Federal Communications Commission FCC 18-133

Before the

FEDERAL COMMUNICATIONS COMMISSION

WASHINGTON, D.C. 20554

In the Matter of

Accelerating Wireless Broadband Deployment by Removing Barriers to Infrastructure Investment

Accelerating Wireline Broadband Deployment by Removing Barriers to Infrastructure Investment

)

)

)

)

)

)

)

WT Docket No. 17-79

WC Docket No. 17-84

DECLARATORY RULING AND THIRD REPORT AND ORDER

Adopted: September 26, 2018 Released: September 27, 2018

By the Commission: Chairman Pai and Commissioners O’Rielly and Carr issuing separate statements; Commissioner Rosenworcel approving in part, dissenting in part and issuing a statement.

TABLE OF CONTENTS

Heading Paragraph #

I. INTRODUCTION 1

II. BACKGROUND 14

A. Legal Background 14

B. The Need for Commission Action 23

III. DECLARATORY RULING 30

A. Overview of the Section 253 and Section 332(c)(7) Framework Relevant to Small Wireless Facilities Deployment 34

B. State and Local Fees 43

C. Other State and Local Requirements that Govern Small Facilities Deployment 81

D. States and Localities Act in Their Regulatory Capacities When Authorizing and Setting Terms for Wireless Infrastructure Deployment in Public Rights of Way 92

E. Responses to Challenges to Our Interpretive Authority and Other Arguments 98

IV. THIRD REPORT AND ORDER 103

A. NEW SHOT CLOCKS FOR SMALL WIRELESS FACILITY DEPLOYMENTS 104

1. Two New Section 332 Shot Clocks for Deployment of Small Wireless Facilities 105

2. Batched Applications for Small Wireless Facilities 113

B. NEW REMEDY FOR VIOLATIONS OF THE SMALL WIRELESS FACILITIES SHOT CLOCKS 116

C. CLARIFICATION OF ISSUES RELATED TO ALL SECTION 332 SHOT CLOCKS 132

1. Authorizations Subject to the “Reasonable Period of Time” Provision of Section 332(c)(7)(B)(ii) 132

2. Codification of Section 332 Shot Clocks 138

3. Collocations on Structures Not Previously Zoned for Wireless Use 140

4. When Shot Clocks Start and Incomplete Applications 141

V. PROCEDURAL MATTERS 148

VI

HOT CLOCKS 116

C. CLARIFICATION OF ISSUES RELATED TO ALL SECTION 332 SHOT CLOCKS 132

1. Authorizations Subject to the “Reasonable Period of Time” Provision of Section 332(c)(7)(B)(ii) 132

2. Codification of Section 332 Shot Clocks 138

3. Collocations on Structures Not Previously Zoned for Wireless Use 140

4. When Shot Clocks Start and Incomplete Applications 141

V. PROCEDURAL MATTERS 148

VI. ORDERING CLAUSES 151

APPENDIX A -- Final Rules

APPENDIX B -- Comments and Reply Comments

APPENDIX C -- Final Regulatory Flexibility Analysis

I. INTRODUCTION

1. America is in the midst of a transition to the next generation of wireless services, known as 5G. These new services can unleash a new wave of entrepreneurship, innovation, and economic opportunity for communities across the country. The FCC is committed to doing our part to help ensure the United States wins the global race to 5G to the benefit of all Americans. Today’s action is the next step in the FCC’s ongoing efforts to remove regulatory barriers that would unlawfully inhibit the deployment of infrastructure necessary to support these new services. We proceed by drawing on the balanced and commonsense ideas generated by many of our state and local partners in their own small cell bills.

2. Supporting the deployment of 5G and other next-generation wireless services through smart infrastructure policy is critical. Indeed, upgrading to these new services will, in many ways, represent a more fundamental change than the transition to prior generations of wireless service. 5G can enable increased competition for a range of services—including broadband—support new healthcare and Internet of Things applications, speed the transition to life-saving connected car technologies, and create jobs

policy is critical. Indeed, upgrading to these new services will, in many ways, represent a more fundamental change than the transition to prior generations of wireless service. 5G can enable increased competition for a range of services—including broadband—support new healthcare and Internet of Things applications, speed the transition to life-saving connected car technologies, and create jobs. It is estimated that wireless providers will invest $275 billion See Accenture Strategy, Accelerating Future Economic Value from the Wireless Industry at 2 (2018) (Accelerating Future Economic Value Report), https://www.ctia.org/news/accelerating-future-economic-value-from-the-wireless-industry, attached to Letter from Scott K. Bergmann, Senior Vice Pres., Reg. Affairs, CTIA to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79 (filed July 19, 2018).

over the next decade in next-generation wireless infrastructure deployments, which should generate an expected three million new jobs and boost our nation’s GDP by half a trillion dollars. See Accenture Strategy, Smart Cities: How 5G Can Help Municipalities Become Vibrant Smart Cities, (2017) http://www.ctia.org/docs/default-source/default-document-library/how-5g-can-help-municipalities-become-vibrantsmart-cities-accenture.pdf; attached to Letter from Scott Bergmann, Vice Pres. Reg. Affairs, CTIA to Marlene H. Dortch, Secretary, FCC, WT Docket No. 16-421, (filed Jan. 13, 2017).

Moving quickly to enable this transition is important, as a new report forecasts that speeding 5G infrastructure deployment by even one year would unleash an additional $100 billion to the U.S. economy. Accelerating Future Economic Value Report at 2.

Removing barriers can also ensure that every community gets a fair shot at these deployments and the opportunities they enable.

3. The challenge for policymakers is that the deployment of these new networks will look different than the 3G and 4G deployments of the past

y even one year would unleash an additional $100 billion to the U.S. economy. Accelerating Future Economic Value Report at 2.

Removing barriers can also ensure that every community gets a fair shot at these deployments and the opportunities they enable.

3. The challenge for policymakers is that the deployment of these new networks will look different than the 3G and 4G deployments of the past. Over the last few years, providers have been increasingly looking to densify their networks with new small cell deployments that have antennas often no larger than a small backpack. From a regulatory perspective, these raise different issues than the construction of large, 200-foot towers that marked the 3G and 4G deployments of the past. Indeed, estimates predict that upwards of 80 percent of all new deployments will be small cells going forward. Letter from John T. Scott, Counsel for Mobilitie, LLC, to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79 at 2-3 (filed Sept. 12, 2018).

To support advanced 4G or 5G offerings, providers must build out small cells at a faster pace and at a far greater density of deployment than before.

4. To date, regulatory obstacles have threatened the widespread deployment of these new services and, in turn, U.S. leadership in 5G. The FCC has lifted some of those barriers, including our decision in March 2018, which excluded small cells from some of the federal review procedures designed for those larger, 200-foot towers. But as the record here shows, the FCC must continue to act in partnership with our state and local leaders that are adopting forward leaning policies.

5. Many states and localities have acted to update and modernize their approaches to small cell deployments. They are working to promote deployment and balance the needs of their communities. At the same time, the record shows that problems remain. In fact, many state and local officials have urged the FCC to continue our efforts in this proceeding and adopt additional reforms

eaning policies.

5. Many states and localities have acted to update and modernize their approaches to small cell deployments. They are working to promote deployment and balance the needs of their communities. At the same time, the record shows that problems remain. In fact, many state and local officials have urged the FCC to continue our efforts in this proceeding and adopt additional reforms. Indeed, we have heard from a number of local officials that the excessive fees or other costs associated with deploying small scale wireless infrastructure in large or otherwise “must serve” cities are materially inhibiting the buildout of wireless services in their own communities.

6. We thus find that now is the appropriate time to move forward with an approach geared at the conduct that threatens to limit the deployment of 5G services. In reaching our decision today, we have benefited from the input provided by a range of stakeholders, including state and local elected officials. See, e.g., Letter from Brian D. Hill, Ohio State Representative, to the Hon. Brendan Carr, Commissioner, FCC, WT Docket No. 17-79 at 1-2 (filed Aug. 31, 2018) (“While the FCC and the Ohio Legislature have worked to reduce the timeline for 5G deployment, the same cannot be said for all local and state governments. Regulations written in a different era continue to dictate the regulatory process for 5G infrastructure”); Letter from Maureen Davey, Commissioner, Stillwater County, to the Hon. Brendan Carr, Commissioner, FCC, WT Docket No. 17-79 at 1-2 (filed Sept. 18, 2018) (“[T]he Commission’s actions to lower regulatory barriers can enable more capital spending to flow to areas like ours. Reducing fees and shortening review times in urban areas, thereby lowering the cost of deployment in such areas, can promote speedier deployment across all of America.”); Letter from Board of County Commissioners, Yellowstone County, to the Hon. Brendan Carr, Commissioner, FCC, WT Docket No. 17-79 at 1-2 (filed Sept

regulatory barriers can enable more capital spending to flow to areas like ours. Reducing fees and shortening review times in urban areas, thereby lowering the cost of deployment in such areas, can promote speedier deployment across all of America.”); Letter from Board of County Commissioners, Yellowstone County, to the Hon. Brendan Carr, Commissioner, FCC, WT Docket No. 17-79 at 1-2 (filed Sept. 21, 2018) (“Reducing these regulatory barriers by setting guidelines on fees, siting requirements and review timeframes, will promote investment including rural areas like ours.”); Letter from Board of Commissioners, Harney County, Oregon, to the Hon. Brendan Carr, Commissioner, FCC, WT Docket No. 17-79 at 1-2 (filed Sept. 5, 2018) (“By taking action to speed and reduce the costs of deployment across the country, and create a more uniform regulatory framework, the Commission will lower the cost of deployment, enabling more investment in both urban and rural communities.”); Letter from Niraj J. Antani, Ohio State Representative, to the Hon. Brendan Carr, Commissioner, FCC, WT Docket No. 17-79 at 1-2 (filed Sept. 4, 2018) (“[T]o truly expedite the small cell deployment process, broader government action is needed on more than just the state level.”); Letter from Michael C. Taylor, Mayor, City of Sterling Heights, to the Hon. Brendan Carr, Commissioner, FCC, WT Docket No. 17-79 at 1-2 (filed Aug. 30, 2018) (“[T]here are significant, tangible benefits to having a nation-wide rule that promotes the deployment of next-generation wireless access without concern that excessive regulation or small cell siting fees slows down the process.”).

FCC leadership spent substantial time over the course of this proceeding meeting directly with local elected officials in their jurisdictions. In light of those discussions and our consideration of the record here, we reach a decision today that does not preempt nearly any of the provisions passed in recent state-level small cell bills

ion or small cell siting fees slows down the process.”).

FCC leadership spent substantial time over the course of this proceeding meeting directly with local elected officials in their jurisdictions. In light of those discussions and our consideration of the record here, we reach a decision today that does not preempt nearly any of the provisions passed in recent state-level small cell bills. We have reached a balanced, commonsense approach, rather than adopting a one-size-fits-all regime. This ensures that state and local elected officials will continue to play a key role in reviewing and promoting the deployment of wireless infrastructure in their communities.

7. Although many states and localities support our efforts, we acknowledge that there are others who advocated for different approaches. See, e.g., Letter from Linda Morse, Mayor, City of Manhattan, KS to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79 at 1-2 (filed Sept. 13, 2018) (City of Manhattan, KS Sept. 13, 2018 Ex Parte Letter); Letter from Ronny Berdugo, Legislative Representative, League of California Cities to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79 at 1-2 (filed Sept. 18, 2018) (Ronny Berdugo Sept. 18, 2018 Ex Parte Letter); Letter from Damon Connolly, Marin County Board of Supervisors to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79 at 1-2 (filed Sept. 17, 2018) (Damon Connolly Sept. 17, 2018 Ex Parte Letter).

We have carefully considered these views, but nevertheless find our actions here necessary and fully supported. By building on state and local ideas, today’s action boosts the United States’ standing in the race to 5G. According to a study submitted by Corning, our action would eliminate around $2 billion in unnecessary costs, which would stimulate around $2.4 billion of additional buildouts. See Letter from Thomas J. Navin, Counsel to Corning, Inc., to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79 at 1, Attach. A at 2-3 (filed Sept. 5, 2018) (Corning Sept

the United States’ standing in the race to 5G. According to a study submitted by Corning, our action would eliminate around $2 billion in unnecessary costs, which would stimulate around $2.4 billion of additional buildouts. See Letter from Thomas J. Navin, Counsel to Corning, Inc., to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79 at 1, Attach. A at 2-3 (filed Sept. 5, 2018) (Corning Sept. 5, 2018 Ex Parte Letter).

And that study shows that such new service would be deployed where it is needed most: 97 percent of new deployments would be in rural and suburban communities that otherwise would be on the wrong side of the digital divide. Id.

8. The FCC will keep pressing ahead to ensure that every community in the country gets a fair shot at the opportunity that next-generation wireless services can enable. As detailed in the sections that follow, we do so by taking the following steps.

9. In the Declaratory Ruling, we note that a number of appellate courts have articulated different and often conflicting views regarding the scope and nature of the limits Congress imposed on state and local governments through Sections 253 and 332. We thus address and reconcile this split in authorities by taking three main actions.

10. First, we express our agreement with the U.S. Courts of Appeals for the First, Second, and Tenth Circuits that the “materially inhibit” standard articulated in 1997 by the Clinton-era FCC’s California Payphone decision is the appropriate standard for determining whether a state or local law operates as a prohibition or effective prohibition within the meaning of Sections 253 and 332.

11. Second, we note, as numerous courts and prior FCC cases have recognized, that state and local fees and other charges associated with the deployment of wireless infrastructure can unlawfully prohibit the provision of service. At the same time, courts have articulated various approaches to determining the types of fees that run afoul of Congress’s limits in Sections 253 and 332

253 and 332.

11. Second, we note, as numerous courts and prior FCC cases have recognized, that state and local fees and other charges associated with the deployment of wireless infrastructure can unlawfully prohibit the provision of service. At the same time, courts have articulated various approaches to determining the types of fees that run afoul of Congress’s limits in Sections 253 and 332. We thus clarify the particular standard that governs the fees and charges that violate Sections 253 and 332 when it comes to the Small Wireless Facilities at issue in this decision. “Small Wireless Facilities,” as used herein and consistent with section 1.1312(e)(2), encompasses facilities that meet the following conditions:

(1) The facilities—

(i) are mounted on structures 50 feet or less in height including their antennas as defined in section 1.1320(d), or

(ii) are mounted on structures no more than 10 percent taller than other adjacent structures, or

(iii) do not extend existing structures on which they are located to a height of more than 50 feet or by more than 10 percent, whichever is greater;

(2) Each antenna associated with the deployment, excluding associated antenna equipment (as defined in the definition of antenna in section 1.1320(d)), is no more than three cubic feet in volume;

(3) All other wireless equipment associated with the structure, including the wireless equipment associated with the antenna and any pre-existing associated equipment on the structure, is no more than 28 cubic feet in volume;

(4) The facilities do not require antenna structure registration under part 17 of this chapter;

(5) The facilities are not located on Tribal lands, as defined under 36 CFR 800.16(x); and

eless equipment associated with the structure, including the wireless equipment associated with the antenna and any pre-existing associated equipment on the structure, is no more than 28 cubic feet in volume;

(4) The facilities do not require antenna structure registration under part 17 of this chapter;

(5) The facilities are not located on Tribal lands, as defined under 36 CFR 800.16(x); and

(6) The facilities do not result in human exposure to radiofrequency radiation in excess of the applicable safety standards specified in section 1.1307(b).

Namely, fees are only permitted to the extent that they are nondiscriminatory and represent a reasonable approximation of the locality’s reasonable costs. In this section, we also identify specific fee levels for the deployment of Small Wireless Facilities that presumptively comply with this standard. We do so to help avoid unnecessary litigation over fees.

12. Third, we focus on a subset of other, non-fee provisions of local law that could also operate as prohibitions on service. We do so in particular by addressing state and local consideration of aesthetic concerns in the deployment of Small Wireless Facilities, recognizing that certain reasonable aesthetic considerations do not run afoul of Sections 253 and 332. This responds in particular to many concerns we heard from state and local governments about deployments in historic districts.

13. Next, we issue a Report and Order that addresses the “shot clocks” governing the review of wireless infrastructure deployments. We take three main steps in this regard. First, we create a new set of shot clocks tailored to support the deployment of Small Wireless Facilities. In particular, we read Sections 253 and 332 as allowing 60 days for reviewing the application for attachment of a Small Wireless Facility using an existing structure and 90 days for the review of an application for attachment of a small wireless facility using a new structure

n this regard. First, we create a new set of shot clocks tailored to support the deployment of Small Wireless Facilities. In particular, we read Sections 253 and 332 as allowing 60 days for reviewing the application for attachment of a Small Wireless Facility using an existing structure and 90 days for the review of an application for attachment of a small wireless facility using a new structure. Second, while we do not adopt a “deemed granted” remedy for violations of our new shot clocks, we clarify that failing to issue a decision up or down during this time period is not simply a “failure to act” within the meaning of applicable law. Rather, missing the deadline also constitutes a presumptive prohibition. We would thus expect any locality that misses the deadline to issue any necessary permits or authorizations without further delay. We also anticipate that a provider would have a strong case for quickly obtaining an injunction from a court that compels the issuance of all permits in these types of cases. Third, we clarify a number of issues that are relevant to all of the FCC’s shot clocks, including the types of authorizations subject to these time periods.

