US 101 / Trinidad Area Access Improvements
Tribal code
Ask Donna
What actually matters in this document.
Text
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
TABLE OF CONTENTS
Section
Page
1.
INTRODUCTION .............................................................................................................. 1
2.
BACKGROUND ................................................................................................................ 2
3.
PURPOSE AND NEED...................................................................................................... 4
4.
TRAFFIC ENGINEERING PERFORMANCE ASSESSMENT ....................................... 4
5.
DEFICIENCIES.................................................................................................................. 8
6.
CORRIDOR AND SYSTEM COORDINATION .............................................................. 9
7.
ALTERNATIVES ............................................................................................................ 10
8.
RIGHT OF WAY.............................................................................................................. 42
9.
STAKEHOLDER INVOLVEMENT ............................................................................... 44
10.
ENVIRONMENTAL DETERMINATION/DOCUMENT .............................................. 45
11.
FUNDING ........................................................................................................................ 45
12.
DELIVERY SCHEDULE................................................................................................. 46
13.
RISKS ............................................................................................................................... 46
14.
FHWA COORDINATION ............................................................................................... 47
15.
PROJECT REVIEWS ....................................................................................................... 47
16.
PROJECT PERSONNEL ................................................................................................. 47
17.
ATTACHMENTS ............................................................................................................. 47
R1721PSR003.docx
ii
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
Project Study Report –
Project Development
Support
US‐101 / Trinidad Area
Access Improvements
EA: 01‐48040K
EFIS ID: 01‐0002‐0301
PPNO:
01‐HUM‐101 PM 98.4/100.7
1. INTRODUCTION
Figure 1 – Exhibit drawing for the programming alternative;
Alternative 3A – New US 101/Cher‐Ae Lane Interchange.
The Trinidad Rancheria and Caltrans District 1 are working in partnership to identify alternatives to
meet the transportation needs of the Trinidad Rancheria and the surrounding community. This PSR‐
PDS identifies 12 alternatives to address the transportation deficiencies between the unincorporated
community of Westhaven and the City of Trinidad. The main deficiencies identified for this area are:
(1) Scenic Drive’s geotechnical instability, with slides and slip‐outs commonly occurring along this
route, causing partial or complete road closures (typically during winter months); (2) anticipated
Rancheria growth is likely to cause several intersections in the area to have inadequate vehicular
capacity; and (3) Tribal lands east and west of US 101 have inadequate connectivity.
Project Limits
01‐HUM‐101 PM 98.4/100.7
Number of Alternatives
12 Plus No‐Build
Alternative Recommended for Programming
Alternative 3A –New US 101/Cher‐Ae Lane Interchange
Capital Outlay Support Estimate for PA&ED
(Anticipated Environmental Approval
7/1/22)
Current (2017):
$2,500,000
Capital Outlay Construction Cost Range
Capital Outlay Right‐of‐Way Cost Range
Funding Source(s)
Funding Year
Type of Facility
Number of Structures
Anticipated Environmental Determination
Legal Description
Project Development Category
R1721PSR003.docx
Current (2017):
Escalated @ 5% to 2024:
$16,600,000 to $46,200,000
$23,360,000 to $65,000,000
Current (2017):
Escalated @ 5% to 2024:
$800,000 to $3,880,000
$1,125,000 to $5,460,000
Anticipated to include some or all of the following:
State Transportation Improvement Program (STIP)
Tribal Transportation Program (TTP)
Indian Reservation Roads (IRR)
Active Transportation Program (ATP)
Highway Safety Improvement Program (HSIP)
Transportation Investment Generating Economic Recovery
(TIGER)
2018
4‐Lane Freeway
1 to 3
EIR/FONSI
In Humboldt County, near Trinidad from Westhaven Drive
Undercrossing to 0.4 Mile North of Trinidad Road
Undercrossing
Category 3 – Projects on previously constructed access
controlled routes requiring a new or revised freeway
agreement, but not a route adoption.
1
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
The range of alternatives includes improvements to the existing Trinidad‐Main Street interchange,
improvements to Scenic Drive and Westhaven Drive, and/or a new local road interchange. A detailed
description of each alternative can be found in Section 7. Additional studies are needed to determine
which of the proposed alternatives will best meet the purpose and need of the project. Either a project
report or a supplemental Project Initiation Document (PID), following the format of a Project Study
Report (PSR), will serve as the programming document for the remaining components of the project. A
project report, accompanied by a signed environmental document, will serve as approval of the selected
alternative.
2. BACKGROUND
Description of Existing Facility:
US 101 is the economic lifeline of the north coast and is the most important route in District 1. It serves
interregional and interstate traffic, with relatively high traffic volumes and heavy use by both truck and
tourist traffic. US 101 is functionally classified as a principal arterial. US 101 is on the National Highway
System but is not part of the FHWA Rural and Single Interstate Routing System. It is part of the Strategic
Highway Network and the Interregional Highway System and is considered a High Emphasis Route in
the Interregional Transportation Strategic Plan. Within the project segment, US 101 is designated a
Surface Transportation Assistance Act (STAA) route and is part of the Pacific Coast Bike Route. Portions
of US 101 are also eligible for Scenic Highway Designation.
US 101 from PM 98.4 to 100.7 is a four lane freeway with a paved median width that ranges from 4 feet
wide at the south end of the project limits, to 22 feet wide at the north end of the project limits. Outside
shoulders within the project limits are consistently 4 feet wide, but widen out to 10 feet wide north of the
existing US 101/Trinidad‐Main Street Interchange. The posted speed limit along US 101 in this area is 65
mph. Within the project limits, US 101 is relatively flat, with some rolling hills, and grades ranging from
approximately 2% to 4.5%. The horizontal alignment is curvilinear, with tangents up to nearly a mile
long, and horizontal curve radii ranging between 1,800 feet and 12,000 feet. Existing right‐of‐way widths
within the project limits vary from approximately 160 feet wide to 460 feet wide, with access controlled
rights‐of‐way. Existing adjacent land use is almost entirely Residential, of which most is comprised of
Rural Residential (RR), with a small amount of Residential Estates (RE). Current year traffic volumes for
US 101 are approximately 10,350 vehicles (ADT). Based on the Trinidad Area Freeway Master Plan
Study, future (year 2040) traffic volumes are estimated to be approximately 14,500 vehicles without full
Trinidad Rancheria Master Plan buildout, and 20,510 vehicles (ADT) with full Trinidad Rancheria Master
Plan buildout.
There are three existing interchanges (I/C) within the project segment as described below:
TABLE 1: EXISTING INTERCHANGES
Post
Mile
Name
Overcrossing
or
Undercrossing
98.1
Westhaven Drive I/C
Undercrossing
98.4
Sixth Street I/C
Overcrossing
100.7
Trinidad ‐ Main Street I/C
Undercrossing
R1721PSR003.docx
2
Description
A half interchange with a tight NB off‐
ramp and a SB hook ramp from Scenic
Drive
A hook ramp Type L‐6 with all ramps
on the north side of Sixth Street
A tight diamond Type L‐1
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
Scenic Drive is a 2‐lane rural roadway, which runs in a south‐north direction on the west side of US 101,
from the community to Westhaven, north to the City of Trinidad. The roadway begins near Moonstone
County Park and the Little River State Beach in Westhaven (Left of PM 97.8), and follows the Pacific coast
line northerly for approximately 3.2 miles to Main Street in the City of Trinidad. Scenic Drive is a
winding and narrow road, approximately 16’‐20’ wide through most of the southerly portion, with no
sidewalks and little to no useable paved shoulders. The majority of Scenic Drive has severe geotechnical
instability, and frequently has closures for emergency roadway repairs to reestablish access. Existing
slopes along Scenic Drive are typically very steep, sloping to the Pacific Ocean on the west side, and
sloping upwards towards US 101 on the east side. The posted speed limit along Scenic Drive is 30 mph.
According to the City of Trinidad Draft General Plan Circulation Element, current year traffic volumes
for Scenic Drive are approximately 870 vehicles (ADT), while future (year 2040) traffic volumes are
estimated to be 1,357 vehicles (ADT).
Westhaven Drive is a 2‐lane rural‐residential roadway, which runs in a south‐north direction on the east
side of US 101 from the community of Westhaven to the City of Trinidad. The roadway begins at a
partial interchange on US 101 (PM 98.1), is approximately 3.3 miles long, and terminates at the Trinidad‐
Main Street interchange (PM 100.7) in the City of Trinidad. The roadway is narrow, typically about 20ʹ
wide, with little to no useable shoulders, and no sidewalks. The posted speed limit along Westhaven
Drive is 25 mph. According to the City of Trinidad Draft General Plan Circulation Element, current year
traffic volumes for Westhaven Drive are approximately 865 vehicles (ADT), while future (year
2040) traffic volumes are estimated to be 1,509 vehicles (ADT).
Main Street is a quiet, 2‐lane roadway which lies in the heart of the City of Trinidad. Main Street runs in
an east‐west direction, and is a primary collector that extends from just east of US 101 through the City of
Trinidad. Main Street has a posted speed limit of 20 mph, and according to the City of Trinidad Draft
General Plan Circulation Element, current year traffic volumes for Main Street are approximately 3,170
vehicles (ADT), while future (year 2040) traffic volumes are estimated to be 4,706 vehicles (ADT). The
City of Trinidad has long been known as a rural, seaside fishing village, with very unique characteristics,
limited tourist activity, and a strong desire to minimize adverse impacts caused by visitors. There are a
few existing RV parks within the area, which typically see increases in use during the summer months.
Discussion of Studies to Date:
Since 2001, several planning studies have been completed, including the draft Project Initiation Document
(PID), in order to study accessibility to the Trinidad Rancheria and the surrounding areas, and to
investigate alternatives that would provide improved access for current and future needs. The different
studies that have been prepared have consistently demonstrated that the existing interchanges and local
roads within this corridor can neither: (1) provide the necessary traffic level of service to all areas within
the corridor, nor (2) be improved economically to appropriately accommodate the design‐year traffic
demands. The various studies that have been completed are listed below:
Trinidad Rancheria Access Improvement Feasibility Study, Winzler & Kelly, May 2002
Trinidad Rancheria Tribal Transportation Plan 2006‐2026, Winzler & Kelly, March 2006
Trinidad Rancheria Highway 101 Interchange Community Design Fair, Local Government
Commission, June 2009
Trinidad Rancheria Comprehensive Community‐Based Plan, Trinidad Rancheria, December 2011
Trinidad Area Freeway Master Plan Study, Omni‐Means, Ltd., February 2014
Trinidad Rancheria Tribal Transportation Safety Plan, Trinidad Rancheria, June 2014
R1721PSR003.docx
3
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
Since 2012, a Project Development Team (PDT) has met to guide the project through the project
development process. This PDT team has been instrumental to date in developing the purpose and need
for the project, and preparing the project to reach this stage. The PDT team will continue to play a key
role in guiding the project through to completion.
3. PURPOSE AND NEED
Purpose:
The purpose of the project is to:
1.
2.
3.
Provide safe and sustainable access to and from US 101, for all modes of transportation, to the
Trinidad Rancheria and the surrounding communities located along Scenic Drive, Westhaven
Drive, and in the City of Trinidad.
Relieve projected traffic congestion associated with planned future development.
Reconnect tribal lands.
Need:
The proposed project is needed because:
1.
2.
3.
The only access to Trinidad Rancheria lands from US 101, Scenic Drive west of the Trinidad
Rancheria, is not safe or sustainable:
a. It is geologically unstable; slides and slip‐outs commonly cause partial or complete road
closures, particularly during the winter months.
b. It is not a pedestrian/bicycle friendly route, due to the lack of sidewalks and minimal or no
paved shoulders.
The current capacity at several intersections would be inadequate to accommodate projected
increases in traffic due to planned future development.
The construction of US 101 severed tribal lands.
4. TRAFFIC ENGINEERING PERFORMANCE ASSESSMENT
Traffic Operations:
The Trinidad Area Freeway Master Plan Study (Traffic Study), prepared by Omni‐Means, Ltd., was
approved by District 1 Traffic Operations in February 2014. The Traffic Study analyzed US 101, from the
Sixth Street I/C to the Trinidad‐Main Street I/C, as well as Main Street, Scenic Drive, Westhaven Drive, the
Sixth Street I/C and the Trinidad‐Main Street I/C. The Traffic Study analyzed existing performance, and
future performance of these facilities based on anticipated growth. The Traffic Study projected traffic
growth for this area of Humboldt County, including the City of Trinidad and the Trinidad Rancheria.
The development envisioned in the Cher‐Ae Heights Indian Community of the Trinidad Rancheria,
December 2011, was included in the traffic projections as well. The Traffic Study projected traffic
volumes to the year 2040 conditions.
While additional alternatives are presented for consideration in this PSR-PDS, the Traffic Study analyzed
three alternatives:
No Project.
Alternative 1A. Reconstruct Trinidad-Main Street I/C to accommodate year 2040 traffic
Alternative 3A. New freeway I/C at Cher-Ae Lane to accommodate year 2040 traffic.
At the time the Traffic Study was prepared, some of the current alternatives had not been brought about
yet, including the Baker Ranch Road interchange or the One‐Mile Spacing Interchange. While the Traffic
R1721PSR003.docx
4
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
Study does not consider the full range of alternatives, the analysis results can be applied to the range of
alternatives presented in the PSR‐PDS, based on comparable alternatives. For example, results from the
Traffic Study for a new Cher‐Ae Lane Interchange can be applied to the Baker Ranch Road Interchange,
with similar results.
According to the Traffic Study, all intersections and roadway segments within the study area, including
US 101 mainline and interchanges, are currently operating at acceptable levels of service (LOS) (LOS B or
higher). With anticipated growth and projected traffic volumes from the Traffic Study, and without full
build‐out of the Trinidad Rancheria Master Plan, all intersections and roadway segments within the
study area are expected to continue operating at acceptable LOS for the year 2040 conditions.
With full development of the Trinidad Rancheria Master Plan, several intersections are expected to
operate at unacceptable LOS (LOS D or lower) in the year 2040 conditions. The Scenic Drive/Main Street
intersection, Main Street/US 101 northbound ramps intersection, and the Scenic Drive/Cher‐Ae Lane
intersections all would be operating at LOS F, and would require improvements to provide for acceptable
levels of service (LOS C or higher). US 101 mainline and ramp junctions would continue to operate at
acceptable LOS under the year 2040 conditions with full build‐out. Table 2 shows a summary of the
intersection LOS for the year 2040 conditions with full development of the Trinidad Rancheria Master
Plan, for the analyzed alternatives.
TABLE 2: INTERSECTION LOS FOR YEAR 2040 CONDITIONS
WITH FULL MASTER PLAN DEVELOPMENT
Location
No‐Build
Alternative 1A
(Maintain Two‐Way
(Reconstruct Trinidad‐
Stop Control
Main Street I/C with
(TWSC)
Signals)
AM Peak PM Peak
Alternative 3A
(New US 101/
Cher‐Ae Lane I/C)
AM Peak
PM Peak
AM Peak
PM Peak
Hour
Hour
Hour
Hour
Hour
Hour
6th Street/Kay Avenue
A
A
A
A
A
A
6th Street/Kahlstrom Avenue
A
A
A
A
A
A
Kay Avenue/US 101 SB Ramps
A
A
A
A
A
A
Kahlstrom Avenue/7th Avenue
A
A
A
A
A
A
Scenic Drive/Main Street
F
F
C
C
C
C
Main Street/US 101 SB Ramps
C
C
B
B
B
B
Main Street/US 101 NB Ramps
F
F
B
B
B
B
Westhaven Drive/Frontage Road
B
B
B
B
B
B
Scenic Drive/Baker Ranch Drive
A
A
A
A
A
A
Scenic Drive/Cher‐Ae Lane
A
B
C
C
A
A
Scenic Drive/Cher‐Ae Heights Casino
B
F
C
C
A
A
Scenic Drive/Landford Road
B
C
B
C
A
A
Cher‐Ae/101 SB Ramps
‐
‐
‐
‐
B
B
Cher‐Ae/101 NB Ramps
‐
‐
‐
‐
A
B
Cher‐Ae/Westhaven
‐
‐
‐
‐
A
A
Notes:
“‐“ Denotes that the intersection does not exist for this alternative.
Either the proposed US 101/Cher‐Ae Lane interchange or reconstruction of the existing Trinidad‐Main
Street interchange will result in acceptable LOS (LOS C or better) for all of the studied intersections.
R1721PSR003.docx
5
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
Table 3 shows a summary of the US 101 mainline and ramp junction LOS for the year 2040 conditions
with full development of the Trinidad Rancheria Master Plan, for the analyzed alternatives.
TABLE 3: US 101 MAINLINE AND RAMP JUNCTION LOS FOR YEAR 2040
CONDITIONS WITH FULL MASTER PLAN DEVELOPMENT
Location
No Project
Alternative 1A
(Maintain Two‐Way
(Reconstruct
Stop Control
Trinidad‐Main Street
(TWSC)
I/C with Signals)
AM Peak PM Peak
Alternative 3A
(New US 101/
Cher‐Ae Lane I/C)
AM Peak
PM Peak
AM Peak
PM Peak
Hour
Hour
Hour
Hour
Hour
Hour
NB US 101 (Westhaven to Trinidad)
A
B
A
B
A
B
SB US 101 (Westhaven to Trinidad)
A
B
A
B
A
A
US 101 Mainline
US 101 Ramps @ Sixth Street Interchange (Merge/Diverge)
NB Off‐Ramp
B
B
B
B
B
B
NB On‐Ramp
B
B
B
B
B
B
SB Off‐Ramp
A
B
A
B
A
B
SB On‐Ramp
A
B
A
B
A
B
US 101 Ramps @ Cher‐Ae Lane Interchange (Merge/Diverge)
NB Off‐Ramp
‐
‐
‐
‐
B
B
NB On‐Ramp
‐
‐
‐
‐
A
B
SB Off‐Ramp
‐
‐
‐
‐
A
B
SB On‐Ramp
‐
‐
‐
‐
A
B
US 101 Ramps @ Trinidad‐Main Street Interchange (Merge/Diverge)
NB Off‐Ramp
B
B
A
B
A
B
NB On‐Ramp
A
B
A
B
A
B
SB Off‐Ramp
A
A
A
A
A
A
SB On‐Ramp
A
B
A
B
A
B
Notes:
“‐“ Denotes that the ramp junctions do not exist for this alternative.
