US 101 / Trinidad Area Access Improvements

Tribal code

Ask Donna

What actually matters in this document.

Text

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

TABLE OF CONTENTS

Section

Page

1.

INTRODUCTION .............................................................................................................. 1

2.

BACKGROUND ................................................................................................................ 2

3.

PURPOSE AND NEED...................................................................................................... 4

4.

TRAFFIC ENGINEERING PERFORMANCE ASSESSMENT ....................................... 4

5.

DEFICIENCIES.................................................................................................................. 8

6.

CORRIDOR AND SYSTEM COORDINATION .............................................................. 9

7.

ALTERNATIVES ............................................................................................................ 10

8.

RIGHT OF WAY.............................................................................................................. 42

9.

STAKEHOLDER INVOLVEMENT ............................................................................... 44

10.

ENVIRONMENTAL DETERMINATION/DOCUMENT .............................................. 45

11.

FUNDING ........................................................................................................................ 45

12.

DELIVERY SCHEDULE................................................................................................. 46

13.

RISKS ............................................................................................................................... 46

14.

FHWA COORDINATION ............................................................................................... 47

15.

PROJECT REVIEWS ....................................................................................................... 47

16.

PROJECT PERSONNEL ................................................................................................. 47

17.

ATTACHMENTS ............................................................................................................. 47

R1721PSR003.docx

ii

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

Project Study Report –

Project Development

Support

US‐101 / Trinidad Area

Access Improvements

EA: 01‐48040K

EFIS ID: 01‐0002‐0301

PPNO:

01‐HUM‐101 PM 98.4/100.7

1. INTRODUCTION

Figure 1 – Exhibit drawing for the programming alternative;

Alternative 3A – New US 101/Cher‐Ae Lane Interchange.

The Trinidad Rancheria and Caltrans District 1 are working in partnership to identify alternatives to

meet the transportation needs of the Trinidad Rancheria and the surrounding community. This PSR‐

PDS identifies 12 alternatives to address the transportation deficiencies between the unincorporated

community of Westhaven and the City of Trinidad. The main deficiencies identified for this area are:

(1) Scenic Drive’s geotechnical instability, with slides and slip‐outs commonly occurring along this

route, causing partial or complete road closures (typically during winter months); (2) anticipated

Rancheria growth is likely to cause several intersections in the area to have inadequate vehicular

capacity; and (3) Tribal lands east and west of US 101 have inadequate connectivity.

Project Limits

01‐HUM‐101 PM 98.4/100.7

Number of Alternatives

12 Plus No‐Build

Alternative Recommended for Programming

Alternative 3A –New US 101/Cher‐Ae Lane Interchange

Capital Outlay Support Estimate for PA&ED

(Anticipated Environmental Approval

7/1/22)

Current (2017):

$2,500,000

Capital Outlay Construction Cost Range

Capital Outlay Right‐of‐Way Cost Range

Funding Source(s)

Funding Year

Type of Facility

Number of Structures

Anticipated Environmental Determination

Legal Description

Project Development Category

R1721PSR003.docx

Current (2017):

Escalated @ 5% to 2024:

$16,600,000 to $46,200,000

$23,360,000 to $65,000,000

Current (2017):

Escalated @ 5% to 2024:

$800,000 to $3,880,000

$1,125,000 to $5,460,000

Anticipated to include some or all of the following:

State Transportation Improvement Program (STIP)

Tribal Transportation Program (TTP)

Indian Reservation Roads (IRR)

Active Transportation Program (ATP)

Highway Safety Improvement Program (HSIP)

Transportation Investment Generating Economic Recovery

(TIGER)

2018

4‐Lane Freeway

1 to 3

EIR/FONSI

In Humboldt County, near Trinidad from Westhaven Drive

Undercrossing to 0.4 Mile North of Trinidad Road

Undercrossing

Category 3 – Projects on previously constructed access

controlled routes requiring a new or revised freeway

agreement, but not a route adoption.

1

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

The range of alternatives includes improvements to the existing Trinidad‐Main Street interchange,

improvements to Scenic Drive and Westhaven Drive, and/or a new local road interchange. A detailed

description of each alternative can be found in Section 7. Additional studies are needed to determine

which of the proposed alternatives will best meet the purpose and need of the project. Either a project

report or a supplemental Project Initiation Document (PID), following the format of a Project Study

Report (PSR), will serve as the programming document for the remaining components of the project. A

project report, accompanied by a signed environmental document, will serve as approval of the selected

alternative.

2. BACKGROUND

Description of Existing Facility:

US 101 is the economic lifeline of the north coast and is the most important route in District 1. It serves

interregional and interstate traffic, with relatively high traffic volumes and heavy use by both truck and

tourist traffic. US 101 is functionally classified as a principal arterial. US 101 is on the National Highway

System but is not part of the FHWA Rural and Single Interstate Routing System. It is part of the Strategic

Highway Network and the Interregional Highway System and is considered a High Emphasis Route in

the Interregional Transportation Strategic Plan. Within the project segment, US 101 is designated a

Surface Transportation Assistance Act (STAA) route and is part of the Pacific Coast Bike Route. Portions

of US 101 are also eligible for Scenic Highway Designation.

US 101 from PM 98.4 to 100.7 is a four lane freeway with a paved median width that ranges from 4 feet

wide at the south end of the project limits, to 22 feet wide at the north end of the project limits. Outside

shoulders within the project limits are consistently 4 feet wide, but widen out to 10 feet wide north of the

existing US 101/Trinidad‐Main Street Interchange. The posted speed limit along US 101 in this area is 65

mph. Within the project limits, US 101 is relatively flat, with some rolling hills, and grades ranging from

approximately 2% to 4.5%. The horizontal alignment is curvilinear, with tangents up to nearly a mile

long, and horizontal curve radii ranging between 1,800 feet and 12,000 feet. Existing right‐of‐way widths

within the project limits vary from approximately 160 feet wide to 460 feet wide, with access controlled

rights‐of‐way. Existing adjacent land use is almost entirely Residential, of which most is comprised of

Rural Residential (RR), with a small amount of Residential Estates (RE). Current year traffic volumes for

US 101 are approximately 10,350 vehicles (ADT). Based on the Trinidad Area Freeway Master Plan

Study, future (year 2040) traffic volumes are estimated to be approximately 14,500 vehicles without full

Trinidad Rancheria Master Plan buildout, and 20,510 vehicles (ADT) with full Trinidad Rancheria Master

Plan buildout.

There are three existing interchanges (I/C) within the project segment as described below:

TABLE 1: EXISTING INTERCHANGES

Post

Mile

Name

Overcrossing

or

Undercrossing

98.1

Westhaven Drive I/C

Undercrossing

98.4

Sixth Street I/C

Overcrossing

100.7

Trinidad ‐ Main Street I/C

Undercrossing

R1721PSR003.docx

2

Description

A half interchange with a tight NB off‐

ramp and a SB hook ramp from Scenic

Drive

A hook ramp Type L‐6 with all ramps

on the north side of Sixth Street

A tight diamond Type L‐1

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

Scenic Drive is a 2‐lane rural roadway, which runs in a south‐north direction on the west side of US 101,

from the community to Westhaven, north to the City of Trinidad. The roadway begins near Moonstone

County Park and the Little River State Beach in Westhaven (Left of PM 97.8), and follows the Pacific coast

line northerly for approximately 3.2 miles to Main Street in the City of Trinidad. Scenic Drive is a

winding and narrow road, approximately 16’‐20’ wide through most of the southerly portion, with no

sidewalks and little to no useable paved shoulders. The majority of Scenic Drive has severe geotechnical

instability, and frequently has closures for emergency roadway repairs to reestablish access. Existing

slopes along Scenic Drive are typically very steep, sloping to the Pacific Ocean on the west side, and

sloping upwards towards US 101 on the east side. The posted speed limit along Scenic Drive is 30 mph.

According to the City of Trinidad Draft General Plan Circulation Element, current year traffic volumes

for Scenic Drive are approximately 870 vehicles (ADT), while future (year 2040) traffic volumes are

estimated to be 1,357 vehicles (ADT).

Westhaven Drive is a 2‐lane rural‐residential roadway, which runs in a south‐north direction on the east

side of US 101 from the community of Westhaven to the City of Trinidad. The roadway begins at a

partial interchange on US 101 (PM 98.1), is approximately 3.3 miles long, and terminates at the Trinidad‐

Main Street interchange (PM 100.7) in the City of Trinidad. The roadway is narrow, typically about 20ʹ

wide, with little to no useable shoulders, and no sidewalks. The posted speed limit along Westhaven

Drive is 25 mph. According to the City of Trinidad Draft General Plan Circulation Element, current year

traffic volumes for Westhaven Drive are approximately 865 vehicles (ADT), while future (year

2040) traffic volumes are estimated to be 1,509 vehicles (ADT).

Main Street is a quiet, 2‐lane roadway which lies in the heart of the City of Trinidad. Main Street runs in

an east‐west direction, and is a primary collector that extends from just east of US 101 through the City of

Trinidad. Main Street has a posted speed limit of 20 mph, and according to the City of Trinidad Draft

General Plan Circulation Element, current year traffic volumes for Main Street are approximately 3,170

vehicles (ADT), while future (year 2040) traffic volumes are estimated to be 4,706 vehicles (ADT). The

City of Trinidad has long been known as a rural, seaside fishing village, with very unique characteristics,

limited tourist activity, and a strong desire to minimize adverse impacts caused by visitors. There are a

few existing RV parks within the area, which typically see increases in use during the summer months.

Discussion of Studies to Date:

Since 2001, several planning studies have been completed, including the draft Project Initiation Document

(PID), in order to study accessibility to the Trinidad Rancheria and the surrounding areas, and to

investigate alternatives that would provide improved access for current and future needs. The different

studies that have been prepared have consistently demonstrated that the existing interchanges and local

roads within this corridor can neither: (1) provide the necessary traffic level of service to all areas within

the corridor, nor (2) be improved economically to appropriately accommodate the design‐year traffic

demands. The various studies that have been completed are listed below:

Trinidad Rancheria Access Improvement Feasibility Study, Winzler & Kelly, May 2002

Trinidad Rancheria Tribal Transportation Plan 2006‐2026, Winzler & Kelly, March 2006

Trinidad Rancheria Highway 101 Interchange Community Design Fair, Local Government

Commission, June 2009

Trinidad Rancheria Comprehensive Community‐Based Plan, Trinidad Rancheria, December 2011

Trinidad Area Freeway Master Plan Study, Omni‐Means, Ltd., February 2014

Trinidad Rancheria Tribal Transportation Safety Plan, Trinidad Rancheria, June 2014

R1721PSR003.docx

3

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

Since 2012, a Project Development Team (PDT) has met to guide the project through the project

development process. This PDT team has been instrumental to date in developing the purpose and need

for the project, and preparing the project to reach this stage. The PDT team will continue to play a key

role in guiding the project through to completion.

3. PURPOSE AND NEED

Purpose:

The purpose of the project is to:

1.

2.

3.

Provide safe and sustainable access to and from US 101, for all modes of transportation, to the

Trinidad Rancheria and the surrounding communities located along Scenic Drive, Westhaven

Drive, and in the City of Trinidad.

Relieve projected traffic congestion associated with planned future development.

Reconnect tribal lands.

Need:

The proposed project is needed because:

1.

2.

3.

The only access to Trinidad Rancheria lands from US 101, Scenic Drive west of the Trinidad

Rancheria, is not safe or sustainable:

a. It is geologically unstable; slides and slip‐outs commonly cause partial or complete road

closures, particularly during the winter months.

b. It is not a pedestrian/bicycle friendly route, due to the lack of sidewalks and minimal or no

paved shoulders.

The current capacity at several intersections would be inadequate to accommodate projected

increases in traffic due to planned future development.

The construction of US 101 severed tribal lands.

4. TRAFFIC ENGINEERING PERFORMANCE ASSESSMENT

Traffic Operations:

The Trinidad Area Freeway Master Plan Study (Traffic Study), prepared by Omni‐Means, Ltd., was

approved by District 1 Traffic Operations in February 2014. The Traffic Study analyzed US 101, from the

Sixth Street I/C to the Trinidad‐Main Street I/C, as well as Main Street, Scenic Drive, Westhaven Drive, the

Sixth Street I/C and the Trinidad‐Main Street I/C. The Traffic Study analyzed existing performance, and

future performance of these facilities based on anticipated growth. The Traffic Study projected traffic

growth for this area of Humboldt County, including the City of Trinidad and the Trinidad Rancheria.

The development envisioned in the Cher‐Ae Heights Indian Community of the Trinidad Rancheria,

December 2011, was included in the traffic projections as well. The Traffic Study projected traffic

volumes to the year 2040 conditions.

While additional alternatives are presented for consideration in this PSR-PDS, the Traffic Study analyzed

three alternatives:

No Project.

Alternative 1A. Reconstruct Trinidad-Main Street I/C to accommodate year 2040 traffic

Alternative 3A. New freeway I/C at Cher-Ae Lane to accommodate year 2040 traffic.

At the time the Traffic Study was prepared, some of the current alternatives had not been brought about

yet, including the Baker Ranch Road interchange or the One‐Mile Spacing Interchange. While the Traffic

R1721PSR003.docx

4

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

Study does not consider the full range of alternatives, the analysis results can be applied to the range of

alternatives presented in the PSR‐PDS, based on comparable alternatives. For example, results from the

Traffic Study for a new Cher‐Ae Lane Interchange can be applied to the Baker Ranch Road Interchange,

with similar results.

According to the Traffic Study, all intersections and roadway segments within the study area, including

US 101 mainline and interchanges, are currently operating at acceptable levels of service (LOS) (LOS B or

higher). With anticipated growth and projected traffic volumes from the Traffic Study, and without full

build‐out of the Trinidad Rancheria Master Plan, all intersections and roadway segments within the

study area are expected to continue operating at acceptable LOS for the year 2040 conditions.

With full development of the Trinidad Rancheria Master Plan, several intersections are expected to

operate at unacceptable LOS (LOS D or lower) in the year 2040 conditions. The Scenic Drive/Main Street

intersection, Main Street/US 101 northbound ramps intersection, and the Scenic Drive/Cher‐Ae Lane

intersections all would be operating at LOS F, and would require improvements to provide for acceptable

levels of service (LOS C or higher). US 101 mainline and ramp junctions would continue to operate at

acceptable LOS under the year 2040 conditions with full build‐out. Table 2 shows a summary of the

intersection LOS for the year 2040 conditions with full development of the Trinidad Rancheria Master

Plan, for the analyzed alternatives.

TABLE 2: INTERSECTION LOS FOR YEAR 2040 CONDITIONS

WITH FULL MASTER PLAN DEVELOPMENT

Location

No‐Build

Alternative 1A

(Maintain Two‐Way

(Reconstruct Trinidad‐

Stop Control

Main Street I/C with

(TWSC)

Signals)

AM Peak PM Peak

Alternative 3A

(New US 101/

Cher‐Ae Lane I/C)

AM Peak

PM Peak

AM Peak

PM Peak

Hour

Hour

Hour

Hour

Hour

Hour

6th Street/Kay Avenue

A

A

A

A

A

A

6th Street/Kahlstrom Avenue

A

A

A

A

A

A

Kay Avenue/US 101 SB Ramps

A

A

A

A

A

A

Kahlstrom Avenue/7th Avenue

A

A

A

A

A

A

Scenic Drive/Main Street

F

F

C

C

C

C

Main Street/US 101 SB Ramps

C

C

B

B

B

B

Main Street/US 101 NB Ramps

F

F

B

B

B

B

Westhaven Drive/Frontage Road

B

B

B

B

B

B

Scenic Drive/Baker Ranch Drive

A

A

A

A

A

A

Scenic Drive/Cher‐Ae Lane

A

B

C

C

A

A

Scenic Drive/Cher‐Ae Heights Casino

B

F

C

C

A

A

Scenic Drive/Landford Road

B

C

B

C

A

A

Cher‐Ae/101 SB Ramps

‐

‐

‐

‐

B

B

Cher‐Ae/101 NB Ramps

‐

‐

‐

‐

A

B

Cher‐Ae/Westhaven

‐

‐

‐

‐

A

A

Notes:

“‐“ Denotes that the intersection does not exist for this alternative.

Either the proposed US 101/Cher‐Ae Lane interchange or reconstruction of the existing Trinidad‐Main

Street interchange will result in acceptable LOS (LOS C or better) for all of the studied intersections.

R1721PSR003.docx

5

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

Table 3 shows a summary of the US 101 mainline and ramp junction LOS for the year 2040 conditions

with full development of the Trinidad Rancheria Master Plan, for the analyzed alternatives.

TABLE 3: US 101 MAINLINE AND RAMP JUNCTION LOS FOR YEAR 2040

CONDITIONS WITH FULL MASTER PLAN DEVELOPMENT

Location

No Project

Alternative 1A

(Maintain Two‐Way

(Reconstruct

Stop Control

Trinidad‐Main Street

(TWSC)

I/C with Signals)

AM Peak PM Peak

Alternative 3A

(New US 101/

Cher‐Ae Lane I/C)

AM Peak

PM Peak

AM Peak

PM Peak

Hour

Hour

Hour

Hour

Hour

Hour

NB US 101 (Westhaven to Trinidad)

A

B

A

B

A

B

SB US 101 (Westhaven to Trinidad)

A

B

A

B

A

A

US 101 Mainline

US 101 Ramps @ Sixth Street Interchange (Merge/Diverge)

NB Off‐Ramp

B

B

B

B

B

B

NB On‐Ramp

B

B

B

B

B

B

SB Off‐Ramp

A

B

A

B

A

B

SB On‐Ramp

A

B

A

B

A

B

US 101 Ramps @ Cher‐Ae Lane Interchange (Merge/Diverge)

NB Off‐Ramp

‐

‐

‐

‐

B

B

NB On‐Ramp

‐

‐

‐

‐

A

B

SB Off‐Ramp

‐

‐

‐

‐

A

B

SB On‐Ramp

‐

‐

‐

‐

A

B

US 101 Ramps @ Trinidad‐Main Street Interchange (Merge/Diverge)

NB Off‐Ramp

B

B

A

B

A

B

NB On‐Ramp

A

B

A

B

A

B

SB Off‐Ramp

A

A

A

A

A

A

SB On‐Ramp

A

B

A

B

A

B

Notes:

“‐“ Denotes that the ramp junctions do not exist for this alternative.