II. BACKGROUND

A. Legal Background

14. In the Telecommunications Act of 1996 (the 1996 Act), Congress enacted sweeping new provisions intended to facilitate the deployment of telecommunications infrastructure. As U.S. Courts of Appeals have stated, “[t]he [1996] Act ‘represents a dramatic shift in the nature of telecommunications regulation.’” Sprint Telephony PCS LP v. County of San Diego, 543 F.3d 571, 575 (9th Cir. 2008) (en banc) (County of San Diego) (quoting Cablevision of Boston, Inc. v. Pub. Improvement Comm’n, 184 F.3d 88, 97 (1st Cir. 1999)).

The Senate floor manager, Senator Larry Pressler, stated that “[t]his is the most comprehensive deregulation of the telecommunications industry in history.” 141 Cong. Rec. S8197 (daily ed. June 12, 1995)

S LP v. County of San Diego, 543 F.3d 571, 575 (9th Cir. 2008) (en banc) (County of San Diego) (quoting Cablevision of Boston, Inc. v. Pub. Improvement Comm’n, 184 F.3d 88, 97 (1st Cir. 1999)).

The Senate floor manager, Senator Larry Pressler, stated that “[t]his is the most comprehensive deregulation of the telecommunications industry in history.” 141 Cong. Rec. S8197 (daily ed. June 12, 1995).

Indeed, the purpose of the 1996 Act is to “provide for a pro-competitive, deregulatory national policy framework . . . by opening all telecommunications markets to competition.” H.R. Conf. Rep. No. 104–458, at 113 (1996), reprinted in 1996 U.S.C.C.A.N. (100 Stat. 5) 124.

The conference report on the 1996 Act similarly indicates that Congress “intended to remove all barriers to entry in the provision of telecommunications services.” S. Rep. No. 104-230, at 126 (1996) (Conf. Rep.).

The 1996 Act thus makes clear Congress’s commitment to a competitive telecommunications marketplace unhindered by unnecessary regulations, explicitly directing the FCC to “promote competition and reduce regulation in order to secure lower prices and higher quality services for American telecommunications consumers and encourage the rapid deployment of new telecommunications technologies.” Preamble, Telecommunications Act of 1996, P.L. 104-104, 100 Stat. 56 (1996); see also AT&T Corp. v. Iowa Utils. Bd., 525 U.S. 366, 371 (1999) (noting that the 1996 Act “fundamentally restructures local telephone markets” to facilitate market entry); Reno v. American Civil Liberties Union, 521 U.S. 844, 857-58 (1997) (“The Telecommunications Act was an unusually important legislative enactment . . . designed to promote competition.”).

15. Several provisions of the 1996 Act speak directly to Congress’s determination that certain state and local regulations are unlawful

ally restructures local telephone markets” to facilitate market entry); Reno v. American Civil Liberties Union, 521 U.S. 844, 857-58 (1997) (“The Telecommunications Act was an unusually important legislative enactment . . . designed to promote competition.”).

15. Several provisions of the 1996 Act speak directly to Congress’s determination that certain state and local regulations are unlawful. Section 253(a) provides that “[n]o State or local statute or regulation, or other State or local legal requirement, may prohibit or have the effect of prohibiting the ability of any entity to provide any interstate or intrastate telecommunications service.” 47 U.S.C. § 253(a).

Courts have observed that Section 253 represents a “broad preemption of laws that inhibit competition.” Puerto Rico Tel. Co. v. Telecomm. Reg. Bd. of Puerto Rico, 189 F.3d 1, 11 n.7 (1st Cir. 1999).

16. The Commission has issued several rulings interpreting and providing guidance regarding the language Congress used in Section 253. For instance, in the 1997 California Payphone decision, the Commission, under the leadership of then Chairman William Kennard, stated that, in determining whether a state or local law has the effect of prohibiting the provision of telecommunications services, it “consider[s] whether the ordinance materially inhibits or limits the ability of any competitor or potential competitor to compete in a fair and balanced legal and regulatory environment.” California Payphone Ass’n, 12 FCC Rcd 14191, 14206, para. 31 (1997) (California Payphone).

17. Similar to Section 253, Congress specified in Section 332(c)(7) that “[t]he regulation of the placement, construction, and modification of personal wireless service facilities by any State or local government or instrumentality thereof—(I) shall not unreasonably discriminate among providers of functionally equivalent services; and (II) shall not prohibit or have the effect of prohibiting the provision of personal wireless services.” 47 U.S.C. § 332(c)(7)(B)(i)

that “[t]he regulation of the placement, construction, and modification of personal wireless service facilities by any State or local government or instrumentality thereof—(I) shall not unreasonably discriminate among providers of functionally equivalent services; and (II) shall not prohibit or have the effect of prohibiting the provision of personal wireless services.” 47 U.S.C. § 332(c)(7)(B)(i).

Clause (B)(ii) of that section further provides that “[a] State or local government or instrumentality thereof shall act on any request for authorization to place, construct, or modify personal wireless service facilities within a reasonable period of time after the request is duly filed with such government or instrumentality, taking into account the nature and scope of such request.” 47 U.S.C § 332(c)(7)(B)(ii).

Section 332(c)(7) generally preserves state and local authority over the “placement, construction, and modification of personal wireless service facilities” but with the important limitations described above. 47 U.S.C. § 332(c)(7)(A) (stating that, “[e]xcept as provided in this paragraph, nothing in this chapter shall limit or affect the authority of a State or local government or instrumentality thereof over decisions regarding the placement, construction, and modification of personal wireless services facilities”). The statute defines “personal wireless services” to include CMRS, unlicensed wireless services, and common carrier wireless exchange access services. 47 U.S.C. § 332(c)(7)(C). In 2012, Congress expressly modified this preservation of local authority by enacting Section 6409(a), which requires local governments to approve certain types of facilities siting applications “[n]otwithstanding section 704 of the Telecommunications Act of 1996 [codified in substantial part as Section 332(c)(7)] . . . or any other provision of law.” Spectrum Act, 47 U.S.C. § 6409(a)(1)

(7)(C). In 2012, Congress expressly modified this preservation of local authority by enacting Section 6409(a), which requires local governments to approve certain types of facilities siting applications “[n]otwithstanding section 704 of the Telecommunications Act of 1996 [codified in substantial part as Section 332(c)(7)] . . . or any other provision of law.” Spectrum Act, 47 U.S.C. § 6409(a)(1).

Section 332(c)(7) also sets forth a judicial remedy, stating that “[a]ny person adversely affected by any final action or failure to act by a State or local government” that is inconsistent with the requirements of Section 332(c)(7) “may, within 30 days after such action or failure to act, commence an action in any court of competent jurisdiction.” 47 U.S.C. § 332(c)(7)(B)(v).

The provision further directs the court to “decide such action on an expedited basis.” 47 U.S.C. § 332(c)(7)(B)(v).

18. The Commission has previously interpreted the language Congress used and the limits it imposed on state and local authority in Section 332. For instance, in interpreting Section 332(c)(7)(B)(i)(II), the Commission has found that “a State or local government that denies an application for personal wireless service facilities siting solely because ‘one or more carriers serve a given geographic market’ has engaged in unlawful regulation that ‘prohibits or ha[s] the effect of prohibiting the provision of personal wireless services,’ within the meaning of Section 332(c)(7)(B)(i)(II).” Petition for Declaratory Ruling to Clarify Provisions of Section 332(c)(7) to Ensure Timely Siting Review, Declaratory Ruling, 24 FCC Rcd 13994, 14016, para. 56 (2009) (2009 Declaratory Ruling), aff’d, City of Arlington v. FCC, 668 F.3d 229 (5th Cir. 2012) (City of Arlington), aff’d, 569 U.S. 290 (2013)

e provision of personal wireless services,’ within the meaning of Section 332(c)(7)(B)(i)(II).” Petition for Declaratory Ruling to Clarify Provisions of Section 332(c)(7) to Ensure Timely Siting Review, Declaratory Ruling, 24 FCC Rcd 13994, 14016, para. 56 (2009) (2009 Declaratory Ruling), aff’d, City of Arlington v. FCC, 668 F.3d 229 (5th Cir. 2012) (City of Arlington), aff’d, 569 U.S. 290 (2013).

In adopting this interpretation, the Commission explained that its “construction of the provision achieves a balance that is most consistent with the relevant goals of the Communications Act” and its understanding that “[i]n promoting the construction of nationwide wireless networks by multiple carriers, Congress sought ultimately to improve service quality and lower prices for consumers.” 2009 Declaratory Ruling, 24 RCC Rcd at 14017-18, para. 61.

The Commission also noted that an alternative interpretation would “diminish the service provided to [a wireless provider’s] customers.” Id.

19. In the 2009 Declaratory Ruling, the Commission acted to speed the deployment of then-new 4G services and concluded that, “[g]iven the evidence of unreasonable delays [in siting decisions] and the public interest in avoiding such delays,” it should offer guidance regarding the meaning of the statutory phrases “reasonable period of time” and “failure to act” “in order to clarify when an adversely affected service provider may take a dilatory State or local government to court.” Id. at 14008, para. 37; see also id. at 14029 (Statement of Chairman Julius Genachowski) (“[T]he rules we adopt today . . . will have an important effect in speeding up wireless carriers’ ability to build new 4G networks--which will in turn expand and improve the range of wireless choices available to American consumers.”).

The Commission interpreted “reasonable period of time” under Section 332(c)(7)(B)(ii) to be 90 days for processing collocation applications and 150 days for processing applications other than collocations. Id. at 14012, para

in speeding up wireless carriers’ ability to build new 4G networks--which will in turn expand and improve the range of wireless choices available to American consumers.”).

The Commission interpreted “reasonable period of time” under Section 332(c)(7)(B)(ii) to be 90 days for processing collocation applications and 150 days for processing applications other than collocations. Id. at 14012, para. 45.

The Commission further determined that failure to meet the applicable time frame enables an applicant to pursue judicial relief within the next 30 days. Id. at 14005, 14012, paras. 32, 45.

In litigation involving the 90-day and 150-day time frames, the locality may attempt to “rebut the presumption that the established timeframes are reasonable.” Id. at 14008-10, 14013-14, paras. 37-42, 49-50.

If the agency fails to make such a showing, it may face “issuance of an injunction granting the application.” Id. at 14009, para. 38; see also City of Rancho Palos Verdes v. Abrams, 544 U.S. 113, 115 (2005) (proper remedies for Section 332(c)(7) violations include injunctions but not constitutional tort damages).

In its 2014 Wireless Infrastructure Order, Specifically, the Commission determined that once a siting application is considered complete for purposes of triggering the Section 332(c)(7) shot clocks, those shot clocks run regardless of any moratoria imposed by state or local governments, and the shot clocks apply to DAS and small-cell deployments so long as they are or will be used to provide “personal wireless services.” Acceleration of Broadband Deployment by Improving Wireless Facilities Siting Policies, Report & Order, 29 FCC Rcd 12865, 12966, 12973, paras. 243, 270, (2014) (2014 Wireless Infrastructure Order), aff’d, Montgomery County v. FCC, 811 F.3d 121 (4th Cir. 2015) (Montgomery County); see also Accelerating Wireless Broadband Deployment by Removing Barriers to Infrastructure Investment, Notice of Proposed Rulemaking and Notice of Inquiry, 32 FCC Rcd 3330, 3339, para

lities Siting Policies, Report & Order, 29 FCC Rcd 12865, 12966, 12973, paras. 243, 270, (2014) (2014 Wireless Infrastructure Order), aff’d, Montgomery County v. FCC, 811 F.3d 121 (4th Cir. 2015) (Montgomery County); see also Accelerating Wireless Broadband Deployment by Removing Barriers to Infrastructure Investment, Notice of Proposed Rulemaking and Notice of Inquiry, 32 FCC Rcd 3330, 3339, para. 22 (2017) (Wireless Infrastructure NPRM/NOI); Accelerating Wireline Broadband Deployment by Removing Barriers to Infrastructure Investment, Third Report and Order and Declaratory Ruling, WC Docket No. 17-84 and WT Docket No. 17-79, FCC 18-111, paras. 140-68 (rel. Aug. 3, 2018) (Moratoria Declaratory Ruling).

the Commission clarified that the time frames under Section 332(c)(7) are presumptively reasonable and begin to run when the application is submitted, not when it is found to be complete by a siting authority. 2014 Wireless Infrastructure Order, 29 FCC Rcd at 12970, para. 258. (“Accordingly, to the extent municipalities have interpreted the clock to begin running only after a determination of completeness, that interpretation is incorrect.”).

20. In 2012, Congress adopted Section 6409 of the Middle Class Tax Relief and Job Creation Act (the Spectrum Act), which provides further evidence of Congressional intent to limit state and local laws that operate as barriers to infrastructure deployment. It states that, “[n]otwithstanding section 704 of the Telecommunications Act of 1996 [codified as 47 U.S.C. § 332(c)(7)] or any other provision of law, a State or local government may not deny, and shall approve, any eligible facilities request for a modification of an existing wireless tower or base station that does not substantially change the physical dimensions of such tower or base station.” Middle Class Tax Relief and Job Creation Act of 2012, Pub. L. No. 112-96 § 6409(a)(2), 126 Stat. 156 (2012)

§ 332(c)(7)] or any other provision of law, a State or local government may not deny, and shall approve, any eligible facilities request for a modification of an existing wireless tower or base station that does not substantially change the physical dimensions of such tower or base station.” Middle Class Tax Relief and Job Creation Act of 2012, Pub. L. No. 112-96 § 6409(a)(2), 126 Stat. 156 (2012).

Subsection (a)(2) defines the term “eligible facilities request” as any request for modification of an existing wireless tower or base station that involves (a) collocation of new transmission equipment; (b) removal of transmission equipment; or (c) replacement of transmission equipment. Id.

In implementing Section 6409 and in an effort to “advance[e] Congress’s goal of facilitating rapid deployment,” 2014 Wireless Infrastructure Order, 29 FCC Rcd at 12872, para. 15.

the Commission adopted rules to expedite the processing of eligible facilities requests, including documentation requirements and a 60-day period for states and localities to review such requests. Id. at 12922, 12956-57, paras. 135, 214-15.

The Commission further determined that a “deemed granted” remedy was necessary for cases in which the reviewing authority fails to issue a decision within the 60-day period in order to “ensur[e] rapid deployment of commercial and public safety wireless broadband services.” Id. at 12961-62, paras. 226, 228.

The Fourth Circuit, affirming that remedy, explained that “[f]unctionally, what has occurred here is that the FCC—pursuant to properly delegated Congressional authority—has preempted state regulation of wireless towers.” Montgomery County, 811 F.3d at 129.

21. Consistent with these broad federal mandates, courts have recognized that the Commission has authority to interpret Sections 253 and 332 of the Act to further elucidate what types of state and local legal requirements run afoul of the statutory parameters Congress established

ated Congressional authority—has preempted state regulation of wireless towers.” Montgomery County, 811 F.3d at 129.

21. Consistent with these broad federal mandates, courts have recognized that the Commission has authority to interpret Sections 253 and 332 of the Act to further elucidate what types of state and local legal requirements run afoul of the statutory parameters Congress established. See, e.g., City of Arlington, 668 F.3d at 253-54; County of San Diego, 543 F.3d at 578; RT Commc’ns., Inc. v. FCC, 201 F.3d 1264, 1268 (10th Cir. 2000).

For instance, the Fifth Circuit affirmed the 2009 Declaratory Ruling in City of Arlington. The court concluded that the Commission possessed the “authority to establish the 90– and 150–day time frames” and that its decision was not arbitrary and capricious. City of Arlington, 668 F.3d at 254, 260-61.

More generally, as the agency charged with administering the Communications Act, the Commission has the authority, responsibility, and expert judgement to issue interpretations of the statutory language and to adopt implementing regulations that clarify and specify the scope and effect of the Act. Such interpretations are particularly appropriate where the statutory language is ambiguous, or the subject matter is “technical, complex, and dynamic,” as it is in the Communications Act, as recognized by the Supreme Court. Nat’l Cable & Telecomm. Ass’n v. Gulf Power Co., 534 U.S. 327, 328 (2002); FDA v. Brown & Williamson Tobacco Corp., 529 U.S. 120 (2000) (recognizing “agency’s greater familiarity with the ever-changing facts and circumstances surrounding the subjects regulated”); see also, e.g., Nat’l Cable & Telecomm. Ass’n v. Brand X Internet Servs., 545 U.S. 967, 983-986 (2005) (Commission’s interpretation of an ambiguous statutory provision overrides earlier court decisions interpreting the same provision).

Here, the Commission has ample experience monitoring and regulating the telecommunications sector

g facts and circumstances surrounding the subjects regulated”); see also, e.g., Nat’l Cable & Telecomm. Ass’n v. Brand X Internet Servs., 545 U.S. 967, 983-986 (2005) (Commission’s interpretation of an ambiguous statutory provision overrides earlier court decisions interpreting the same provision).

Here, the Commission has ample experience monitoring and regulating the telecommunications sector. It is well-positioned, in light of this experience and the record in this proceeding, to issue a clarifying interpretation of Sections 253 and 332(c)(7) that accounts both for the changing needs of a dynamic wireless sector that is increasingly reliant on Small Wireless Facilities and for state and local oversight that does not materially inhibit wireless deployment.

