DEPARTMENT OF AGRICULTURE
Forest Service
Starbucky Restoration Project; Nez Perce National Forest, Idaho
County, Idaho
AGENCY: Forest Service, USDA.
ACTION: Notice; intent to prepare an environmental impact statement.
-----------------------------------------------------------------------
SUMMARY: The project area is located in the Buckhorn, Santiam, Rabbit,
and Center Star watersheds, along with South Fork Clearwater River face
drainages, T28N, R6E, Sections 1 and 12; T28N, R7E, Sections 3-10;
T29N, R6E, Section 36; T29N, R7E, Sections 23 and 25-35, Boise
Meridian.
The Forest Service will prepare an environmental impact statement
(EIS) to analyze and disclose the environmental effects of the project.
The primary purpose of this project is to maintain the project
area's forest ecosystems ecological structure and function within a
natural and sustainable condition. The projected ecological succession
within these watersheds will not maintain desired conditions, because
of the limited role natural fire has been allowed to perform, and could
pose a risk to watershed condition, fish, wildlife, and sensitive plant
habitat.
DATES: Written comments and suggestions should be received on or before
January 12, 2000 to receive timely consideration in the preparation of
the draft EIS.
ADDRESSES: Send written comments and suggestions on the proposed action
or requests for a map of the proposed action or to be placed on the
project mailing list to Kevin Martin, District Ranger, Red River
District, P.O. Box 416, Elk City, Idaho 83525.
FOR FURTHER INFORMATION CONTACT: Kara Chadwick, District
Silviculturist, Red River Ranger District, P.O. Box 416, Elk City,
Idaho 83525, phone (208) 842-2245.
SUPPLEMENTARY INFORMATION: The proposed action includes the following
possible actions: (1) Maintaining the desired vegetation condition
through timber harvest and/or prescribed burning; priority will be
given to treat those vegetative ecosystems most at risk of moving
outside the natural range of variability; this includes western larch,
lodgepole pine, and ponderosa pine forest types, and candystick
habitat; these actions may or may not provide timber products; (2)
reducing the risk of adverse effects from wildfire to the aquatic
resources and firefighter safety, again through timber harvest and/or
prescribed burning; (3) improving fish habitat and stream morphology
and function by reducing sediment production through road obliteration
and other watershed improvement activities; (4) rehabilitating
abandoned mine sites that pose a threat to the public or the
environment; and (5) providing dispersed and roaded recreation
opportunities compatible with other resources.
The scope of this analysis is limited to activities related to the
purpose and need and measures necessary to mitigate the effects these
activities may have on the environment. The decision will include if,
when, how, and where to schedule: timber harvest, watershed improvement
activities, road obliteration, prescribed burning, recreation site
improvement and access management, resource protection measures,
monitoring, and other K-V activities.
This project was originally scoped beginning in February of 1998
prior to undertaking preparation of an Environmental Assessment (EA).
The EA was sent out for a 30-day comment period in May 1998. Due to the
issues raised during the comment period, both internally and
externally, the decision has been made to prepare an Environmental
Impact Statement (EIS). This Notice of Intent serves as notice of the
intent to prepare an EIS for the Starbucky Restoration Project. The
issues raised and the alternatives developed as a result of the public
participation for the EA will be brought forward for the EIS. The
general categories of issues already identified, and the alternatives
developed from the public participation are as follows:
Issues
Current vegetative patterns, structures, and species
composition, and effects of activities on these components.
Effects on Threatened, Endangered, and Sensitive (TES)
wildlife species and their habitat.
Effects on TES plant species, especially candystick, due
to the presence of a Priority One Conservation Unit for candystick.
Effects on big game summer and winter range, security
areas, and big game summer forage.
Effects on water yield and peak flows, and effects of
sedimentation to streams, all of which affect water quality and fish
habitat.
Concern for road densities.
Concern over limited number of recreation sites/
opportunities, and resulting impacts of these limitations to resources.
Economics of proposal.
Effect from cumulative effects.
Current old growth allocation and effects of project on.
Effects on not only visuals of area, but also in respect
to the South Fork Clearwater River corridor.
Access to active mining claims.
Safety of public in regards to old, abandoned mine sites.
Relationship of this proposal to the Interim Roads Rule.
Alternatives
In addition to the ``No Action'' alternative, five action
alternatives have been identified for analysis:
(a) No action.
(b) Vegetative treatment through timber harvest and/or prescribed
burning of approximately 1338 acres; verification and allocation of
Forest Plan old growth; construction of approximately 5.0 miles of
temporary road; obliteration of approximately 4.1 miles of existing
road, along with other watershed improvement activities; mine
reclamation; recreation site improvement; and access management.
