CLEAN WATER ACT SECTION 401 CERTIFICATION PROCEDURES FOR:

1) ISSUANCE OR REISSUANCE OF NATIONWIDE PERMITS AND REGIONAL

GENERAL PERMITS BY THE U.S. ARMY CORPS OF ENGINEERS

2) GENERAL PERMITS ISSUED BY THE ENVIRONMENTAL PROTECTION

AGENCY

(Procedures for Federal Permitting Agencies)

ARTICLE 1. GENERAL PROVISIONS

1-101. Purpose.

Under these procedures, the Southern Ute Indian Tribe’s Water Quality & Remediation

Division will evaluate requests from the U.S. Army Corps of Engineers (“Army Corps”) for

issuance or reissuance of nationwide or regional general permits, or the Environmental

Protection Agency (“EPA”) for issuance or reissuance of general permits. The Division will

grant, grant with conditions, deny, or waive certification for issuance or reissuance of these

permits.

1-102. Effective date.

These procedures shall become effective upon approval by the Southern Ute Indian

Tribal Council.

1-103. Definitions.

(1)

“Best Management Practices (BMPs)” means structural and non-structural

methods, measures, or practices to prevent, reduce, or mitigate adverse water quality impacts

originating from point or nonpoint sources that are associated with the proposed project’s

activities.

(2)

“Certification” means a letter granting certification, granting certification with

conditions, or denying certification, issued by the Tribe’s Environmental Programs Division.

(3)

“Certification request” means a written, signed, and dated communication that

satisfies the requirements of 40 C.F.R. § 121.5(a), (c), or (d) as applicable.

(4)

“Days” means, unless otherwise specified, calendar days.

(5)

“Division” means the Tribe’s Water Quality & Remediation Division.

1

(6)

“Division Head” means the Division Head of the Tribe’s Water Quality &

Remediation Division.

(7)

“EPA” means the U.S. Environmental Protection Agency.

(8)

“Permit” means an Army Corps-issued nationwide or regional general permit or an

EPA-issued general permit.

(9)

“Permittee” means the person or entity who has obtained coverage under a permit

for which a tribal water quality certification has been issued.

(10) “Federal permitting or licensing agency” means (1) the U.S. Army Corps of

Engineers, which is proposing a nationwide or regional general permit pursuant to Section 404

of the Clean Water Act (CWA), or (2) the Environmental Protection Agency, which is

proposing a general permit pursuant to Section 402 of the CWA, under which persons may

obtain coverage for activities that may result in a discharge into waters of the United States.

(11) “Public” means Southern Ute Indian Tribe members; adjacent tribal member land

assignees; adjacent property owners or lessees; any Federal, state, or local government agencies

responsible for water quality improvement on the Reservation; and other parties known to be

interested in the matter.

(12) “Reasonable period of time” means the period between the date on which the

Division receives a request for certification and the date the Federal agency and the Division have

agreed in writing by which the Division must act on the request for certification, provided the

reasonable period of time may not exceed one year from the date that the Division received the

request for certification. If the Federal agency and the Department have not agreed in writing on

the length of the reasonable period of time, the reasonable period of time shall be six months.

(13) “Reservation” means the Southern Ute Indian Reservation, the exterior

boundaries of which are defined in the Act of May 21, 1984, Pub. L. No. 98-290, 98 Stat. 201,

202.

(14)

“Tribe” means the Southern Ute Indian Tribe.

(15) “Waters of the United States” means waters that satisfy the Federal definition of

“waters of the United States” and are located on trust lands within the exterior boundaries of the

Southern Ute Indian Reservation and over which the Tribe has authority, pursuant to approval by

EPA, for purposes of setting water quality standards.

The definitions of other terms used in these procedures shall be consistent with those

used in the Federal Clean Water Act and its implementing regulations.

2

ARTICLE 2. PRE-FILING MEETING REQUEST.

2-101. Invitation to request meeting.

