WATER MAIN LOOP CONSTRUCTION

Tribal code

Ask Donna

What actually matters in this document.

Text

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

WATER MAIN LOOP CONSTRUCTION

PROJECT PO-21-N04

KOOTENAI INDIAN RESERVATION

BOUNDARY COUNTY, IDAHO

A COOPERATIVE PROJECT BETWEEN

THE INDIAN HEALTH SERVICE

AND

THE KOOTENAI TRIBE OF IDAHO

BID DOCUMENTS

CONTRACT # ______________

KOOTENAI TRIBAL COUNCIL

CONTRACT PACKAGE PREPARED FOR THE KOOTENAI TRIBE BY:

U.S. DEPARTMENT OF HEALTH AND HUMAN SERVICES

PUBLIC HEALTH SERVICE

INDIAN HEALTH SERVICE

OFFICE OF ENVIRONMENTAL HEALTH

AND ENGINEERING

PORTLAND AREA OFFICE

SPOKANE DISTRICT OFFICE

MARCH 2024

SECTION 00001 – CONTRACT TITLE PAGE

PAGE 1 OF 2

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

This page intentionally left blank

SECTION 00001 – CONTRACT TITLE PAGE

PAGE 2 OF 2

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

SECTION 00010

TABLE OF CONTENTS

Specifications Divisions 0 – Divisions 16

Contract Drawings

Division 0 – Bidding Requirements, Contract Documents and Conditions

Section 00001

Section 00010

Section 00100

Section 00110

Section 00400

Section 00410

Section 00450

Section 00500

Section 00510

Section 00550

Section 00610

Section 00620

Section 00630

Section 00700

Section 00705

Section 00810

Section 00930

Title Page

Table of Contents

Advertisement for Bids

Information for Bidders

Bid Offer Sheet

Bid Schedule

Indian Owned Qualification Statement

Agreement

Notice of Award

Notice to Proceed

Bid Bond

Payment Bond

Performance Bond

General Conditions

Special Provisions

Labor Provisions

Change Order Form

Division 1 – General Requirements

Section 011100

Section 012200

Section 013100

Section 013300

Section 014200

Section 014300

Section 015600

Section 016000

Section 017700

Section 017800

Summary of Work

Price and Payment

Project Management and Coordination

Submittal Procedures and Requirements

References

Quality Assurance

Temporary Facilities and Controls

Product Requirements

Closeout Procedures

Closeout Submittals

Division 3 – Concrete

Section 033000 – Cast-in-Place Concrete

SECTION 00010 - TABLE OF CONTENTS

PAGE 1 OF 2

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

Division 31 – Earthwork

Section 311100 – Clearing and Grubbing

Section 312200 – Grading

Section 312300 – Excavation and Fill

Section 312500 – Erosion and Sedimentation Controls

Division 32 – Exterior Improvements

Section 329219 – Seeding

Division 33 – Utilities

Section 331400 – Water Utility Transmission and Distribution

Section 331413 – Water Service Lines

Division 34 – Transportation

Section 340513 – Common Work Results for Roadways

END

SECTION 00010 - TABLE OF CONTENTS

PAGE 2 OF 2

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

SECTION 00100

ADVERTISEMENT FOR BIDS

Scope:

This project proposes the following:

• Construction of a new section of 6-inch PVC water main to loop the

existing community water distribution system, relocate an existing fire

hydrant, install a new one, and reconfigure valves to optimize water

movement in the Kootenai Indian Reservation.

Eligible Contractors shall bid on all items on the Bid Offer Sheet.

Contacts:

Contract information, including project specifications and drawings may be

obtained from:

Theresa Wheat

Administrative Director

Kootenai Tribe of Idaho

100 Circle Dr.

Bonners Ferry, ID 83805

Office: 208-267-3519

Cell: 208-255-0075

Email: theresa@kootenai.org

Performance Time:

120 Calendar Days

Liquidated Damages:

$100.00 per Calendar Day

SECTION 00100 – ADVERTISEMENT FOR BIDS

PAGE 1 OF 2

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

This page intentionally left blank

SECTION 00100 – ADVERTISEMENT FOR BIDS

PAGE 2 OF 2

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

SECTION 00110

INFORMATION FOR BIDDERS

BIDS will be received by the Tribe, at 100 Circle Dr. Bonners Ferry, ID 83805, until 1:30

PM PST on Tuesday, April 30th, 2024 and then at said office publicly opened and

read aloud.

Each BID must be submitted in a sealed envelope, addressed to:

Bid for Kootenai Community Water Main Loop Construction Sanitation

Facilities

Theresa Wheat

Administrative Director

Kootenai Tribe of Idaho

100 Circle Dr.

Bonners Ferry, ID 83805

Each sealed envelope containing a BID must be plainly marked on the outside as BID

Kootenai Community Water Main Loop Construction Sanitation Facilities and the

envelope should bear on the outside the name of the BIDDER, their address, their

license number if applicable and the name of the project for which the BID is submitted.

If forwarded by mail, the sealed envelope containing the BID must be enclosed in

another envelope addressed to the TRIBE.

All BIDS must be made on the required BID form. All blank spaces for BID prices must

be filled in, in ink or typewritten, and the BID form must be fully completed and executed

when submitted. Only one copy of the BID form is required.

Pre-BID meeting will be held for interested bidders on Wednesday, April 17th, 2024 at

11:00 AM PST at the address listed above.

Required Forms for BID submittal:

1. BID OFFER

2. BID SCHEDULE

3. BID BOND

4. INDIAN ENTERPRISE QUALIFICATION STATEMENT (If applicable)

The TRIBE may waive any informalities or minor defects or reject any and all BIDS. Any

BID may be withdrawn prior to the above scheduled time for the opening of BIDS or

authorized postponement thereof. Any BID received after the time and date specified

shall not be considered. No BIDDER may withdraw a BID within 60 days after the actual

date of the opening thereof. Should there be reasons why the contract cannot be

awarded within the specified period, the time may be extended by mutual agreement

between the TRIBE and the BIDDER.

SECTION 00110 – INFORMATION FOR BIDDERS

PAGE 1 OF 4

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

BIDDERS must satisfy themselves of the accuracy of the estimated quantities in the

BID Schedule by examination of the site and a review of the drawings and specifications

including ADDENDA. After BIDS have been submitted, the BIDDER shall not assert that

there was a misunderstanding concerning the quantities of WORK or of the nature of

the WORK to be done.

The TRIBE shall provide to BIDDERS prior to BIDDING, all information, which is

pertinent to, and delineates and describes, the land owned and rights-of-way acquired

or to be acquired.

The CONTRACT DOCUMENTS contain the provisions required for the construction of

the PROJECT. Information obtained from an officer, agent, or employee of the TRIBE or

any other person shall not affect the risks or obligations assumed by the

CONTRACTOR or relieve him from fulfilling any of the conditions of the contract.

A BID bond payable to the TRIBE must accompany each BID for five percent of the total

amount of the BID. As soon as the BID prices have been compared, the TRIBE will

return the BONDS of all except the three lowest responsible BIDDERS. When the

Agreement is executed the bonds of the two remaining unsuccessful BIDDERS will be

returned. The BID BOND of the successful BIDDER will be retained until the payment

BOND and performance BOND have been executed and approved, after which it will be

returned. A certified check may be used in lieu of a BID BOND.

A performance BOND and a payment BOND, each in the amount of 100 percent of the

CONTRACT PRICE, with a corporate surety approved by the TRIBE, will be required for

the faithful performance of the contract.

Attorneys-in-fact who sign BID BONDS or payment BONDS and performance BONDS

must file with each BOND a certified and effective dated copy of their power of attorney.

The party to whom the contract is awarded will be required to execute the Agreement

and obtain the performance BOND and payment BOND within ten (10) calendar days

from the date when NOTICE OF AWARD is delivered to the BIDDER. The necessary

Agreement and BOND forms shall accompany the NOTICE OF AWARD. In case of

failure of the BIDDER to execute the Agreement, the TRIBE may at their option

consider the BIDDER in default, in which case the BID BOND accompanying the

proposal shall become the property of the TRIBE.

The TRIBE within ten (10) days of receipt of acceptable performance BOND, payment

BOND and Agreement signed by the party to whom the Agreement was awarded shall

sign the Agreement and return to such party an executed duplicate of the Agreement.

Should the TRIBE not execute the Agreement within such period, the BIDDER may by

WRITTEN NOTICE withdraw his signed Agreement. Such notice of withdrawal shall be

effective upon receipt of the notice by the TRIBE.

SECTION 00110 – INFORMATION FOR BIDDERS

PAGE 2 OF 4

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

The NOTICE TO PROCEED shall be issued within (10) days of the execution of the

Agreement by the TRIBE. Should there be reasons why the NOTICE TO PROCEED

cannot be issued within such period, the time may be extended by mutual agreement

between the TRIBE AND CONTRACTOR. If the NOTICE TO PROCEED has not been

issued within the ten (10) day period or within the period mutually agreed upon, the

CONTRACTOR may terminate the Agreement without further liability on the part of

either party.

The TRIBE may make such investigations as he deems necessary to determine the

ability of the BIDDER to perform the WORK, and the BIDDER shall furnish to the TRIBE

all such information and data for this purpose as the TRIBE may request. The TRIBE

reserves the right to reject any BID if the evidence submitted by, or investigation of,

such BIDDER fails to satisfy the TRIBE that such BIDDER is properly qualified to carry

out the obligations of the Agreement and to complete the WORK contemplated therein.

A conditional or qualified BID will not be accepted.

Award will be made to the lowest responsible BIDDER.

All applicable laws, ordinances, and the rules and regulations of all authorities

having jurisdiction over construction of the PROJECT shall apply to the contract

throughout.

Disputes under this contract will be submitted to for third party mediation; if not

resolved, submit the dispute to the tribal court.

Each BIDDER is responsible for inspecting the site and for reading and being

thoroughly familiar with the CONTRACT DOCUMENTS. The failure or omission of any

BIDDER to do any of the foregoing shall in no way relieve any BIDDER from any

obligation in respect to his BID. Further, the BIDDER agrees to abide by the

requirements under Executive Order No. 11246, as amended, including specifically the

provisions of the equal opportunity clause set forth in the SUPPLEMENTAL GENERAL

CONDITIONS.

The low BIDDER shall supply the names and addresses of major material SUPPLIERS

and SUBCONTRACTOR when requested to do so by the TRIBE.

Minimum percentage of work to be completed by the prime CONTRACTOR is 33-1/3%.

State lien laws do not apply on Federal Trust Land.

This is not a Federal Contract, responsibility for compliance with and enforcement of the

contract resides with the TRIBE. State and Local taxes apply.

The Indian Health Service is serving as a technical advisor and Construction Inspector

for the TRIBE.

SECTION 00110 – INFORMATION FOR BIDDERS

PAGE 3 OF 4

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

The DESIGN ENGINEER is:

Benjamin Chadwick, P.E.

Acting District Engineer

Spokane District Office

Indian Health Service

528 E Spokane Falls Blvd, Ste. 302

Spokane, WA 99202

The PROJECT ENGINEER is:

Jullyanne De Pasion

Environmental Engineer

Spokane District Office

Indian Health Service

528 E Spokane Falls Blvd, Ste. 302

Spokane, WA 99202

SECTION 00110 – INFORMATION FOR BIDDERS

PAGE 4 OF 4

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

SECTION 00400

BID OFFER

Proposal of _______________________________________________________

(hereinafter called “BIDDER”), organized and existing under the laws of the

State of __________________________doing business with

_______________________________________ (hereinafter called “TRIBE”).

In compliance with your Advertisement for Bids, BIDDER hereby proposes to

perform all WORK for the construction of ________________________________

in strict accordance with the CONTRACT DOCUMENTS, within the time set forth

therein, and at the prices stated below.

By submission of this BID, each BIDDER certifies, and in the case of a joint BID

each party thereto certifies as to his own organization, that this BID has been

arrived at independently, without consultation, communication, or agreement as to

any matter relating to this BID with any other BIDDER or with any competitor.

BIDDER hereby agrees to commence WORK under this contract on or before a

date to be specified in the NOTICE TO PROCEED and to fully complete the

PROJECT within 120 consecutive calendar days thereafter. BIDDER further

agrees to pay as liquidated damages, the sum of $100.00 for each consecutive

calendar day thereafter as provided in the General Conditions.

BIDDER acknowledges receipt of the following ADDENDUM:

_________________________________________________________________

_________________________________________________________________

________________________________________________________________

BIDDER agrees to perform all the work described in the CONTRACT

DOCUMENTS for the following prices or lump sum:

BIDDER agrees to submit a complete salary breakdown of all hired employees to

the Tribe.

SECTION 00400 – BID OFFER

PAGE 1 OF 2

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

This page intentionally left blank

SECTION 00400 – BID OFFER

PAGE 2 OF 2

PO-21-N04 KOOTENAI WATER LOOP CONSTRUCTION

INDIAN HEALTH SERVICE

Schedule A

QTY

UNIT

UNIT

PRICE

TOTAL

PRICE

1

LS

______________

______________

1,247

LF

______________

______________

Fire Hydrant Assembly

1

EA

______________

______________

4.

6-inch Gate Valve with Box

4

EA

______________

______________

5.

1-inch Corporation Stop with Saddle

1

EA

______________

______________

6.

1-inch Curb Stop with Box

1

EA

______________

______________

7.

1-inch Water Service Line, HDPE, SDR09

55

LF

______________

______________

8.

2-inch Corporation Stop with Saddle

1

EA

______________

______________

9.

2-inch Curb Stop with Box

1

EA

______________

______________

10.

2-inch Water Service Line, HDPE, SDR09

15

LF

______________

______________

11.

Connections to Existing System

1

LS

______________

______________

12.

Pipe Abandonment

1

LS

______________

______________

13.

Asphalt Pavement Resurfacing (Driveway)

120

SF

______________

______________

14.

Tree Removal (if necessary)

2

EA

______________

______________

ITEM

DESCRIPTION

1.

Mobilization and Demobilization

2.

6-inch PVC Watermain, C900 - DR-18

3.

Total Schedule A: ______________

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

SECTION 00450

INDIAN ENTERPRISE QUALIFICATION STATEMENT

NOTE:

If BIDDER wishes to qualify as an “Indian-owned Economic Enterprise”, submit this completed

questionnaire to the OWNER within the time frame specified. Use additional sheets to complete

answers if needed.

The undersigned certifies under oath the truth and correctness of all answers to questions made hereinafter:

1.

Applicant wishes to qualify as:

An "Economic Enterprise" as defined in Section 23(e) of the Indian Financing Act of 1974 (P.L.

93-262); that is "any Indian-Owned ... commercial, industrial or business activity established or

organized for the purpose of profit: provided, that such Indian ownership shall constitute not less

than 51 percent of the enterprise:

or

A "Tribal Organization" as defined in Section 4 (c ) of the Indian Self-Determination and Education

Assistance Act (P.L. 93-638); that is: "the recognized governing body of any Indian Tribe; any

legally established organization of Indians which is controlled, sanctioned or chartered by such

governing body or which is democratically elected by the adult members of the Indian community

to be served by such organization and which includes the maximum participation of Indian in all

phases of its activities: Provided, that in any case where a contract is let or grant made to an

organization to perform services benefitting more than one Indian Tribe, the approval of each

such Indian Tribe shall be a prerequisite to the letting or making of such contract or grant ..."

2.

Name of Enterprise or Organization:

Address:

Telephone Number:

3.

Check One:

Corporation

Partnership

Sole Proprietorship

Joint Venture

Other

SECTION 00450 - INDIAN ENTERPRISE QUALIFICATION STATEMENT

PAGE 1 OF 6

KOOTENAI TRIBE

4.

WATER MAIN LOOP CONSTRUCTION

Answer the following:

If a Corporation:

a. Date of incorporation:

b. State of incorporation:

c. Give the names and addresses of the officers of this Corporation and establish whether they

are Indian (I) or Non-Indian (NI).

Name and Social

Security No.

I or

NI

Title

Address

% of stock

Ownership

President

VicePresident

Secretary

or Clerk

Treasurer

d. Complete the following information on all stockholders who are not listed in C above, owning

10% or more of the stock. Establish whether they are Indian (I) or Non-Indian (NI).

Name and

Social Security No.

I or

NI

Address

SECTION 00450 - INDIAN ENTERPRISE QUALIFICATION STATEMENT

% of stock

Ownership

PAGE 2 OF 6

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

If a Sole Proprietorship or Partnership:

a.

Date of Organization:

b.

Give the following information on the individual or partners and establish whether they are Indian

(I) or Non-Indian (NI).

Name and

Social Security No.

I or

NI

Address

% of stock

Ownership

If a Joint Venture:

a.

Date of Joint Venture Agreement:

b.

Attach the information for each member of the joint venture prepared in the appropriate format

given above.

5.

Give the name, address, and telephone number of the principal spokesperson of your

organization:

6.

Will any officer or partner listed in #4 be engaged in outside employment?

Yes

No

If Yes, complete:

Name/Title:

SECTION 00450 - INDIAN ENTERPRISE QUALIFICATION STATEMENT

Hours Per Week

Outside the Enterprise

PAGE 3 OF 6

KOOTENAI TRIBE

7.

WATER MAIN LOOP CONSTRUCTION

Does this enterprise have any subsidiaries or affiliates or is it a subsidiary or affiliate of another

concern?

Yes

No

If yes, complete:

Name and address of subsidiary,

affiliate or other concern:

8.

Description

of Relationship

Does this enterprise or any person listed in #4 above have or intend to enter into any type of

agreement with any other concern or person which relates to or affects the on-going

administration, management or operations of this enterprise? These include but are not limited

to management and joint venture agreements and any arrangement or contract involving the

provision of such compensated services as administrative assistance, data processing,

management consulting of all types, marketing, purchasing, production and other type of

compensated assistance.

