NASA Structured Approach for Profit or Fee Objective

Federal RegisterSep 23, 1999

Ask Donna

What actually matters in this document.

Text

NATIONAL AERONAUTICS AND SPACE ADMINISTRATION

48 CFR Part 1815

NASA Structured Approach for Profit or Fee Objective

AGENCY: National Aeronautics and Space Administration.

ACTION: Final rule.

-----------------------------------------------------------------------

SUMMARY: This final rule revises the agency's structured approach for

developing a profit or fee objective. This rule eliminates the element

of cost approach currently prescribed for establishing profit and fee

objectives and focuses on performance risk analysis which requires the

evaluation of specific technical, management and cost risk factors;

provides a new method for determining contract type risk and introduces

a working capital adjustment provision; retains with modification the

Other Considerations factor contained in the structured approach

currently prescribed; and establishes a ceiling for facilities capital

cost of money offset.

EFFECTIVE DATE: September 23, 1999.

FOR FURTHER INFORMATION CONTACT: Donna Fortunat, NASA Headquarters,

Code HC, Washington, DC 20546, telephone: (202) 358-0426; email:

[email protected].

SUPPLEMENTARY INFORMATION:

Background

A proposed rule was published in the Federal Register on June 8,

1999 (64 FR 30468-30472). Comments were received from one respondent,

an industry association. All comments were considered in the

development of this final rule. This final rule includes changes to

adjust the specified values under Contract Type Risk to preclude a

situation where the calculated profit objective would be greater for a

fixed price contract with progress payments than it would for a similar

contract without government financing. Other Consideration values for

both Corporate Capital Investment and Unusual Request for GFP are

adjusted. The facilities capital cost of money offset was changed to

establish a ceiling of one percent. This final rule also includes

changes made for clarification purposes.

FAR 15.404-4(b)(1)(i) requires agencies to use a structured

approach for determining profit or fee prenegotiation objectives. This

revision to the NASA structured approach method uses a performance risk

method for calculating profit and fee objectives instead of the

currently used cost element approach. The revised approach is expected

to provide more appropriate emphasis on the nature of the goods and

services being acquired and on the risks inherent in delivering those

goods and services and thereby prove to be more effective in motivating

and rewarding contractor performance. In addition, the revised policy

provides a common framework for NASA and industry to evaluate potential

risk and profitability in a way that is relevant to both parties. FAR

15.404-4(b)(2) permits agencies to use another agency's structured

approach and the changes in this revised policy represent an Agency

adaptation of DoD's alternate structured approach.

Impact

Regulatory Flexibility Act

NASA certifies that this final rule will not have a significant

economic impact on a substantial number of small entities within the

meaning of the Regulatory Flexibility Act, 5 U.S.C. 601 et seq.,

because most small entities receive contracts based on competition and

are not subject to the structured fee process.

Paperwork Reduction Act

The Paperwork Reduction Act does not apply because the changes to

the NFS do not impose any recordkeeping or information collection

requirements, or collections of information from offerors, contractors,

or members of the public that require the approval of the Office of

Management and Budget under 44 U.S.C. 3501, et seq.

List of Subjects in 48 CFR Part 1815

Government procurement.

Tom Luedtke,

Associate Administrator for Procurement.

Accordingly, 48 CFR Part 1815 is amended as follows:

1. The authority citation for 48 CFR Part 1815 continues to read as

follows:

Authority: 42 U.S.C. 2473(c)(1).

PART 1815--CONTRACTING BY NEGOTIATION

2. Sections 1815.404-4, 1815.404-470, and 1815.404-471 are revised

and sections 1815.404-471-1, 1815.404-471-2, 1815.404-471-3, 1815.404-

471-4, and 1815.404-471-5 are added to read as follows:

1815.404-4 Profit. (NASA supplements paragraphs (b) and (c))

(b)(1)(i)(a) The NASA structured approach for determining profit or

fee objectives, described in 1815.404-471 shall be used to determine

profit or fee objectives in the negotiation of contracts greater than

or equal to $100,000 that use cost analysis and are:

(1) Awarded on the basis of other than full and open competition

(see FAR 6.3);

(2) Awarded under NASA Research Announcements (NRAs) and

Announcements of Opportunity (AO's); or

(3) Awarded under the Small Business Innovative Research (SBIR) or

the Small Business Technology Transfer Research (STTR) programs.