22. The congressional and FCC decisions described above point to consistent federal action, particularly when faced with changes in technology, to ensure that our country’s approach to wireless infrastructure deployment promotes buildout of the facilities needed to provide Americans with next-generation services. Consistent with that long-standing approach, in the 2017 Wireless Infrastructure NPRM/NOI, the Commission sought comment on whether the FCC should again update its approach to infrastructure deployment to ensure that regulations are not operating as prohibitions in violation of Congress’s decisions and federal policy. See generally Wireless Infrastructure NPRM/NOI, 32 FCC Rcd at 3332-39, paras. 4-22.

In August 2018, the Commission concluded that state and local moratoria on telecommunications services and facilities deployment are barred by Section 253(a). See generally Moratoria Declaratory Ruling, FCC 18-111, paras. 140-68.

B. The Need for Commission Action

23

f Congress’s decisions and federal policy. See generally Wireless Infrastructure NPRM/NOI, 32 FCC Rcd at 3332-39, paras. 4-22.

In August 2018, the Commission concluded that state and local moratoria on telecommunications services and facilities deployment are barred by Section 253(a). See generally Moratoria Declaratory Ruling, FCC 18-111, paras. 140-68.

B. The Need for Commission Action

23. In response to the opportunities presented by offering new wireless services, and the problems facing providers that seek to deploy networks to do so, we find it necessary and appropriate to exercise our authority to interpret the Act and clarify the preemptive scope that Congress intended. The introduction of advanced wireless services has already revolutionized the way Americans communicate and transformed the U.S. economy. Indeed, the FCC’s most recent wireless competition report indicates that American demand for wireless services continues to grow exponentially. It has been reported that monthly data usage per smartphone subscriber rose to an average of 3.9 gigabytes per subscriber per month, an increase of approximately 39 percent from year-end 2015 to year-end 2016. See Implementation of Section 6002(b) of the Omnibus Budget Reconciliation Act of 1993 Annual Report and Analysis of Competitive Market Conditions with Respect to Mobile Wireless, Including Commercial Mobile Services, Twentieth Report, 32 FCC Rcd 8968, 8972, para. 20 (2017) (Twentieth Wireless Competition Report).

As more Americans use more wireless services, demand for new technologies, coverage and capacity will necessarily increase, making it critical that the deployment of wireless infrastructure, particularly Small Wireless Facilities, not be stymied by unreasonable state and local requirements.

24. 5G wireless services, in particular, will transform the U.S. economy through increased use of high-bandwidth and low-latency applications and through the growth of the Internet of Things

and capacity will necessarily increase, making it critical that the deployment of wireless infrastructure, particularly Small Wireless Facilities, not be stymied by unreasonable state and local requirements.

24. 5G wireless services, in particular, will transform the U.S. economy through increased use of high-bandwidth and low-latency applications and through the growth of the Internet of Things. See Wireless Infrastructure NPRM/NOI, 32 FCC Rcd at 3331, para. 1.

While the existing wireless infrastructure in the U.S. was erected primarily using macro cells with relatively large antennas and towers, wireless networks increasingly have required the deployment of small cell systems to support increased usage and capacity. We expect this trend to increase with next-generation networks, as demand continues to grow, and providers deploy 5G service across the nation. See, e.g., Letter from Brett Haan, Principal, Deloitte Consulting, U.S., to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79 at 2 (filed Sept. 17, 2018) (“Significant investment in new network infrastructure is needed to deploy 5G networks at-scale in the United States. 5G’s speed and coverage capabilities rely on network densification, which requires the addition of towers and small cells to the network. . . . This requires carriers to add 3 to 10 times the number of existing sites to their networks. Most of this additional infrastructure will likely be built with small cells that use lampposts, utility phones, or other structures of similar size able to host smaller, less obtrusive radios required to build a densified network.” (citation omitted)); see also Deloitte LLP, 5G: The Chance to Lead for a Decade (2018) (Deloitte 5G Paper), available at https://www2.deloitte.com/content/dam/Deloitte/us/Documents/technology-media-telecommunications/us-tmt-5gdeployment-imperative.pdf

e lampposts, utility phones, or other structures of similar size able to host smaller, less obtrusive radios required to build a densified network.” (citation omitted)); see also Deloitte LLP, 5G: The Chance to Lead for a Decade (2018) (Deloitte 5G Paper), available at https://www2.deloitte.com/content/dam/Deloitte/us/Documents/technology-media-telecommunications/us-tmt-5gdeployment-imperative.pdf.

It is precisely “[b]ecause providers will need to deploy large numbers of wireless cell sites to meet the country’s wireless broadband needs and implement next-generation technologies” that the Commission has acknowledged “an urgent need to remove any unnecessary barriers to such deployment, whether caused by Federal law, Commission processes, local and State reviews, or otherwise.” See Wireless Infrastructure NPRM/NOI, 32 FCC Rcd at 3331, para. 2.

As explained below, the need to site so many more 5G-capable nodes leaves providers’ deployment plans and the underlying economics of those plans vulnerable to increased per site delays and costs.

25. Some states and local governments have acted to facilitate the deployment of 5G and other next-gen infrastructure, looking to bring greater connectivity to their communities through forward-looking policies.  Leaders in these states are working hard to meet the needs of their communities and balance often competing interests.  At the same time, outlier conduct persists.  The record here suggests that the legal requirements in place in other state and local jurisdictions are materially impeding that deployment in various ways. See, e.g., Letter from Henry Hultquist, AT&T, to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79, at 1 (filed Aug. 10, 2018) (“Unfortunately, many municipalities are unable, unwilling, or do not make it a priority to act on applications within the shot clock period.” ); Letter from Keith Buell, Sprint, to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79, at 1-2 (filed Aug. 13, 2018) (Sprint Aug

Letter from Henry Hultquist, AT&T, to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79, at 1 (filed Aug. 10, 2018) (“Unfortunately, many municipalities are unable, unwilling, or do not make it a priority to act on applications within the shot clock period.” ); Letter from Keith Buell, Sprint, to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79, at 1-2 (filed Aug. 13, 2018) (Sprint Aug. 13, 2018 Ex Parte Letter); Letter from Katherine R. Saunders, Verizon, to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79, at 2 (filed June 21, 2018) (“[L]ocal permitting delays continue to stymie deployments.”); Letter from Kenneth J. Simon, Crown Castle, to Marlene H. Dortch, FCC, WT Docket No. 17-79 (filed Aug. 10, 2018); Letter from Scott K. Bergmann, Senior Vice President, Regulatory Affairs, CTIA, to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79, at 1 (filed Aug. 30, 2018) (CTIA Aug. 30, 2018 Ex Parte Letter).

Crown Castle, for example, describes “excessive and unreasonable” “fees to access the [rights-of-way] that are completely unrelated to their maintenance or management.” It also points to barriers to market entry “for independent network and telecommunications service providers,” including municipalities that “restric[t] access to the [right-of-way] only to providers of commercial mobile services” or that impose “onerous zoning requirements on small cell installations when other similar [right of way] utility installations are erected with simple building permits.” Crown Castle Comments at 7; see also Letter from Kenneth J. Simon, Senior Vice President and General Counsel, Crown Castle International Corp., to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79 at 1-2 (filed Sept. 19, 2018) (“In Hillsborough, California, Crown Castle submitted applications covering 16 nodes, and was assessed $60,000 in application fees

rected with simple building permits.” Crown Castle Comments at 7; see also Letter from Kenneth J. Simon, Senior Vice President and General Counsel, Crown Castle International Corp., to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79 at 1-2 (filed Sept. 19, 2018) (“In Hillsborough, California, Crown Castle submitted applications covering 16 nodes, and was assessed $60,000 in application fees. Not only did Hillsborough go on to deny these applications, following that denial it also then sent Crown Castle an invoice for an additional $351,773 (attached as Exhibit A), most of which appears to be related to outside counsel fees—all for equipment that was not approved and has not yet been constructed.”).

Crown Castle is not alone in describing local regulations that slow deployment. AT&T states that localities in Maryland, California, and Massachusetts have imposed fees so high that it has had to pause or decrease deployments. Letter from Henry Hultquist, Vice President, Federal Regulatory, AT&T, to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79 at 2 (filed Aug. 6, 2018) (AT&T Aug. 6, 2018 Ex Parte Letter).

Likewise, AT&T states that a Texas city has refused to allow small cell placement on any structures in a right-of-way (ROW). AT&T Comments at 6-7.

T-Mobile states that the Town of Hempstead, New York requires service providers who seek to collocate or upgrade equipment on existing towers that have been properly constructed pursuant to Class II standards to upgrade and certify these facilities under Class III standards that apply to civil and national defense and military facilities. T-Mobile Reply Comments at 7-9; see also CCA Reply Comments at 12; CTIA Reply Comments at 18; WIA Reply Comments at 22-23.

Verizon states that a Minnesota town has proposed barring construction of new poles in rights-of-way and that a Midwestern suburb where it has been trying to get approval for small cells since 2014 has no established procedures for small cell approvals. See Verizon Comments at 7

ile Reply Comments at 7-9; see also CCA Reply Comments at 12; CTIA Reply Comments at 18; WIA Reply Comments at 22-23.

Verizon states that a Minnesota town has proposed barring construction of new poles in rights-of-way and that a Midwestern suburb where it has been trying to get approval for small cells since 2014 has no established procedures for small cell approvals. See Verizon Comments at 7.

Verizon states that localities in New York and Washington have required special use permits involving multiple layers of approval to locate small cells in some or all zoning districts. See Verizon Comments at 35.

While some localities dispute some of these characterizations, their submissions do not persuade us that there is no basis or need for the actions we take here.

26. Further, the record in this proceeding demonstrates that many local siting authorities are not complying with our existing Section 332 shot clock rules. See, e.g., T-Mobile Comments at 8 (stating that “roughly 30% of all of its recently proposed sites (including small cells) involve cases where the locality failed to act in violation of the shot clocks.”). According to WIA, one of its members “reports that 70% of its applications to deploy Small Wireless Facilities in the public ROWs during a two-year period exceeded the 90-day shot clock for installation of Small Wireless Facilities on an existing utility pole, and 47% exceeded the 150-day shot clock for the construction of new towers.” WIA Comments at 7. A New Jersey locality took almost five years to deny a Sprint application. See Sprint Spectrum L.P. v. Zoning Bd. of Adjustment of the Borough of Paramus, N.J., 21 F. Supp. 3d 381, 383, 387 (D.N.J. 2014), aff’d, 606 Fed. Appx. 669 (3d Cir. 2015). Another locality took almost three years to deny a Crown Castle application to install a DAS system. See Crown Castle NG East, Inc. v. Town of Greenburgh, 2013 WL 3357169, *6-8 (S.D.N.Y. 2013), aff’d, 552 Fed. Appx. 47 (2d Cir. 2014)

int Spectrum L.P. v. Zoning Bd. of Adjustment of the Borough of Paramus, N.J., 21 F. Supp. 3d 381, 383, 387 (D.N.J. 2014), aff’d, 606 Fed. Appx. 669 (3d Cir. 2015). Another locality took almost three years to deny a Crown Castle application to install a DAS system. See Crown Castle NG East, Inc. v. Town of Greenburgh, 2013 WL 3357169, *6-8 (S.D.N.Y. 2013), aff’d, 552 Fed. Appx. 47 (2d Cir. 2014).

WIA states that its members routinely face lengthy delays and specifically cite localities in New Jersey, New Hampshire, and Maine as being problematic. WIA Comments at 8. WIA states that one of its “member reports that the wireless siting approval process exceeds 90 days in more than 33% of jurisdictions it surveyed and exceeds 150 days in 25% of surveyed jurisdictions.” WIA Comments at 8. In some cases, WIA members have experienced delays ranging from one to three years in multiple jurisdictions—significantly longer than the 90- and 150-day time frames that the Commission established in 2009.

Similarly, AT&T identified an instance in which it took a locality in California 800 days to process an application. See WIA Comments at 9 (citing and discussing AT&T’s Comments in the 2016 Streamlining Public Notice, WT Docket No. 16-421).

GCI provides an example in which it took an Alaska locality nine months to decide an application. GCI Comments at 5-6.

T-Mobile states that a community in Colorado and one in California have lengthy pre-application processes for all small cell installations that include notification to all nearby households, a public meeting, and the preparation of a report, none of which these jurisdictions view as triggering a shot clock. T-Mobile Comments at 21.

Similarly, Lightower provides examples of long delays in processing siting applications. Lightower submits that average processing timeframes have increased from 300 days in 2016 to approximately 570 days in 2017, much longer than the Commission’s shot clocks

ic meeting, and the preparation of a report, none of which these jurisdictions view as triggering a shot clock. T-Mobile Comments at 21.

Similarly, Lightower provides examples of long delays in processing siting applications. Lightower submits that average processing timeframes have increased from 300 days in 2016 to approximately 570 days in 2017, much longer than the Commission’s shot clocks. Lightower states that “forty-six separate jurisdictions in the last two years had taken longer than 150 days to consider applications, with twelve of those jurisdictions—representing 101 small wireless facilities—taking more than a year.” Lightower Comments at 5-6. See also WIA Comments at 9 (citing and discussing Lightower’s Comments in the 2016 Streamlining Public Notice, WT Docket No. 16-421).

Finally, Crown Castle describes a case in which a “town took approximately two years and nearly twenty meetings, with constantly shifting demands, before it would even ‘deem complete’ Crown Castle’s application.” WIA Comments at 8 (citing and discussing Crown Castle’s Comments in 2016 Streamlining Public Notice, WT Docket No. 16-421).

27. Our Declaratory Ruling and Third Report and Order are intended to address these issues and outlier conduct. Our conclusions are also informed by findings, reports, and recommendations from the FCC Broadband Deployment Advisory Committee (BDAC), including the Model Code for Municipalities, the Removal of State and Local Regulatory Barriers Working Group report, and the Rates and Fees Ad Hoc Working Group report, which the Commission created in 2017 to identify barriers to deployment of broadband infrastructure, many of which are addressed here

dings, reports, and recommendations from the FCC Broadband Deployment Advisory Committee (BDAC), including the Model Code for Municipalities, the Removal of State and Local Regulatory Barriers Working Group report, and the Rates and Fees Ad Hoc Working Group report, which the Commission created in 2017 to identify barriers to deployment of broadband infrastructure, many of which are addressed here. BDAC Report of the Removal of State and Local Regulatory Barriers Working Group, https://www.fcc.gov/sites/default/files/bdac-regulatorybarriers-01232018.pdf (approved by the BDAC on January 23, 2018) (BDAC Regulatory Barriers Report); Draft Final Report of the Ad Hoc Committee on Rates and Fees to the BDAC, https://www.fcc.gov/sites/default/files/bdac-07-2627-2018-rates-fees-wg-report-07242018.pdf (July 26, 2018) (Draft BDAC Rates and Fees Report); BDAC Model Municipal Code (Harmonized), https://www.fcc.gov/sites/default/files/bdac-07-2627-2018-harmonization-wg-model-code-muni.pdf (approved July 26, 2018) (BDAC Model Municipal Code). The Draft Final Report of the Ad Hoc Committee on Rates and Fees to the BDAC was presented to the BDAC on July 26, 2018 but has not been voted by the BDAC as of the adoption of this Declaratory Ruling. Certain members of the Removal of State and Local Barriers Working Group also submitted a minority report disagreeing with certain findings in the BDAC Regulatory Barriers Report. See Minority Report Submitted by McAllen, TX, San Jose, CA, and New York, NY, GN Docket No. 17-83 (Jan 23, 2018); Letter from Kevin Pagan, City Attorney of McAllen to Marlene Dortch, Secretary, FCC (filed September 14, 2018).

We also considered input from numerous state and local officials about their concerns, and how they have approached wireless deployment, much of which we took into account here. Our action is also consistent with congressional efforts to hasten deployment, including bi-partisan legislation pending in Congress like the STREAMLINE Small Cell Deployment Act and SPEED Act

iled September 14, 2018).

We also considered input from numerous state and local officials about their concerns, and how they have approached wireless deployment, much of which we took into account here. Our action is also consistent with congressional efforts to hasten deployment, including bi-partisan legislation pending in Congress like the STREAMLINE Small Cell Deployment Act and SPEED Act. The STREAMLINE Small Cell Deployment Act proposes to streamline wireless infrastructure deployments by requiring siting agencies to act on deployment requests within specified time frames and by limiting the imposition of onerous conditions and fees. See, e.g., STREAMLINE Small Cell Deployment Act, S.3157, 115th Congress (2017-2018).

The SPEED Act would similarly streamline federal permitting processes. See, e.g., Streamlining Permitting to Enable Efficient Deployment of Broadband Infrastructure Act of 2017 (SPEED Act), S. 1988, 115th Cong. (2017).

In the same vein, the Model Code for Municipalities adopts streamlined infrastructure siting requirements while other BDAC reports and recommendations emphasize the negative impact of high fees on infrastructure deployments. See BDAC Model Municipal Code; Draft BDAC Rates and Fees Report; BDAC Regulatory Barriers Report.

28. As do members of both parties of Congress and experts on the BDAC, we recognize the urgent need to streamline regulatory requirements to accelerate the deployment of wireless infrastructure for current needs and for the next generation of wireless service in 5G. See, e.g., Letter from Patricia Paoletta, Counsel to Deloitte Consulting LLP, to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79 at 1 (filed Sept. 20, 2018) (“Deloitte noted that, as with many technology standard evolutions, the value of being a first-mover in 5G will be significant. Being first to LTE afforded the United States macroeconomic benefits, as it became a test bed for innovative mobile, social, and streaming applications

ounsel to Deloitte Consulting LLP, to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79 at 1 (filed Sept. 20, 2018) (“Deloitte noted that, as with many technology standard evolutions, the value of being a first-mover in 5G will be significant. Being first to LTE afforded the United States macroeconomic benefits, as it became a test bed for innovative mobile, social, and streaming applications. Being first to 5G can have even greater and more sustained benefits to our national economy given the network effects associated with adding billions of devices to the 5G network, enabling machine-to-machine interactions that generates data for further utilization by vertical industries”).

