Standard Stipulations

for Preliminary Applications and Design Review Applications

Planning Services Division:

General:

1. The developer shall revise plans incorporating the approved Design Review Committee (DRC)

stipulations prior to submitting construction documents to SRPMIC Engineering and Construction

Services (ECS) Compliance Division.

2. This Preliminary Application Review is based on the current version of the Community Zoning

Ordinance, SRO-467-2015. The Planning Services Division is drafting a new version of the Zoning

Ordinance that is currently projected to be adopted in the fall of 2025, dependent on approval by the

Community Council. All applications received after the new ordinance's adoption will be assessed

according to its provisions. Please note that the comments in this letter may not necessarily be

applicable under the new ordinance. Projects that have received Design Review approval will remain

valid, provided that the application for a construction permit is submitted within two (2) years from the

date of Design Review approval.

3. Underground stormwater storage facilities require approval from the SRPMIC Floodplain

Administrator. Such approval shall occur before a construction permit is issued for the project.

Changes to the site plan as a result of final underground storage facility design may require a

Design Review process.

4. Any substitution of exterior materials shall be approved through a Design Review process. Such

materials include exterior building materials, walkways, pedestrian crosswalks, shade structures, art

work, landscaping, hardscape elements, and any other design related items.

5. If a project requires a cross-access agreement(s), developer shall record agreement with Maricopa

County.

a. First, a draft of the agreement (ex: cross access to adjacent or landlocked property) shall be

submitted to SRPMIC to be reviewed and approved prior to submitting to Maricopa County for

recordation.

b. Once the agreement is approved, it shall be recorded with Maricopa County.

6. Developers are required to document “land rights” for all new utility services in accordance with 25

CFR 169. Should you have any questions, contact Adrianne Smith (ECS Rights of Way Supervisor)

at 480-362-5489 or Aaronn Mattingly (ECS Design Division Manager) at 480-362-5708.

a. Normally, these land rights will be documented on Service Line Agreements (SLA) that are

“executed” between the various utility providers (e.g. SRP, Saddleback, SW Gas, etc.) and

Revised 10/28/2025

Page 1

the Authorized Occupant and “filed” with the Bureau of Indian Affairs through the

Community’s ROW Section and should never cross master lease boundaries.

b. Developers are authorized to coordinate with the utility providers directly to obtain “will serve”

letters and to begin the design process; however, they should realize that no utility provider

will “energize” without the land rights being properly executed and filed with the Community.

c. All wet and dry utilities shall be shown on the construction documents prior to a construction

permit being issued by the SRPMIC Engineering and Construction Services (ECS)

Compliance Division. If not, a separate permit application will be required. Any customerprovided trench (CUPT) must be shown on the Civil Plan or Utility Plan, and shall include

trench details, sleeve diameter, backfill requirements, etc. The utility provider (e.g. Salt River

Project, SW Gas, Saddleback, etc.) will be required to submit their own permit application to

tie-into the public right-of-way, set meter(s), and energize.

d. In coordination with the utility providers, the Developer may be required to provide a map of

definite location. Said legal plat must show the boundary of the allotted or tribal parcel(s), the

master lease boundary, point of connection at the nearest distribution line, the new point of

delivery, and the as-built alignment of the new electric, tele/data, and/or natural gas service

lines using survey precision (bearing and distance callouts).

7. All new projects require a project address. To obtain an address, contact the assigned project

planner. You will be asked to submit a site plan with building the footprints. The Site plan shall be

submitted in both PDF and a georeferenced, AutoCAD (.DWG) file formats. The .DWG file shall be

“Assigned” to the NAD 1983 Arizona State Plane Central International Feet Coordinate System. You

may contact the GIS Addressing Team at 480-362-7900 with questions.

8. Contact Maleena Deer in the Community Development Department, Discover Salt River to obtain a

list of Community Member artists for developing cultural references for use by the developer and

architects in designing the cultural aspects of the development. Email: Maleena.Deer@SRPMICnsn.gov, Telephone: 480-362-6925

9. All projects will require submittal of a legal description that follows the SRPMIC Survey Guidance to

Satisfy Recordation Requirements within the SRPMIC and the Trust Asset and Accounting

Management System (TAAMS) System of Record for Trust Lands and all land surveys conducted

after 8/12/2020. Here’s the link to the Survey Guidance: https://www.srpmic-nsn.gov/wpcontent/uploads/2024/10/20241001_SRPMIC_SurveyGuidance_v05.pdf

10. Employment Preference Program*:

a. For Preliminary Applications: Prior to submitting the Design Review application, the Human

Resources or owner authorized representative of the business or businesses that will occupy

the new development (or if none is known, the developer/owner of the project) is required to

contact Mr. Seneca Peters, SRPMIC Human Resources Department’s Community

Employment Compliance Coordinator regarding the Community’s Employment Preference