For the base (no project) year 2040 conditions, the traffic operations analysis shows that without
improvements, there will be an unacceptable LOS at several intersections. In order to provide adequate
traffic operations, either the existing Trinidad‐Main Street interchange will need to be reconstructed or a
new interchange in the vicinity of the Trinidad Rancheria is required.
Intersection Control Evaluation (ICE) ‐ New US 101/Cher‐Ae Lane Interchange:
In accordance with Traffic Operations Policy Directive (TOPD) 13‐02, an Intersection Control Evaluation –
Step 1 (ICE) was completed for the proposed US 101/Cher‐Ae Lane interchange, which evaluated three
alternatives at this proposed interchange. The three intersection alternatives that were evaluated were
All‐Way Stop Control, Signalized Intersections, and Modern Roundabouts. Based on the ICE Report
prepared by Omni‐Means, dated November 30, 2015, all three alternatives are projected to provide
acceptable traffic operations beyond the year 2040 conditions. The All‐Way Stop Control and Signalized
Intersection alternatives provide LOS B for both AM and PM peak hours, while the Modern Roundabout
alternative provides LOS A for both AM and PM peak hours.
R1721PSR003.docx
6
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
Intersection Control Evaluation (ICE) ‐ US 101/Trinidad‐Main Street Interchange:
In accordance with Traffic Operations Policy Directive (TOPD) 13‐02, an intersection control evaluation
was completed for the US 101/Trinidad‐Main Street interchange, which evaluated three alternatives at
this interchange. The three intersection alternatives that were evaluated were No‐Build, Signalized
Intersections, and Modern Roundabouts. Based on the ICE Report prepared by Omni‐Means, dated
November 30, 2015, the No‐Build alternative is projected to provide unacceptable traffic operations under
the year 2040 conditions. Both the Signalized Intersections and Modern Roundabout alternatives are
projected to provide acceptable traffic operations under the year 2040 conditions. The Modern
Roundabout alternative is projected to provide the highest levels of service for all intersections, with LOS
of either A or B for the year 2040 conditions. Signalized intersections would provide LOS B or C, and the
No‐Build alternative is projected to provide levels of service as low as LOS F.
ICE Review by Caltrans District 1 Traffic Operations:
The Intersection Control Evaluations prepared for both the Proposed US 101/Cher‐Ae Lane Interchange
and the US 101/Trinidad‐Main Street Interchange were reviewed by Caltrans District 1 Traffic Operations
staff, and concurrence on both ICE Reports was received in a letter from Troy Arseneau, PE, District 1
ICE Coordinator, dated December 16, 2015. Along with concurrence on the ICE Reports, the letter states
that if full build‐out of the Rancheria Master Plan is anticipated, a new interchange is the appropriate
alternative, versus making significant improvements to downtown Main Street in Trinidad.
Weaving Analysis:
Caltrans District 1 Office of Traffic Operations performed an independent weaving analysis for the
proposed US 101/Cher‐Ae Lane interchange, with results provided in a memorandum dated January 17,
2014. Based on the approximate 0.7 mile spacing proposed, the conclusion from this analysis was that
there is adequate distance on US 101 between the proposed interchange ramps and the existing Trinidad
interchange ramps to accommodate the interaction of entering and exiting traffic. The analysis included
both current and projected traffic volumes on US 101, in both the north and south directions. The
analysis also confirmed that auxiliary lanes will not be needed if a new interchange is constructed near
PM 100.2.
Traffic Collision Analysis:
A traffic collision analysis was prepared by the District 1 Traffic Safety Office on November 17, 2017.
The collision analysis was conducted for the most recently available 3‐year time period (in TASAS
database), from 07/01/2012 to 6/30/2015, for the US 101 corridor from PM 97.4 to PM 101.2 (From 0.7 mile
south of Westhaven Undercrossing to 0.5 mile north of the Trinidad‐Main Street interchange).
There were 30 total reported collisions within this 4.068 mile segment (13 SB, 17 NB, 0 fatality, 9 injury, 23
ʺproperty damage onlyʺ, 5 multi‐vehicle, 8 ʺwet road surfaceʺ, 2 ʺsnow, icy road surfaceʺ, 3 ʺdark‐no
street lightʺ, 3 ʺdark‐street lightʺ). From TASAS Table B, this highway segment has actual ʺFatalʺ and
ʺF+Iʺ collision rates which are less than the statewide average for similar highway facilities. The actual
ʺTotalʺ collision rate is 1.9 times greater than the statewide average for similar highway facilities, as
shown below in Table 4.
TABLE 4: COLLISION RATE SUMMARY FOR HUM‐101‐97.4 / 101.2
TABLE B DATES: 07/01/2012 TO 6/30/2015
Actual Accident Rates
Fatal
F+I
Total
0.000
0.17
0.72
R1721PSR003.docx
Average Accident Rates
Fatal
F+I
Total
0.014
0.17
0.38
7
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
Of the reported 30 collisions within this segment, the principal primary collision factor was ʺimproper
turnʺ (11 of 30), followed by ʺspeedingʺ (6 of 30), ʺother than driverʺ (6 of 30), ʺinfluence of alcoholʺ (4 of
30), ʺother violationsʺ (2 of 30), and ʺfailure to yieldʺ (1 of 30). The primary ʺType of Collisionʺ resulted in
a single vehicle running off the road in 18 of 30 collisions. Of the 18 run off road collisions, 17 involved a
vehicle hitting an object off the roadway; the objects struck are as follows: tree(s) (1 of 17), sign (3 of 17),
embankment (6 of 17), fence (1 of 17), guard rail (1 of 17), object off road (1 of 17), curb or dike (1 of 17),
ditch (1 of 17), utility pole (1 of 17).
Summarizing the 18 run off road collisions, 4 involved a driver under the influence of alcohol, 13 of 18
were of unknown cause, 4 of 18 were the result of improper turn, and 1 of 18 was caused by a merging
vehicle at the Westhaven SB onramp. The initial movement preceding collision involved a vehicle run off
road. The majority of the 30 reported collisions occurred during ʺdaylightʺ (20 of 30) on a ʺdryʺ road
surface (20 of 30). There has been no history of Table B collision concentration locations within this
segment. After review and consideration of all driver/witness statements and Traffic Collision Report
summaries, no collision concentrations or apparent collision patterns were identified. Three of the
reported 30 collisions occurred on ramps within the project limits; these collisions are as follows:
•
•
SB Westhaven On‐ramp ‐ PM 97.772 SB: This collision involved a motorist that ran off the road
to the driverʹs right due to speeding and uncertainty as to which way to turn onto this onramp.
NB Westhaven Off‐ramp ‐ PM 98.003 NB: This collision involved a reckless driver speeding and
running off the road.
SB Trinidad Off‐ramp ‐ PM l00.832 SB: This collision involved a reckless driver (traveling at 80‐
120 mph) which ran off the road to the driverʹs left, over‐corrected, and ran off the road to the
driverʹs right.
The project is expected to include shoulder widening to reduce the frequency of run off road collisions
within the project limits, by providing additional recovery room for errant vehicles. As stated in the
previous collision analysis from November 16, 2015, collision frequency from construction of one of the
proposed interchange alternatives (HUM‐101 approximately PM 98.8/100.3) is expected to increase when
compared with the collision frequency of the existing highway segment at this location. This increase is
expected to be offset by a decrease in collision frequency at the Westhaven, Sixth St., and Trinidad
Interchanges due to lower traffic volumes utilizing these interchanges after construction of one of the
proposed interchange alternatives. Perpetuation of existing center‐line and shoulder rumble strip at all
appropriate locations within the project limits is recommended to help continue to provide auditory and
vibro‐tactile warning to errant drivers.
5. DEFICIENCIES
Primary Deficiencies:
Safe and Sustainable Access to the Trinidad Rancheria ‐ Scenic Drive, from 1.5 miles south of Cher‐Ae
Lane to Cher‐Ae Lane, has numerous narrow, one‐lane unpaved areas that are geologically unstable.
Maintaining this section of Scenic Drive in a sustainable and reliable manner is not viable as documented
in the Geotechnical Screening of Alternatives Memorandum, SHN Consulting Engineering & Geologists,
Inc., August 27, 2015. See Attachment J. Winter storms often result in full closure of this section of Scenic
Drive, leaving the Rancheria with only one means of ingress/egress (Scenic Drive, north of Cher‐Ae
Lane).
Traffic Level of Service ‐ Based on the information presented in Section 4 above, and the Trinidad Area
Freeway Master Plan Study (Traffic Study), prepared by Omni‐Means, Ltd, projected traffic growth within
R1721PSR003.docx
8
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
the study will result in LOS F conditions at intersections on Scenic Drive and at the US 101/Trinidad‐Main
Street I/C.
Tribal Lands Connectivity ‐ When US 101 was constructed in the early 1950’s, Tribal lands were severed
by the freeway. Currently, Tribal members living on the east side of US 101 have to travel 2 miles to
access services at the Trinidad Rancheria. Some residents on the east side of the freeway simply walk
across the freeway lanes to reach the Rancheria (a 0.3+/‐ mile distance).
Secondary Deficiencies:
Inadequate Shoulder Widths ‐ According to the collision analysis prepared by Caltrans District 1 Traffic
Operations, collisions along US 101 in the study area more often than not have resulted in the driver
running off road, typically hitting another object off the road. US 101 shoulder widths through most of
the study area are 4’ wide, rather than the standard 10’ wide. In addition, shoulder widths along Scenic
Drive and Westhaven Drive are minimal or non‐existent.
6. CORRIDOR AND SYSTEM COORDINATION
Route Adoption:
US 101, from Little River Bridge (PM 97.5) to 0.3 mile north of Trinidad‐Main Street (PM 101.0), was
adopted into the freeway system by the California Highway Commission on June 21, 1955.
The US 101 freeway agreement, within the then City of Trinidad city limits, between the California
Department of Public Works and the City of Trinidad, was approved in 1957. The freeway agreement
reconfigured portions of the state highway and identified a half interchange at Trinidad‐Main Street.
The US 101 freeway agreement, from Little River Bridge to 0.3 mile north of Trinidad‐Main Street,
between the California Division of Highways and Humboldt County, was approved in 1957. In 1959, the
freeway agreement was amended to provide a full interchange at Trinidad‐Main Street. The freeway
agreements reconfigured state and local roads to result in the current configuration.
Statewide, Regional, and Local Planning:
The US 101 Draft Transportation Concept Report (TCR) within District 1 was completed in October, 2017.
The Draft TCR concept is to maintain the existing Ultimate Facility Concept in Humboldt County, which
includes a mixture of 4‐lane freeway/expressway and 2‐lane conventional highway. US 101 is a 4‐lane
Freeway within the project area.
US 101, within much of District 1 and within the project limits, is legislatively designated as the “Pacific
Coast Bike Route”. Meeting the needs of non‐motorized travel is a priority with ongoing consideration
being given to upgrading shoulders and providing parallel route access where appropriate.
The District System Management Plan for District 1 was approved on October 3, 2012. US 101, in the
project area, meets the ultimate transportation concept.
US 101, in the project area, is served by Redwood Coast Transit and Redwood Transit System.
There are park and ride lots on both the east and west sides of the Trinidad‐Main Street I/C.
There are not any other planned or programmed STIP projects in the project area.
The Trinidad Rancheria approved the Cher‐Ae Heights Indian Community of the Trinidad Rancheria
Comprehensive Community‐Based Plan in December 2011. The 90+/‐ acre Rancheria is bisected by US
R1721PSR003.docx
9
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
101 and includes housing, offices, library, restaurant and casino on the west side of US 101. East of US
101, the Rancheria includes housing. In the City of Trinidad, the Rancheria owns the Trinidad Pier &
Harbor, as well as a restaurant. The land use portion of the plan identifies expanded commercial, cultural
and residential development.
The Trinidad Rancheria Transportation Plan (TRTP) identifies the need to develop a new interchange
with US 101 at Cher‐Ae Lane (Cher‐Ae Heights Indian Community of the Trinidad Rancheria – Tribal
Transportation Plan 2006‐2026, Winzler & Kelly, March 15, 2006).
The Humboldt County General Plan does not specifically allow for construction of new roadways,
highway overcrossings, or interchanges. However, Humboldt County representatives have been
involved with the development of the project, and have expressed support with regards to moving
forward with the project.
The City of Trinidad’s General Plan update has been in draft form since 2009. Within the City’s draft
General Plan update, significant effort was made to express the City’s desire to maintain the current rural
lifestyle, protect the unique character of the City as a “fishing village”, encourage limited tourism, and
minimize adverse impacts caused by visitors.
Maintenance Agreements:
Improvements identified in the various alternatives will likely require a modification to the existing
maintenance agreement, or a new maintenance agreement with Humboldt County or the Trinidad
Rancheria. This modified or new maintenance agreement would be needed to define maintenance
responsibilities and financial arrangements, and would be executed after the Project Approval and
Environmental Document (PA&ED) phase.
FHWA Actions:
No FHWA action is required.
State Actions:
Alternatives proposing modifications to existing or new interchanges will affect existing freeway access‐
control, and will need to be addressed. In addition, the California Transportation Commission (CTC) will
need to provide consent prior to adding a new public road connection to US 101, which will require a
new freeway agreement with Humboldt County (to be completed after PA&ED phase).
7. ALTERNATIVES
A range of alternatives, including the No‐Build Alternative, were considered at this Project Initiation
phase. All these alternatives, and potentially additional alternatives, will be analyzed in the Project
Approval and Environmental Document (PA&ED) phase. Following are the alternatives under
consideration. Each alternative was analyzed using consistent factors in order to provide similar
comparisons between each alternative. As summarized in Table 5 below, five alternatives have been
identified (Alternatives 3A, 3B, 5A, 5B, and 8) that appear to meet the Purpose and Need. See
Attachment B for preliminary exhibits for each alternative.
R1721PSR003.docx
10
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
R1721PSR003.docx
Increased Safety?
Estimated Project
Cost
Environmental
Impacts
Right‐of‐Way
Impacts
Aesthetics
(Analysis Item)
Alternative 1A: Improvements to
the US 101/Trinidad‐Main Street
interchange with Traffic Signals
Alternative 1B: Improvements to
the US 101/Trinidad‐Main Street
interchange with Roundabouts
Alternative 2: Cher‐Ae Lane
Overcrossing with local road
connections to Westhaven Drive and
Scenic Drive
Alternative 3A: New US 101/Cher‐
Ae Lane interchange with local road
connections to Scenic Drive and
Westhaven Drive
Alternative 3B: Identical to
Alternative 3A but with local road
connection to Scenic Drive and Class
I Mixed‐Use Trail connection to
Westhaven Drive
Alternative 4A: Improvements to
Scenic Drive from Westhaven to
Trinidad.
Alternative 4B: Construction of new
frontage road to replace Scenic
Drive, from Westhaven to Cher‐Ae
Lane, and improvements to Scenic
Drive from Cher‐Ae Lane to
Trinidad.
Alternative 5A: Combine
Alternative 1A and Alternative 2.
Improvements to the US
101/Trinidad‐Main Street
interchange with Traffic Signals, and
Cher‐Ae Lane Overcrossing with
local road connections to Westhaven
Drive and Scenic Drive.
Improves Traffic
Operations?
Alternative
Appears to Meet
Purpose and need?
TABLE 5: SUMMARY OF PROJECT ALTERNATIVES
(1)
(2)
(3)
(4)
(5)
(6)
(7)
No
Yes
Yes
$38.8M
Med
Med
High
No
Yes
Yes
$20.1M
Med
High
High
No
Yes
Yes
$18.2M
High
High
High
Yes
Yes
Yes
$32.3M
High
High
High
Yes
Yes
Yes
$31.3M
High
High
High
No
No
Yes
$22.0M
Med
Low
Low
No
No
Yes
$31.7M
Very
High
Very
High
Med
Yes
Yes
Yes
$48.0M
High
High
Very
High
11
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
R1721PSR003.docx
Increased Safety?
Estimated Project
Cost
Environmental
Impacts
Right‐of‐Way
Impacts
Aesthetics
(Analysis Item)
Alternative 5B: Combine
Alternative 1B and Alternative 2.
Improvements to the US
101/Trinidad‐Main Street
interchange with Roundabouts, and
Cher‐Ae Lane Overcrossing with
local road connections to Westhaven
Drive and Scenic Drive.
Alternative 6: New US 101/Baker
Ranch Road interchange with local
road connections to Scenic Drive
and Westhaven Drive, and frontage
road between Baker Ranch Road and
Cher‐Ae Lane.
Alternative 7: Combine Alternative
2 and Alternative 4B. Cher‐Ae Lane
Overcrossing with local road
connections to Westhaven Drive and
Scenic Drive, new frontage road to
replace Scenic Drive, from
Westhaven to Cher‐Ae Lane, and
improvement to Scenic Drive from
Cher‐Ae Lane to Trinidad.
Alternative 8: New US 101/1.0 Mile
Spacing Interchange approximately
1 mile south of the US 101/Trinidad‐
Main Street Interchange, with local
road connections to Cher‐Ae Lane
and Westhaven Drive.
No‐Build Alternative: This
alternative assumes no
improvements to any of the
roadways in the study area.
Improves Traffic
Operations?
Alternative
Appears to Meet
Purpose and need?
