start the Statute

of limitations period because it was a “mistaken denial.” Id. at 9. Plaintiff further argues that “[t]he

only proper and valid denial of the claim occurred on October 26, 2018, when the Defendant sent

a letter to the Plaintiff denying its proof of loss.” Id. at 17.

3

In its Reply, Defendant argues that Plaintiff provided no case law to support its arguments.

Defendant in turn cites two cases from sister circuits which support that the initial denial letter

from an insurance company, even if based on mistaken facts, starts the one-year statute of

limitations period. See Wagner v. Dir., FEMA, 847 F.2d 515 (9th Cir 1988); See Cohen v. Allstate

Ins. Co., 924 F.3d 776 (5th Cir. 2019).

Federal law requires the claimant to bring suit within one year of the mailing of the denial

of the claimant's flood insurance claim. 42 U.S.C. § 4072; 44 C.F.R. § 62.22; Lynn Phillips and

James Brown v. American Strategic Insurance Corp., No. 4:18-cv-10292-JLK, 2020 U.S. Dist.

LEXIS 5423, at *1 (S.D. Fla. Jan. 10, 2020). The policy itself states: “[i]f you do sue, you must

start the suit within 1 year after the date of written denial of all or part of the claim. . . .” DE 19-6

at 16–17.

Here, Defendant initially denied Plaintiff’s claim by letter dated October 12, 2017 and

Plaintiff received this letter. See Denial Letter Ex. 2, DE 19-2; Mot. at 7–8 ¶ 8. The October 12,

2017 letter informed Plaintiff to “[f]ile suit within one (1) of the denial of your claim.” DE 19-2 at

3. Therefore, the one-year statute of limitations in this case expired on or about October 12, 2018

regardless of the mistaken inspection. Because Plaintiff did not bring suit until September 25,

2019, Plaintiff’s claim is time barred by the statute of limitations.

Accordingly, it is ORDERED, ADJUDGED, AND DECREED as follows:

1) Defendant’s Motion for Summary Judgment (DE 19) be, and the same is, hereby

GRANTED.

2) Defendant’s Motion in Limine (DE 20) is hereby DENIED AS MOOT.

3) Pursuant to Rule 58(a) of the Federal Rules of Civil Procedure, final judgment in favor

of Defendant will be set out in a separate Order.

4

DONE AND ORDERED in Chambers at the James Lawrence King Federal Justice

Building and U.S. Courthouse, Miami, Florida this 7th day of April, 2021.

□ JAMES LAWRENCE KING A

“~EINITED STATES DISTRICT JUDGE

ce: All counsel of record