Program. His telephone number is 480-362-6642 and his email address is

Seneca.Peters@SRPMIC-nsn.gov.

b. For Design Review Applications: Applicant shall submit information that the Human

Resources director or owner authorized representative of the business or businesses that will

occupy the new development (or if none is known, the developer/owner of the project) has

contacted Mr. Seneca Peters, SRPMIC Human Resources Department’s Community

Employment Compliance Coordinator regarding the Community’s Employment Preference

Program prior to building permit issuance. His telephone number is 480-362-6642 and his

email address is Seneca.Peters@SRPMIC-nsn.gov.

c. For Design Review Approval: As the identified Representative and point of contact for this

project; you are obligated to notify the SRPMIC- HR Employment Compliance Office (contact

Revised 10/28/2025

Page 2

info below) when the project is awarded to the contractor; failure to notify the SRPMIC- HR

Office will only hinder the contractors ability to start the project as scheduled:

Mr. Seneca Peters

SRPMIC Employment Compliance Coordinator

(O) 480-362-6642

(M) 480-791-3942

(E) Seneca.Peters@srpmic-nsn.gov

*Provide written documentation that you have made contact with the Employment Compliance

Coordinator with your formal Design Review application submittal.

11. Seasonal outdoor sales are subject to a Special Use Permit. Contact SRPMIC CDD Planning

Services Division (PSD) at 480-362-7600 to obtain a Special Use Permit.

12. Signage requires a separate approval process. Signage is subject to review under Article 6.7 of the

SRPMIC Zoning Ordinance. Contact SRPMIC ECS Compliance Division at 480-362-7738 to obtain a

Sign Permit Application.

13. Applicant/developer has sole responsibility for identifying and securing location for any construction

staging needs.

14. Impact fees:

a. Instructions for Preliminary Applications: SRPMIC requires payment of development impact

fees prior to issuance of a building permit for this project. Development impact fees paid are

based on fee rates in effect at the time of building permit issuance. Contact Richard

McAllister, Principal Planner at 480-360-7655 or Noah Katt, Planner II at 480-362-3269 with

SRPMIC CDD Planning Services Division to obtain the required forms or for any questions.

i. Step 1: Submit a completed Non-Binding Fee Form and Fee Calculation Form with

your Design Review application. These forms will be reviewed for accuracy and

completeness, and any errors or anomalies will be discussed at this time to ensure

that the parties understand the fee and how the fee is calculated.

ii. Step 2: Submit the completed final Development Fee Calculation Form and the Fee

Calculation form to the CDD Planning Division at least three (3) weeks prior to the

time of building permit issuance. The forms will be reviewed and processed for

invoicing the payer.

iii. Step 3: Receive the two (2) invoices from SRPMIC (one (1) for the impact fee and

one (1) for the administrative fee) and remit payment in two separate checks to the

Finance Department.

b. For Design Review Applications: With the approval of the Design Review application,

lessee/developer acknowledges that payment of development impact fees is required prior to

issuance of any building permit. Development impact fees paid are based on fee rates in

effect at the time of building permit issuance. Contact Richard McAllister, Principal Planner at

480-360-7655 or Noah Katt, Planner II at 480-362-3269 with SRPMIC CDD Planning Services

Division for fee rates and calculation forms prior to submittal of construction documents for

building review. We recommend that you submit the completed forms (Development Fee

Calculation Form and the Fee Calculation Form) at least 3 weeks prior to the time of building

permit issuance.

Cultural

15. Development should be designed with careful consideration of the Community’s physical context and

shall incorporate aspects of the Community’s cultural values into the design principles and

characteristics as illustrated in the Design Standards and Guidelines (Article 6.4). For example,

consider integrating the lower Sonoran vegetation (i.e. saguaro, chollas, ocotillo, etc.); mountains (i.e.

Revised 10/28/2025

Page 3

color, shape), rivers and arroyo’s (i.e. water, sedimentation, rocks, shape); animals (i.e. coyotes,

eagles, desert hares); traditional art (i.e. Pima basketry, Maricopa pottery); and traditional

practices/methods (i.e. outdoor living/gathering, farming). Apply the following design elements into

the development’s design for optimal cultural expression and representation:

a. Take solar conditions into consideration when designing buildings. Provide shading on all

east, south and west facing windows. For example, a combination of shade canopies,

recessed windows, building fins, pop outs, large overhangs, and other building design

elements may be used. The shading over windows and building entries should be a

significant design element of the buildings. Consider placing outdoor seating, entrances and

windows on north side of buildings and minimizing these on other elevations. Consider

applying shade devices that resemble historic Pima and/or Maricopa shade structures and

have an organic appearance (e.g., irregular placement or sizing of beams/posts.

b. Design entry areas with a welcoming sense of entry. Create this through human scaled, wellshaded entries, attractive landscaping, seating, art, etc. Pay particular attention to

landscaping, pedestrian amenities, shaded entry features, etc.