TABLE 5: SUMMARY OF PROJECT ALTERNATIVES
(1)
(2)
(3)
(4)
(5)
(6)
(7)
Yes
Yes
Yes
$31.5M
High
High
Very
High
No
Yes
Yes
$39.6M
Very
High
Very
High
High
No
No
Yes
$39.5M
Very
High
Very
High
High
Yes
Yes
Yes
$32.6M
High
High
High
No
No
No
‐
None
None
None
12
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
Nonstandard Design Features:
For each alternative, the preliminary designs were compared to design standards using the DIB 78 Design
Checklist and a Design Standards Risk Assessment was completed. Common to alternatives 3A and 3B is
the need for an exception to the following mandatory design standard:
Nonstandard Feature:
It is proposed to construct a new interchange on US 101 that would result in interchange spacing
less than the minimum standard spacing. A new interchange is proposed to be located between
the 6th Street Interchange and the Trinidad‐Main Street Interchange, and would be a minimum of
0.7 miles or greater south of the Trinidad‐Main Street Interchange.
Standard for Which Exception is Required:
Per the Highway Design Manual (HDM), Topic 501.3: The minimum interchange spacing shall
be one mile in urban areas, two miles outside of urban areas, and two miles between freeway‐
to‐freeway interchanges and other interchanges.
Reason for Requesting Exception:
The primary reason for requesting the exception is that the project will provide improved access
between the Trinidad Rancheria and US 101. Currently, Scenic Drive is the only roadway
serving the residential, recreational and tribal developments along the coast, between the
community of Westhaven and the City of Trinidad. North and south of the Trinidad
Rancheria, Scenic Drive extends along unstable coastal bluffs that have a history of slides
and slip‐outs resulting in closure of the road for extended periods of time. Numerous
locations are unpaved and single‐lane. These closures have a significant negative impact
on public access and emergency access along Scenic Drive. The proposed project would
add another point of access between US 101 and Scenic Drive which will improve
emergency access and result in a public safety benefit.
Additional benefits to the project are the reconnection of tribal lands, which were severed by the
construction of US 101, and to provide infrastructure that will accommodate planned future
development. Development of the Trinidad Rancheria’s approved master plan (Cher‐Ae Heights
Indian Community of the Trinidad Rancheria, Comprehensive Community‐Based Plan, December
2011) would increase traffic volume and cause an unacceptable level of service.
Interchange Spacing Design Exception Approval:
The interchange spacing design standard exception was approved on September 29, 2016 and can
be provided upon request.
In support of the approval of the interchange spacing design exception, Omni‐Means prepared a
Technical Memorandum, dated September 22, 2016, that provides a detailed analysis of the items
required to be addressed pursuant to DIB No. 77 “Interchange Spacing”.
Other anticipated exceptions to design standards that are common to all alternatives are summarized
below and included in Table 6.
Standard for Which Exception is Required:
Mandatory Design Standard, 203.2 Standards for Curvature: Tables 202.2A through 202.2E shall
be the minimum radius of curve for superelevation rates and design speeds on highways.
R1721PSR003.docx
13
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
Nonstandard Feature:
The minimum radius of horizontal curves for US 101 is 2,100 feet. Existing horizontal curves
along US 101 vary from 1,800 feet to 12,000 feet, thus would require an exception without a
change in the horizontal alignment.
Standard for Which Exception is Required:
Mandatory Design Standard, 305.1 Median Width: Freeways and Expressways. In areas where
restrictive conditions prevail the minimum median width shall be 22 feet.
Nonstandard Feature:
Currently the median width along US 101 in the project area varies from 4 feet at the south end to
22 feet at the north end. The various project alternatives would improve US 101 with a minimum
median width of 12’.
Standard for Which Exception is Required:
Advisory Design Standard, 309.1 Horizontal Clearances for Highways: Existing above‐ground
utilities and existing large trees as defined in Index 902.2(2) should conform to the guidance
associated with necessary highway features stated above.
Nonstandard Feature:
It is anticipated that all alternatives will have conflicts with existing trees, and may not be able to
conform to the guidance discussed above. This item will be further reviewed during subsequent
phases of project development.
TABLE 6: DESIGN STANDARDS RISK ASSESSMENT
(COMMON TO ALL ALTERNATIVES)
Probability
of Design
Exception
Approval
Mandatory Design Standard
Existing condition.
Evaluate collisions.
M: 203.2 Standards for Curvature:
Tables 202.2A through 202.2E shall be the
minimum radius of curve for superelevation
rates and design speeds on highways.
The minimum radius of horizontal curves for US
101 is 2,100 feet. Existing horizontal curves along
US 101 vary from 1,800 feet to 12,000 feet, thus
would require an exception without a change in the
horizontal alignment.
M: 305.1 Median Width: Freeways and
Expressways.
In areas where restrictive conditions prevail the
minimum median width shall be 22 feet.
Currently the median width along US 101 in the
project area varies from 4 feet at the south end to 22
feet at the north end. The various project
alternatives would improve US 101 with a minimum
median width of 12’.
R1721PSR003.docx
Justification for Probability Rating
14
HIGH
Existing condition.
Proposed improvement to
existing condition.
HIGH
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
TABLE 6: DESIGN STANDARDS RISK ASSESSMENT
(COMMON TO ALL ALTERNATIVES)
Probability
of Design
Exception
Approval
Advisory Design Standard
Justification for Probability Rating
Fixed objects will be addressed
and removed to the fullest
extent feasible.
A: 309.1 Horizontal Clearances for Highways:
Existing above-ground utilities and existing large
trees as defined in Index 902.2(2) should conform to
the guidance associated with necessary highway
features stated above.
HIGH
It is anticipated that all alternatives will have
conflicts with existing trees, and may not be able to
conform to the guidance discussed above. This item
will be further reviewed during subsequent phases
of project development.
For all other exceptions to design standards, a Design Standards Risk Assessment was completed and is
included with each alternative discussion below.
Improvements to Main Street with Signalized Intersections:
Alternative 1A
Four traditional signalized intersections
Replacement of the Trinidad‐Main Street Interchange
Widen Main Street from Scenic Drive to Westhaven Drive
Widen Scenic Drive from Cher‐Ae Lane to Main Street
Alternative 1A includes Improvements to Main Street with signalized intersections, replacement of the
Trinidad‐Main Street Interchange (PM 100.7), widening of Main Street from Scenic Drive to Westhaven
Drive, and widening of Scenic Drive from Cher‐Ae Lane to Main Street in the City of Trinidad.
See Figure 2.
R1721PSR003.docx
15
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
Figure 2 ‐ Alternative 1A Schematic Exhibit
Alternative 1A improvements include:
Construction of traffic signals at each of the four Main Street and Westhaven Drive intersections
at this location
Reconstruction and widening of Main Street to accommodate future traffic demands
Reconstruction of the Main Street profile to meet current design standards
Construction of a new US 101 undercrossing structure to accommodate the widened Main Street
Reconstruction of the US 101 on and off‐ramps to accommodate future traffic demands
Reconstruction of US 101 mainline to provide a minimum 12 foot wide median and 10 foot
shoulders
Reconstruction of US 101 mainline profile to meet current decision sight distance standards
Widening and/or reconstruction of Scenic Drive to provide 4 foot minimum shoulders and
sidewalk on one side
Reconstruction of adjacent roadways to tie in to existing improvements
(1) Purpose and Need: Alternative 1A alone does not meet the purpose and need for this project.
While improvements to the Trinidad‐Main Street Interchange would accommodate the planned
future development in the area, it does not provide for a 2nd safe and sustainable access to and from
US 101, for all modes of transportation, to the Trinidad Rancheria and the surrounding communities,
nor does it reconnect tribal lands within the study area.
(2) Traffic Operations: Alternative 1A includes improvements to the US 101/Trinidad‐Main Street
interchange, as well as Scenic Drive, that would result in improved traffic operations, and would
provide for acceptable levels of service for the 3 intersections that would otherwise perform at
unacceptable levels of service.
(3) Increased Safety: Alternative 1A will widen the median and shoulders on US 101, and would
chiefly construct the proposed improvements to current standards (See Section 8). Scenic Drive,
between Cher‐Ae Lane and Main Street, will also be improved. These improvements will likely
result in increased public safety.
R1721PSR003.docx
16
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
(4) Project Costs: Total Capital Outlay project costs for Alternative 1A are estimated at $38.8 million,
are higher than expected for projects of similar size and nature, and are in the high‐range of
estimated costs for all alternatives. The additional project costs can be attributed to replacement of
the Trinidad‐Main Street Interchange (PM 100.7), extensive grading work and significant retaining
wall work. See Appendix E for the preliminary project cost estimate worksheet.
(5) Environmental Impacts: It is anticipated that Alternative 1A will have some minor impacts to
existing environmental resources within the project limit. Some existing drainage features, including
culverts and drainage ditches/streams will need modification or mitigation. In addition, there is
potential to discover cultural resources in the vicinity of the project. However, since it is
reconstruction and will have a similar footprint to the existing footprint, the risk level is less than
other alternatives proposing new roadways.
(6) Right‐of‐Way Impacts: Due to the extensive grading and vertical profile changes, it is
anticipated that some right‐of‐way acquisition will be required for Alternative 1A. Right‐of‐way
acquisition is expected to be limited to partial takes in areas where roads are widened, or extensive
grading must be done to allow for adequate sight distance or to meet other standards. It is estimated
that 7‐10 parcels will be affected adjacent to the US 101/Trinidad‐Main Street interchange, and 10‐15
parcels could be affected along Scenic Drive. See Section 8 and Appendix D for the right‐of‐way
impact summary and exhibit.
(7) Aesthetics: Alternative 1A will significantly alter the existing rural and unique character of the
Trinidad‐Main Street interchange. The drastic change is likely to be considered incompatible with
the rural fishing village character of the City of Trinidad, and the City’s Draft General Plan.
(8) Design Exceptions: The preliminary design and design standards were checked using the DIB 78
Design Checklist. A Design Standards Risk Assessment was completed for Alternative 1A and the
anticipated exceptions to design standards (beyond those identified for all alternatives) are presented
in Table 6. The Design Standards Risk Assessment for this alternative will be further addressed in
the PA&ED phase.
TABLE 7: DESIGN STANDARDS RISK ASSESSMENT (ALTERNATIVE 1A)
Probability
of Design
Exception
Approval
Mandatory Design Standard
Proposed is similar to the
existing condition.
Operation to be verified by
traffic modeling.
M: 504.3(3) - Location and Design of Ramp
Intersections on the Crossroads.
The minimum distance (curb return to curb
return) between ramp intersections and local
road intersections shall be 400 feet.
MEDIUM
As little as 20 feet is provided in the design.
R1721PSR003.docx
Justification for Probability Rating
17
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
TABLE 7: DESIGN STANDARDS RISK ASSESSMENT (ALTERNATIVE 1A)
Probability
of Design
Exception
Approval
Advisory Design Standard
A: 310.2 - Outer Separation.
In urban areas and in mountainous terrain, the width
of the outer separation should be a minimum of 26
feet from edge of traveled way to edge of traveled
way.
Justification for Probability Rating
Existing condition.
Need to evaluate collisions.
HIGH
Outer separation between the southbound US 101
off-ramp and Patricks Point Drive is only 24'.
Improvements to Main Street with Roundabouts:
Alternative 1B
Construct two modern roundabouts
Reconstruct on and off‐ramps
Widen Scenic Drive from Cher‐Ae Lane to Main Street
Alternative 1B includes improvements to Main Street with modern roundabouts, including
reconstruction of the on and off‐ramps, reconstruction of Main Street, and widening of Scenic Drive from
Cher‐Ae Lane to Main Street in the City of Trinidad (PM 100.0 – 101.1).
See Figure 3.
Figure 3 ‐ Alternative 1B Schematic Exhibit
R1721PSR003.docx
18
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
Alternative 1B improvements include:
Construction of two large modern roundabouts at the interchange
Reconstruction of Main Street to accommodate future traffic demands
Reconstruction of the US 101 on and off‐ramps
Widening and/or reconstruction of Scenic Drive to provide 4 foot minimum shoulders and
sidewalk on one side
Reconstruction of adjacent roadways to tie in to existing improvements
(1) Purpose and Need: Alternative 1B alone does not meet the purpose and need for this project.
While improvements to the Trinidad‐Main Street Interchange would accommodate the planned
future development in the area, it does not provide for a 2nd safe and sustainable access to and from
US 101, for all modes of transportation, to the Trinidad Rancheria and the surrounding communities,
nor does it reconnect tribal lands within the study area.
(2) Traffic Operations: Alternative 1B includes improvements to the US 101/Trinidad‐Main Street
interchange, as well as Scenic Drive, that would result in improved traffic operations, and would
provide for acceptable levels of service for the 3 intersections that would otherwise perform at
unacceptable levels of service.
(3) Increased Safety: Alternative 1B will widen the shoulders on US 101 within the immediate
project area, and would chiefly construct the proposed improvements to current standards (See
Section 8). Scenic Drive, between Cher‐Ae Lane and Main Street, will also be improved. These
improvements will likely result in increased public safety.
(4) Project Costs: Total Capital Outlay project costs for Alternative 1B are estimated at $20.1 million,
which is similar to what would be expected for projects of similar size and nature, and is in the low‐
range of estimated costs for all alternatives. The cost estimate provided for this alternative assumes
significantly less reconstruction of US 101 adjacent to the Trinidad‐Main Street interchange, as well as
allowing the existing undercrossing structure to remain in place. The median is not widened with
this alternative, since the existing structure would remain in place, and there would not be adequate
decision sight distance (DSD) from US 101 to the northbound off‐ramp to Main Street without
reconstruction of US 101 similar to alternative 1A. To replace the existing structure and reconstruct
US 101 to meet the DSD standard, estimated costs for Alternative 1B would be similar to Alternative
1A, around $37.8 million. See Appendix E for the preliminary project cost estimate worksheet.
(5) Environmental Impacts: It is anticipated that Alternative 1B will have slightly more impacts
(than Alternative 1A) to existing environmental resources within the project limit. Some existing
drainage features, including culverts and drainage ditches/streams will need modification or
mitigation. In addition, there is potential to discover cultural resources in the vicinity of the project.
However, since it is reconstruction and will have a similar footprint to the existing footprint, the risk
level is less than other alternatives proposing new roadways.
(6) Right‐of‐Way Impacts: Due to the extensive grading and vertical profile changes, it is
anticipated that some right‐of‐way acquisition will be required for Alternative 1B. Right‐of‐way
acquisition would be similar to Alternative 1A, with the exception that the roundabout footprints will
be larger, and providing accessibility through the interchange will require additional length of lower
grades, thereby lowering the vertical profile of Main Street more than Alternative 1A. This would
likely require some full R/W acquisition to adjacent parcels east of US 101, and northeast of
Westhaven Drive. It is estimated that 7‐10 parcels will be affected adjacent to the US 101/Trinidad‐
R1721PSR003.docx
19
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
Main Street interchange, and 10‐15 parcels could be affected along Scenic Drive. See Section 8 and
Appendix D for the right‐of‐way impact summary and exhibit.
(7) Aesthetics: Alternative 1B will significantly alter the existing rural character of the Trinidad‐
Main Street interchange, and will require a significantly larger footprint within the interchange area.
The drastic change is likely to be considered incompatible with the rural fishing village character of
the City of Trinidad, and the City’s Draft General Plan.
(8) Design Exceptions: The preliminary design and design standards were checked using the DIB 78
Design Checklist. A Design Standards Risk Assessment was completed for Alternative 1B and the
anticipated exceptions to design standards (beyond those identified for all alternatives) are presented
in Table 7. The Design Standards Risk Assessment for this alternative will be further addressed in
the PA&ED phase.
TABLE 8: DESIGN STANDARDS RISK ASSESSMENT (ALTERNATIVE 1B)
Probability
of Design
Exception
Approval
Mandatory Design Standard
M: 504.3(3) - Location and Design of Ramp
Intersections on the Crossroads.
The minimum distance (curb return to curb
return) between ramp intersections and local
road intersections shall be 400 feet.
MEDIUM
Justification for Probability Rating
Proposed is similar to the
existing condition.
Operation to be verified by
traffic modeling.
As little as 20 feet is provided in the design.
Probability
of Design
Exception
Approval
Advisory Design Standard
A: 201.7 – Decision Sight Distance.
On freeways and expressways the decision sight
distance values in Table 201.7 should be used at
lane drops and at off-ramp noses to interchanges,
branch connections, roadside rests, vista points, and
inspection stations.
The minimum Decision Sight Distance for 70 mph
is 1,105 feet. Without reconstruction of the US 101
profile, a decision sight distance of approximately
972 feet (55 mph) is provided for the northbound
off-ramp to Main Street.
A: 310.2 - Outer Separation.
In urban areas and in mountainous terrain, the width
of the outer separation should be a minimum of 26
feet from edge of traveled way to edge of traveled
way.
Outer separation between the southbound US 101
off-ramp and Patricks Point Drive is only 24'.
R1721PSR003.docx
20
MEDIUM
Justification for Probability Rating
SSD is OK; 70 mph SSD =
750-ft.
Need to evaluate collisions.
Need to evaluate potential
mitigation measures including
lighting striping, signage and
others.
Existing condition.
Need to evaluate collisions.
HIGH
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
New Cher‐Ae Lane Overcrossing (PM 100.0):
Alternative 2
Construct new Cher‐Ae Lane Overcrossing
Local road connection to Scenic Drive and Westhaven Drive
Widen Scenic Drive from Cher‐Ae Lane to Main Street
Widen Westhaven Drive from Westhaven to Trinidad
Alternative 2 includes construction of a new overcrossing structure at Cher‐Ae Lane (PM 100.0), with
local road connections to Scenic Drive and Westhaven Drive, widening of Scenic Drive from Cher‐Ae
Lane to Main Street in the City of Trinidad, and widening of Westhaven Drive in the Community of
Westhaven to Main Street in the City of Trinidad. (PM 98.1 – 100.7).
See Figure 4.
Figure 4 ‐ Alternative 2 Schematic Exhibit
Alternative 2 improvements include:
Construction of a new overcrossing structure at PM 100.0
Reconstruction of Cher‐Ae Lane from Scenic Drive into the Rancheria
Construction of the Cher‐Ae Lane Extension to Westhaven Drive
Widening and/or reconstruction of Scenic Drive to provide 4 foot minimum shoulders and
sidewalk on one side
Widening of Westhaven Drive from the Community of Westhaven to the City of Trinidad
(1) Purpose and Need: Alternative 2 alone does not meet the purpose and need for this project. A
new overcrossing structure without a connection to US 101 would provide for only 2 of the 3 items of
the purpose and need. The new overcrossing would provide for a 2nd safe and sustainable access to
the Trinidad Rancheria, and would also reconnect tribal lands across US 101. But these
improvements will not accommodate the planned future development in the area, and thus, does not
meet the purpose and need.