Before submitting a certification request, the Division requires the Federal

permitting or licensing agency to request a pre-filing meeting with the Division. A project

proponent should refer to the “Instructions for Project Proponents Seeking 401 Pre Filing

Meeting with SUIT” document posted on the Divisions 401 certifications webpage

(https://www.southernute-nsn.gov/government/departments/epd/water-quality/401certification/). The pre-filing meeting is for the Federal permitting or licensing agency to

provide advance notice to the Division that a certification request may be forthcoming and

therefore promotes early coordination. The Division requires Federal permitting or

licensing agency to request a pre-filing meeting with the Tribe at least 30 days prior to

submitting a request for certification in accordance with the Tribe’s applicable submission

procedures. In order for a pre-filing meeting to occur, the Tribe must respond to the prefiling meeting request prior to their receipt of the Federal permitting or licensing agency’s

written certification request. Consistent with 40 CFR § 121.4, the Tribe agrees to maintain

the requirement for a pre-filing meeting request. Upon request, the Tribe may consider

waiving the 30-day period or establishing a different period of time between the date of

the pre-filing meeting and the certification request.

2-102. Discretion.

In its discretion, the Division will decide whether a pre-filing meeting may be necessary

or appropriate for a particular project.

2-103. Topics.

At a pre-filing meeting, the Federal permitting or licensing agency and the Division

may, among other topics, discuss:

•

The nature of the discharges that could be authorized by the proposed permit;

•

Potential water quality effects;

ARTICLE 3. CERTIFICATION REQUEST

3-101. Submittal. The Federal permitting or licensing agency shall refer to the

“Instructions for Project Proponents Seeking a Section 401 Certification with SUIT” document

posted on the Divisions 401 certifications webpage (https://www.southernutensn.gov/government/departments/epd/water-quality/401-certification/), and submit a

certification request to the Division Head by email to: wqs@southernute-nsn.gov.

3-102. Written Confirmation of Receipt.

In accordance with 40 C.F.R. § 121.6(a), the Division shall send written confirmation to the

3

Federal permitting or licensing agency of the date that the request for certification was received.

ARTICLE 4. DIVISION PROCEDURES AND DECISION MAKING

4-101. Internal tribal review and comment.

Upon receipt of a certification request, the Division shall initiate a process

designed to solicit review and comment by interested Tribal divisions and departments within

the tribal organization.

4-102. Public notice process.

The Division will provide public notice of each certification request. The method of

public notice will depend on the potential for water quality impacts and the amount of time

available to the Tribe within the established reasonable period of time. Public notice will occur

by either posting a notice and the draft certification decision on the Division’s website, mailing

notice and the draft certification decision, emailing notice and the draft certification, publishing

notice and the draft certification decision in The Southern Ute Drum or another newspaper of

general circulation in the area in which the activity is proposed to be conducted, and/or holding

one or more public meetings or hearings. In such manner as the Division deems appropriate, the

Division will provide interested parties with an opportunity to comment on such certification

request.

The final certification shall be prepared following the public comment period. The final

certification shall include any changes determined appropriate by the Division based upon

internal Tribal Division and Department review and comment and based on public comments

and information raised during the public comment period. Notice of the final certification shall

be sent to the Federal permitting or licensing agency and to the public in the same manner and

to the same recipients as the notice of the draft certification.

4-103. Public hearings.

The Division may, in its discretion, hold a public hearing with respect to the certification

request before any determination on the certification request.

4-104. Factors considered.

In determining whether to issue certification, the Division shall consider and review the

certification request submitted, and the following, as appropriate:

(1)

Antidegradation review pursuant to applicable Federal or tribal procedures

(2)

Designated uses and applicable water quality standards assigned to the waters into

which discharges that could be authorized by the permit could flow

(3)

Any applicable effluent limitations or control regulations

4

(4)

Best Management Practices required by the Tribe or proposed by the

Federal permitting or licensing agency

(5)

Stormwater discharge requirements

(6)

Comments and other information submitted during the internal tribal review

process and during the public comment period

(7)

Any project-specific conditions proposed by the Federal permitting or licensing

agency and agreed to by the Division

Any other factors the Division considers pertinent in evaluating the activity for water-quality

related impacts.

4-105. Water quality certification decisions and timeframes.