c. Colors should be earthen tone with an incorporation of various textures, accents, colors and

materials. Introduction of new colors is strongly encouraged, and shall be complementary to

earthen color palette.

d. Building materials should incorporate various textures. Generally, textured materials are

preferred over smooth and natural materials are preferred over engineered.

e. Building exteriors may resemble exteriors of historical Pima and/or Maricopa structures,

environmental elements and geographic/land forms. Historic structures were typically very

organic in form and simple. This may be achieved through application of organic, rough and

earthen textures to exterior. Smooth and sharp edges and planes are not encouraged.

f. Shading devices may resemble historic Pima and/or Maricopa shade structures. Designs

shall be more organic in form whether attached above windows or ground structures (i.e.

offset the overhead beams shall be narrow spaced for function, irregular placement and

shape of beams and posts for natural appearance, and appropriate natural color and

textures).

g. You may incorporate use of Pima basketry or Maricopa pottery onto the exterior elevation.

Incorporation of these elements shall be done in a subtle, respectful, architectural and artistic

application. Elements shall not be stamped on.

h. Large-scale buildings should incorporate all of these principles into the building expression.

Design shall also pay particular attention to using any cultural design element to break up an

expansive wall plane and minimizing the appearance of the building.

i. Suggest incorporating cultural hardscape features (i.e. stamping or pavement design/color) at

building entry area and outdoor patio area. Materials are to be compliant with the American

with Disabilities Act (ADA).

j. The Design Review application requires submittal of a ‘Cultural Board’. This is an exhibit that

explicitly illustrates what cultural elements have been included in development design, the

meaning of them and the inspiration behind them.

16. The owner, authorized representative and/or Marketing Division of the company that will occupy the

building/project must contact the Community Development Department, Discover Salt River Division

at 480-362-6925 or by emailing Maleena.Deer@SRPMIC-nsn.gov to get information about the

Community’s commercial development areas. Provide the date, means of contact, and who you

contacted at Discover Salt River with the Design Review application submittal.

Site:

17. Detention/retention basin design shall have a natural contour and appearance by utilizing curvilinear

shapes and by varying distances between topographical lines.

Revised 10/28/2025

Page 4

Pedestrian Circulation:

18. Pedestrian sidewalks and pathways shall be treated with a variation of Pima and/or Maricopa

culturally-relevant material, colors, patterns and textures.

19. All key pedestrian crossings at entrances and exits shall meet the requirements of the ADA.

Screening:

20. All rooftop mechanical units, pipes and other appurtenances shall be painted to match the building

roof color.

21. All roof mounted equipment shall be screened by parapet or wall that matches the architectural color

and finish of the building. Height of the screening shall extend at least to the top of the equipment.

22. Ground-mounted mechanical equipment shall be fully screened from view (from streets, public areas

and adjacent sites) by a combination of decorative walls and/ or landscape exceeding the height of

the equipment. If a screen wall is used, the wall shall be at least 1-foot higher than the tallest unit.

23. Ground-mounted electrical equipment including transformers shall not be placed within twenty (20)

feet of a street or street intersection.

24. Ground-mounted equipment shall be screened with appropriate walls, landscaping and/or berms.

25. All backflow prevention devices two (2) inches or larger shall be screened with landscaping located

within a six (6) feet radius of the device. All backflow preventers less than two (2) inches shall be

placed in a wire cage painted to match the primary building color.

26. All backflow prevention devices shall be located away from the building base area and shall be

placed within an open space area away from the building.

27. All bollards surrounding ground units (i.e. transformers, backflow preventions devices, FDCs,

hydrants, etc.) shall be painted to match the building color.

Landscaping:

28. All landscaping within the project site shall be planted with low water use, primarily indigenous

Sonoran desert plant material.

29. Do not use Chilean Mesquite (Prosopis chilensis) and Mexican Palo Verde (Parkinsonia aculeate).

Both tree are considered invasive species to indigenous plant material.

30. Spiny plant material shall be located at least three (3) feet away from a pedestrian walkway.

31. Plant material shall not be severely pruned such that the natural growth pattern or characteristic form

is significantly altered unless it is required for safety of pedestrians or to remove obstructions from

signage and lighting.

32. Developer shall be responsible for installation of all irrigation and landscaping along property

frontage, behind curb or edge of pavement within the adjacent right of way.

33. All new and existing landscaping behind curb or edge of pavement shall be irrigated and kept in live

condition. Landscaping and irrigation systems shall be reasonably maintained in accordance with the

Revised 10/28/2025

Page 5

approved landscape plan. Such landscaped areas shall be kept free of trash, debris, weeds, and

dead plant material, and shall in all respects be maintained in a neat and clean condition.

34. Any improvements installed as part of the approved landscape and irrigation plan that does not

survive, function properly or is in need of repair shall be replaced or repaired within thirty (30) days of

its demise or damage.