(b) The rate calculated for the basic contract may only be used on

actions under a negotiated contract when the conditions affecting

profit or fee do not change.

(c) Although specific agreement on the applied weights or values

for individual profit or fee factors shall not be attempted, the

contracting officer may encourage the contractor to--

(1) Present the details of its proposed profit amounts in the

structured approach format or similar structured approach; and

(2) Use the structured approach method in developing profit or fee

objectives for negotiated subcontracts.

[[Page 51473]]

(ii) The use of the NASA structured approach for profit or fee is

not required for:

(a) Architect-engineer contracts;

(b) Management contracts for operation and/or maintenance of

Government facilities;

(c) Construction contracts;

(d) Contracts primarily requiring delivery of materials supplied by

subcontractors;

(e) Termination settlements; and

(f) Contracts having unusual pricing situations when the

procurement officer determines in writing that the structured approach

is unsuitable.

(c)(2) Contracting officers shall document the profit or fee

analysis in the contract file.

1815.404-470 NASA Form 634.

NASA Form (NF) 634 shall be used in performing the analysis

necessary to develop profit or fee objectives.

1815.404-471 NASA structured approach for profit or fee objective.

1815.404-471-1 General.

(a) The structured approach for determining profit or fee

objectives (NF 634) focuses on three profit factors:

(1) Performance risk;

(2) Contract type risk including working capital adjustment; and

(3) Other Considerations which may be considered by the contracting

officer to account for special circumstances that are not adequately

addressed in the performance risk and contract type risk factors.

(b) The contracting officer assigns values to each profit or fee

factor; the value multiplied by the base results in the profit/fee

objective for that factor. Each factor has a normal value and a

designated range of values. The normal value is representative of

average conditions on the prospective contract when compared to all

goods and services acquired by NASA. The designated range provides

values based on above normal or below normal conditions. In the

negotiation documentation, the contracting officer need not explain

assignment of the normal value, but must address conditions that

justify assignment of other than the normal value.

1815.404-471-2 Performance risk.

(a) Risk factors. Performance risk addresses the contractor's

degree of risk in fulfilling the contract requirements. It consists of

three risk factors:

(1) Technical--the technical uncertainties of performance;

(2) Management--the degree of management effort necessary to ensure

that contract requirements are met; and

(3) Cost control--the contractor's efforts to reduce and control

costs.

(b) Risk factor weighting, values and calculations. A weighting and

value is assigned to each of the risk factors to determine a profit/fee

objective.

(c) Values. The normal value is 6 percent and the designated range

is 4 percent to 8 percent.

(d) Evaluation criteria for technical risk factor. (1) In

determining the appropriate value for the technical risk factor, the

contracting officer shall review the contract requirements and focus on

the critical performance elements in the statement of work or

specifications. Contracting officers shall consider the--

(i) Technology being applied or developed by the contractor;

(ii) Technical complexity;

(iii) Program maturity;

(iv) Performance specifications and tolerances;

(v) Delivery schedule; and

(vi) Extent of a warranty or guarantee.

(2) Above normal conditions indicating substantial technical risk.

(i) The contracting officer may assign a higher than normal value in

those cases where there is a substantial technical risk, such as when--

(A) The contractor is either developing or applying advanced

technologies;

(B) Items are being manufactured using specifications with

stringent tolerance limits;

(C) The efforts require highly skilled personnel or require the use

of state-of-the-art machinery;

(D) The services or analytical efforts are extremely important to

the government and must be performed to exacting standards;

(E) The contractor's independent development and investment has

reduced the Government's risk or cost;

(F) The contractor has accepted an accelerated delivery schedule to

meet the Government's requirements; or

(G) The contractor has assumed additional risk through warranty

provisions.

(ii) The contracting officer may assign a value significantly above

normal. A maximum value may be assigned when the effort involves--

(A) Extremely complex, vital efforts to overcome difficult

technical obstacles that require personnel with exceptional abilities,

experience, and professional credentials;

(B) Development or initial production of a new item, particularly

if performance or quality specifications are tight; or

(C) A high degree of development or production concurrency.

(3) Below normal conditions indicating lower than normal technical

risk. (i) The contracting officer may assign a lower than normal value

in those cases where the technical risk is low, such as when the--

(A) Acquisition is for off-the-shelf items;

(B) Requirements are relatively simple;

(C) Technology is not complex;

(D) Efforts do not require highly skilled personnel;

(E) Efforts are routine; or

(F) Acquisition is a follow-on effort or a repetitive type

acquisition.

