Grand Junction Office; Floodplain/Wetlands Statement of Findings for Site Characterization Activities at the Uranium Mill Tailings Site Located Near Shiprock, NM
Federal RegisterSep 25, 1998
Ask Donna
What actually matters in this document.
Text
DEPARTMENT OF ENERGY
Grand Junction Office; Floodplain/Wetlands Statement of Findings
for Site Characterization Activities at the Uranium Mill Tailings Site
Located Near Shiprock, NM
AGENCY: Grand Junction Office, Department of Energy.
ACTION: Floodplain/wetlands statement of findings.
-----------------------------------------------------------------------
SUMMARY: This Floodplain/Wetlands Statement of Findings is prepared
pursuant to Executive Orders 11990 and 11988 and 10 CFR Part 1022,
Compliance with Floodplain/Wetlands Environmental Review Requirements.
The U.S. Department of Energy (DOE) is proposing to conduct site
characterization activities at the Uranium Mill Tailings Site near
Shiprock, New Mexico. The purposes of the activities are to determine
the extent of ground water contamination and to investigate flow
patterns in the ground water system; this information will assist DOE
in selecting a ground water remediation strategy for the site in
accordance with 40 CFR 192, Health and Environmental Protection
Standards for Uranium and Thorium Mill Tailings. Portions of the
proposed field activities would occur on the 100-year floodplain of the
San Juan River and in a nearby wetland. Approximately 18,000 square
feet (0.4 acre) of the 100-year floodplain and approximately 120 square
feet (0.003 acre) of the wetland area would be temporarily disturbed by
these field activities. A floodplain/wetlands assessment was prepared
that described the effects, alternatives, and measures designed to
avoid or minimize potential harm to or within the affected floodplain/
wetlands. The assessment found that the proposed action would have
minimal temporary or long-term impacts on the floodplain and associated
wetland.
DATES: Written comments are due to the address below no later than
October 13, 1998.
ADDRESSES: Written comments should be addressed to Audrey Berry, U.S.
Department of Energy-Grand Junction Office, 2597 B3/4 Road, Grand
Junction, Colorado; or transmitted electronically by E-mail via
Internet to Audrey.B[email protected]; or by facsimile at (970)
248-6040.
FOR FURTHER INFORMATION ON THIS PROPOSED ACTION, CONTACT: Don Metzler,
Project Manager, U.S. Department of Energy, Grand Junction Office, 2597
B3/4 Road, Grand Junction, Colorado 81503, Telephone 1-970-248-7612 or
1-800-399-5618, E-mail Don.M[email protected].
FOR FURTHER INFORMATION ON GENERAL DOE FLOODPLAIN/WETLANDS
ENVIRONMENTAL REVIEW REQUIREMENTS, CONTACT: Carol M. Borgstrom,
Director, Office of NEPA Policy and Assistance (EH-42), U.S. Department
of Energy, 1000 Independence Avenue, SW, Washington, DC 20585, (202)
586-4600 or (800) 472-2756.
SUPPLEMENTARY INFORMATION:
Background
The Notice of Floodplain/Wetlands Involvement for the Shiprock site
characterization activities was published in the Federal Register on
June 23, 1998 (63 FR 34153). The Floodplain/Wetlands Assessment was
completed in August 1998.
Project Description
The Shiprock site is located on the Navajo Nation in northwestern
New Mexico, approximately 1 mile (1.6 kilometers) south of Shiprock,
New Mexico, and about 30 miles (48 kilometers) west of Farmington, New
Mexico. The proposed action would involve (1) installing monitoring
wells to characterize ground water quality and other hydrologic
properties, and (2) constructing a surface water distribution system
consisting of a 30-foot-long, 4-foot-high, concrete intake structure on
Bob Lee Wash; a connecting 6-inch diameter, 2,000-foot-long pipeline
along the upper limit of the 100-year floodplain; and a 1- to 2-foot
deep, gravel-filled infiltration trench underneath the last half of the
pipeline. Most of the pipeline would be outside the wetlands, in
higher-elevation areas. The intake structure would divert a portion of
the flow in Bob Lee Wash into the pipeline and infiltration trench and
increase ground water flow in the floodplain alluvial aquifer. The
purpose of the surface water distribution system would be to flush
ground water contaminants towards the San Juan River and decrease
contaminant concentrations within the aquifer. Features of the surface
water distribution system would be in place for two to three years.
Because contaminated ground water is present in the floodplain alluvial
aquifer, the monitoring wells and surface water distribution system
must be located on the floodplain.
Alternatives
No alternative sites or actions exist for the proposed
characterization activities; the only other alternative would be no
action. Under a no action alternative, no impact to the floodplain or
wetland would occur. The ground water contamination, however, would
remain in place, and no additional characterization would be performed.
Floodplain and Wetland Effects
Installation of the monitoring wells, pipeline, and infiltration
trench would directly affect approximately 18,000 square feet (0.4
acre) of floodplain. Present vegetation consists primarily of inland
saltgrass (Distichlis spicata) and salt cedar (Tamarix ramosissima).
The areas disturbed by installation activities would be more
susceptible to wind and water erosion until vegetation became
reestablished. None of the proposed characterization activities would
be expected to affect lives, property, or any natural and beneficial
floodplain values. In addition, the construction of an intake structure
across Bob Lee Wash would directly affect approximately 120 square feet
(0.003 acre) of wetland. This construction within a wetland would
require regulation under Section 404 of the Clean Water Act. The U.S.
Army, Corps of Engineers has been consulted and a Nationwide Permit
will be required before construction begins.
Diversion of water from Bob Lee Wash through the intake structure
and into the pipeline could potentially affect the downstream emergent
wetland over time by reducing the amount of water supplied by the wash.
Temporary displacement of birds, small mammals, and other wildlife in
adjacent areas may occur during installation of the intake structure
and the associated pipeline and trench. Wildlife use of the wetland
would be expected to return shortly after construction work is
complete. No threatened or endangered species would be affected.
Floodplain and Wetland Mitigation Measures
Potential adverse effects within floodplain and wetland areas would
be mitigated by (1) installing monitoring wells only in higher-
elevation areas (2) reseeding floodplain areas where vegetation has
been disturbed as a result of characterization activities (3) avoiding
wetland areas whenever possible by constructing most of the pipeline
and all of the infiltration trench outside wetlands (4) diverting a
minimal amount of flow from Bob Lee Wash (5) using access routes that
are well outside wetlands, and (6) monitoring emergent wetland
boundaries annually for the duration of the proposed activities to
ensure wetlands are not permanently reduced. With the implementation of
these mitigation measures, the proposed action would be protective of
the 100-
[[Page 51343]]
year floodplain and associated wetland at the Shiprock site and would
conform to the Navajo Nation's floodplain protection standards.
Issued in Albuerque, N.M. on September 16, 1998.
Constance L. Soden,
Director, Environmental Protection Division, U.S. Department of Energy,
Albuquerque Operations Office.
[FR Doc. 98-25688 Filed 9-24-98; 8:45 am]
BILLING CODE 6450-01-P
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.