For the base (no project) year 2040 conditions, the traffic operations analysis shows that without

improvements, there will be an unacceptable LOS at several intersections. In order to provide adequate

traffic operations, either the existing Trinidad‐Main Street interchange will need to be reconstructed or a

new interchange in the vicinity of the Trinidad Rancheria is required.

Intersection Control Evaluation (ICE) ‐ New US 101/Cher‐Ae Lane Interchange:

In accordance with Traffic Operations Policy Directive (TOPD) 13‐02, an Intersection Control Evaluation –

Step 1 (ICE) was completed for the proposed US 101/Cher‐Ae Lane interchange, which evaluated three

alternatives at this proposed interchange. The three intersection alternatives that were evaluated were

All‐Way Stop Control, Signalized Intersections, and Modern Roundabouts. Based on the ICE Report

prepared by Omni‐Means, dated November 30, 2015, all three alternatives are projected to provide

acceptable traffic operations beyond the year 2040 conditions. The All‐Way Stop Control and Signalized

Intersection alternatives provide LOS B for both AM and PM peak hours, while the Modern Roundabout

alternative provides LOS A for both AM and PM peak hours.

R1721PSR003.docx

6

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

Intersection Control Evaluation (ICE) ‐ US 101/Trinidad‐Main Street Interchange:

In accordance with Traffic Operations Policy Directive (TOPD) 13‐02, an intersection control evaluation

was completed for the US 101/Trinidad‐Main Street interchange, which evaluated three alternatives at

this interchange. The three intersection alternatives that were evaluated were No‐Build, Signalized

Intersections, and Modern Roundabouts. Based on the ICE Report prepared by Omni‐Means, dated

November 30, 2015, the No‐Build alternative is projected to provide unacceptable traffic operations under

the year 2040 conditions. Both the Signalized Intersections and Modern Roundabout alternatives are

projected to provide acceptable traffic operations under the year 2040 conditions. The Modern

Roundabout alternative is projected to provide the highest levels of service for all intersections, with LOS

of either A or B for the year 2040 conditions. Signalized intersections would provide LOS B or C, and the

No‐Build alternative is projected to provide levels of service as low as LOS F.

ICE Review by Caltrans District 1 Traffic Operations:

The Intersection Control Evaluations prepared for both the Proposed US 101/Cher‐Ae Lane Interchange

and the US 101/Trinidad‐Main Street Interchange were reviewed by Caltrans District 1 Traffic Operations

staff, and concurrence on both ICE Reports was received in a letter from Troy Arseneau, PE, District 1

ICE Coordinator, dated December 16, 2015. Along with concurrence on the ICE Reports, the letter states

that if full build‐out of the Rancheria Master Plan is anticipated, a new interchange is the appropriate

alternative, versus making significant improvements to downtown Main Street in Trinidad.

Weaving Analysis:

Caltrans District 1 Office of Traffic Operations performed an independent weaving analysis for the

proposed US 101/Cher‐Ae Lane interchange, with results provided in a memorandum dated January 17,

2014. Based on the approximate 0.7 mile spacing proposed, the conclusion from this analysis was that

there is adequate distance on US 101 between the proposed interchange ramps and the existing Trinidad

interchange ramps to accommodate the interaction of entering and exiting traffic. The analysis included

both current and projected traffic volumes on US 101, in both the north and south directions. The

analysis also confirmed that auxiliary lanes will not be needed if a new interchange is constructed near

PM 100.2.

Traffic Collision Analysis:

A traffic collision analysis was prepared by the District 1 Traffic Safety Office on November 17, 2017.

The collision analysis was conducted for the most recently available 3‐year time period (in TASAS

database), from 07/01/2012 to 6/30/2015, for the US 101 corridor from PM 97.4 to PM 101.2 (From 0.7 mile

south of Westhaven Undercrossing to 0.5 mile north of the Trinidad‐Main Street interchange).

There were 30 total reported collisions within this 4.068 mile segment (13 SB, 17 NB, 0 fatality, 9 injury, 23

ʺproperty damage onlyʺ, 5 multi‐vehicle, 8 ʺwet road surfaceʺ, 2 ʺsnow, icy road surfaceʺ, 3 ʺdark‐no

street lightʺ, 3 ʺdark‐street lightʺ). From TASAS Table B, this highway segment has actual ʺFatalʺ and

ʺF+Iʺ collision rates which are less than the statewide average for similar highway facilities. The actual

ʺTotalʺ collision rate is 1.9 times greater than the statewide average for similar highway facilities, as

shown below in Table 4.

TABLE 4: COLLISION RATE SUMMARY FOR HUM‐101‐97.4 / 101.2

TABLE B DATES: 07/01/2012 TO 6/30/2015

Actual Accident Rates

Fatal

F+I

Total

0.000

0.17

0.72

R1721PSR003.docx

Average Accident Rates

Fatal

F+I

Total

0.014

0.17

0.38

7

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

Of the reported 30 collisions within this segment, the principal primary collision factor was ʺimproper

turnʺ (11 of 30), followed by ʺspeedingʺ (6 of 30), ʺother than driverʺ (6 of 30), ʺinfluence of alcoholʺ (4 of

30), ʺother violationsʺ (2 of 30), and ʺfailure to yieldʺ (1 of 30). The primary ʺType of Collisionʺ resulted in

a single vehicle running off the road in 18 of 30 collisions. Of the 18 run off road collisions, 17 involved a

vehicle hitting an object off the roadway; the objects struck are as follows: tree(s) (1 of 17), sign (3 of 17),

embankment (6 of 17), fence (1 of 17), guard rail (1 of 17), object off road (1 of 17), curb or dike (1 of 17),

ditch (1 of 17), utility pole (1 of 17).

Summarizing the 18 run off road collisions, 4 involved a driver under the influence of alcohol, 13 of 18

were of unknown cause, 4 of 18 were the result of improper turn, and 1 of 18 was caused by a merging

vehicle at the Westhaven SB onramp. The initial movement preceding collision involved a vehicle run off

road. The majority of the 30 reported collisions occurred during ʺdaylightʺ (20 of 30) on a ʺdryʺ road

surface (20 of 30). There has been no history of Table B collision concentration locations within this

segment. After review and consideration of all driver/witness statements and Traffic Collision Report

summaries, no collision concentrations or apparent collision patterns were identified. Three of the

reported 30 collisions occurred on ramps within the project limits; these collisions are as follows:

•

•

SB Westhaven On‐ramp ‐ PM 97.772 SB: This collision involved a motorist that ran off the road

to the driverʹs right due to speeding and uncertainty as to which way to turn onto this onramp.

NB Westhaven Off‐ramp ‐ PM 98.003 NB: This collision involved a reckless driver speeding and

running off the road.

SB Trinidad Off‐ramp ‐ PM l00.832 SB: This collision involved a reckless driver (traveling at 80‐

120 mph) which ran off the road to the driverʹs left, over‐corrected, and ran off the road to the

driverʹs right.

The project is expected to include shoulder widening to reduce the frequency of run off road collisions

within the project limits, by providing additional recovery room for errant vehicles. As stated in the

previous collision analysis from November 16, 2015, collision frequency from construction of one of the

proposed interchange alternatives (HUM‐101 approximately PM 98.8/100.3) is expected to increase when

compared with the collision frequency of the existing highway segment at this location. This increase is

expected to be offset by a decrease in collision frequency at the Westhaven, Sixth St., and Trinidad

Interchanges due to lower traffic volumes utilizing these interchanges after construction of one of the

proposed interchange alternatives. Perpetuation of existing center‐line and shoulder rumble strip at all

appropriate locations within the project limits is recommended to help continue to provide auditory and

vibro‐tactile warning to errant drivers.

5. DEFICIENCIES

Primary Deficiencies:

Safe and Sustainable Access to the Trinidad Rancheria ‐ Scenic Drive, from 1.5 miles south of Cher‐Ae

Lane to Cher‐Ae Lane, has numerous narrow, one‐lane unpaved areas that are geologically unstable.

Maintaining this section of Scenic Drive in a sustainable and reliable manner is not viable as documented

in the Geotechnical Screening of Alternatives Memorandum, SHN Consulting Engineering & Geologists,

Inc., August 27, 2015. See Attachment J. Winter storms often result in full closure of this section of Scenic

Drive, leaving the Rancheria with only one means of ingress/egress (Scenic Drive, north of Cher‐Ae

Lane).

Traffic Level of Service ‐ Based on the information presented in Section 4 above, and the Trinidad Area

Freeway Master Plan Study (Traffic Study), prepared by Omni‐Means, Ltd, projected traffic growth within

R1721PSR003.docx

8

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

the study will result in LOS F conditions at intersections on Scenic Drive and at the US 101/Trinidad‐Main

Street I/C.

Tribal Lands Connectivity ‐ When US 101 was constructed in the early 1950’s, Tribal lands were severed

by the freeway. Currently, Tribal members living on the east side of US 101 have to travel 2 miles to

access services at the Trinidad Rancheria. Some residents on the east side of the freeway simply walk

across the freeway lanes to reach the Rancheria (a 0.3+/‐ mile distance).

Secondary Deficiencies:

Inadequate Shoulder Widths ‐ According to the collision analysis prepared by Caltrans District 1 Traffic

Operations, collisions along US 101 in the study area more often than not have resulted in the driver

running off road, typically hitting another object off the road. US 101 shoulder widths through most of

the study area are 4’ wide, rather than the standard 10’ wide. In addition, shoulder widths along Scenic

Drive and Westhaven Drive are minimal or non‐existent.

6. CORRIDOR AND SYSTEM COORDINATION

Route Adoption:

US 101, from Little River Bridge (PM 97.5) to 0.3 mile north of Trinidad‐Main Street (PM 101.0), was

adopted into the freeway system by the California Highway Commission on June 21, 1955.

The US 101 freeway agreement, within the then City of Trinidad city limits, between the California

Department of Public Works and the City of Trinidad, was approved in 1957. The freeway agreement

reconfigured portions of the state highway and identified a half interchange at Trinidad‐Main Street.

The US 101 freeway agreement, from Little River Bridge to 0.3 mile north of Trinidad‐Main Street,

between the California Division of Highways and Humboldt County, was approved in 1957. In 1959, the

freeway agreement was amended to provide a full interchange at Trinidad‐Main Street. The freeway

agreements reconfigured state and local roads to result in the current configuration.

Statewide, Regional, and Local Planning:

The US 101 Draft Transportation Concept Report (TCR) within District 1 was completed in October, 2017.

The Draft TCR concept is to maintain the existing Ultimate Facility Concept in Humboldt County, which

includes a mixture of 4‐lane freeway/expressway and 2‐lane conventional highway. US 101 is a 4‐lane

Freeway within the project area.

US 101, within much of District 1 and within the project limits, is legislatively designated as the “Pacific

Coast Bike Route”. Meeting the needs of non‐motorized travel is a priority with ongoing consideration

being given to upgrading shoulders and providing parallel route access where appropriate.

The District System Management Plan for District 1 was approved on October 3, 2012. US 101, in the

project area, meets the ultimate transportation concept.

US 101, in the project area, is served by Redwood Coast Transit and Redwood Transit System.

There are park and ride lots on both the east and west sides of the Trinidad‐Main Street I/C.

There are not any other planned or programmed STIP projects in the project area.

The Trinidad Rancheria approved the Cher‐Ae Heights Indian Community of the Trinidad Rancheria

Comprehensive Community‐Based Plan in December 2011. The 90+/‐ acre Rancheria is bisected by US

R1721PSR003.docx

9

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

101 and includes housing, offices, library, restaurant and casino on the west side of US 101. East of US

101, the Rancheria includes housing. In the City of Trinidad, the Rancheria owns the Trinidad Pier &

Harbor, as well as a restaurant. The land use portion of the plan identifies expanded commercial, cultural

and residential development.

The Trinidad Rancheria Transportation Plan (TRTP) identifies the need to develop a new interchange

with US 101 at Cher‐Ae Lane (Cher‐Ae Heights Indian Community of the Trinidad Rancheria – Tribal

Transportation Plan 2006‐2026, Winzler & Kelly, March 15, 2006).

The Humboldt County General Plan does not specifically allow for construction of new roadways,

highway overcrossings, or interchanges. However, Humboldt County representatives have been

involved with the development of the project, and have expressed support with regards to moving

forward with the project.

The City of Trinidad’s General Plan update has been in draft form since 2009. Within the City’s draft

General Plan update, significant effort was made to express the City’s desire to maintain the current rural

lifestyle, protect the unique character of the City as a “fishing village”, encourage limited tourism, and

minimize adverse impacts caused by visitors.

Maintenance Agreements:

Improvements identified in the various alternatives will likely require a modification to the existing

maintenance agreement, or a new maintenance agreement with Humboldt County or the Trinidad

Rancheria. This modified or new maintenance agreement would be needed to define maintenance

responsibilities and financial arrangements, and would be executed after the Project Approval and

Environmental Document (PA&ED) phase.

FHWA Actions:

No FHWA action is required.

State Actions:

Alternatives proposing modifications to existing or new interchanges will affect existing freeway access‐

control, and will need to be addressed. In addition, the California Transportation Commission (CTC) will

need to provide consent prior to adding a new public road connection to US 101, which will require a

new freeway agreement with Humboldt County (to be completed after PA&ED phase).

7. ALTERNATIVES

A range of alternatives, including the No‐Build Alternative, were considered at this Project Initiation

phase. All these alternatives, and potentially additional alternatives, will be analyzed in the Project

Approval and Environmental Document (PA&ED) phase. Following are the alternatives under

consideration. Each alternative was analyzed using consistent factors in order to provide similar

comparisons between each alternative. As summarized in Table 5 below, five alternatives have been

identified (Alternatives 3A, 3B, 5A, 5B, and 8) that appear to meet the Purpose and Need. See

Attachment B for preliminary exhibits for each alternative.

R1721PSR003.docx

10

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

R1721PSR003.docx

Increased Safety?

Estimated Project

Cost

Environmental

Impacts

Right‐of‐Way

Impacts

Aesthetics

(Analysis Item)

Alternative 1A: Improvements to

the US 101/Trinidad‐Main Street

interchange with Traffic Signals

Alternative 1B: Improvements to

the US 101/Trinidad‐Main Street

interchange with Roundabouts

Alternative 2: Cher‐Ae Lane

Overcrossing with local road

connections to Westhaven Drive and

Scenic Drive

Alternative 3A: New US 101/Cher‐

Ae Lane interchange with local road

connections to Scenic Drive and

Westhaven Drive

Alternative 3B: Identical to

Alternative 3A but with local road

connection to Scenic Drive and Class

I Mixed‐Use Trail connection to

Westhaven Drive

Alternative 4A: Improvements to

Scenic Drive from Westhaven to

Trinidad.

Alternative 4B: Construction of new

frontage road to replace Scenic

Drive, from Westhaven to Cher‐Ae

Lane, and improvements to Scenic

Drive from Cher‐Ae Lane to

Trinidad.

Alternative 5A: Combine

Alternative 1A and Alternative 2.

Improvements to the US

101/Trinidad‐Main Street

interchange with Traffic Signals, and

Cher‐Ae Lane Overcrossing with

local road connections to Westhaven

Drive and Scenic Drive.

Improves Traffic

Operations?

Alternative

Appears to Meet

Purpose and need?

TABLE 5: SUMMARY OF PROJECT ALTERNATIVES

(1)

(2)

(3)

(4)

(5)

(6)

(7)

No

Yes

Yes

$38.8M

Med

Med

High

No

Yes

Yes

$20.1M

Med

High

High

No

Yes

Yes

$18.2M

High

High

High

Yes

Yes

Yes

$32.3M

High

High

High

Yes

Yes

Yes

$31.3M

High

High

High

No

No

Yes

$22.0M

Med

Low

Low

No

No

Yes

$31.7M

Very

High

Very

High

Med

Yes

Yes

Yes

$48.0M

High

High

Very

High

11

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

R1721PSR003.docx

Increased Safety?

Estimated Project

Cost

Environmental

Impacts

Right‐of‐Way

Impacts

Aesthetics

(Analysis Item)

Alternative 5B: Combine

Alternative 1B and Alternative 2.

Improvements to the US

101/Trinidad‐Main Street

interchange with Roundabouts, and

Cher‐Ae Lane Overcrossing with

local road connections to Westhaven

Drive and Scenic Drive.

Alternative 6: New US 101/Baker

Ranch Road interchange with local

road connections to Scenic Drive

and Westhaven Drive, and frontage

road between Baker Ranch Road and

Cher‐Ae Lane.

Alternative 7: Combine Alternative

2 and Alternative 4B. Cher‐Ae Lane

Overcrossing with local road

connections to Westhaven Drive and

Scenic Drive, new frontage road to

replace Scenic Drive, from

Westhaven to Cher‐Ae Lane, and

improvement to Scenic Drive from

Cher‐Ae Lane to Trinidad.

Alternative 8: New US 101/1.0 Mile

Spacing Interchange approximately

1 mile south of the US 101/Trinidad‐

Main Street Interchange, with local

road connections to Cher‐Ae Lane

and Westhaven Drive.

No‐Build Alternative: This

alternative assumes no

improvements to any of the

roadways in the study area.

Improves Traffic

Operations?

Alternative

Appears to Meet

Purpose and need?

TABLE 5: SUMMARY OF PROJECT ALTERNATIVES

(1)

(2)

(3)

(4)

(5)

(6)

(7)

Yes

Yes

Yes

$31.5M

High

High

Very

High

No

Yes

Yes

$39.6M

Very

High

Very

High

High

No

No

Yes

$39.5M

Very

High

Very

High

High

Yes

Yes

Yes

$32.6M

High

High

High

No

No

No

‐

None

None

None

12

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

Nonstandard Design Features:

For each alternative, the preliminary designs were compared to design standards using the DIB 78 Design

Checklist and a Design Standards Risk Assessment was completed. Common to alternatives 3A and 3B is

the need for an exception to the following mandatory design standard:

Nonstandard Feature:

It is proposed to construct a new interchange on US 101 that would result in interchange spacing

less than the minimum standard spacing. A new interchange is proposed to be located between

the 6th Street Interchange and the Trinidad‐Main Street Interchange, and would be a minimum of

0.7 miles or greater south of the Trinidad‐Main Street Interchange.