(ii) The contracting officer may assign a value significantly below

normal. A minimum value may be justified when the effort involves--

(A) Routine services;

(B) Production of simple items;

(C) Rote entry or routine integration of Government-furnished

information; or

(D) Simple operations with Government-furnished property.

(e) Evaluation criteria for management risk factor. (1) In

determining the appropriate value for the management risk factor, the

contracting officer shall review the contract requirements and focus on

the critical performance elements in the statement of work or

specifications. Contracting officers shall--

(i) Assess the contractor's management and internal control systems

using contracting office information and reviews made by contract

administration offices;

(ii) Assess the management involvement expected on the prospective

contract action; and

(iii) Consider the degree of cost mix as an indication of the types

of resources applied and value added by the contractor.

(2) Above normal conditions indicating substantial management risk.

(i) The contracting officer may assign a higher than normal value when

the management effort is intense, such as when--

(A) The contractor's value added is both considerable and

reasonably difficult; or

(B) The effort involves a high degree of integration and

coordination.

(ii) The contracting officer may justify a maximum value when the

effort--

(A) Requires large-scale integration of the most complex nature;

(B) Involves major international activities with significant

management coordination; or

(C) Has critically important milestones.

(3) Below normal conditions indicating lower than normal

[[Page 51474]]

management risk. (i) The contracting officer may assign a lower than

normal value when the management effort is minimal, such as when--

(A) The program is mature and many end item deliveries have been

made;

(B) The contractor adds minimum value to an item;

(C) The efforts are routine and require minimal supervision;

(D) The contractor fails to provide an adequate analysis of

subcontractor costs; or

(E) The contractor does not cooperate in the evaluation and

negotiation of the proposal.

(ii) The contracting officer may assign a value significantly below

normal. A minimum value may be assigned when--

(A) Reviews performed by the field administration offices disclose

unsatisfactory management and internal control systems (e.g., quality

assurance, property control, safety, security); or

(B) The effort requires an unusually low degree of management

involvement.

(f) Evaluation criteria for cost control risk factor. (1) In

determining the appropriate value for the cost control risk factor, the

contracting officer shall--

(i) Evaluate the expected reliability of the contractor's cost

estimates (including the contractor's cost estimating system);

(ii) Evaluate the contractor's cost reduction initiatives (e.g.,

competition advocacy programs);

(iii) Assess the adequacy of the contractor's management approach

to controlling cost and schedule; and

(iv) Evaluate any other factors that affect the contractor's

ability to meet the cost targets (e.g., foreign currency exchange rates

and inflation rates).

(2) Above normal conditions indicating substantial cost control

risk. (i) The contracting officer may assign a value higher than normal

value if the contractor can demonstrate a highly effective cost control

program, such as when--

(A) The contractor has an aggressive cost reduction program that

has demonstrable benefits;

(B) The contractor uses a high degree of subcontract competition;

or

(C) The contractor has a proven record of cost tracking and

control.

(3) Below normal conditions indicating lower than normal cost

control risk. (i) The contracting officer may assign a lower than

normal value in those cases where the contractor demonstrates minimal

concern for cost control, such as when--

(A) The contractor's cost estimating system is marginal;

(B) The contractor has made minimal effort to initiate cost

reduction programs;

(C) The contractor's cost proposal is inadequate; or

(D) The contractor has a record of cost overruns or the indication

of unreliable cost estimates and lack of cost control.

1815.404-471-3 Contract type risk and working capital adjustment.

(a) Risk factors. The contract type risk factor focuses on the

degree of cost risk accepted by the contractor under varying contract

types. The working capital adjustment is an adjustment added to the

profit objective for contract type risk. It applies to fixed-price type

contracts that provide for progress payments. Though it uses a formula

approach, it is not intended to be an exact calculation of the cost of

working capital. Its purpose is to give general recognition to the

contractor's cost of working capital under varying contract

circumstances, financing policies, and the economic environment. This

adjustment is limited to a maximum of 2 percent.

(b) Risk factor values and calculations. A risk value is assigned

to calculate the profit or fee objective for contract type. A contract

length factor is assigned and applied to costs financed when a working

capital adjustment is appropriate. This calculation is only performed

when the prospective contract is a fixed-price contract containing

provisions for progress payments.