Yes

No

If yes, attach a copy of any written agreement or an explanation of any oral or intended

agreement:

9.

Trade References (include addresses and phone numbers):

10.

a. Indicate the core employees in your work force, their job titles, and whether they are Indian or

Non-Indian. Core crew is defined as an individual who is a current bona-fide individual who is

regularly employed by the contractor in a supervisory or other key position when work is

available.

b.

Over the past three years, what has been the average number of employees?

11.

Attach certification by a Tribe or other evidence of enrollment in a Federally recognized Tribe,

or qualification as a California Indian according to Federal law, for each officer, partner or

individual designated as an Indian in #4.

12.

Attach a certified copy of the charter, article of incorporation, by-laws, partnership agreement,

joint venture agreement and/or other pertinent organizational documentation.

NOTE:

I. Omission of any information may be cause for this statement not receiving timely and

complete consideration.

SECTION 00450 - INDIAN ENTERPRISE QUALIFICATION STATEMENT

PAGE 4 OF 6

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

II.

The persons signing below certify that all information in the Indian Enterprise Qualification

statement, including exhibits and attachments is true and correct.

III.

Print and type name below all signatures.

If applicant is Sole Proprietor, sign below:

Name

Date

If applicant is in a Partnership or Joint Venture, all Partners must sign below:

Name

Date

Name

Date

Name

Date

Name

Date

If applicant is a corporation, affix corporate seal:

Corporate Seal

Date

By:

Attested by:

Corporate Secretary's Signature

SECTION 00450 - INDIAN ENTERPRISE QUALIFICATION STATEMENT

PAGE 5 OF 6

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

This page intentionally left blank

SECTION 00450 - INDIAN ENTERPRISE QUALIFICATION STATEMENT

PAGE 6 OF 6

CONTRACT

FOR CONSTRUCTION SERVICES

This Contract is between the KOOTENAI TRIBE OF IDAHO, with headquarters at

Bonners Ferry, Idaho, hereinafter referred to as "The Tribe" and _________________

hereinafter referred to as the "Contractor.” This Contract shall take effect upon signing

by the authorized representatives of both parties.

1.0

Description of Work and Contract Documents

1.1

This Contract consists of this written agreement and all attached "contract

documents" CONTRACTOR shall perform the following described work in

accordance with this written agreement and the attached contract

documents (do not leave blank):

___________________________________________________________

___________________________________________________________

______________________________________.

1.2

As part of Contract Documents, required attachments include at a minimum,

the RFP/RFQQ or Sealed Bid for the Project, Bidder’s Response, and a

Certification Regarding Debarment by any Tribal government, Federal

agency or State government.

1.3

These contract documents together form the Contract for the work herein

described. The parties intend that the documents include provisions for all

labor, materials, equipment, supplies, and other items necessary for the

execution and completion of the work by the CONTRACTOR, and all terms

and conditions of payment. The documents also include a requirement to

perform all work and procedures not expressly indicated herein, but which

are necessary for the proper execution of the project. In case of a conflict

between this written agreement and any document attached to it, the terms

of this written agreement shall govern.

2.0

Contract Price

The Tribe agrees to pay CONTRACTOR for the work described not to exceed

__________________. Payment of this amount is subject to additions or

deductions in accordance with the provisions of this Contract.

3.0

Payments

3.1

Payment shall be made by the Tribe within thirty days of review and

approval of Contractor’s monthly billing, minus any amount retained in

accordance with this written agreement. Payment shall be made for

accepted work completed according to the approved “Schedule of Values”

which is the written and approved estimates of costs of material, equipment,

and/or labor necessary to complete the work required by this Contract.

SECTION 00500 – AGREEMENT

1

3.2

Progress payments may be withheld and this Contract may be terminated

if:

3.2.1 Work is found to be defective and not remedied;

3.2.2 CONTRACTOR does not make prompt and proper payments to

subcontractors;

3.2.3 CONTRACTOR does not make prompt and proper payments for

labor, materials, or equipment furnished to him;

3.2.4 Another CONTRACTOR is damaged by an act for which

CONTRACTOR is responsible;

3.2.5 Claims or liens are filed on the job;

3.2.6 In the opinion of the Contract Officer Representative,

CONTRACTOR’s work is not progressing in a satisfactory manner.

4.0

Final Payment

4.1

The Tribe shall make final payment to CONTRACTOR within thirty (30) days

after the work is completed, provided that:

4.1.1 This Contract is then fully performed;

4.1.2 CONTRACTOR has delivered to the Tribe:

a)

A complete release of all liens arising out of the contract;

b)

Receipts showing payment has been made for all

labor, materials, and equipment for which a lien could be filed

or other satisfactory evidence that no such amounts remain

due and owing; or

c)

A bond satisfactory to the Tribe indemnifying the Tribe

against such liens.

d)

As-built drawings showing all changes from original design

documents

5.0

Claims

5.1

By making final payment, the Tribe waives all claims except those arising

out of:

5.1.1 Faulty work appearing after a certificate of substantial completion

has been issued;

5.1.2 Work that does not comply with the contract documents;

5.1.3 Outstanding claims of liens;

5.1.4. Failure of CONTRACTOR to comply with any special guarantees or

warranty required by the contract documents.

5.2 CONTRACTOR, by accepting final payment, waives all claims except those

which he or she has previously made in writing, and which remain unsettled

at the time of acceptance.

SECTION 00500 – AGREEMENT

2

6.0

Starting and Completion Dates

CONTRACTOR’s work under this Contract shall begin on _________________,

and shall be completed by _________________. The Contractor and or

Contractors surety, if any will be liable for and pay $100.00, and not as a penalty,

for each calendar day of delay after 50 days from the notice to proceed date until

the work is substantially complete.

7.0

Work Changes

7.1

The Tribe reserves the right to order work changes in the nature of

additions, deletions, or modifications to this Contract, without invalidating

the Contract, and agrees to make corresponding adjustments in the

Contract Price and time for completion as are then agreed to by the parties.

Any such changes will be authorized by a written Change Order, which must

be signed by the tribe’s Contract Officer, designated in Section Nine (9)

below. The Change Order will include conforming changes in the Contract

and completion time.

7.2

The scope of work shall be changed, and the Contract Price and completion

time shall be modified only as set out in the written Change Order. Any

adjustment in the Contract Price resulting in a credit or a charge to the Tribe

shall be determined by the mutual agreement of the parties to this Contract

before starting the work involved in the change.

8.0

Default and Termination

8.1

This Contract may be terminated by either party without prejudice to any

other remedy that the non-defaulting party may have if the other party

defaults in performance of any provision of this Contract. The non-defaulting

party shall give the defaulting party 10 days’ written notice of the nondefaulting party’s intention to terminate this Contract, within which time the

defaulting party may cure the default condition to the satisfaction of the nondefaulting party. Should the defaulting party be CONTRACTOR, the Tribe

may, pursuant to Section 3 of this Contract, withhold any portion of the

Contract Price still owing at the time of default.

8.2

The Tribe may also terminate this Contract for its convenience without

cause. Should the Tribe elect to terminate under this subparagraph, the

Tribe shall give the CONTRACTOR 10 days’ written notice of the

termination. The Tribe shall pay for all work completed and building

materials purchased for the project up to the effective date of the

termination. CONTRACTOR shall have no additional rights as against the

Tribe except for the payment provided under this subparagraph.

8.3

This Contract is funded from appropriated funds or federal funds. Should

those funds be reduced or eliminated, the Tribe may terminate or modify

this Contract to reflect the change in funding. If this Contract is terminated

under this subparagraph, CONTRACTOR shall be paid for all work properly

completed and building materials purchased up to the effective date of

SECTION 00500 – AGREEMENT

3

termination. Any work changes required, as a result of the provisions of this

Section shall be processed as provided under herein.

9.0

Contract Officer/Contract Officer Representative/Contractor Representative

9.1

Theresa Wheat is the designated Contract Officer (CO) for the purpose of

this Contract and shall provide general administration of the Contract as the

Tribe’s representative.

9.2

The designated Contract Officer Representative (COR) for the purpose of

this Contract shall be _Theresa Wheat_. The Contract Officer

Representative shall provide specific administration of the Contract as the

Tribe’s representative, and shall have authority to initiate Change Orders,

including approval of compensation and expense payments.

9.3

CONTRACTOR’s representative for this project is ____________ who shall

be responsible for the conduct of the work completed hereunder, and who

shall have signature authority for the CONTRACTOR for all matters related

to this Contract.

10.0 Authorities

10.1 The duties and authority of the Tribe’s CO and COR shall be as follows:

10.1.1 Specific Administration of Contract: COR

10.1.2 Inspections and Instructions: COR

The COR shall keep familiar with the progress and quality of the work

by making periodic visits to the work site. The COR will make general

determinations as to whether the work is proceeding in accordance

with the contract. Neither the Tribe nor the COR will be responsible

for the means of construction or for CONTRACTOR’s failure to

perform the work properly and in accordance with the contract

documents. Any instructions given to the CONTRACTOR by the

Tribe shall be given through the COR or his or her designate. The

COR/designate has the authority to reject work not in compliance

with this Contract.

10.1.3 Access to Worksite for Inspection: COR

The COR shall be given free access to the work at all times during

the contract period. However, the COR is not required to make

exhaustive or continuous onsite inspections to perform the duty of

checking and reporting on work progress.

10.1.4 Interpretation of Contract Documents: CO/ORA

The CO in consultation with the Legal Department will interpret the

contract documents requirements and make decisions on claims and

disputes between the CONTRACTOR and the Tribe. The COR does

not have the authority to make decisions on these matters.

10.1.5 Rejection and Stoppage of Work: COR

The COR shall have authority to reject work which in his or her

opinion does not conform to the contract documents, and in this

SECTION 00500 – AGREEMENT

4

connection, to stop the work or a portion thereof when necessary to

insure CONTRACTOR’s performance is in accordance with the

terms of this Contract.

11.0

Rights of the Tribe

The Tribe reserves the right to let other contracts in connection with the project.

CONTRACTOR shall cooperate with all other contractors to the effect that their

work shall not be impeded by CONTRACTOR’s construction, and shall give them

access to the work site necessary to perform their contracts.

12.0 Responsibilities of Contractor

12.1 CONTRACTOR’s duties and rights in connection with the project herein are

as follows:

12.1.1 Responsibility for and Supervision of Construction:

CONTRACTOR represents that he or she has inspected and is

familiar with the work site and the local conditions under which the

work is to be performed. CONTRACTOR shall be solely responsible

for all construction under this Contract, including the techniques,

sequences, procedures, and means for coordination of all work.

CONTRACTOR shall properly supervise and direct the work of his or

her employees and subcontractors, and shall give all attention

necessary for such proper supervision and direction.

12.1.2 Discipline and Employment:

CONTRACTOR shall maintain at all times strict discipline among his

or her employees, and agrees not to employ for work on the project

any person unfit or without sufficient skill to perform the job for which

he or she was employed.

12.1.3 Furnishing of Labor, Materials, etc.:

CONTRACTOR shall provide and pay for all labor, materials and

equipment, including but not limited to tools, construction equipment,

and machinery, utilities including water, transportation, and all other

facilities and services necessary for the proper completion of the

work on the project in accordance with the contract documents.

12.1.4 Payment of Taxes, Procurement of Licenses and Permits:

CONTRACTOR shall pay any taxes required by law in connection

with work on the project and shall secure all licenses and permits

necessary for proper completion of the work, paying the fees

therefore.

12.1.5 Compliance with Laws and Regulations:

CONTRACTOR shall comply with all applicable laws, ordinances,

and rules, regulations, or orders of all public authorities relating to

the performance of the work herein. If any of the contract documents

are at variance therewith, he or she shall notify the Contract Officer

promptly on discovery of such variance.

SECTION 00500 – AGREEMENT

5

12.1.6 Responsibility for Negligence of Employees and Subcontractors:

CONTRACTOR assumes full responsibility for acts, negligence or

omissions of all his or her employees on the project, for those of his

or her subcontractors and their employees, and for those of all other

persons doing work under a contract with him.

12.1.7 Warranty of Fitness of Structures, Work Equipment and Materials:

CONTRACTOR represents and warrants to the Tribe that all

structures constructed and work done under this Contract and

equipment and materials used in the work and made a part of any

structure, or placed permanently in connection with any structure, will

be new unless otherwise specified in the contract documents, of

good quality, free of defects, and in conformity with the contract

documents. It is understood between the parties hereto that all

equipment and materials that are not so in conformity are defective.

Upon completion of the project which is the subject of this Contract,

the Contractor shall provide valid written warranties for all materials

and equipment provided which will remain on site; such warranties

shall be in force for at least year or per the manufacturer’s warranty

period, whichever is longer.

12.1.8 Furnishing of Samples, Shop Drawings and As-Built Drawings:

CONTRACTOR agrees to furnish the Tribe COR, upon request, all

samples and shop drawings for consideration and approval as to

conformance with the specifications of the contract documents and

concepts of design called for therein.

12.1.9 Clean Up: CONTRACTOR agrees to keep the work premises and

adjoining ways free of waste materials and rubbish caused by his or

her work or that of subcontractors. He or she further agrees to

remove all such waste materials and rubbish caused by his or her

work or that of subcontractors, and to dispose of such materials only

at approved landfill sites or collection stations as approved by a valid

solid waste permit issued to Contractor or his/her subcontractor(s).

He or she further agrees to remove all such waste materials and

rubbish on termination of the project, together with all

CONTRACTOR’s tools, equipment, machinery, and surplus

materials. CONTRACTOR agrees on terminating work at the site to

conduct general clean up operations of any and all areas affected by

the work, including the cleaning of all glass surfaces, paved streets

and walks, steps, and interior floors and walls.

12.1.10 Indemnity and Hold Harmless Agreement:

CONTRACTOR agrees to indemnify and hold harmless the Tribe

and its agents and employees from and against all claims, damages,

losses, and expenses including reasonable attorney’s fees in case it

shall be necessary for the Tribe to commence or defend an action

SECTION 00500 – AGREEMENT

6

arising out of or associated in any way with performance of the work

herein which is

a)

For bodily injury, illness, or death, property damage including loss of

use, or other damage, and

b)

Caused in whole or part by CONTRACTOR’s negligent act or

omission, or that of a subcontractor, or that of anyone employed by

them or for whose acts CONTRACTOR or subcontractor may be

liable.

12.1.11 Payment of Royalties and License Fee (Hold Harmless

Agreement):

CONTRACTOR agrees to pay all royalties and license fees

necessary for the work and to defend all actions and settle all claims

for infringement of copyright or patent rights, and to save the Tribe

harmless therefrom.

12.1.12 Safety Precautions and Programs:

CONTRACTOR has the duty of providing for and overseeing all

safety orders, precautions, and programs necessary to the

reasonable safety of the work and will comply with all applicable

Tribal and federal laws, rules, and regulations. In this connection

CONTRACTOR shall take reasonable precautions for the safety of

all work employees and other persons whom the work might affect,

all work and materials incorporated in the project, and all property

and improvements on the constructions site and adjacent thereto,

complying with all applicable laws, ordinances, rules, regulations,

and orders.

12.1.13 Drug and Alcohol-Free Workplace:

CONTRACTOR shall at all times maintain a drug and alcohol-free

workplace, and shall take reasonable steps to ensure that no

employees of, nor subcontractors of the CONTRACTOR are

allowed to work while under the influence of illegal drugs or of

alcohol, and that no such illegal drugs or alcohol are allowed at any

time at the work site. Failure to comply with this paragraph is

grounds for immediate termination of this Contract.

13.0

Time of Essence/Extension of Time

All times for performance set out in the Contract Documents are deemed to be of

the essence. The CONTRACTOR will schedule and perform all work under this

Contract to complete the work within the time required by this Contract. Contract

times may only be extended by a written Change Order from the Contract Officer

issued to the CONTRACTOR prior to the expiration of the original date for

performance of this Contract or any of its parts. Contract times may be extended

by a Change Order from the Tribe’s Contract Officer for such reasonable time as

the Contract Officer may determine when in his or her opinion CONTRACTOR is

delayed in work progress by Change Ordered, labor disputes, fire, prolonged

SECTION 00500 – AGREEMENT

7

transportation delays, injuries, or other causes beyond CONTRACTOR’s control

or which justify the delay. The Tribe reserves the absolute right to refuse to permit

an extension of the contract except in case of Change Orders issued by the Tribe.

14.0

Subcontractors

CONTRACTOR agrees to furnish the Tribe Contract Officer, before the

commencement of work under this Contract, a list of subcontractors to whom he

or she proposes to award the work to be subcontracted by him. A subcontractor

for the purpose of this Contract shall be a person with whom contractor has a direct

contract for work at the project site. CONTRACTOR agrees not to employ a

subcontractor to whose employment the Contract Officer of the Tribe objects, nor

shall he or she be required to hire a subcontractor to whose employment he or she

may reasonably object. All contracts between CONTRACTOR and subcontractors

shall conform to the provisions of the contract documents and shall incorporate in

such subcontracts the relevant provisions of this Contract. All subcontractors shall

be informed in writing of the contents of this Contract, including all Contract

documents, which apply to the performance of subcontractors. Additionally,

Contractor shall provide written notification to all subcontractors that they are

subject to all the terms of this Contract which reasonably may be applied to their

performance.