Standard for Which Exception is Required:

Per the Highway Design Manual (HDM), Topic 501.3: The minimum interchange spacing shall

be one mile in urban areas, two miles outside of urban areas, and two miles between freeway‐

to‐freeway interchanges and other interchanges.

Reason for Requesting Exception:

The primary reason for requesting the exception is that the project will provide improved access

between the Trinidad Rancheria and US 101. Currently, Scenic Drive is the only roadway

serving the residential, recreational and tribal developments along the coast, between the

community of Westhaven and the City of Trinidad. North and south of the Trinidad

Rancheria, Scenic Drive extends along unstable coastal bluffs that have a history of slides

and slip‐outs resulting in closure of the road for extended periods of time. Numerous

locations are unpaved and single‐lane. These closures have a significant negative impact

on public access and emergency access along Scenic Drive. The proposed project would

add another point of access between US 101 and Scenic Drive which will improve

emergency access and result in a public safety benefit.

Additional benefits to the project are the reconnection of tribal lands, which were severed by the

construction of US 101, and to provide infrastructure that will accommodate planned future

development. Development of the Trinidad Rancheria’s approved master plan (Cher‐Ae Heights

Indian Community of the Trinidad Rancheria, Comprehensive Community‐Based Plan, December

2011) would increase traffic volume and cause an unacceptable level of service.

Interchange Spacing Design Exception Approval:

The interchange spacing design standard exception was approved on September 29, 2016 and can

be provided upon request.

In support of the approval of the interchange spacing design exception, Omni‐Means prepared a

Technical Memorandum, dated September 22, 2016, that provides a detailed analysis of the items

required to be addressed pursuant to DIB No. 77 “Interchange Spacing”.

Other anticipated exceptions to design standards that are common to all alternatives are summarized

below and included in Table 6.

Standard for Which Exception is Required:

Mandatory Design Standard, 203.2 Standards for Curvature: Tables 202.2A through 202.2E shall

be the minimum radius of curve for superelevation rates and design speeds on highways.

R1721PSR003.docx

13

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

Nonstandard Feature:

The minimum radius of horizontal curves for US 101 is 2,100 feet. Existing horizontal curves

along US 101 vary from 1,800 feet to 12,000 feet, thus would require an exception without a

change in the horizontal alignment.

Standard for Which Exception is Required:

Mandatory Design Standard, 305.1 Median Width: Freeways and Expressways. In areas where

restrictive conditions prevail the minimum median width shall be 22 feet.

Nonstandard Feature:

Currently the median width along US 101 in the project area varies from 4 feet at the south end to

22 feet at the north end. The various project alternatives would improve US 101 with a minimum

median width of 12’.

Standard for Which Exception is Required:

Advisory Design Standard, 309.1 Horizontal Clearances for Highways: Existing above‐ground

utilities and existing large trees as defined in Index 902.2(2) should conform to the guidance

associated with necessary highway features stated above.

Nonstandard Feature:

It is anticipated that all alternatives will have conflicts with existing trees, and may not be able to

conform to the guidance discussed above. This item will be further reviewed during subsequent

phases of project development.

TABLE 6: DESIGN STANDARDS RISK ASSESSMENT

(COMMON TO ALL ALTERNATIVES)

Probability

of Design

Exception

Approval

Mandatory Design Standard

 Existing condition.

 Evaluate collisions.

M: 203.2 Standards for Curvature:

Tables 202.2A through 202.2E shall be the

minimum radius of curve for superelevation

rates and design speeds on highways.

The minimum radius of horizontal curves for US

101 is 2,100 feet. Existing horizontal curves along

US 101 vary from 1,800 feet to 12,000 feet, thus

would require an exception without a change in the

horizontal alignment.

M: 305.1 Median Width: Freeways and

Expressways.

In areas where restrictive conditions prevail the

minimum median width shall be 22 feet.

Currently the median width along US 101 in the

project area varies from 4 feet at the south end to 22

feet at the north end. The various project

alternatives would improve US 101 with a minimum

median width of 12’.

R1721PSR003.docx

Justification for Probability Rating

14

HIGH

 Existing condition.

 Proposed improvement to

existing condition.

HIGH

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

TABLE 6: DESIGN STANDARDS RISK ASSESSMENT

(COMMON TO ALL ALTERNATIVES)

Probability

of Design

Exception

Approval

Advisory Design Standard

Justification for Probability Rating

 Fixed objects will be addressed

and removed to the fullest

extent feasible.

A: 309.1 Horizontal Clearances for Highways:

Existing above-ground utilities and existing large

trees as defined in Index 902.2(2) should conform to

the guidance associated with necessary highway

features stated above.

HIGH

It is anticipated that all alternatives will have

conflicts with existing trees, and may not be able to

conform to the guidance discussed above. This item

will be further reviewed during subsequent phases

of project development.

For all other exceptions to design standards, a Design Standards Risk Assessment was completed and is

included with each alternative discussion below.

Improvements to Main Street with Signalized Intersections:

Alternative 1A

 Four traditional signalized intersections

 Replacement of the Trinidad‐Main Street Interchange

 Widen Main Street from Scenic Drive to Westhaven Drive

 Widen Scenic Drive from Cher‐Ae Lane to Main Street

Alternative 1A includes Improvements to Main Street with signalized intersections, replacement of the

Trinidad‐Main Street Interchange (PM 100.7), widening of Main Street from Scenic Drive to Westhaven

Drive, and widening of Scenic Drive from Cher‐Ae Lane to Main Street in the City of Trinidad.

See Figure 2.

R1721PSR003.docx

15

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

Figure 2 ‐ Alternative 1A Schematic Exhibit

Alternative 1A improvements include:

Construction of traffic signals at each of the four Main Street and Westhaven Drive intersections

at this location

Reconstruction and widening of Main Street to accommodate future traffic demands

Reconstruction of the Main Street profile to meet current design standards

Construction of a new US 101 undercrossing structure to accommodate the widened Main Street

Reconstruction of the US 101 on and off‐ramps to accommodate future traffic demands

Reconstruction of US 101 mainline to provide a minimum 12 foot wide median and 10 foot

shoulders

Reconstruction of US 101 mainline profile to meet current decision sight distance standards

Widening and/or reconstruction of Scenic Drive to provide 4 foot minimum shoulders and

sidewalk on one side

Reconstruction of adjacent roadways to tie in to existing improvements

(1) Purpose and Need: Alternative 1A alone does not meet the purpose and need for this project.

While improvements to the Trinidad‐Main Street Interchange would accommodate the planned

future development in the area, it does not provide for a 2nd safe and sustainable access to and from

US 101, for all modes of transportation, to the Trinidad Rancheria and the surrounding communities,

nor does it reconnect tribal lands within the study area.

(2) Traffic Operations: Alternative 1A includes improvements to the US 101/Trinidad‐Main Street

interchange, as well as Scenic Drive, that would result in improved traffic operations, and would

provide for acceptable levels of service for the 3 intersections that would otherwise perform at

unacceptable levels of service.

(3) Increased Safety: Alternative 1A will widen the median and shoulders on US 101, and would

chiefly construct the proposed improvements to current standards (See Section 8). Scenic Drive,

between Cher‐Ae Lane and Main Street, will also be improved. These improvements will likely

result in increased public safety.

R1721PSR003.docx

16

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

(4) Project Costs: Total Capital Outlay project costs for Alternative 1A are estimated at $38.8 million,

are higher than expected for projects of similar size and nature, and are in the high‐range of

estimated costs for all alternatives. The additional project costs can be attributed to replacement of

the Trinidad‐Main Street Interchange (PM 100.7), extensive grading work and significant retaining

wall work. See Appendix E for the preliminary project cost estimate worksheet.

(5) Environmental Impacts: It is anticipated that Alternative 1A will have some minor impacts to

existing environmental resources within the project limit. Some existing drainage features, including

culverts and drainage ditches/streams will need modification or mitigation. In addition, there is

potential to discover cultural resources in the vicinity of the project. However, since it is

reconstruction and will have a similar footprint to the existing footprint, the risk level is less than

other alternatives proposing new roadways.

(6) Right‐of‐Way Impacts: Due to the extensive grading and vertical profile changes, it is

anticipated that some right‐of‐way acquisition will be required for Alternative 1A. Right‐of‐way

acquisition is expected to be limited to partial takes in areas where roads are widened, or extensive

grading must be done to allow for adequate sight distance or to meet other standards. It is estimated

that 7‐10 parcels will be affected adjacent to the US 101/Trinidad‐Main Street interchange, and 10‐15

parcels could be affected along Scenic Drive. See Section 8 and Appendix D for the right‐of‐way

impact summary and exhibit.

(7) Aesthetics: Alternative 1A will significantly alter the existing rural and unique character of the

Trinidad‐Main Street interchange. The drastic change is likely to be considered incompatible with

the rural fishing village character of the City of Trinidad, and the City’s Draft General Plan.

(8) Design Exceptions: The preliminary design and design standards were checked using the DIB 78

Design Checklist. A Design Standards Risk Assessment was completed for Alternative 1A and the

anticipated exceptions to design standards (beyond those identified for all alternatives) are presented

in Table 6. The Design Standards Risk Assessment for this alternative will be further addressed in

the PA&ED phase.

TABLE 7: DESIGN STANDARDS RISK ASSESSMENT (ALTERNATIVE 1A)

Probability

of Design

Exception

Approval

Mandatory Design Standard

 Proposed is similar to the

existing condition.

 Operation to be verified by

traffic modeling.

M: 504.3(3) - Location and Design of Ramp

Intersections on the Crossroads.

The minimum distance (curb return to curb

return) between ramp intersections and local

road intersections shall be 400 feet.

MEDIUM

As little as 20 feet is provided in the design.

R1721PSR003.docx

Justification for Probability Rating

17

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

TABLE 7: DESIGN STANDARDS RISK ASSESSMENT (ALTERNATIVE 1A)

Probability

of Design

Exception

Approval

Advisory Design Standard

A: 310.2 - Outer Separation.

In urban areas and in mountainous terrain, the width

of the outer separation should be a minimum of 26

feet from edge of traveled way to edge of traveled

way.

Justification for Probability Rating

 Existing condition.

 Need to evaluate collisions.

HIGH

Outer separation between the southbound US 101

off-ramp and Patricks Point Drive is only 24'.

Improvements to Main Street with Roundabouts:

Alternative 1B

 Construct two modern roundabouts

 Reconstruct on and off‐ramps

 Widen Scenic Drive from Cher‐Ae Lane to Main Street

Alternative 1B includes improvements to Main Street with modern roundabouts, including

reconstruction of the on and off‐ramps, reconstruction of Main Street, and widening of Scenic Drive from

Cher‐Ae Lane to Main Street in the City of Trinidad (PM 100.0 – 101.1).

See Figure 3.

Figure 3 ‐ Alternative 1B Schematic Exhibit

R1721PSR003.docx

18

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

Alternative 1B improvements include:

Construction of two large modern roundabouts at the interchange

Reconstruction of Main Street to accommodate future traffic demands

Reconstruction of the US 101 on and off‐ramps

Widening and/or reconstruction of Scenic Drive to provide 4 foot minimum shoulders and

sidewalk on one side

Reconstruction of adjacent roadways to tie in to existing improvements

(1) Purpose and Need: Alternative 1B alone does not meet the purpose and need for this project.

While improvements to the Trinidad‐Main Street Interchange would accommodate the planned

future development in the area, it does not provide for a 2nd safe and sustainable access to and from

US 101, for all modes of transportation, to the Trinidad Rancheria and the surrounding communities,

nor does it reconnect tribal lands within the study area.

(2) Traffic Operations: Alternative 1B includes improvements to the US 101/Trinidad‐Main Street

interchange, as well as Scenic Drive, that would result in improved traffic operations, and would

provide for acceptable levels of service for the 3 intersections that would otherwise perform at

unacceptable levels of service.

(3) Increased Safety: Alternative 1B will widen the shoulders on US 101 within the immediate

project area, and would chiefly construct the proposed improvements to current standards (See

Section 8). Scenic Drive, between Cher‐Ae Lane and Main Street, will also be improved. These

improvements will likely result in increased public safety.

(4) Project Costs: Total Capital Outlay project costs for Alternative 1B are estimated at $20.1 million,

which is similar to what would be expected for projects of similar size and nature, and is in the low‐

range of estimated costs for all alternatives. The cost estimate provided for this alternative assumes

significantly less reconstruction of US 101 adjacent to the Trinidad‐Main Street interchange, as well as

allowing the existing undercrossing structure to remain in place. The median is not widened with

this alternative, since the existing structure would remain in place, and there would not be adequate

decision sight distance (DSD) from US 101 to the northbound off‐ramp to Main Street without

reconstruction of US 101 similar to alternative 1A. To replace the existing structure and reconstruct

US 101 to meet the DSD standard, estimated costs for Alternative 1B would be similar to Alternative

1A, around $37.8 million. See Appendix E for the preliminary project cost estimate worksheet.

(5) Environmental Impacts: It is anticipated that Alternative 1B will have slightly more impacts

(than Alternative 1A) to existing environmental resources within the project limit. Some existing

drainage features, including culverts and drainage ditches/streams will need modification or

mitigation. In addition, there is potential to discover cultural resources in the vicinity of the project.

However, since it is reconstruction and will have a similar footprint to the existing footprint, the risk

level is less than other alternatives proposing new roadways.

(6) Right‐of‐Way Impacts: Due to the extensive grading and vertical profile changes, it is

anticipated that some right‐of‐way acquisition will be required for Alternative 1B. Right‐of‐way

acquisition would be similar to Alternative 1A, with the exception that the roundabout footprints will

be larger, and providing accessibility through the interchange will require additional length of lower

grades, thereby lowering the vertical profile of Main Street more than Alternative 1A. This would

likely require some full R/W acquisition to adjacent parcels east of US 101, and northeast of

Westhaven Drive. It is estimated that 7‐10 parcels will be affected adjacent to the US 101/Trinidad‐

R1721PSR003.docx

19

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

Main Street interchange, and 10‐15 parcels could be affected along Scenic Drive. See Section 8 and

Appendix D for the right‐of‐way impact summary and exhibit.

(7) Aesthetics: Alternative 1B will significantly alter the existing rural character of the Trinidad‐

Main Street interchange, and will require a significantly larger footprint within the interchange area.

The drastic change is likely to be considered incompatible with the rural fishing village character of

the City of Trinidad, and the City’s Draft General Plan.

(8) Design Exceptions: The preliminary design and design standards were checked using the DIB 78

Design Checklist. A Design Standards Risk Assessment was completed for Alternative 1B and the

anticipated exceptions to design standards (beyond those identified for all alternatives) are presented

in Table 7. The Design Standards Risk Assessment for this alternative will be further addressed in

the PA&ED phase.

TABLE 8: DESIGN STANDARDS RISK ASSESSMENT (ALTERNATIVE 1B)

Probability

of Design

Exception

Approval

Mandatory Design Standard

M: 504.3(3) - Location and Design of Ramp

Intersections on the Crossroads.

The minimum distance (curb return to curb

return) between ramp intersections and local

road intersections shall be 400 feet.

MEDIUM

Justification for Probability Rating

 Proposed is similar to the

existing condition.

 Operation to be verified by

traffic modeling.

As little as 20 feet is provided in the design.

Probability

of Design

Exception

Approval

Advisory Design Standard

A: 201.7 – Decision Sight Distance.

On freeways and expressways the decision sight

distance values in Table 201.7 should be used at

lane drops and at off-ramp noses to interchanges,

branch connections, roadside rests, vista points, and

inspection stations.

The minimum Decision Sight Distance for 70 mph

is 1,105 feet. Without reconstruction of the US 101

profile, a decision sight distance of approximately

972 feet (55 mph) is provided for the northbound

off-ramp to Main Street.

A: 310.2 - Outer Separation.

In urban areas and in mountainous terrain, the width

of the outer separation should be a minimum of 26

feet from edge of traveled way to edge of traveled

way.

Outer separation between the southbound US 101

off-ramp and Patricks Point Drive is only 24'.

R1721PSR003.docx

20

MEDIUM

Justification for Probability Rating

 SSD is OK; 70 mph SSD =

750-ft.

 Need to evaluate collisions.

 Need to evaluate potential

mitigation measures including

lighting striping, signage and

others.

 Existing condition.

 Need to evaluate collisions.

HIGH

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

New Cher‐Ae Lane Overcrossing (PM 100.0):

Alternative 2

 Construct new Cher‐Ae Lane Overcrossing

 Local road connection to Scenic Drive and Westhaven Drive

 Widen Scenic Drive from Cher‐Ae Lane to Main Street

 Widen Westhaven Drive from Westhaven to Trinidad

Alternative 2 includes construction of a new overcrossing structure at Cher‐Ae Lane (PM 100.0), with

local road connections to Scenic Drive and Westhaven Drive, widening of Scenic Drive from Cher‐Ae

Lane to Main Street in the City of Trinidad, and widening of Westhaven Drive in the Community of

Westhaven to Main Street in the City of Trinidad. (PM 98.1 – 100.7).

See Figure 4.

Figure 4 ‐ Alternative 2 Schematic Exhibit

Alternative 2 improvements include:

Construction of a new overcrossing structure at PM 100.0

Reconstruction of Cher‐Ae Lane from Scenic Drive into the Rancheria

Construction of the Cher‐Ae Lane Extension to Westhaven Drive

Widening and/or reconstruction of Scenic Drive to provide 4 foot minimum shoulders and

sidewalk on one side

Widening of Westhaven Drive from the Community of Westhaven to the City of Trinidad

(1) Purpose and Need: Alternative 2 alone does not meet the purpose and need for this project. A

new overcrossing structure without a connection to US 101 would provide for only 2 of the 3 items of

the purpose and need. The new overcrossing would provide for a 2nd safe and sustainable access to

the Trinidad Rancheria, and would also reconnect tribal lands across US 101. But these

improvements will not accommodate the planned future development in the area, and thus, does not

meet the purpose and need.