(1)

The Division has established reasonable periods of time for issuing certification

decisions for projects submitted under Army Corps permits and EPA Section 402 National

Pollutant Elimination System (NPDES) general permits. These metrics are listed within

“Established Reasonable Periods of Time between SUIT and USACE” and “Memorandum of

Agreement between the Southern Ute Indian Tribe and the United States Environmental Protection

Agency Region 8” on the Division’s 401 certification webpage (https://www.southernutensn.gov/government/departments/epd/water-quality/401-certification/).

If the Tribe needs more time to finalize a certification decision about a particular draft NPDES

permit, the Tribe may:

(a) Submit a written notification to the EPA for the additional amount of time needed in

accordance with 40 CFR § 121.6(d) if a longer period of time is necessary to

accommodate public notice procedures or force majeure events (including, but not

limited to, government closure or natural disasters), in which case the reasonable

period of time is automatically extended to time necessitated by the procedure or

event, or

(b) For other reasons, submit a request for more time to the EPA indicating the reason

for request and the amount of time requested, in which case the EPA may agree to

the extension in writing in accordance with 40 CFR §§ 121.6(e).

Any notification or request must be received before the reasonable period of time expires.

In no circumstances may the reasonable period of time for a certification decision be extended to

more than one year from the Tribe’s receipt of the request from the EPA.

(2)

After consideration of the factors in section 4-104 and within the scope of

certification allowed under 40 C.F.R. § 121.3 and within the established reasonable period of time

(see below for Army Corps) within which the Tribe’s certification decision is required, the

5

Division shall notify the Federal permitting or licensing agency of its decision to grant, condition,

deny, or waive certification or, alternatively, the Division may notify the Federal permitting or

licensing agency that additional time is required to process the certification request and request

additional time from the Federal permitting or licensing agency (with the understanding the

USACE Federal permitting or licensing agency may or may not grant such an extension, in their

discretion).

The Division agrees that the Army Corps may, on a case-by-case basis, establish a reasonable

period of time for Sec. 401 permits different from the above categorical timeframes, taking into

consideration the complexity of the proposed project, the nature of the potential discharge, and the

possible need for additional study or evaluation of water quality effects. The Division also

anticipates that written requests to extend the reasonable period of time will be infrequent.

Division agreed to only submit one request per certification review at least two weeks before the

initially established reasonable period of time ends. Additionally, the Division acknowledged that

the Army Corps will, when deemed appropriate, grant extensions on a limited time basis,

generally not more than 30 calendar days.

(3)

Certification decision outcomes are listed below:

(a) Grant. The granting of §401 water quality certification to a Federal permitting or

licensing agency for a permit signifies that the Division has determined that the

activities that can obtain coverage under the permit will comply with water

quality requirements as well as the other identified provisions of the Federal

Clean Water Act and appropriate requirements of tribal law. Any grant of

certification shall be in writing and, in conformance with 40 C.F.R. § 121.7(c),

shall include the following: identification of the decision as a grant of

certification; identification of the applicable Federal license or permit; a statement

that the activity will comply with water quality requirements; and an indication

that the Division complied with its public notice procedures established pursuant

to Clean Water Act section 401(a)(1).

(b) Grant with conditions. The granting of §401 water quality certification with

conditions signifies that the Division has concluded that the permit for which

certification is required and the projects that can obtain coverage under the permit

will comply with all applicable requirements only if one or more conditions are

placed on the permit. The Division, as a part of conditional approval, may require

BMPs and water quality monitoring, based on site-specific circumstances, to

ensure that BMPs are performing as designed and that the covered projects

comply with all applicable requirements. Before issuing a conditional

certification, the Division may hold one or more meetings or conferences to

inform the Federal permitting or licensing agency of the need for such conditions

and to discuss options for the covered projects including redesign or modification.

A grant of certification with conditions shall be in writing and, in conformance

with 40 C.F.R. § 121.7(d), shall include the following: identification of the

decision as a grant of certification with conditions; identification of the applicable

Federal license or permit; a statement explaining why each of the included

conditions is necessary to assure that the activity will comply with water quality

6

requirements; and an indication that the Division complied with its public notice

procedures established pursuant to Clean Water Act section 401(a)(1). For

purposes of clarity in enforcement, the Division may indicate which certification

conditions derive from tribal law.