R1721PSR003.docx
21
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
(2) Traffic Operations: Alternative 2 includes construction of a new overcrossing structure over US
101 at Cher‐Ae Lane, as well as improvements to Scenic Drive and Westhaven Drive, that would
result in slightly improved traffic operations. However, without any improvements to any of the
interchange areas, and without a direct connection to US 101, conditions for the Trinidad‐Main Street
interchange will remain at unacceptable levels of service, as outlined in the Traffic Operations section
above.
(3) Increased Safety: Alternative 2 will not provide any improvements to US 101, but will provide
improvements to Scenic Drive and Westhaven Drive. Therefore, increased safety would be expected
on Scenic Drive, from Cher‐Ae Lane to Trinidad, and along the length of Westhaven Drive, but
generally, overall increased safety would be minimal.
(4) Project Costs: Total Capital Outlay project costs for Alternative 2 are estimated at $18.2 million,
which is similar to what would be expected for projects of similar size and nature, and is in the low‐
range of estimated costs for all alternatives. The cost estimate provided for this alternative assumes
no reconstruction of US 101 adjacent to the Trinidad Rancheria or Trinidad. See Appendix E for the
preliminary project cost estimate worksheet.
(5) Environmental Impacts: It is anticipated that Alternative 2 will have somewhat high
environmental impacts, since it includes construction of a new roadway. It is likely that impacts
would include existing environmental resources within the project limit. Some existing drainage
features, including culverts and drainage ditches/streams will need modification or mitigation. The
area east of US 101 is mostly undeveloped, and has an increased potential of various environmental
impacts. In addition, there is potential to discover cultural resources in the vicinity of the project.
This alternative is in the medium range of environmental impacts as compared to other alternatives,
since the footprint only includes a single road connection across US 101, with no connection to US
101.
(6) Right‐of‐Way Impacts: Right‐of‐Way impacts for Alternative 2 will be somewhat high, since the
project will construct a new roadway across US 101, thereby requiring acquisition of R/W for the full
width of the roadway and associated improvements, including grading. Much of the R/W that will
be required for this project is land already owned by the Trinidad Rancheria, which will significantly
decrease the overall R/W impacts. It is estimated that 10‐12 parcels may be affected adjacent to US
101 in the Cher‐Ae Lane area for the overcrossing, as well as 10‐15 parcels along Scenic Drive. See
Section 8 and Appendix D for the right‐of‐way impact summary and exhibit.
(7) Aesthetics: Alternative 2 will alter the US 101 corridor with construction of a new overcrossing
structure. This impact will be significant for the area, but will be similar to existing interchanges and
overcrossing structures along the US 101 corridor.
(8) Design Exceptions: The preliminary design and design standards were checked using the DIB 78
Design Checklist. A Design Standards Risk Assessment was completed for Alternative 2 and there
no anticipated exceptions to design standards (beyond those identified for all alternatives). The
Design Standards Risk Assessment for this alternative will be further addressed in the PA&ED phase.
R1721PSR003.docx
22
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
New US 101/Cher‐Ae Lane Interchange (PM 100.0):
Alternative 3A
Construct new US 101/Cher‐Ae Lane Interchange
Local road connection to Scenic Drive and Westhaven Drive
Widen Scenic Drive from Cher‐Ae Lane to Main Street
Widen Westhaven Drive from Westhaven to Trinidad
Alternative 3A includes construction of a new Type L‐1 Compact Diamond interchange at Cher‐Ae Lane
(PM 100.0), with both northbound and southbound ramp connections, local road connections to Scenic
Drive and Westhaven Drive, widening of Scenic Drive from Cher‐Ae Lane to Main Street in the City of
Trinidad, and widening of Westhaven Drive in the Community of Westhaven to Main Street in the City
of Trinidad. (PM 98.1 – 100.7).
See Figure 5.
Figure 5 ‐ Alternative 3A Schematic Exhibit
Alternative 3A improvements include:
Construction of a new Type L‐1 Compact Diamond interchange at PM 100.0
Construction of all northbound and southbound ramp connections
Reconstruction of Cher‐Ae Lane from Scenic Drive into the Rancheria
Construction of the Cher‐Ae Lane Extension to Westhaven Drive
Widening and/or reconstruction of Scenic Drive to provide 4 foot minimum shoulders and
sidewalk on one side
Widening of Westhaven Drive from the Community of Westhaven to the City of Trinidad
(1) Purpose and Need: Alternative 3A appears to meet the purpose and need for this project. A new
interchange with connections to US 101, and public road connections to Scenic Drive and Westhaven
Drive would provide for all of the purpose and need requirements outlined in this study. The new
interchange would provide for a 2nd safe and sustainable access to and from US 101, for all modes of
transportation, to the Trinidad Rancheria and the surrounding communities, accommodate the
planned future development in the area, and would also reconnect tribal lands across US 101.
R1721PSR003.docx
23
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
(2) Traffic Operations: Alternative 3A includes construction of a new interchange with an
overcrossing structure over US 101, public road connections to Scenic Drive and Westhaven Drive, as
well as improvements to Scenic Drive from Cher‐Ae Lane to Trinidad and for the length of
Westhaven Drive. These improvements would result in greatly improved traffic operations within
the study area. Once constructed, and upon full build‐out of the Trinidad Rancheria Master Plan, all
roadways, including US 101 mainline and interchanges, will operate at acceptable levels of service,
including the 3 intersections that would otherwise perform at unacceptable levels of service.
(3) Increased Safety: Alternative 3A will widen the median and shoulders on US 101, and would
chiefly construct the proposed improvements to current standards (See Section 8). Scenic Drive,
between Cher‐Ae Lane and Main Street, will also be improved, along with Westhaven Drive from the
community of Westhaven to Trinidad. These improvements will likely result in increased public
safety.
(4) Project Costs: Total Capital Outlay project costs for Alternative 3A are estimated at $32.3 million,
which is slightly higher than what would be expected for projects of similar size and nature, and is in
the mid‐range of estimated costs for all alternatives. Costs estimated for this alternative are increased
due to areas that will require some extensive grading and retaining wall work due to existing
topography. This additional cost is typical of nearly all of the alternatives that were analyzed with
this study, due to the highly variable terrain within the entire study area. See Appendix E for the
preliminary project cost estimate worksheet.
(5) Environmental Impacts: It is anticipated that Alternative 3A will have somewhat high
environmental impacts, since it includes construction of a new roadway, and construction of a full
new interchange. It is likely that impacts would include existing environmental resources within the
project limit. Some existing drainage features, including culverts and drainage ditches/streams will
need modification or mitigation. The area east of US 101 is mostly undeveloped, and has an
increased potential of various environmental impacts. The area that includes the new interchange
and on and off‐ramps is also mostly undeveloped, and will likely have impacts to existing
environmentally sensitive areas. In addition, there is potential to discover cultural resources in the
vicinity of the project. This alternative is in the high range of environmental impacts as compared to
other alternatives, since the footprint includes a road connection across US 101, along with full ramp
connections to US 101.
(6) Right‐of‐Way Impacts: Right‐of‐Way impacts for this alternative will be somewhat high, since
the project will construct a new roadway across US 101, as well as new ramp connections to US 101,
thereby requiring acquisition of R/W for the full width of the roadway, ramps, and associated
improvements, including grading. A significant amount of the R/W that will be required for this
project is land already owned by the Trinidad Rancheria, and therefore will significantly decrease the
overall R/W impacts. It is estimated that 15‐20 parcels may be affected adjacent to US 101 in the
Cher‐Ae Lane/Trinidad Rancheria area, as well as 10‐15 parcels along Scenic Drive. See Section 8 and
Appendix D for the right‐of‐way impact summary and exhibit.
(7) Aesthetics: Alternative 3A will alter the US 101 corridor with construction of a new interchange.
While this impact will be significant for the area, a new interchange will be similar to existing
interchanges and overcrossing structures along the US 101 corridor.
(8) Design Exceptions: The preliminary design and design standards were checked using the DIB 78
Design Checklist. A Design Standards Risk Assessment was completed for Alternative 3A and the
anticipated exceptions to design standards (beyond those identified for all alternatives) are presented
R1721PSR003.docx
24
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
in Table 9. The Design Standards Risk Assessment for this alternative will be further addressed in
the PA&ED phase.
TABLE 9: DESIGN STANDARDS RISK ASSESSMENT (ALTERNATIVE 3A)
Probability
of Design
Exception
Approval
Mandatory Design Standard
M: 504.3(3) - Location and Design of Ramp
Intersections on the Crossroads.
The minimum distance (curb return to curb
return) between ramp intersections and local
road intersections shall be 400 feet.
HIGH
250-ft provided between the southbound ramps and
the new Cher-Ae Lane roundabout.
M: 504.7 – Weaving Sections.
The minimum weaving length, measured as
shown on Figures 504.2A and 504.2B shall be
2,000 feet in urban areas, 5,000 feet outside
urban areas, and 5,000 feet between freeway-tofreeway interchanges and other interchanges.
The minimum distance (curb return to curb
return) between ramp intersections and local
road intersections shall be 400 feet.
1,720-ft and 2,385-ft provided in the NB and SB
directions, respectively, between the proposed
interchange ramps and the existing interchange
ramps.
HIGH
R1721PSR003.docx
25
Justification for Probability Rating
No negative operational effect,
to be verified by traffic
modeling.
Maximized distance based on
other design criteria to match
existing facilities.
The CT District 1 Traffic
Operations Branch completed a
weaving analysis between the US
101/Trinidad-Main Street
Interchange (PM 100.7) and the
Alternative 3A and 3B proposed
interchange at Route 101/CherAe Lane (PM 100.0). Projected
design year 2040 traffic volumes
were used and concluded that the
freeway section between the two
interchanges would operate with
acceptable levels of service with
the project’s full build out under
future conditions and auxiliary
lanes on the freeway between the
interchanges would not be
required within the design year
period. These findings would
also apply to interchanges at
greater spacing such as the
Alternative 8 proposed
interchange at US 101/New
Local Road (PM 99.7).
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
TABLE 9: DESIGN STANDARDS RISK ASSESSMENT (ALTERNATIVE 3A)
Probability
of Design
Exception
Approval
Advisory Design Standard
A: 201.7 – Decision Sight Distance.
On freeways and expressways the decision sight
distance values in Table 201.7 should be used at
lane drops and at off-ramp noses to interchanges,
branch connections, roadside rests, vista points, and
inspection stations.
HIGH
Justification for Probability Rating
SSD is OK; 70 mph SSD =
750-ft.
Need to evaluate collisions.
Need to evaluate potential
mitigation measures including
lighting striping, signage and
others.
The minimum Decision Sight Distance for 70 mph
is 1,105 feet. Without reconstruction of the US 101
profile, a decision sight distance of approximately
750 feet (50 mph) is provided for the northbound
off-ramp to Cher-Ae Lane.
New US 101/Cher‐Ae Lane Interchange (PM 100.0):
Alternative 3B
Construct new US 101/Cher‐Ae Lane Interchange
Local road connection to Scenic Drive; mixed‐use path to
Westhaven
Widen Scenic Drive from Cher‐Ae Lane to Main Street
Widen Westhaven Drive from Westhaven to Trinidad
Alternative 3B is identical to Alternative 3A, with the exception that instead of a local road connection to
Westhaven Drive, a Class I mixed‐use trail will be constructed from the northbound ramps intersection
east to Westhaven Drive.
See Figure 6.
R1721PSR003.docx
26
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
Figure 6 ‐ Alternative 3B Schematic Exhibit
Alternative 3B improvements include:
Construction of a new Type L‐1 Compact Diamond interchange at PM 100.0
Construction of all northbound and southbound ramp connections
Reconstruction of Cher‐Ae Lane from Scenic Drive into the Rancheria
Construction of a Class I mixed‐use trail connection to Westhaven Drive
Widening and/or reconstruction of Scenic Drive to provide 4 foot minimum shoulders and
sidewalk on one side
Widening of Westhaven Drive from the Community of Westhaven to the City of Trinidad
(1) Purpose and Need: Alternative 3B appears to meet the purpose and need for this project. A new
interchange with connections to US 101, and an improved public road connection to Scenic Drive,
would provide for all of the purpose and need requirements outlined in this study. The new
interchange would provide for a 2nd safe and sustainable access to and from US 101, for all modes of
transportation, to the Trinidad Rancheria and the surrounding communities, accommodate the
planned future development in the area, and would also reconnect tribal lands across US 101 with a
mixed‐use trail connection to Westhaven Drive.
(2) Traffic Operations: Alternative 3B includes construction of a new interchange with an
overcrossing structure over US 101, a public road connection to Scenic Drive, a mixed‐use trail
connection to Westhaven Drive, as well as improvements to Scenic Drive from Cher‐Ae Lane and for
the length of Westhaven Drive. These improvements would result in greatly improved traffic
operations within the study area. Once constructed, and upon full build‐out of the Trinidad
Rancheria Master Plan, all roadways, including US 101 mainline and interchanges, will operate at
acceptable levels of service, including the 3 intersections that would otherwise perform at
unacceptable levels of service.
(3) Increased Safety: Alternative 3B will widen the median and shoulders on US 101, and would
chiefly construct the proposed improvements to current standards (See Section 8). Scenic Drive,
between Cher‐Ae Lane and Main Street, will also be improved, along with Westhaven Drive from the
community of Westhaven to Trinidad. These improvements will likely result in increased public
safety.
R1721PSR003.docx
27
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
(4) Project Costs: Total Capital Outlay project costs for Alternative 3B are estimated at $31.3 million,
slightly less than alternative 3A, is slightly higher than what would be expected for projects of similar
size and nature, and is in the mid‐range of estimated costs for all alternatives. Costs estimated for
this alternative are increased due to areas that will require some extensive grading and retaining wall
work due to existing topography. This additional cost is typical of nearly all of the alternatives that
were analyzed with this study, due to the highly variable terrain within the entire study area. See
Appendix E for the preliminary project cost estimate worksheet.
(5) Environmental Impacts: It is anticipated that Alternative 3B will have somewhat high
environmental impacts, since it includes construction of a new roadway, and construction of a full
new interchange. It is likely that impacts would include existing environmental resources within the
project limit. Some existing drainage features, including culverts and drainage ditches/streams will
need modification or mitigation. The area east of US 101 is mostly undeveloped, and has an
increased potential of various environmental impacts. The area that includes the new interchange
and on and off‐ramps is also mostly undeveloped, and will likely have impacts to existing
environmentally sensitive areas. In addition, there is potential to discover cultural resources in the
vicinity of the project. This alternative is in the high range of environmental impacts as compared to
other alternatives, since the footprint includes a road connection across US 101, along with full ramp
connections to US 101.
(6) Right‐of‐Way Impacts: Right‐of‐Way impacts for Alternative 3B will be somewhat high, slightly
less than Alternative 3A as the project will construct a new roadway across US 101, as well as new
ramp connections to US 101, thereby requiring acquisition of R/W for the full width of the roadway,
ramps, and associated improvements, including grading. A significant amount of the R/W that will
be required for this project is land already owned by the Trinidad Rancheria, and therefore will
significantly decrease the overall R/W impacts. It is estimated that 15‐20 parcels may be affected
adjacent to US 101 in the Cher‐Ae Lane/Trinidad Rancheria area, as well as 10‐15 parcels along Scenic
Drive. See Section 8 and Appendix D for the right‐of‐way impact summary and exhibit.
(7) Aesthetics: Alternative 3B will alter the US 101 corridor with construction of a new interchange.
While this impact will be significant for the area, a new interchange will be similar to existing
interchanges and overcrossing structures along the US 101 corridor.
(8) Design Exceptions: The preliminary design and design standards were checked using the DIB 78
Design Checklist and a draft Design Standards Risk Assessment was completed for Alternative 3B.
The exceptions to design standards for Alternative 3B are anticipated to be identical to Alternative
3A. See previous Table 9.
Improve Scenic Drive from Westhaven to Trinidad:
Alternative 4A
Improve Scenic Drive from US 101 in the Community of
Westhaven to Main Street in the City of Trinidad (PM
98.4/100.7)
Alternative 4A includes widening of Scenic Drive from US 101 in the Community of Westhaven to Main
Street in the City of Trinidad. (PM 98.4/100.7)
R1721PSR003.docx
28
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
See Figure 7.
Figure 7 – Section of Scenic Drive, south of Cher‐Ae Lane, showing slopes falling into Scenic Drive, and existing
pavement in poor condition.
Alternative 4A improvements include:
Widening and/or reconstruction of Scenic Drive to provide 4 foot minimum shoulders and
sidewalk on one side
(1) Purpose and Need: Alternative 4A does not meet the purpose and need for this project.
Improvements to Scenic Drive from the community of Westhaven, to Main Street in the City of
Trinidad, will improve the safety and reliability of Scenic Drive, but will not sufficiently address any
of the requirements of the purpose and need for the study.
(2) Traffic Operations: Alternative 4A includes improvements to Scenic Drive, from the community
of Westhaven, to Main Street in the City of Trinidad. These improvements will have little effect on
the overall traffic operations within the study area. Upon full build‐out of the Trinidad Rancheria
Master Plan, conditions for the Trinidad‐Main Street interchange will operate at unacceptable levels
of service, as outlined in the Traffic Operations section above.
(3) Increased Safety: Alternative 4A will improve Scenic Drive, between the community of
Westhaven and Main Street. This will increase the safety of Scenic Drive through this segment, but
increased safety for this alternative is significantly lower than most other alternatives.
(4) Project Costs: Total Capital Outlay project costs for Alternative 4A are estimated at $22.0 million,
which is significantly higher than what would be expected for projects of similar size and nature, and
is in the low‐range of estimated costs for all alternatives. Costs estimated for this alternative are
increased significantly due to multiple areas along Scenic Drive that will require extensive grading
and retaining wall work due to existing topography along the roadway. Much of Scenic Drive
R1721PSR003.docx
29
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
includes steep slopes down to the ocean on the west side of Scenic Drive, and steep slopes upwards
to the east of Scenic Drive. See Appendix E for the preliminary project cost estimate worksheet.