State government officials also have urged us to act to expedite the deployment of 5G technology, in particular, by streamlining overly burdensome regulatory processes to ensure that 5G technology will expand beyond just urban centers. These officials have expressed their belief that reducing high regulatory costs and delays in urban areas would leave more money and encourage development in rural areas. Letter from Montana State Senator Duane Ankney to Marlene H. Dortch, Secretary, FCC, WT Docket 17-79, at 1 (filed July 31, 2018) (Duane Ankney July 31, 2018 Ex Parte Letter); Letter from Fred A. Lamphere, Butte County Sheriff, to the Hon. Brendan Carr, Commissioner, FCC, WT Docket No. 17-79 at 1 (filed Sept. 11, 2018) (Fred A. Lamphere Sept. 11, 2018 Ex Parte Letter); Letter from Todd Nash, Susan Roberts, Paul Catstilleja, Wallowa County Board of Commissioners, to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79 at 2 (filed Aug. 20, 2018); Letter from Lonnie Gilbert, First Responder, National Black Growers Council Member, to the Hon. Brendan Carr, Commissioner, FCC, WT Docket No. 17-79 at 1 (filed Sept. 12, 2018); Letter from Jason R. Saine, North Caroline House of Representatives, to the Hon. Brendan Carr, Commissioner, FCC, WT Docket No. 17-79, at 1(filed Sept. 14, 2018) (Jason R. Saine Sept

t No. 17-79 at 2 (filed Aug. 20, 2018); Letter from Lonnie Gilbert, First Responder, National Black Growers Council Member, to the Hon. Brendan Carr, Commissioner, FCC, WT Docket No. 17-79 at 1 (filed Sept. 12, 2018); Letter from Jason R. Saine, North Caroline House of Representatives, to the Hon. Brendan Carr, Commissioner, FCC, WT Docket No. 17-79, at 1(filed Sept. 14, 2018) (Jason R. Saine Sept. 14, 2018 Ex Parte Letter) (minimal regulatory standard across the United States is critical to ensure that the United States wins the race to the 5G economy).

“[G]etting [5G] infrastructure out in a timely manner can be a challenge that involves considerable time and financial resources. The solution is to streamline relevant policies—allowing more modern rules for modern infrastructure.” Letter from LaWana Mayfield, City Council Member, Charlotte, NC, to Marlene H. Dortch, Secretary, FCC, WT Docket 17-79, at 1 (filed July 31, 2018) (LaWana Mayfield July 31, 2018 Ex Parte Letter); see also Letter from South Carolina State Representative Terry Alexander to Marlene H. Dortch, Secretary, FCC, WT Docket 17-79, at 1 (filed August 7, 2018) (“[P]olicymakers at all levels of government must streamline complex siting stipulations that will otherwise slow down 5G buildout for small cells in particular.”); Letter from Sal Pace, Pueblo County Commissioner, District 3, CO, to Marlene H. Dortch, Secretary, FCC, WT Docket 17-79, at 1 (filed July 30, 2018) (Sal Pace July 30, 2018 Ex Parte Letter) (“[T]he FCC should ensure that localities are fully compensated for their costs . . . Such fees should be reasonable and non-discriminatory, and should ensure that localities are made whole. Lastly, the FCC should set reasonable and enforceable deadlines for localities to act on wireless permit applications. . .

WT Docket 17-79, at 1 (filed July 30, 2018) (Sal Pace July 30, 2018 Ex Parte Letter) (“[T]he FCC should ensure that localities are fully compensated for their costs . . . Such fees should be reasonable and non-discriminatory, and should ensure that localities are made whole. Lastly, the FCC should set reasonable and enforceable deadlines for localities to act on wireless permit applications. . . . The distinction between siting large macro-towers and small cells should be reflected in any rulemaking.”)

State officials have acknowledged that current regulations are “outdated” and “could hinder the timely arrival of 5G throughout the country,” and urged the FCC “to push for more reforms that will streamline infrastructure rules from coast to coast.” Letter from Dr. Carolyn A. Prince, Chairwoman, Marlboro County Council, SC, to Marlene H. Dortch, Secretary, FCC, WT Docket 17-79, at 1 (filed July 31, 2018) (Dr. Carolyn Prince July 31, 2018 Ex Parte Letter)

Although many states and localities support our efforts, we acknowledge that there are others who advocated for different approaches, arguing, among other points, that the FCC lacks authority to take certain actions. See, e.g., City of Manhattan, KS Sept. 13, 2018 Ex Parte Letter at 1-2; Ronny Berdugo Sept. 18, 2018 Ex Parte Letter at 1-2; Damon Connolly Sept. 17, 2018 Ex Parte Letter at 1-2.

We have carefully considered these views, but nevertheless find our actions here necessary and fully supported.

29. Accordingly, in this Declaratory Ruling and Third Report and Order, we act to reduce regulatory barriers to the deployment of wireless infrastructure and to ensure that our nation remains the leader in advanced wireless services and wireless technology.

III. DECLARATORY RULING

30. In this Declaratory Ruling, we note that a number of appellate courts have articulated different and often conflicting views regarding the scope and nature of the limits Congress imposed on state and local governments through Sections 253 and 332

less infrastructure and to ensure that our nation remains the leader in advanced wireless services and wireless technology.

III. DECLARATORY RULING

30. In this Declaratory Ruling, we note that a number of appellate courts have articulated different and often conflicting views regarding the scope and nature of the limits Congress imposed on state and local governments through Sections 253 and 332. In light of these diverging views, Congress’s vision for a consistent, national policy framework, and the need to ensure that our approach continues to make sense in light of the relatively new trend towards the large-scale deployment of Small Wireless Facilities, we take this opportunity to clarify and update the FCC’s reading of the limits Congress imposed. We do so in three main respects.

31. First, in Part III.A, we express our agreement with the views already stated by the First, Second, and Tenth Circuits that the “materially inhibit” standard articulated in 1997 by the Clinton-era FCC’s California Payphone decision is the appropriate standard for determining whether a state or local law operates as a prohibition or effective prohibition within the meaning of Sections 253 and 332.

32. Second, in Part III.B, we note, as numerous courts have recognized, that state and local fees and other charges associated with the deployment of wireless infrastructure can effectively prohibit the provision of service. At the same time, courts have articulated various approaches to determining the types of fees that run afoul of Congress’s limits in Sections 253 and 332. We thus clarify the particular standard that governs the fees and charges that violate Sections 253 and 332 when it comes to the Small Wireless Facilities at issue in this decision. Namely, fees are only permitted to the extent that they represent a reasonable approximation of the local government’s objectively reasonable costs, and are non-discriminatory

ngress’s limits in Sections 253 and 332. We thus clarify the particular standard that governs the fees and charges that violate Sections 253 and 332 when it comes to the Small Wireless Facilities at issue in this decision. Namely, fees are only permitted to the extent that they represent a reasonable approximation of the local government’s objectively reasonable costs, and are non-discriminatory. Fees charged by states or localities in connection with Small Wireless Facilities would be “compensation” for purposes of Section 253(c). This Declaratory Ruling interprets Section 253 and 332(c)(7) in the context of three categories of fees, one of which applies to all deployments of Small Wireless Facilities while the other two are specific to Small Wireless Facilities deployments inside the ROW. (1) “Event” or “one-time” fees are charges that providers pay on a non-recurring basis in connection with a one-time event, or series of events occurring within a finite period. The one-time fees addressed in this Declaratory Ruling are not specific to the ROW. For example, a provider may be required to pay fees during the application process to cover the costs related to processing an application building or construction permits, street closures, or a permitting fee, whether or not the deployment is in the ROW. (2) Recurring charges for a Small Wireless Facility’s use of or attachment to property inside the ROW owned or controlled by a state or local government, such as a light pole or traffic light, is the second category of fees addressed here, and is typically paid on a per structure/per year basis. (3) Finally, ROW access fees are recurring charges that are assessed, in some instances, to compensate a state or locality for a Small Wireless Facility’s access to the ROW, which includes the area on, below, or above a public roadway, highway, street, sidewalk, alley, utility easement, or similar property (including when such property is government-owned)

y paid on a per structure/per year basis. (3) Finally, ROW access fees are recurring charges that are assessed, in some instances, to compensate a state or locality for a Small Wireless Facility’s access to the ROW, which includes the area on, below, or above a public roadway, highway, street, sidewalk, alley, utility easement, or similar property (including when such property is government-owned). A ROW access fee may be charged even if the Small Wireless Facility is not using government owned property within the ROW. AT&T Comments at 18 (describing three categories of fees); Letter from Tamara Preiss, Vice President, Federal Regulatory and Legal Affairs, Verizon, to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79, Attach. at 11 (filed Aug. 10, 2018) (Verizon Aug. 10, 2018 Ex Parte Letter) (characterizing fees as recurring or non-recurring); see also Draft BDAC Rates and Fees Report at p. 15-16. Unless otherwise specified, a reference to “fee” or “fees” herein refers to any one of, or any combination of, these three categories of charges.

In this section, we also identify specific fee levels for the deployment of Small Wireless Facilities that presumptively comply with this standard. We do so to help avoid unnecessary litigation, while recognizing that it is the standard itself, not the particular, presumptive fee levels we articulate, that ultimately will govern whether a particular fee is allowed under Sections 253 and 332. So fees above those levels would be permissible under Sections 253 and 332 to the extent a locality’s actual, reasonable costs (as measured by the standard above) are higher.

33. Finally, in Part III.C, we focus on a subset of other, non-fee provisions of state and local law that could also operate as prohibitions on service. We do so in particular by addressing state and local consideration of aesthetic concerns in the deployment of Small Wireless Facilities

nd 332 to the extent a locality’s actual, reasonable costs (as measured by the standard above) are higher.

33. Finally, in Part III.C, we focus on a subset of other, non-fee provisions of state and local law that could also operate as prohibitions on service. We do so in particular by addressing state and local consideration of aesthetic concerns in the deployment of Small Wireless Facilities. We note that the Small Wireless Facilities that are the subject of this Declaratory Ruling remain subject to the Commission’s rules governing Radio Frequency (RF) emissions exposure. See 47 CFR §§ 1.1307, 1.1310.  We disagree with commenters who oppose the Declaratory Ruling on the basis of concerns regarding RF emissions. See, e.g., Comments from Judy Aizuss, Comments from Jeffrey Arndt, Comments from Jeanice Barcelo, Comments from Kristin Beatty, Comments from James M. Benster, Comments from Terrie Burns, Comments from EMF Safety Network, Comments from Kate Reese Hurd, Comments from Marilynne Martin, Comments from Lisa Mayock, Comments from Kristen Moriarty Termunde, Comments from Sage Associates, Comments from Elizabeth Shapiro, Comments from Paul Silver, Comments from Natalie Ventrice. The Commission has authority to adopt and enforce RF exposure limits, and nothing in this Declaratory Ruling changes the applicability of the Commission’s existing RF emissions exposure rules.  See, e.g., Section 704(b) of the Telecommunications Act of 1996, Pub. L. No. 104-104 (directing Commission to “prescribe and make effective rules regarding the environmental effects of radio frequency emissions” upon completing action in then-pending rulemaking proceeding that included proposals for, inter alia, maximum exposure limits); 47 U.S.C

Commission’s existing RF emissions exposure rules.  See, e.g., Section 704(b) of the Telecommunications Act of 1996, Pub. L. No. 104-104 (directing Commission to “prescribe and make effective rules regarding the environmental effects of radio frequency emissions” upon completing action in then-pending rulemaking proceeding that included proposals for, inter alia, maximum exposure limits); 47 U.S.C. § 332(c)(7)(B)(iv) (recognizing legitimacy of FCC’s existing regulations on environmental effects of RF emissions of personal wireless service facilities, by proscribing state and local regulation of such facilities on the basis of such effects, to the extent such facilities comply with Commission regulations concerning such RF emissions); 47 U.S.C. § 151 (creating the FCC “[f]or the purpose of regulating interstate and foreign commerce in communication by wire and radio so as to make available, so far as possible, to all the people of the United States, . . . a rapid, efficient, Nation-wide, and world-wide wire and radio communication service, . . . for the purpose of [inter alia] promoting safety of life and property through the use of wire and radio communications”).  See also H.R. Rep. No. 204(I), 104th Cong., 1st Sess. 94 (1995), reprinted in 1996 U.S.C.C.A.N. 10, 61 (1996) (in legislative history of Section 704 of 1996 Telecommunications Act, identifying “adequate safeguards of the public health and safety” as part of a framework of uniform, nationwide RF regulations); ; Reassessment of FCC Radiofrequency Exposure Limits and Policies, First Report and Order, Further Notice of Proposed Rulemaking and Notice of Inquiry, 28 FCC Rcd 3498, 3530-31, para. 103, n.176 (2013).

A. Overview of the Section 253 and Section 332(c)(7) Framework Relevant to Small Wireless Facilities Deployment

34. In Sections 253(a) and 332(c)(7)(B) of the Act, Congress determined that state or local requirements that prohibit or have the effect of prohibiting the provision of service are unlawful and thus preempted. 47 U.S.C

e of Inquiry, 28 FCC Rcd 3498, 3530-31, para. 103, n.176 (2013).

A. Overview of the Section 253 and Section 332(c)(7) Framework Relevant to Small Wireless Facilities Deployment

34. In Sections 253(a) and 332(c)(7)(B) of the Act, Congress determined that state or local requirements that prohibit or have the effect of prohibiting the provision of service are unlawful and thus preempted. 47 U.S.C. §§ 253(a), 332(c)(7)(B)(i)(II).

Section 253(a) addresses “any interstate or intrastate telecommunications service,” while Section 332(c)(7)(B)(i)(II) addresses “personal wireless services.” Id. The actions in this proceeding update the FCC’s approach to Sections 253 and 332 by addressing effective prohibitions that apply to the deployment of services covered by those provisions. Our interpretations in this proceeding do not provide any basis for increasing the regulation of services deployed consistent with Section 621 of the Cable Communications Policy Act of 1984.

Although the provisions contain identical “effect of prohibiting” language, the Commission and different courts over the years have each employed inconsistent approaches to deciding what it means for a state or local legal requirement to have the “effect of prohibiting” services under these two sections of the Act. This has caused confusion among both providers and local governments about what legal requirements are permitted under Sections 253 and 332(c)(7). For example, despite Commission decisions to the contrary construing such language under Section 253, some courts have held that a denial of a wireless siting application will “prohibit or have the effect of prohibiting” the provision of a personal wireless service under Section 332(c)(7)(B)(i)(II) only if the provider can establish that it has a significant gap in service coverage in the area and a lack of feasible alternative locations for siting facilities. Courts vary widely regarding the type of showing needed to satisfy the second part of that standard

cation will “prohibit or have the effect of prohibiting” the provision of a personal wireless service under Section 332(c)(7)(B)(i)(II) only if the provider can establish that it has a significant gap in service coverage in the area and a lack of feasible alternative locations for siting facilities. Courts vary widely regarding the type of showing needed to satisfy the second part of that standard. The First, Fourth, and Seventh Circuits have imposed a “heavy burden” of proof on applicants to establish a lack of alternative feasible sites, requiring them to show “not just that this application has been rejected but that further reasonable efforts to find another solution are so likely to be fruitless that it is a waste of time even to try.” Green Mountain Realty Corp. v. Leonard, 750 F.3d 30, 40 (1st Cir. 2014); accord New Cingular Wireless PCS, LLC v. Fairfax County, 674 F.3d 270, 277 (4th Cir. 2012); T-Mobile Northeast LLC v. Fairfax County, 672 F.3d 259, 266-68 (4th Cir. 2012) (en banc); Helcher v. Dearborn County, 595 F.3d 710, 723 (7th Cir. 2010) (Helcher). The Second, Third, and Ninth Circuits have held that an applicant must show only that its proposed facilities are the “least intrusive means” for filling a coverage gap in light of the aesthetic or other values that the local authority seeks to serve. Sprint Spectrum, LP v. Willoth, 176 F.3d 630, 643 (2d Cir. 1999) (Willoth); APT Pittsburgh Ltd. P’ship v. Penn Township, 196 F.3d 469, 480 (3d Cir. 1999) (APT); American Tower Corp. v. City of San Diego, 763 F.3d 1035, 1056-57 (9th Cir. 2014); T-Mobile USA, Inc. v. City of Anacortes, 572 F.3d 987, 995-99 (9th Cir. 2009) (City of Anacortes).

Other courts have held that evidence of an already-occurring or complete inability to offer a telecommunications service is required to demonstrate an effective prohibition under Section 253(a). See, e.g., County of San Diego, 543 F.3d at 579-80; Level 3 Commc’ns, LLC v. City of St. Louis, 477 F.3d 528, 533-34 (8th Cir. 2007) (City of St. Louis)

987, 995-99 (9th Cir. 2009) (City of Anacortes).

Other courts have held that evidence of an already-occurring or complete inability to offer a telecommunications service is required to demonstrate an effective prohibition under Section 253(a). See, e.g., County of San Diego, 543 F.3d at 579-80; Level 3 Commc’ns, LLC v. City of St. Louis, 477 F.3d 528, 533-34 (8th Cir. 2007) (City of St. Louis).