(c) Deny. Denial of §401 water quality certification signifies that the Division has

concluded that the activities covered under the permit will not comply with the

applicable requirements. Before denying certification, the Division may hold one

or more meetings to inform the Federal permitting or licensing agency of the

preliminary decision to deny certification and to allow the Federal permitting or

licensing agency to make necessary modifications to the permit leading toward

certification, if possible. A denial of a water quality certification shall be made in

writing and shall include the following: identification of the decision as a denial

of certification; identification of the applicable Federal license or permit; a

statement explaining why the certifying authority cannot certify that the activity

will comply with water quality requirements, including but not limited to a

description of any missing water quality-related information if the denial is based

on insufficient information; and an indication that the Division complied with its

public notice procedures established pursuant to Clean Water Act section

401(a)(1).

(d) Waive. Waiver of the Tribe’s §401 water quality certification may occur, either

explicitly through notification by the Division to the Federal permitting or

licensing agency, or by the Division’s failure to take action on the certification

request within the time allowed by the Army Corps reasonable period of time. If

the Division fails or refuses to act on a certification request within the “reasonable

period of time” established by the Federal permitting or licensing agency and

Tribe or default reasonable period of time (which cannot exceed one year), the

certification requirement shall be waived with respect to the request for

certification. An express waiver shall be in writing and should include the

following: identification of the decision as an express waiver of certification;

identification of the applicable Federal license or permit; a statement that the

Division expressly waives its authority to act on the request for certification; and

an indication that the Division complied with its public notice procedures

established pursuant to Clean Water Act section 401(a)(1).

(4)

The certification shall be delivered via electronic mail to the Federal permitting or

licensing agency. The notice shall advise the Federal permitting or licensing agency of the

appeal rights and procedures provided in these procedures.

(5)

Any water quality certification approved by the Division shall be made in writing,

signed by the Division Head, and include:

(a) The name and address of the Federal permitting or licensing agency;

(b) Findings that projects covered under the permit will not cause or contribute to a

7

violation of applicable Federal or tribal water quality standards or any other

appropriate requirements of tribal law relating to water quality;

(c) Conditions that the Division deems necessary to ensure that projects covered under

the permit will not cause or contribute to a violation of applicable Federal or tribal

water quality standards or other appropriate tribal requirements relating to water

quality. Such conditions may include but are not limited to restrictions on effluent

discharge, effluent monitoring and reporting, minimum flow requirements, consent

to tribal inspections, requirements for decommissioning or closure of the facility,

and a one-time or periodic fee sufficient to reimburse the Tribe for all costs, fees,

and expenses reasonably incurred to administer project compliance. Any one-time

or periodic fee imposed as a condition of certification will be limited to costs that

are necessary to assure compliance with project water quality requirements. Such

costs may include, but are not limited to: post-certification inspections, water

quality monitoring, laboratory analyses, review of compliance reports, and other

activities directly related to verifying and enforcing compliance with certification

conditions. Fees will not be imposed for activities that are not necessary to assure

compliance with water quality requirements. The Division will provide written

notice to the project proponent specifying the basis for any post-certification fee

and the activities it is intended to cover.

4-106. Certification requirements.

(1)

The following requirements shall apply to all certifications unless specifically

authorized by the 401 certification issued by the Division. The Tribe may, at its own

discretion, omit Section 4-106 conditions if the Permitting Agency has included requirements

in the draft permit equal to, or more stringent than, the Tribe’s listed conditions:

(a) A water quality certification shall require the Federal permitting or licensing

agency to notify the Division Head of all changes in the nationwide permit,

regional general permit, or general permit subsequent to certification.

(b) Except in the event of any changes in control or ownership of facilities as

contemplated in 4-106(d), a 401 certification for projects with coverage under a

nationwide permit, regional general permit, or general permit shall not be

transferrable without the prior written approval of the Division Head. A 401

certification may be transferred to a new owner or operator only if the certification

has been modified or revoked and reissued, or a minor modification made, to

identify the new owner or operator and incorporate such other requirements as

may be necessary under the CWA.