15.0

Insurance

CONTRACTOR shall provide insurance as follows, and shall provide to the CO

certificates verifying the indicated insurance coverage:

15.1 CONTRACTOR’s Liability Insurance:

CONTRACTOR agrees to keep in force at CONTRACTOR’s expense

during the entire period of construction on the project such liability insurance

as will protect him from claims under workman's compensation, and other

employee benefit laws for bodily injury and death, and for property damage

that may arise out of work under this Contract, whether directly or indirectly

by CONTRACTOR, or directly or indirectly by a subcontractor. The amount

of such coverage shall be at least $1 million per incident and $2 million

aggregate and the Certificate of Insurance provided by CONTRACTOR

shall specifically name the Tribe as an additional insured. Such insurance

shall include contractual liability insurance applicable to CONTRACTOR’s

obligations under this Contract. Proof of such insurance shall be filed by

CONTRACTOR with the Tribe within a reasonable time after execution of

this Contract and before the commencement of work by the

CONTRACTOR.

Failure to provide proof of insurance prior to

commencement of work shall result in a Stop Work order by the CO.

15.2 Builder’s Risk Insurance:

Builder’s Risk Insurance is not required for work on structures currently

insured by the Tribe. However, CONTRACTOR further agrees to purchase

and maintain in full force and effect during the entire period of construction

SECTION 00500 – AGREEMENT

8

a policy of Builder’s Risk Insurance for the benefit of the Tribe in the amount

equal to the cost of the project which provides insurance coverage for the

Tribe against any claim or lawsuit against the Tribe for bodily injury, illness

or death, or for property damage, including loss of use, or any other

damage, which is caused in whole or in part by CONTRACTOR’s negligent

act or omission or that of a subcontractor.

16.0 Performance/Payment Bond or Increased Retainage (select one)

16.1 If the Contract Price set out in §2.0 of this written agreement equals or

exceeds $10,000.00, Contractor shall:

[ ]

16.1.1 Provide a performance and payment bond for the full

Contract price, and any increase in that price authorized by a

Change Order, guaranteeing the faithful performance of this

Contract. In this case,10% of the contract price shall be retained

and released to the Contractor only upon completion of this

contract. OR

[ ]

16.1.2 Contractor shall agree that the total amount retained from

the Contract Price shall be 25%, which shall be released to the

Contractor only upon completion of this contract. If the Performance

Bond option is chosen, the bond shall be provided before the

performance of any work on this contract.

17.0

Correcting Work

When it appears to the COR or CONTRACTOR during the course of construction

that any work does not conform to the provisions of the contract documents,

Contractor shall make necessary corrections so that such work will so conform,

and in addition will correct any defects caused by faulty materials, equipment, or

workmanship in work supervised by him or by at any work does not conform to the

provisions of the contract documents, he or she shall make necessary corrections

so that such work will so conform, and in addition will correct any defects caused

by faulty materials, equipment, or workmanship in work supervised by him or by a

subcontractor, appearing within One (1) Year from the date of issuance of a

certificate of substantial completion by the Contract Officer, or within such longer

period as may be prescribed by law or as may be provided for by applicable special

guarantees in the contract documents.

18.0

Possession upon Substantial Completion

The Tribe reserves the right to take over and utilize areas of the work site in

which CONTRACTOR’s work has been substantially completed, although other

portions of the contracted work remain to be finished. In such an instance, all

CONTRACTOR’s obligations under this Contract shall remain in force and

CONTRACTOR will remain responsible for the entire project covered by this

Contract until the Contract Officer has issued a certificate of substantial

completion. Should the Tribe take possession of a portion of the Project which is

SECTION 00500 – AGREEMENT

9

substantially completed prior to completion of the Project, CONTRACTOR shall

be relieved of liability for liquidated damages for the portion of the Project

occupied by the Tribe pursuant to this paragraph.

19.0

Jurisdiction

The Tribe and CONTRACTOR agree that sole and exclusive jurisdiction over

disputes arising from this Contract shall be in the Tribal Courts of the Kootenai

Tribe.

20.0

Reporting

CONTRACTOR shall report to the COR or as requested by the COR. Reports may

be made in writing, or by fax, teleconference, or E-mail, as directed by the COR.

21.0

Independent Contractor

It is understood that the CONTRACTOR is operating as an independent contractor,

and as such shall comply with all applicable laws and regulations and shall pay all

applicable taxes and other assessments and hold the Tribe harmless from the

consequences of any act or omission of whatever kind or nature of CONTRACTOR

or its employees or agents of whatever kind. CONTRACTOR shall not have any

right as an employee of the Tribe, and no employee-employer relationship is

established by this Contract. Further, the CONTRACTOR is responsible for

reporting this income to the applicable federal and/or state agencies. The

CONTRACTOR is responsible for all taxes associated with this income.

22.0

Proprietary Rights

CONTRACTOR agrees that all proprietary rights, including patents and copyrights,

contracted for or otherwise created for or on behalf of the Tribe shall be owned by

the Kootenai Tribe of Idaho.

23.0

Records

CONTRACTOR will maintain adequate financial records, in accordance with

generally accepted accounting practices, such that the CONTRACTOR can clearly

and easily identify all claimed costs and expenses and the relatedness of those

costs and expenses to this Contract.

24.0

Embezzlement

The CONTRACTOR agrees to insert this clause in all subcontracts:

Any officer, director, agent, employee or other person connected in any capacity

with this Contract or any subcontract hereunder who embezzles, willfully

misapplies, steals or obtains by fraud any of the money, funds, assets or property

provided through this Contract may be subject to federal and tribal criminal

prosecution and may be fined up to $10,000 or imprisoned for up to two years, or

both if convicted.

SECTION 00500 – AGREEMENT

10

25.0

Certification of Non-Segregated Facilities

By signing this Contract, the CONTRACTOR certifies that it does not maintain or

provide for its employees any segregated facilities at any of CONTRACTOR’s

establishments, and that CONTRACTOR’s employees are not permitted to

perform their services at any location, under this Contract, where segregated

facilities are maintained.

The CONTRACTOR agrees that failure to abide this certification is a breach of this

Contract.

26.0

Warranty of Special Expertise

The CONTRACTOR warrants that he or she has the educational credentials,

expertise and training required to accomplish the purposes of this Contract.

27.0

Compliance with Applicable Laws

By acceptance of this Contract, the CONTRACTOR agrees that it will comply with

this and all other applicable tribal, state, and federal laws.

IN WITNESS WHEREOF, the parties have executed this Contract at Bonners

Ferry, Idaho, on the date herein indicated.

DATE

DATE

___________________________________

AUTHORIZED REPRESENTATIVE

KOOTENAI TRIBE OF IDAHO

____________________________________

AUTHORIZED COMPANY RESPRSENTATIVE

Contract Number: _______________

SECTION 00500 – AGREEMENT

11

This page intentionally left blank

SECTION 00500 – AGREEMENT

12

KOOTENAI TRIBE

To:

__________________

WATER MAIN LOOP CONSTRUCTION

SECTION 00510

NOTICE OF AWARD

__________________

Project Description: KOOTENAI “COMMUNITY WATER MAIN LOOP CONSTRUCTION

SANITATION FACILITIES”, IHS Project PO-21-N04

The TRIBE has considered the BID submitted by you for the above-described WORK in

response to its Advertisement for Bids dated _______________, and Information for

Bidders.

You are hereby notified that your BID has been accepted for items in the amount of

$_________________.

You are required by the Information for Bidders to execute the Agreement and furnish

the required CONTRACTOR’S Performance BOND, Payment BOND, and certificates of

insurance within ten (10) calendar days from the date of this Notice to you.

If you fail to execute said Agreement and to furnish said BONDS within ten (10) days

from the date of this Notice, said TRIBE will be entitled to consider all your right arising

out of the TRIBE’S acceptance of your BID as abandoned and as a forfeiture of your

BID BOND. The TRIBE will be entitled to such other rights as may be granted by law.

You are required to return an acknowledged copy of this NOTICE OF AWARD to the

TRIBE.

Dated this ________ day of _______________.

__________________________

TRIBE

By _______________________

Title_______________________

ACCEPTANCE OF NOTICE

Receipt of the above NOTICE OF AWARD is hereby acknowledged

by____________________________________________________________________

this the ___________________________day of _________________________

By ______________________________________

Title ____________________________________

SECTION 00510 – NOTICE OF AWARD

PAGE 1 OF 2

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

This page intentionally left blank

SECTION 00510 – NOTICE OF AWARD

PAGE 2 OF 2

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

SECTION 00550

NOTICE TO PROCEED

To:

Date:

Project Description: KOOTENAI “COMMUNITY WATER MAIN LOOP CONSTRUCTION

SANITATION FACILITIES”, IHS Project PO-21-N04

You are hereby notified to commence WORK in accordance with the Agreement dated

, 20

, on or before

, 20

, and

you are to complete the WORK within one hundred and twenty (120) consecutive

calendar days thereafter. The date of completion of all WORK is therefore

, 20

. You will be required to mobilize within 10 days from the commencement

date given above.

You are required to return an acknowledged copy of this NOTICE OF AWARD to the

TRIBE.

Dated this ________ day of __________,2_____.

__________________________

TRIBE

By _______________________

Title_______________________

ACCEPTANCE OF NOTICE

Receipt of the above NOTICE OF AWARD is hereby acknowledged

by____________________________________________________________________

this the ___________________________day of _______________________,2____

By ______________________________________

Title ____________________________________

SECTION 00550 – NOTICE TO PROCEED

PAGE 1 OF 2

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

This page intentionally left blank

SECTION 00550 – NOTICE TO PROCEED

PAGE 2 OF 2

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

SECTION 00610

BID BOND

KNOW ALL MEN BY THESE PRESENTS, that we, the undersigned,

__________________________________ as Principal, and

__________________________________as Surety, are hereby held and firmly

bound unto _______________________________________as TRIBE in the

penal sum of $__________________ for the payment of which, well and truly to

be made, we hereby jointly and severally bind ourselves, successors and assigns.

Signed this ____________________ day of _______________2____.

The Condition of the above obligation is such that whereas the Principal has

submitted to the Kootenai Tribe a certain BID, attached hereto and hereby made a

part hereof to enter into a contract in writing, for the

_________________________________________________________________

NOW, THEREFORE,

(a) If said BID shall be rejected, or

(b) If said BID shall be accepted and the Principal shall execute and deliver a

contract in the Form of Contract attached hereto (properly completed in

accordance with said BID) and shall furnish a BOND for his faithful

performance of said contract and for the payment of all persons performing

labor or furnishing materials in connection therewith, and shall in all other

respects perform the agreement created by the acceptance of said BID, then

this obligation, shall be void, otherwise the same shall remain in force and

effect: it being expressly understood and agreed that the liability of the Surety

for any and all claims hereunder shall, in no event, exceed the penal amount

of this obligation as herein stated.

The Surety, for value received, hereby stipulates and agrees that the obligations

of said Surety and its BOND shall be in no way impaired or affected by any

extension of the time with which the TRIBE may accept such BID: and said Surety

does hereby waive notice of any such extension.

IN WITNESS WHEREOF, the Principal and the Surety have hereunto set their

hands and seals, and such of them as are corporations have caused their

corporate seals to be hereto affixed and these presents to be signed by their

proper officers, the day and year first set forth above.

____________________________________(L.S.)

Principal

____________________________________

Surety

SECTION 00610 – BID BOND

PAGE 1 OF 2

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

By: _________________________________

IMPORTANT – Surety companies executing BONDS must appear on the

Treasury Department’s most current list (Circular 570 as amended) and be

authorized to transact business in the state where the PROJECT is located.

SECTION 00610 – BID BOND

PAGE 2 OF 2

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

SECTION 00620

PAYMENT BOND

KNOW ALL MEN BY THESE PRESENTS: THAT

_________________________________________________________________

Name of Contractor

_________________________________________________________________

Address of Contractor

a__________________________________________ hereinafter called Principal.

Corporation, Partnership or Individual

and______________________________________________________________

Name of Surety

_________________________________________________________________

Address of Surety

Hereinafter called Surety, are held and firmly bound unto____________________

_________________________________________________________________

Name of TRIBE

_________________________________________________________________

Address of TRIBE

Hereinafter called TRIBE, in the penal sum of __________Dollars, $ (_________)

In lawful money of the United States, for the payment of which sum well and truly

to be made, we bind ourselves, successors, and assigns, jointly and severally,

firmly by these presents.

THE CONDITION OF THIS OBLIGATION is such that whereas, the Principal

entered into a certain contract with the TRIBE, dated the _____ day of __, 2____,

a copy of which is hereto attached and made a part hereof for the construction of:

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

_________________________________________________________________

NOW, THEREFORE, if the Principal shall promptly make payment to all person,

firms, SUBCONTRACTORS, and corporations furnishing materials for or

performing labor in the prosecution of the WORK provided for in such contract,

and any authorized extension or modification thereof, including all amounts due

for materials, lubricants, oil, gasoline, coal and coke, repairs on machinery,

equipment and tools, consumed or used in connection with the construction of

such WORK, and all insurance premiums on said WORK, and for all labor,

performed in such WORK whether by SUBCONTRACTOR or otherwise, then this

obligation shall be void: otherwise to remain in full force and effect.

SECTION 00620 – PAYMENT BOND

PAGE 1 OF 2

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

PROVIDED, FURTHER, that the said Surety for value received hereby stipulates

and agrees that no change, extension of time, alteration or addition to the terms of

the contract or to the WORK to be performed hereunder or the SPECIFICATIONS

accompanying the same shall in any wise affect its obligation on this

BOND, and it does hereby waive notice of any such change, extension of time,

alteration or addition to the terms of the contract or to the WORK or the

SPECIFICATIONS.

PROVIDED, FURTHER, that no final settlement between the TRIBE and the

CONTRACTOR shall abridge the right of any beneficiary hereunder, whose claim

may be unsatisfied.

IN WITNESS WHEREOF, this instrument is executed in _____counterparts, each

Number

one of which shall be deemed an original, this the ______day of _______,2____

ATTEST:

(SEAL)

_____________________________________

Principal

_________________________________________

Principal Secretary

________________________

Witness as to Principal

________________________

Address

________________________

ATTEST:

________________________

Witness as to Surety Address

________________________

Address

________________________

By __________________________(s)

_______________________

Address

_______________________

____________________________

Surety

____________________________

Attorney-in-Fact

________________________

Address

________________________

________________________

NOTE: Date of BOND must not be prior to date of Contract.

If CONTRACTOR is Partnership, all partners should execute BOND.

IMPORTANT: Surety companies executing BONDS must appear on the Treasury

Department’s most current list (Circular 570 as amended) and be authorized to

transact business in the State where the PROJECT is located.

SECTION 00620 – PAYMENT BOND

PAGE 2 OF 2

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

SECTION 00630

PERFORMANCE BOND

KNOW ALL MEN BY THESE PRESENTS: THAT

_________________________________________________________________

Name of Contractor

_________________________________________________________________

Address of Contractor

a__________________________________________ hereinafter called Principal.

Corporation, Partnership or Individual

and______________________________________________________________

Name of Surety

_________________________________________________________________

Address of Surety

Hereinafter called Surety, are held and firmly bound unto____________________

_________________________________________________________________

Name of TRIBE

_________________________________________________________________

Address of TRIBE

Hereinafter called TRIBE, in the penal sum of __________Dollars, $ (_________)

In lawful money of the United States, for the payment of which sum well and truly

to be made, we bind ourselves, successors, and assigns, jointly and severally,

firmly by these presents.

THE CONDITION OF THIS OBLIGATION is such that whereas, the Principal

entered into a certain contract with the TRIBE, dated the _____ day of __, 2____,

a copy of which is hereto attached and made a part hereof for the construction of:

_________________________________________________________________

_________________________________________________________________

NOW, THEREFORE, if the Principal shall well, truly and faithfully perform its

duties, all the undertakings, covenants, terms, conditions, and agreements of said

contract during the original term thereof, and any extensions thereof, which may

be granted by the TRIBE, with or without notice to the Surety, and during the one

year guaranty period, and if he shall satisfy all claims and demands incurred

under such contract, and shall fully indemnify and save harmless the TRIBE, from

all costs and damages which it may suffer by reason of failure to do so, and shall

reimburse and repay the TRIBE all outlay and expense which the TRIBE may

incur in making good any default, then this obligation shall be void; otherwise to

remain in full force and effect.

SECTION 00630 – PERFORMANCE BOND

PAGE 1 OF 2

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

PROVIDED, FURTHER, that the said surety, for value received hereby stipulates

and agrees that no change, extension of time, alteration or addition to the terms of

the contract or to WORK to be performed hereunder or the SPECIFICATIONS

accompanying the same shall in any wise affect its obligation on this BOND, and it

does hereby waive notice of any such change, extension of time, alteration or

addition to the terms of the contract or to the WORK or to the SPECIFICATIONS.

PROVIDED, FURTHER, that no final settlement between the TRIBE and the

CONTRACTOR shall abridge the right of any beneficiary hereunder, whose claim

may be unsatisfied.

IN WITNESS WHEREOF, this instrument is executed in _____counterparts, each

Number

one of which shall be deemed an original, this the ______day of _______,2____

ATTEST:

(SEAL)

_____________________________________

Principal

_________________________________________

Principal Secretary

________________________

Witness as to Principal

________________________

Address

________________________

ATTEST:

________________________

Witness as to Surety Address

________________________

Address

________________________

By __________________________(s)

_______________________

Address

_______________________

____________________________

Surety

____________________________

Attorney-in-Fact

________________________

Address

________________________

________________________

NOTE: Date of BOND must not be prior to date of Contract.

IF CONTRACTOR is Partnership, all partners should execute BOND.

IMPORTANT: Surety companies executing BONDS must appear on the Treasury

Department’s most current list (Circular 570 as amended) and be authorized to

transact business in the state where the PROJECT is located.

SECTION 00630 – PERFORMANCE BOND

PAGE 2 OF 2

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

SECTION 00700

GENERAL CONDITIONS

01.