Conversely, still other courts like the First, Second, and Tenth Circuits have endorsed prior Commission interpretations of what constitutes an effective prohibition under Section 253(a) and recognized that, under that analytical framework, a legal requirement can constitute an effective prohibition of services even if it is not an insurmountable barrier. See Puerto Rico Tel. Co. v. Municipality of Guayanilla, 450 F.3d 9, 18 (1st Cir. 2006) (Municipality of Guayanilla); TCG New York, Inc. v. City of White Plains, 305 F.3d 67, 76 (2d Cir. 2002) (City of White Plains); RT Communications v. FCC, 201 F.3d 1264, 1268 (10th Cir. 2000) (“[Section] 253(a) forbids any statute which prohibits or has ‘the effect of prohibiting’ entry. Nowhere does the statute require that a bar to entry be insurmountable before the FCC must preempt it.”) (RT Communications) (affirming Silver Star Tel. Co. Petition for Preemption and Declaratory Ruling, 12 FCC Rcd 15639 (1997)).

35. In this Declaratory Ruling, we first reaffirm, as our definitive interpretation of the effective prohibition standard, the test we set forth in California Payphone, namely, that a state or local legal requirement constitutes an effective prohibition if it “materially limits or inhibits the ability of any competitor or potential competitor to compete in a fair and balanced legal and regulatory environment.” California Payphone, 12 FCC Rcd at 14206, para. 31. A number of circuit courts have cited California Payphone as the leading authority regarding the standard to be applied under Section 253(a). See, e.g., County of San Diego, 543 F.3d at 578; City of St

ly limits or inhibits the ability of any competitor or potential competitor to compete in a fair and balanced legal and regulatory environment.” California Payphone, 12 FCC Rcd at 14206, para. 31. A number of circuit courts have cited California Payphone as the leading authority regarding the standard to be applied under Section 253(a). See, e.g., County of San Diego, 543 F.3d at 578; City of St. Louis, 477 F.3d at 533; Municipality of Guayanilla, 450 F.3d at 18; Qwest Corp. v. City of Santa Fe, 380 F.3d 1258, 1270 (10th Cir. 2004) (City of Santa Fe); City of White Plains, 305 F.3d at 76. Crown Castle argues that the Eighth and Ninth Circuit cited the FCC’s California Payphone decision,but read the standard in an overly narrow fashion. See, e.g., Letter from Kenneth J. Simon, Senior Vice Pres. and Gen. Counsel, Crown Castle, et al., to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79 at 12 (filed June 7, 2018) (Crown Castle June 7, 2018 Ex Parte Letter); see also Smart Communities Comments at 60-61 (describing circuit split). Some commenters cite selected dictionary definitions or otherwise argue for a narrow definition of “prohibit.” See, e.g., Smart Communities Reply at 53. But because they do not go on to dispute the validity of the California Payphone standard that has been employed not only by the Commission but also many courts, those arguments do not persuade us to depart from the California Payphone standard here.

We then explain how this “material inhibition” standard applies in the context of state and local fees and aesthetic requirements. In doing so, we confirm the First, Second, and Tenth Circuits’ understanding that under this analytical framework, a legal requirement can “materially inhibit” the provision of services even if it is not an insurmountable barrier. See, e.g., City of White Plains, 305 F.3d at 76; Municipality of Guayanilla, 450 F.3d at 18; see also, e.g., Crown Castle June 7, 2018 Ex Parte Letter at 12

quirements. In doing so, we confirm the First, Second, and Tenth Circuits’ understanding that under this analytical framework, a legal requirement can “materially inhibit” the provision of services even if it is not an insurmountable barrier. See, e.g., City of White Plains, 305 F.3d at 76; Municipality of Guayanilla, 450 F.3d at 18; see also, e.g., Crown Castle June 7, 2018 Ex Parte Letter at 12. Because the clarifications in this order should reduce uncertainty regarding the application of these provisions for state and local governments as well as stakeholders, we are not persuaded by some commenters’ arguments that an expedited complaint process is required. See, e.g., AT&T Comments at 28; CTIA Reply at 21. We do not address, at this time, recently-filed petitions for reconsideration of our August 2018 Moratoria Declaratory Ruling. See, e.g., Smart Communities Petition for Reconsideration, WC Docket No. 17-84 & WT Docket No. 17-79 (filed Sept. 4, 2018); New York City Petition for Reconsideration, WC Docket No. 17-84 & WT Docket No. 17-79 (filed Sept. 4, 2018). Nor do we address requests for clarification and/or action on other issues raised in the record beyond those expressly discussed in this order. These other issues include arguments regarding other statutory interpretations that we do not address here. See, e.g., CTIA Reply at 23 (raising broader questions about the precise interplay of Section 253 and Section 332(c)(7)); Crown Castle June 7, 2018 Ex Parte Letter at 16-17 (raising broader questions about the scope of “legal requirements” under Section 253(a)). Consequently, this order should not be read as impliedly taking a position on those issues.

We also resolve the conflicting court interpretations of the ‘effective prohibition’ language so that continuing confusion on the meaning of Sections 253 and 332(c)(7) does not materially inhibit the critical deployments of Small Wireless Facilities and our nation’s drive to deploy 5G

r Section 253(a)). Consequently, this order should not be read as impliedly taking a position on those issues.

We also resolve the conflicting court interpretations of the ‘effective prohibition’ language so that continuing confusion on the meaning of Sections 253 and 332(c)(7) does not materially inhibit the critical deployments of Small Wireless Facilities and our nation’s drive to deploy 5G. See, e.g., Crown Castle June 7, 2018 Ex Parte Letter at 11-12 (arguing that “[d]espite the Commission’s efforts to define the boundaries of federal preemption under Section 253, courts have issued a number of conflicting decisions that have only served to confuse the preemption analysis sunder section 253” and that “the Commission should clarify that the California Payphone standard as interpreted by the First and Second Circuits is the appropriate standard going forward”); see also BDAC Regulatory Barriers Report at p. 9 (“The Commission should provide clarity on what actually constitutes an “excessive” fee for right-of-way access and use. The FCC should provide guidance on what constitutes a fee that is excessive and/or duplicative, and that therefore is not “fair and reasonable.” The Commission should specifically clarify that “fair and reasonable” compensation for right-of way access and use implies some relation to the burden of new equipment placed in the ROW or on the local asset, or some other objective standard.”). Because our decision provides clarity by addressing conflicting court decisions and reaffirming that the “materially inhibits” standard articulated in the Commission’s California Payphone decision is the appropriate standard for determining whether a state or local law operates as an effective prohibition within the meaning of Sections 253 and 332, we reject arguments that our action will increase conflicts and lead to more litigation. See e.g., Letter from Michael Dylan Brennan, Mayor, City of University Heights, Ohio, to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79, at 2 (filed Sept

e appropriate standard for determining whether a state or local law operates as an effective prohibition within the meaning of Sections 253 and 332, we reject arguments that our action will increase conflicts and lead to more litigation. See e.g., Letter from Michael Dylan Brennan, Mayor, City of University Heights, Ohio, to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79, at 2 (filed Sept. 19, 2018) (stating that “…this framing and definition of effective prohibition opens local governments to the likelihood of more, not less, conflict and litigation over requirements for aesthetics, spacing, and undergrounding”).

36. As an initial matter, we note that our Declaratory Ruling applies with equal measure to the effective prohibition standard that appears in both Sections 253(a) and 332(c)(7). See infra Part III.A, B.

This ruling is consistent with the basic canon of statutory interpretation that identical words appearing in neighboring provisions of the same statute generally should be interpreted to have the same meaning. See County of San Diego, 543 F.3d at 579 (“We see nothing suggesting that Congress intended a different meaning of the text ‘prohibit or have the effect of prohibiting’ in the two statutory provisions, enacted at the same time, in the same statute. * * * * * As we now hold, the legal standard is the same under either [Section 253 or 332(c)(7)].”); see also, e.g., Puerto Rico v. Franklin Cal. Tax-Free Trust, 136 S. Ct. 1938, 1946 (citing Sullivan v. Stroop, 496 U.S. 478, 484 (1990) (reading same term used in different parts of the same Act to have the same meaning); Northcross v. Board of Ed. of Memphis City Schools, 412 U.S. 427, 428 (1973) (per curiam) (“[S]imilarity of language . . . is . . . a strong indication that the two statutes should be interpreted pari passu”); Verizon Comments at 9-10; AT&T Reply at 3-4; Crown Castle June 7, 2018 Ex Parte Letter at 15

484 (1990) (reading same term used in different parts of the same Act to have the same meaning); Northcross v. Board of Ed. of Memphis City Schools, 412 U.S. 427, 428 (1973) (per curiam) (“[S]imilarity of language . . . is . . . a strong indication that the two statutes should be interpreted pari passu”); Verizon Comments at 9-10; AT&T Reply at 3-4; Crown Castle June 7, 2018 Ex Parte Letter at 15.

Moreover, both of these provisions apply to wireless telecommunications services Common carrier wireless services meet the definition of “telecommunications services,” and thus are within the scope of Section 253(a) of the Act. See, e.g., Moratoria Declaratory Ruling, FCC 18-111, para 142 n.523; see also, e.g., League of Minnesota Cities Comments at 11; Verizon Reply at 9-10. While some commenters cite certain distinguishing factual characteristics between wireline and wireless services, the record does not reveal why those distinctions would be material to whether wireless telecommunications services are covered by Section 253 in the first instance. See, e.g., City of San Antonio et al. Comments, Exh. A at 13; Virginia Joint Commenters Comments at 5, Exh. A at 45-46. To the contrary, Section 253(e) expressly preserves “application of section 332(c)(3) of this title to commercial mobile service providers” notwithstanding Section 253—a provision that would be meaningless if wireless telecommunications services already fell outside the scope of Section 253. 47 U.S.C. § 253(e). For this same reason, we also reject claims that the existence of certain protections for personal wireless services in Section 332(c)(7), or the phrase “nothing in this chapter” in Section 332(c)(7)(A), demonstrate that states’ or localities’ regulations affecting wireless telecommunications services must fall outside the scope of Section 253. See, e.g., Virginia Joint Commenters Comments, Exh. A at iii, 45-46; Smart Communities Comments at 56

the existence of certain protections for personal wireless services in Section 332(c)(7), or the phrase “nothing in this chapter” in Section 332(c)(7)(A), demonstrate that states’ or localities’ regulations affecting wireless telecommunications services must fall outside the scope of Section 253. See, e.g., Virginia Joint Commenters Comments, Exh. A at iii, 45-46; Smart Communities Comments at 56. Even if, as some parties argue, the phrase “nothing in this chapter” could be construed as preserving state or local decisions on the placement, construction, or modification of personal wireless service facilities from preemption by other sections of the Communications Act, Section 332(c)(7)(A) goes on to make clear that such state or local decisions are not immune from preemption if they violate any of the standards set forth in Section 332(c)(7)(B)--including Section 332(c)(7)(B)(i)(II)’s ban of requirements that “prohibit or have the effect of prohibiting” the provision of service, which is identical to the preemption provision in Section 253(a). Thus, states and localities may charge fees and dispose of applications relating to the matters subject to Section 332(c)(7) in any manner they deem appropriate, so long as that conduct does not amount to a prohibition or effective prohibition, as interpreted in this Declaratory Ruling or otherwise run afoul of federal or state law; but because Sections 332(c)(7)(B)(i)(II) and 253(a) use identical ”effective prohibition” language, the standard for what is saved and what is preempted is the same under both provisions.

as well as to commingled services and facilities. See infra para. 40 (discussing use of small cells to close coverage gaps, including voice gaps); see also, e.g., Moratoria Declaratory Ruling, FCC 18-111, para 145 n.531; Restoring Internet Freedom, Declaratory Ruling, Report and Order, and Order, 33 FCC Rcd 311, 425, para. 190 (2018); Letter from Andre J. Lachance, Associate General Counsel, Verizon to Marlene H. Dortch, Secretary, FCC, WT Docket No

infra para. 40 (discussing use of small cells to close coverage gaps, including voice gaps); see also, e.g., Moratoria Declaratory Ruling, FCC 18-111, para 145 n.531; Restoring Internet Freedom, Declaratory Ruling, Report and Order, and Order, 33 FCC Rcd 311, 425, para. 190 (2018); Letter from Andre J. Lachance, Associate General Counsel, Verizon to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79 at 3 (filed Sept. 19, 2018) (confirming that “telecommunications services can be provided over small cells and Verizon has deployed Small Wireless Facilities in its network that provide telecommunications services.”); Letter from David M. Crawford, Senior Corporate Counsel, Fed. Reg. Affairs, T-Mobile, to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79 at 1 (filed Sept. 19, 2018) (stating that “small wireless facilities are a critical component of T-Mobile’s network deployment plans to support both the 5G evolution of wireless services, as well as more traditional services such as mobile broadband and even voice calls. T-Mobile, for example, uses small wireless facilities to densify our network to provide better coverage and greater capacity, and to provide traditional services such as voice calls in areas where our macro site coverage is insufficient to meet demand.”); Letter from Henry G. Hultquist, Vice President, Federal Regulatory, AT&T, to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79 at 1 (filed Sept. 20, 2018) (“AT&T has operated and continues to operate commercial mobile radio services as well as information services from small wireless facilities...”); see also, e.g., Coastal Communications Service v. City of New York, 658 F. Supp. 2d 425, 441-42 (E.D.N.Y. 2009) (finding that a restriction on advertising on newly-installed payphones was subject to Section 253(a) where the advertising was a material factor in the provider’s ability to provide the payphone service itself)

ervices as well as information services from small wireless facilities...”); see also, e.g., Coastal Communications Service v. City of New York, 658 F. Supp. 2d 425, 441-42 (E.D.N.Y. 2009) (finding that a restriction on advertising on newly-installed payphones was subject to Section 253(a) where the advertising was a material factor in the provider’s ability to provide the payphone service itself). The fact that facilities are sometimes deployed by third parties not themselves providing covered services also does not place such deployment beyond the purview of Section 253(a) or Section 332(c)(7)(B)(i) insofar as the facilities are used by wireless service providers on a wholesale basis to provide covered services (among other things). See, e.g., T-Mobile Comments at 26. Given our conclusion that neither commingling of services nor the identity of the entity engaged in the deployment activity changes the applicability of Section 253(a) or Section 332(c)(7)(B)(i)(II) where the facilities are being used for the provisioning of services within the scope of the relevant statutory provisions, we reject claims to the contrary. See, e.g., Colorado Communications and Utility Alliance et al. Comments at 15-16; City of San Antonio et al. Comments, Exh. A at 12; id., Exh. C at 13-15. Because local jurisdictions do not have the authority to regulate these interstate services, there is no basis for local jurisdictions to conduct proceedings on the types of personal wireless services offered over particular wireless service facilities or the licensee’s service area, which are matters within the Commission’s licensing authority. Furthermore, local jurisdictions do not have the authority to require that providers offer certain types or levels of service, or to dictate the design of a provider’s network. See 47 U.S.C. § 332(c)(3)(A); see also Bastien v. AT&T Wireless Servs., Inc., 205 F.3d 983, 989 (7th Cir. 2000).

37

ilities or the licensee’s service area, which are matters within the Commission’s licensing authority. Furthermore, local jurisdictions do not have the authority to require that providers offer certain types or levels of service, or to dictate the design of a provider’s network. See 47 U.S.C. § 332(c)(3)(A); see also Bastien v. AT&T Wireless Servs., Inc., 205 F.3d 983, 989 (7th Cir. 2000).

37. As explained in California Payphone and reaffirmed here, a state or local legal requirement will have the effect of prohibiting wireless telecommunications services if it materially inhibits the provision of such services. We clarify that an effective prohibition occurs where a state or local legal requirement materially inhibits a provider’s ability to engage in any of a variety of activities related to its provision of a covered service. By “covered service” we mean a telecommunications service or a personal wireless service for purposes of Section 253 and Section 332(c)(7), respectively.

This test is met not only when filling a coverage gap but also when densifying a wireless network, introducing new services or otherwise improving service capabilities. See, e.g., Crown Castle Comments at 54-55; Free State Foundation Comments at 12; T-Mobile Comments at 43-45; CTIA Reply at 14; WIA Reply at 26; Crown Castle June 7, 2018 Ex Parte Letter at 13-14; Letter from Kara Romagnino Graves, Director, Regulatory Affairs, CTIA, to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79, at 8-9 (filed June 27, 2018) (CTIA June 27, 2018 Ex Parte Letter). As T-Mobile explains, for example, a provider might need to improve “signal strength or system capacity to allow it to provide reliable service to consumers in residential and commercial buildings.” T-Mobile Comments at 43; see also, e.g., Acceleration of Broadband Deployment by Improving Wireless Facilities Siting Policies, WT Docket Nos. 13-238, et al., Notice of Proposed Rulemaking, 28 FCC Rcd 14238, 14253, para

s, for example, a provider might need to improve “signal strength or system capacity to allow it to provide reliable service to consumers in residential and commercial buildings.” T-Mobile Comments at 43; see also, e.g., Acceleration of Broadband Deployment by Improving Wireless Facilities Siting Policies, WT Docket Nos. 13-238, et al., Notice of Proposed Rulemaking, 28 FCC Rcd 14238, 14253, para. 38 (2013) (observing that “DAS and small cell facilities[ ] are critical to satisfying demand for ubiquitous mobile voice and broadband services”). The growing prevalence of smart phones has only accelerated the demand for wireless providers to take steps to improve their service offerings. See, e.g., Twentieth Wireless Competition Report, 32 FCC Rcd at 9011-13, paras. 62-65.