(5) Environmental Impacts: It is anticipated that Alternative 4A will have a medium amount of
environmental impacts, since it includes improvements to an existing roadway. It is likely that
impacts would include existing environmental resources within the project limit. Some existing
drainage features, including culverts and drainage ditches/streams will need modification or
mitigation. There are up to 4‐5 existing streams within the Scenic Drive corridor that would likely
require modification or mitigation. Extensive grading for this alternative will likely impact other
environmentally sensitive areas. In addition, there is potential to discover cultural resources in the
vicinity of the project. This alternative is in the mid‐range of environmental impacts as compared to
other alternatives, since the footprint is increased only slightly because the project area is an existing
roadway.
(6) Right‐of‐Way Impacts: Right‐of‐Way impacts for Alternative 4A will be lower than other
alternatives included in this study. Since the roadway already exists, R/W impacts are expected to be
limited to small takes along Scenic Drive for grading modifications. It is estimated that 20 parcels
may be affected adjacent to Scenic Drive along this corridor, with impacts mostly including sliver
R/W acquisitions. See Section 8 and Appendix D for the right‐of‐way impact summary and exhibit.
(7) Aesthetics: Alternative 4A will have somewhat low impacts to aesthetics as compared to other
project alternatives. The main impacts to aesthetics include the extensive retaining wall work that is
anticipated for this work. Overall the impacts to Aesthetics are lower than most other alternatives.
(8) Design Exceptions: A design standards check and Design Standards Risk Assessment was not
fully performed for Alternative 4A, since the project consists only of reconstruction/improvements to
an existing roadway, along an existing local road corridor. It is anticipated that the project would
have various exceptions to design standards. The Design Standards Risk Assessment for this
alternative will be further addressed in the PA&ED phase.
Alternative 4B
Improve Scenic Drive from Cher‐Ae Lane; New Frontage Road
from Westhaven to Cher‐Ae Lane:
Improve Scenic Drive from Cher‐Ae Lane to Trinidad
Construct new frontage road from US 101 in the
Community of Westhaven to Cher‐Ae Lane
Alternative 4B includes widening of Scenic Drive from Cher‐Ae Lane to Main Street in the City of
Trinidad, and construction of a new frontage road from US 101 in the Community of Westhaven to Cher‐
Ae Lane.
Alternative 4B improvements include:
Widening and/or reconstruction of Scenic Drive from Cher‐Ae Lane to Trinidad, to provide 4
foot minimum shoulders and sidewalk on one side
Construction of a new frontage road from US 101 in the Community of Westhaven to Cher‐Ae
Lane
R1721PSR003.docx
30
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
(1) Purpose and Need: Alternative 4B does not meet the purpose and need for this project.
Improvements to Scenic Drive from Cher‐Ae Lane to Main Street, and a new frontage road from the
community of Westhaven to Cher‐Ae Lane will improve the safety and reliability of the access to the
Trinidad Rancheria, but will not sufficiently address any of the requirements of the purpose and need
for the study. This alternative will not reconnect tribal lands, and will not accommodate the planned
future development in the area.
(2) Traffic Operations: Alternative 4B includes improvements to Scenic Drive, from Cher‐Ae Lane
to Main Street in the City of Trinidad, and a new frontage road from the community of Westhaven to
Cher‐Ae Lane. These improvements will have some effect on the overall traffic operations within the
study area. However, upon full build‐out of the Trinidad Rancheria Master Plan, conditions for the
Trinidad‐Main Street interchange will continue to operate at unacceptable levels of service, as
outlined in the Traffic Operations section above.
(3) Increased Safety: Alternative 4B will improve Scenic Drive from Cher‐Ae Lane to Main Street,
and provide a new frontage road to the community of Westhaven to the south. This will increase the
safety of access routes to the Trinidad Rancheria and surrounding community, but overall increases
in safety for this alternative are still significantly lower than most other alternatives.
(4) Project Costs: Total Capital Outlay project costs for Alternative 4B are estimated at $31.7 million,
which is significantly higher than what would be expected for projects of similar size and nature, and
is in the mid‐range of estimated costs for all alternatives. Costs estimated for this alternative are
increased significantly due to some extensive grading and retaining wall work along Scenic Drive
north of Cher‐Ae Lane, as well as significant grading, retaining walls, clearing and grubbing work,
and R/W acquisition within the area proposed along US 101 for this alternative. See Appendix E for
the preliminary project cost estimate worksheet.
(5) Environmental Impacts: It is anticipated that Alternative 4B will have a high amount of
environmental impacts, since it includes improvements to a completely undeveloped area adjacent to
US 101, between the community of Westhaven and the Trinidad Rancheria. It is likely that impacts
would include existing environmental resources within the project limit. Some existing drainage
features, including culverts and drainage ditches/streams will need modification or mitigation. There
are multiple existing drainage ways along this stretch that could require up to 50‐60 foot fills, along
with excavation of similar amounts in multiple areas. In addition, there is a high potential to
discover cultural resources in the vicinity of this proposed frontage road. This alternative is in the
very high range of environmental impacts as compared to other alternatives, since the footprint
includes construction of a new roadway within a completely undeveloped area adjacent to US 101,
south of Cher‐Ae Lane.
(6) Right‐of‐Way Impacts: Right‐of‐Way impacts for Alternative 4B will be in the high range as
compared to other alternatives included in this study. R/W impacts for Scenic Drive from Cher‐Ae
Lane to Main Street will be similar to other alternatives, and will include small partial acquisitions.
R/W impacts for the new frontage road along US 101 will be significant, and would likely require
multiple acquisitions of full parcels within this corridor, along with multiple partial acquisitions of
parcels adjacent to US 101. It is estimated that 10‐15 parcels may be affected adjacent to the Scenic
Drive corridor, with impacts mostly including sliver R/W acquisitions. It is estimated that 15‐20
parcels may be affected with the proposed frontage road from Westhaven to Cher‐Ae Lane, with
many of the acquisitions requiring full parcel takes. See Section 8 and Appendix D for the right‐of‐
way impact summary and exhibit.
R1721PSR003.docx
31
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
(7) Aesthetics: Alternative 4B will have medium impacts to aesthetics as compared to other project
alternatives. The main impact to aesthetics will be the new frontage road that parallels US 101 from
Westhaven to Cher‐Ae Lane, to include removal of significant amounts of trees and vegetation, as
well as significant grading and slopes along this segment of new roadway.
(8) Design Exceptions: A design standards check and Design Standards Risk Assessment was not
fully performed for Alternative 4B, since the project consists of reconstruction/improvements to an
existing roadway, and a new local road facility adjacent to US 101, south of Cher‐Ae Lane. It is
anticipated that the project would have various exceptions to design standards. The Design
Standards Risk Assessment for this alternative will be further addressed in the PA&ED phase.
Alternative 5A
Improvements to Main Street with Signalized Intersections and
Construction of a new Cher‐Ae Lane Overcrossing:
Four traditional signalized intersections
Replacement of the Trinidad‐Main Street Interchange
Widen Main Street from Scenic Drive to Westhaven Drive
Widen Scenic Drive from Cher‐Ae Lane to Main Street
Construct new overcrossing at Cher‐Ae Lane
Alternative 5A is a combination of Alternative 1A and 2, and includes Improvements to Main Street with
signalized intersections, replacement of the Trinidad‐Main Street Interchange (PM 100.7), widening of
Main Street from Scenic Drive to Westhaven Drive, widening of Scenic Drive from Cher‐Ae Lane to Main
Street in the City of Trinidad (PM 100.0 – 101.1), and construction of a new overcrossing structure at
Cher‐Ae Lane (PM 100.0), with local road connections to Scenic Drive and Westhaven Drive.
See previous Figures 2 and 4.
Alternative 5A improvements include:
Construction of traffic signals at each of the four intersections at this location
Reconstruction and widening of Main Street to accommodate future traffic demands
Reconstruction of the Main Street profile to meet current design standards
Construction of a new US 101 undercrossing structure to accommodate the widened Main Street
Reconstruction of the US 101 on and off‐ramps to accommodate future traffic demands
Reconstruction of US 101 mainline to provide a minimum 12 foot wide median and 10 foot
shoulders
Reconstruction of US 101 mainline profile to meet current decision sight distance standards
Widening and/or reconstruction of Scenic Drive to provide 4 foot minimum shoulders and
sidewalk on one side
Construction of a new overcrossing structure at PM 100.0
Reconstruction of Cher‐Ae Lane from Scenic Drive into the Rancheria
Construction of the Cher‐Ae Lane Extension to Westhaven Drive
Widening of Westhaven Drive from the Community of Westhaven to the City of Trinidad
Reconstruction of adjacent roadways to tie in to existing improvements
(1) Purpose and Need: Alternative 5A appears to meet the purpose and need for this project.
Improvements to the Trinidad‐Main Street Interchange, along with a new overcrossing structure at
R1721PSR003.docx
32
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
Cher‐Ae Lane, would accommodate the planned future development in the area, would provide for a
2nd safe and sustainable access to the Trinidad Rancheria, and would also reconnect tribal lands
across US 101.
(2) Traffic Operations: Alternative 5A includes improvements to the US 101/Trinidad‐Main Street
interchange, as well as Scenic Drive, and a new overcrossing structure at Cher‐Ae Lane, which would
result in improved traffic operations, and would provide for acceptable levels of service for the 3
intersections that would otherwise perform at unacceptable levels of service.
(3) Increased Safety: Alternative 5A will widen the median and shoulders on US 101, and would
chiefly construct the proposed improvements to current standards (See Section 8). Scenic Drive,
between Cher‐Ae Lane and Main Street, will also be improved, as will Westhaven Drive from the
community of Westhaven to Trinidad. These improvements will likely result in increased public
safety.
(4) Project Costs: Total Capital Outlay project costs for Alternative 5A are estimated at $48.0 million,
which is somewhat higher than expected for projects of similar size and nature, and has the highest
estimated cost of all alternatives. The additional project costs can be attributed to replacement of the
Trinidad‐Main Street Interchange (PM 100.7), extensive grading work and significant retaining wall
work. See Appendix E for the preliminary project cost estimate worksheet.
(5) Environmental Impacts: It is anticipated that Alternative 5A will have some minor impacts to
existing environmental facilities within the Trinidad‐Main Street Interchange area, along with more
significant impacts to the areas adjacent to US 101 at Cher‐Ae Lane. Existing drainage features,
including culverts and drainage ditches/streams, will need modification or mitigation. The area east
of US 101 near the Trinidad Rancheria is mostly undeveloped, and has an increased potential of
various environmental impacts. In addition, there is potential to discover cultural resources in the
vicinity of the project. This alternative is in the high range of environmental impacts as compared to
other alternatives.
(6) Right‐of‐Way Impacts: Due to the extensive grading and vertical profile changes in the Trinidad‐
Main Street interchange area, along with a new overcrossing structure at Cher‐Ae Lane, it is
anticipated that significant right‐of‐way acquisition will be required for Alternative 5A. Right‐of‐way
acquisition is expected to be limited to partial takes in areas where roads are widened, or extensive
grading must be done to allow for adequate sight distance or to meet other standards. Much of the
R/W that will be required for this project in the Cher‐Ae Lane area is land already owned by the
Trinidad Rancheria, which will significantly decrease the overall R/W impacts. It is estimated that 7‐
10 parcels may be affected adjacent to the US 101/Trinidad‐Main Street interchange, 10‐12 parcels
may be affected adjacent to US 101 in the Cher‐Ae Lane area for the overcrossing, and 10‐15 parcels
could be affected along Scenic Drive between Cher‐Ae Lane and Main Street.
(7) Aesthetics: Alternative 5A will significantly alter the existing rural and unique character of the
Trinidad‐Main Street interchange. The drastic change is likely to be considered incompatible with
the rural fishing village character of the City of Trinidad, and the City’s Draft General Plan.
Alternative 5A will also alter the US 101 corridor with construction of a new overcrossing structure.
This impact will also be significant for the area, but will be similar to existing interchanges and
overcrossing structures along the US 101 corridor.
(8) Design Exceptions: The preliminary design and design standards were checked using the DIB 78
Design Checklist and a draft Design Standards Risk Assessment was completed for Alternative 5A,
with various exceptions to design standards anticipated. The anticipated exceptions to design
R1721PSR003.docx
33
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
standards for Alternative 5A will be identical to those presented for Alternatives 1A and 2. The
Design Standards Risk Assessment for this alternative will be further addressed in the PA&ED phase.
Alternative 5B
Improvements to Main Street with Roundabouts and
Construction of a new Cher‐Ae Lane Overcrossing:
Construct two large scale modern roundabouts
Reconstruct on and off‐ramps
Widen Scenic Drive from Cher‐Ae Lane to Main Street
Construct new Cher‐Ae Lane Overcrossing
Alternative 5B is a combination of Alternative 1B and 2, and includes improvements to Main Street with
modern roundabouts, including reconstruction of the on and off‐ramps, reconstruction of Main Street,
widening of Scenic Drive from Cher‐Ae Lane to Main Street in the City of Trinidad (PM 100.0 – 101.1),
and construction of a new overcrossing structure at Cher‐Ae Lane (PM 100.0), with local road connections
to Scenic Drive and Westhaven Drive.
See previous Figures 3 and 4.
Alternative 5B improvements include:
Construction of two large modern roundabouts at the interchange
Reconstruction of Main Street to accommodate future traffic demands
Reconstruction of the US 101 on and off‐ramps
Widening and/or reconstruction of Scenic Drive to provide 4 foot minimum shoulders and
sidewalk on one side
Construction of a new overcrossing structure at PM 100.0
Reconstruction of Cher‐Ae Lane from Scenic Drive into the Rancheria
Construction of the Cher‐Ae Lane Extension to Westhaven Drive
Widening of Westhaven Drive from the Community of Westhaven to the City of Trinidad
Reconstruction of adjacent roadways to tie in to existing improvements
(1) Purpose and Need: Alternative 5B appears to meet the purpose and need for this project.
Improvements to the Trinidad‐Main Street Interchange, along with a new overcrossing structure at
Cher‐Ae Lane, would accommodate the planned future development in the area, would provide for a
2nd safe and sustainable access to the Trinidad Rancheria, and would also reconnect tribal lands
across US 101.
(2) Traffic Operations: Alternative 5B includes improvements to the US 101/Trinidad‐Main Street
interchange, as well as Scenic Drive, and a new overcrossing structure at Cher‐Ae Lane, which would
result in improved traffic operations, and would provide for acceptable levels of service for the 3
intersections that would otherwise perform at unacceptable levels of service.
(3) Increased Safety: Alternative 5B will widen the shoulders on US 101 within the immediate
project area, and would chiefly construct the proposed improvements to current standards (See
Section 8). Scenic Drive, between Cher‐Ae Lane and Main Street, will also be improved, as will
Westhaven Drive from the community of Westhaven to Trinidad. These improvements will likely
result in increased public safety.
R1721PSR003.docx
34
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
(4) Project Costs: Total Capital Outlay project costs for Alternative 5B are estimated at $31.5 million,
which is similar to what would be expected for projects of similar size and nature, and is in the mid‐
range of estimated costs for all alternatives. The cost estimate provided for this alternative assumes
significantly less reconstruction of US 101 adjacent to the Trinidad‐Main Street interchange, as well as
allowing the existing undercrossing structure to remain in place. The median is not widened with
this alternative, since the existing structure would remain in place, and there would not be adequate
decision sight distance (DSD) from US 101 to the northbound off‐ramp to Main Street without
reconstruction of US 101 similar to alternative 5A. To replace the existing structure and reconstruct
US 101 to meet the DSD standard, estimated costs for Alternative 5B would be similar to Alternative
5A, around $47.8 million. See Appendix E for the preliminary project cost estimate worksheet.
(5) Environmental Impacts: It is anticipated that Alternative 5B will have some minor impacts to
existing environmental facilities within the Trinidad‐Main Street Interchange area, along with more
significant impacts to the areas adjacent to US 101 at Cher‐Ae Lane. Existing drainage features,
including culverts and drainage ditches/streams, will need modification or mitigation. The area east
of US 101 near the Trinidad Rancheria is mostly undeveloped, and has an increased potential of
various environmental impacts. In addition, there is potential to discover cultural resources in the
vicinity of the project. This alternative is in the high range of environmental impacts as compared to
other alternatives.
(6) Right‐of‐Way Impacts: Due to the extensive grading and vertical profile changes in the Trinidad‐
Main Street interchange area, along with a new overcrossing structure at Cher‐Ae Lane, it is
anticipated that significant right‐of‐way acquisition will be required for Alternative 5B. The
extensive reconstruction in the Trinidad‐Main Street interchange area would likely require some full
R/W acquisition for adjacent parcels east of US 101, and northeast of Westhaven Drive, similar to
Alternative 1B. Much of the R/W that will be required for this project in the Cher‐Ae Lane area is
land already owned by the Trinidad Rancheria, which will significantly decrease the overall R/W
impacts. It is estimated that 7‐10 parcels may be affected adjacent to the US 101/Trinidad‐Main Street
interchange, 10‐12 parcels may be affected adjacent to US 101 in the Cher‐Ae Lane area for the
overcrossing, and 10‐15 parcels could be affected along Scenic Drive between Cher‐Ae Lane and
Scenic Drive. See Section 8 and Appendix D for the right‐of‐way impact summary and exhibit.
(7) Aesthetics: Alternative 5B will significantly alter the existing rural and unique character of the
Trinidad‐Main Street interchange. The drastic change is likely to be considered incompatible with
the rural fishing village character of the City of Trinidad, and the City’s Draft General Plan.
Alternative 5B will also alter the US 101 corridor with construction of a new overcrossing structure.
This impact will also be significant for the area, but will be similar to existing interchanges and
overcrossing structures along the US 101 corridor.