Lighting:

35. All freestanding light poles shall be located within landscaped areas or planter islands, concrete base

shall be painted to match the primary building color or finished to match the parking screen walls, and

be placed to avoid conflict with trees.

Refuse Enclosure:

36. All refuse enclosures shall include fully opaque screening gates, finished and painted to match the

enclosure. Screening gates shall not open into vehicular drive aisles.

37. All refuse enclosures shall permit space for an equally-sized recycling container.

38. Refuse enclosure design shall be consistent with building design incorporating use of color, material

and patterns.

Building Elevations:

39. Pneumatic tubes, whether metal or plastic, shall be routed underground or enclosed in pilasters,

columns or other architectural features of the canopy or building.

40. Commercial building downspouts shall be internalized.

Environmental Protection and Natural Resources (CDD/EPNR):

41. The applicant (lessee) shall comply with the National Environmental Policy Act (NEPA), the National

Historic Preservation Act (NHPA), the Archaeological Resources Protection Act (ARPA), and

applicable provisions of the Salt River Pima-Maricopa Indian Community Code of Ordinances. The

applicant (lessee) must receive a CDD/EPNR Memorandum clearly stating “Archaeological

Monitoring Required” or “Archaeological Monitoring Not Required” before a construction permit can

be issued by the Community. Applicant shall submit a Request for Environmental Review (RER) to

CDD/EPNR as soon as the project limits and off-site requirements are fully understood. The

applicant may submit for a construction permit using the RER, however, no construction permit will

be issued until the CDD/EPNR Memorandum is completed. Call 480-362-7600 or email

epnr@srpmic-nsn.gov to request an RER form.

Recommend applicant clearly describe all related off-site ground disturbance in their RER, so that the

individual utility providers don’t have to submit their own RERs. For example, include trench location

for any off-site electrical, telephone, natural gas, water, sewer, etc. in your RER. An aerial photo

clearly depicting the area of potential effect, including ingress, egress, and laydown yards, must be

included with the RER. If the RER process has already been completed, include a copy of the

CDD/EPNR Memorandum in your Planning and construction permit applications.

42. Prior to any ground disturbance, including, but not limited to, driving on, clearing and grubbing or

grading, all construction personnel who will be engaged in ground-disturbing activities shall obtain

Revised 10/28/2025

Page 6

Cultural Sensitivity Training. Any individual employed by an establishment operating on tribal lands

who holds an upper management position (including supervisors and corporate office staff) is also

required to complete our CST. The class is online and can be accessed at

https://www.research.net/r/SRPMIC_CST. CST is completed on an individual basis and requires

access to YouTube. Once the training and accompanying test are successfully completed, the results

will be entered into our database within 24–48 hours (please note this may take longer if completed

on a weekend or tribal holiday). After the record is received, the following will occur:

• Add the individual to our SharePoint system, and

• Create a decal that must be carried when conducting official business within the boundaries of

the Community.

Once the decal is ready, it will be mailed to the address provided during the training process. If there

are any issues or questions at any point, call 480-362-7600 with questions. Non-Tribal Government

employees are certified for 3 years from the date of successful completion. Tribal Government

employees are certified for 5 years from the date of successful completion.

43. Cultural resources, natural resources, and hazardous materials encountered during construction or

project activity shall cause work to cease at that location immediately and the CDD/EPNR Division

shall be notified immediately at 480-362-7600.

44. Construction waste reduction and recycling efforts shall be addressed and incorporated in all

applicable plans. Certain construction and demolition waste materials may need to be disposed of in

specialized landfills. Call CDD/EPNR at 480-362-7600 for more information.

45. All non-hazardous, solid waste generated during and after construction is required to be taken to the

Salt River Landfill utilizing SRPMIC Public Works Department bins or vehicles. Any wastes that the

Salt River Landfill will not accept shall be disposed of in accordance with federal regulations. Call to

CDD/EPNR at 480-362-7600 for more information. The SRPMIC Public Works Department shall

advise the developer of any restrictions imposed by the landfill operations. If you have any

questions, please contact the SRPMIC Public Works Department at 480-362-5600.

46. Hazardous material or waste spills shall be reported to CDD/EPNR immediately at 480-362-7600 and

these wastes shall be cleaned up and disposed of properly pursuant to CDD/EPNR direction.

47. Open burning is not allowed.

48. A Storm Water - Construction General Permit shall be obtained from EPA Region 9. Submit one

electronic copy of the Notice of Intent (NOI) and Storm Water Pollution Prevention Plan (SWPPP) to

CDD/EPNR at epnr@srpmic-nsn.gov.

49. An approved Dust Control Plan (DCP) for all ground-disturbing activities (>0.1 acre) shall be in place

prior to construction. Contact CDD/EPNR at 480-362-7600 or epnr@srpmic-nsn.gov to request dust

control planning documents.