Under the California Payphone standard, a state or local legal requirement could materially inhibit service in numerous ways—not only by rendering a service provider unable to provide an existing service in a new geographic area or by restricting the entry of a new provider in providing service in a particular area, but also by materially inhibiting the introduction of new services or the improvement of existing services. Thus, an effective prohibition includes materially inhibiting additional services or improving existing services. Our conclusion finds further support in our broad understanding of the statutory term “service,” which, as we explained in our recent Moratoria Declaratory Ruling, means “any covered service a provider wishes to provide, incorporating the abilities and performance characteristics it wishes to employ, including to provide existing services more robustly, or at a higher level of quality—such as through filling a coverage gap, densification, or otherwise improving service capabilities.” Moratoria Declaratory Ruling, FCC 18-111, para

ratoria Declaratory Ruling, means “any covered service a provider wishes to provide, incorporating the abilities and performance characteristics it wishes to employ, including to provide existing services more robustly, or at a higher level of quality—such as through filling a coverage gap, densification, or otherwise improving service capabilities.” Moratoria Declaratory Ruling, FCC 18-111, para. 162 n.594; see also Public Utility Comm’n of Texas Petition for Declaratory Ruling and/or Preemption of Certain Provisions of the Texas Public Utility Regulatory Act of 1995, Memorandum Opinion and Order, 13 FCC Rcd 3460, 3496, para. 74 (1997) (Texas PUC Order) (interpreting the scope of ‘telecommunications services’ covered by Section 253(a) and clarifying that it would be an unlawful prohibition for a state or locality to specify “the means or facilities” through which a service provider must offer service); Crown Castle June 7, 2018 Ex Parte Letter at 10-11 (discussing this precedent). We find this interpretation of “service” warranted not only under Section 253(a), but Section 332(c)(7)(B)(i)(II)’s reference to “services” as well.

38. Our reading of Section 253(a) and Section 332(c)(7)(B)(i)(II) reflects and supports a marketplace in which services can be offered in a multitude of ways with varied capabilities and performance characteristics consistent with the policy goals in the 1996 Act and the Communications Act. To limit Sections 253(a) and 332(c)(7)(B)(i)(II) to protecting only against coverage gaps or the like would be to ignore Congress’s contemporaneously-expressed goals of “promot[ing] competition[,] . . . secur[ing] . . . higher quality services for American telecommunications consumers and encourage[ing] the rapid deployment of new telecommunications technologies.” Preamble to the Telecommunications Act of 1996, Pub. Law. No. 104-104, § 202, 110 Stat. 56 (1996)

nly against coverage gaps or the like would be to ignore Congress’s contemporaneously-expressed goals of “promot[ing] competition[,] . . . secur[ing] . . . higher quality services for American telecommunications consumers and encourage[ing] the rapid deployment of new telecommunications technologies.” Preamble to the Telecommunications Act of 1996, Pub. Law. No. 104-104, § 202, 110 Stat. 56 (1996). Consequently, we reject arguments suggesting that the provision of some level of wireless service in the past necessarily demonstrates that there is no effective prohibition of service under the state or local legal requirements that applied during those periods or that an effective prohibition only is present if a provider can provide no covered service whatsoever. See, e.g., City and County of San Francisco Comments at 25-26; Virginia Joint Commenters Comments, Exh. A at 31-33. Nor, in light of these goals, do we find it reasonable to interpret the protections of these provisions as doing nothing more than guarding against a monopoly as some suggest. See, e.g., Smart Communities Comments, WC Docket No. 17-84, at 8-9 (filed June 15, 2017) cited in Smart Communities Comments at 57 n.141.

In addition, as the Commission recently explained, the implementation of the Act “must factor in the fundamental objectives of the Act, including the deployment of a ‘rapid, efficient . . . wire and radio communication service with adequate facilities at reasonable charges’ and ‘the development and rapid deployment of new technologies, products and services for the benefit of the public . . . without administrative or judicial delays[, and] efficient and intensive use of the electromagnetic spectrum.’” Accelerating Wireless Broadband Deployment by Removing Barriers to Infrastructure Investment, Second Report and Order, FCC 18-30, para. 62 (rel. Mar. 30, 2018) (Wireless Infrastructure Second R&O) (quoting 47 U.S.C. §§ 151, 309(j)(3)(A), (D))

services for the benefit of the public . . . without administrative or judicial delays[, and] efficient and intensive use of the electromagnetic spectrum.’” Accelerating Wireless Broadband Deployment by Removing Barriers to Infrastructure Investment, Second Report and Order, FCC 18-30, para. 62 (rel. Mar. 30, 2018) (Wireless Infrastructure Second R&O) (quoting 47 U.S.C. §§ 151, 309(j)(3)(A), (D)).

These provisions demonstrate that our interpretation of Section 253 and Section 332(c)(7)(B)(i)(II) is in accordance with the broader goals of the various statutes that the Commission is entrusted to administer.

39. California Payphone further concluded that providers must be allowed to compete in a “fair and balanced regulatory environment.” California Payphone, 12 FCC Rcd at 14206, para. 31.

As reflected in decisions such as the Commission’s Texas PUC Order, a state or local legal requirement can function as an effective prohibition either because of the resulting “financial burden” in an absolute sense, or, independently, because of a resulting competitive disparity. Texas PUC Order, 13 FCC Rcd at 3466, 3498-500, paras. 13, 78-81; see also, e.g., Crown Castle June 7, 2018 Ex Parte at 10-11, 13.

We clarify that “[a] regulatory structure that gives an advantage to particular services or facilities has a prohibitory effect, even if there are no express barriers to entry in the state or local code; the greater the discriminatory effect, the more certain it is that entities providing service using the disfavored facilities will experience prohibition.” Crown Castle June 7, 2018 Ex Parte Letter at 13.

This conclusion is consistent with both Commission and judicial precedent recognizing the prohibitory effect that results from a competitor being treated materially differently than similarly-situated providers. See, e.g., Texas PUC Order, 13 FCC Rcd at 3466, 3498-500, paras

ng service using the disfavored facilities will experience prohibition.” Crown Castle June 7, 2018 Ex Parte Letter at 13.

This conclusion is consistent with both Commission and judicial precedent recognizing the prohibitory effect that results from a competitor being treated materially differently than similarly-situated providers. See, e.g., Texas PUC Order, 13 FCC Rcd at 3466, 3498-500, paras. 13, 78-81; Federal-State Joint Board on Universal Service; Western Wireless Corporation Petition for Preemption of an Order of the South Dakota Public Utilities, Declaratory Ruling, 15 FCC Rcd 15168, 15173, paras. 12-13 (2000) (Western Wireless Order); Pittencrieff Communications, Inc. Petition for Declaratory Ruling Regarding Preemption of the Texas Public Utility Regulatory Act of 1995, Memorandum Opinion and Order, 13 FCC Rcd 1735, 1751-52, para. 32 (1997) (Pittencrieff), aff’d, Cellular Telecomm. Indus. Ass‘n v. FCC, 168 F.3d 1332 (5th Cir. 1999); City of White Plains, 305 F.3d at 80.

We provide our authoritative interpretation below of the circumstances in which a “financial burden,” as described in the Texas PUC Order, constitutes an effective prohibition in the context of certain state and local fees.

40. As we explained above, we reject alternative readings of the effective prohibition language that have been adopted by some courts and used to defend local requirements that have the effect of prohibiting densification of networks. Decisions that have applied solely a “coverage gap”-based approach under Section 332(c)(7)(B)(i)(II) reflect both an unduly narrow reading of the statute and an outdated view of the marketplace. Smart Communities seeks clarification of whether this Declaratory Ruling is meant to say that the “coverage gap” standard followed by a number of courts should include consideration of capacity as well as coverage issues. Letter from Gerard Lavery Lederer, Counsel, Smart Communities and Special Districts Coalition, to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79, Att

f the marketplace. Smart Communities seeks clarification of whether this Declaratory Ruling is meant to say that the “coverage gap” standard followed by a number of courts should include consideration of capacity as well as coverage issues. Letter from Gerard Lavery Lederer, Counsel, Smart Communities and Special Districts Coalition, to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79, Att. at 17 (Sept. 19, 2018) (Smart Communities Sept. 19 Ex Parte Letter). We are not holding that prior “coverage gap” analyses are consistent with the standards we articulate here as long as they also take into account “capacity gaps”; rather, we are articulating here the effective prohibition standard that should apply while, at the same time, noting one way in which prior approaches erred by requiring coverage gaps. Accordingly, we reject both the version of the “coverage gap” test followed by the First, Fourth, and Seventh Circuits (requiring applicants to show “not just that this application has been rejected but that further reasonable efforts to find another solution are so likely to be fruitless that it is a waste of time even to try”) and the version endorsed by the Second, Third, and Ninth Circuits (requiring applicants to show that the proposed facilities are the “least intrusive means” for filling a coverage gap) See supra n. 75. We also note that some courts have expressed concern about alternative readings of the statute that would lead to extreme outcomes—either always requiring a grant under some interpretations, or never preventing a denial under other interpretations. See, e.g., Willoth, 176 F.3d at 639-41; APT, 196 F.3d at 478-79; Town of Amherst v. Omnipoint Communications Enterprises, Inc., 173 F.3d 9, 14 (1st Cir. 1999); AT&T Wireless PCS v. City Council of Virginia Beach, 155 F.3d 423, 428 (4th Cir. 1998) (City Council of Virginia Beach); see also, e.g., Greenling Comments at 2; City and County of San Francisco Reply at 16

ial under other interpretations. See, e.g., Willoth, 176 F.3d at 639-41; APT, 196 F.3d at 478-79; Town of Amherst v. Omnipoint Communications Enterprises, Inc., 173 F.3d 9, 14 (1st Cir. 1999); AT&T Wireless PCS v. City Council of Virginia Beach, 155 F.3d 423, 428 (4th Cir. 1998) (City Council of Virginia Beach); see also, e.g., Greenling Comments at 2; City and County of San Francisco Reply at 16. Our interpretation avoids those concerns while better reflecting the text and policy goals of the Communications Act and 1996 Act than coverage gap-based approaches ultimately adopted by those courts. Our approach ensures meaningful constraints on state and local conduct that otherwise would prohibit or have the effect of prohibiting the provision of personal wireless services. At the same time, our standard does not preclude all state and local denials of requests for the placement, construction, or modification of personal wireless service facilities, as explained below. See infra III.B, C.

Those cases, including some that formed the foundation for “coverage gap”-based analytical approaches, appear to view wireless service as if it were a single, monolithic offering provided only via traditional wireless towers. See, e.g., Willoth, 176 F.3d at 641-44; 360 Degrees Commc’ns Co. v.Board of Supervisors of Albemarle County, 211 F.3d 79, 86-88 & n.1 (4th Cir. 2000) (Albemarle County); see also, e.g., ExteNet Comments at 29; T-Mobile Comments at 42; Verizon Comments at 18; WIA Comments at 38-40. Even some cases that implicitly recognize the limitations of a gap-based test fail to account for those limitations in practice when applying Section 332(c)(7)(B)(i)(II). See, e.g., Second Generation Properties v. Town of Pelham, 313 F.3d 620, 633 n.14 (4th Cir

000) (Albemarle County); see also, e.g., ExteNet Comments at 29; T-Mobile Comments at 42; Verizon Comments at 18; WIA Comments at 38-40. Even some cases that implicitly recognize the limitations of a gap-based test fail to account for those limitations in practice when applying Section 332(c)(7)(B)(i)(II). See, e.g., Second Generation Properties v. Town of Pelham, 313 F.3d 620, 633 n.14 (4th Cir. 2002) (discussing scenarios where a carrier has coverage but insufficient capacity to adequately handle the volume of calls or where new technology emerges and a carrier would like to use it in areas that already have coverage using prior-generation technology). Courts that have sought to identify limited set of characteristics of personal wireless services covered by the Act essentially allow actual or effective prohibition of many personal wireless services that providers wish to offer with additional or more advanced characteristics. See, e.g., Willoth, 176 F.3d at 641-43 (drawing upon certain statutory definitions); Cellular Tel. Co. v. Zoning Bd. of Adjustment of the Borough of Ho-Ho-Kus, 197 F.3d 64, 70 (3d Cir. 1999) (Borough of Ho-Ho-Kus) (concluding that it should be up to state or local authorities to assess and weigh the benefits of differing service qualities); Albemarle County, 211 F.3d at 87 (citing 47 CFR §§ 22.99, 22.911(b) as noting the possibility of some ‘dead spots’); cf. USCOC of Greater Iowa, Inc. v. Zoning Bd. of Adjustment of the City of Des Moines, 465 F.3d 817 (8th Cir. 2006) (describing as a “dubious proposition” the argument that a denial of a request to construct a tower resulting in “less than optimal” service quality could be an effective prohibition). An outcome that allows the actual or effective prohibition of some covered services is contrary to the Act. Section 253(a) applies to any state or local legal requirement that prohibits or has the effect of prohibiting any entity from providing “any” interstate or intrastate telecommunications service, 47 U.S.C. § 253(a)

in “less than optimal” service quality could be an effective prohibition). An outcome that allows the actual or effective prohibition of some covered services is contrary to the Act. Section 253(a) applies to any state or local legal requirement that prohibits or has the effect of prohibiting any entity from providing “any” interstate or intrastate telecommunications service, 47 U.S.C. § 253(a). Similarly, Section 332(c)(7)(B)(i)(II) categorically precludes state or local regulation of the placement, construction, or modification of personal wireless service facilities that prohibits or has the effect of prohibiting the provision of personal wireless “services.” 47 U.S.C. § 332(c)(7)(B)(i)(II). We find the most natural interpretation of these sections is that any service that meets the definition of “telecommunications service” or “personal wireless service” is encompassed by the language of each provision, rather than only some subset of such services or service generally. The notion that such state or local regulation permissibly could prohibit some personal wireless services, so long as others are available, is at odds with that interpretation. In addition, as we explain above, a contrary approach would fail to advance important statutory goals as well as the interpretation we adopt. Further, the approach reflected in these court decisions could involve state or local authorities “inquir[ing] into and regulat[ing] the services offered—an inquiry for which they are ill-qualified to pursue and which could only delay infrastructure deployment.” Crown Castle June 7, 2018 Ex Parte Letter at 14. Instead, our effective prohibition analysis focuses on the service the provider wishes to provide, incorporating the capabilities and performance characteristics it wishes to employ, including facilities deployment to provide existing services more robustly, or at a better level of quality, all to offer a more robust and competitive wireless service for the benefit of the public

rte Letter at 14. Instead, our effective prohibition analysis focuses on the service the provider wishes to provide, incorporating the capabilities and performance characteristics it wishes to employ, including facilities deployment to provide existing services more robustly, or at a better level of quality, all to offer a more robust and competitive wireless service for the benefit of the public.

By contrast, the current wireless marketplace is characterized by a wide variety of offerings with differing service characteristics and deployment strategies. See generally, e.g., Twentieth Wireless Competition Report, 32 FCC Rcd at 8968; see also, e.g., T-Mobile Comments at 42-43; AT&T Reply at 4-5; CTIA Reply at 13-14; WIA Reply at 23-24; Crown Castle June 7, 2018 Ex Parte Letter at 15. We do not suggest that viewing wireless service as if it were a single, monolithic offering provided only via traditional wireless towers would have reflected an accurate understanding of the marketplace in the past, even if it might have been somewhat more understandable that courts held such a simplified view at that time. Rather, the current marketplace conditions highlight even more starkly the shortcomings of coverage gap-based approaches, which do not account for other characteristics and deployment strategies. See, e.g., Twentieth Wireless Competition Report, 32 FCC Rcd at 8974-75, para. 12 (observing that “[p]roviders of mobile wireless services typically offer an array of mobile voice and data services,” including “interconnected mobile voice services”); id. at 8997-97, paras. 42-43 (discussing various types of wireless infrastructure deployment to, among other things, “improve spectrum efficiency for 4G and future 5G services,” “to fill local coverage gaps, to densify networks and to increase local capacity”)

of mobile wireless services typically offer an array of mobile voice and data services,” including “interconnected mobile voice services”); id. at 8997-97, paras. 42-43 (discussing various types of wireless infrastructure deployment to, among other things, “improve spectrum efficiency for 4G and future 5G services,” “to fill local coverage gaps, to densify networks and to increase local capacity”).