(8) Design Exceptions: The preliminary design and design standards were checked using the DIB 78
Design Checklist and a draft Design Standards Risk Assessment was completed for Alternative 5B,
with various exceptions to design standards anticipated. The anticipated exceptions to design
standards for Alternative 5B will be identical to those presented for Alternatives 1B and 2. The
Design Standards Risk Assessment for this alternative will be further addressed in the PA&ED phase.
R1721PSR003.docx
35
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
New US 101/Baker Ranch Road Interchange (PM 99.6):
Alternative 6
Construct new US 101/Baker Ranch Road Interchange
Local road connection to Scenic Drive and Westhaven Drive
Widen Scenic Drive from Cher‐Ae Lane to Main Street
Widen Westhaven Drive from Westhaven to Trinidad
New frontage road from Baker Ranch Road to Cher‐Ae
Lane
Alternative 6 includes construction of a new Type L‐1 Compact Diamond interchange at Baker Ranch
Road (PM 99.6), with both northbound and southbound ramp connections, local road connections to
Scenic Drive and Westhaven Drive, widening of Scenic Drive from Cher‐Ae Lane to Main Street in the
City of Trinidad, widening of Westhaven Drive in the Community of Westhaven to Main Street in the
City of Trinidad (PM 98.1 – 100.7), and construction of a new frontage road from Baker Ranch Road to
Cher‐Ae Lane.
See Figure 8.
Figure 8 ‐ Alternative 6 Schematic Exhibit
Alternative 6 improvements include:
Construction of a new Type L‐1 Compact Diamond interchange at PM 99.6
Construction of all northbound and southbound ramp connections
Reconstruction of Baker Ranch Road east of US 101
Construction of Baker Ranch Road from US 101 to Westhaven Drive
Construction of a new frontage road from Baker Ranch Road to Cher‐Ae Lane
Widening and/or reconstruction of Scenic Drive to provide 4 foot minimum shoulders and
sidewalk on one side
Widening of Westhaven Drive from the Community of Westhaven to the City of Trinidad
(1) Purpose and Need: Alternative 6 does not meet the purpose and need for this project. A new
interchange at Baker Ranch Road, with connections to US 101, and public road connections to Scenic
R1721PSR003.docx
36
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
Drive and Westhaven Drive would provide only 2 of 3 of the requirements of the purpose and need
outlined in this study. The new interchange would provide for a 2nd safe and sustainable access to
and from US 101, for all modes of transportation, to the Trinidad Rancheria and the surrounding
communities, and it would accommodate the planned future development in the area. This new
interchange at Baker Ranch Road would not reconnect tribal lands across US 101 in the Trinidad
Rancheria area, and therefore does not meet the purpose and need.
(2) Traffic Operations: Alternative 6 includes construction of a new interchange at Baker Ranch
Road (PM 99.6), with an overcrossing structure over US 101, public road connections to Scenic Drive
and Westhaven Drive, frontage road between Baker Ranch Road and Cher‐Ae Lane, as well as
improvements to Scenic Drive from Baker Ranch Road to Trinidad, and for the length of Westhaven
Drive from the community of Westhaven to Trinidad. These improvements would result in improved
traffic operations within the study area. If constructed, and upon full build‐out of the Trinidad
Rancheria Master Plan, it is possible that this alternative may improve traffic operations enough to
provide acceptable levels of service for the entire study area. Additional analysis may be required to
fully determine if this alternative would provide for acceptable LOS for the study area.
(3) Increased Safety: Alternative 6 will widen the median and shoulders on US 101, and would
chiefly construct the proposed improvements to current standards. Scenic Drive, between Baker
Ranch Road and Main Street, will also be improved, along with Westhaven Drive from the
community of Westhaven to Trinidad. A new frontage road would be provided between Baker
Ranch Road and Cher‐Ae Lane, thereby creating a 2nd access point to the Trinidad Rancheria. These
improvements will likely result in increased public safety within the study area.
(4) Project Costs: Total Capital Outlay project costs for Alternative 6 are estimated at $39.6 million,
which is significantly higher than what would be expected for an interchange project of similar size
and nature, and is in the high‐range of estimated costs for all alternatives. Costs estimated for this
alternative are increased due to areas that will require extensive grading, retaining wall work,
clearing and grubbing work, R/W acquisition within the proposed interchange area, and frontage
road between Baker Ranch Road and Cher‐Ae Lane. See Appendix E for the preliminary project cost
estimate worksheet.
(5) Environmental Impacts: It is anticipated that Alternative 6 will have the highest amount of
environmental impacts of all the alternatives studied, since it includes construction of a new
roadway, construction of a full new interchange, as well as construction of a new frontage road
adjacent to US 101. It is very likely that impacts would include existing environmental resources
within the project limit. Some existing drainage features, including culverts and drainage
ditches/streams will need modification or mitigation. There are multiple existing drainage ways
along this stretch that could require up to 50‐60 foot fills, along with excavation of similar amounts to
provide for an acceptable vertical profile of the new Baker Ranch Road segment. The area that
includes the new interchange and on and off‐ramps is also mostly undeveloped, and will likely have
impacts to existing environmentally sensitive areas. In addition, there is potential to discover cultural
resources in the vicinity of the project. This alternative is anticipated to have the most environmental
impacts of all alternatives analyzed for this study.
(6) Right‐of‐Way Impacts: Right‐of‐Way impacts for this alternative will also likely be the highest of
all alternatives, since the project will construct a new roadway across US 101, as well as new ramp
connections to US 101, thereby requiring acquisition of R/W for the full width of the roadway, ramps,
and associated improvements, including grading. Much of this area includes very steep terrain,
which will likely require additional R/W acquisition to provide for grading. Additional R/W will also
likely be required along the new frontage road from Baker Ranch Road to Cher‐Ae Lane. It is
R1721PSR003.docx
37
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
estimated that 25‐35 parcels may be affected in the Baker Ranch Road interchange area, as well as 15‐
20 parcels along Scenic Drive. See Section 8 and Appendix D for the right‐of‐way impact summary
and exhibit.
(7) Aesthetics: Alternative 6 will alter the US 101 corridor with construction of a new interchange,
similar to Alternatives 3A and 3B. While this impact will be significant for the area, a new
interchange will be similar to existing interchanges and overcrossing structures along the US 101
corridor.
(8) Design Exceptions: A design standards check was performed for Alternative 6, at a lesser degree
than Alternatives 1A, 1B, 2, 3A, 3B, 5A, and 5B. It is anticipated that various exceptions to design
standards would be required. One of the concerns with regards to design standards would be the
vertical design standards. A preliminary vertical profile for the Baker Ranch Road connection from
Scenic Drive to Westhaven Drive includes grades near 15%, while holding grades within the
interchange area at 4% +/‐ to meet interchange standards. The Design Standards Risk Assessment for
this alternative will be further addressed in the PA&ED phase.
Alternative 7
New Cher‐Ae Lane Overcrossing (PM 100.0); New Frontage
Road from Westhaven to Cher‐Ae Lane:
Construct new Cher‐Ae Lane Overcrossing
Local road connection to Scenic Drive and Westhaven Drive
Improve Scenic Drive from Cher‐Ae Lane to Trinidad
Widen Westhaven Drive from Westhaven to Trinidad
Construct new frontage road from US 101 in the
Community of Westhaven to Cher‐Ae Lane
Alternative 7 is a combination of Alternative 2 and Alternative 4B, and includes construction of a new
overcrossing structure at Cher‐Ae Lane (PM 100.0), with local road connections to Scenic Drive and
Westhaven Drive, widening of Scenic Drive from Cher‐Ae Lane to Main Street in the City of Trinidad,
widening of Westhaven Drive in the Community of Westhaven to Main Street in the City of Trinidad,
and construction of a new frontage road from Westhaven to Cher‐Ae Lane.
See previous Figure 4.
Alternative 7 improvements include:
Construction of a new overcrossing structure at PM 100.0
Reconstruction of Cher‐Ae Lane from Scenic Drive into the Rancheria
Construction of the Cher‐Ae Lane Extension to Westhaven Drive
Widening and/or reconstruction of Scenic Drive to provide 4 foot minimum shoulders and
sidewalk on one side
Widening of Westhaven Drive from the Community of Westhaven to the City of Trinidad
Construction of a new frontage road from Westhaven to Cher‐Ae Lane
(1) Purpose and Need: Alternative 7 does not meet the purpose and need for this project. A new
overcrossing structure without a connection to US 101, along with a new frontage road from
R1721PSR003.docx
38
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
Westhaven to Cher‐Ae Lane would provide for 2 of the 3 items of the purpose and need. The new
overcrossing and frontage road would provide for a 2nd safe and sustainable access to the Trinidad
Rancheria, and would also reconnect tribal lands across US 101. But these improvements will not
accommodate the planned future development in the area, and thus, does not meet the purpose and
need.
(2) Traffic Operations: Alternative 7 includes construction of a new overcrossing structure over US
101 at Cher‐Ae Lane, a new frontage road from Westhaven to Cher‐Ae Lane, as well as
improvements to Scenic Drive and Westhaven Drive, that would result in slightly improved traffic
operations. However, without any improvements to any of the interchange areas, and without a
direct connection to US 101, conditions for the Trinidad‐Main Street interchange will remain at
unacceptable levels of service, as outlined in the Traffic Operations section above.
(3) Increased Safety: Alternative 7 will not provide any improvements to US 101, but will provide
improvements to Scenic Drive and Westhaven Drive, and provide a 2nd safe access between
Westhaven and Cher‐Ae Lane. Therefore, increased safety would be expected on Scenic Drive, from
Cher‐Ae Lane to Trinidad, along the length of Westhaven Drive, and along the new frontage road.
However, overall increased safety for the project study area would be minimal.
(4) Project Costs: Total Capital Outlay project costs for Alternative 7 are estimated at $39.5 million,
which is significantly higher than what would be expected for a project of similar size and nature,
and is in the high‐range of estimated costs for all alternatives. Similar to estimated costs for
Alternative 4B, estimated costs for this alternative include amounts for significant grading, retaining
walls, clearing and grubbing work, and R/W acquisition within the area proposed along US 101
between Westhaven and the Trinidad Rancheria for the new frontage road. See Appendix E for the
preliminary project cost estimate worksheet.
(5) Environmental Impacts: It is anticipated that Alternative 7 will have similar environmental
impacts to combining Alternatives 2 and 4B. Environmental impacts will be very high, and in the
high range for all of the alternatives analyzed for this study. For additional environmental discussion
on this alternative, see Alternatives 2 and 4B above.
(6) Right‐of‐Way Impacts: It is anticipated that Alternative 7 will have similar R/W impacts to
combining Alternatives 2 and 4B. R/W impacts will be somewhat high, and in the high range for all
of the alternatives analyzed for this study. For additional R/W impact discussion on this alternative,
see Alternatives 2 and 4B above. See Section 8 and Appendix D for the right‐of‐way impact
summary and exhibit.
(7) Aesthetics: Alternative 7 will alter the US 101 corridor with construction of a new overcrossing at
Cher‐Ae Lane. While this impact will be significant for the area, a new interchange will be similar to
existing interchanges and overcrossing structures along the US 101 corridor. Similar to Alternative
4B, the new frontage road will have significant impacts on aesthetics along this corridor, to include
removal of significant amounts of trees and vegetation, as well as significant grading and slopes
along this segment of new roadway.
(8) Design Exceptions: A design standards check and Design Standards Risk Assessment were not
performed specifically for Alternative 7. Design exception discussions for this alternative are
included in the Alternative 2 and 4B sections. The Design Standards Risk Assessment for this
alternative will be further addressed in the PA&ED phase.
R1721PSR003.docx
39
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
New US 101/1.0 Mile Spacing Interchange (PM 99.7):
Alternative 8
Construct new US 101/1.0 Mile Spacing Interchange
Local road connection to Cher‐Ae Lane and Westhaven
Drive
Widen Scenic Drive from Cher‐Ae Lane to Main Street
Widen Westhaven Drive from Westhaven to Trinidad
Alternative 8 includes construction of a new Type L‐1 Compact Diamond interchange approximately 1
mile south of the US 101/Trinidad‐Main Street Interchange (PM 100.7), with both northbound and
southbound ramp connections, local road connections to Cher‐Ae Lane and Westhaven Drive, widening
of Scenic Drive from Cher‐Ae Lane to Main Street in the City of Trinidad, and widening of Westhaven
Drive in the Community of Westhaven to Main Street in the City of Trinidad (PM 98.1 – 100.7).
See Figure 9.
Figure 9 ‐ Alternative 8 Schematic Exhibit
Alternative 8 improvements include:
Construction of a new Type L‐1 Compact Diamond interchange at PM 99.7
Construction of all northbound and southbound ramp connections
Construction of a new road from Cher‐Ae Lane to Westhaven Drive
Widening and/or reconstruction of Scenic Drive to provide 4 foot minimum shoulders and
sidewalk on one side
Widening of Westhaven Drive from the Community of Westhaven to the City of Trinidad
(1) Purpose and Need: Alternative 8 appears to meet the purpose and need for this project. A new
interchange 1 mile south of the existing US 101/Trinidad‐Main Street Interchange, with connections to
US 101, and public road connections to Cher‐Ae Lane and Westhaven Drive would provide for all of
the purpose and need requirements outlined in this study. The new interchange would provide for a
2nd safe and sustainable access to and from US 101, for all modes of transportation, to the Trinidad
R1721PSR003.docx
40
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
Rancheria and the surrounding communities, accommodate the planned future development in the
area, and would also reconnect tribal lands across US 101.
(2) Traffic Operations: Alternative 8 includes construction of a new US 101 interchange (PM 99.7) at
approximately 1.0 mile south of the existing US 101/Trinidad‐Main Street Interchange (PM 100.7),
with an overcrossing structure over US 101, public road connections to Cher‐Ae Lane and Westhaven
Drive, as well as improvements to Scenic Drive from Cher‐Ae Lane to Trinidad, and for the length of
Westhaven Drive from the community of Westhaven to Trinidad. These improvements would result
in improved traffic operations within the study area. If constructed, and upon full build‐out of the
Trinidad Rancheria Master Plan, it is projected that this alternative would improve traffic operations
enough to provide acceptable levels of service for the entire study area. Additional analysis may be
needed to fully determine if this alternative would provide for acceptable LOS for the entire study
area.
(3) Increased Safety: Alternative 8 will widen the median and shoulders on US 101, and would
chiefly construct the proposed improvements to current standards (See Section 8). Scenic Drive,
between Cher‐Ae Lane and Main Street, will also be improved, along with Westhaven Drive from the
community of Westhaven to Trinidad. This alternative would provide a new stable crossing location
for US 101, as well as easier access to US 101 from Cher‐Ae Lane along a more stabilized roadway.
These improvements will likely result in increased public safety within the study area.
(4) Project Costs: Total Capital Outlay project costs for Alternative 8 are estimated at $32.6 million,
which is slightly higher than what would be expected for projects of similar size and nature, and is in
the mid‐range of estimated costs for all alternatives. Costs estimated for this alternative are increased
due to areas that will require some extensive grading and retaining wall work due to existing
topography. This additional cost is typical of nearly all of the alternatives that were analyzed with
this study, due to the highly variable terrain within the entire study area. See Appendix E for the
preliminary project cost estimate worksheet.
(5) Environmental Impacts: It is anticipated that Alternative 8 will have somewhat high
environmental impacts, since it includes construction of a new roadway, and construction of a full
new interchange. It is likely that impacts would include existing environmental resources within the
project limit. Some existing drainage features, including culverts and drainage ditches/streams will
need modification or mitigation. The areas both east and west of US 101 are mostly undeveloped,
and have an increased potential of various environmental impacts. The area that includes the new
interchange and on and off‐ramps is also mostly undeveloped, and will likely have impacts to
existing environmentally sensitive areas. In addition, there is potential to discover cultural resources
in the vicinity of the project. This alternative is in the high range of environmental impacts as
compared to other alternatives, since the footprint includes a road connection across US 101, along
with full ramp connections to US 101, and a longer roadway extension to Cher‐Ae Lane.
(6) Right‐of‐Way Impacts: Right‐of‐Way impacts for this alternative will also be somewhat high,
since the project will construct a new roadway across US 101, as well as new ramp connections to US
101, and a lengthy extension of new roadway connecting to Cher‐Ae Lane. R/W acquisition would be
required for the full roadway width and associated improvements, including grading and retaining
walls. Some of this area includes very steep terrain, which will likely require additional R/W
acquisition to provide for extensive grading. The roadway extension to Cher‐Ae Lane skirts privately
owned and Rancheria residential neighborhoods. It is estimated that 10‐15 parcels may be affected in
the interchange area, and another 10‐15 parcels may be affected along Scenic Drive; including impact
to a Rancheria residence and close proximity to two privately owned residences. See Section 8 and
Appendix D for the right‐of‐way impact summary and exhibit.
R1721PSR003.docx
41
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
(7) Aesthetics: Alternative 8 will alter the US 101 corridor with construction of a new interchange,
similar to Alternatives 3A and 3B. While this impact will be significant for the area, a new
interchange will be similar to existing interchanges and overcrossing structures along the US 101
corridor.
(8) Design Exceptions: A design standards check and Design Standards Risk Assessment were not
performed specifically for Alternative 8. Geometric features influencing design exception
requirements include vertical grades, minimum curve radii for the new road, cut slopes affecting
sight distance requirements, and interchange configuration. The Design Standards Risk Assessment
for this alternative will be further addressed in the PA&ED phase.
8. RIGHT OF WAY
All alternatives will require some amount of right of way acquisition to accommodate new or widened
roadways, new alignments and other improvements. Anticipated right of way acquisition for all
alternatives is summarized below. See Attachment D for right of way impact exhibits.