R1721PSR003.docx

21

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

(2) Traffic Operations: Alternative 2 includes construction of a new overcrossing structure over US

101 at Cher‐Ae Lane, as well as improvements to Scenic Drive and Westhaven Drive, that would

result in slightly improved traffic operations. However, without any improvements to any of the

interchange areas, and without a direct connection to US 101, conditions for the Trinidad‐Main Street

interchange will remain at unacceptable levels of service, as outlined in the Traffic Operations section

above.

(3) Increased Safety: Alternative 2 will not provide any improvements to US 101, but will provide

improvements to Scenic Drive and Westhaven Drive. Therefore, increased safety would be expected

on Scenic Drive, from Cher‐Ae Lane to Trinidad, and along the length of Westhaven Drive, but

generally, overall increased safety would be minimal.

(4) Project Costs: Total Capital Outlay project costs for Alternative 2 are estimated at $18.2 million,

which is similar to what would be expected for projects of similar size and nature, and is in the low‐

range of estimated costs for all alternatives. The cost estimate provided for this alternative assumes

no reconstruction of US 101 adjacent to the Trinidad Rancheria or Trinidad. See Appendix E for the

preliminary project cost estimate worksheet.

(5) Environmental Impacts: It is anticipated that Alternative 2 will have somewhat high

environmental impacts, since it includes construction of a new roadway. It is likely that impacts

would include existing environmental resources within the project limit. Some existing drainage

features, including culverts and drainage ditches/streams will need modification or mitigation. The

area east of US 101 is mostly undeveloped, and has an increased potential of various environmental

impacts. In addition, there is potential to discover cultural resources in the vicinity of the project.

This alternative is in the medium range of environmental impacts as compared to other alternatives,

since the footprint only includes a single road connection across US 101, with no connection to US

101.

(6) Right‐of‐Way Impacts: Right‐of‐Way impacts for Alternative 2 will be somewhat high, since the

project will construct a new roadway across US 101, thereby requiring acquisition of R/W for the full

width of the roadway and associated improvements, including grading. Much of the R/W that will

be required for this project is land already owned by the Trinidad Rancheria, which will significantly

decrease the overall R/W impacts. It is estimated that 10‐12 parcels may be affected adjacent to US

101 in the Cher‐Ae Lane area for the overcrossing, as well as 10‐15 parcels along Scenic Drive. See

Section 8 and Appendix D for the right‐of‐way impact summary and exhibit.

(7) Aesthetics: Alternative 2 will alter the US 101 corridor with construction of a new overcrossing

structure. This impact will be significant for the area, but will be similar to existing interchanges and

overcrossing structures along the US 101 corridor.

(8) Design Exceptions: The preliminary design and design standards were checked using the DIB 78

Design Checklist. A Design Standards Risk Assessment was completed for Alternative 2 and there

no anticipated exceptions to design standards (beyond those identified for all alternatives). The

Design Standards Risk Assessment for this alternative will be further addressed in the PA&ED phase.

R1721PSR003.docx

22

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

New US 101/Cher‐Ae Lane Interchange (PM 100.0):

Alternative 3A

 Construct new US 101/Cher‐Ae Lane Interchange

 Local road connection to Scenic Drive and Westhaven Drive

 Widen Scenic Drive from Cher‐Ae Lane to Main Street

 Widen Westhaven Drive from Westhaven to Trinidad

Alternative 3A includes construction of a new Type L‐1 Compact Diamond interchange at Cher‐Ae Lane

(PM 100.0), with both northbound and southbound ramp connections, local road connections to Scenic

Drive and Westhaven Drive, widening of Scenic Drive from Cher‐Ae Lane to Main Street in the City of

Trinidad, and widening of Westhaven Drive in the Community of Westhaven to Main Street in the City

of Trinidad. (PM 98.1 – 100.7).

See Figure 5.

Figure 5 ‐ Alternative 3A Schematic Exhibit

Alternative 3A improvements include:

Construction of a new Type L‐1 Compact Diamond interchange at PM 100.0

Construction of all northbound and southbound ramp connections

Reconstruction of Cher‐Ae Lane from Scenic Drive into the Rancheria

Construction of the Cher‐Ae Lane Extension to Westhaven Drive

Widening and/or reconstruction of Scenic Drive to provide 4 foot minimum shoulders and

sidewalk on one side

Widening of Westhaven Drive from the Community of Westhaven to the City of Trinidad

(1) Purpose and Need: Alternative 3A appears to meet the purpose and need for this project. A new

interchange with connections to US 101, and public road connections to Scenic Drive and Westhaven

Drive would provide for all of the purpose and need requirements outlined in this study. The new

interchange would provide for a 2nd safe and sustainable access to and from US 101, for all modes of

transportation, to the Trinidad Rancheria and the surrounding communities, accommodate the

planned future development in the area, and would also reconnect tribal lands across US 101.

R1721PSR003.docx

23

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

(2) Traffic Operations: Alternative 3A includes construction of a new interchange with an

overcrossing structure over US 101, public road connections to Scenic Drive and Westhaven Drive, as

well as improvements to Scenic Drive from Cher‐Ae Lane to Trinidad and for the length of

Westhaven Drive. These improvements would result in greatly improved traffic operations within

the study area. Once constructed, and upon full build‐out of the Trinidad Rancheria Master Plan, all

roadways, including US 101 mainline and interchanges, will operate at acceptable levels of service,

including the 3 intersections that would otherwise perform at unacceptable levels of service.

(3) Increased Safety: Alternative 3A will widen the median and shoulders on US 101, and would

chiefly construct the proposed improvements to current standards (See Section 8). Scenic Drive,

between Cher‐Ae Lane and Main Street, will also be improved, along with Westhaven Drive from the

community of Westhaven to Trinidad. These improvements will likely result in increased public

safety.

(4) Project Costs: Total Capital Outlay project costs for Alternative 3A are estimated at $32.3 million,

which is slightly higher than what would be expected for projects of similar size and nature, and is in

the mid‐range of estimated costs for all alternatives. Costs estimated for this alternative are increased

due to areas that will require some extensive grading and retaining wall work due to existing

topography. This additional cost is typical of nearly all of the alternatives that were analyzed with

this study, due to the highly variable terrain within the entire study area. See Appendix E for the

preliminary project cost estimate worksheet.

(5) Environmental Impacts: It is anticipated that Alternative 3A will have somewhat high

environmental impacts, since it includes construction of a new roadway, and construction of a full

new interchange. It is likely that impacts would include existing environmental resources within the

project limit. Some existing drainage features, including culverts and drainage ditches/streams will

need modification or mitigation. The area east of US 101 is mostly undeveloped, and has an

increased potential of various environmental impacts. The area that includes the new interchange

and on and off‐ramps is also mostly undeveloped, and will likely have impacts to existing

environmentally sensitive areas. In addition, there is potential to discover cultural resources in the

vicinity of the project. This alternative is in the high range of environmental impacts as compared to

other alternatives, since the footprint includes a road connection across US 101, along with full ramp

connections to US 101.

(6) Right‐of‐Way Impacts: Right‐of‐Way impacts for this alternative will be somewhat high, since

the project will construct a new roadway across US 101, as well as new ramp connections to US 101,

thereby requiring acquisition of R/W for the full width of the roadway, ramps, and associated

improvements, including grading. A significant amount of the R/W that will be required for this

project is land already owned by the Trinidad Rancheria, and therefore will significantly decrease the

overall R/W impacts. It is estimated that 15‐20 parcels may be affected adjacent to US 101 in the

Cher‐Ae Lane/Trinidad Rancheria area, as well as 10‐15 parcels along Scenic Drive. See Section 8 and

Appendix D for the right‐of‐way impact summary and exhibit.

(7) Aesthetics: Alternative 3A will alter the US 101 corridor with construction of a new interchange.

While this impact will be significant for the area, a new interchange will be similar to existing

interchanges and overcrossing structures along the US 101 corridor.

(8) Design Exceptions: The preliminary design and design standards were checked using the DIB 78

Design Checklist. A Design Standards Risk Assessment was completed for Alternative 3A and the

anticipated exceptions to design standards (beyond those identified for all alternatives) are presented

R1721PSR003.docx

24

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

in Table 9. The Design Standards Risk Assessment for this alternative will be further addressed in

the PA&ED phase.

TABLE 9: DESIGN STANDARDS RISK ASSESSMENT (ALTERNATIVE 3A)

Probability

of Design

Exception

Approval

Mandatory Design Standard

M: 504.3(3) - Location and Design of Ramp

Intersections on the Crossroads.

The minimum distance (curb return to curb

return) between ramp intersections and local

road intersections shall be 400 feet.

HIGH

250-ft provided between the southbound ramps and

the new Cher-Ae Lane roundabout.

M: 504.7 – Weaving Sections.

The minimum weaving length, measured as

shown on Figures 504.2A and 504.2B shall be

2,000 feet in urban areas, 5,000 feet outside

urban areas, and 5,000 feet between freeway-tofreeway interchanges and other interchanges.

The minimum distance (curb return to curb

return) between ramp intersections and local

road intersections shall be 400 feet.

1,720-ft and 2,385-ft provided in the NB and SB

directions, respectively, between the proposed

interchange ramps and the existing interchange

ramps.

HIGH

R1721PSR003.docx

25

Justification for Probability Rating

 No negative operational effect,

to be verified by traffic

modeling.

 Maximized distance based on

other design criteria to match

existing facilities.

The CT District 1 Traffic

Operations Branch completed a

weaving analysis between the US

101/Trinidad-Main Street

Interchange (PM 100.7) and the

Alternative 3A and 3B proposed

interchange at Route 101/CherAe Lane (PM 100.0). Projected

design year 2040 traffic volumes

were used and concluded that the

freeway section between the two

interchanges would operate with

acceptable levels of service with

the project’s full build out under

future conditions and auxiliary

lanes on the freeway between the

interchanges would not be

required within the design year

period. These findings would

also apply to interchanges at

greater spacing such as the

Alternative 8 proposed

interchange at US 101/New

Local Road (PM 99.7).

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

TABLE 9: DESIGN STANDARDS RISK ASSESSMENT (ALTERNATIVE 3A)

Probability

of Design

Exception

Approval

Advisory Design Standard

A: 201.7 – Decision Sight Distance.

On freeways and expressways the decision sight

distance values in Table 201.7 should be used at

lane drops and at off-ramp noses to interchanges,

branch connections, roadside rests, vista points, and

inspection stations.

HIGH

Justification for Probability Rating

 SSD is OK; 70 mph SSD =

750-ft.

 Need to evaluate collisions.

 Need to evaluate potential

mitigation measures including

lighting striping, signage and

others.

The minimum Decision Sight Distance for 70 mph

is 1,105 feet. Without reconstruction of the US 101

profile, a decision sight distance of approximately

750 feet (50 mph) is provided for the northbound

off-ramp to Cher-Ae Lane.

New US 101/Cher‐Ae Lane Interchange (PM 100.0):

Alternative 3B

 Construct new US 101/Cher‐Ae Lane Interchange

 Local road connection to Scenic Drive; mixed‐use path to

Westhaven

 Widen Scenic Drive from Cher‐Ae Lane to Main Street

 Widen Westhaven Drive from Westhaven to Trinidad

Alternative 3B is identical to Alternative 3A, with the exception that instead of a local road connection to

Westhaven Drive, a Class I mixed‐use trail will be constructed from the northbound ramps intersection

east to Westhaven Drive.

See Figure 6.

R1721PSR003.docx

26

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

Figure 6 ‐ Alternative 3B Schematic Exhibit

Alternative 3B improvements include:

Construction of a new Type L‐1 Compact Diamond interchange at PM 100.0

Construction of all northbound and southbound ramp connections

Reconstruction of Cher‐Ae Lane from Scenic Drive into the Rancheria

Construction of a Class I mixed‐use trail connection to Westhaven Drive

Widening and/or reconstruction of Scenic Drive to provide 4 foot minimum shoulders and

sidewalk on one side

Widening of Westhaven Drive from the Community of Westhaven to the City of Trinidad

(1) Purpose and Need: Alternative 3B appears to meet the purpose and need for this project. A new

interchange with connections to US 101, and an improved public road connection to Scenic Drive,

would provide for all of the purpose and need requirements outlined in this study. The new

interchange would provide for a 2nd safe and sustainable access to and from US 101, for all modes of

transportation, to the Trinidad Rancheria and the surrounding communities, accommodate the

planned future development in the area, and would also reconnect tribal lands across US 101 with a

mixed‐use trail connection to Westhaven Drive.

(2) Traffic Operations: Alternative 3B includes construction of a new interchange with an

overcrossing structure over US 101, a public road connection to Scenic Drive, a mixed‐use trail

connection to Westhaven Drive, as well as improvements to Scenic Drive from Cher‐Ae Lane and for

the length of Westhaven Drive. These improvements would result in greatly improved traffic

operations within the study area. Once constructed, and upon full build‐out of the Trinidad

Rancheria Master Plan, all roadways, including US 101 mainline and interchanges, will operate at

acceptable levels of service, including the 3 intersections that would otherwise perform at

unacceptable levels of service.

(3) Increased Safety: Alternative 3B will widen the median and shoulders on US 101, and would

chiefly construct the proposed improvements to current standards (See Section 8). Scenic Drive,

between Cher‐Ae Lane and Main Street, will also be improved, along with Westhaven Drive from the

community of Westhaven to Trinidad. These improvements will likely result in increased public

safety.

R1721PSR003.docx

27

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

(4) Project Costs: Total Capital Outlay project costs for Alternative 3B are estimated at $31.3 million,

slightly less than alternative 3A, is slightly higher than what would be expected for projects of similar

size and nature, and is in the mid‐range of estimated costs for all alternatives. Costs estimated for

this alternative are increased due to areas that will require some extensive grading and retaining wall

work due to existing topography. This additional cost is typical of nearly all of the alternatives that

were analyzed with this study, due to the highly variable terrain within the entire study area. See

Appendix E for the preliminary project cost estimate worksheet.

(5) Environmental Impacts: It is anticipated that Alternative 3B will have somewhat high

environmental impacts, since it includes construction of a new roadway, and construction of a full

new interchange. It is likely that impacts would include existing environmental resources within the

project limit. Some existing drainage features, including culverts and drainage ditches/streams will

need modification or mitigation. The area east of US 101 is mostly undeveloped, and has an

increased potential of various environmental impacts. The area that includes the new interchange

and on and off‐ramps is also mostly undeveloped, and will likely have impacts to existing

environmentally sensitive areas. In addition, there is potential to discover cultural resources in the

vicinity of the project. This alternative is in the high range of environmental impacts as compared to

other alternatives, since the footprint includes a road connection across US 101, along with full ramp

connections to US 101.

(6) Right‐of‐Way Impacts: Right‐of‐Way impacts for Alternative 3B will be somewhat high, slightly

less than Alternative 3A as the project will construct a new roadway across US 101, as well as new

ramp connections to US 101, thereby requiring acquisition of R/W for the full width of the roadway,

ramps, and associated improvements, including grading. A significant amount of the R/W that will

be required for this project is land already owned by the Trinidad Rancheria, and therefore will

significantly decrease the overall R/W impacts. It is estimated that 15‐20 parcels may be affected

adjacent to US 101 in the Cher‐Ae Lane/Trinidad Rancheria area, as well as 10‐15 parcels along Scenic

Drive. See Section 8 and Appendix D for the right‐of‐way impact summary and exhibit.

(7) Aesthetics: Alternative 3B will alter the US 101 corridor with construction of a new interchange.

While this impact will be significant for the area, a new interchange will be similar to existing

interchanges and overcrossing structures along the US 101 corridor.

(8) Design Exceptions: The preliminary design and design standards were checked using the DIB 78

Design Checklist and a draft Design Standards Risk Assessment was completed for Alternative 3B.

The exceptions to design standards for Alternative 3B are anticipated to be identical to Alternative

3A. See previous Table 9.

Improve Scenic Drive from Westhaven to Trinidad:

Alternative 4A

 Improve Scenic Drive from US 101 in the Community of

Westhaven to Main Street in the City of Trinidad (PM

98.4/100.7)

Alternative 4A includes widening of Scenic Drive from US 101 in the Community of Westhaven to Main

Street in the City of Trinidad. (PM 98.4/100.7)

R1721PSR003.docx

28

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

See Figure 7.

Figure 7 – Section of Scenic Drive, south of Cher‐Ae Lane, showing slopes falling into Scenic Drive, and existing

pavement in poor condition.

Alternative 4A improvements include:

Widening and/or reconstruction of Scenic Drive to provide 4 foot minimum shoulders and

sidewalk on one side

(1) Purpose and Need: Alternative 4A does not meet the purpose and need for this project.

Improvements to Scenic Drive from the community of Westhaven, to Main Street in the City of

Trinidad, will improve the safety and reliability of Scenic Drive, but will not sufficiently address any

of the requirements of the purpose and need for the study.

(2) Traffic Operations: Alternative 4A includes improvements to Scenic Drive, from the community

of Westhaven, to Main Street in the City of Trinidad. These improvements will have little effect on

the overall traffic operations within the study area. Upon full build‐out of the Trinidad Rancheria

Master Plan, conditions for the Trinidad‐Main Street interchange will operate at unacceptable levels

of service, as outlined in the Traffic Operations section above.

(3) Increased Safety: Alternative 4A will improve Scenic Drive, between the community of

Westhaven and Main Street. This will increase the safety of Scenic Drive through this segment, but

increased safety for this alternative is significantly lower than most other alternatives.