As Crown Castle explains, coverage gap-based approaches are “simply incompatible with a world where the vast majority of new wireless builds are going to be designed to add network capacity and take advantage of new technologies, rather than plug gaps in network coverage.” Crown Castle June 7, 2018 Ex Parte Letter at 15; see also id. at 13 (“Densification of networks will be key for augmenting the capacity of existing networks and laying the groundwork for the deployment of 5G.”); id. at 15-16 (“When trying to maximize spectrum re-use and boost capacity, moving facilities by just a few hundred feet can mean the difference between excellent service and poor service. The FCC’s rules, therefore, must account for the effect siting decisions would have on every level of service, including increasing capacity and adding new spectrum bands. Practices and decisions that prevent carriers from doing either materially prohibit the provision of telecommunications service and thus should be considered impermissible under Section 332.”). Contrary approaches appear to occur in part when courts’ policy balancing places more importance on broadly preserving state and local authority than is justified. See, e.g., APT, 196 F.3d at 479; Albemarle County, 211 F.3d at 86; City Council of Virginia Beach, 155 F.3d at 429; National Tower, LLC v. Plainville Zoning Bd. of Appeals, 297 F.3d 14 (1st Cir. 2002); see also, e.g., League of Arizona Cities et al. Joint Comments at 45; Smart Communities Reply at 33

lancing places more importance on broadly preserving state and local authority than is justified. See, e.g., APT, 196 F.3d at 479; Albemarle County, 211 F.3d at 86; City Council of Virginia Beach, 155 F.3d at 429; National Tower, LLC v. Plainville Zoning Bd. of Appeals, 297 F.3d 14 (1st Cir. 2002); see also, e.g., League of Arizona Cities et al. Joint Comments at 45; Smart Communities Reply at 33. As explained above, our interpretation that “telecommunications services” in Section 253(a) and “personal wireless services” in Section 332(c)(7)(B)(i)(II) are focused on the covered services that providers seek to provide —including the relevant service characteristics they seek to incorporate—not only is consistent with the text of those provisions but better reflects the broader policy goals of the Communications Act and the 1996 Act.

Moreover, a critical feature of these new wireless builds is to accommodate increased in-building use of wireless services, necessitating deployment of small cells in order to ensure quality service to wireless callers within such buildings. See WIA Comments at 39; T-Mobile Comments at 43-44.

41. Likewise, we reject the suggestion of some courts like the Eighth and Ninth Circuits that evidence of an existing or complete inability to offer a telecommunications service is required under 253(a). See, e.g., County of San Diego, 543 F.3d at 577, 579-80; City of St. Louis, 477 F.3d at 533-34; see also, e.g., Virginia Joint Commenters Comments, Exh. A at 39-41. Although the Ninth Circuit in County of San Diego found that “the unambiguous text of §253(a)” precluded a prior Ninth Circuit approach that found an effective prohibition based on broad governmental discretion and the “mere possibility of prohibition,” that holding is not implicated by our interpretations here. County of San Diego, 543 F.3d at 578; cf. City of St. Louis, 477 F.3d at 532

39-41. Although the Ninth Circuit in County of San Diego found that “the unambiguous text of §253(a)” precluded a prior Ninth Circuit approach that found an effective prohibition based on broad governmental discretion and the “mere possibility of prohibition,” that holding is not implicated by our interpretations here. County of San Diego, 543 F.3d at 578; cf. City of St. Louis, 477 F.3d at 532. Consequently, those decisions do not preclude the Commission’s interpretations here, see, e.g., Verizon Reply at 7, and we reject claims to the contrary. See, e.g., Smart Communities Comments at 60.

Such an approach is contrary to the material inhibition standard of California Payphone and the correct recognition by courts “that a prohibition does not have to be complete or ‘insurmountable’” to constitute an effective prohibition. City of White Plains, 305 F.3d at 76 (citing RT Commc’ns, 201 F.3d at 1268); see also, e.g., Municipality of Guayanilla, 450 F.3d at 18 (quoting City of White Plains, 305 F.3d at 76 and citing City of Santa Fe, 380 F.3d at 1269); Crown Castle June 7, 2018 Ex Parte Letter at 12; Verizon Aug. 10, 2018 Ex Parte Letter, Attach at 5. Indeed, the Eighth Circuit’s City of St. Louis decision acknowledges that under Section 253 “[t]he plaintiff need not show a complete or insurmountable prohibition,” even while other aspects of that decision suggest that an insurmountable barrier effectively would be required. City of St. Louis, 477 F.3d at 533 (citing City of White Plains, 305 F.3d at 76).

Commission precedent beginning with California Payphone itself makes clear that an insurmountable barrier is not required to find an effective prohibition under Section 253(a)

surmountable prohibition,” even while other aspects of that decision suggest that an insurmountable barrier effectively would be required. City of St. Louis, 477 F.3d at 533 (citing City of White Plains, 305 F.3d at 76).

Commission precedent beginning with California Payphone itself makes clear that an insurmountable barrier is not required to find an effective prohibition under Section 253(a). In California Payphone, the Commission concluded that the ordinance at issue “does not ‘prohibit’ the ability of any payphone service provider to provide payphone service in the Central Business District within the meaning of section 253(a),” but went on to evaluate the possibility of an effective prohibition by considering “whether the Ordinance materially inhibits or limits the ability of any competitor or potential competitor to compete in a fair and balanced legal and regulatory environment.” California Payphone, 12 FCC Rcd at 14205, 14206, paras. 28, 31. In the Texas PUC Order, the Commission found that state law build-out requirements would require “substantial financial investment” and a “comparatively high cost per loop sold” in particular areas, interfering with the “statewide entry” plans that new entrants “may reasonable contemplate” in violation of Section 253(a) notwithstanding claims that the specific new entrants at issue had “‘vast resources and access to capital’ sufficient to meet those added costs. Texas PUC Order, 13 FCC Rcd at 3498, para. 78. The Commission also has expressed “great concern” about an exclusive rights-of-way access agreement that “appear[ed] to have the potential to adversely affect the provision of telecommunications services by facilities-based providers, in violation of the provision of section 253(a).” Minnesota Order, 14 FCC Rcd at 21700, para. 3

those added costs. Texas PUC Order, 13 FCC Rcd at 3498, para. 78. The Commission also has expressed “great concern” about an exclusive rights-of-way access agreement that “appear[ed] to have the potential to adversely affect the provision of telecommunications services by facilities-based providers, in violation of the provision of section 253(a).” Minnesota Order, 14 FCC Rcd at 21700, para. 3. As another example, in the Western Wireless Order, the Commission stated that a “universal service fund mechanism that provides funding only to ILECs” would likely violate Section 253(a) not because it was insurmountable but because it would “effectively lower the price of ILEC-provided service relative to competitor-provided service” and thus “give customers a strong incentive to choose service from ILECs rather than competitors.” Western Wireless Order, 15 FCC Rcd at 16231, para. 8.

The “effectively prohibit” language must have some meaning independent of the “prohibit” language, and we find that the interpretation of the First, Second, and Tenth Circuits reflects that principle, while being more consistent with the California Payphone standard than the approach of the Eighth and Ninth Circuits. We discuss specific applications of the California Payphone standard in the context of certain fees and non-fee regulations in the sections below; we leave others to be addressed case-by-case as they arise or otherwise are taken up by the Commission or courts in the future.

The reasonableness of our interpretation that ‘effective prohibition’ does not require a showing of an insurmountable barrier to entry is demonstrated not only by a number of circuit courts’ acceptance of that view, but in the Supreme Court’s own characterization of Section 253(a) as “prohibit[ing] state and local regulation that impedes the provision of ‘telecommunications service.’” Verizon Communications, Inc. v. FCC, 535 U.S

retation that ‘effective prohibition’ does not require a showing of an insurmountable barrier to entry is demonstrated not only by a number of circuit courts’ acceptance of that view, but in the Supreme Court’s own characterization of Section 253(a) as “prohibit[ing] state and local regulation that impedes the provision of ‘telecommunications service.’” Verizon Communications, Inc. v. FCC, 535 U.S. 467, 491 (2002) (emphasis added); see also, e.g., Level 3 Communications, Petition for a Writ of Certiorari, Level 3 Communications, LLC v. City of St. Louis, No. 08-626, at 13 (filed Nov. 7, 2008) (“[T]he term ‘[p]rohibit’ commonly has a less absolute meaning than that adopted below, and properly refers to actions that ‘hold back,’ ‘hinder,’ or ‘obstruct.’” (quoting Random House Webster’s Unabridged Dictionary 1546 (2d ed. 1998)). We thus are not compelled to interpret ‘effective prohibition’ to set the high bar suggested by some commenters based on other dictionary definitions. Smart Communities Petition for Reconsideration, WC Docket No. 17-84, WT Docket No. 17-79 at 7 (filed Sept. 4, 2018). Because we are unpersuaded that the statutory terminology requires us to interpret an effective prohibition as satisfied only by an insurmountable barrier to entry, we likewise reject commenters’ attempts to argue that “effective prohibition” must be understood to set a higher bar by comparison to the “impairment” language in Section 251 of the Act and associated regulatory interpretations of network unbundling requirements taken from that context. Id at 6. In addition, commenters do not demonstrate why the statutory framework and regulatory context of network unbundling under Section 251—and the specific concerns about access by non-facilities-based providers to competitive networks underlying the court precedent they cite—is sufficiently analogous to that of Section 253 and Section 332(c)(7)(B)(i)(II) that statements from that context should inform our interpretation here. See, e.g., AT&T Corp. v

statutory framework and regulatory context of network unbundling under Section 251—and the specific concerns about access by non-facilities-based providers to competitive networks underlying the court precedent they cite—is sufficiently analogous to that of Section 253 and Section 332(c)(7)(B)(i)(II) that statements from that context should inform our interpretation here. See, e.g., AT&T Corp. v. Iowa Utilities Bd., 525 U.S. at 392. In responding to these discrete arguments raised in a petition for reconsideration of the Moratoria Declaratory Ruling that bear on actions we take in this order we do not thereby resolve any of the petition’s arguments with respect to that order. The requests for relief raised in the petition remain pending in full.

42. The Eighth and Ninth Circuits’ suggestion that a provider must show an insurmountable barrier to entry in the jurisdiction imposing the relevant regulation is at odds with relevant statutory purposes and goals, as well. Section 253(a) is designed to protect “any entity” seeking to provide telecommunications services from state and local barriers to entry, and Sections 253(b) and (c) emphasize the importance of “competitively neutral” and “nondiscriminatory” treatment of providers. 47 U.S.C. § 253(a), (b), (c).

Yet focusing on whether the carrier seeking relief faces an insurmountable barrier to entry would lead to disparities in statutory protections among providers based merely on considerations such as their access to capital and the breadth or narrowness of their entry strategies. See, e.g., Texas PUC Order, 13 FCC Rcd at 3498, para. 78 (rejecting claims that there should be a higher bar to find an effective prohibition for providers with significant financial resources and recognizing that the effects of the relevant state requirements on a given provider could differ depending on the planned geographic scope of entry)

d the breadth or narrowness of their entry strategies. See, e.g., Texas PUC Order, 13 FCC Rcd at 3498, para. 78 (rejecting claims that there should be a higher bar to find an effective prohibition for providers with significant financial resources and recognizing that the effects of the relevant state requirements on a given provider could differ depending on the planned geographic scope of entry).

In addition, the Commission has observed in connection with Section 253: “Each local government may believe it is simply protecting the interests of its constituents. The telecommunications interests of constituents, however, are not only local. They are statewide, national and international as well. We believe that Congress’ recognition of this fact was the genesis of its grant of preemption authority to this Commission.” TCI Cablevision of Oakland County, Inc. Petition for Declaratory Ruling, Preemption and Other Relief Pursuant to 47 U.S.C. §§ 541, 544(e), and 253, Memorandum Opinion and Order, 12 FCC Rcd 21396, 21442, para. 106 (1997) (TCI Cablevision Order).

As illustrated by our consideration of effective prohibitions flowing from state and local fees, there also can be cases where a narrow focus on whether an insurmountable barrier can be shown within the jurisdiction imposing a particular legal requirement would neglect the serious effects that flow through in other jurisdictions as a result, including harms to regional or national deployment efforts. See infra Part III.B.

B. State and Local Fees

43. Federal courts have long recognized that the fees charged by local governments for the deployment of communications infrastructure can run afoul of the limits Congress imposed in the effective prohibition standard embodied in Sections 253 and 332. The Commission also has recognized the potential for fees to result in an effective prohibition. See, e.g., Pittencrieff, 13 FCC Rcd at 1751-52, para

. Federal courts have long recognized that the fees charged by local governments for the deployment of communications infrastructure can run afoul of the limits Congress imposed in the effective prohibition standard embodied in Sections 253 and 332. The Commission also has recognized the potential for fees to result in an effective prohibition. See, e.g., Pittencrieff, 13 FCC Rcd at 1751-52, para. 37 (observing that “even a neutral [universal service] contribution requirement might under some circumstances effectively prohibit an entity from offering a service”).

In Municipality of Guayanilla, for example, the First Circuit addressed whether a city could lawfully charge a 5 percent gross revenue fee. The court found that the “5% gross revenue fee would constitute a substantial increase in costs” for the provider, and that the ordinance consequently “will negatively affect [the provider’s] profitability.” Municipality of Guayanilla, 450 F.3d at 18-19.

The fee, together with other requirements, thus “place a significant burden” on the provider. Id. at 19.

In light of this analysis, the First Circuit agreed that the fee “‘materially inhibits or limits the ability’” of the provider “‘to compete in a fair and balanced legal and regulatory environment.’” Id. (quoting City of White Plains, 305 F.3d at 76).

The court thus held that the fee does not survive scrutiny under Section 253. In doing so, the First Circuit also noted that the inquiry is not limited to the impact that a fee would have on deployment in the jurisdiction that imposes the fee. Rather, the court noted the aggregate effect of fees when totaled across all relevant jurisdictions. Municipality of Guayanilla, 450 F.3d at 17 (looking at the aggregate cost of fees charged across jurisdictions given the interconnected nature of the service)

cuit also noted that the inquiry is not limited to the impact that a fee would have on deployment in the jurisdiction that imposes the fee. Rather, the court noted the aggregate effect of fees when totaled across all relevant jurisdictions. Municipality of Guayanilla, 450 F.3d at 17 (looking at the aggregate cost of fees charged across jurisdictions given the interconnected nature of the service).

At the same time, the First Circuit did not decide whether the fair and reasonable compensation allowed under Section 253 must be limited to cost recovery or, at the very least, related to the actual use of the ROW. Id. at 22 (“We need not decide whether fees imposed on telecommunications providers by state and local governments must be limited to cost recovery. We agree with the district court’s reasoning that fees should be, at the very least, related to the actual use of rights of way and that ‘the costs [of maintaining those rights of way] are an essential part of the equation.’”).

44. In City of White Plains, the Second Circuit likewise faced a 5 percent gross revenue fee, which it found to be “[t]he most significant provision” in a franchise agreement implementing an ordinance that the court concluded effectively prohibited service in violation of Section 253. City of White Plains, 305 F.3d at 77.

While the court noted that “compensation is . . . sometimes used as a synonym for cost,” Id. In this context, the court stated that the term “compensation” is “flexible” and capable of different meanings depending on the context in which it is used. Id.

it ultimately did not resolve whether fair and reasonable compensation “is limited to cost recovery, or whether it also extends to a reasonable rent,” relying instead on the fact that “White Plains has not attempted to charge Verizon the fee that it seeks to charge TCG,” thus failing Section 253’s “competitively neutral and nondiscriminatory” standard. City of White Plains, 305 F.3d at 79

. Id.

it ultimately did not resolve whether fair and reasonable compensation “is limited to cost recovery, or whether it also extends to a reasonable rent,” relying instead on the fact that “White Plains has not attempted to charge Verizon the fee that it seeks to charge TCG,” thus failing Section 253’s “competitively neutral and nondiscriminatory” standard. City of White Plains, 305 F.3d at 79. In particular, the court concluded that “fees that exempt one competitor are inherently not ‘competitively neutral,’ regardless of how that competitor uses its resulting market advantage,” id. at 80, and thus “[a]llowing White Plains to strengthen the competitive position of the incumbent service provider would run directly contrary to the pro-competitive goals of the [1996 Act],” id. at 79.

But the court did observe that “Section 253(c) requires compensation to be reasonable essentially to prevent monopolist pricing by towns.” Id.

45. In another example, the Tenth Circuit in City of Santa Fe addressed a $6,000 per foot fee set for Qwest’s use of the ROW. City of Santa Fe, 380 F.3d at 1270-71.

The court held “that the rental provisions are prohibitive because they create[d] a massive increase in cost” for Qwest. Id. at 1271.

The court recognized that Section 253 allows the recovery of cost-based fees, though it ultimately did not decide whether to “measure ‘fair and reasonable’ by the City’s costs or by a ‘totality of circumstances test’” applied in other courts because it determined that the fees at issue were not cost-based and “fail[ed] even the totality of the circumstances test.” Id. at 1272 (observing that “[t]he City acknowledges . . . that the rent required by the Ordinance is not limited to recovery of costs”).

Consequently, the fee was preempted under Section 253.

46. At the same time, the courts have adopted different approaches to analyzing whether fees run afoul of Section 253, at times failing even to articulate a particular test

ty of the circumstances test.” Id. at 1272 (observing that “[t]he City acknowledges . . . that the rent required by the Ordinance is not limited to recovery of costs”).

Consequently, the fee was preempted under Section 253.

46. At the same time, the courts have adopted different approaches to analyzing whether fees run afoul of Section 253, at times failing even to articulate a particular test. Compare, e.g., Municipality of Guayanilla, 450 F.3d at 18-19 (finding that fees were significant and had the effect of prohibiting service); City of Santa Fe, 380 F.3d at 1271 (similar); with, e.g., Qwest v. Elephant Butte Irrigation Dist., 616 F. Supp. 2d 1110, 1123-24 (D.N.M. 2008) (rejecting Qwest’s reliance on preceding finding of effective prohibition from quadrupled costs where the fee at issue was a penny per foot); Qwest v. City of Portland, 2006 WL 2679543, *15 (D. Or. 2006) (asserting with no explanation that “a registration fee of $35 and a refundable deposit of $2,000 towards processing expenses . . . could not possibly have the effect of prohibiting Qwest from providing telecommunications services”).