50. The owner and/or operator shall prevent and control track out, carry-out, spillage, and/or erosion of

dirt and other materials. Fugitive dust control measures are required for all work sites, as follows:

a. At all exits onto paved areas accessible to the public, install a Gravel Pad.

b. At all exits onto paved areas accessible to the public, install a Grizzly or rumble grate that

consists of raised dividers (rail, pipes, or grates) a minimum of three inches tall, six (6) inches

apart, and twenty (20) feet long, to allow a vibration to be produced such that the dust is

shaken off the wheels of a vehicle as the entire circumference of each wheel of the vehicle

passes over the Grizzly or rumble gate; and

Revised 10/28/2025

Page 7

c. Pave starting from the point of intersection with a paved area accessible to the public and

extending for a centerline distance of at least 100 feet and a width of at least twenty (20) feet.

d. Criterion for Clean Up of Track out: Clean up, track out, carry-out, spillage, and/or erosion

from paved areas accessible to the public including curbs, gutters, and sidewalks, on the

following as needed.

i. No person shall allow track-out to extend twenty-five (25) linear feet or more in

cumulative length from the point of origin from an active operation. Notwithstanding

the preceding, all track-out from an active operation shall be removed at the

conclusion of each workday or evening shift.

ii. Operate a street sweeper as necessary or wet broom with sufficient water, including

but not limited to kick broom, steel bristle broom, Teflon broom, or vacuum, at the

speed recommended by the manufacturer.

e. Soil Moisture: If water is the chosen control measure in the submitted Dust Control Plan, the

owner and/or operator of a dust-generating operation shall operate a water application system

on-site (e.g., water truck, water hose) while conducting any earth-moving operations on

disturbed surface areas 0.1 acre or larger, unless a visible crust is maintained or the soil is

sufficiently damp to prevent loose grains of soil from becoming dislodged.

Fire Department:

51. Developers and subcontractors shall follow applicable standards from the National Fire Protection

Association (NFPA 13 Sprinkler, NFPA 72 Fire Alarm, etc.), the 2021 Edition of the International Fire

Code, 2021 NFPA 101 Life Safety Code and the 2023 SRPMIC Fire Code Amendments.

52. In buildings exceeding 10,000 square feet in area per story, Class I automatic wet standpipes shall

be provided and where any portion of the building’s interior area is more than 200 feet of travel,

vertically and horizontally, from the nearest point of fire department vehicle access. Reference SRFD

IFC 905.3.1.1

a. Exceptions:

i. Single story structures are not required to have hose connections, except in those

interior portions of the building that exceed 200 feet of travel from an emergency

access road.

ii. Required wet standpipes may be an integral part of an approved sprinkler system and

may be connected to the sprinkler systems horizontal cross-mains. Calculations for

required hose demand shall be submitted with sprinkler plans.

53. 901.4.6.1 Fire riser room. All fire riser rooms shall have exterior access doors, with Knox box on the

exterior, and all NFPA signage. The fire alarm control panel (FACP) shall be located in the fire riser

room. Reference SRFD IFC 901.84.6.1.

54. All fire hose threads used in conjunction with automatic sprinkler system shall be National Hose

Thread (NHT). Reference SRFD IFC 903.3.6.

55. Fire department connections shall be located at a corner of the building being protected, within four

(4) feet to eight (8) feet of the curb line of an access road or public street, forty (40) feet or one and

one half times the height of the building being protected, whichever is less, or as approved by the fire

code official. The fire department connection line shall be a wet line with the check valve at the hose

connection above grade. The access to the fire department connection shall be at curb grade.

Reference SRFD IFC 912.2

56. Fire department connections (FDC) for all occupancies shall be within 100 feet to a fire hydrant. All

FDC connections shall be 4 inch Storz connections with KNOX locks installed. All FDC connections

Revised 10/28/2025

Page 8

shall be properly signed with address and name of business. In Group H Occupancies, the distance

shall be a minimum of 150 feet but not more than 200 feet. Reference SRFD IFC 903.3.7.

57. All fire alarm and occupant notification system plans submitted for review and approval shall bear a

review certification of a minimum level III NICET (National Institute for the Certification of Engineering

Technologies) in Fire Alarms. Reference SRFD IFC 907.1.2

58. A minimum of one temporary fire department access roadway shall be installed prior to and during

construction of every facility, building or portion of a building and maintain a roadway sixteen (16) feet

wide, with minimum four (4) inch thickness of aggregate base course or decomposed granite

compacted to a 90% density where natural soil will not meet compaction requirements. The

temporary fire department access roadway shall be constructed as to allow fire department personnel

access to the entire perimeter of the entire construction site from the public roadway. Reference

SRFD IFC 503.1.1

59. Fire apparatus access roads shall have an unobstructed width of not less than 26 feet, except for

approved security gates in accordance with section 503.6, and an unobstructed vertical clearance of

not less than 20 feet. SRFD IFC 503.2.1.