(4) Project Costs: Total Capital Outlay project costs for Alternative 4A are estimated at $22.0 million,

which is significantly higher than what would be expected for projects of similar size and nature, and

is in the low‐range of estimated costs for all alternatives. Costs estimated for this alternative are

increased significantly due to multiple areas along Scenic Drive that will require extensive grading

and retaining wall work due to existing topography along the roadway. Much of Scenic Drive

R1721PSR003.docx

29

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

includes steep slopes down to the ocean on the west side of Scenic Drive, and steep slopes upwards

to the east of Scenic Drive. See Appendix E for the preliminary project cost estimate worksheet.

(5) Environmental Impacts: It is anticipated that Alternative 4A will have a medium amount of

environmental impacts, since it includes improvements to an existing roadway. It is likely that

impacts would include existing environmental resources within the project limit. Some existing

drainage features, including culverts and drainage ditches/streams will need modification or

mitigation. There are up to 4‐5 existing streams within the Scenic Drive corridor that would likely

require modification or mitigation. Extensive grading for this alternative will likely impact other

environmentally sensitive areas. In addition, there is potential to discover cultural resources in the

vicinity of the project. This alternative is in the mid‐range of environmental impacts as compared to

other alternatives, since the footprint is increased only slightly because the project area is an existing

roadway.

(6) Right‐of‐Way Impacts: Right‐of‐Way impacts for Alternative 4A will be lower than other

alternatives included in this study. Since the roadway already exists, R/W impacts are expected to be

limited to small takes along Scenic Drive for grading modifications. It is estimated that 20 parcels

may be affected adjacent to Scenic Drive along this corridor, with impacts mostly including sliver

R/W acquisitions. See Section 8 and Appendix D for the right‐of‐way impact summary and exhibit.

(7) Aesthetics: Alternative 4A will have somewhat low impacts to aesthetics as compared to other

project alternatives. The main impacts to aesthetics include the extensive retaining wall work that is

anticipated for this work. Overall the impacts to Aesthetics are lower than most other alternatives.

(8) Design Exceptions: A design standards check and Design Standards Risk Assessment was not

fully performed for Alternative 4A, since the project consists only of reconstruction/improvements to

an existing roadway, along an existing local road corridor. It is anticipated that the project would

have various exceptions to design standards. The Design Standards Risk Assessment for this

alternative will be further addressed in the PA&ED phase.

Alternative 4B

Improve Scenic Drive from Cher‐Ae Lane; New Frontage Road

from Westhaven to Cher‐Ae Lane:

 Improve Scenic Drive from Cher‐Ae Lane to Trinidad

 Construct new frontage road from US 101 in the

Community of Westhaven to Cher‐Ae Lane

Alternative 4B includes widening of Scenic Drive from Cher‐Ae Lane to Main Street in the City of

Trinidad, and construction of a new frontage road from US 101 in the Community of Westhaven to Cher‐

Ae Lane.

Alternative 4B improvements include:

Widening and/or reconstruction of Scenic Drive from Cher‐Ae Lane to Trinidad, to provide 4

foot minimum shoulders and sidewalk on one side

Construction of a new frontage road from US 101 in the Community of Westhaven to Cher‐Ae

Lane

R1721PSR003.docx

30

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

(1) Purpose and Need: Alternative 4B does not meet the purpose and need for this project.

Improvements to Scenic Drive from Cher‐Ae Lane to Main Street, and a new frontage road from the

community of Westhaven to Cher‐Ae Lane will improve the safety and reliability of the access to the

Trinidad Rancheria, but will not sufficiently address any of the requirements of the purpose and need

for the study. This alternative will not reconnect tribal lands, and will not accommodate the planned

future development in the area.

(2) Traffic Operations: Alternative 4B includes improvements to Scenic Drive, from Cher‐Ae Lane

to Main Street in the City of Trinidad, and a new frontage road from the community of Westhaven to

Cher‐Ae Lane. These improvements will have some effect on the overall traffic operations within the

study area. However, upon full build‐out of the Trinidad Rancheria Master Plan, conditions for the

Trinidad‐Main Street interchange will continue to operate at unacceptable levels of service, as

outlined in the Traffic Operations section above.

(3) Increased Safety: Alternative 4B will improve Scenic Drive from Cher‐Ae Lane to Main Street,

and provide a new frontage road to the community of Westhaven to the south. This will increase the

safety of access routes to the Trinidad Rancheria and surrounding community, but overall increases

in safety for this alternative are still significantly lower than most other alternatives.

(4) Project Costs: Total Capital Outlay project costs for Alternative 4B are estimated at $31.7 million,

which is significantly higher than what would be expected for projects of similar size and nature, and

is in the mid‐range of estimated costs for all alternatives. Costs estimated for this alternative are

increased significantly due to some extensive grading and retaining wall work along Scenic Drive

north of Cher‐Ae Lane, as well as significant grading, retaining walls, clearing and grubbing work,

and R/W acquisition within the area proposed along US 101 for this alternative. See Appendix E for

the preliminary project cost estimate worksheet.

(5) Environmental Impacts: It is anticipated that Alternative 4B will have a high amount of

environmental impacts, since it includes improvements to a completely undeveloped area adjacent to

US 101, between the community of Westhaven and the Trinidad Rancheria. It is likely that impacts

would include existing environmental resources within the project limit. Some existing drainage

features, including culverts and drainage ditches/streams will need modification or mitigation. There

are multiple existing drainage ways along this stretch that could require up to 50‐60 foot fills, along

with excavation of similar amounts in multiple areas. In addition, there is a high potential to

discover cultural resources in the vicinity of this proposed frontage road. This alternative is in the

very high range of environmental impacts as compared to other alternatives, since the footprint

includes construction of a new roadway within a completely undeveloped area adjacent to US 101,

south of Cher‐Ae Lane.

(6) Right‐of‐Way Impacts: Right‐of‐Way impacts for Alternative 4B will be in the high range as

compared to other alternatives included in this study. R/W impacts for Scenic Drive from Cher‐Ae

Lane to Main Street will be similar to other alternatives, and will include small partial acquisitions.

R/W impacts for the new frontage road along US 101 will be significant, and would likely require

multiple acquisitions of full parcels within this corridor, along with multiple partial acquisitions of

parcels adjacent to US 101. It is estimated that 10‐15 parcels may be affected adjacent to the Scenic

Drive corridor, with impacts mostly including sliver R/W acquisitions. It is estimated that 15‐20

parcels may be affected with the proposed frontage road from Westhaven to Cher‐Ae Lane, with

many of the acquisitions requiring full parcel takes. See Section 8 and Appendix D for the right‐of‐

way impact summary and exhibit.

R1721PSR003.docx

31

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

(7) Aesthetics: Alternative 4B will have medium impacts to aesthetics as compared to other project

alternatives. The main impact to aesthetics will be the new frontage road that parallels US 101 from

Westhaven to Cher‐Ae Lane, to include removal of significant amounts of trees and vegetation, as

well as significant grading and slopes along this segment of new roadway.

(8) Design Exceptions: A design standards check and Design Standards Risk Assessment was not

fully performed for Alternative 4B, since the project consists of reconstruction/improvements to an

existing roadway, and a new local road facility adjacent to US 101, south of Cher‐Ae Lane. It is

anticipated that the project would have various exceptions to design standards. The Design

Standards Risk Assessment for this alternative will be further addressed in the PA&ED phase.

Alternative 5A

Improvements to Main Street with Signalized Intersections and

Construction of a new Cher‐Ae Lane Overcrossing:

 Four traditional signalized intersections

 Replacement of the Trinidad‐Main Street Interchange

 Widen Main Street from Scenic Drive to Westhaven Drive

 Widen Scenic Drive from Cher‐Ae Lane to Main Street

 Construct new overcrossing at Cher‐Ae Lane

Alternative 5A is a combination of Alternative 1A and 2, and includes Improvements to Main Street with

signalized intersections, replacement of the Trinidad‐Main Street Interchange (PM 100.7), widening of

Main Street from Scenic Drive to Westhaven Drive, widening of Scenic Drive from Cher‐Ae Lane to Main

Street in the City of Trinidad (PM 100.0 – 101.1), and construction of a new overcrossing structure at

Cher‐Ae Lane (PM 100.0), with local road connections to Scenic Drive and Westhaven Drive.

See previous Figures 2 and 4.

Alternative 5A improvements include:

Construction of traffic signals at each of the four intersections at this location

Reconstruction and widening of Main Street to accommodate future traffic demands

Reconstruction of the Main Street profile to meet current design standards

Construction of a new US 101 undercrossing structure to accommodate the widened Main Street

Reconstruction of the US 101 on and off‐ramps to accommodate future traffic demands

Reconstruction of US 101 mainline to provide a minimum 12 foot wide median and 10 foot

shoulders

Reconstruction of US 101 mainline profile to meet current decision sight distance standards

Widening and/or reconstruction of Scenic Drive to provide 4 foot minimum shoulders and

sidewalk on one side

Construction of a new overcrossing structure at PM 100.0

Reconstruction of Cher‐Ae Lane from Scenic Drive into the Rancheria

Construction of the Cher‐Ae Lane Extension to Westhaven Drive

Widening of Westhaven Drive from the Community of Westhaven to the City of Trinidad

Reconstruction of adjacent roadways to tie in to existing improvements

(1) Purpose and Need: Alternative 5A appears to meet the purpose and need for this project.

Improvements to the Trinidad‐Main Street Interchange, along with a new overcrossing structure at

R1721PSR003.docx

32

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

Cher‐Ae Lane, would accommodate the planned future development in the area, would provide for a

2nd safe and sustainable access to the Trinidad Rancheria, and would also reconnect tribal lands

across US 101.

(2) Traffic Operations: Alternative 5A includes improvements to the US 101/Trinidad‐Main Street

interchange, as well as Scenic Drive, and a new overcrossing structure at Cher‐Ae Lane, which would

result in improved traffic operations, and would provide for acceptable levels of service for the 3

intersections that would otherwise perform at unacceptable levels of service.

(3) Increased Safety: Alternative 5A will widen the median and shoulders on US 101, and would

chiefly construct the proposed improvements to current standards (See Section 8). Scenic Drive,

between Cher‐Ae Lane and Main Street, will also be improved, as will Westhaven Drive from the

community of Westhaven to Trinidad. These improvements will likely result in increased public

safety.

(4) Project Costs: Total Capital Outlay project costs for Alternative 5A are estimated at $48.0 million,

which is somewhat higher than expected for projects of similar size and nature, and has the highest

estimated cost of all alternatives. The additional project costs can be attributed to replacement of the

Trinidad‐Main Street Interchange (PM 100.7), extensive grading work and significant retaining wall

work. See Appendix E for the preliminary project cost estimate worksheet.

(5) Environmental Impacts: It is anticipated that Alternative 5A will have some minor impacts to

existing environmental facilities within the Trinidad‐Main Street Interchange area, along with more

significant impacts to the areas adjacent to US 101 at Cher‐Ae Lane. Existing drainage features,

including culverts and drainage ditches/streams, will need modification or mitigation. The area east

of US 101 near the Trinidad Rancheria is mostly undeveloped, and has an increased potential of

various environmental impacts. In addition, there is potential to discover cultural resources in the

vicinity of the project. This alternative is in the high range of environmental impacts as compared to

other alternatives.

(6) Right‐of‐Way Impacts: Due to the extensive grading and vertical profile changes in the Trinidad‐

Main Street interchange area, along with a new overcrossing structure at Cher‐Ae Lane, it is

anticipated that significant right‐of‐way acquisition will be required for Alternative 5A. Right‐of‐way

acquisition is expected to be limited to partial takes in areas where roads are widened, or extensive

grading must be done to allow for adequate sight distance or to meet other standards. Much of the

R/W that will be required for this project in the Cher‐Ae Lane area is land already owned by the

Trinidad Rancheria, which will significantly decrease the overall R/W impacts. It is estimated that 7‐

10 parcels may be affected adjacent to the US 101/Trinidad‐Main Street interchange, 10‐12 parcels

may be affected adjacent to US 101 in the Cher‐Ae Lane area for the overcrossing, and 10‐15 parcels

could be affected along Scenic Drive between Cher‐Ae Lane and Main Street.

(7) Aesthetics: Alternative 5A will significantly alter the existing rural and unique character of the

Trinidad‐Main Street interchange. The drastic change is likely to be considered incompatible with

the rural fishing village character of the City of Trinidad, and the City’s Draft General Plan.

Alternative 5A will also alter the US 101 corridor with construction of a new overcrossing structure.

This impact will also be significant for the area, but will be similar to existing interchanges and

overcrossing structures along the US 101 corridor.

(8) Design Exceptions: The preliminary design and design standards were checked using the DIB 78

Design Checklist and a draft Design Standards Risk Assessment was completed for Alternative 5A,

with various exceptions to design standards anticipated. The anticipated exceptions to design

R1721PSR003.docx

33

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

standards for Alternative 5A will be identical to those presented for Alternatives 1A and 2. The

Design Standards Risk Assessment for this alternative will be further addressed in the PA&ED phase.

Alternative 5B

Improvements to Main Street with Roundabouts and

Construction of a new Cher‐Ae Lane Overcrossing:

 Construct two large scale modern roundabouts

 Reconstruct on and off‐ramps

 Widen Scenic Drive from Cher‐Ae Lane to Main Street

 Construct new Cher‐Ae Lane Overcrossing

Alternative 5B is a combination of Alternative 1B and 2, and includes improvements to Main Street with

modern roundabouts, including reconstruction of the on and off‐ramps, reconstruction of Main Street,

widening of Scenic Drive from Cher‐Ae Lane to Main Street in the City of Trinidad (PM 100.0 – 101.1),

and construction of a new overcrossing structure at Cher‐Ae Lane (PM 100.0), with local road connections

to Scenic Drive and Westhaven Drive.

See previous Figures 3 and 4.

Alternative 5B improvements include:

Construction of two large modern roundabouts at the interchange

Reconstruction of Main Street to accommodate future traffic demands

Reconstruction of the US 101 on and off‐ramps

Widening and/or reconstruction of Scenic Drive to provide 4 foot minimum shoulders and

sidewalk on one side

Construction of a new overcrossing structure at PM 100.0

Reconstruction of Cher‐Ae Lane from Scenic Drive into the Rancheria

Construction of the Cher‐Ae Lane Extension to Westhaven Drive

Widening of Westhaven Drive from the Community of Westhaven to the City of Trinidad

Reconstruction of adjacent roadways to tie in to existing improvements

(1) Purpose and Need: Alternative 5B appears to meet the purpose and need for this project.

Improvements to the Trinidad‐Main Street Interchange, along with a new overcrossing structure at

Cher‐Ae Lane, would accommodate the planned future development in the area, would provide for a

2nd safe and sustainable access to the Trinidad Rancheria, and would also reconnect tribal lands

across US 101.

(2) Traffic Operations: Alternative 5B includes improvements to the US 101/Trinidad‐Main Street

interchange, as well as Scenic Drive, and a new overcrossing structure at Cher‐Ae Lane, which would

result in improved traffic operations, and would provide for acceptable levels of service for the 3

intersections that would otherwise perform at unacceptable levels of service.

(3) Increased Safety: Alternative 5B will widen the shoulders on US 101 within the immediate

project area, and would chiefly construct the proposed improvements to current standards (See

Section 8). Scenic Drive, between Cher‐Ae Lane and Main Street, will also be improved, as will

Westhaven Drive from the community of Westhaven to Trinidad. These improvements will likely

result in increased public safety.

R1721PSR003.docx

34

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

(4) Project Costs: Total Capital Outlay project costs for Alternative 5B are estimated at $31.5 million,

which is similar to what would be expected for projects of similar size and nature, and is in the mid‐

range of estimated costs for all alternatives. The cost estimate provided for this alternative assumes

significantly less reconstruction of US 101 adjacent to the Trinidad‐Main Street interchange, as well as

allowing the existing undercrossing structure to remain in place. The median is not widened with

this alternative, since the existing structure would remain in place, and there would not be adequate

decision sight distance (DSD) from US 101 to the northbound off‐ramp to Main Street without

reconstruction of US 101 similar to alternative 5A. To replace the existing structure and reconstruct

US 101 to meet the DSD standard, estimated costs for Alternative 5B would be similar to Alternative

5A, around $47.8 million. See Appendix E for the preliminary project cost estimate worksheet.

(5) Environmental Impacts: It is anticipated that Alternative 5B will have some minor impacts to

existing environmental facilities within the Trinidad‐Main Street Interchange area, along with more

significant impacts to the areas adjacent to US 101 at Cher‐Ae Lane. Existing drainage features,

including culverts and drainage ditches/streams, will need modification or mitigation. The area east

of US 101 near the Trinidad Rancheria is mostly undeveloped, and has an increased potential of

various environmental impacts. In addition, there is potential to discover cultural resources in the

vicinity of the project. This alternative is in the high range of environmental impacts as compared to

other alternatives.

(6) Right‐of‐Way Impacts: Due to the extensive grading and vertical profile changes in the Trinidad‐

Main Street interchange area, along with a new overcrossing structure at Cher‐Ae Lane, it is

anticipated that significant right‐of‐way acquisition will be required for Alternative 5B. The

extensive reconstruction in the Trinidad‐Main Street interchange area would likely require some full

R/W acquisition for adjacent parcels east of US 101, and northeast of Westhaven Drive, similar to

Alternative 1B. Much of the R/W that will be required for this project in the Cher‐Ae Lane area is

land already owned by the Trinidad Rancheria, which will significantly decrease the overall R/W

impacts. It is estimated that 7‐10 parcels may be affected adjacent to the US 101/Trinidad‐Main Street

interchange, 10‐12 parcels may be affected adjacent to US 101 in the Cher‐Ae Lane area for the

overcrossing, and 10‐15 parcels could be affected along Scenic Drive between Cher‐Ae Lane and

Scenic Drive. See Section 8 and Appendix D for the right‐of‐way impact summary and exhibit.

(7) Aesthetics: Alternative 5B will significantly alter the existing rural and unique character of the

Trinidad‐Main Street interchange. The drastic change is likely to be considered incompatible with

the rural fishing village character of the City of Trinidad, and the City’s Draft General Plan.

Alternative 5B will also alter the US 101 corridor with construction of a new overcrossing structure.

This impact will also be significant for the area, but will be similar to existing interchanges and

overcrossing structures along the US 101 corridor.