Among other things, courts have expressed different views on whether Section 253 limits states’ and localities’ fees to recovery of their costs or allows fees set in excess of that level. For example and as noted above, in Municipality of Guayanilla the First Circuit reserved judgment on whether the fair and reasonable compensation allowed under Section 253 must be limited to cost recovery or if it was sufficient if the compensation was related to the actual use of rights of way. Municipality of Guayanilla, 450 F.3d at 22. Other courts have found reasonable compensation to require cost-based fees. XO Missouri v. City of Maryland Heights, 256 F. Supp. 2d 987, 993-95 (E.D. Mo. 2003) (City of Maryland Heights); Bell Atlantic–Maryland, Inc. v. Prince George’s County, 49 F. Supp. 2d 805, 818 (D. Md. 1999) (Prince George’s County) vacated on other grounds, 212 F.3d 863 (4th Cir. 2000)

lity of Guayanilla, 450 F.3d at 22. Other courts have found reasonable compensation to require cost-based fees. XO Missouri v. City of Maryland Heights, 256 F. Supp. 2d 987, 993-95 (E.D. Mo. 2003) (City of Maryland Heights); Bell Atlantic–Maryland, Inc. v. Prince George’s County, 49 F. Supp. 2d 805, 818 (D. Md. 1999) (Prince George’s County) vacated on other grounds, 212 F.3d 863 (4th Cir. 2000). Still other courts have applied a test that weighs a number of considerations when evaluating whether compensation is fair and reasonable. TCG Detroit v. City of Dearborn, 206 F.3d 618, 625 (6th Cir. 2000) (City of Dearborn) (considering “the amount of use contemplated . . . the amount that other providers would be willing to pay . . . and the fact that TCG had agreed in earlier negotiations to a fee almost identical to what it now was challenging as unfair”).

We articulate below the Commission’s interpretation of Section 253(a) and the standards we adopt for evaluating when a fee for Small Wireless Facility deployment is preempted, regardless how the fee is challenged. We also clarify that the Commission interprets Section 332(c)(7)(B)(i)(II) to have the same substantive meaning as Section 253(a).

47. Record Evidence on Costs Associated with Small Wireless Facilities. Keeping pace with the demands on current 4G networks and upgrading our country’s wireless infrastructure to 5G require the deployment of many more Small Wireless Facilities. See CTIA June 27, 2018 Ex Parte Letter at 6 (“[s]mall cell technology is needed to support 4G densification and 5G connectivity.”); see also Accelerating Wireless Deployment by Removing Barriers to Infrastructure Investment, Report and Order, 32 FCC Rcd 9760, 9765, para. 12 (2017) (2017 Pole Replacement Order) (recognizing that Small Wireless Facilities will be increasingly necessary to support the rollout of next-generation services)

at 6 (“[s]mall cell technology is needed to support 4G densification and 5G connectivity.”); see also Accelerating Wireless Deployment by Removing Barriers to Infrastructure Investment, Report and Order, 32 FCC Rcd 9760, 9765, para. 12 (2017) (2017 Pole Replacement Order) (recognizing that Small Wireless Facilities will be increasingly necessary to support the rollout of next-generation services).

For example, Verizon anticipates that network densification and the upgrade to 5G will require 10 to 100 times more antenna locations than currently exist. AT&T estimates that providers will deploy hundreds of thousands of wireless facilities in the next few years alone—equal to or more than the number providers have deployed in total over the last few decades. See Verizon Comments at 3; AT&T Comments at 1.

Sprint, in turn, has announced plans to build at least 40,000 new small sites over the next few years. See Letter from Keith C. Buell, Senior Counsel, Sprint, to Marlene H. Dortch, Secretary, FCC, WT Docket No. 17-79 at 2 (filed Feb. 21, 2018).

A report from Accenture estimates that, overall, during the next three or four years, 300,000 small cells will need to be deployed—a total that it notes is “roughly double the number of macro cells built over the last 30 years.” Accelerating Future Economic Value Report at 6; see also Deloitte 5G Paper.

48. The many-fold increase in Small Wireless Facilities will magnify per-facility fees charged to providers. Per-facility fees that once may have been tolerable when providers built macro towers several miles apart now act as effective prohibitions when multiplied by each of the many Small Wireless Facilities to be deployed. Thus, a per-facility fee may affect a prohibition on 5G service or the densification needed to continue 4G service even if that same per-facility fee did not effectively prohibit previous generations of wireless service.

49

lerable when providers built macro towers several miles apart now act as effective prohibitions when multiplied by each of the many Small Wireless Facilities to be deployed. Thus, a per-facility fee may affect a prohibition on 5G service or the densification needed to continue 4G service even if that same per-facility fee did not effectively prohibit previous generations of wireless service.

49. Cognizant of the changing technology and its interaction with regulations created for a previous generation of service, the 2017 Wireline Infrastructure NPRM/NOI sought comment on whether government-imposed fees could act as a prohibition within the meaning of Section 253, and if so, what fees would qualify for 253(c)’s savings clause. Accelerating Wireline Broadband Deployment by Removing Barriers to Infrastructure Investment, Notice of Proposed Rulemaking and Notice of Inquiry, 32 FCC Rcd 3266, 3296-97, paras. 100 -101 and 3298-99, paras. 104-105 (2017).

The 2017 Wireless Infrastructure NPRM/NOI similarly sought comment on the scope of Sections 253 and 332(c)(7) and on any new or updated guidance the Commission should provide, potentially through a Declaratory Ruling. Wireless Infrastructure NPRM/NOI, 32 FCC Rcd at 3360, para. 87. In addition, in 2016, the Wireless Telecommunications Bureau released a public notice seeking comment on ways to expedite the deployment of next generation wireless infrastructure, including providing guidance on application processing fees and charges for use of rights of way. See Streamlining Deployment of Small Cell Infrastructure by Improving Wireless Facilities Siting Policies, Public Notice, 31 FCC Rcd 13360 (WTB 2016).

In particular, the Commission sought comment on whether it should provide further guidance on how to interpret and apply the phrase “prohibit or have the effect of prohibiting.” Wireless Infrastructure NPRM/NOI, 32 FCC Rcd at 3362, para. 90.

50

ee Streamlining Deployment of Small Cell Infrastructure by Improving Wireless Facilities Siting Policies, Public Notice, 31 FCC Rcd 13360 (WTB 2016).

In particular, the Commission sought comment on whether it should provide further guidance on how to interpret and apply the phrase “prohibit or have the effect of prohibiting.” Wireless Infrastructure NPRM/NOI, 32 FCC Rcd at 3362, para. 90.

50. We conclude that ROW access fees, and fees for the use of government property in the ROW, We do not find these fees to be taxes within the meaning of Section 601(c)(2) of the 1996 Act. See, e.g., Smart Communities Reply at 36 (quoting the savings clause for “State or local law pertaining to taxation” in Section 601(c)(2) of the 1996 Act). It is ambiguous whether a fee charged for access to ROWs should be viewed as a tax for purposes of Section 601(c)(2) of the 1996 Act. See, e.g., City of Dallas v. FCC, 118 F.3d 393, 397-98 (5th Cir. 1997) (distinguishing “the price paid to rent use of public right-of-ways” from a “tax” and citing similar precedent). Given that Congress clearly contemplated in Section 253(c) that states’ and localities’ fees for access to ROWs could be subject to preemption where they violate Section 253—or else the savings clause in that regard would be superfluous—we find the better view is that such fees do not represent a tax encompassed by Section 601(c)(2) of the 1996 Act. We do not address whether particular fees could be considered taxes under other statutes not administered by the FCC, but we reject the suggestion that tests courts use to determine what constitute “taxes” in the context of such other statutes should apply to the Commission’s interpretation of Section 601(c)(2) here in light of the statutory context for Section 601(c)(2) in the 1996 Act and the Communications Act discussed above. See, e.g., Qwest Corp. v. City of Surprise, 434 F.3d 1176, 1183-84 & n.3 (9th Cir

, but we reject the suggestion that tests courts use to determine what constitute “taxes” in the context of such other statutes should apply to the Commission’s interpretation of Section 601(c)(2) here in light of the statutory context for Section 601(c)(2) in the 1996 Act and the Communications Act discussed above. See, e.g., Qwest Corp. v. City of Surprise, 434 F.3d 1176, 1183-84 & n.3 (9th Cir. 2006) (holding that particular fees at issue there were taxes for purposes of the Tax Injunction Act and stating in dicta that had the Tax Injunction Act not applied it would agree with the conclusion of the district court that it was covered by Section 601(c)(2) of the 1996 Act); MCI Communications Services, Inc. v. City of Eugene, 359 F. Appx. 692, 696 (9th Cir. 2009) (asserting without analysis that the same test would apply to determine if a fee constitutes a tax under both the Tax Injunction Act and Section 601(c)(2) of the 1996 Act).

such as light poles, traffic lights, utility poles, and other similar property suitable for hosting Small Wireless Facilities, as well as application or review fees and similar fees imposed by a state or local government as part of their regulation of the deployment of Small Wireless Facilities inside and outside the ROW, violate Sections 253 or 332(c)(7) unless these conditions are met: (1) the fees are a reasonable approximation of the state or local government’s costs, By costs, we mean those costs specifically related to and caused by the deployment. These include, for instance, the costs of processing applications or permits, maintaining the ROW, and maintaining a structure within the ROW. See Puerto Rico Tel. Co. v. Municipality of Guayanilla, 354 F. Supp. 2d 107, 114 (D.P.R. 2005) (Guayanilla District Ct. Opinion), aff'd, 450 F.3d 9 (1st Cir. 2006) (“fees charged by a municipality need to be related to the degree of actual use of the public rights-of way” to constitute fair and reasonable compensation under Section 253(c)).

g the ROW, and maintaining a structure within the ROW. See Puerto Rico Tel. Co. v. Municipality of Guayanilla, 354 F. Supp. 2d 107, 114 (D.P.R. 2005) (Guayanilla District Ct. Opinion), aff'd, 450 F.3d 9 (1st Cir. 2006) (“fees charged by a municipality need to be related to the degree of actual use of the public rights-of way” to constitute fair and reasonable compensation under Section 253(c)).

(2) only objectively reasonable costs are factored into those fees, and (3) the fees are no higher than the fees charged to similarly-situated competitors in similar situations. We explain above what we mean by “fees.” See supra note 71. Contrary to some claims, we are not asserting a “general ratemaking authority.” Virginia Joint Commenters Comments at 6. Our interpretations in this order bear on whether and when fees associated with Small Wireless Facility deployment have the effect of prohibiting wireless telecommunications service and thus are subject to preemption under Section 253(a), informed by the savings clause in Section 253(c). While that can implicate issues surrounding how those fees were established, it does so only to the extent needed to vindicate Congress’s intent in Section 253. We do not interpret Section 253(a) or (c) to authorize the regulation or establishment of state and local fees as an exercise in itself. We likewise are not persuaded by undeveloped assertions that the Commission’s interpretation of Section 253 in the context of fees would somehow violate constitutional separation of powers principles. See, e.g., Virginia Joint Commenters Comments, Exh. A at 52.

51

interpret Section 253(a) or (c) to authorize the regulation or establishment of state and local fees as an exercise in itself. We likewise are not persuaded by undeveloped assertions that the Commission’s interpretation of Section 253 in the context of fees would somehow violate constitutional separation of powers principles. See, e.g., Virginia Joint Commenters Comments, Exh. A at 52.

51. We base our interpretation on several considerations, including the text and structure of the Act as informed by legislative history, the economics of capital expenditures in the context of Small Wireless Facilities (including the manner in which capital budgets are fixed ex ante), and the extensive record evidence that shows the actual effects that state and local fees have in deterring wireless providers from adding to, improving, or densifying their networks and consequently the service offered over them (including, but not limited to, introducing next-generation 5G wireless service). We address each of these considerations in turn.

52. Text and Structure. We start our analysis with a consideration of the text and structure of Section 253. That section contains several related provisions that operate in tandem to define the roles that Congress intended the federal government, states, and localities to play in regulating the provision of telecommunications services. Section 253(a) sets forth Congress’s intent to preempt state or local legal requirements that “prohibit or have the effect of prohibiting the ability of any entity to provide any interstate or intrastate telecommunications service.” 47 U.S.C. § 253(a).

Section 253(b), in turn, makes clear Congress’s intent that state “requirements necessary to preserve and advance universal service, protect the public safety and welfare, ensure the continued quality of telecommunications services, and safeguard the rights of consumers” are not preempted. 47 U.S.C. § 253(b)

o provide any interstate or intrastate telecommunications service.” 47 U.S.C. § 253(a).

Section 253(b), in turn, makes clear Congress’s intent that state “requirements necessary to preserve and advance universal service, protect the public safety and welfare, ensure the continued quality of telecommunications services, and safeguard the rights of consumers” are not preempted. 47 U.S.C. § 253(b).

Of particular importance in the fee context, Section 253(c) reflects a considered policy judgment that “[n]othing in this section” shall prevent states and localities from recovering certain carefully delineated fees. Specifically, Section 253(c) makes clear that fees are not preempted that are “fair and reasonable” and imposed on a “competitively neutral and nondiscriminatory basis,” for “use of public rights-of-way on a “nondiscriminatory basis,” so long as they are “publicly disclosed” by the government. 47 U.S.C. § 253(c).

Section 253(d), in turn, provides one non-exclusive mechanism by which a party can obtain a determination from the Commission of whether a specific state or local requirement is preempted under Section 253(a)—namely, by filing a petition with the Commission. 47 U.S.C. § 253(d).

53. In reviewing this statutory scheme, the Commission previously has construed Section 253(a) as “broadly limit[ing] the ability of state[s] to regulate,” while the remaining subsections set forth “defined areas in which states may regulate.” Texas PUC Order, 13 FCC Rcd at 3481, para. 44.

We reaffirm this conclusion, consistent with the view of most courts to have considered the issue—namely, that Sections 253(b) and (c) make clear that certain state or local laws, regulations, and legal requirements are not preempted under the expansive scope of Section 253(a). See, e.g., Connect America Fund; Sandwich Isles Communications, Inc., Memorandum Opinion and Order, 32 FCC Rcd 5878, 5881, 5885-87, paras. 8, 19-25 (2017) (Sandwich Isles Section 253 Order); Texas PUC Order, 13 FCC Rcd at 3480-81, paras

ions 253(b) and (c) make clear that certain state or local laws, regulations, and legal requirements are not preempted under the expansive scope of Section 253(a). See, e.g., Connect America Fund; Sandwich Isles Communications, Inc., Memorandum Opinion and Order, 32 FCC Rcd 5878, 5881, 5885-87, paras. 8, 19-25 (2017) (Sandwich Isles Section 253 Order); Texas PUC Order, 13 FCC Rcd at 3480-81, paras. 41-44; Global Network Commc’ns, Inc. v. City of New York, 562 F.3d 145, 150-51 (2d Cir. 2009); Southwestern Bell Tel. Co. v. City of Houston, 529 F.3d 257, 262 (5th Cir. 2008); City of St. Louis, 477 F.3d at 531-32 (8th Cir. 2007); Municipality of Guayanilla, 450 F.3d at 15-16; City of Santa Fe, 380 F.3d at 1269; BellSouth Telecomm’s, Inc. v. Town of Palm Beach, 252 F.3d 1169, 1187-89 (11th Cir. 2001). Some courts appear to have viewed Section 253(c) as an independent basis for preemption. See, e.g., City of Dearborn, 206 F.3d at 624 (after concluding that a franchise fee did not violate Section 253(a), going on to evaluate whether it was “fair and reasonable” under Section 253(c)). We find more persuasive the Commission and other court precedent to the contrary, which we find better adheres to the statutory language.

Our interpretation of Section 253(a) is informed by this statutory context, See, e.g., Utility Air Regulatory Group v. EPA, 134 S. Ct. 2427, 2442 (2014).

and the observation of courts that when a preemption provision precedes a narrowly-tailored savings clause, it is reasonable to infer that Congress intended a broad preemptive scope. See, e.g., Pilot Life Ins. Co. v. Dedeaux, 481 U.S. 41, 44-45 (1987); City of New York v. Permanent Mission of India to United Nations, 618 F.3d 172, 189-90 (2d Cir. 2010); Frank v. Delta Airlines, Inc., 314 F.3d 195, 199 (5th Cir. 2002); cf. United States v. Kay, 359 F.3d 738 (5th Cir. 2004) (justifying a broad reading of a statute given that Congress “narrowly defin[ed] exceptions and affirmative defenses against a backdrop of broad applicability”)

, 44-45 (1987); City of New York v. Permanent Mission of India to United Nations, 618 F.3d 172, 189-90 (2d Cir. 2010); Frank v. Delta Airlines, Inc., 314 F.3d 195, 199 (5th Cir. 2002); cf. United States v. Kay, 359 F.3d 738 (5th Cir. 2004) (justifying a broad reading of a statute given that Congress “narrowly defin[ed] exceptions and affirmative defenses against a backdrop of broad applicability”).

We need not decide today whether Section 253(a) preempts all fees not expressly saved by Se

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.

Accelerating Wireless Broadband Deployment by Removing Barriers to Infrastructure Investment; Accelerating Wireline Broadband Deployment by Removing Barriers to Infrastructure Investment · FCC-18-133: Accelerating Wireless Broadband Deployment by Removing Barriers to Infrastructure Investment; Accelerating Wireline Broadband Deployment by Removing Barriers to Infrastructure Investment (09/27/18) | Frix