60. Fire apparatus access roads shall be designed and maintained to support a minimum 90,000 pound

gross vehicle weight and shall be surfaced so as to provide all-weather driving capabilities, minimum

three (3) inches of AC over 6 inches of ABC. Reference SRFD IFC 503.1.2.

61. The required turning radius of a fire apparatus access road shall be a minimum turning radius of 35

feet inside and 61 feet outside for the required fire apparatus access road. Reference SRFD IFC

503.2.4.

62. All access roads, whether temporary or permanent, shall not exceed six percent (6%). Reference

SRFD IFC 503.2.7.

63. For fire hydrants, a clearance of eighteen (18) inches from center of four (4) inch steamer connection

(pumper outlet) to final grade shall be maintained. Connection shall face towards fire lane or

roadway. Reference NFPA 24, 7.3.3.

64. Fire hydrants shall be placed to ensure that the distance to fire department connections shall not

exceed 100 feet. Reference SRFD IFC 507.5.7.

65. Fire department apparatus access to roof. For buildings two (2) or more stories in height, maintain a

minimum of a 50 by 50 foot flat area at grade at two corners of the building for fire department

operations and apparatus placement. This 50 by 50 foot flat area shall not impede the twenty-six (26)

feet fire lane. Reference SRFD IFC 504.4.

66. All commercial buildings with limited communication penetration shall have a communication wrap

included. SRFD/SRPD radio communications as of 2014 are 700/800 MHz VHF. SRFD will provide

all data and specifications for the communication plan. (Either a DBA or DAS system shall be

installed.)

Engineering & Construction Services:

67. Construction design shall conform to the 2021 International Codes (Building, Mechanical, Plumbing,

Energy Conservation and Fire), the 2010 ADA Standards for Accessible Design, the 2009 ANSI

A117.1, the 2020 National Electrical Code, and the latest revision of MAG Uniform Standard

Revised 10/28/2025

Page 9

Specifications. Starting January 1, 2024, all design shall be in compliance with the 2023 Building and

Fire Code Amendments to the 2021 ICC Building and Fire Codes (https://www.srpmicnsn.gov/government/ecs/construction-compliance/). If you have any questions regarding these

codes and standards, please contact Stanimira Todorova, SRPMIC Engineering and Construction

Services (ECS) Compliance Division Manager at 480-362-6604.

68. All construction improvement plans within the public right-of-way easements shall conform to the

Community’s 2018 Supplement to Maricopa Association of Governments (MAG) Uniform Standard

Specifications and Details for Public Works Construction and the 2018 Construction Note Details. If

you have any questions regarding these references, please contact Stanimira Todorova, SRPMIC

Engineering & Construction Services at 480-362-6604 or Richard Alvarado, Public Works at 480-3625477.

69. The applicant shall submit a final Grading and Drainage Plan to SRPMIC ECS Department for

review and approval. The design storm is the 100-year, 2-hour event (P = Precipitation amount

from the 100-year 2-hour duration rainfall for specific project location. Use the isopluvial from the

FCDMC Drainage Design Manual).

70. The applicant shall meet the first flush water quality criteria as required by the Environmental

Protection Agency (EPA).

71. Grading and drainage plan shall show outfall locations and elevations for the existing and proposed

improvements.

72. The maximum depth of ponded water within any parking lot location shall be six (6) inches with the

deeper portions confined to remote areas of the parking lot.

73. High water elevations shall be clearly delineated for all retention/detention basins.

74. Basin side slopes shall not exceed a 4:1 maximum slope.

75. The applicant shall show existing drainage patterns for the project site on the grading plan.

76. The design of all storm water facilities shall ensure that the stored runoff shall be emptied

completely from the facility within 36 hours after the runoff event has ended by infiltration, controlled

bleed off, dry well or discharge pump to an approved facility. All dry wells to be Max Well Plus® or

equal. The applicant shall indicate the method of dissipation and percolation test data to support

compliance with the above. Minimum accepted dissipation rate is 0.1cfs per drywell.

77. Discharges shall be in compliance with 40 CFR 122, the National Pollution Discharge Elimination

System (NPDES).

78. Any underground storage facilities shall require approval from the SRPMIC Floodplain

Administrator. Contact CDD/Environmental Protection and Natural Resources at 480-362-7500.

Note: If underground storage facilities are located in or near the fire access lane(s), or in the 50 foot

x 50 foot clear area(s); then the design for the loading described in item #52 above applies.

79. The applicant shall provide storm water detention/retention for run-off from the half street fronting or

abutting the proposed development.

80. If detention is provided for the project, post-development peak discharges shall not exceed predevelopment peak discharges for the 2, 10, and 100-year storm events.