(8) Design Exceptions: The preliminary design and design standards were checked using the DIB 78

Design Checklist and a draft Design Standards Risk Assessment was completed for Alternative 5B,

with various exceptions to design standards anticipated. The anticipated exceptions to design

standards for Alternative 5B will be identical to those presented for Alternatives 1B and 2. The

Design Standards Risk Assessment for this alternative will be further addressed in the PA&ED phase.

R1721PSR003.docx

35

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

New US 101/Baker Ranch Road Interchange (PM 99.6):

Alternative 6

 Construct new US 101/Baker Ranch Road Interchange

 Local road connection to Scenic Drive and Westhaven Drive

 Widen Scenic Drive from Cher‐Ae Lane to Main Street

 Widen Westhaven Drive from Westhaven to Trinidad

 New frontage road from Baker Ranch Road to Cher‐Ae

Lane

Alternative 6 includes construction of a new Type L‐1 Compact Diamond interchange at Baker Ranch

Road (PM 99.6), with both northbound and southbound ramp connections, local road connections to

Scenic Drive and Westhaven Drive, widening of Scenic Drive from Cher‐Ae Lane to Main Street in the

City of Trinidad, widening of Westhaven Drive in the Community of Westhaven to Main Street in the

City of Trinidad (PM 98.1 – 100.7), and construction of a new frontage road from Baker Ranch Road to

Cher‐Ae Lane.

See Figure 8.

Figure 8 ‐ Alternative 6 Schematic Exhibit

Alternative 6 improvements include:

Construction of a new Type L‐1 Compact Diamond interchange at PM 99.6

Construction of all northbound and southbound ramp connections

Reconstruction of Baker Ranch Road east of US 101

Construction of Baker Ranch Road from US 101 to Westhaven Drive

Construction of a new frontage road from Baker Ranch Road to Cher‐Ae Lane

Widening and/or reconstruction of Scenic Drive to provide 4 foot minimum shoulders and

sidewalk on one side

Widening of Westhaven Drive from the Community of Westhaven to the City of Trinidad

(1) Purpose and Need: Alternative 6 does not meet the purpose and need for this project. A new

interchange at Baker Ranch Road, with connections to US 101, and public road connections to Scenic

R1721PSR003.docx

36

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

Drive and Westhaven Drive would provide only 2 of 3 of the requirements of the purpose and need

outlined in this study. The new interchange would provide for a 2nd safe and sustainable access to

and from US 101, for all modes of transportation, to the Trinidad Rancheria and the surrounding

communities, and it would accommodate the planned future development in the area. This new

interchange at Baker Ranch Road would not reconnect tribal lands across US 101 in the Trinidad

Rancheria area, and therefore does not meet the purpose and need.

(2) Traffic Operations: Alternative 6 includes construction of a new interchange at Baker Ranch

Road (PM 99.6), with an overcrossing structure over US 101, public road connections to Scenic Drive

and Westhaven Drive, frontage road between Baker Ranch Road and Cher‐Ae Lane, as well as

improvements to Scenic Drive from Baker Ranch Road to Trinidad, and for the length of Westhaven

Drive from the community of Westhaven to Trinidad. These improvements would result in improved

traffic operations within the study area. If constructed, and upon full build‐out of the Trinidad

Rancheria Master Plan, it is possible that this alternative may improve traffic operations enough to

provide acceptable levels of service for the entire study area. Additional analysis may be required to

fully determine if this alternative would provide for acceptable LOS for the study area.

(3) Increased Safety: Alternative 6 will widen the median and shoulders on US 101, and would

chiefly construct the proposed improvements to current standards. Scenic Drive, between Baker

Ranch Road and Main Street, will also be improved, along with Westhaven Drive from the

community of Westhaven to Trinidad. A new frontage road would be provided between Baker

Ranch Road and Cher‐Ae Lane, thereby creating a 2nd access point to the Trinidad Rancheria. These

improvements will likely result in increased public safety within the study area.

(4) Project Costs: Total Capital Outlay project costs for Alternative 6 are estimated at $39.6 million,

which is significantly higher than what would be expected for an interchange project of similar size

and nature, and is in the high‐range of estimated costs for all alternatives. Costs estimated for this

alternative are increased due to areas that will require extensive grading, retaining wall work,

clearing and grubbing work, R/W acquisition within the proposed interchange area, and frontage

road between Baker Ranch Road and Cher‐Ae Lane. See Appendix E for the preliminary project cost

estimate worksheet.

(5) Environmental Impacts: It is anticipated that Alternative 6 will have the highest amount of

environmental impacts of all the alternatives studied, since it includes construction of a new

roadway, construction of a full new interchange, as well as construction of a new frontage road

adjacent to US 101. It is very likely that impacts would include existing environmental resources

within the project limit. Some existing drainage features, including culverts and drainage

ditches/streams will need modification or mitigation. There are multiple existing drainage ways

along this stretch that could require up to 50‐60 foot fills, along with excavation of similar amounts to

provide for an acceptable vertical profile of the new Baker Ranch Road segment. The area that

includes the new interchange and on and off‐ramps is also mostly undeveloped, and will likely have

impacts to existing environmentally sensitive areas. In addition, there is potential to discover cultural

resources in the vicinity of the project. This alternative is anticipated to have the most environmental

impacts of all alternatives analyzed for this study.

(6) Right‐of‐Way Impacts: Right‐of‐Way impacts for this alternative will also likely be the highest of

all alternatives, since the project will construct a new roadway across US 101, as well as new ramp

connections to US 101, thereby requiring acquisition of R/W for the full width of the roadway, ramps,

and associated improvements, including grading. Much of this area includes very steep terrain,

which will likely require additional R/W acquisition to provide for grading. Additional R/W will also

likely be required along the new frontage road from Baker Ranch Road to Cher‐Ae Lane. It is

R1721PSR003.docx

37

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

estimated that 25‐35 parcels may be affected in the Baker Ranch Road interchange area, as well as 15‐

20 parcels along Scenic Drive. See Section 8 and Appendix D for the right‐of‐way impact summary

and exhibit.

(7) Aesthetics: Alternative 6 will alter the US 101 corridor with construction of a new interchange,

similar to Alternatives 3A and 3B. While this impact will be significant for the area, a new

interchange will be similar to existing interchanges and overcrossing structures along the US 101

corridor.

(8) Design Exceptions: A design standards check was performed for Alternative 6, at a lesser degree

than Alternatives 1A, 1B, 2, 3A, 3B, 5A, and 5B. It is anticipated that various exceptions to design

standards would be required. One of the concerns with regards to design standards would be the

vertical design standards. A preliminary vertical profile for the Baker Ranch Road connection from

Scenic Drive to Westhaven Drive includes grades near 15%, while holding grades within the

interchange area at 4% +/‐ to meet interchange standards. The Design Standards Risk Assessment for

this alternative will be further addressed in the PA&ED phase.

Alternative 7

New Cher‐Ae Lane Overcrossing (PM 100.0); New Frontage

Road from Westhaven to Cher‐Ae Lane:

 Construct new Cher‐Ae Lane Overcrossing

 Local road connection to Scenic Drive and Westhaven Drive

 Improve Scenic Drive from Cher‐Ae Lane to Trinidad

 Widen Westhaven Drive from Westhaven to Trinidad

 Construct new frontage road from US 101 in the

Community of Westhaven to Cher‐Ae Lane

Alternative 7 is a combination of Alternative 2 and Alternative 4B, and includes construction of a new

overcrossing structure at Cher‐Ae Lane (PM 100.0), with local road connections to Scenic Drive and

Westhaven Drive, widening of Scenic Drive from Cher‐Ae Lane to Main Street in the City of Trinidad,

widening of Westhaven Drive in the Community of Westhaven to Main Street in the City of Trinidad,

and construction of a new frontage road from Westhaven to Cher‐Ae Lane.

See previous Figure 4.

Alternative 7 improvements include:

Construction of a new overcrossing structure at PM 100.0

Reconstruction of Cher‐Ae Lane from Scenic Drive into the Rancheria

Construction of the Cher‐Ae Lane Extension to Westhaven Drive

Widening and/or reconstruction of Scenic Drive to provide 4 foot minimum shoulders and

sidewalk on one side

Widening of Westhaven Drive from the Community of Westhaven to the City of Trinidad

Construction of a new frontage road from Westhaven to Cher‐Ae Lane

(1) Purpose and Need: Alternative 7 does not meet the purpose and need for this project. A new

overcrossing structure without a connection to US 101, along with a new frontage road from

R1721PSR003.docx

38

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

Westhaven to Cher‐Ae Lane would provide for 2 of the 3 items of the purpose and need. The new

overcrossing and frontage road would provide for a 2nd safe and sustainable access to the Trinidad

Rancheria, and would also reconnect tribal lands across US 101. But these improvements will not

accommodate the planned future development in the area, and thus, does not meet the purpose and

need.

(2) Traffic Operations: Alternative 7 includes construction of a new overcrossing structure over US

101 at Cher‐Ae Lane, a new frontage road from Westhaven to Cher‐Ae Lane, as well as

improvements to Scenic Drive and Westhaven Drive, that would result in slightly improved traffic

operations. However, without any improvements to any of the interchange areas, and without a

direct connection to US 101, conditions for the Trinidad‐Main Street interchange will remain at

unacceptable levels of service, as outlined in the Traffic Operations section above.

(3) Increased Safety: Alternative 7 will not provide any improvements to US 101, but will provide

improvements to Scenic Drive and Westhaven Drive, and provide a 2nd safe access between

Westhaven and Cher‐Ae Lane. Therefore, increased safety would be expected on Scenic Drive, from

Cher‐Ae Lane to Trinidad, along the length of Westhaven Drive, and along the new frontage road.

However, overall increased safety for the project study area would be minimal.

(4) Project Costs: Total Capital Outlay project costs for Alternative 7 are estimated at $39.5 million,

which is significantly higher than what would be expected for a project of similar size and nature,

and is in the high‐range of estimated costs for all alternatives. Similar to estimated costs for

Alternative 4B, estimated costs for this alternative include amounts for significant grading, retaining

walls, clearing and grubbing work, and R/W acquisition within the area proposed along US 101

between Westhaven and the Trinidad Rancheria for the new frontage road. See Appendix E for the

preliminary project cost estimate worksheet.

(5) Environmental Impacts: It is anticipated that Alternative 7 will have similar environmental

impacts to combining Alternatives 2 and 4B. Environmental impacts will be very high, and in the

high range for all of the alternatives analyzed for this study. For additional environmental discussion

on this alternative, see Alternatives 2 and 4B above.

(6) Right‐of‐Way Impacts: It is anticipated that Alternative 7 will have similar R/W impacts to

combining Alternatives 2 and 4B. R/W impacts will be somewhat high, and in the high range for all

of the alternatives analyzed for this study. For additional R/W impact discussion on this alternative,

see Alternatives 2 and 4B above. See Section 8 and Appendix D for the right‐of‐way impact

summary and exhibit.

(7) Aesthetics: Alternative 7 will alter the US 101 corridor with construction of a new overcrossing at

Cher‐Ae Lane. While this impact will be significant for the area, a new interchange will be similar to

existing interchanges and overcrossing structures along the US 101 corridor. Similar to Alternative

4B, the new frontage road will have significant impacts on aesthetics along this corridor, to include

removal of significant amounts of trees and vegetation, as well as significant grading and slopes

along this segment of new roadway.

(8) Design Exceptions: A design standards check and Design Standards Risk Assessment were not

performed specifically for Alternative 7. Design exception discussions for this alternative are

included in the Alternative 2 and 4B sections. The Design Standards Risk Assessment for this

alternative will be further addressed in the PA&ED phase.

R1721PSR003.docx

39

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

New US 101/1.0 Mile Spacing Interchange (PM 99.7):

Alternative 8

 Construct new US 101/1.0 Mile Spacing Interchange

 Local road connection to Cher‐Ae Lane and Westhaven

Drive

 Widen Scenic Drive from Cher‐Ae Lane to Main Street

 Widen Westhaven Drive from Westhaven to Trinidad

Alternative 8 includes construction of a new Type L‐1 Compact Diamond interchange approximately 1

mile south of the US 101/Trinidad‐Main Street Interchange (PM 100.7), with both northbound and

southbound ramp connections, local road connections to Cher‐Ae Lane and Westhaven Drive, widening

of Scenic Drive from Cher‐Ae Lane to Main Street in the City of Trinidad, and widening of Westhaven

Drive in the Community of Westhaven to Main Street in the City of Trinidad (PM 98.1 – 100.7).

See Figure 9.

Figure 9 ‐ Alternative 8 Schematic Exhibit

Alternative 8 improvements include:

Construction of a new Type L‐1 Compact Diamond interchange at PM 99.7

Construction of all northbound and southbound ramp connections

Construction of a new road from Cher‐Ae Lane to Westhaven Drive

Widening and/or reconstruction of Scenic Drive to provide 4 foot minimum shoulders and

sidewalk on one side

Widening of Westhaven Drive from the Community of Westhaven to the City of Trinidad

(1) Purpose and Need: Alternative 8 appears to meet the purpose and need for this project. A new

interchange 1 mile south of the existing US 101/Trinidad‐Main Street Interchange, with connections to

US 101, and public road connections to Cher‐Ae Lane and Westhaven Drive would provide for all of

the purpose and need requirements outlined in this study. The new interchange would provide for a

2nd safe and sustainable access to and from US 101, for all modes of transportation, to the Trinidad

R1721PSR003.docx

40

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

Rancheria and the surrounding communities, accommodate the planned future development in the

area, and would also reconnect tribal lands across US 101.

(2) Traffic Operations: Alternative 8 includes construction of a new US 101 interchange (PM 99.7) at

approximately 1.0 mile south of the existing US 101/Trinidad‐Main Street Interchange (PM 100.7),

with an overcrossing structure over US 101, public road connections to Cher‐Ae Lane and Westhaven

Drive, as well as improvements to Scenic Drive from Cher‐Ae Lane to Trinidad, and for the length of

Westhaven Drive from the community of Westhaven to Trinidad. These improvements would result

in improved traffic operations within the study area. If constructed, and upon full build‐out of the

Trinidad Rancheria Master Plan, it is projected that this alternative would improve traffic operations

enough to provide acceptable levels of service for the entire study area. Additional analysis may be

needed to fully determine if this alternative would provide for acceptable LOS for the entire study

area.

(3) Increased Safety: Alternative 8 will widen the median and shoulders on US 101, and would

chiefly construct the proposed improvements to current standards (See Section 8). Scenic Drive,

between Cher‐Ae Lane and Main Street, will also be improved, along with Westhaven Drive from the

community of Westhaven to Trinidad. This alternative would provide a new stable crossing location

for US 101, as well as easier access to US 101 from Cher‐Ae Lane along a more stabilized roadway.

These improvements will likely result in increased public safety within the study area.

(4) Project Costs: Total Capital Outlay project costs for Alternative 8 are estimated at $32.6 million,

which is slightly higher than what would be expected for projects of similar size and nature, and is in

the mid‐range of estimated costs for all alternatives. Costs estimated for this alternative are increased

due to areas that will require some extensive grading and retaining wall work due to existing

topography. This additional cost is typical of nearly all of the alternatives that were analyzed with

this study, due to the highly variable terrain within the entire study area. See Appendix E for the

preliminary project cost estimate worksheet.

(5) Environmental Impacts: It is anticipated that Alternative 8 will have somewhat high

environmental impacts, since it includes construction of a new roadway, and construction of a full

new interchange. It is likely that impacts would include existing environmental resources within the

project limit. Some existing drainage features, including culverts and drainage ditches/streams will

need modification or mitigation. The areas both east and west of US 101 are mostly undeveloped,

and have an increased potential of various environmental impacts. The area that includes the new

interchange and on and off‐ramps is also mostly undeveloped, and will likely have impacts to

existing environmentally sensitive areas. In addition, there is potential to discover cultural resources

in the vicinity of the project. This alternative is in the high range of environmental impacts as

compared to other alternatives, since the footprint includes a road connection across US 101, along

with full ramp connections to US 101, and a longer roadway extension to Cher‐Ae Lane.

(6) Right‐of‐Way Impacts: Right‐of‐Way impacts for this alternative will also be somewhat high,

since the project will construct a new roadway across US 101, as well as new ramp connections to US

101, and a lengthy extension of new roadway connecting to Cher‐Ae Lane. R/W acquisition would be

required for the full roadway width and associated improvements, including grading and retaining

walls. Some of this area includes very steep terrain, which will likely require additional R/W

acquisition to provide for extensive grading. The roadway extension to Cher‐Ae Lane skirts privately

owned and Rancheria residential neighborhoods. It is estimated that 10‐15 parcels may be affected in

the interchange area, and another 10‐15 parcels may be affected along Scenic Drive; including impact

to a Rancheria residence and close proximity to two privately owned residences. See Section 8 and

Appendix D for the right‐of‐way impact summary and exhibit.

R1721PSR003.docx

41

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

(7) Aesthetics: Alternative 8 will alter the US 101 corridor with construction of a new interchange,

similar to Alternatives 3A and 3B. While this impact will be significant for the area, a new

interchange will be similar to existing interchanges and overcrossing structures along the US 101

corridor.

(8) Design Exceptions: A design standards check and Design Standards Risk Assessment were not

performed specifically for Alternative 8. Geometric features influencing design exception

requirements include vertical grades, minimum curve radii for the new road, cut slopes affecting

sight distance requirements, and interchange configuration. The Design Standards Risk Assessment

for this alternative will be further addressed in the PA&ED phase.

8. RIGHT OF WAY

All alternatives will require some amount of right of way acquisition to accommodate new or widened

roadways, new alignments and other improvements. Anticipated right of way acquisition for all

alternatives is summarized below. See Attachment D for right of way impact exhibits.