TABLE 10: RIGHT OF WAY ACQUISITION SUMMARY (ALTERNATIVE 1A)
Location (Number of Parcels)
General Description
Acres
West of US 101 at Trinidad‐Main I/C (3)
Commercial
0.4
East of US 101 at the Trinidad‐Main I/C (4)
Residential and Vacant
0.4
Scenic Drive north of Cher‐Ae Lane (15)
Residential and Vacant
1.7
TABLE 11: RIGHT OF WAY ACQUISITION SUMMARY (ALTERNATIVE 1B)
Location (Number of Parcels)
General Description
Acres
West of US 101 at Trinidad‐Main I/C (3)
Commercial
0.3
East of US 101 at the Trinidad‐Main I/C (4)
Residential and Vacant
2.7
Scenic Drive north of Cher‐Ae Lane (15)
Residential and Vacant
1.7
TABLE 12: RIGHT OF WAY ACQUISITION SUMMARY (ALTERNATIVE 2)
Location (Number of Parcels)
General Description
Acres
West of US 101 at Cher‐Ae Lane (6)
Residential and Tribal Government
2.3
East of US 101 at Cher‐Ae Lane (3)
Residential
2.3
Scenic Drive north of Cher‐Ae Lane (15)
Residential and Vacant
1.7
TABLE 13: RIGHT OF WAY ACQUISITION SUMMARY (ALTERNATIVE 3A)
Location (Number of Parcels)
General Description
Acres
West of US 101 at Cher‐Ae Lane (7)
Residential and Tribal Government
3.7
East of US 101 at Cher‐Ae Lane (10)
Residential
4.4
Scenic Drive north of Cher‐Ae Lane (15)
Residential and Vacant
1.7
R1721PSR003.docx
42
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
TABLE 14: RIGHT OF WAY ACQUISITION SUMMARY (ALTERNATIVE 3B)
Location (Number of Parcels)
General Description
Acres
Same as Alternative 3A
TABLE 15: RIGHT OF WAY ACQUISITION SUMMARY (ALTERNATIVE 4A)
Location (Number of Parcels)
General Description
Acres
Scenic Drive south of Cher‐Ae Lane (26)
Residential and Vacant
4.0
Scenic Drive north of Cher‐Ae Lane (15)
Residential and Vacant
1.7
TABLE 16: RIGHT OF WAY ACQUISITION SUMMARY (ALTERNATIVE 4B)
Location (Number of Parcels)
General Description
Acres
New Frontage Road south of Cher‐Ae Lane (18)
Residential
11.2
Scenic Drive north of Cher‐Ae Lane (15)
Residential and Vacant
1.7
TABLE 17: RIGHT OF WAY ACQUISITION SUMMARY (ALTERNATIVE 5A)
Location (Number of Parcels)
General Description
Acres
West of US 101 at Trinidad‐Main I/C (3)
Commercial
0.4
East of US 101 at the Trinidad‐Main I/C (4)
Residential and Vacant
0.4
Scenic Drive north of Cher‐Ae Lane (15)
Residential and Vacant
1.7
West of US 101 at Cher‐Ae Lane (6)
Residential and Tribal Government
2.3
East of US 101 at Cher‐Ae Lane (3)
Residential
2.3
TABLE 18: RIGHT OF WAY ACQUISITION SUMMARY (ALTERNATIVE 5B)
Location (Number of Parcels)
General Description
Acres
West of US 101 at Trinidad‐Main I/C (3)
Commercial
0.3
East of US 101 at the Trinidad‐Main I/C (4)
Residential and Vacant
2.7
Scenic Drive north of Cher‐Ae Lane (15)
Residential and Vacant
1.7
West of US 101 at Cher‐Ae Lane (6)
Residential and Tribal Government
2.3
East of US 101 at Cher‐Ae Lane (3)
Residential
2.3
TABLE 19: RIGHT OF WAY ACQUISITION SUMMARY (ALTERNATIVE 6)
Location (Number of Parcels)
General Description
Acres
West of US 101 at Baker Ranch Road (5)
Residential and Vacant
7.8
East of US 101 at Baker Ranch Road (9)
Residential and Vacant
9.2
Scenic Drive (19)
Residential and Vacant
2.8
R1721PSR003.docx
43
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
New Frontage Road between Baker Ranch
Road and Cher‐Ae Lane (15)
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
Residential and Vacant
7.5
TABLE 20: RIGHT OF WAY ACQUISITION SUMMARY (ALTERNATIVE 7)
Location (Number of Parcels)
General Description
Acres
West of US 101 at Cher‐Ae Lane (6)
Residential and Tribal Government
2.3
East of US 101 at Cher‐Ae Lane (3)
Residential
2.3
Scenic Drive north of Cher‐Ae Lane (15)
Residential and Vacant
1.7
New Frontage Road south of Cher‐Ae Lane (18)
Residential
11.2
Scenic Drive north of Cher‐Ae Lane (15)
Residential and Vacant
1.7
TABLE 21: RIGHT OF WAY ACQUISITION SUMMARY (ALTERNATIVE 8)
Location (Number of Parcels)
General Description
Acres
West of US 101 (8)
Residential and Tribal Government
5.0
East of US 101 (10)
Residential
5.7
Scenic Drive (15)
Residential and Vacant
1.7
Utilities
The following utilities may be impacted in various degrees by the project:
City of Trinidad Water: Existing water facilities will be impacted and require relocation for
Alternatives 1A, 1B, 5A and 5B.
City of Trinidad Sewer: Existing sewer facilities will be impacted and require relocation for
Alternatives 1A, 1B, 5A and 5B.
AT&T: Existing AT&T facilities will be impacted for all alternatives.
PG&E: Existing PG&E facilities will be impacted for all alternatives.
Railroad
There are not any railroad impacts or involvement.
9. STAKEHOLDER INVOLVEMENT
The Trinidad Rancheria held a 5‐day Design Fair for the Highway 101 I/C in May 2009, and held another
5‐day Design Fair in November 2010 for the Comprehensive Community‐Based Plan. Tribal members,
tribal council, community members, and City, County and State Officials shared their visions for
improving access to the Rancheria and the surrounding community. A design team of professional
architects, landscape architects, engineers, and environmental planners were also in attendance to
facilitate the public presentations and interactions. Construction of a new US 101/Cher‐Ae Lane I/C was
identified by the Rancheria as a core necessity.
The Project Development Team (PDT) includes staff representatives as attendees from Caltrans, Trinidad
Rancheria, City of Trinidad, Humboldt County, and Humboldt Council of Governments. The PDT team
has been instrumental in developing the purpose and need statement for the project, as well as
R1721PSR003.docx
44
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
identifying all of the alternatives studied to date, and guiding discussions relating to design exceptions
and this PSR‐PDS.
10. ENVIRONMENTAL DETERMINATION/DOCUMENT
The CEQA environmental document for the project is anticipated to be an Environmental Impact Report
(EIR) and the NEPA environmental document is anticipated to be a Finding of No Significant Impact
(FONSI).
A Preliminary Environmental Analysis Report (PEAR) was submitted for approval on November 30,
2015, with comments subsequently received and addressed. An updated PEAR is included in this PSR‐
PDS as Attachment H. The updated PEAR identifies the need for the following technical studies in
support of the environmental documents:
Community Impact Assessment.
Visual Impact Assessment.
Archeological Survey Report.
Historical Resources Evaluation Report.
Historic Property Survey Report.
Geotechnical Investigation.
Air Quality Analysis.
Greenhouse Gas Modeling.
Biological Assessment.
11. FUNDING
Capital Outlay Project Estimate:
The proposed project is anticipated to include some or all of the following funding sources: State
Transportation Improvement Program (STIP), Tribal Transportation Program (TTP), Indian Reservation
Roads (IRR), Active Transportation Program (ATP), Highway Safety Improvement Program (HSIP), and
Transportation Investment Generating Economic Recovery (TIGER).
The estimated range for capital outlay project costs for the alternatives are shown below. At the PSR‐PDS
phase, the anticipated capital outlay funding by source has not been determined.
TABLE 22 CAPITAL OUTLAY PROJECT COST ESTIMATE2
Alternative
Alternative 1A
Alternative 1B
Alternative 2
Alternative 3A
Alternative 3B
Alternative 4A
Alternative 4B
Alternative 5A
Alternative 5B
Alternative 6
Alternative 7
Alternative 8
R1721PSR003.docx
R/W Capital
($1,000’s)
Construction Capital
($1,000’s)
Total
($1,000’s)
$800
$1,290
$1,6001
$2,4101
$2,4101
$1,520
$3,070
$1,8201
$2,3401
$3,880
$2,8301
$3,0161
$38,020
$18,775
$16,586
$29,882
$28,846
$20,501
$28,596
$46,194
$29,199
35,735
$36,629
$29,585
$38,820
$20,065
$18,2061
$32,2921
$31,2561
$22,021
$31,666
$48,0141
$31,5391
$39,615
$39,4591
$32,6011
45
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
Note:
(1) Includes the estimated value of R/W currently under ownership of the Trinidad Rancheria, which will provide a
reduction in overall right‐of‐way impacts and costs.
Capital Outlay Support Estimate:
Cooperative Agreement Number 01‐0365 addresses the PID phase only. A Cooperative Agreement will
be required for the PA&ED phase. The Trinidad Rancheria is the project Sponsor with Caltrans
providing Quality Assurance. At the PA&ED phase, each partner will be responsible for their own costs.
The capital outlay support estimate for programming PA&ED in the 2018 STIP for this project is $2.5
million. The estimated resources by WBS Code for environmental studies during the PA&ED phase are
included as an attachment to the PEAR, with an estimated total of 15,354 person‐hours. This total
includes 15% for Caltrans oversight. The environmental studies are estimated to be two‐thirds of the
total resources required during the PA&ED phase (or ~$1.7M), while the engineering studies are
estimated to be the remaining one‐third (or ~$0.8M).
Of the $2.5 million total estimated for the PA&ED phase, $775,000 will come from STIP funding through
the Humboldt County Association of Governments (HCAOG), while the remaining funds, $1,725,000,
would come from Tribal Transportation Funds and/or Economic Development Funds.
12. DELIVERY SCHEDULE
TABLE 23 ESTIMATED PROJECT DELIVERY SCHEDULE
Project Milestones
Program Project
Begin Environmental (PA&ED) Phase
Notice of Intent (NOI)
Circulate Draft Environmental Document (DED) Externally
End Environmental (PA&ED) Phase
Begin Project Design (PS&E) Phase
Begin Right of Way Phase
End Right of Way Phase (Right of Way Certification)
End Project Design (PS&E) Phase (Ready to List)
Begin Construction Phase (Contract Award)
End Construction Phase (Contract Acceptance)
M015
M020
M035
M120
M200
M377
M377
M410
M460
M495
M600
Scheduled Delivery Date
July 1, 2018
July 1, 2018
November 1, 2018
January 1, 2021
July 1, 2022
July 1, 2022
July 1, 2022
February 1, 2024
March 1, 2024
July 1, 2024
July 1, 2026
13. RISKS
A risk assessment was performed for the project, and a Risk Register created. A total of eight (8) risks
were identified on the Risk Register, and include: (1) Funding, (2) EIR / EA., (3) Design Exceptions, (4)
Right of Way, (5) External Project Sponsor, (6) Public Controversy/Opposition, (7) Local Coastal
Amendment Approval, and (8) Litigation. The risks identified range from low risk for External Project
Sponsor, to very high risk for Public Controversy/Opposition and environmental related risks.
See Attachment I for the Risk Register and Risk Register Certification Page.
R1721PSR003.docx
46
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
14. FHWA COORDINATION
NEPA approval is anticipated to be from either the Office of Federal Lands Highway (FHWA) or the
Bureau of Indian Affairs.
It is also anticipated that the FHWA Office of Federal Lands Highway may be a funding partner.
15. PROJECT REVIEWS
District Maintenance __________________________________
District Traffic Operations _____________________________
District Traffic Safety Bryan Thomas_____________________
Headquarters Project Delivery Coordinator ________________
District Safety Review ________________________________
Date _________________
Date _________________
Date 11/16/15__________
Date _________________
Date _________________
16. PROJECT PERSONNEL
Name
Jacque Hostler‐Carmesin
Leslie Sanders
Kim Floyd, PE
Lena Ashley, PE
Russ Wenham, PE
Brandon Tenney, PE
Douglas DeMallie, PE
Title
Trinidad Rancheria CEO
Transp. Manager (Trinidad Rancheria)
Project Manager (Caltrans)
Design Engineer (Caltrans)
Project Manager (Omni‐Means, Ltd.)
Project Engineer (Omni‐Means, Ltd.)
Project Planner (Omni‐Means, Ltd.)
17. ATTACHMENTS
A.
B.
C.
D.
E.
F.
G.
H.
I.
J.
Location Map (1)
Preliminary Alternative Schematic Exhibits (15)
Structures Cost Estimates Memorandum (3)
Right of Way Impact Exhibits (7)
Project Cost Estimate Worksheets (36)
Storm Water Data Report Signature Page (1)
Transportation Management Plan (6)
Preliminary Environmental Analysis Report (PEAR) (26)
Risk Register and Certification Form (2)
Geotechnical Screening Report (4)
R1721PSR003.docx
47
Phone Number
707‐677‐0211
707‐825‐2738
707‐441‐5739
707‐445‐6602
530‐242‐1700
530‐242‐1700
530‐242‐1700
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
ATTACHMENT A
PROJECT LOCATION MAP
R1721PSR003.docx
48
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
ATTACHMENT B
PRELIMINARY ALTERNATIVE SCHEMATIC
EXHIBITS
R1721PSR003.docx
49
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
ATTACHMENT C
STRUCTURES COST ESTIMATES MEMORANDUM
R1721PSR003.docx
50
Morrison Structures
1890 Park Marina Drive, Ste 104
Redding, CA 96001
Structure Memorandum
From: Bob Morrison, Jr., S.E., Morrison Structures, Redding, California
To:
Russ Wenham, P.E, Omni Means, Redding, California
Date: November 21, 2017
Re:
US 101/Trinidad Area Access Improvements
HUM-101, PM 98.4/100.7
01-48040K
General
The purpose of this memorandum is to provide structure information for the proposed interchange
Alternatives 1A, 2, 3A, 3B, 5A, 5B, 6, 7, & 8 for the Trinidad Area Access Improvements Study project.
The level of study we have conducted is a Project Study Report-Project Development Support (PSR-PDS)
Cost Estimate. The purpose of this study is to determine preliminary scope, feasibility, rough cost range,
and a list of potential project risks for the proposed structures work.
Alternative 1A – Construct a replacement US 101/Main Street (Trinidad) Undercrossing
The existing US101/Trinidad Undercrossing (04-0058) is a 3-span, 125-foot-long, cast-in-place T-beam
bridge structure on column bents (3) and concrete abutments. The structure was constructed in 1960. The
bent columns are supported on spread footings, and the abutments on driven steel 45-ton piles. The
structure is located east of, or over the Trinidad fault on a hanging wall. Recent surface rupture studies
conducted by Caltrans indicate that surface rupture does not need to be further addressed. The studies
estimated that only a few inches of vertical separation will occur based on a 975 year return period and
using a probabilistic fault displacement analysis.
This proposed improvement intends to construct a replacement US 101/Main Street Undercrossing to
facilitate the improvement of Main Street in the City of Trinidad by widening the roadway and roadway
shoulders, raising profile grade, and adding pedestrian sidewalks. Also proposed are improvements to the
existing northbound and southbound US 101 on and off-ramps. In order to provide for widening and
raising Main Street, it will be necessary to replace the existing 3-span undercrossing. The existing bridge
is in fair condition, however its’ main span is of insufficient dimension to accommodate the wider Main
Street and its soffit elevation will not allow for raising Main Street’s profile grade beneath the structure.
Based on the conditions at the site and the interchange geometrics, the replacement undercrossing will be
a single-span structure approximately 99-feet in length and 86.33-feet in width. The most economical
structure type will likely be a precast, prestressed, concrete girder structure with a 5-foot structure depth.
Supports will be high-cantilever wall type abutments founded on driven piling. An increase in elevation
of US 101 on the order of 2.5-feet will be necessary to allow for a minimum of 15-feet vertical clear
distance from the bottom of soffit to Main Street. The undercrossing will be designed to accommodate a
Type 742 concrete left barrier, a 13.5-foot left shoulder, two 12-foot lanes of southbound traffic, a 5-foot
southbound median shoulder, a future Type 60 median barrier, a 5-foot northbound median shoulder, two
12-foot lanes of northbound traffic, a 10-foot right shoulder, and a Type 742 concrete right barrier.
Falsework is not necessary to erect this type of girder structure. Girders will be set in place from Main
Street using traffic closures.
1
The anticipated 2017 structure cost including bridge removal ($200,000), 10 percent for mobilization,
and 25 percent for contingencies is $6,818,000 which is $798/SF.
Alternatives 2, 5B, & 7 – Construct a new US 101/Cher-Ae Lane Overcrossing
This proposed improvement intends to construct a new Cher-Ae Lane Overcrossing of US 101 about 0.73
miles south of the Trinidad undercrossing. The new overcrossing will connect Scenic Drive, west of US
101, to Westhaven Drive, east of US 101.
Based on the conditions at the site and the roadway geometrics, the new overcrossing will be a singlespan structure approximately 132-feet in length and 47.3-feet in width. The most economical structure
type will likely be a precast, prestressed, concrete girder structure with a 6.3-foot structure depth.
Supports will be high-cantilever wall type abutments founded on driven piling. The overcrossing will be
designed to accommodate a Type 742 concrete left barrier, a 4-foot left shoulder, a 12-foot lane of
westbound traffic, a 12-foot lane of eastbound traffic, a 4-foot right shoulder, a 12.5-foot mixed use path,
and a Type 742 concrete right barrier. Falsework is not necessary to erect this type of girder structure.
Girders will be set in place from US 101 using traffic closures.
The anticipated 2017 structure cost including 10 percent for mobilization, and 25 percent for
contingencies is $4,074,000 which is $652/SF.
Alternatives 3A & 3B – Construct a new US 101/Cher-Ae Lane Interchange
This proposed improvement intends to construct a new Cher-Ae Lane Interchange with a new Cher-Ae
Lane Overcrossing of US 101 about 0.73 miles south of the Trinidad undercrossing. The new
overcrossing will connect Scenic Drive, west of US 101, to Westhaven Drive, east of US 101. New
northbound and southbound on and off-ramps will be constructed connecting US 101 to Cher-Ae Lane.