(c) Vegetative treatment through prescribed burning only of
approximately 330 acres of winter range; no road construction;
verification and allocation of Forest Plan old growth; obliteration of
approximately 4.1 miles of existing road, along with other watershed
improvement activities; mine reclamation; recreation site improvement;
and access management.
[[Page 69474]]
(d) Vegetative treatment through timber harvest and/or prescribed
burning of approximately 675 acres; verification and allocation of
Forest Plan old growth; construction of approximately 0.7 miles of
temporary road; obliteration of approximately 4.1 miles of existing
road, along with other watershed improvement activities; mine
reclamation; recreation site improvement; and access management.
(e) Vegetative treatment through timber harvest and/or prescribed
burning of approximately 1338 acres; verification and allocation of
Forest Plan old growth; construction of approximately 6.1 miles of
temporary road; obliteration of approximately 4.1 miles of existing
road, along with other watershed improvement activities; mine
reclamation; recreation site improvement; and access management.
(f) Vegetative treatment through timber harvest and/or prescribed
burning of approximately 1338 acres; verification and allocation of
Forest Plan old growth; construction of approximately 8.6 miles of
temporary road; obliteration of approximately 4.1 miles of existing
road, along with other watershed improvement activities; mine
reclamation; recreation site improvement; and access management.
Note that the acreages, the miles of temporary road construction
and miles of road obliteration are approximate only and may change
during the analysis.
Public participation will continue to be an important part of the
project, commencing with the EIS initial scoping process (40 CFR
1501.7), which starts with publication of this notice and continues for
the next 30 days. In addition, the public is encouraged to visit with
Forest Service officials at any time during the analysis and prior to
the decision. The Forest Service will be seeking information, comments,
and assistance from Federal, State, and local agencies, the Nez Perce
Tribe, and other individuals or organizations who may be interested in
or affected by the proposed action.
Comments from the public and other agencies will be used in
preparation of the draft EIS. The scoping process will be used to:
1. Identify additional potential issues;
2. Identify additional major issues to be analyzed in depth;
3. Eliminate minor issues or those which have been covered by a
relevant previous environmental analysis, such as the Nez Perce
National Forest Plan EIS;
4. Identify additional alternatives to the proposed action;
5. Identify potential environmental effects of the proposed action
and alternatives (i.e., direct, indirect, and cumulative effects).
While public participation in this analysis is welcome at any time,
comments received within 30 days of the publication of this notice will
be especially useful in the preparation of the draft EIS, which is
expected to be filed with the Environmental Protection Agency and
available for public review in March 2000. A 45-day comment period will
follow publication of a Notice of Availability of the draft EIS in the
Federal Register. The comments received will be analyzed and considered
in preparation of a final EIS, which is expected to be filed in July
2000. A Record of Decision will be issued not less than 30 days after
publication of a Notice of Availability of the final EIS in the Federal
Register.
The Forest Service believes it is important at this early stage to
give reviewers notice of several court rulings related to public
participation in the environmental review process. First, reviewers of
draft EISs must structure their participation in the environmental
review of the proposal in such a way that it is meaningful and alerts
an agency to the reviewer's position and contentions. Vermont Yankee
Nuclear Power Corp. v. NRDC, 435 U.S. 519, 513 (1978). Also,
environmental objections that could be raised at the draft EIS stage
but that are not raised until after completion of the final EIS may be
waived or dismissed by the courts. City of Angoon v. Hodel, 803 F.2d
1016, 1022 (9th Cir, 1986), and Wisconsin Heritages Inc. v. Harris, 490
F.Supp. 1334, 1338 (E.D. Wis., 1980). Because of these court rulings,
it is very important that those interested in this proposed action
participate by the close of the 45-day comment period in order that
substantive comments and objections are available to the Forest Service
at a time when it can meaningfully consider them and respond to them in
the final EIS. To assist the Forest Service in identifying and
considering issues and concerns on the proposed action, comments should
be as specific as possible. Reviewers may wish to refer to the Council
on Environmental Quality Regulations for implementing the procedural
provisions of the National Environmental Policy Act at 40 CFR 1503.3 in
addressing these points.
Bruce Bernhardt is the responsible official for this environmental
impact statement.
Dated: November 29, 1999.
Bruce Bernhardt,
Forest Supervisor, Nez Perce National Forest.
[FR Doc. 99-32214 Filed 12-10-99; 8:45 am]
BILLING CODE 3410-11-M