02.

03.

04.

05.

06.

07.

08.

09.

10.

11.

12.

13.

14.

15.

16.

17.

18.

19.

20.

21.

22.

23.

24.

25.

26.

27.

28.

29.

30.

31.

32.

33.

34.

35.

36.

37.

38.

39.

40.

Definitions

Additional Instructions and Detail Drawings

Reports and Records

Drawings and Specifications

Site Investigation and Conditions Affecting the Work

Shop Drawings

Materials, Services and Facilities

Substitutions

Patents

Surveys, Permits, Regulations

Laws and Regulations Affecting Work

Taxes

Protection of Work, Property, Persons

Protection of Existing Vegetation, Structures, Equipment, Utilities, and

Improvements

Operations and Storage Areas

Insurance

Indemnification

Contract Security

Accident Prevention and Safety Program

Temporary Sanitary Facilities

Supervision by Contractor

Subcontracting

Separate Contracts

Time for Completion and Liquidated Damages

Progress Schedules and Requirements for Compliance

Land and Right-of-Way

Suspension of Work, Termination and Delay

Inspection and Testing

Correction of Work

Changes in the Work

Changes in the Contract Price

Differing Site Conditions

Use and Possession Prior to Completion

Cleanup and Finish Grading

Measurement and Payment

Variation in Estimated Quantities

Payments to Contractor

Assignments

Guaranty

Acceptance of Final Payment as release

SECTION 00700 – GENERAL CONDITIONS

PAGE 1 OF 32

KOOTENAI TRIBE

41.

42.

43.

44.

45.

Engineer’s Role and Authority

Resolution of Disputes

Equal Employment Opportunity

Clean Air and Water

Indian Health Service

1.

DEFINITIONS

WATER MAIN LOOP CONSTRUCTION

1.1

Wherever used in the CONTRACT DOCUMENTS, the following terms

shall have the meanings indicated which shall be applicable to both the

singular and plural thereof:

1.2

ADDENDA -Written or graphic instruments issued prior to the execution of

the Agreement which modify or interpret the CONTRACT DOCUMENTS,

DRAWINGS and SPECIFICATIONS, by additions, deletions, clarifications

or corrections.

1.3

BID -The offer or proposal of the BIDDER submitted on the prescribed

form setting forth the prices for the WORK to be performed.

1.4

BIDDER -Any person, firm or corporation submitting a BID for the WORK.

1.5

BONDS -Bid, Performance, and Payment Bonds and other instruments of

security, furnished by the CONTRACTOR and his surety in accordance

with the CONTRACT DOCUMENTS.

1.6

CHANGE ORDER -A written order to the CONTRACTOR authorizing an

addition, deletion or revision in the WORK within the general scope of the

CONTRACT DOCUMENTS, or authorizing an adjustment in the

CONTRACT PRICE or CONTRACT TIME.

1.7

CONTRACT DOCUMENTS -The contract, including Advertisement For

Bids, Information For Bidders, Bid, Bid Bond, Agreement, General

Provisions, Labor Provisions, Special Provisions, Payment Bond,

Performance Bond, NOTICE OF AWARD, NOTICE TO PROCEED,

CHANGE ORDER, DRAWINGS, Technical Provisions, Submittal

Requirements, and ADDENDA.

1.8

CONTRACT PRICE -The total monies payable to the CONTRACTOR

under the terms and conditions of the CONTRACT DOCUMENTS.

1.9

CONTRACT TIME -The number of calendar days stated in the

CONTRACT DOCUMENTS for the completion of the WORK.

SECTION 00700 – GENERAL CONDITIONS

PAGE 2 OF 32

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

1.10

CONTRACTING OFFICER -The person with the OWNER organization

who is authorized to administer the contract for the OWNER.

1.11

CONTRACTING OFFICER'S REPRESENTATIVE - The representative of

the CONTRACTING OFFICER authorized to deal with the CONTRACTOR

at the site to administer the technical aspects of the CONTRACT, and to

assure compliance with the drawings and specifications.

1.12

CONTRACTOR - The person, firm or corporation with whom the OWNER

has executed the Agreement.

1.13

DRAWINGS - The part of the CONTRACT DOCUMENTS, which show the

characteristics and scope of the WORK to be performed, and which have

been prepared or approved by the ENGINEER.

1.14

ENGINEER - The person, firm or corporation named as such in the

CONTRACT DOCUMENTS.

1.15

FIELD ORDER- A written order effecting a change in the WORK not

involving an adjustment in the CONTRACT PRICE or an extension of the

CONTRACT TIME, issued by the ENGINEER to the CONTRACTOR

during construction.

1.16

INDIAN HEALTH SERVICE (IHS) - Federal agency which is providing

funding and/or technical assistance to the Owner on this project.

1.17

NOTICE OF AWARD -The written notice of the acceptance of the Bid from

the OWNER to the successful BIDDER.

1.18

NOTICE TO PROCEED -Written communication issued by the OWNER to

the CONTRACTOR authorizing him to proceed with the WORK and

establishing the date of commencement of the WORK.

1.19

OWNER -A public or quasi-public body or authority, tribe, corporation,

association, partnership, or individual for whom the WORK is to be

performed.

1.20

PROJECT -The undertaking to be performed as provided in the

CONTRACT DOCUMENTS.

1.21

RESIDENT PROJECT REPRESENTATIVE -The authorized

representative of the OWNER who is assigned to the PROJECT site or

any part thereof.

SECTION 00700 – GENERAL CONDITIONS

PAGE 3 OF 32

KOOTENAI TRIBE

2.

WATER MAIN LOOP CONSTRUCTION

1.22

SHOP DRAWINGS -All drawings, diagrams, illustrations, brochures,

schedules and other data which are prepared by the CONTRACTOR, a

SUBCONTRACTOR, manufacturer, SUPPLIER or distributor, which

illustrate how specific portions of the WORK shall be fabricated or

installed.

1.23

SPECIFICATIONS -A part of the CONTRACT DOCUMENTS consisting of

written descriptions of a technical nature of materials, equipment,

construction systems, standards and workmanship.

1.24

SUBCONTRACTOR -An individual, firm or corporation having a direct

contract with the CONTRACTOR or with any other SUBCONTRACTOR

for the performance of a part of the WORK at the site.

1.25

SUBSTANTIAL COMPLETION -That date as certified by the ENGINEER

when the construction of the PROJECT is sufficiently completed in

accordance with the CONTRACT DOCUMENTS, so that the PROJECT or

specified part can be utilized for the purposes for which it is intended.

1.26

SPECIAL PROVISIONS -Modifications and additions to General

Provisions which may be required by a Federal agency for participation in

the PROJECT, or such requirements that may be imposed by applicable

state or local laws, or the OWNER'S contracting practices.

1.27

SUPPLIER - ANY person or organization who supplies materials or

equipment for the WORK, including that fabricated to a special design, but

who does not perform labor at the site.

1.28

TRIBE -The governing body of the INDIAN TRIBE which has jurisdiction

on the INDIAN RESERVATION on or near which the WORK will be

performed.

1.29

WORK -All labor necessary to produce the construction required by the

CONTRACT DOCUMENTS and all materials and equipment incorporated

or to be incorporated in the PROJECT.

1.30

WRITTEN NOTICE -Any notice to any party of the Agreement relative to

any part of this Agreement in writing and considered delivered and the

service thereof completed, when posted by certified or registered mail to

the said party at his last given address, or delivered in person to said party

or his authorized representative on the WORK.

ADDITIONAL INSTRUCTIONS AND DETAIL DRAWINGS

SECTION 00700 – GENERAL CONDITIONS

PAGE 4 OF 32

KOOTENAI TRIBE

3.

4.

5.

WATER MAIN LOOP CONSTRUCTION

2.1

The CONTRACTOR may be furnished additional instructions and detail

drawings, by the ENGINEER, as necessary to carry out the WORK

required by the CONTRACT DOCUMENTS.

2.2

The additional drawings and instruction thus supplied will become a part of

the CONTRACT DOCUMENTS. The CONTRACTOR shall carry out the

WORK in accordance with the additional detail drawings and instructions.

REPORTS AND RECORDS

3.1

The CONTRACTOR shall submit to the OWNER such schedule of

quantities and costs, payrolls, reports, estimates, records and other data

where applicable as are required by the CONTRACT DOCUMENTS for

the WORK to be performed.

3.2

The CONTRACTOR shall keep all records related to the CONTRACT for a

minimum of three years after acceptance of the completed work.

DRAWINGS AND SPECIFICATIONS

4.1

The intent of the DRAWINGS and SPECIFICATIONS is that the

CONTRACTOR shall furnish all labor, materials, tools, equipment, and

transportation necessary for the proper execution of the WORK in

accordance with the CONTRACT DOCUMENTS and all incidental work

necessary to complete the PROJECT in an acceptable manner, ready for

use, occupancy or operation by the OWNER.

4.2

In case of conflict between the DRAWINGS and SPECIFICATIONS, the

SPECIFICATIONS shall govern. Figure dimensions on DRAWINGS shall

govern over scale dimensions, and detailed DRAWINGS shall govern over

general DRAWINGS.

4.3

Any discrepancies found between the DRAWINGS and SPECIFICATIONS

and site conditions or any inconsistencies or ambiguities in the

DRAWINGS or SPECIFICATIONS shall be immediately reported to the

ENGINEER, in writing, who shall promptly correct such inconsistencies or

ambiguities in writing. WORK done by the CONTRACTOR after his

discovery of such discrepancies, inconsistencies or ambiguities shall be

done at the CONTRACTOR'S risk.

SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK

5.1

The CONTRACTOR will take steps necessary to ascertain the nature and

location of the work, and investigate the general and local conditions

SECTION 00700 – GENERAL CONDITIONS

PAGE 5 OF 32

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

which can affect the work or its cost, including but not limited to (1)

conditions bearing upon transportation, disposal, handling, and storage of

materials; (2) the availability of labor, water, electric power, and roads; (3)

uncertainties of weather, river stages, tides, or similar physical conditions

at the site; (4) the conformation and conditions of the ground; and (5) the

character of equipment and facilities needed preliminary to and during

work performance. The CONTRACTOR also will observe and determine

the character, quality, and quantity of surface and subsurface materials or

obstacles to be encountered insofar as this information is reasonably

ascertainable from an inspection of the site, including all exploratory work

done by the OWNER, as well as from the drawings and specifications

made a part of this contract. Any failure of the CONTRACTOR to take the

actions described and acknowledged in this paragraph will not relieve the

CONTRACTOR from responsibility for estimating properly the difficulty

and cost of successfully performing the work, or for proceeding to

successfully perform the work without additional expense to the OWNER.

5.2

6.

The OWNER assumes no responsibility for any conclusions or

interpretations made by the Contractor based on the information made

available by the OWNER. The OWNER does not assume responsibility for

any understanding reached or representation made concerning conditions

which can affect the work by any of its representatives before the

execution of this contract, unless that understanding or representation is

expressly stated in this contract.

SHOP DRAWINGS

6.1

The CONTRACTOR shall provide SHOP DRAWINGS as may be

necessary for the prosecution of the WORK as required by the

CONTRACT DOCUMENTS. The ENGINEER shall promptly review all

SHOP DRAWINGS. The ENGINEER'S approval of any SHOP DRAWING

shall not release the CONTRACTOR from responsibility for deviations

from the CONTRACT DOCUMENTS. The approval of any SHOP

DRAWING which substantially deviates from the requirement of the

CONTRACT DOCUMENTS shall be evidenced by a CHANGE ORDER.

6.2

When submitted for the ENGINEER'S review, SHOP DRAWINGS shall

bear the CONTRACTOR'S certification that he has reviewed, checked and

approved the SHOP DRAWINGS and that they are in conformance with

the requirements of the CONTRACT DOCUMENTS.

6.3

Portions of the WORK requiring a SHOP DRAWING or sample

submission shall not begin until the SHOP DRAWING or submission has

been approved by the ENGINEER. A copy of each approved SHOP

SECTION 00700 – GENERAL CONDITIONS

PAGE 6 OF 32

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

DRAWING and each approved sample shall be kept in good order by the

CONTRACTOR at the site and shall be available to the ENGINEER.

7.

8.

MATERIALS, SERVICES AND FACILITIES

7.1

It is understood that, except as otherwise specifically stated in the

CONTRACT DOCUMENTS, the CONTRACTOR shall provide and pay for

all materials, labor, tools, equipment, water, light, power, transportation,

supervision, temporary construction of any nature, and all other services

and facilities of any nature whatsoever necessary to execute, complete,

and deliver the WORK within the specified time.

7.2

Materials and equipment shall be so stored as to insure the preservation

of their quality and fitness for the WORK. Stored materials and equipment

to be incorporated in the WORK shall be located so as to facilitate prompt

inspection.

7.3

Manufactured articles, materials and equipment shall be applied, installed,

connected, erected, used, cleaned and conditioned as directed by the

manufacturer.

7.4

Materials, supplies and equipment shall be in accordance with samples

submitted by the CONTRACTOR and approved by the ENGINEER.

7.5

Materials, supplies or equipment to be incorporated into the WORK shall

not be purchased by the CONTRACTOR or the SUBCONTRACTOR

subject to a chattel mortgage or under a conditional sale contract or other

agreement by which an interest is retained by the seller.

SUBSTITUTIONS

8.1

Whenever a material, article or piece of equipment is identified on the

drawings or specifications by reference to brand name or catalogue

number, it shall be understood that this is referenced for the purpose of

defining the performance or other salient requirements and that other

products of equal capacities, quality and function shall be considered. The

CONTRACTOR may recommend the substitution of a material, article, or

piece of equipment of equal substance and function for those referred to in

the CONTRACT DOCUMENTS by reference to brand name or catalogue

number, and if, in the opinion of the ENGINEER, such material, article, or

piece of equipment is of equal substance and function to that specified,

the ENGINEER may approve its substitution and use by the

CONTRACTOR. Any cost differential shall be deductible from the

CONTRACT PRICE and the CONTRACT DOCUMENTS shall be

SECTION 00700 – GENERAL CONDITIONS

PAGE 7 OF 32

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

appropriately modified by CHANGE ORDER. The CONTRACTOR

warrants that if substitutes are approved, no major changes in the function

or general design of the PROJECT will result. Incidental changes or extra

component parts required to accommodate the substitute will be made by

the CONTRACTOR without a change in the CONTRACT PRICE or

CONTRACT TIME.

9.

PATENTS

9.1

10.

The CONTRACTOR shall pay all applicable royalties and license fees. He

shall defend all suits or claims for infringement of any patent rights and

save the OWNER harmless from loss on account thereof, except that the

OWNER shall be responsible for any such loss when a particular process,

design, or the product of a particular manufacturer or manufacturers is

specified, however if the CONTRACTOR has reason to believe that the

design, or product specified is an infringement of a patent, he shall be

responsible for such loss unless he promptly gives such information to the

ENGINEER.

SURVEYS, PERMITS, AND REGULATIONS

10.1

The OWNER shall furnish all boundary surveys and establish all base

lines for locating the principal component parts of the WORK together with

a suitable number of benchmarks adjacent to the WORK as shown in the

CONTRACT DOCUMENTS. From the information provided by the

OWNER, unless otherwise specified in the CONTRACT DOCUMENTS,

the CONTRACTOR shall develop and make all detail surveys needed for

construction such as slope stakes, batter boards, stakes for pile locations

and other working points, lines, elevations and cut sheets.

10.2

The CONTRACTOR shall carefully preserve bench marks, reference

points and stakes and, in case of willful or careless destruction, he shall

be charged with the resulting expense and shall be responsible for any

mistakes that may be caused by their unnecessary loss or disturbance.

10.3

Permits and licenses of a temporary nature necessary for the prosecution

of the WORK shall be secured and paid for by the CONTRACTOR unless

otherwise specified in the CONTRACT DOCUMENTS. Permits, licenses

and easements for permanent structures or permanent changes in

existing facilities shall be secured and paid for by the OWNER, unless

otherwise specified. The CONTRACTOR shall give all notices and comply

with all laws, ordinances, rules and regulations bearing on the conduct of

the WORK as drawn and specified. If the CONTRACTOR observes that

the CONTRACT DOCUMENTS are at variance therewith, he shall

SECTION 00700 – GENERAL CONDITIONS

PAGE 8 OF 32

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

promptly notify the ENGINEER in writing, and any necessary changes

shall be adjusted as provided in Section 30 - "CHANGES IN THE WORK".

11.

LAWS AND REGULATIONS AFFECTING WORK

11.1

12.

TAXES

12.1

13.

The CONTRACTOR will pay all sales, consumer, use and other similar

taxes required by the law of the place where the WORK is performed.

PROTECTION OF WORK, PROPERTY AND PERSONS

13.1

14.

The CONTRACTOR shall at all times observe and comply with Federal,

State, City, County and Tribal laws, ordinances and regulations which in

any manner affect the conduct of the work; and all such orders and

decrees as exist at the present and which may be enacted later by

legislative bodies or tribunals having legal jurisdiction or authority over the

work. No pleas of misunderstanding or ignorance thereof will be

considered. The CONTRACTOR shall be wholly responsible for any claim

or liability arising from or based on the violation of any such law,

ordinance, regulation, order or decree.

The CONTRACTOR will be responsible for initiating, maintaining and

supervising all safety precautions and programs in connection with the

WORK. He will take all necessary precautions for the safety of and will

provide the necessary protection to prevent damage, injury or loss to all

employees on the WORK and other persons who may be affected

thereby, all the WORK and all materials or equipment to be incorporated

therein, whether in storage on or off the site, and other property at the site

or adjacent thereto.

PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS

14.1

The CONTRACTOR shall preserve and protect all structures, equipment,

and vegetation (such as trees, shrubs, and grass) on or adjacent to the

work site, which are not to be removed and which do not unreasonably

interfere with the work required under this contract The CONTRACTOR

shall remove trees only when specifically authorized to do so, and shall

avoid damaging vegetation that will remain in place. If any limbs or

branches of trees are broken during contract performance, or by the

careless operation of equipment, or by workmen, the CONTRACTOR shall

trim those limbs or branches with a clean cut and paint the cut with a treepruning compound as directed by the ENGINEER.

SECTION 00700 – GENERAL CONDITIONS

PAGE 9 OF 32

KOOTENAI TRIBE

14.2

15.

16.

WATER MAIN LOOP CONSTRUCTION

The CONTRACTOR shall protect from damage all existing improvements

and utilities (1) on or near the work site and (2) on adjacent property of a

third party, the locations of which are made known to or should be known

by the CONTRACTOR. The existence and location of utilities are not

guaranteed by the OWNER and shall be investigated and verified in the

field by the CONTRACTOR before commencing construction activities in

any particular area. The CONTRACTOR shall repair any damage to those

facilities, including those that are the property of a third party, resulting

from failure to comply with the requirements of this contract or failure to

exercise reasonable care in performing the work. If the CONTRACTOR

fails or refuses to repair the damage promptly, the OWNER may have the

necessary work performed and charge the cost to the CONTRACTOR.

OPERATIONS AND STORAGE AREAS

15.1

The CONTRACTOR shall confine all operations (including storage of

materials) to areas authorized or approved by the OWNER. The

CONTRACTOR shall hold and save the OWNER and its representatives,

free and harmless from liability of any nature occasioned by the

CONTRACTOR'S performance.

15.2

Temporary buildings (e.g., storage sheds, shops, offices) and utilities may

be erected by the CONTRACTOR only with the approval of the OWNER

and shall be built with labor and materials furnished by the

CONTRACTOR without expense to the OWNER. The temporary buildings

and utilities shall remain the property of the CONTRACTOR and shall be

removed by the CONTRACTOR at its expense upon completion of the

work. Only with the written consent of the OWNER may the buildings and

utilities be abandoned and not removed.

15.3

The CONTRACTOR shall use only established roadways, or use

temporary roadways constructed by the CONTRACTOR when and as

authorized by the OWNER. In such case, the CONTRACTOR shall

minimize disruption and delays to traffic in the affected areas. When

materials are transported in prosecuting the work vehicles shall not be

loaded beyond the loading capacity recommended by the manufacturer of

the vehicle or prescribed by any Federal, State, or local law or regulation.

When it is necessary to cross curbs or sidewalks, the CONTRACTOR

shall protect them from damage. The CONTRACTOR shall repair or pay

for the repair of any damaged curbs, sidewalks, or roads.

INSURANCE

SECTION 00700 – GENERAL CONDITIONS

PAGE 10 OF 32

KOOTENAI TRIBE

16.1

WATER MAIN LOOP CONSTRUCTION

The CONTRACTOR shall purchase and maintain such insurance as will

protect him from claims set forth below which may arise out of or result

from the CONTRACTOR'S execution of the WORK, whether such

execution be by himself or by any SUBCONTRACTOR or by anyone

directly or indirectly employed by any of them, or by anyone for whose

acts any of them may be liable:

16.1.1

Claims under workmen's compensation, disability benefit

and other

similar employee benefit acts;

16.1.2

Claims for damages because of bodily injury, occupational

sickness or disease, or death of his employees;

16.1.3

Claims for damages because of bodily injury, sickness or

disease, or death of any person other than his employees;

16.1.4

Claims for damages insured by usual personal injury liability

coverage which are sustained (1) by any person as a result

of an offense directly or indirectly related to the employment

of such person by the CONTRACTOR or (2) by any other

person; and

16.1.5

Claims for damages because of injury to or destruction of

tangible property, including loss of use resulting therefrom.

16.2

Certificates of Insurance acceptable to the OWNER shall be filed with the

OWNER prior to commencement of the WORK. These Certificates shall

contain a provision that coverages afforded under the Policies will not be

cancelled unless at least fifteen (15) days prior WRITTEN NOTICE has

been given to the OWNER.

16.3

The CONTRACTOR shall procure and maintain, at his own expense,

during the CONTRACT TIME, liability insurance as hereinafter specified;

16.3.1

CONTRACTOR'S General Public Liability and Property

Damage Insurance including vehicle coverage issued to the

CONTRACTOR and protecting him from all claims for

personal injury, including death, and all claims for

destruction of or damage to any property, arising out of or in

connection with any operations under the CONTRACT

DOCUMENTS, whether such operations be by himself or by

any SUBCONTRACTOR under him, or anyone directly or

indirectly employed by the CONTRACTOR or by a

SECTION 00700 – GENERAL CONDITIONS

PAGE 11 OF 32

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

SUBCONTRACTOR under him. Insurance shall be written

with a limit of liability of not less than $500,000 for all

damages arising out of bodily injury, including death, at any

time resulting therefrom, sustained by any one person in any

one accident; and a limit of liability of not less than

$1,000,000 aggregate for any such damages sustained by

two or more persons in any one accident. Insurance shall be

written with a limit of liability of not less than $200,000 for all

property damage sustained by any one person in any one

accident; and a limit of liability of not less than $500,000

aggregate for any such damage sustained by two or more

persons in any one accident.

16.3.2

The CONTRACTOR shall acquire and maintain, if

applicable, Fire and Extended Coverage insurance upon the

PROJECT to the full insurable value thereof for the benefit of

the OWNER, the CONTRACTOR, and

SUBCONTRACTORS as their interest may appear. This

provision shall in no way release the CONTRACTOR or

CONTRACTOR'S surety from obligations under the

CONTRACT DOCUMENTS to fully complete the PROJECT.

16.4

The CONTRACTOR shall procure and maintain, at his own expense,

during the CONTRACT TIME, in accordance with the provisions of the

laws of the state in which the work is performed, Workmen's

Compensation Insurance, including occupational disease provisions, for

all of his employees at the site of the PROJECT and in case any work is

sublet, the CONTRACTOR shall require such SUBCONTRACTOR

similarly to provide Workmen's Compensation Insurance, including

occupational disease provisions for all of the latter's employees unless

such employees are covered by the protection afforded by the

CONTRACTOR. In case any class of employees engaged in hazardous

work under this contract at the site of the PROJECT is not protected under

Workmen's Compensation statute, the CONTRACTOR shall provide, and

shall cause each SUBCONTRACTOR to provide, adequate and suitable

insurance for the protection of his employees not otherwise protected.

16.5

The CONTRACTOR shall secure, if applicable, "All Risk" type Builder's

Risk Insurance for WORK to be performed. Unless specifically authorized

by the OWNER the amount of such insurance shall not be less than the

CONTRACT PRICE totaled in the BID. The policy shall cover not less than

the losses due to fire, explosion, hail, lightning, vandalism, malicious

mischief, wind, collapse, riot, aircraft, and smoke during the CONTRACT

TIME, and until the WORK is accepted by the OWNER. The policy shall

SECTION 00700 – GENERAL CONDITIONS

PAGE 12 OF 32

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

name as the insured the CONTRACTOR, the ENGINEER, and the

OWNER.

17.

18.

INDEMNIFICATION

17.1

The CONTRACTOR will indemnify and hold harmless the OWNER and

the ENGINEER and their agents and employees from and against all

claims, damages, losses and expenses including attorney's fees arising

out of or resulting from the performance of the WORK, provided that any

such claims, damage, loss or expense is attributable to bodily injury,

sickness, disease or death, or to injury to or destruction of tangible

property including the loss of use resulting therefrom; and is caused in

whole or in part by any negligent or willful act or omission of the

CONTRACTOR, and SUBCONTRACTOR, anyone directly or indirectly

employed by any of them or anyone for whose acts any of them may be

liable.

17.2

In any and all claims against the OWNER or the ENGINEER or any of

their agents or employees, by any employee of the CONTRACTOR, any

SUBCONTRACTOR anyone directly or indirectly employed by any of

them, or anyone for whose acts any of them may be liable, the

indemnification obligation shall not be limited in any way by any limitation

on the amount or type of damages, compensation or benefits payable by

or for the CONTRACTOR or any SUBCONTRACTOR under Workmen's

Compensation Acts, disability benefit acts or other employee benefits acts.

17.3

The obligation of the CONTRACTOR under this paragraph shall not

extend to the liability of the ENGINEER, his agents or employees arising

out of the preparation or approval of maps, DRAWINGS, opinions, reports,

surveys, CHANGE ORDERS, designs or SPECIFICATIONS.

CONTRACT SECURITY (For Contracts Greater than $100,000.00)

18.1

The CONTRACTOR shall submit with the BID OFFER with a 5% Bid

Bond.

18.2

The CONTRACTOR shall within ten (10) days after the receipt of the

NOTICE OF AWARD furnish the OWNER with a Performance Bond and a

Payment Bond in penal sums equal to the amount of the CONTRACT

PRICE, conditioned upon the performance by the CONTRACTOR of all

undertakings, covenants, terms, conditions and agreements of the

CONTRACT DOCUMENTS, and upon the prompt payment by the

CONTRACTOR to all persons supplying labor and materials in the

prosecution of the WORK provided by the CONTRACT DOCUMENTS.

SECTION 00700 – GENERAL CONDITIONS

PAGE 13 OF 32

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

Such BONDS shall be executed by the CONTRACTOR and a corporate

bonding company licensed to transact such business in the state in which

the WORK is to be performed. The expense of these BONDS shall be

borne by the CONTRACTOR. If at any time a surety on any such BOND is

declared as bankrupt or loses its right to do business in the state in which

the WORK is to be performed, the CONTRACTOR shall within ten (10)

days after notice from the OWNER to do so, substitute an acceptable

BOND (or BONDS) in such form and sum and signed by such other surety

or sureties as may be satisfactory to the OWNER. The premiums on such

BOND shall be paid by the CONTRACTOR. No further payments shall be

deemed due nor shall be made until the new surety or sureties shall have

furnished an acceptable BOND to the OWNER.

19.

ACCIDENT PREVENTION AND SAFETY PROGRAM

19.1

The CONTRACTOR shall be solely and completely responsible for

conditions of the jobsite, including safety of all persons, including

employees, and property during performance of the work. This

requirement shall apply continuously and not be limited to normal working

hours. Safety provisions shall conform to U.S. Department of Labor

(OSHA), and all other applicable Federal, State, County, and local laws,

ordinances, codes, the requirements set forth below, and any regulations

that may be detailed in other parts of these documents. Where any of

these are in conflict, the more stringent requirement shall be followed. The

CONTRACTOR's failure to thoroughly familiarize himself with the

aforementioned safety provisions shall not relieve him from compliance

with the obligations and penalties set forth herein.

19.2

The OWNER or his Representative will notify the CONTRACTOR of any

observed non-compliance with the foregoing provisions and the action to

be taken. The CONTRACTOR shall, upon receipt of such notice,

immediately take corrective action. If the CONTRACTOR fails or refuses

to comply promptly, the OWNER may issue an order stopping all or part of

the WORK until satisfactory corrective action has been taken. No part of

the time lost due to any such stop orders shall be made the subject of

claims for extension of time, or for excess costs or damages by the

CONTRACTOR.

19.3

The CONTRACTOR shall develop and maintain for the duration of this

Contract, a safety program that will effectively incorporate and implement

all required safety provisions. The CONTRACTOR shall appoint an

employee who is qualified and authorized to supervise and enforce

compliance with the safety program.

SECTION 00700 – GENERAL CONDITIONS

PAGE 14 OF 32

KOOTENAI TRIBE

20.

19.4

The CONTRACTOR as a part of his safety program, shall maintain at his

office or other well-known place at the jobsite, safety equipment applicable

to the WORK as prescribed by the aforementioned authorities, all articles

necessary for giving first aid to the injured, and shall establish the

procedure for the immediate removal to a hospital or a doctor's care of

persons who may be injured on the jobsite.

19.5

If death or serious injuries or serious damages are caused, the accident

shall be reported immediately by telephone or messenger to both the

ENGINEER and OWNER. In addition, the CONTRACTOR must promptly

report in writing to appropriate authorities and the OWNER'S

representative all accidents whatsoever arising out of, or in connection

with, the performance of the WORK whether on, or adjacent to, the site,

giving full details and statements of witnesses. If a claim is made by

anyone against the CONTRACTOR or any subcontractor on account of

any accident, the CONTRACTOR shall promptly report the facts in writing

to the OWNER giving full details of the claim.

19.6

The CONTRACTOR shall provide, erect, and maintain all necessary

barricades, suitable and sufficient lights, danger signals, signs and other

traffic control devices, and shall take all necessary. precautions for the

protection of the WORK and safety of the public. Highways closed to

traffic shall be protected by effective barricades, and obstructions shall be

illuminated during the hours of darkness. Suitable warning signs shall be

provided to control and direct traffic properly. The CONTRACTOR shall

erect warning signs in advance of any place on the project where

operations may interfere with the use of the road by traffic, and at all

intermediate points where the new work crosses or coincides with an

existing road.

19.7

Compliance with the requirements of this provision by subcontractors will

be the responsibility of the CONTRACTOR.

TEMPORARY SANITARY FACILITIES

20.1

21.

WATER MAIN LOOP CONSTRUCTION

The CONTRACTOR shall provide and maintain necessary sanitary

conveniences for the use of those employed on or about the WORK,

properly secluded from public observation in such a manner and at such

points as shall be approved by the OWNER'S representative, and their

use shall be strictly enforced.

SUPERVISION BY CONTRACTOR

21.1

The CONTRACTOR will supervise and direct the WORK. He will be solely

SECTION 00700 – GENERAL CONDITIONS

PAGE 15 OF 32

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

responsible for the means, methods, techniques, sequences and

procedures of construction. The CONTRACTOR will employ and maintain

on the WORK a qualified supervisor or superintendent who shall have

been designated in writing by the CONTRACTOR as the

CONTRACTOR'S representative at the site. The supervisor shall have full

authority to act on behalf of the CONTRACTOR and all communications

given to the supervisor shall be as binding as if given to the

CONTRACTOR. The supervisor shall be present on the site at all times

as required to perform adequate supervision and coordination of the

WORK.

22.

23.

SUBCONTRACTING

22.1

The CONTRACTOR may utilize the services of specialty

SUBCONTRACTORS on those parts of the WORK which, under normal

contracting practices, are performed by specialty SUBCONTRACTORS.

22.2

The CONTRACTOR must perform at least thirty three (33%) of the total

amount of the WORK using the CONTRACTOR'S own work force and

equipment The CONTRACTOR shall not award WORK to

SUBCONTRACTOR(s), in excess of sixty seven (67%) percent of the

CONTRACT PRICE, without prior written approval of the OWNER.

22.3

The CONTRACTOR shall be fully responsible to the OWNER for the acts

and omissions of his SUBCONTRACTORS, and of persons either directly

or indirectly employed by them, as he is for the acts and omissions of

persons directly employed by him.

22.4

The CONTRACTOR shall cause appropriate provisions to be inserted in

all subcontracts relative to the WORK to bind SUBCONTRACTORS to the

CONTRACTOR by the terms of the CONTRACT DOCUMENT insofar as

applicable to the WORK of SUBCONTRACTORS and to give the

CONTRACTOR the same power as regards terminating any subcontract

that the OWNER may exercise over the CONTRACTOR under any

provision of the CONTRACT DOCUMENTS.

22.5

Nothing contained in this CONTRACT shall create any contractual relation

between any SUBCONTRACTOR and the OWNER

SEPARATE CONTRACTS

23.1

The OWNER reserves the right to let other contracts in connection with

this PROJECT. The CONTRACTOR shall afford other CONTRACTORS

reasonable opportunity for the introduction and storage of their materials

SECTION 00700 – GENERAL CONDITIONS

PAGE 16 OF 32

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

and the execution of their WORK, and shall properly connect and

coordinate his WORK with theirs. If the proper execution or results of any

part of the CONTRACTOR'S WORK depends upon the WORK of any

other CONTRACTOR, the CONTRACTOR shall inspect and promptly

report to the ENGINEER any defects in such WORK that render it

unsuitable for such proper execution and results.

24.

23.2

The OWNER may perform additional WORK related to the PROJECT by

himself, or he may let other contracts containing provisions similar to

these. The CONTRACTOR will afford the other CONTRACTORS who are

parties to such Contracts (or the OWNER, if he is performing the

additional WORK himself), reasonable opportunity for the introduction and

storage of materials and equipment and the execution of WORK. and shall

properly connect and coordinate his WORK with theirs.

23.3

If the performance of additional WORK by other CONTRACTORS or the

OWNER is not noted in the CONTRACT DOCUMENTS prior to the

execution of the CONTRACT, written notice thereof shall be given to the

CONTRACTOR prior to starting any such additional WORK. If the

CONTRACTOR believes that the performance of such additional WORK

by the OWNER or others involves him in additional expense or entitles

him to an extension of the CONTRACT TIME, he may make a claim

therefore as provided in Sections 30 and 31.

TIME FOR COMPLETION AND LIQUIDATED DAMAGES

24.1

The TIME FOR COMPLETION of the WORK is an essential condition of

the CONTRACT DOCUMENTS. The TIME FOR COMPLETION appears

in the Special Provisions. The WORK embraced shall be commenced on a

date specified in the NOTICE TO PROCEED.

24.2

The CONTRACTOR will proceed with the WORK at such rate of progress

to insure full completion within the TIME FOR COMPLETION. It is

expressly understood and agreed, by and between the CONTRACTOR

and the OWNER, that TIME FOR COMPLETION of the WORK under the

CONTRACT is a reasonable time, taking into consideration the average

climatic and economic conditions and other factors prevailing in the

locality of the WORK.