Revised 10/28/2025

Page 10

81. Any basins located within ten feet of the right-of-way shall comply with the following requirements:

a. The maximum depth of the basin within ten (10) feet shall be 18-inches, and between ten

(10) feet and twenty (20) feet shall be twenty-four (24) inches.

b. The basin side slope shall not begin any closer than two (2) feet from the edge of the

sidewalk.

c. Basins in excess of 0.5 acre-ft design storage and over three (3) feet in depth shall

incorporate benches no narrower than ten feet (level bench width) for at least 40% of the

circumference of the basin. The bench shall be at least two (2) feet higher than the basin

bottom.

d. Basins shall have a maximum water depth of three (3) feet to accommodate the 100-year, 2hour storm event.

e. Public safety requirements (fences, railing, etc.) shall be installed as needed to limit public

access to the basins.

82. Provide the SRPMIC Engineering and Construction Services Department with final as-builts for the

legal description/survey, site plan, floor plan, building elevations, lighting plan, and service utilities

prior to issuance of a Certificate of Occupancy. Legal survey will include not only the acreage of the

overall subject area, but also a breakout of acreage and square footage by individual Salt River

allotment. Said plans shall be submitted in .PDF format and AutoCad (.DWG), based on the Salt

River Coordinate System, or alternatively the NAD 1983 Arizona State Plane Central International

Feet Coordinate System. All legal plats must comply with the Arizona Boundary Survey Minimum

Standards as defined by the Arizona Board of Technical Registration (AZBTR) and the Arizona

Professional Land Surveyors Association (APLS). A copy of those standards can be found here:

https://btr.az.gov/laws-standards/standards/land-surveyors . Contact Kevin Womble, SRPMIC ECS

Senior Surveyor with any questions related to Community, BLM, or GLO monuments and boundary

information at kevin.womble@srpmic-nsn.gov or 480-362-7803.

83. Horizontal / Vertical Datum. Use the following with regard to horizontal and vertical datum for all

site/civil and topographic work.

a. Horizontal: Community Project Datum (CPD) is based on the Arizona Coordinate System

(ACS) (1983, Central Zone, US Survey Feet), where, XACS = (XCPD + 600,000) * 0.9998392

YACS = (YCPD + 350,000) * 0.9998392

b. Vertical: North American Vertical Datum of 1929 (NAVD 1929).

Information Technology (Internal Public Projects Only)

84. The following is abbreviated information that will help determine if a Distributed Antenna Systems

(DAS) / Bi-Directional Amplification Systems (BDA) is required to provide the minimum standards of

in-building public safety communications within the SRPMIC. If after review of the following standards

it is determined a BDA/DAS is required, detailed guidelines will be provided by SRPMIC. A BDA/DAS

will be required for the following:

a. Buildings greater than 20,000 square feet

b. Existing buildings over 20,000 square feet when modifications, alterations or repairs exceed

fifty percent (50%) of the value of the existing building(s) and are made within any 12 month

period or the usable floor area is expanded or enlarged by more than fifty percent (50%)

c. Initial buildings under 20,000 square feet that are enlarged or exceed 20,000 shall be

upgraded.

Buildings that meet any of the above standards will be required to be tested for the following signal

strength levels as set forth in the SRPMIC detailed guidelines.

Revised 10/28/2025

Page 11

a. General areas: a minimum signal strength of (-95dBm) in 90% of the area of each floor of the

building or structure from both the SRPMIC Public Safety System and from within the building

or structure.

b. Critical areas: a minimum signal strength of -95dBm in 99% of areas deemed critical such as

the fire command center, the fire pump room(s), exit stairs, exit passageways, elevator

lobbies and other areas deemed critical by the AHJ.

Public Safety

85. Provide the Salt River Police Department and Salt River Fire Department with the Emergency

or Crisis Management and Operations Guidelines Manual for our public safety response (in the

event of a public safety emergency) for the project. Please contact Salt River Police

Department Chief Walter Holloway at 480-362-6313 for any questions.

86. Provide Salt River Police Department and Salt River Fire Department with detailed floor plans

of all new structures for our public safety response (in the event of a public safety emergency).

Please contact Salt River Police Department Chief Walter Holloway at SRPD at 480-362-6313

for any questions.

87. During the project construction, the contractor shall provide adequate fencing or barriers to protect

outsiders from entering the construction area, as approved by the Engineering and Construction

Services (ECS) Compliance Division.

88. During the building construction, the contractor shall provide adequate barriers or signage at and

around the construction site to warn motorists of the construction activities and any blockage of

sidewalks, shoulders and road lanes, as approved by the Engineering and Construction Services

(ECS) Compliance Division.

Public Works

89. SRPMIC Public Works Solid Waste Division is the exclusive commercial trash hauler for the

Community. For containers and information, contact Public Works Customer Service at 480362-5600.

90. All trash enclosures shall meet the following design and clearance requirements as allowed by

the SRPMIC Public Works Department. See page 15 through 22 of this document for

requirements. If you have any questions, regarding these requirements, contact Public Works

at 480-362-5600.