(c) Authorized representatives from the Division shall be permitted to enter upon the

site where the construction activity or operation of project with coverage under a

nationwide permit, regional general permit, or general permit is taking place for

purposes of inspection of compliance with BMPs and certification conditions.

8

(d) In the event of any changes in control or ownership of facilities, or where the

construction activity or operation of the project with coverage under a nationwide

permit, regional general permit, or general permit is taking place, the successor

shall be notified in writing by his predecessor of the existence of the BMPs and

certification conditions. The permittee shall provide a copy of such notification to

the Division.

(e) If the permittee with coverage under a nationwide, regional general permit, or

general permit discovers that certification conditions are not being implemented as

designed, or are not operating or functioning as designed, or if there is an

exceedance of water quality standards despite compliance with the certification

conditions by the permittee, the permittee shall verbally notify the Division of

such failure or exceedance within two working days of becoming aware of the

same. Within ten working days of such notification, the permittee shall provide to

the Division, in writing, the following:

(f) In the case of the failure to comply with the certification conditions, a

description of (i) the nature of such failure, (ii) any reasons for such failure,

(iii) the period of non-compliance, and (iv) the measures to be taken to correct

such failure to comply; and

(g) In the case of the exceedance of water quality criteria, (i) an explanation, to the

extent known after reasonable investigation, of the relationship between the

project and the exceedance, (ii) the identity of any other known contributions to

the exceedance, and (iii) a proposal to modify the certification conditions so as to

remedy the contribution of the project to the exceedance.

(h) Any anticipated change in discharge location, quantities, or composition

associated with the project must be reported to the Division by submission of a

written notice by the permittee no less than ten days before the change. If the

change is determined to be significant, the permittee will be notified within ten

days, and the change will be acknowledged and approved or disapproved.

(i) Any diversion from or bypass of facilities necessary to maintain compliance with

the terms and conditions herein is prohibited, except (i) where unavoidable to

prevent loss of life or severe property damage, or (ii) where excessive storm

drainage or runoff would damage any facilities necessary for compliance with

limitations and prohibitions herein. The Division shall be notified immediately in

writing of each such diversion or bypass.

(j) At least 5 days before commencement of a project in a watercourse, which the

Division has certified, or conditionally certified, the permittee shall notify the

Division.

(k) Immediately upon discovery of any spill or other discharge to waters of the

United States not authorized by the applicable license or permit, the permittee

shall notify the Division.

9

(l) Construction operations within watercourses and water bodies shall be restricted

to only those project areas specified in the Federal license or permit.

(m) No construction equipment shall be operated below the existing water surface.

(n) Work should be carried out diligently and completed as soon as practicable. To

the maximum extent practicable, discharges of dredged or fill material shall be

restricted to those periods when impacts to designated uses are minimal.

(o) The project shall incorporate provisions for operation, maintenance, and

replacement of BMPs to assure compliance with the conditions identified in this

section, and any other conditions placed in the permit or certification. All such

provisions shall be identified and complied with in an operation and maintenance

plan which will be retained by the project owner and available for inspection

within a reasonable timeframe upon request by any authorized representative of

the Division.

(p) The use of chemicals during construction and operation shall be in accordance

with the manufacturers’ specifications. There shall be no excess application and

introduction of chemicals into waters of the United States.

(q) All solids, sludges, dredged or stockpiled materials and all fuels, lubricants, or

other toxic materials shall be controlled in a manner so as to prevent such

materials from entering waters of the United States.

(r) All seed, mulching material and straw used in the project shall be certified weedfree.

(s) Discharges of dredged or fill material in excess of the permit associated with the

water quality certification are not permitted.

(t) Discharges to waters of the United States not identified in the license or permit

and not certified in accordance therewith are not allowed.

(u) No discharge shall be allowed which causes non-attainment of Tribal narrative

water quality or biological criteria.