TABLE 10: RIGHT OF WAY ACQUISITION SUMMARY (ALTERNATIVE 1A)

Location (Number of Parcels)

General Description

Acres

West of US 101 at Trinidad‐Main I/C (3)

Commercial

0.4

East of US 101 at the Trinidad‐Main I/C (4)

Residential and Vacant

0.4

Scenic Drive north of Cher‐Ae Lane (15)

Residential and Vacant

1.7

TABLE 11: RIGHT OF WAY ACQUISITION SUMMARY (ALTERNATIVE 1B)

Location (Number of Parcels)

General Description

Acres

West of US 101 at Trinidad‐Main I/C (3)

Commercial

0.3

East of US 101 at the Trinidad‐Main I/C (4)

Residential and Vacant

2.7

Scenic Drive north of Cher‐Ae Lane (15)

Residential and Vacant

1.7

TABLE 12: RIGHT OF WAY ACQUISITION SUMMARY (ALTERNATIVE 2)

Location (Number of Parcels)

General Description

Acres

West of US 101 at Cher‐Ae Lane (6)

Residential and Tribal Government

2.3

East of US 101 at Cher‐Ae Lane (3)

Residential

2.3

Scenic Drive north of Cher‐Ae Lane (15)

Residential and Vacant

1.7

TABLE 13: RIGHT OF WAY ACQUISITION SUMMARY (ALTERNATIVE 3A)

Location (Number of Parcels)

General Description

Acres

West of US 101 at Cher‐Ae Lane (7)

Residential and Tribal Government

3.7

East of US 101 at Cher‐Ae Lane (10)

Residential

4.4

Scenic Drive north of Cher‐Ae Lane (15)

Residential and Vacant

1.7

R1721PSR003.docx

42

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

TABLE 14: RIGHT OF WAY ACQUISITION SUMMARY (ALTERNATIVE 3B)

Location (Number of Parcels)

General Description

Acres

Same as Alternative 3A

TABLE 15: RIGHT OF WAY ACQUISITION SUMMARY (ALTERNATIVE 4A)

Location (Number of Parcels)

General Description

Acres

Scenic Drive south of Cher‐Ae Lane (26)

Residential and Vacant

4.0

Scenic Drive north of Cher‐Ae Lane (15)

Residential and Vacant

1.7

TABLE 16: RIGHT OF WAY ACQUISITION SUMMARY (ALTERNATIVE 4B)

Location (Number of Parcels)

General Description

Acres

New Frontage Road south of Cher‐Ae Lane (18)

Residential

11.2

Scenic Drive north of Cher‐Ae Lane (15)

Residential and Vacant

1.7

TABLE 17: RIGHT OF WAY ACQUISITION SUMMARY (ALTERNATIVE 5A)

Location (Number of Parcels)

General Description

Acres

West of US 101 at Trinidad‐Main I/C (3)

Commercial

0.4

East of US 101 at the Trinidad‐Main I/C (4)

Residential and Vacant

0.4

Scenic Drive north of Cher‐Ae Lane (15)

Residential and Vacant

1.7

West of US 101 at Cher‐Ae Lane (6)

Residential and Tribal Government

2.3

East of US 101 at Cher‐Ae Lane (3)

Residential

2.3

TABLE 18: RIGHT OF WAY ACQUISITION SUMMARY (ALTERNATIVE 5B)

Location (Number of Parcels)

General Description

Acres

West of US 101 at Trinidad‐Main I/C (3)

Commercial

0.3

East of US 101 at the Trinidad‐Main I/C (4)

Residential and Vacant

2.7

Scenic Drive north of Cher‐Ae Lane (15)

Residential and Vacant

1.7

West of US 101 at Cher‐Ae Lane (6)

Residential and Tribal Government

2.3

East of US 101 at Cher‐Ae Lane (3)

Residential

2.3

TABLE 19: RIGHT OF WAY ACQUISITION SUMMARY (ALTERNATIVE 6)

Location (Number of Parcels)

General Description

Acres

West of US 101 at Baker Ranch Road (5)

Residential and Vacant

7.8

East of US 101 at Baker Ranch Road (9)

Residential and Vacant

9.2

Scenic Drive (19)

Residential and Vacant

2.8

R1721PSR003.docx

43

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

New Frontage Road between Baker Ranch

Road and Cher‐Ae Lane (15)

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

Residential and Vacant

7.5

TABLE 20: RIGHT OF WAY ACQUISITION SUMMARY (ALTERNATIVE 7)

Location (Number of Parcels)

General Description

Acres

West of US 101 at Cher‐Ae Lane (6)

Residential and Tribal Government

2.3

East of US 101 at Cher‐Ae Lane (3)

Residential

2.3

Scenic Drive north of Cher‐Ae Lane (15)

Residential and Vacant

1.7

New Frontage Road south of Cher‐Ae Lane (18)

Residential

11.2

Scenic Drive north of Cher‐Ae Lane (15)

Residential and Vacant

1.7

TABLE 21: RIGHT OF WAY ACQUISITION SUMMARY (ALTERNATIVE 8)

Location (Number of Parcels)

General Description

Acres

West of US 101 (8)

Residential and Tribal Government

5.0

East of US 101 (10)

Residential

5.7

Scenic Drive (15)

Residential and Vacant

1.7

Utilities

The following utilities may be impacted in various degrees by the project:

 City of Trinidad Water: Existing water facilities will be impacted and require relocation for

Alternatives 1A, 1B, 5A and 5B.

 City of Trinidad Sewer: Existing sewer facilities will be impacted and require relocation for

Alternatives 1A, 1B, 5A and 5B.

 AT&T: Existing AT&T facilities will be impacted for all alternatives.

 PG&E: Existing PG&E facilities will be impacted for all alternatives.

Railroad

There are not any railroad impacts or involvement.

9. STAKEHOLDER INVOLVEMENT

The Trinidad Rancheria held a 5‐day Design Fair for the Highway 101 I/C in May 2009, and held another

5‐day Design Fair in November 2010 for the Comprehensive Community‐Based Plan. Tribal members,

tribal council, community members, and City, County and State Officials shared their visions for

improving access to the Rancheria and the surrounding community. A design team of professional

architects, landscape architects, engineers, and environmental planners were also in attendance to

facilitate the public presentations and interactions. Construction of a new US 101/Cher‐Ae Lane I/C was

identified by the Rancheria as a core necessity.

The Project Development Team (PDT) includes staff representatives as attendees from Caltrans, Trinidad

Rancheria, City of Trinidad, Humboldt County, and Humboldt Council of Governments. The PDT team

has been instrumental in developing the purpose and need statement for the project, as well as

R1721PSR003.docx

44

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

identifying all of the alternatives studied to date, and guiding discussions relating to design exceptions

and this PSR‐PDS.

10. ENVIRONMENTAL DETERMINATION/DOCUMENT

The CEQA environmental document for the project is anticipated to be an Environmental Impact Report

(EIR) and the NEPA environmental document is anticipated to be a Finding of No Significant Impact

(FONSI).

A Preliminary Environmental Analysis Report (PEAR) was submitted for approval on November 30,

2015, with comments subsequently received and addressed. An updated PEAR is included in this PSR‐

PDS as Attachment H. The updated PEAR identifies the need for the following technical studies in

support of the environmental documents:

Community Impact Assessment.

Visual Impact Assessment.

Archeological Survey Report.

Historical Resources Evaluation Report.

Historic Property Survey Report.

Geotechnical Investigation.

Air Quality Analysis.

Greenhouse Gas Modeling.

Biological Assessment.

11. FUNDING

Capital Outlay Project Estimate:

The proposed project is anticipated to include some or all of the following funding sources: State

Transportation Improvement Program (STIP), Tribal Transportation Program (TTP), Indian Reservation

Roads (IRR), Active Transportation Program (ATP), Highway Safety Improvement Program (HSIP), and

Transportation Investment Generating Economic Recovery (TIGER).

The estimated range for capital outlay project costs for the alternatives are shown below. At the PSR‐PDS

phase, the anticipated capital outlay funding by source has not been determined.

TABLE 22 CAPITAL OUTLAY PROJECT COST ESTIMATE2

Alternative

Alternative 1A

Alternative 1B

Alternative 2

Alternative 3A

Alternative 3B

Alternative 4A

Alternative 4B

Alternative 5A

Alternative 5B

Alternative 6

Alternative 7

Alternative 8

R1721PSR003.docx

R/W Capital

($1,000’s)

Construction Capital

($1,000’s)

Total

($1,000’s)

$800

$1,290

$1,6001

$2,4101

$2,4101

$1,520

$3,070

$1,8201

$2,3401

$3,880

$2,8301

$3,0161

$38,020

$18,775

$16,586

$29,882

$28,846

$20,501

$28,596

$46,194

$29,199

35,735

$36,629

$29,585

$38,820

$20,065

$18,2061

$32,2921

$31,2561

$22,021

$31,666

$48,0141

$31,5391

$39,615

$39,4591

$32,6011

45

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

Note:

(1) Includes the estimated value of R/W currently under ownership of the Trinidad Rancheria, which will provide a

reduction in overall right‐of‐way impacts and costs.

Capital Outlay Support Estimate:

Cooperative Agreement Number 01‐0365 addresses the PID phase only. A Cooperative Agreement will

be required for the PA&ED phase. The Trinidad Rancheria is the project Sponsor with Caltrans

providing Quality Assurance. At the PA&ED phase, each partner will be responsible for their own costs.

The capital outlay support estimate for programming PA&ED in the 2018 STIP for this project is $2.5

million. The estimated resources by WBS Code for environmental studies during the PA&ED phase are

included as an attachment to the PEAR, with an estimated total of 15,354 person‐hours. This total

includes 15% for Caltrans oversight. The environmental studies are estimated to be two‐thirds of the

total resources required during the PA&ED phase (or ~$1.7M), while the engineering studies are

estimated to be the remaining one‐third (or ~$0.8M).

Of the $2.5 million total estimated for the PA&ED phase, $775,000 will come from STIP funding through

the Humboldt County Association of Governments (HCAOG), while the remaining funds, $1,725,000,

would come from Tribal Transportation Funds and/or Economic Development Funds.

12. DELIVERY SCHEDULE

TABLE 23 ESTIMATED PROJECT DELIVERY SCHEDULE

Project Milestones

Program Project

Begin Environmental (PA&ED) Phase

Notice of Intent (NOI)

Circulate Draft Environmental Document (DED) Externally

End Environmental (PA&ED) Phase

Begin Project Design (PS&E) Phase

Begin Right of Way Phase

End Right of Way Phase (Right of Way Certification)

End Project Design (PS&E) Phase (Ready to List)

Begin Construction Phase (Contract Award)

End Construction Phase (Contract Acceptance)

M015

M020

M035

M120

M200

M377

M377

M410

M460

M495

M600

Scheduled Delivery Date

July 1, 2018

July 1, 2018

November 1, 2018

January 1, 2021

July 1, 2022

July 1, 2022

July 1, 2022

February 1, 2024

March 1, 2024

July 1, 2024

July 1, 2026

13. RISKS

A risk assessment was performed for the project, and a Risk Register created. A total of eight (8) risks

were identified on the Risk Register, and include: (1) Funding, (2) EIR / EA., (3) Design Exceptions, (4)

Right of Way, (5) External Project Sponsor, (6) Public Controversy/Opposition, (7) Local Coastal

Amendment Approval, and (8) Litigation. The risks identified range from low risk for External Project

Sponsor, to very high risk for Public Controversy/Opposition and environmental related risks.

See Attachment I for the Risk Register and Risk Register Certification Page.

R1721PSR003.docx

46

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

14. FHWA COORDINATION

NEPA approval is anticipated to be from either the Office of Federal Lands Highway (FHWA) or the

Bureau of Indian Affairs.

It is also anticipated that the FHWA Office of Federal Lands Highway may be a funding partner.

15. PROJECT REVIEWS

District Maintenance __________________________________

District Traffic Operations _____________________________

District Traffic Safety Bryan Thomas_____________________

Headquarters Project Delivery Coordinator ________________

District Safety Review ________________________________

Date _________________

Date _________________

Date 11/16/15__________

Date _________________

Date _________________

16. PROJECT PERSONNEL

Name

Jacque Hostler‐Carmesin

Leslie Sanders

Kim Floyd, PE

Lena Ashley, PE

Russ Wenham, PE

Brandon Tenney, PE

Douglas DeMallie, PE

Title

Trinidad Rancheria CEO

Transp. Manager (Trinidad Rancheria)

Project Manager (Caltrans)

Design Engineer (Caltrans)

Project Manager (Omni‐Means, Ltd.)

Project Engineer (Omni‐Means, Ltd.)

Project Planner (Omni‐Means, Ltd.)

17. ATTACHMENTS

A.

B.

C.

D.

E.

F.

G.

H.

I.

J.

Location Map (1)

Preliminary Alternative Schematic Exhibits (15)

Structures Cost Estimates Memorandum (3)

Right of Way Impact Exhibits (7)

Project Cost Estimate Worksheets (36)

Storm Water Data Report Signature Page (1)

Transportation Management Plan (6)

Preliminary Environmental Analysis Report (PEAR) (26)

Risk Register and Certification Form (2)

Geotechnical Screening Report (4)

R1721PSR003.docx

47

Phone Number

707‐677‐0211

707‐825‐2738

707‐441‐5739

707‐445‐6602

530‐242‐1700

530‐242‐1700

530‐242‐1700

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

ATTACHMENT A

PROJECT LOCATION MAP

R1721PSR003.docx

48

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

ATTACHMENT B

PRELIMINARY ALTERNATIVE SCHEMATIC

EXHIBITS

R1721PSR003.docx

49

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

ATTACHMENT C

STRUCTURES COST ESTIMATES MEMORANDUM

R1721PSR003.docx

50

Morrison Structures

1890 Park Marina Drive, Ste 104

Redding, CA 96001

Structure Memorandum

From: Bob Morrison, Jr., S.E., Morrison Structures, Redding, California

To:

Russ Wenham, P.E, Omni Means, Redding, California

Date: November 21, 2017

Re:

US 101/Trinidad Area Access Improvements

HUM-101, PM 98.4/100.7

01-48040K

General

The purpose of this memorandum is to provide structure information for the proposed interchange

Alternatives 1A, 2, 3A, 3B, 5A, 5B, 6, 7, & 8 for the Trinidad Area Access Improvements Study project.

The level of study we have conducted is a Project Study Report-Project Development Support (PSR-PDS)

Cost Estimate. The purpose of this study is to determine preliminary scope, feasibility, rough cost range,

and a list of potential project risks for the proposed structures work.

Alternative 1A – Construct a replacement US 101/Main Street (Trinidad) Undercrossing

The existing US101/Trinidad Undercrossing (04-0058) is a 3-span, 125-foot-long, cast-in-place T-beam

bridge structure on column bents (3) and concrete abutments. The structure was constructed in 1960. The

bent columns are supported on spread footings, and the abutments on driven steel 45-ton piles. The

structure is located east of, or over the Trinidad fault on a hanging wall. Recent surface rupture studies

conducted by Caltrans indicate that surface rupture does not need to be further addressed. The studies

estimated that only a few inches of vertical separation will occur based on a 975 year return period and

using a probabilistic fault displacement analysis.

This proposed improvement intends to construct a replacement US 101/Main Street Undercrossing to

facilitate the improvement of Main Street in the City of Trinidad by widening the roadway and roadway

shoulders, raising profile grade, and adding pedestrian sidewalks. Also proposed are improvements to the

existing northbound and southbound US 101 on and off-ramps. In order to provide for widening and

raising Main Street, it will be necessary to replace the existing 3-span undercrossing. The existing bridge

is in fair condition, however its’ main span is of insufficient dimension to accommodate the wider Main

Street and its soffit elevation will not allow for raising Main Street’s profile grade beneath the structure.

Based on the conditions at the site and the interchange geometrics, the replacement undercrossing will be

a single-span structure approximately 99-feet in length and 86.33-feet in width. The most economical

structure type will likely be a precast, prestressed, concrete girder structure with a 5-foot structure depth.

Supports will be high-cantilever wall type abutments founded on driven piling. An increase in elevation

of US 101 on the order of 2.5-feet will be necessary to allow for a minimum of 15-feet vertical clear

distance from the bottom of soffit to Main Street. The undercrossing will be designed to accommodate a

Type 742 concrete left barrier, a 13.5-foot left shoulder, two 12-foot lanes of southbound traffic, a 5-foot

southbound median shoulder, a future Type 60 median barrier, a 5-foot northbound median shoulder, two

12-foot lanes of northbound traffic, a 10-foot right shoulder, and a Type 742 concrete right barrier.

Falsework is not necessary to erect this type of girder structure. Girders will be set in place from Main

Street using traffic closures.

1

The anticipated 2017 structure cost including bridge removal ($200,000), 10 percent for mobilization,

and 25 percent for contingencies is $6,818,000 which is $798/SF.

Alternatives 2, 5B, & 7 – Construct a new US 101/Cher-Ae Lane Overcrossing

This proposed improvement intends to construct a new Cher-Ae Lane Overcrossing of US 101 about 0.73

miles south of the Trinidad undercrossing. The new overcrossing will connect Scenic Drive, west of US

101, to Westhaven Drive, east of US 101.

Based on the conditions at the site and the roadway geometrics, the new overcrossing will be a singlespan structure approximately 132-feet in length and 47.3-feet in width. The most economical structure

type will likely be a precast, prestressed, concrete girder structure with a 6.3-foot structure depth.

Supports will be high-cantilever wall type abutments founded on driven piling. The overcrossing will be

designed to accommodate a Type 742 concrete left barrier, a 4-foot left shoulder, a 12-foot lane of

westbound traffic, a 12-foot lane of eastbound traffic, a 4-foot right shoulder, a 12.5-foot mixed use path,

and a Type 742 concrete right barrier. Falsework is not necessary to erect this type of girder structure.

Girders will be set in place from US 101 using traffic closures.

The anticipated 2017 structure cost including 10 percent for mobilization, and 25 percent for

contingencies is $4,074,000 which is $652/SF.

Alternatives 3A & 3B – Construct a new US 101/Cher-Ae Lane Interchange

This proposed improvement intends to construct a new Cher-Ae Lane Interchange with a new Cher-Ae

Lane Overcrossing of US 101 about 0.73 miles south of the Trinidad undercrossing. The new

overcrossing will connect Scenic Drive, west of US 101, to Westhaven Drive, east of US 101. New

northbound and southbound on and off-ramps will be constructed connecting US 101 to Cher-Ae Lane.

