Boulder Canyon ProjectFirm Power Services Base Charge

Federal RegisterMar 24, 1999

Ask Donna

What actually matters in this document.

Text

DEPARTMENT OF ENERGY

Western Area Power Administration

Boulder Canyon Project--Firm Power Services Base Charge

AGENCY: Western Area Power Administration, DOE.

ACTION: Notice of Proposed Base Charge Adjustments.

-----------------------------------------------------------------------

SUMMARY: The Western Area Power Administration's (Western) Desert

Southwest Region (DSW) is initiating a rate adjustment process for the

firm power services base charge for the Boulder Canyon Project (BCP)

for FY 2000. The annual base charge adjustments are a requirement of

the rate setting methodology approved on a final basis by the Federal

Energy Regulatory Commission (FERC) on April 19, 1996. The existing

rate schedule was placed into effect on November 1, 1995. The power

repayment study indicates the proposed base charge herein for BCP firm

power services is appropriate to provide sufficient revenue to pay all

[[Page 14228]]

annual costs (including interest expense), plus repayment of required

investment within the allowable time period.

The proposed base charge is explained in greater detail during the

informal and formal processes and made available to all power customers

and interested parties.

The proposed base charge for firm power services is expected to

become effective October 1, 1999. This Federal Register notice

initiates the formal process for the proposed base charge.

DATES: The consultation and comment period will begin from the date of

publication of this Federal Register notice and will end June 22, 1999.

A public information forum at which Western will present a detailed

explanation of the proposed base charge is scheduled for April 21,

1999, beginning at 10:00 a.m. MST, at the Desert Southwest Regional

Office. A public comment forum at which Western will receive oral and

written comments is scheduled for June 2, 1999, beginning at 10:30 a.m.

MST, at the same location.

ADDRESSES: Written comments should be sent to: Mr. J. Tyler Carlson,

Regional Manager, Desert Southwest Customer Service Region, Western

Area Power Administration, P.O. Box 6457, Phoenix, AZ 85005-6457.

Western should receive written comments by the end of the consultation

and comment period to be assured consideration. The public forums will

be held at the Desert Southwest Regional Office, 615 South 43rd Avenue,

Phoenix, Arizona.

FOR FURTHER INFORMATION CONTACT: Mr. Maher A. Nasir, Rates Team Lead,

Desert Southwest Customer Service Region, Western Area Power

Administration, P.O. Box 6457, Phoenix, AZ 85005-6457, (602) 352-2768.

SUPPLEMENTARY INFORMATION:

Proposed Base Charge for Firm Power Services

In accordance with established rate design principles for the BCP

firm power services, Western has established a proposed base charge,

consisting of an energy dollar and capacity dollar, and has established

a forecast energy rate and forecast capacity rate. The proposed base

charge for BCP firm power services is based on an annual revenue

requirement of $47,929,196. The proposed base charge consists of an

energy dollar amount of $24,752,366 and a capacity dollar amount of

$23,176,831. The proposed forecast energy rate is 4.6249 mills/

kilowatthour (mills/kWh), and the proposed forecast capacity rate is

$0.9900 per kilowattmonth ($/kWmo).

The existing BCP firm power services base charge is based on an

annual revenue requirement of $48,842,126, consisting of an energy

dollar amount of $25,208,831 and a capacity dollar amount of

$23,633,296. The existing BCP forecast energy rate is 4.8646 mills/kWh

and the forecast capacity rate is $1.0095/kWmo.

Authorities

Since the proposed change to the base charge constitutes a major

rate adjustment as defined in 10 CFR 903.2, both a public information

forum and a public comment forum will be held. After review of public

comments, Western will recommend the proposed base charge or revised

proposed base charge for approval on an interim basis by the Department

of Energy (DOE) Deputy Secretary.

The proposed firm power services base charge for BCP is being

established pursuant to the Department of Energy Organization Act (42

U.S.C. 7101, et seq.) and the Reclamation Act of 1902 (43 U.S.C. 371,

et seq.), as amended and supplemented by subsequent enactments,

particularly section 9(c) of the Reclamation Project Act of 1939 (43

U.S.C. 485h(c)) and section 8 of the Act of August 31, 1964 (16 U.S.C.

837g), the Colorado River Basin Project Act of 1968 (43 U.S.C. 1501, et

seq.), the Colorado River Storage Project Act (43 U.S.C. 620, et seq.),

the Boulder Canyon Project Act (43 U.S.C. 617, et seq.), the Boulder

Canyon Project Adjustment Act (43 U.S.C. 618, et seq.), the Hoover

Power Plant Act of 1984 (43 U.S.C. 619, et seq.), the General

Regulations for Power Generation, Operation, Maintenance, and

Replacement at the BCP, Arizona/Nevada (43 CFR Part 431) published in

the Federal Register at 51 FR 23960 on July 1, 1986, and the General

Regulations for the Charges for the Sale of Power From the BCP, Final

Rule (10 CFR Part 904) published in the Federal Register at 50 FR 37837

on September 18, 1985, and the DOE financial reporting policies,

procedures, and methodology (DOE Order No. RA 6120.2 dated September

20, 1979).

By Amendment No. 3 to Delegation Order No. 0204-108, published

November 10, 1993 (58 FR 59716), the Secretary of DOE delegated (1) the

authority to develop long-term power and transmission rates on a

nonexclusive basis to the Administrator of Western; (2) the authority

to confirm, approve, and place such rates in effect on an interim basis

to the Deputy Secretary; and (3) the authority to confirm, approve, and

place into effect on a final basis, to remand, or to disapprove such

rates to FERC. Existing DOE procedures for public participation in

power rate adjustments (10 CFR Part 903) became effective on September

18, 1985 (50 FR 37835).

Regulatory Procedure Requirements

Regulatory Flexibility Analysis

The Regulatory Flexibility Act of 1980 (5 U.S.C. 601, et seq.)

requires Federal agencies to perform a regulatory flexibility analysis

if a proposed rule is likely to have a significant economic impact on a

substantial number of small entities and there is a legal requirement

to issue a general notice of proposed rulemaking. Western has

determined that this action relates to rates or services offered by

Western, and therefore is not a rule within the purview of the Act.

Environmental Compliance

In compliance with the National Environmental Policy Act of 1969

(NEPA) (42 U.S.C. 4321, et seq.); the Council On Environmental Quality

Regulations (40 CFR Parts 1500-1508); and DOE NEPA Regulations (10 CFR

Part 1021), Western conducts environmental evaluations of the proposed

base charge and develops the appropriate level of documentation.

Determination Under Executive Order 12866

Western has an exemption from centralized regulatory review under

Executive Order 12866; accordingly, no clearance of this notice by the

Office of Management and Budget is required.

Availability of Information

All brochures, studies, comments, letters, memorandums, and other

documents made or kept by Western for the purpose of developing the

proposed base charge will be made available for inspection and copying

at Western's Desert Southwest Regional Office at 615 South 43rd Avenue

in Phoenix, Arizona.

Dated: March 5, 1999.

Michael S. Hacskaylo,

Administrator.

[FR Doc. 99-7213 Filed 3-23-99; 8:45 am]

BILLING CODE 6450-01-U