(v) Before any equipment touches the water, the project proponent must provide to

the Division (i) a certification that (a) the equipment has not been used in waters

with the possibility of aquatic nuisance species infestation and (b) the equipment

has been thoroughly decontaminated using water that is heated to a temperature

necessary to kill aquatic nuisance species, (ii) evidence that the equipment has

passed a Colorado Parks and Wildlife invasive species inspection, or (iii) a

certification in a form that is acceptable to the Division, signed by a third-party

consultant, certifying that the equipment has undergone a waters of the United

States-specific preventative decontamination using water that is heated to a

10

temperature necessary to kill aquatic nuisance species.

(2)

Best Management Practices.

(a) BMPs are required for all projects for which Division certification is issued except

for Section 402 permits. Project proponents must select and propose BMPs to the

Division to be employed in their project. For Section 404 projects, information

supporting common BMPs is provided within our Stormwater Pollution Prevention

Guidelines for Construction and Remediation Activities on Tribal Lands document

posted on EPD’s 401 certification webpage: https://www.southernutensn.gov/government/departments/epd/water-quality/401-certification/.

(b) All certification requests which require BMPs shall include a map of project

location, a site plan, and a listing of the selected BMPs chosen for the project. At

a minimum, each project must provide for the following:

i.

Temporary erosion and sediment control measures that shall be

coordinated with permanent measures to assure economical,

effective, and continuous control throughout the construction phase

and during the operation of the project

ii.

Permanent erosion and sediment control measures that shall be

installed at the earliest practicable time consistent with good

construction practices and that shall be maintained and replaced as

necessary throughout the life of the project.

ARTICLE 5. PRE-OPERATION INSPECTION.

5-101. Inspection opportunity.

In accordance with Clean Water Act section 401(a)(4) (codified at 33 U.S.C. §

1341(a)(4)), for certified Federally licensed or permitted activities or facilities that do not

require a Federal operating license to assure its operation will not violate water quality

requirements, the Federal permitting or licensing agency must afford the Division an

opportunity to inspect the activity or facility for the purpose of determining whether activity or

facility will violate applicable water quality requirements.

5-102. Notice that certified project will violate the certification.

If the Division, after an inspection pursuant to section 5-101, determines that the

discharge from the certified project will violate the certification, the Division will notify the

Federal permitting or licensing agency and the Federal licensing or permitting agency in writing,

and recommend remedial measures necessary to bring the certified project into compliance with

the certification.

ARTICLE 6. IMPLEMENTATION AND ENFORCEMENT OF CERTIFICATIONS.

(1)

Upon receipt of information that water quality requirements are not being met as a

11

consequence of a project’s construction or operation, the Division, after consultation with the

permittee and notification of the Federal permitting or licensing agency, may ask the Federal

permitting or licensing agency to take enforcement action.

(2)

Upon receipt of information indicating that one or more certification conditions

have not been complied with during the construction or operation of a project, the Division shall

notify the Federal permitting or licensing agency in writing and request that necessary action be

taken to implement such conditions as contemplated in Sections 401(a)(5) and 401(d) of the

Federal Clean Water Act. A copy of any such notification and request shall be sent to the

permittee. The Division shall remain in communication with the Federal permitting or licensing

agency and the permittee regarding the progress towards implementation of the conditions until

satisfactory compliance has been obtained, or until the Federal agency has completed

enforcement action.

(3)

If necessary and if authorized under Tribal law, the Division may take action

to enforce its certifications or certification conditions in Southern Ute Indian Tribal Court or

another court of competent jurisdiction.

ARTICLE 7. JUDICIAL REVIEW.

Within 30 days of a Division decision to grant, grant with conditions, deny a water

quality certification, or waive certification, any person aggrieved by the decision may seek

judicial review in the Southern Ute Indian Tribal Court. The review shall be on the record

without taking additional evidence. If the court finds that the Division exceeded its authority,

made an erroneous interpretation of the law, acted in an arbitrary and capricious manner, or

made a determination which is unsupported by the evidence in the record, the court may reverse

or modify the Division’s decision or action. Otherwise, the decision of the Division shall be

affirmed. Upon request by the court, the Division shall provide the court with a certified copy of

all documents, records, transcripts, or other information which formed the basis for any decision

or action for which an aggrieved party seeks judicial review.

12

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.