Opinion

District Council 16 Northern California Health and Welfare Trust Fund v. Hulsey Contracting Inc.

Court
District Court, N.D. California
Filed
Sep 23, 2020
Cited by
0 cases
Authority
More cited than 18.7%

The opinion

1

2

3

4 UNITED STATES DISTRICT COURT

5 NORTHERN DISTRICT OF CALIFORNIA

6

DISTRICT COUNCIL 16 NORTHERN

7 CALIFORNIA HEALTH AND WELFARE Case No. 20-cv-02863-JCS

TRUST FUND, et al.,

8

Plaintiffs, ORDER GRANTING MOTION FOR

9 LEAVE TO FILE FIRST AMENDED

v. COMPLAINT AND DENYING

10 MOTION TO STRIKE

HULSEY CONTRACTING INC.,

11 Re: Dkt. Nos. 16, 24

Defendant.

12

13 I. INTRODUCTION A ND BACKGROUND

14 Plaintiffs1 move for leave to file a first amended complaint under Rule 15(a)(2) of the

15 Federal Rules of Civil Procedure in order to add a second defendant, Roberto Hulsey, an

16 individual who purportedly signed an agreement assuming individual liability for amounts owed

17 by the existing defendant, Hulsey Contracting Inc., under the terms of an applicable collective

18 bargaining agreement. See generally Mot. (dkt. 16). The Court finds the matter suitable for

19 resolution without oral argument under Civil Local Rule 7-1(b) and VACATES the hearing

20 noticed for October 9, 2020.2

21 In an opposition brief filed one week after the deadline to do so, Hulsey Contracting argues

22 that amendment should be denied as futile because the agreement signed by Mr. Hulsey was

23 signed “only in a capacity for an employer,” Opp’n (dkt. 22) at 6, because it does not recite any

24 consideration, id., because “hold[ing] an individual personally liable for such asserted massive

25 business debt is contrary to public policy,” id., and because of fraud in the execution of the

26

1 Plaintiffs are District Council 16 Northern California Health and Welfare Trust Fund and related

27

union trust funds and trustees.

1 underlying collective bargaining agreement, id. at 6–8. Hulsey Contracting also argues that a

2 discrepancy involving the signature pages to certain contracts at issue evinces bad faith by

3 Plaintiffs. Id. at 8–9. Mr. Hulsey asserts in a declaration that he was not presented with the

4 contracts themselves, but instead only with blank signature pages, and believed that his signature

5 indicated assent to different terms than contained in the contracts now submitted by Plaintiffs.

6 Hulsey Decl. (dkt. 22-1) ¶¶ 9–12.

7 II. ANALYSIS

8 In general, when a party seeks to amend a pleading more than twenty-one days after

9 serving it, or more than twenty-one days after service of a responsive pleading or motion, the party

10 must obtain either the opposing party’s consent or leave of the court. Fed. R. Civ. P. 15(a). The

11 Federal Rules of Civil Procedure provide that “courts should freely give leave when justice so

12 requires.” Id. “Courts may decline to grant leave to amend only if there is strong evidence of

13 ‘undue delay, bad faith or dilatory motive on the part of the movant, repeated failure to cure

14 deficiencies by amendments previously allowed, undue prejudice to the opposing party by virtue

15 of allowance of the amendment, [or] futility of amendment, etc.’” Sonoma Cty. Ass’n of Retired

16 Emps. v. Sonoma County, 708 F.3d 1109, 1117 (9th Cir. 2013) (quoting Foman v. Davis, 371 U.S.

17 178, 182 (1962)) (alteration in original). Of those factors, “prejudice to the opposing party carries

18 the most weight.” Brown v. Stored Value Cards, Inc., 953 F.3d 567, 574 (9th Cir. 2020).

19 “Requests for leave to amend should be granted with ‘extreme liberality.’” Id.

20 Here, Hulsey Contracting filed its answer on Sunday, July 19, 2020; the deadline to amend

21 by right therefore expired on Monday, August 10, 2020. Plaintiffs filed their motion for leave to

22 amend three weeks after that, on August 31, 2020, after becoming aware of the purported

23 agreement providing for individual liability by Mr. Hulsey. The parties have not yet appeared for

24 an initial case management conference, the record does not indicate that any other meaningful

25 development in the case happened during that three-week period, and Hulsey Contracting does not

26 argue that it was prejudiced by the short delay.

27 Instead, Hulsey Contracting’s arguments against amendment go to the merits of Plaintiffs’

] Hulsey Contracting. To the extent such issues can be resolved on the pleadings, they are better

2 || addressed on a motion to dismiss under Rule 12(b)(6) or a motion for judgment on the pleadings

3 || under Rule 12(c). To the extent they rely on evidence beyond the pleadings, such as Mr. Hulsey’s

4 || declaration regarding the circumstances of his signatures, they would be more appropriate for

5 summary judgment or trial. While Hulsey Contracting is correct that “futile amendments should

6 not be permitted,” Klamath-Lake Pharm. Ass'n v. Klamath Med. Serv. Bureau, 701 F.2d 1276,

7 1293 (9th Cir. 1983), Hulsey Contracting cites no case applying that standard to conduct a

8 summary-judgment-type inquiry before a claim is even filed, much less at such an early stage of

9 || the case and with no showing that the timing of the amendment, specifically, caused any prejudice

10 || toa defendant. The motion for leave to amend is therefore GRANTED, without prejudice to any

11 argument that Defendants might raise in a later motion attacking the sufficiency of Plaintiffs’

12 || allegations or the merits of their claims.

13 || IH. CONCLUSION

14 For the reasons discussed above, Plaintiffs’ motion for leave to amend is GRANTED,

3 15 || without prejudice to any motion that Defendants might raise in a motion under Rule 12 or at some

16 || other stage of the case. Plaintiffs shall file their first amended complaint no later than October 2,

17 || 2020, and Defendants shall respond by answer or motion no later than October 23, 2020. The

18 initial case management conference previously set for October 23, 2020 is CONTINUED to

19 || November 6, 2020 at 2:00 PM, and the parties shall file a joint case management statement no

20 later than October 30, 2020.

21 Plaintiffs filed a motion to strike Hulsey Contracting’s opposition brief as untimely. Dkt.

22 || 24. That motion is DENIED as moot. Going forward, the parties are encouraged to meet and

23 confer regarding such procedural disputes before seeking intervention by the Court.

24 IT ISSO ORDERED.

25 || Dated: September 23, 2020

26 5 Z Z c ao

JOSEPH C. SPERO

27 ief Magistrate Judge

28

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.