Based on the conditions at the site and the interchange geometrics, the new overcrossing will be a singlespan structure approximately 132 feet in length and 54.8 feet in width. The most economical structure
type will likely be a precast, prestressed, concrete girder structure with a 6.3-foot structure depth.
Supports will be high-cantilever wall type abutments founded on driven piling. The overcrossing will be
designed to accommodate a Type 742 concrete left barrier, an 8-foot left shoulder, a 12-foot lane of
westbound traffic, a 12-foot lane of eastbound traffic, an 8-foot right shoulder, a 12-foot mixed use path,
and a Type 742 concrete right barrier. Falsework is not necessary to erect this type of girder structure.
Girders will be set in place from US 101 using traffic closures.
The anticipated 2017 structure cost including 10 percent for mobilization, and 25 percent for
contingencies is $4,441,000 which is $614/SF.
Alternative 5A – Construct a replacement US 101/Main Street Undercrossing and a new
US101/Cher-Ae Lane Interchange
This proposed improvement intends to construct a replacement US 101/Main Street Undercrossing in
Trinidad and a new Cher-Ae Lane Interchange with a new Cher-Ae Lane Overcrossing of US 101 about
0.73 miles south of the Trinidad undercrossing. The replacement undercrossing structure includes
improvements to the existing northbound and southbound US 101 on and off-ramps. The new
overcrossing will connect Scenic Drive, west of US 101, to Westhaven Drive, east of US 101.
Based on the conditions at the sites and the site specific geometrics, the replacement undercrossing will
be a single-span structure approximately 99-feet in length and 86.33-feet in width while the new
overcrossing will be a single-span structure approximately 132-feet in length and 47.3-feet in width. The
most economical structure types will likely be precast, prestressed, concrete girders with 5-foot and 6.3foot structure depths respectively. Supports for both will be high-cantilever wall type abutments founded
on driven piling. The undercrossing will be designed to accommodate a Type 742 concrete left barrier, a
13.5-foot left shoulder, two 12-foot lanes of southbound traffic, a 5-foot southbound median shoulder, a
2
future Type 60 median barrier, a 5-foot northbound median shoulder, two 12-foot lanes of northbound
traffic, a 10-foot right shoulder, and a Type 742 concrete right barrier. The overcrossing will be designed
to accommodate a Type 742 concrete left barrier, a 4-foot left shoulder, a 12-foot lane of westbound
traffic, a 12-foot lane of eastbound traffic, a 4-foot right shoulder, a 12.5-foot mixed use path, and a Type
742 concrete right barrier. Falsework is not necessary to erect this type of girder structure. Girders will be
set in place from Main Street in Trinidad and US 101 respectively using traffic closures.
The anticipated 2017 structure cost including bridge removal ($200,000), 10 percent for mobilization, and
25 percent for contingencies is $10,892,000 which is $736/SF for this two structure project.
Alternative 6 – Construct a new US 101/Baker Ranch Road Interchange
This proposed improvement intends to construct a new Baker Ranch Road Interchange with a new Baker
Ranch Road Undercrossing of US 101 about 1.24 miles south of the Trinidad undercrossing. The new
undercrossing will connect Scenic Drive, west of US 101, to Westhaven Drive, east of US 101. New
northbound and southbound on and off-ramps will be constructed connecting US 101 to Baker Ranch
Road.
Based on the conditions at the site and the interchange geometrics, the new undercrossing will be a singlespan structure approximately 71-feet in length and 86.33-feet in width. The most economical structure
type will likely be a precast, prestressed, concrete girder structure with a 3.75-foot structure depth.
Supports will be high-cantilever wall type abutments founded on driven piling. The undercrossing will be
designed to accommodate a Type 742 concrete left barrier, a 13.5-foot left shoulder, two 12-foot lanes of
southbound traffic, a 5-foot southbound median shoulder, a future Type 60 median barrier, a 5-foot
northbound median shoulder, two 12-foot lanes of northbound traffic, a 10-foot right shoulder, and a Type
742 concrete right barrier. Falsework is not necessary to erect this type of structure. Girders will be set in
place from Baker Ranch Road below.
The anticipated 2017 structure cost including 10 percent for mobilization, and 25 percent for
contingencies is $6,585,000 which is $1074/SF.
Alternative 8 – Construct a new US 101/New Local Road Interchange
This proposed improvement intends to construct a New Local Road Interchange with a New Local Road
Overcrossing of US 101 about 1.0 miles south of the Trinidad undercrossing. The new overcrossing will
connect Scenic Drive (via Cher-Ae Lane), west of US 101, to Westhaven Drive, east of US 101. New
northbound and southbound on and off-ramps will be constructed connecting US 101 to the New Local
Road.
Based on the conditions at the site and the interchange geometrics, the new overcrossing will be a singlespan structure approximately 94-feet in length and 42.83-feet in width . The most economical structure
type will likely be a precast, prestressed, concrete girder structure with a 5-foot structure depth. Supports
will be high-cantilever wall type abutments founded on driven piling. The overcrossing will be designed
to accommodate a Type 742 concrete left barrier, an 8-foot left shoulder, a 12-foot lane of westbound
traffic, a 12-foot lane of eastbound traffic, an 8-foot right shoulder, and a Type 742 concrete right barrier.
Falsework is not necessary to erect this type of girder structure. Girders will be set in place from US 101
using traffic closures.
The anticipated 2017 structure cost including 10 percent for mobilization, and 25 percent for
contingencies is $3,119,000 which is $775/SF.
3
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
ATTACHMENT D
RIGHT OF WAY IMPACT EXHIBITS
R1721PSR003.docx
51
US 101 / Trinidad Area Access Improvements
PSR‐PDS, December, 2017
01‐HUM‐101 PM 98.4/100.7
EA: 01‐48040K; EFIS: 0100020301
ATTACHMENT E
PROJECT COST ESTIMATE WORKSHEETS
R1721PSR003.docx
52
US 101 / Trinidad Area Access Improvements
Capital Outlay Project Estimate
01-HUM-101 PM 98.4/100.7
01-48040K
Project Study Report - Project Development Support
Capital Outlay Project Estimate
Dist - Co - Rte 01-HUM-101
PM 98.4/100.7
Program Code
Project Number
Month / Year December 2017
PROJECT DESCRIPTION:
Limits:
From 0.6 Mile south to 0.4 Mile north of Trinidad Road Undercrossing
Proposed Improvement (Scope): Improvements to Main Street with signalized intersections, including
reconstruction of the Trinidad-Main Street Interchange (PM 100.7), widening of Main Street from Scenic
Drive to Westhaven Drive, and widening of Scenic Drive from Cher-Ae Lane to Main Street in the City of
Trinidad (PM 100.1-101.1).
Alternate: 1A
SUMMARY OF PROJECT COST ESTIMATE
TOTAL ROADWAY ITEMS
TOTAL STRUCTURES ITEMS
TOTAL ENVIRONMENTAL MITIGATION ITEMS
SUBTOTAL CONSTRUCTION COSTS
TOTAL RIGHT-OF-WAY ITEMS
R1721CST024.xls
$
$
$
$
$
30,400,000
6,818,000
800,000
38,018,000
800,000
TOTAL PROJECT CAPITAL OUTLAY COSTS $
Note: Costs escalated at 5% per year for 4 years
38,818,000
Alternative 1A - Page 1
US 101 / Trinidad Area Access Improvements
Capital Outlay Project Estimate
I.
01-HUM-101 PM 98.4/100.7
01-48040K
ROADWAY ITEMS
Total Cost $
Average Cost Per Lane Mile
3,800,000
Number of Lane Miles
8.0
X
Total Cost
$
30,400,000
=
Explanation:
Cost includes complete replacement of Main Street on new vertical profile to meet structure clearance
requirements and accessibility requirements. All ramps are completely replaced to current geometric
standards. Scenic Drive is widened. The mainline UC structure is replaced necessitating half width
stage construction and a raised vertical profile to provide standard vertical clearance on Main Street.
Number of lane miles includes Main Street, Westhaven Drive, Secenic Drive, mainline, and ramps.
Significant costs include an estimated 12,000 feet of retaining walls, with an average height of 8 feet;
nearly 1,000,000 square feet of structure section; an estimated 130,000 cubic yards of excavation.
$
TOTAL ROADWAY ITEMS
II.
30,400,000
STRUCTURES ITEMS
Structure
1
Bridge Name
Trinidad UC
Total Cost for Structure $
6,818,000
Structure
2
N/A
$
Structure
3
N/A
-
$
-
Explanation:
Existing UC structure will be replaced to accommodate standard vertical clearance on Main Street.
Half width construction will be required and the vertical profile raised. The cost assumes a precast,
prestressed, concrete girder structure. Supports would be high-cantilever wall type abutments on
driven piling. The cost includes removal of the existing structure and aesthetic treatments.
TOTAL STRUCTURE ITEMS
R1721CST024.xls
$
6,818,000
Alternative 1A - Page 2
US 101 / Trinidad Area Access Improvements
Capital Outlay Project Estimate
III.
01-HUM-101 PM 98.4/100.7
01-48040K
ENVIRONMENTAL MITIGATION
Quantity
Environmental Mitigation
Unit
1
LS
Unit Price
X
$
800,000
Item Cost
=
$
800,000
Explanation:
Environmental mitigation cost includes costs for mitigating impacts to permanently filling wetlands and other
mitigation items that may be necessary to meet Coastal Commission expectations.
TOTAL ENVIRONMENTAL MITIGATION ITEMS
IV.
800,000
$
RIGHT-OF-WAY ITEMS
Escalated
Value
A. Acquisition, including excess lands,
damages to remainder(s) and Goodwill
$
590,000
B. Utility Relocation (State share)
$
210,000
Anticipated Date of Right-of-Way Certification
(Date to which values are escalated at 5% per year)
2019
Explanation:
Acquisition estimate assumes full take of small retail business in SW quadrant of the Scenic Drive/Main Street
intersection and partial takes of other businesses in the vicinity of the Trinidad-Main Street Interchange.
Numerous additional takes along the frontages of Scenic Drive, from Cher-Ae Lane to Main Street are included
in the estimate. City of Trinidad utility impacts are assumed to be in franchise agreement areas. It is assumed
that a portion of the PG&E and AT&T impacts, east of the I/C and along Scenic Drive, will be relocated as state
expense.
TOTAL RIGHT-OF-WAY ITEMS
R1721CST024.xls
$
800,000
Alternative 1A - Page 3
US 101 / Trinidad Area Access Improvements
Capital Outlay Project Estimate
01-HUM-101 PM 98.4/100.7
01-48040K
Project Study Report - Project Development Support
Capital Outlay Project Estimate
Dist - Co - Rte 01-HUM-101
PM 98.4/100.7
Program Code
Project Number
Month / Year December 2017
PROJECT DESCRIPTION:
Limits:
From 0.4 Mile South to 0.4 Mile North of Trinidad Road Undercrossing
Proposed Improvement (Scope): Improvements to Main Street with roundabout intersections, including
reconstruction of the Trinidad-Main Street Interchange ramps (PM 100.7), widening of Main Street from
Scenic Drive to Westhaven Drive, and widening of Scenic Drive from Cher-Ae Lane to Main Street in the
City of Trinidad (PM 100.3 – 101.1).
Alternate: 1B
SUMMARY OF PROJECT COST ESTIMATE
TOTAL ROADWAY ITEMS
TOTAL STRUCTURES ITEMS
TOTAL ENVIRONMENTAL MITIGATION ITEMS
SUBTOTAL CONSTRUCTION COSTS
TOTAL RIGHT-OF-WAY ITEMS
R1721CST024.xls
$
$
$
$
$
18,200,000
575,000
18,775,000
1,290,000
TOTAL PROJECT CAPITAL OUTLAY COSTS $
Note: Costs escalated at 5% per year for 4 years
20,065,000
Alternative 1B - Page 1
US 101 / Trinidad Area Access Improvements
Capital Outlay Project Estimate
I.
01-HUM-101 PM 98.4/100.7
01-48040K
ROADWAY ITEMS
Total Cost $
Average Cost Per Lane Mile
5,200,000
Number of Lane Miles
3.5
X
Total Cost
$
18,200,000
=
Explanation:
Cost includes complete replacement of Main Street on new vertical profile to meet accessibility
requirements and acceptable grades through the roundabouts, while leaving US 101 mainline and
structure intact. All ramps are completely replaced to current geometric standards. Scenic Drive is
widened. The mainline UC structure will remain, while Main Street is lowered significantly to the
east of the interchange. Lowering Main Street increases costs per lane mile since numerous walls and
right-of-way takes are required to account for the lower profile. Number of lane miles includes Main
street, Westhaven Drive, Scenic Drive,Patricks Point Drive, Trinidad Frontacge Road, and ramp
replacement.
Significant costs include an estimated 10,000 feet of retaining walls, with an average height if 8 feet;
neary 550,000 square feet of stuctural section.
$
TOTAL ROADWAY ITEMS
II.
18,200,000
STRUCTURES ITEMS
Bridge Name
Total Cost for Structure $
Structure
1
N/A
Structure
2
N/A
-
$
Structure
3
N/A
-
-
$
Explanation:
This alternative assumes the existing structure will remain in place.
TOTAL STRUCTURE ITEMS
R1721CST024.xls
$
-
Alternative 1B - Page 2
US 101 / Trinidad Area Access Improvements
Capital Outlay Project Estimate
III.
01-HUM-101 PM 98.4/100.7
01-48040K
ENVIRONMENTAL MITIGATION
Quantity
Environmental Mitigation
Unit
1
LS
Unit Price
X
$
575,000
Item Cost
=
$
575,000
Explanation:
Environmental mitigation cost includes costs for mitigating impacts to permanently filling wetlands and other
mitigation items that may be necessary to meet Coastal Commission expectations. This alternative is mostly
contained within existing areas, which minimizes environmental impacts.
TOTAL ENVIRONMENTAL MITIGATION ITEMS
IV.
575,000
$
RIGHT-OF-WAY ITEMS
Escalated
Value
A. Acquisition, including excess lands,
damages to remainder(s) and Goodwill
$
1,040,000
B. Utility Relocation (State share)
$
250,000
Anticipated Date of Right-of-Way Certification
(Date to which values are escalated at 5% per year)
2019
Explanation:
Acquisition estimate assumes full take of small retail business in SW quadrant of the Scenic Drive/Main Street
intersection and partial takes of other businesses in the vicinity of the Trinidad-Main Street Interchange. Full
takes of multiple parcels along Westhaven Drive and Trinidad Frontage Road east of the interchange increase the
acquisition estimates significantly. Numerous additional takes along the frontages of Scenic Drive, from CherAe Lane to Main Street are included in the estimate. City of Trinidad utility impacts are assumed to be in
franchise agreement areas. It is assumed that a portion of the PG&E and AT&T impacts, east of the I/C and
along Scenic Drive, will be relocated as state expense.
TOTAL RIGHT-OF-WAY ITEMS
R1721CST024.xls
$
1,290,000
Alternative 1B - Page 3
US101/TrinidadAreaAccessImprovements
CapitalOutlayProjectEstimate
01ͲHUMͲ101PM98.4/100.7
01Ͳ48040K
Project Study Report - Project Development Support
Capital Outlay Project Estimate
Dist - Co - Rte 01-HUM-101
PM 98.4/100.7
Program Code
Project Number
Month / Year December 2017
PROJECT DESCRIPTION:
Limits:
0.8 Mile South of Trinidad Undercrossing
Proposed Improvement (Scope): Construct new Cher-Ae Lane Overcrossing (PM 100.0) with local road
connection to Scenic Drive and Westhaven Drive (no connection to US 101), including widening of Scenic
Drive from Cher-Ae Lane to Main Street in the City of Trinidad and widening of Westhaven Drive from
US
101 in the Community of Westhaven to Main Street in the City of Trinidad (PM 98.1 – 100.7).
Alternate: 2
SUMMARY OF PROJECT COST ESTIMATE
TOTAL ROADWAY ITEMS
TOTAL STRUCTURES ITEMS
TOTAL ENVIRONMENTAL MITIGATION ITEMS
SUBTOTAL CONSTRUCTION COSTS
TOTAL RIGHT-OF-WAY ITEMS
R1721CST024.xls
$
$
$
$
$
12,012,000
4,074,000
500,000
16,586,000
1,620,000
TOTAL PROJECT CAPITAL OUTLAY COSTS $
Note: Costs escalated at 5% per year for 4 years
18,206,000
Alternative2ͲPage1
US101/TrinidadAreaAccessImprovements
CapitalOutlayProjectEstimate
I.
01ͲHUMͲ101PM98.4/100.7
01Ͳ48040K
ROADWAY ITEMS
Total Cost $
Average Cost Per Lane Mile
1,320,000.00
Number of Lane Miles
9.1
X
Total Cost
$
12,012,000
=
Explanation:
Cost includes all new roadway for Cher-Ae Lane connecting Scenic Drive to Westhaven Drive.
Scenic Drive is widened from Cher-Ae Lane to Main Street in the City of Trinidad. Westhaven Drive
is widened from the Community of Westhaven to Main Street in the City of Trinidad. Number of lane
miles includes Cher-Ae Lane, Scenic Drive, and Westhaven Drive. Costs per lane mile are low since
there is not a lot of significant retaining wall and roadway excavation work.
Significant costs include nearly 750,000 square feet of structural section.
TOTAL ROADWAY ITEMS
II.
12,012,000
$
STRUCTURES ITEMS
Structure
1
Bridge Name
Cher-Ae Lane OC
Total Cost for Structure $
4,074,000
Structure
2
N/A
$
Structure
3
N/A
-
-
$
Explanation:
A new one span OC structure is proposed over Route 101 as an extension of Cher-Ae Lane. The cost
assumes a precast, prestressed, concrete girder structure. Supports would be high-cantilever wall type
abutments on driven piling. The cost includes aesthetic treatments.
TOTAL STRUCTURE ITEMS
R1721CST024.xls
$
4,074,000
Alternative2ͲPage2
US101/TrinidadAreaAccessImprovements
CapitalOu