24.3

If the CONTRACTOR shall fail to complete the WORK within the TIME

FOR COMPLETION, or extension of time granted by the OWNER, then

the CONTRACTOR will pay to the OWNER the amount for liquidated

damages as specified in the Special Provisions for each calendar day that

the work shall be incomplete after the date established by the TIME FOR

SECTION 00700 – GENERAL CONDITIONS

PAGE 17 OF 32

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

COMPLETION.

24.4

25.

The CONTRACTOR shall not be charged with liquidated damages or any

excess cost when the delay in completion of the WORK is due to the

following, and the CONTRACTOR has promptly given WRITTEN NOTICE

of such delay to the OWNER or ENGINEER.

24.4.1

To any preference, priority or allocation order duly issued by

the OWNER.

24.4.2

To unforeseeable causes beyond the control and without the

fault or negligence of the CONTRACTOR, including but not

restricted to, acts of God, or of the public enemy, acts of the

OWNER, acts of another CONTRACTOR in the performance

of a contract with the OWNER, fires, floods, epidemics,

quarantine restrictions, strikes, freight embargoes, and

abnormal and unforeseeable weather; and

24.4.3

To any delays of SUBCONTRACTORS occasioned by any

of the causes specified in paragraphs 24.4.1 and 24.4.2 of

this article.

PROGRESS SCHEDULES AND REQUIREMENTS FOR COMPLIANCE

25.1

The CONTRACTOR shall within 10 days of receipt of NOTICE TO

PROCEED, submit to the OWNER through the ENGINEER for approval a

practicable schedule, showing the order in which the CONTRACTOR

proposes to carry on the WORK, the dates on which he will start the major

items of work (including procurement of materials, plant and equipment)

and the contemplated dates for completing the same. The schedule shall

be prepared on the form entitled "Contract Progress Schedule," a copy of

which is included in the contract.

25.2

If, in the opinion of the OWNER, the CONTRACTOR falls behind the

progress schedule, the CONTRACTOR shall take such steps as may be

necessary to assure performance within the allowable TIME FOR

COMPLETION. The CONTRACTOR may propose for approval by the

OWNER measures such as increasing number of workers, number of

shifts, or overtime operations, days of work, or the amount of construction

plant, or all of them. The OWNER may require the CONTRACTOR to

submit for approval such supplementary schedule or schedules necessary

to demonstrate that the WORK shall be performed within the allowable

TIME FOR COMPLETION, all without additional cost to the OWNER.

SECTION 00700 – GENERAL CONDITIONS

PAGE 18 OF 32

KOOTENAI TRIBE

25.3

26.

27.

WATER MAIN LOOP CONSTRUCTION

Failure of the CONTRACTOR to comply with the requirements of this

provision shall be grounds for determination that the CONTRACTOR is

not prosecuting the work with such diligence as will insure completion

within the specified TIME FOR COMPLETION. Upon such determination

the OWNER may terminate the CONTRACTOR'S right to proceed with the

WORK, or any separable part thereof in accordance with Section 27

entitled "Suspension of Work, Termination and Delay".

LAND AND RIGHTS-OF- WAY

26.1

Prior to issuance of NOTICE TO PROCEED, the OWNER shall obtain all

land and rights-of-way necessary for carrying out and for the completion of

the WORK to be performed pursuant to the CONTRACT DOCUMENTS,

unless otherwise mutually agreed.

26.2

The OWNER shall provide to the CONTRACTOR information which

delineates and describes the lands owned and rights-of-way acquired.

26.3

The CONTRACTOR shall provide at his own expense and without liability

to the OWNER any additional land and access thereto that the

CONTRACTOR may desire for temporary construction facilities, or for

storage of materials.

SUSPENSION OF WORK, TERMINATION AND DELAY

27.1

The OWNER may suspend the WORK or any portion thereof for a period

of not more than ninety (90) days or such further time as agreed upon by

the CONTRACTOR, by WRITTEN NOTICE to the CONTRACTOR and the

ENGINEER which notice shall fix the date on which WORK shall be

resumed. The CONTRACTOR will resume that WORK on the date so

fixed. The CONTRACTOR will be allowed an increase in the CONTRACT

PRICE or an extension of the CONTRACT TIME, or both, directly

attributable to any suspension.

27.2

If the CONTRACTOR is adjudged as bankrupt or insolvent, or if he makes

a general assignment for the benefit of his creditors or if a trustee or

receiver is appointed for the CONTRACTOR or for any of his property, or

if he files a petition to take advantage of any debtor's act, or to reorganize

under the bankruptcy or applicable laws, or if he repeatedly fails to supply

sufficient skilled workmen or suitable materials or equipment, or if he

repeatedly fails to make prompt payments to SUBCONTRACTORS or for

labor, materials or equipment or if he disregards laws, ordinances, rules,

regulations or orders of any public body having jurisdiction of the WORK,

or if he disregards the authority of the ENGINEER, or if he otherwise

SECTION 00700 – GENERAL CONDITIONS

PAGE 19 OF 32

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

violates any provision of the CONTRACT DOCUMENTS then the OWNER

may, without prejudice to any other right or remedy and after giving the

CONTRACTOR and his surety a minimum of ten (10) days from delivery

of a WRITTEN NOTICE, terminate the services of the CONTRACTOR and

take possession of the PROJECT and of all materials, equipment, tools,

construction equipment and machinery thereon owned by the

CONTRACTOR, and finish the WORK by whatever method he may deem

expedient. In such case the CONTRACTOR shall not be entitled to

receive any further payment until the WORK is finished. If the unpaid

balance of the CONTRACT PRICE exceeds the direct and indirect costs

of completing the PROJECT, including compensation for additional

professional services, such excess SHALL BE PAID TO THE

CONTRACTOR. If such costs exceed such unpaid balance, the

CONTRACTOR will pay the difference to the OWNER. Such costs

incurred by the OWNER will be determined by the ENGINEER and

incorporated in a CHANGE ORDER.

27.3

Where the CONTRACTOR'S services have been so terminated by the

OWNER, said termination shall not affect any right of the OWNER against

the CONTRACTOR then existing or which may thereafter accrue. Any

retention or payment of monies by the OWNER due the CONTRACTOR

will not release the CONTRACTOR from compliance with the CONTRACT

DOCUMENTS.

27.4

After ten (10) days from delivery of a WRITTEN NOTICE to the

CONTRACTOR and the ENGINEER, the OWNER may without cause and

without prejudice to any other right or remedy, elect to abandon the

PROJECT and terminate the CONTRACT. In such case, the

CONTRACTOR shall be paid for all WORK executed and any expense

sustained plus reasonable profit. If this contract is terminated by the

OWNER without cause, the rights, duties, and obligations of the parties,

including compensation to the CONTRACTOR, shall be in accordance

with Part 49 of the Federal Acquisition Regulation in effect on the date of

this contract.

27.5

If, through no act or fault of the CONTRACTOR, the WORK is suspended

for a period of more than ninety (90) days by the OWNER or under an

order of court or other public authority, or the ENGINEER fails to act on

any request for payment within thirty (30) days after it is submitted, or the

OWNER fails to pay the CONTRACTOR substantially the sum approved

by the ENGINEER or awarded by arbitrators within thirty (30) days of its

approval and presentation, then the CONTRACTOR may, after ten (10)

days from delivery of a WRITTEN NOTICE to the OWNER and the

ENGINEER, terminate the CONTRACT and recover from the OWNER

SECTION 00700 – GENERAL CONDITIONS

PAGE 20 OF 32

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

payment for all WORK executed and all expenses sustained. In addition

and in lieu of terminating the CONTRACT, if the ENGINEER has failed to

act on a request for payment or if the OWNER has failed to make any

payment as aforesaid, the CONTRACTOR may upon ten (10) days

WRITTEN NOTICE to the OWNER and the ENGINEER stop the WORK

until he has been paid all amounts then due, in which event and upon

resumption of the WORK, CHANGE ORDERS shall be issued for

adjusting the CONTRACT' PRICE or extending the CONTRACT TIME or

both to compensate for the costs and delays attributed to the stoppage of

the WORK.

27.6

28.

If the performance of all or any portion of the WORK is suspended,

delayed, or interrupted as a result of a failure of the OWNER or

ENGINEER to act within the time specified in the CONTRACT

DOCUMENTS, or if no time is specified, within a reasonable time, an

adjustment in the CONTRACT PRICE or an extension of the CONTRACT

TIME, or both, shall be made by CHANGE ORDER to compensate the

CONTRACTOR for the costs and delays necessarily caused by the failure

of the OWNER or ENGINEER.

INSPECTION AND TESTING

28.1

All materials and equipment used in the construction of the PROJECT

shall be subject to adequate inspection and testing in accordance with

generally accepted standards, as required and defined in the CONTRACT

DOCUMENTS.

28.2

The OWNER shall provide all inspection and testing services not required

by the CONTRACT DOCUMENTS.

28.3

The CONTRACTOR shall provide at his expense the testing and

inspection services required by the CONTRACT DOCUMENTS.

28.4

If the CONTRACT DOCUMENTS, laws, ordinances, rules, regulations or

orders of any public authority having jurisdiction require any WORK to

specifically be inspected, tested, or approved by someone other than the

CONTRACTOR, the CONTRACTOR will give the ENGINEER timely

notice of readiness. The CONTRACTOR will then furnish the ENGINEER

the required certificates of inspection, testing or approval.

28.5

Inspections, tests or approvals by the ENGINEER or others shall not

relieve the CONTRACTOR from his obligations to perform the WORK in

accordance with the requirements of the CONTRACT DOCUMENTS.

SECTION 00700 – GENERAL CONDITIONS

PAGE 21 OF 32

KOOTENAI TRIBE

29.

30.

WATER MAIN LOOP CONSTRUCTION

28.6

The ENGINEER and his representatives will at all times have access to

the WORK. In addition, authorized representatives and agents of any

participating Federal or state agency shall be permitted to inspect all work,

materials, payrolls, records of personnel, invoices of materials, and other

relevant data and records. The CONTRACTOR will provide proper

facilities for such access and observation of the WORK and also for any

inspection, or testing thereof.

28.7

If any WORK is covered contrary to the written instructions of the

ENGINEER it must, if requested by the ENGINEER, be uncovered for his

observation and replaced at the CONTRACTOR'S expense.

28.8

If the ENGINEER considers it necessary or advisable that covered WORK

be inspected or tested by others, the CONTRACTOR, at the ENGINEER'S

request, will uncover, expose or otherwise make available for observation,

inspection or testing as the ENGINEER may require, that portion of the

WORK in question, furnishing all necessary labor, materials, tools and

equipment. If it is found that such WORK is defective, the CONTRACTOR

will bear all the expenses of such uncovering, exposure, observation,

inspection and testing and of satisfactory reconstruction. If, however,

such WORK is not found to be defective, the CONTRACTOR will be

allowed an increase in the CONTRACT PRICE or an extension of the

CONTRACT TIME, or both, directly attributable to such uncovering,

exposure, observation, inspection, testing and reconstruction and an

appropriate CHANGE ORDER shall be issued.

CORRECTION OF WORK

29.1

The CONTRACTOR shall promptly remove from the premises all WORK

rejected by the ENGINEER for failure to comply with the CONTRACT

DOCUMENTS, whether incorporated in the construction or not, and the

CONTRACTOR shall promptly replace and re-execute the WORK in

accordance with the CONTRACT DOCUMENTS and without expense to

the OWNER and shall bear the expense of making good all WORK of

other CONTRACTORS destroyed or damaged by such removal or

replacement.

29.2

All removal and replacement WORK shall be done at the

CONTRACTOR'S expense. If the CONTRACTOR does not take action to

remove such rejected WORK within ten (10) days after receipt of

WRITTEN NOTICE, the OWNER may remove such WORK and store the

materials at the expense of the CONTRACTOR.

CHANGES IN THE WORK

SECTION 00700 – GENERAL CONDITIONS

PAGE 22 OF 32

KOOTENAI TRIBE

31.

30.1

The OWNER may at any time, as the need arises, order changes within

the scope of the WORK without invalidating the Agreement. If such

changes increase or decrease the amount due under the CONTRACT

DOCUMENTS, or in the time required for performance of the WORK, an

equitable adjustment shall be authorized by CHANGE ORDER.

30.2

The ENGINEER, also, may at any time, by issuing a FIELD ORDER,

make changes in the details of the WORK. The CONTRACTOR shall

proceed with the performance of any changes in the WORK so ordered by

the ENGINEER unless the CONTRACTOR believes that such FIELD

ORDER entitles him to a change in CONTRACT PRICE or TIME, or both,

in which event he shall give the ENGINEER WRITTEN NOTICE thereof

within seven (7) days after the receipt of the ordered change. Thereafter

the CONTRACTOR shall document the basis for the change in

CONTRACT PRICE or TIME within thirty (30) days. The CONTRACTOR

shall not execute such. changes pending the receipt of an executed

CHANGE ORDER or further instruction from the OWNER.

CHANGES IN CONTRACT PRICE

31.1

32.

WATER MAIN LOOP CONSTRUCTION

The CONTRACT PRICE may be changed only by a CHANGE ORDER.

The value of any WORK covered by a CHANGE ORDER or of any claim

for increase or decrease in the CONTRACT PRICE shall be determined

by one or more of the following methods in the order of precedence listed

below:

a.

Unit prices previously approved.

b.

An agreed lump sum

c.

The actual cost for labor, direct overhead, materials, supplies,

equipment, and other services necessary to complete the work. In addition

there shall be added an amount to be agreed upon but not to exceed

fifteen (15) percent of the actual cost of the WORK to cover the cost of

general overhead and profit.

DIFFERING SITE CONDITIONS

32.1

The CONTRACTOR shall promptly, and before such conditions are

disturbed, except in the event of an emergency, notify the OWNER by

WRITTEN NOTICE of:

32.1.1

Subsurface or latent physical conditions at the site differing

materially from those indicated in the CONTRACT

DOCUMENTS; or

SECTION 00700 – GENERAL CONDITIONS

PAGE 23 OF 32

KOOTENAI TRIBE

32.1.2

32.2

33.

34.

WATER MAIN LOOP CONSTRUCTION

Unknown physical conditions at the site, of an unusual

nature, differing materially from those ordinarily encountered

and generally recognized as inherent in WORK of the

character provided for in the CONTRACT DOCUMENTS.

The OWNER shall promptly investigate the conditions, and if he finds that

such conditions do so materially differ and cause an increase or decrease

in the cost of, or in the time required for, performance of the WORK, an

equitable adjustment shall be made and the CONTRACT DOCUMENTS

shall be modified by a CHANGE ORDER. Any claim of the

CONTRACTOR for adjustment hereunder shall not be allowed unless he

has given the required WRITTEN NOTICE; provided that the OWNER

may, if he determines the facts so justify, consider and adjust any such

claims asserted before the date of final payment.

USE AND POSSESSION PRIOR TO COMPLETION

33.1

The OWNER shall have the right to take possession of or use any

completed or partially completed part of the work. Before taking

possession of or using any work, the OWNER shall furnish the Contractor

a list of items of work remaining to be performed or corrected on those

portions of the work that the OWNER intends to take possession of or use.

However, failure of the OWNER to list any item of work shall not relieve

the Contractor of responsibility for complying with the terms of the

contract. The OWNER'S possession or use shall not be deemed an

acceptance of any work under the contract

33.2

While the OWNER has such possession or use, the Contractor shall be

relieved of the responsibility for the loss of or damage to the work resulting

directly from the OWNER'S possession or use. If prior possession or use

by the OWNER delays the progress of the work or causes additional

expense to the Contractor, an adjustment shall be made in the contract

price, the time of completion or both, and the contract shall be modified in

writing accordingly.

CLEANUP AND FINISH GRADING

34.1

The CONTRACTOR shall restore all areas disturbed by construction to a

condition at least equal to that existing prior to construction. Excess

construction materials, equipment, tools, waste excavation, and rubbish

shall be removed. Excavated areas shall be finish graded to provide

drainage as required by the drawings and specifications, or in the absence

of specific requirements, to provide drainage away from the facilities

constructed and to restore original drainage patterns in existence prior to

SECTION 00700 – GENERAL CONDITIONS

PAGE 24 OF 32

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

construction and to provide drainage away from excavated areas and

installed facilities.

35.

MEASUREMENT AND PAYMENT

35.1

36.

VARIATION IN ESTIMATED QUANTITIES

36.1

37.

Completed items of work shall be measured and paid for in accordance

with the requirements listed in the Bid Schedule. Payment shall be based

on the actual quantities completed and shall represent full compensation

under the contract. The price paid for the completed item of work shall

include full compensation for furnishing all labor, materials, (other than

that furnished by the OWNER), tools, equipment, and performing all work

required by the provisions of the contract to furnish and install the item of

work, complete in place. In all cases, the finished product shall be a

complete, operational system or component. The price for the completed

item of work shall also include all applicable state and local sales and

other taxes.

If the quantity of a unit-priced item in this CONTRACT is an estimated

quantity and the actual quantity of the unit-priced item varies more than 25

percent above or below the estimated quantity, an equitable adjustment in

the contract price shall be made upon demand of either party. The

equitable adjustment shall be based upon any increase or decrease in

costs due solely to the variation above 125 percent or below 75 percent of

the estimated quantity. If the quantity variation is such as to cause an

increase in the time necessary for completion, the CONTRACTOR may

request, in writing, an extension of time, to be received by the OWNER

within 10 days from the beginning of the delay, or within such further

period as may be granted by the OWNER before the date of final

settlement of the CONTRACT. Upon the receipt of a written request for an

extension, the OWNER shall ascertain the facts and make any appropriate

adjustment for extending the completion date.