(c) Values: Normal and designated ranges.

------------------------------------------------------------------------

Designated

Contract Type Note Normal value range

(Percent) (Percent)

------------------------------------------------------------------------

Firm-fixed-price, no financing (1) 5 4 to 6

Firm-fixed-price with (6) 4 2.5 to 5.5

performance-based payments.

Firm-fixed-price with progress (2) 3 2 to 4

payments.

Fixed-price-incentive, no (1) 3 2 to 4

financing.

Fixed-price-incentive, with (6) 2 .5 to 3.5

performance-based payments.

Fixed-price, redeterminable... (3)

Fixed-price-incentive, with (2) 1 0 to 2

progress payments.

Cost-plus-incentive-fee....... (4) 1 0 to 2

Cost-plus-award fee........... (4) .75 .5 to 1.5

Cost-plus-fixed fee........... (4) .5 0 to 1

Time-and-materials............ (5) .5 0 to 1

Labor-hour.................... (5) .5 0 to 1

Firm-fixed-price, level-of- (5) .5 0 to 1

effort, term.

------------------------------------------------------------------------

(1) ``No financing,'' means that the contract either does not

provide progress or performance based payments, or provides them only

on a limited basis. Do not compute a working capital adjustment.

(2) When progress payments are present, compute a working capital

adjustment.

(3) For purposes of assigning profit values, treat a fixed-price

redeterminable contract as if it were a fixed-price-incentive contract

with below normal provisions.

(4) Cost-plus contracts shall not receive the working capital

adjustment.

(5) These types of contracts are considered cost-plus-fixed-fee

contracts for the purposes of assigning profit values. Do not compute

the working capital adjustment. However, higher than normal values may

be assigned within the designated range to the extent that portions of

cost are fixed.

(6) When performance-based payments are used, do not compute a

working capital adjustment.

(d) Evaluation criteria. (1) General. The contracting officer shall

consider elements that affect contract type risk such as--

(i) Length of contract;

(ii) Adequacy of cost projection data;

(iii) Economic environment;

(iv) Nature and extent of subcontracted activity;

[[Page 51475]]

(v) Protection provided to the contractor under contract provisions

(e.g., economic price adjustment clauses);

(vi) The ceilings and share lines contained in the incentive

provisions; and

(vii) The rate, frequency, and risk to the contractor of

performance-based payments, if provided.

(2) Mandatory. The contracting officer shall assess the extent to

which costs have been incurred prior to definitization of the contract.

When costs have been incurred prior to definitization, generally regard

the contract type risk to be in the low end of the designated range. If

a substantial portion of the costs have been incurred prior to

definitization, the contracting officer may assign a value as low as 0

percent regardless of contract type.

(3) Above normal conditions. The contracting officer may assign a

higher than normal value when there is substantial contract type risk.

Conditions indicating higher than normal contract type risk are--

(i) Efforts where there is minimal cost history;

(ii) Long-term contracts without provisions protecting the

contractor, particularly when there is considerable economic

uncertainty;

(iii) Incentive provisions that place a high degree of risk on the

contractor;

(iv) Performance-based payments totaling less than the maximum

allowable amount(s) specified at FAR 32.1004(b)(2); or

(v) An aggressive performance-based payment schedule that increases

risk.

(4) Below normal conditions. The contracting officer may assign a

lower than normal value when the contract type risk is low. Conditions

indicating lower than normal contract type risk are:

(i) Very mature product line with extensive cost history;

(ii) Relatively short-term contracts;

(iii) Contractual provisions that substantially reduce the

contractor's risk, e.g. economic price adjustment provisions; and

(iv) Incentive provisions that place a low amount of risk on the

contractor.

(v) A performance-based payment schedule that is routine with

minimal risk.

(e) Costs financed. (1) Costs financed equal the total costs

multiplied by the percent of costs financed by the contractor.

(2) Total costs may be reduced as appropriate when--

(i) The contractor has little cash investment (e.g., subcontractor

progress payments are liquidated late in the period of performance);

(ii) Some costs are covered by special funding arrangements, such

as advance payments;

(3) The portion financed by the contractor is generally the portion

not covered by progress payments. (i.e.--for progress payments: 100

percent minus the customary progress payments rate. For example, if a

contractor receives progress payments at 75 percent, the portion

financed by the contractor is 25 percent. On contracts that provide

progress payments to small business, use the customary progress payment

rate for large businesses.)