91. Native trees and cacti that are not salvageable for replanting shall be offered to the SRPMIC

Public Works Department for Community use before they are disposed of. Contact Eric Burke,

Cemetery Supervisor, at 480-278-7051 prior to clearing.

Human Resources – Employment Compliance Program

92. If you have any questions regarding this list of SRPMIC Employment Preference stipulations, please

contact Seneca Peters, Employment Compliance Coordinator of Human Resources Department’s

Community Employment Compliance Program. His telephone number is 480-362-6642 and his

email address is Seneca.Peters@SRPMIC-nsn.gov.

Revised 10/28/2025

Page 12

93. The Contractor and its Subcontractors (“employers”) shall use the Human Resources Department of

the Salt River Pima-Maricopa Indian Community as the ‘first source’ of referrals and placement of all

new employees to be hired to work in the Community. Employers are expected to hire as many

Community members and qualified Native Americans as possible in these new positions, with a goal

of at least 30% of the employer’s new work force comprised of qualified Community members and

other Native Americans. These requirements shall apply to skilled and non-skilled full time, part time,

temporary and permanent employees to include security, janitorial service and general labor.

94. The employer shall include the requirements of this section in their bid solicitation documents for the

Work they intend to subcontract.

95. Each employer shall contact Seneca Peters, Human Resources’ Community Employment

Compliance Program Coordinator at 480-362-6642 to obtain required reporting forms and additional

information.

96. The Employer shall fill their new job openings through their normal practices if the Human Resources

Department is unable to refer a qualified applicant within seventy-two hours (excluding weekends

and holidays recognized by the Community) of receiving a written referral request for a new position

opening. However, nothing in this paragraph shall release the employer from the goal of having at

least 30% of its new work force comprised of qualified Community members and other Native

Americans

97. The Human Resources Department Director is authorized to take the following actions when an

employer is found to be in non-compliance with these requirements:

a. Require the employer to adjust its actions, procedures or policies, as needed, to bring the

employer into compliance.

b. Recommend to the Community Manager suspension of a non-compliant employer’s

business operations until reasonable corrective action is taken or an acceptable plan of

corrective action is developed. Suspension shall not be imposed on any employer unless

approved by the Community Manager and the employer has been given three (3) working

days to correct the violation.

Environmental Health

98. Any food services to be a part of the proposed project will require a Health Permit. Please contact

Christopher Henke at 480-362-5706 for the review and permitting process.

Community Regulatory Agency

99. Any alcohol services to be part of the proposed project will be required to obtain two (2) separate

alcohol licenses from the Arizona Department of Liquor Control (ADLLC) and with the Community

Regulatory Agency Office of Alcohol Beverage Control (CRA-OABC) . Please contact CRA-OABC

at 480-362-5450 to start the licensing process.

Saddleback Communications

100. Saddleback Communications is the exclusive provider of the SRPMIC’s local telecommunications

services. Per Chapter 17, Section 17-5.1(b) of the SRPMIC Code of Ordinances it shall provide,

either through its own resources or by contract with other governmental or private entities, all

telecommunications services, including but not limited to telephone systems, wireless, voice data

Revised 10/28/2025

Page 13

services, the assignment and porting of telephone numbers, transport services and other

telecommunications facilities or services as may be established within the boundaries of the

SRPMIC.

101. For Phone and Internet service please contact Judy Young, Saddleback Sales Representative.

Direct: 480-362-7110. Email: jyoung@saddlebackcomm.com.

102. Wireless communications are necessary to ensure the safety of all tenants, visitors, first

responders, or members of the public that are on the premises. The developer is responsible for

ensuring that any building provides adequate internal wireless carrier coverage:

a. The ability to call 911 from any wireless device within the premises.

b. The ability to meet Next Generation 911 (NG911) requirements within the premises.

c. The ability of first responders to communicate from within the premises to outside entities.

103. The developer shall contact Engineering Wireless Services as a “Design & Review” provider of

such services to ensure the General Provisions of wireless communications are incorporated in the

buildings design and they meet the “General Compliance”. Please contact Saddleback

Communications Engineering at 480-362-7037 or engineering@saddlebackcomm.com:

a. For development telecommunications services, which will provide point of feed information

and conduit requirements. This information must be included on plans at time of submittal.

b. If a developer would like to explore opportunities for integrating wireless communications

facility into the project.

Revised 10/28/2025

Page 14

Attachment 1: Standards for Solid Waste Containers

Revised 10/28/2025

Page 15

Revised 10/28/2025

Page 16

Revised 10/28/2025

Page 17

Revised 10/28/2025

Page 18

Revised 10/28/2025

Page 19

Revised 10/28/2025

Page 20

Revised 10/28/2025

Page 21

Revised 10/28/2025

Page 22