PAYMENTS TO CONTRACTOR

37.1

The CONTRACTOR will submit to the ENGINEER a partial payment

estimate filled out and signed by the CONTRACTOR covering the WORK

performed during the period covered by the partial payment estimate and

supported by such data as the ENGINEER may reasonably require. The

request for payment may also include an allowance for the cost of such

major materials and equipment which are suitably stored either at or near

the site. If payment is requested on the basis of materials and equipment

not incorporated in the WORK but delivered and suitably stored at or near

SECTION 00700 – GENERAL CONDITIONS

PAGE 25 OF 32

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

the site, the partial payment estimate shall also be accompanied by such

supporting data, satisfactory to the OWNER, as will establish the

OWNER'S title to the material and equipment and protect his interest

therein, including applicable insurance. The ENGINEER will, within ten

(10) days after receipt of each partial payment estimate, either indicate in

writing his approval of payment and present the partial payment estimate

to the OWNER, or return the partial payment estimate to the

CONTRACTOR indicating in writing his reasons for refusing to approve

payment. In the latter case, the CONTRACTOR may make the necessary

corrections and resubmit the partial payment estimate. The OWNER will,

within twenty (20) days of presentation to him of an approved partial

payment estimate, pay the CONTRACTOR a progress payment on the

basis of the approved partial payment estimate. The OWNER shall retain

ten (10) percent of the amount of each payment until final completion and

acceptance of all work covered by the CONTRACT DOCUMENTS. The

OWNER at any time, however, after fifty (50) percent of the WORK has

been completed, if he finds that satisfactory progress is being made, shall

reduce retainage to five (5%) percent on the current and remaining

estimates. When the WORK is substantially complete (operational or

beneficial occupancy), the retained amount may be further reduced below

five (5) percent to only that amount necessary to assure completion. On

completion and acceptance of a part of the WORK on which the price is

stated separately in the CONTRACT DOCUMENTS, payment may be

made in full, including retained percentages less authorized deductions.

37.2

Upon completion and acceptance of the WORK, the ENGINEER shall

issue a certificate attached to the final payment request that the WORK

has been accepted by him under the conditions of the CONTRACT

DOCUMENTS. The entire balance found to be due the CONTRACTOR

including the retained percentages, but except such sums as may be

lawfully retained by the OWNER, shall be paid to the CONTRACTOR

within thirty (30) days of completion and acceptance of the WORK

37.3

The CONTRACTOR will indemnify and save the OWNER or the

OWNER'S agents harmless from all claims growing out of the lawful

demands of SUBCONTRACTORS, laborers, workmen, mechanics,

material men, and furnishers of machinery and parts thereof, equipment,

tools, and all supplies, incurred in the furtherance of the performance of

the WORK. The CONTRACTOR shall at the OWNER'S request, furnish

satisfactory evidence that all obligations of the nature designated above

have been paid, discharged, or waived. If the CONTRACTOR fails to do

so the OWNER may, after having notified the CONTRACTOR, either pay

unpaid bills or withhold from the CONTRACTOR'S unpaid compensation a

sum of money deemed reasonably sufficient to pay any and all such lawful

SECTION 00700 – GENERAL CONDITIONS

PAGE 26 OF 32

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

claims until satisfactory evidence is furnished that all liabilities have been

fully discharged whereupon payment to the CONTRACTOR shall be

resumed, in accordance with the terms of the CONTRACT DOCUMENTS,

but in no event shall the provisions of this sentence be construed to

impose any obligations upon the OWNER to either the CONTRACTOR,

his Surety, or any third party. In paying any unpaid bills of the

CONTRACTOR, any payment so made by the OWNER shall be

considered as a payment made under the CONTRACT DOCUMENTS by

the OWNER to the CONTRACTOR and the OWNER shall not be liable to

the CONTRACTOR for any such payments made in good faith.

37.4

38.

ASSIGNMENTS

38.1

39.

Neither the CONTRACTOR nor the OWNER shall sell, transfer, assign or

otherwise dispose of the CONTRACT or any portion thereof, or of his

right, title or interest therein, or his obligations thereunder, without written

consent of the other party.

GUARANTY

39.1

40.

If the OWNER fails to make payment thirty (30) days after approval by the

ENGINEER, in addition to other remedies available to the

CONTRACTOR, there shall be added to each such payment interest at

the maximum legal rate commencing on the first day after said payment is

due and continuing until the payment is received by the CONTRACTOR.

The CONTRACTOR shall guarantee all materials and equipment

furnished and WORK performed for a period of one (1) year from the date

of SUBSTANTIAL COMPLETION of the system that the completed

system is free from all defects due to faulty materials or workmanship and

the CONTRACTOR shall promptly make such corrections as may be

necessary by reason of such defects including the repairs of any damage

to other parts of the systems resulting from such defects. The OWNER will

give notice of observed defects with reasonable promptness. In the event

that the CONTRACTOR should fail to make such repairs, adjustments, or

other WORK that may be made necessary by such defects, the OWNER

may do so and charge the CONTRACTOR the cost thereby incurred. The

performance BOND shall remain in full force and effect through the

guarantee period.

ACCEPTANCE OF FINAL PAYMENT AS RELEASE

SECTION 00700 – GENERAL CONDITIONS

PAGE 27 OF 32

KOOTENAI TRIBE

40.1

41.

42.

WATER MAIN LOOP CONSTRUCTION

The acceptance by the CONTRACTOR of final payment shall be and shall

operate as a release to the OWNER of all claims and all liability to the

CONTRACTOR other than claims in stated amounts as may be

specifically excepted by the CONTRACTOR for all things done or

furnished in connection with this WORK and for every act and neglect of

the OWNER and others relating to or arising out of this WORK. Any

payment, however, final or otherwise, shall not release the

CONTRACTOR or his sureties from any obligations under the

CONTRACT DOCUMENTS or the performance BOND and Payment

BONDS.

ENGINEER'S ROLE AND AUTHORITY

41.1

The ENGINEER shall act as the OWNER'S representative during the

construction period. He shall decide questions which may arise as to

quality and acceptability of materials furnished and WORK performed. He

shall interpret the intent of the CONTRACT DOCUMENTS in a fair and

unbiased manner. The ENGINEER will make visits to the site and

determine if the WORK is proceeding in accordance with the CONTRACT

DOCUMENTS.

41.2

The CONTRACTOR will be held strictly to the intent of the CONTRACT

DOCUMENTS in regard to the quality of materials, workmanship and

execution of the WORK. Inspections may be made at the factory or

fabrication plant of the source of material supply.

41.3

The ENGINEER will not be responsible for the construction means,

controls, techniques, sequences, procedures, or construction safety.

41.4

The ENGINEER does not have authority to obligate the OWNER to

changes in the terms of the CONTRACT without the approval of the

OWNER.

RESOLUTION OF DISPUTES

42.1 All claims, disputes and other matters in question arising out of, or relating

to, the CONTRACT DOCUMENTS or the breach thereof, except for claims which

have been waived by the making and acceptance of final payment as provided

by Section 40, if not resolved, submit the dispute to the tribal court.

43.

EQUAL EMPLOYMENT OPPORTUNITY

43.1

During the performance of this contract, the CONTRACTOR agrees as

follows:

SECTION 00700 – GENERAL CONDITIONS

PAGE 28 OF 32

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

43.1.1

The CONTRACTOR shall not discriminate against any

employee or applicant for employment because of race,

color, religion, sex, or national origin.

43.1.2

The CONTRACTOR shall take affirmative action to ensure

the applicants are employed, and that employees are treated

during employment, without regard to their race, color,

religion, sex, or national origin. Such action shall include, but

not be limited to, the following: employment, upgrading,

demotion, transfer, recruitment or recruitment advertising,

layoff or termination, rates of pay or other forms of

compensation, and selection for training, including

apprenticeship.

43.1.3

The CONTRACTOR agrees to post in conspicuous places

available to employees and applicants for employment,

notices setting forth the provisions of this nondiscrimination

clause.

43.1.4

The CONTRACTOR shall, in all solicitations or

advertisements for employees placed by or on behalf of the

CONTRACTOR, state that all qualified applicants shall

receive consideration for employment without regard to race,

color, religion, sex, or national origin.

43.1.5

The CONTRACTOR shall send, to each labor union or

representative of workers with which he/she has a collective

bargaining agreement or other contract or understanding, a

notice advising the labor union or workers' representative of

the CONTRACTOR'S commitment under this clause, and

post copies of the notice in conspicuous places available to

employees and applicants for employment.

43.1.5

The CONTRACTOR shall comply with all provisions of

Executive Order No. 11246, as amended, and the rules,

regulations, and relevant orders of the Secretary of Labor.

43.1.6

The CONTRACTOR shall furnish to the OWNER, all

information required by Executive Order No. 11246, as

amended, and by the rules, regulations, and orders of the

Secretary of Labor. Standard Form 100 (EEO -1), or any

successor form, is the prescribed form to be filed within 30

days following the award, unless filed within 12 months

SECTION 00700 – GENERAL CONDITIONS

PAGE 29 OF 32

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

preceding, the date of award.

44.

43.1.7

The CONTRACTOR shall permit access to its books,

records, and accounts by the OWNER or the Office of

Federal Contract Programs (OFCCP) for the purposes of

investigation to ascertain compliance with the applicable

rules, regulations, and orders.

43.1.8

If the OFCCP determines that the CONTRACTOR is not in

compliance with this clause or any rules, regulations, and

orders of the Secretary of Labor, this contract may be

cancelled, terminated, or suspended in whole or in part and

the CONTRACTOR may be declared ineligible for further

Government contracts in accordance with procedures

authorized in Executive Order No. 11246, as amended. In

addition, sanctions may be imposed and remedies invoked

against the CONTRACTOR as provided in Executive

Order No. 11246, as amended, the rules, regulations, or

orders of

the Secretary of Labor, or as otherwise

provided by law.

43.1.9

The CONTRACTOR shall include the terms and conditions

of this clause in every SUBCONTRACT or purchase order

unless exempted by the rules, regulations, or orders of the

Secretary of Labor issued under Executive Order No. 12246,

as amended, so that such provisions will be binding upon

each SUBCONTRACTOR or vendor.

43.1.10

The CONTRACTOR shall take such action with respect to

any SUBCONTRACT or purchase order as the OWNER may

direct as a means of enforcing these terms and conditions,

including sanctions for noncompliance; provided that if the

CONTRACTOR becomes involved in, or is threatened with

litigation with a SUBCONTRACTOR or vendor as a result of

such direction by the OWNER, the CONTRACTOR may

request the OWNER and the United States to enter into such

litigation to protect the interests of the United States.

43.1.11

Notwithstanding any other clause in this contract, disputes

relative to this clause will be governed by the procedures in

41 CFR 60-1.1.

CLEAN AIR AND WATER

SECTION 00700 – GENERAL CONDITIONS

PAGE 30 OF 32

KOOTENAI TRIBE

44.1

45.

WATER MAIN LOOP CONSTRUCTION

The CONTRACTOR agrees:

44.1.1

To comply with all the requirements of section 114 of the

Clean Air Act (42 U.S.C. 7414) and section 308 of the Clean

Water Act (33 U.S.C. 1318) relating to inspection,

monitoring, entry, reports, and information, as well as other

requirements specified in section 114 and section 308 of the

Clean Air Act and the Clean Water Act, and all regulations

and guidelines issued to implement those acts before the

award of this contract

44.1.2

That no portion of the WORK required by this prime contract

will be performed in a facility listed on the Environmental

Protection Agency List of Violating Facilities on the date

when this contract was awarded unless and until the EPA

eliminates the name of the facility from the listing.

44.1.3

To use best efforts to comply with clean air standards and

clean water standards at the facility in which the contract is

being performed.

44.1.4

To insert the substance of this clause into any nonexempt

SUBCONTRACT, including this subparagraph 44.1.4.

INDIAN HEALTH SERVICE

45.1

There shall be no contractual relationship either implied or express

between the IHS and the CONTRACTOR or any SUBCONTRACTOR at

any tier.

45.2

IHS representatives shall be afforded access to the site at all times during

the construction period to observe the work and determine if the work

conforms to the intent of the design.

45.3

IHS representatives shall not be responsible for the construction means,

controls, techniques, sequences, procedures, or construction safety.

45.4

IHS representatives do not have authority to obligate the OWNER to

changes in the terms of the CONTRACT nor to act as an agent of the

OWNER in any manner. Inspections conducted by IHS representatives

shall be for the sole benefit of the IHS and the OWNER and shall not

relieve the CONTRACTOR of any contract requirements.

SECTION 00700 – GENERAL CONDITIONS

PAGE 31 OF 32

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

This page intentionally left blank

SECTION 00700 – GENERAL CONDITIONS

PAGE 32 OF 32

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

SECTION 00705

SPECIAL PROVISIONS

SP-01

SITE CONDITIONS

Work is to be performed on the Kootenai Indian Reservation Bonners Ferry, Idaho and

is accessible from U.S. Route 95 and Kootenai Trail Rd. Special site conditions to be

noted by the CONTRACTOR are as follows:

1)

SP-02

The CONTRACTOR is responsible to verify the location of all utilities,

including those not located or shown on the drawings.

DAYS OF WORK AND WORK HOURS

Construction work shall not be normally permitted on Saturdays, Sundays, Federal, or

Tribal holidays. Contractor shall request dates of Tribal holidays from the Tribe. The

CONTRACTOR may submit a written request to the Owner at least 48 hours in

advance, for permission to work on any Saturday, Sunday, or Federal holiday. Written

approval must be obtained before the CONTRACTOR may work on any such day.

Work shall be performed between the hours of 7:00 AM and 5:00 PM.

SP-03

TIME FOR COMPLETION

In accordance with the NOTICE TO PROCEED, the TIME FOR COMPLETION (as

described in GC 24.1) shall be 120 calendar days for all work.

SP-04

LIQUIDATED DAMAGES

If the CONTRACTOR shall fail to complete the WORK within the TIME FOR

COMPLETION, or extension of time granted by the OWNER, then the CONTRACTOR

will pay to the OWNER $100.00 for each calendar day that the work shall be incomplete

after the date established by the TIME FOR COMPLETION

SP-05

LICENSING

The General Contractor performing work shall be registered in the State of Idaho for the

type of construction and magnitude of construction being performed.

SECTION 00705 – SPECIAL PROVISIONS

PAGE 1 OF 4

KOOTENAI TRIBE

SP-06

WATER MAIN LOOP CONSTRUCTION

INSURANCE

CONTRACTOR'S insurance policy shall name the Kootenai Tribe as co-insured. A

certificate of insurance naming the Kootenai Tribe shall be submitted to the Kootenai

Tribe prior to NOTICE TO PROCEED.

CONTRACTOR shall carry General Public Liability and Property Damage Insurance

including vehicle coverage issued to the CONTRACTOR and protecting him from all

claims for personal injury, including death, and all claims for destruction of or damage to

any property, arising out of or in connection with any operations under the CONTRACT

DOCUMENTS, whether such operations be by himself or by any SUBCONTRACTOR

under him, or anyone directly or indirectly employed by the CONTRACTOR or by a

SUBCONTRACTOR under him. Insurance shall be written with a limit of liability of not

less than $1,000,000 for all damages arising out of bodily injury, including death, at any

time resulting therefrom, sustained by any one person in any one accident; and a limit of

liability of not less than $2,000,000 aggregate for any such damages sustained by two

or more persons in any one accident. Insurance shall be written with a limit of liability of

not less than $200,000 for all property damage sustained by any one person in any one

accident; and a limit of liability of not less than $500,000 aggregate for any such

damage sustained by two or more persons in any one accident.

SP-07

RESOLUTION OF DISPUTES

Any dispute or claim relating to this Contract or any breach hereof that cannot be

negotiated between the parties shall be submitted to the office for third party mediation.

If not resolved the dispute shall be heard in Kootenai Tribal Court. The CONTRACTOR

will carry on the WORK and maintain the progress schedule during any proceedings,

unless otherwise mutually agreed in writing. This shall supersede the conditions of

GENERAL CONDITION 42 - RESOLUTION OF DISPUTES.

SP-08

RIGHT TO AWARD ALL, NONE, OR A COMBINATION OF LINE ITEMS

The OWNER reserves the right to award all, none, or a combination of the line items on

the BID OFFER SHEET.

SP-09

ORDER OF PRECEDENCE

In the event of an inconsistency between provisions of this contract, the inconsistency

shall be resolved by giving precedence in the following order:

1) Bid Schedule (Schedule A & B) and Terms and Conditions of Contract.

2) Written bid instructions.

SECTION 00705 – SPECIAL PROVISIONS

PAGE 2 OF 4

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

3) Special Provisions

4) General Conditions

5) Exhibits and other provisions of the contract, where incorporated by reference

or otherwise

6) Technical Provisions

7) Drawings

SP-10

INDIAN OWNED PREFERENCE

Preference in the award of this CONTRACT shall be given to Indian and Alaskan Native

organizations and economic enterprises. The OWNER shall give preference to a 51

percent Indian owned Economic Enterprise so long as the BID by this Enterprise does

not exceed the lowest responsive bid submitted by more than ten (10) percent and is

within the project budget. "Indian owned Economic Enterprise" means any Indian

owned commercial, industrial, or business activity established or organized for the

purpose of profit, provided that such Indian ownership shall constitute not less than 51

percent of the enterprise, and that ownership shall encompass active operation and

control of the enterprise. All preferences shall be publicly announced at the bid

opening. Any BIDDER claiming Indian preference shall complete and submit with the

BID the attached form entitled “Indian Enterprise Qualification Statement” to support

their claim. The BIDDER also agrees to give preference to Indian-owned economic

enterprises in the awarding of any subcontracts, and the acquisition of materials, to the

extent feasible and consistent with the efficient performance of this CONTRACT.