Based on the conditions at the site and the interchange geometrics, the new overcrossing will be a singlespan structure approximately 132 feet in length and 54.8 feet in width. The most economical structure

type will likely be a precast, prestressed, concrete girder structure with a 6.3-foot structure depth.

Supports will be high-cantilever wall type abutments founded on driven piling. The overcrossing will be

designed to accommodate a Type 742 concrete left barrier, an 8-foot left shoulder, a 12-foot lane of

westbound traffic, a 12-foot lane of eastbound traffic, an 8-foot right shoulder, a 12-foot mixed use path,

and a Type 742 concrete right barrier. Falsework is not necessary to erect this type of girder structure.

Girders will be set in place from US 101 using traffic closures.

The anticipated 2017 structure cost including 10 percent for mobilization, and 25 percent for

contingencies is $4,441,000 which is $614/SF.

Alternative 5A – Construct a replacement US 101/Main Street Undercrossing and a new

US101/Cher-Ae Lane Interchange

This proposed improvement intends to construct a replacement US 101/Main Street Undercrossing in

Trinidad and a new Cher-Ae Lane Interchange with a new Cher-Ae Lane Overcrossing of US 101 about

0.73 miles south of the Trinidad undercrossing. The replacement undercrossing structure includes

improvements to the existing northbound and southbound US 101 on and off-ramps. The new

overcrossing will connect Scenic Drive, west of US 101, to Westhaven Drive, east of US 101.

Based on the conditions at the sites and the site specific geometrics, the replacement undercrossing will

be a single-span structure approximately 99-feet in length and 86.33-feet in width while the new

overcrossing will be a single-span structure approximately 132-feet in length and 47.3-feet in width. The

most economical structure types will likely be precast, prestressed, concrete girders with 5-foot and 6.3foot structure depths respectively. Supports for both will be high-cantilever wall type abutments founded

on driven piling. The undercrossing will be designed to accommodate a Type 742 concrete left barrier, a

13.5-foot left shoulder, two 12-foot lanes of southbound traffic, a 5-foot southbound median shoulder, a

2

future Type 60 median barrier, a 5-foot northbound median shoulder, two 12-foot lanes of northbound

traffic, a 10-foot right shoulder, and a Type 742 concrete right barrier. The overcrossing will be designed

to accommodate a Type 742 concrete left barrier, a 4-foot left shoulder, a 12-foot lane of westbound

traffic, a 12-foot lane of eastbound traffic, a 4-foot right shoulder, a 12.5-foot mixed use path, and a Type

742 concrete right barrier. Falsework is not necessary to erect this type of girder structure. Girders will be

set in place from Main Street in Trinidad and US 101 respectively using traffic closures.

The anticipated 2017 structure cost including bridge removal ($200,000), 10 percent for mobilization, and

25 percent for contingencies is $10,892,000 which is $736/SF for this two structure project.

Alternative 6 – Construct a new US 101/Baker Ranch Road Interchange

This proposed improvement intends to construct a new Baker Ranch Road Interchange with a new Baker

Ranch Road Undercrossing of US 101 about 1.24 miles south of the Trinidad undercrossing. The new

undercrossing will connect Scenic Drive, west of US 101, to Westhaven Drive, east of US 101. New

northbound and southbound on and off-ramps will be constructed connecting US 101 to Baker Ranch

Road.

Based on the conditions at the site and the interchange geometrics, the new undercrossing will be a singlespan structure approximately 71-feet in length and 86.33-feet in width. The most economical structure

type will likely be a precast, prestressed, concrete girder structure with a 3.75-foot structure depth.

Supports will be high-cantilever wall type abutments founded on driven piling. The undercrossing will be

designed to accommodate a Type 742 concrete left barrier, a 13.5-foot left shoulder, two 12-foot lanes of

southbound traffic, a 5-foot southbound median shoulder, a future Type 60 median barrier, a 5-foot

northbound median shoulder, two 12-foot lanes of northbound traffic, a 10-foot right shoulder, and a Type

742 concrete right barrier. Falsework is not necessary to erect this type of structure. Girders will be set in

place from Baker Ranch Road below.

The anticipated 2017 structure cost including 10 percent for mobilization, and 25 percent for

contingencies is $6,585,000 which is $1074/SF.

Alternative 8 – Construct a new US 101/New Local Road Interchange

This proposed improvement intends to construct a New Local Road Interchange with a New Local Road

Overcrossing of US 101 about 1.0 miles south of the Trinidad undercrossing. The new overcrossing will

connect Scenic Drive (via Cher-Ae Lane), west of US 101, to Westhaven Drive, east of US 101. New

northbound and southbound on and off-ramps will be constructed connecting US 101 to the New Local

Road.

Based on the conditions at the site and the interchange geometrics, the new overcrossing will be a singlespan structure approximately 94-feet in length and 42.83-feet in width . The most economical structure

type will likely be a precast, prestressed, concrete girder structure with a 5-foot structure depth. Supports

will be high-cantilever wall type abutments founded on driven piling. The overcrossing will be designed

to accommodate a Type 742 concrete left barrier, an 8-foot left shoulder, a 12-foot lane of westbound

traffic, a 12-foot lane of eastbound traffic, an 8-foot right shoulder, and a Type 742 concrete right barrier.

Falsework is not necessary to erect this type of girder structure. Girders will be set in place from US 101

using traffic closures.

The anticipated 2017 structure cost including 10 percent for mobilization, and 25 percent for

contingencies is $3,119,000 which is $775/SF.

3

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

ATTACHMENT D

RIGHT OF WAY IMPACT EXHIBITS

R1721PSR003.docx

51

US 101 / Trinidad Area Access Improvements

PSR‐PDS, December, 2017

01‐HUM‐101 PM 98.4/100.7

EA: 01‐48040K; EFIS: 0100020301

ATTACHMENT E

PROJECT COST ESTIMATE WORKSHEETS

R1721PSR003.docx

52

US 101 / Trinidad Area Access Improvements

Capital Outlay Project Estimate

01-HUM-101 PM 98.4/100.7

01-48040K

Project Study Report - Project Development Support

Capital Outlay Project Estimate

Dist - Co - Rte 01-HUM-101

PM 98.4/100.7

Program Code

Project Number

Month / Year December 2017

PROJECT DESCRIPTION:

Limits:

From 0.6 Mile south to 0.4 Mile north of Trinidad Road Undercrossing

Proposed Improvement (Scope): Improvements to Main Street with signalized intersections, including

reconstruction of the Trinidad-Main Street Interchange (PM 100.7), widening of Main Street from Scenic

Drive to Westhaven Drive, and widening of Scenic Drive from Cher-Ae Lane to Main Street in the City of

Trinidad (PM 100.1-101.1).

Alternate: 1A

SUMMARY OF PROJECT COST ESTIMATE

TOTAL ROADWAY ITEMS

TOTAL STRUCTURES ITEMS

TOTAL ENVIRONMENTAL MITIGATION ITEMS

SUBTOTAL CONSTRUCTION COSTS

TOTAL RIGHT-OF-WAY ITEMS

R1721CST024.xls

$

$

$

$

$

30,400,000

6,818,000

800,000

38,018,000

800,000

TOTAL PROJECT CAPITAL OUTLAY COSTS $

Note: Costs escalated at 5% per year for 4 years

38,818,000

Alternative 1A - Page 1

US 101 / Trinidad Area Access Improvements

Capital Outlay Project Estimate

I.

01-HUM-101 PM 98.4/100.7

01-48040K

ROADWAY ITEMS

Total Cost $

Average Cost Per Lane Mile

3,800,000

Number of Lane Miles

8.0

X

Total Cost

$

30,400,000

=

Explanation:

Cost includes complete replacement of Main Street on new vertical profile to meet structure clearance

requirements and accessibility requirements. All ramps are completely replaced to current geometric

standards. Scenic Drive is widened. The mainline UC structure is replaced necessitating half width

stage construction and a raised vertical profile to provide standard vertical clearance on Main Street.

Number of lane miles includes Main Street, Westhaven Drive, Secenic Drive, mainline, and ramps.

Significant costs include an estimated 12,000 feet of retaining walls, with an average height of 8 feet;

nearly 1,000,000 square feet of structure section; an estimated 130,000 cubic yards of excavation.

$

TOTAL ROADWAY ITEMS

II.

30,400,000

STRUCTURES ITEMS

Structure

1

Bridge Name

Trinidad UC

Total Cost for Structure $

6,818,000

Structure

2

N/A

$

Structure

3

N/A

-

$

-

Explanation:

Existing UC structure will be replaced to accommodate standard vertical clearance on Main Street.

Half width construction will be required and the vertical profile raised. The cost assumes a precast,

prestressed, concrete girder structure. Supports would be high-cantilever wall type abutments on

driven piling. The cost includes removal of the existing structure and aesthetic treatments.

TOTAL STRUCTURE ITEMS

R1721CST024.xls

$

6,818,000

Alternative 1A - Page 2

US 101 / Trinidad Area Access Improvements

Capital Outlay Project Estimate

III.

01-HUM-101 PM 98.4/100.7

01-48040K

ENVIRONMENTAL MITIGATION

Quantity

Environmental Mitigation

Unit

1

LS

Unit Price

X

$

800,000

Item Cost

=

$

800,000

Explanation:

Environmental mitigation cost includes costs for mitigating impacts to permanently filling wetlands and other

mitigation items that may be necessary to meet Coastal Commission expectations.

TOTAL ENVIRONMENTAL MITIGATION ITEMS

IV.

800,000

$

RIGHT-OF-WAY ITEMS

Escalated

Value

A. Acquisition, including excess lands,

damages to remainder(s) and Goodwill

$

590,000

B. Utility Relocation (State share)

$

210,000

Anticipated Date of Right-of-Way Certification

(Date to which values are escalated at 5% per year)

2019

Explanation:

Acquisition estimate assumes full take of small retail business in SW quadrant of the Scenic Drive/Main Street

intersection and partial takes of other businesses in the vicinity of the Trinidad-Main Street Interchange.

Numerous additional takes along the frontages of Scenic Drive, from Cher-Ae Lane to Main Street are included

in the estimate. City of Trinidad utility impacts are assumed to be in franchise agreement areas. It is assumed

that a portion of the PG&E and AT&T impacts, east of the I/C and along Scenic Drive, will be relocated as state

expense.

TOTAL RIGHT-OF-WAY ITEMS

R1721CST024.xls

$

800,000

Alternative 1A - Page 3

US 101 / Trinidad Area Access Improvements

Capital Outlay Project Estimate

01-HUM-101 PM 98.4/100.7

01-48040K

Project Study Report - Project Development Support

Capital Outlay Project Estimate

Dist - Co - Rte 01-HUM-101

PM 98.4/100.7

Program Code

Project Number

Month / Year December 2017

PROJECT DESCRIPTION:

Limits:

From 0.4 Mile South to 0.4 Mile North of Trinidad Road Undercrossing

Proposed Improvement (Scope): Improvements to Main Street with roundabout intersections, including

reconstruction of the Trinidad-Main Street Interchange ramps (PM 100.7), widening of Main Street from

Scenic Drive to Westhaven Drive, and widening of Scenic Drive from Cher-Ae Lane to Main Street in the

City of Trinidad (PM 100.3 – 101.1).

Alternate: 1B

SUMMARY OF PROJECT COST ESTIMATE

TOTAL ROADWAY ITEMS

TOTAL STRUCTURES ITEMS

TOTAL ENVIRONMENTAL MITIGATION ITEMS

SUBTOTAL CONSTRUCTION COSTS

TOTAL RIGHT-OF-WAY ITEMS

R1721CST024.xls

$

$

$

$

$

18,200,000

575,000

18,775,000

1,290,000

TOTAL PROJECT CAPITAL OUTLAY COSTS $

Note: Costs escalated at 5% per year for 4 years

20,065,000

Alternative 1B - Page 1

US 101 / Trinidad Area Access Improvements

Capital Outlay Project Estimate

I.

01-HUM-101 PM 98.4/100.7

01-48040K

ROADWAY ITEMS

Total Cost $

Average Cost Per Lane Mile

5,200,000

Number of Lane Miles

3.5

X

Total Cost

$

18,200,000

=

Explanation:

Cost includes complete replacement of Main Street on new vertical profile to meet accessibility

requirements and acceptable grades through the roundabouts, while leaving US 101 mainline and

structure intact. All ramps are completely replaced to current geometric standards. Scenic Drive is

widened. The mainline UC structure will remain, while Main Street is lowered significantly to the

east of the interchange. Lowering Main Street increases costs per lane mile since numerous walls and

right-of-way takes are required to account for the lower profile. Number of lane miles includes Main

street, Westhaven Drive, Scenic Drive,Patricks Point Drive, Trinidad Frontacge Road, and ramp

replacement.

Significant costs include an estimated 10,000 feet of retaining walls, with an average height if 8 feet;

neary 550,000 square feet of stuctural section.

$

TOTAL ROADWAY ITEMS

II.

18,200,000

STRUCTURES ITEMS

Bridge Name

Total Cost for Structure $

Structure

1

N/A

Structure

2

N/A

-

$

Structure

3

N/A

-

-

$

Explanation:

This alternative assumes the existing structure will remain in place.

TOTAL STRUCTURE ITEMS

R1721CST024.xls

$

-

Alternative 1B - Page 2

US 101 / Trinidad Area Access Improvements

Capital Outlay Project Estimate

III.

01-HUM-101 PM 98.4/100.7

01-48040K

ENVIRONMENTAL MITIGATION

Quantity

Environmental Mitigation

Unit

1

LS

Unit Price

X

$

575,000

Item Cost

=

$

575,000

Explanation:

Environmental mitigation cost includes costs for mitigating impacts to permanently filling wetlands and other

mitigation items that may be necessary to meet Coastal Commission expectations. This alternative is mostly

contained within existing areas, which minimizes environmental impacts.

TOTAL ENVIRONMENTAL MITIGATION ITEMS

IV.

575,000

$

RIGHT-OF-WAY ITEMS

Escalated

Value

A. Acquisition, including excess lands,

damages to remainder(s) and Goodwill

$

1,040,000

B. Utility Relocation (State share)

$

250,000

Anticipated Date of Right-of-Way Certification

(Date to which values are escalated at 5% per year)

2019

Explanation:

Acquisition estimate assumes full take of small retail business in SW quadrant of the Scenic Drive/Main Street

intersection and partial takes of other businesses in the vicinity of the Trinidad-Main Street Interchange. Full

takes of multiple parcels along Westhaven Drive and Trinidad Frontage Road east of the interchange increase the

acquisition estimates significantly. Numerous additional takes along the frontages of Scenic Drive, from CherAe Lane to Main Street are included in the estimate. City of Trinidad utility impacts are assumed to be in

franchise agreement areas. It is assumed that a portion of the PG&E and AT&T impacts, east of the I/C and

along Scenic Drive, will be relocated as state expense.

TOTAL RIGHT-OF-WAY ITEMS

R1721CST024.xls

$

1,290,000

Alternative 1B - Page 3

US101/TrinidadAreaAccessImprovements

CapitalOutlayProjectEstimate

01ͲHUMͲ101PM98.4/100.7

01Ͳ48040K

Project Study Report - Project Development Support

Capital Outlay Project Estimate

Dist - Co - Rte 01-HUM-101

PM 98.4/100.7

Program Code

Project Number

Month / Year December 2017

PROJECT DESCRIPTION:

Limits:

0.8 Mile South of Trinidad Undercrossing

Proposed Improvement (Scope): Construct new Cher-Ae Lane Overcrossing (PM 100.0) with local road

connection to Scenic Drive and Westhaven Drive (no connection to US 101), including widening of Scenic

Drive from Cher-Ae Lane to Main Street in the City of Trinidad and widening of Westhaven Drive from

US

101 in the Community of Westhaven to Main Street in the City of Trinidad (PM 98.1 – 100.7).

Alternate: 2

SUMMARY OF PROJECT COST ESTIMATE

TOTAL ROADWAY ITEMS

TOTAL STRUCTURES ITEMS

TOTAL ENVIRONMENTAL MITIGATION ITEMS

SUBTOTAL CONSTRUCTION COSTS

TOTAL RIGHT-OF-WAY ITEMS

R1721CST024.xls

$

$

$

$

$

12,012,000

4,074,000

500,000

16,586,000

1,620,000

TOTAL PROJECT CAPITAL OUTLAY COSTS $

Note: Costs escalated at 5% per year for 4 years

18,206,000

Alternative2ͲPage1

US101/TrinidadAreaAccessImprovements

CapitalOutlayProjectEstimate

I.

01ͲHUMͲ101PM98.4/100.7

01Ͳ48040K

ROADWAY ITEMS

Total Cost $

Average Cost Per Lane Mile

1,320,000.00

Number of Lane Miles

9.1

X

Total Cost

$

12,012,000

=

Explanation:

Cost includes all new roadway for Cher-Ae Lane connecting Scenic Drive to Westhaven Drive.

Scenic Drive is widened from Cher-Ae Lane to Main Street in the City of Trinidad. Westhaven Drive

is widened from the Community of Westhaven to Main Street in the City of Trinidad. Number of lane

miles includes Cher-Ae Lane, Scenic Drive, and Westhaven Drive. Costs per lane mile are low since

there is not a lot of significant retaining wall and roadway excavation work.

Significant costs include nearly 750,000 square feet of structural section.

TOTAL ROADWAY ITEMS

II.

12,012,000

$

STRUCTURES ITEMS

Structure

1

Bridge Name

Cher-Ae Lane OC

Total Cost for Structure $

4,074,000

Structure

2

N/A

$

Structure

3

N/A

-

-

$

Explanation:

A new one span OC structure is proposed over Route 101 as an extension of Cher-Ae Lane. The cost

assumes a precast, prestressed, concrete girder structure. Supports would be high-cantilever wall type

abutments on driven piling. The cost includes aesthetic treatments.

TOTAL STRUCTURE ITEMS

R1721CST024.xls

$

4,074,000

Alternative2ͲPage2

US101/TrinidadAreaAccessImprovements

CapitalOu

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.