(f) Contract length factor. (1) This is the period of time that the

contractor has a working capital investment in the contract. It--

(i) Is based on the time necessary for the contractor to complete

the substantive portion of the work;

(ii) Is not necessarily the period of time between contract award

and final delivery, as periods of minimal effort should be excluded;

(iii) Should not include periods of performance contained in option

provisions when calculating the objective for the base period; and

(iv) Should not, for multiyear contracts, include periods of

performance beyond that required to complete the initial year's

requirements.

(2) The contracting officer--

(i) Should use the following to select the contract length factor:

------------------------------------------------------------------------

Contract

Period to perform substantive portion (in months) length factor

------------------------------------------------------------------------

21 or less.............................................. .40

22 to 27................................................ .65

28 to 33................................................ .90

34 to 39................................................ 1.15

40 or more.............................................. 1.40

------------------------------------------------------------------------

(ii) Should develop a weighted average contract length when the

contract has multiple deliveries; and

(iii) May use sampling techniques provided they produce a

representative result.

(3) Example: A prospective contract has a performance period of 40

months with end items being delivered in the 34th, 36th, 38th and 40th

months of the contract. The average period is 37 months and the

contract length factor is 1.15.

1815.404-471-4 Other considerations.

(a) Other Considerations may be included by the contracting officer

to account for special circumstances, such as contractor efficiencies

or unusual acceptance of contractual or program risks that are not

adequately addressed in the structured approach calculations described

in 1815.404-471-2 or 1815.404-4713. The total adjustment resulting from

Other Considerations may be positive or negative but in no case should

the total adjustment exceed +/-5 percent.

(b) The contracting officer shall analyze and verify information

provided by the contractor that demonstrates that the special

circumstances being recognized under this section--

(1) Provide substantial benefits to the Government under the

contract and/or overall program;

(2) Have not been recognized in the structured approach

calculations; and

(3) Represent unusual and innovative actions or acceptance of risk

by the contractor.

(c) Examples of special circumstances include, but are not limited

to the following:

(1) Consistent demonstration by the contractor of excellent past

performance within the last three years, with a special emphasis on

excellence in safety, may merit an upward adjustment of as much as 1

percent. Similarly, an assessment of poor past performance, especially

in the area of safety, may merit a downward adjustment of as much -1

percent. This consideration is especially important when negotiating

modifications or changes to an ongoing contract.

(2) Extraordinary steps to achieve the Government's socioeconomic

goals, environmental goals, and public policy goals established by law

or regulation that are sufficiently unique or unusual may merit an

upward adjustment of as much as .5 percent. Similarly, for non-

participation in or violation of Federal programs, the contracting

officer may adjust the objective by as much as -.5 percent. However,

this consideration does not apply to the utilization of small

disadvantaged businesses. Incentives for use of these firms may only be

structured according to FAR 19.1203 and 19.1204(c).

(3) Consideration of up to 1 percent should be given when contract

performance requires the expenditure of significant corporate capital

resources.

(4) Unusual requests for use of government facilities and property

may merit a downward adjustment of as much as--1 percent.

(5) Cost efficiencies arising from innovative product design,

process improvements, or integration of a life cycle cost approach for

the design and development of systems that minimize maintenance and

operations costs, that have not been recognized in Performance Risk or

Contract Type Risk, may merit an upward adjustment. This factor is

intended to recognize and

[[Page 51476]]

reward improvements resulting from better ideas and management that

will benefit the Government in the contract and/or program.

(d) Other considerations need not be limited to situations that

increase profit/fee levels. A negative consideration may be appropriate

when there is a significant expectation of near-term spin-off benefits

as a direct result of the contract.

1815.404-471-5 Facilities capital cost of money.

(a) When facilities capital cost of money is included as an item of

cost in the contractor's proposal, it shall not be included in the cost

base for calculating profit/fee. In addition, a reduction in the

profit/fee objective shall be made in the amount equal to the

facilities capital cost of money allowed in accordance with FAR 31.205-

10(a)(2) or 1 percent of the cost base, whichever is less.

(b) CAS 417, cost of money as an element of the cost of capital

assets under construction, should not appear in contract proposals.

These costs are included in the initial value of a facility for

purposes of calculating depreciation under CAS 414.

[FR Doc. 99-24852 Filed 9-22-99; 8:45 am]

BILLING CODE 7510-01-U

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.