Feasibility regards reasonable terms and conditions, including price, and the timely

delivery of services and supplies.

SP-11

ADVERSE WEATHER

If in the opinion of the Contractor, adverse weather conditions prevent construction

activities to proceed under this contract, the contractor may submit a written request to

the Contracting Officer to suspend the contract performance period and construction

activities until fairer seasonal weather returns. The Contracting Officer shall consider

the request and if in agreement, issue a modification to the contract to suspend work

due to adverse weather conditions and establish a date to resume work. The contract

performance period shall remain unchanged by the modification and there will be no

additional payment made. If the Contracting Officer disapproves the contractor's

request, the contractor will be notified in writing. If the request is disapproved, the

contractor shall proceed with work under the contract and no additional payment will be

made.

SECTION 00705 – SPECIAL PROVISIONS

PAGE 3 OF 4

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

This page intentionally left blank

SECTION 00705 – SPECIAL PROVISIONS

PAGE 4 OF 4

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

SECTION 00810

LABOR PROVISIONS

l.

DAVIS-BACON ACT

(a)

All laborers and mechanics employed or working upon the site of the WORK will

be paid unconditionally and not less often than once a week, and without

subsequent deduction or rebate on any account (except such payroll

deductions as are permitted by regulations issued by the Secretary of Labor

under the Copeland Act (29 CFR Part 3), the full amount of wages and bona

fide fringe benefits (or cash equivalents thereof) due at time of payment

computed at rates not less than those contained in the wage determination of

the Secretary of Labor which is attached hereto and made a part hereof,

regardless of any contractual relationship which may be alleged to exist

between the CONTRACTOR and such laborers and mechanics. Contributions

made or costs reasonably anticipated for bona fide fringe benefits under section

l(b)(2) of the Davis-Bacon Act on behalf of laborers or mechanics are

considered wages paid to such laborers or mechanics, subject to the provisions

or paragraph (d) of this clause also, regular contributions made or costs

incurred for more than a weekly period (but not less than quarterly) under plans,

funds, or programs which cover the particular weekly period, are deemed to be

constructively made or incurred during such period. Such laborers and

mechanics shall be paid not less than the appropriate wage rate and fringe

benefits in the wage determination for classification of work actually performed

without regard to skill, except as provided in the clause entitled "Apprentices"

and "Trainees." Laborers or mechanics performing work in more than one

classification may be compensated at the rate specified for each classification

for the time actually worked therein: Provided, that the employer's payroll

records accurately set forth the time spent in each classification in which work is

performed. The wage determination (including any additional classification and

wage rates conformed under paragraph (b) of this clause) and the Davis-Bacon

poster (WH-l32l) shall be posted at all times by the CONTRACTOR and its

subcontractors at the site of the WORK in a prominent and accessible place

where it can be easily seen by the workers.

(b)

(1) The OWNER shall require that any class of laborers or mechanics which is

not listed in the wage determination and which is to be employed under the

contract shall be classified in conformance with the wage determination. The

OWNER shall approve an additional classification and wage rate and fringe

benefits therefore only when the following criteria have been met:

(i)

The work to be performed by the classification requested is not

performed by a classification in the wage determination; and

(ii)

The Classification is utilized in the area by the construction

industry; and

(iii)

The proposed wage rate, including any bona fide fringe benefits,

bears a reasonable relationship to the wage rates contained in the

wage determination.

(2) If the CONTRACTOR and the laborers and mechanics to be employed in

SECTION 00810 – LABOR PROVISIONS

PAGE 1 OF 8

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

the classification (if known), or their representatives, and the OWNER agree on

the classification and wage rate (including the amount designated for fringe

benefits where appropriate), a report of the action taken shall be sent by the

OWNER to the Administrator of the Wage and Hour Division, Employment

Standards Administration, U.S. Department of Labor, Washington, D.C. 202l0.

The Administrator or an approved authorized representative, will approve,

modify, or disapprove every additional classification action within 30 days of

receipt and so advise the OWNER or will notify the OWNER within a 30-day

period of that additional time is necessary.

(3) In the event the CONTRACTOR, the laborers or mechanics to be employed

in the classification or their representatives, and the OWNER do not agree on

the proposed classification and wage rate (including the amount designated for

fringe benefits, where appropriate), the OWNER shall refer the questions,

including the views of all interested parties and the recommendation of the

OWNER, to the Administrator of the Wage and Hour Division for determination.

The Administrator or an authorized representative, will issue a determination

within 30 days of receipt and so advise the OWNER or will notify the OWNER

within the 30-day period that additional time is necessary.

(4) The wage rate (including fringe benefits where appropriate) determined

pursuant to subparagraphs (b)(2) or (b)(3) of this clause, shall be paid to all

workers performing work in the classification under this contract from the first

day on which work is performed in the classification.

(c)

Whenever the minimum wage rate prescribed in the contract for a class of

laborers or mechanics includes a fringe benefit which is not expressed as an

hourly rate, the CONTRACTOR shall either pay the benefit as stated in the

wage determination or shall pay another bona fide fringe benefit or an hourly

cash equivalent thereof.

(d)

If the CONTRACTOR does not make payments to a trustee or other third

person, the CONTRACTOR may consider as part of the wages of any laborer

or mechanic the amount of any costs reasonably anticipated in providing bona

fide fringe benefits under a plan or program. Provided, that the Secretary of

Labor has found, upon the written request of the CONTRACTOR, that

applicable standards of the Davis-Bacon Act have been met. The Secretary of

Labor may require the CONTRACTOR to set aside in a separate account

assets for the meeting of obligations under the plan or program.

2.

CONTRACT WORK HOURS AND SAFETY STANDARDS ACT - OVERTIME

COMPENSATION

(a)

Overtime requirements: No contractor or subcontractor contracting for any part

of the contract work which may require or involve the employment of laborers or

mechanics (See Federal Acquisition Regulation 22.300) shall require or permit

any such laborer or mechanic in any workweek in which individual is employed

on such work to work in excess of forty hours in such workweek unless such

laborer or mechanic receives compensation at a rate not less than one and

one-half times the basic rate of pay for all hours worked in excess of forty hours

in such workweek.

(b)

Violation, liability for unpaid wages, liquidated damages: In the event of any

SECTION 00810 – LABOR PROVISIONS

PAGE 2 OF 8

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

violation of the provisions set forth in paragraph (a) of this clause, the

CONTRACTOR and any subcontractor responsible therefore shall be liable for

the unpaid wages. In addition, such contractor and subcontractor shall be liable

to the United States (in the case of work done under contract for the District of

Columbia or a territory, to such District or to such territory), for liquidated

damages. Such liquidated damages shall be computed with respect to each

individual laborer or mechanic, employed in violation of the provisions set forth

in paragraph (a) of this clause, in the sum of $l0 for each calendar day for which

such individual was required or permitted to work in excess of the standard

workweek of 40 hours without payment of the overtime wages required by the

provisions set forth in paragraph (a) of this clause.

(c)

Withholding for unpaid wages and liquidated damages: The Contracting officer

shall upon his or her own action or written request of an authorized

representative of the Department of Labor withhold or cause to be withheld,

from any moneys payable on account of work performed by the CONTRACTOR

or subcontractor under any such contract or any other Contract with the same

Prime Contractor, or any other Federally-assisted contract subject to the

Contract Work Hours and Safety Standards Act, which is held by the same

Prime contractor, such sums as may be determined to be necessary to satisfy

any liabilities of such contractor or subcontractor for unpaid wages and

liquidated damages as provided in the provisions set forth in paragraph (b) of

this clause.

(d)

Payrolls and basic records:

(1) The CONTRACTOR or subcontractor shall maintain payrolls and basic

payroll records during the course of contract work and shall preserve them for a

period of 3 years from the completion of the contract for all laborers and

mechanics working on the contract. Such records shall contain the name and

address of each such employee, social security number, correct classifications,

hourly rates of wages paid, daily and weekly number of hours worked,

deductions made, and actual wages paid. Nothing in this paragraph shall

require the duplication of records required to be maintained for construction

work by Department of Labor regulations at 29 CFR 5.5(a)(3) implementing the

Davis-Bacon Act.

(2) The records to be maintained under paragraph (d)(1) of this clause shall be

made available by the CONTRACTOR or subcontractor for inspection, copying,

or transcription by authorized representatives of the OWNER or the Department

of Labor. The CONTRACTOR or subcontractor shall permit such

representatives to interview employees during working hours on the job.

(e)

Subcontracts: The CONTRACTOR or subcontractor shall insert in any

subcontracts the provisions set forth in paragraphs (a) through (d) of this clause

and also a clause requiring the subcontractors to include these provisions any

lower tier subcontracts. The Prime CONTRACTOR shall be responsible for

compliance by any subcontractor or lower tier subcontractor with the provisions

set forth in paragraphs (a) through (d) of this clause.

3.

APPRENTICES AND TRAINEES

SECTION 00810 – LABOR PROVISIONS

PAGE 3 OF 8

KOOTENAI TRIBE

(a)

WATER MAIN LOOP CONSTRUCTION

Apprentices: Apprentices will be permitted to work at less than the

predetermined rate for the work they performed when they are employed

pursuant to and individually registered in a bona fide apprenticeship program

registered with the U.S. Department of Labor, Employment and Training

Administration, Bureau of Apprenticeship and Training, or with a State

Apprenticeship Agency recognized by the Bureau, or if a person is employed in

his or her first 90 days of probationary employment as an apprentice in such an

apprenticeship program, who is not individually registered in the Program but

who has been certified by the Bureau of Apprenticeship and Training or a State

Apprenticeship Agency (where appropriate) to be eligible for probationary

employment as an apprentice. The allowable ratio of apprentices to

journeyman on the job site in any craft classification shall not be greater than

the ratio permitted to the CONTRACTOR as to the entire work force under the

registered program. Any worker listed on a payroll at an apprentice wage rate,

who is not registered or otherwise employed as stated in this paragraph shall be

paid not less than the applicable wage rate on the wage determination for the

classification of work actually performed. In addition, any apprentice performing

work on the job site in excess of the ratio permitted under the registered

program shall be paid not less than the applicable wage rate on the wage

determination for the work actually performed. Where a contractor is

performing construction on a project in a locality other than that in which its

program is registered, the ratios and wage rates (expressed in percentages of

the journeyman's hourly rate) specified in the contractor's or subcontractor's

registered program shall be observed. Every apprentice must be paid at not

less than the rate specified in the registered program for the apprentice’s level

of progress, expressed as percentage of the journeyman hourly rate specified in

the applicable wage determination. Apprentices shall be paid fringes in

accordance with the provisions of the apprenticeship program.

If the apprenticeship program does not specify fringe benefits, apprentices must

be paid the full amount of fringe benefits listed on the wage determination for

the applicable classification. If the Administrator determines that a different

practice prevails for the applicable apprentice classification, fringe benefits shall

be paid in accordance with that determination.

In the event the Bureau of Apprenticeship and Training, or a State

Apprenticeship Agency recognized by the Bureau, withdraws approval of an

apprenticeship program, the CONTRACTOR will no longer be permitted to

utilize apprentices at less than the applicable predetermined rate for the work

performed until an acceptable program is approved.

(b)

Trainees: Except as provided in 29 CFR 5.l6, trainees will not be permitted to

work at less than the predetermined rate for the work performed unless they are

employed pursuant to and individually registered in a program which has

received prior approval, evidenced by formal certification by the U.S.

Department of Labor, Employment and Training Administration. The ratio of

trainees to journeymen on the job site shall not be greater than permitted under

the plan approved by the Employment and Training Administration. Every

trainee must be paid at not less than the rate specified in the approved program

for the trainee's level of progress, expressed as a percentage of the journeyman

hourly rate specified in the applicable wage determination. Trainees shall be

SECTION 00810 – LABOR PROVISIONS

PAGE 4 OF 8

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

paid fringe benefits in accordance with the provisions of the trainee program. If

the trainee program does not mention fringe benefits, trainees shall be paid the

full amount of fringe benefits listed on the wage determination unless the

Administrator of the Wage and Hour Division determines that there is an

apprenticeship program associated with the corresponding journeyman wage

rate on the wage determination which provides for less than full fringe benefits

for apprentices. Any employee listed on the payroll at a trainee rate who is not

registered and participating in a training plan approved by the Employment and

Training Administration shall be paid not less than the applicable wage rate on

the wage determination for the classification of work actually performed. In

addition, any trainee performing work on the job site in excess of the ratio

permitted under the registered program shall be paid not less than the

applicable wage rate on the wage determination for the work actually

performed. In the event the Employee and Training Administration withdraws

approval of a training program, the CONTRACTOR will not longer be permitted

to utilize trainees at less than the applicable predetermined rate for the work

performed until an acceptable program is approved.

(c)

Equal Employment Opportunity: The utilization of apprentices, trainees and

journeymen under this part shall be in conformity with the equal employment

opportunity requirements of Executive Order ll246, as amended, and 29 CFR

Part 30.

4.

PAYROLLS AND BASIC RECORDS

(a)

Payrolls and basic records relating thereto shall be maintained by the

CONTRACTOR during the course of the work and preserved for a period of

three years thereafter for all laborers and mechanics working at the site of the

WORK. Such records shall contain the name, address, and social security

number of each such worker, his or her correct classification, hourly rates or

wages paid (including rates of contributions or costs anticipated for bona fide

fringe benefits or cash equivalents thereof of the types described in section

l(b)(2)(B) of the Davis-Bacon Act), daily and weekly number of hours worked,

deduction made and actual wages paid. Whenever the Secretary of Labor has

found under paragraph (d) of the clause entitled "Davis-Bacon Act" that the

wages of any Laborer or mechanic include the amount of any costs reasonably

anticipated in providing benefits under a plan or program described in section

l(b)(2)(B) of the Davis-Bacon Act, the CONTRACTOR shall maintain records

which show that the commitment to provide such benefits is enforceable, that

the plan or program is financially responsible, and the plan or program has

been communicated in writing to the laborers or mechanics affected, and

records which show the costs anticipated or the actual costs incurred in

providing such benefits. Contractors employing apprentices or trainees under

approved programs shall maintain written evidence of the registration of

apprenticeship programs and certification of trainee programs, the registration

of the apprentices and trainees, and the ratios and wage rates prescribed in the

applicable programs.

(b)

(1) The CONTRACTOR shall submit weekly for each week in which any

contract work is performed a copy of all payrolls to the OWNER. The payrolls

submitted shall set out accurately and completely all of the information required

SECTION 00810 – LABOR PROVISIONS

PAGE 5 OF 8

KOOTENAI TRIBE

WATER MAIN LOOP CONSTRUCTION

to be maintained under paragraph (a) of this clause. The information may be

submitted in any form desired. Optional Form WH-347 Federal stock number

029-005-00014-1 is available for this purpose and may be purchased from the

Superintendent of Documents, U.S. Government Printing Office, Washington,

D.C. 20402. The Prime Contractor is responsible for the submission of copies

of payrolls by all subcontractors.

(2) Each payroll submitted shall be accompanied by a "Statement of

Compliance" signed by the CONTRACTOR or subcontractor or his or her agent

who pays or supervises the payment of the persons employed under the

contract and shall certify the following:

(i)

That the payroll for the payroll period contains the information

required to be maintained under paragraph (a) of this clause

entitled "Payrolls and Basic Records" and that such information is

correct and complete.

(ii)

That each laborer or mechanic (including each helper, apprentice,

and trainee) employed on the contract during the payroll period has

been paid the full weekly wages earned, without rebate, either

directly or indirectly and that no deductions have been made either

directly or indirectly from the full wages earned, other than

permissible deduction as set forth in Regulations, 29 CFR Part 3

and

(iii)

That each laborer or mechanic has been paid not less that the

applicable wage rates and fringe benefits or cash equivalents for

the classification of work performed, as specified in the applicable

wage determination incorporated into the contract.

(3) The weekly submission of a properly executed certification set forth on the

reverse side of Optional Form WH-347 shall satisfy the requirement for

submission of the "Statement of Compliance" required by subparagraph (b)(2)

of this clause.

(4) The falsification of any of the certifications may subject the CONTRACTOR

or subcontractor to civil or criminal prosecution under Section 1001 of Title 18

and Section 18 and Section 231 of Title 31 of the United States Code.

(c)

The CONTRACTOR or subcontractor shall make the records required under

paragraph (a) of this clause available for inspection, copying, or transcription by

authorized OWNER or representatives of the OWNER or the Department of

Labor. The CONTRACTOR or subcontractor shall permit the OWNER or

representatives of the OWNER or the Department of Labor to interview

employees during working hours on the job. If the CONTRACTOR or

subcontractor fails to submit the required records or to make them available, the

OWNER may, after written notice to the CONTRACTOR, sponsor take such

action as may be necessary to cause the suspension of any further payment.

Furthermore, failure to submit the required records upon request or to make

such records available may be grounds for debarment action pursuant to 29

CFR 5.12.

SECTION 00810 – LABOR PROVISIONS

PAGE 6 OF 8

KOOTENAI TRIBE

5.

WATER MAIN LOOP CONSTRUCTION

COMPLIANCE WITH COPELAND ACT REQUIREMENTS

The CONTRACTOR shall comply with the requirements of 29 CFR Part 3,

which are incorporated by reference in this contract.

6.

WITHHOLDING OF FUNDS

The OWNER shall upon his or her own action or upon written request of an

authorized representative of the Department of Labor withhold or cause to be

withheld from the CONTRACTOR under this contract or any other Federal

contract with the same Prime C

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.