DEPARTMENT OF TRANSPORTATION

Surface Transportation Board

[STB Finance Docket No. 33407]

Dakota, Minnesota & Eastern Railroad Corporation--Construction

and Operation of New Rail Facilities in Campbell, Converse, Niobrara,

and Weston Counties, Wyoming; Custer, Fall River, Jackson, and

Pennington Counties, South Dakota; and Blue Earth, Nicollet, and Steele

Counties, Minnesota

AGENCIES: Surface Transportation Board; U.S.D.A. Forest Service;

U.S.D.I. Bureau of Land Management; U.S. Army Corps of Engineers

(collectively, the ``Agencies'').

ACTION: Amended Notice of Intent to Prepare an Environmental Impact

Statement (EIS); Extension of Request for Comments on the Draft EIS

Scope.

-----------------------------------------------------------------------

SUMMARY: On February 20, 1998, the Dakota, Minnesota & Eastern Railroad

Corporation (DM&E) filed an application with the Surface Transportation

Board (Board) for authority to construct and operate new rail line

facilities in east-central Wyoming, southwest South Dakota, and south-

central Minnesota. The project involves approximately 280.9 miles of

new rail line construction. Additionally, DM&E proposes to rebuild

approximately 597.8 miles of existing rail line along its current

system to standards acceptable for operation of unit coal trains. On

April 28, 1998, DM&E submitted a Special Use Application to the

U.S.D.A. Forest Service (USFS) for an easement under the Federal Land

Management Policy Act to build new rail lines across portions of the

Thunder Basin National Grassland in Wyoming, administered by the

Medicine Bow-Routt National Forests, and across portions of the Buffalo

Gap National Grassland, administered by the Nebraska National Forest.

Because portions of RARE II roadless areas on the Buffalo Gap National

Grassland could be affected, there is a possibility that the Nebraska

National Forest Land and Resource Management Plan could be amended in

the Forest Service Record of Decision. The Northern Great Plains (NGP)

Management Plan Revision Environmental Impact Statement (EIS) is being

prepared at this time, which could affect the proposed action.

Conversely, the proposed action, if approved, could affect the NGP

Management Plan and a plan amendment may also be necessary. In April,

1998, DM&E also submitted its application to the U.S.D.I. Bureau of

[[Page 42481]]

Land Management (BLM) for a right-of-way across public lands

administered by the BLM in Wyoming and South Dakota for the

construction of new rail lines. Because the BLM is presently preparing

the Newcastle Resource Management Plan EIS, the proposed action could

affect this Plan as well or the Plan could have an effect on the

proposed action. Additionally, the DM&E will submit an application to

the U.S. Army Corps of Engineers (COE), when appropriate, for a permit

regarding the proposed dredge and fill activities within the waters of

the United States, and any other appropriate permit required by the

COE, relative to the proposed construction of new rail lines or

reconstruction of existing lines. The U.S. Bureau of Reclamation is

presently preparing an EIS on the Cheyenne River/Angostura project,

which could be affected by the proposed action or which could have an

effect on the proposed action.

Because the construction and operation of the proposed project has

the potential to result in significant impacts on the quality of the

human environment, the Agencies have determined that the preparation of

an EIS is appropriate. The Board's Section of Environmental Analysis

(SEA) has previously held agency and public scoping meetings and has

accepted written public comments as part of the EIS process. However,

the previous Notice of Intent did not include notification to the

public that other federal agencies would have decision-making

authority. Therefore, the purpose of this Amended Notice of Intent is

to notify persons and agencies interested in or affected by the

proposed project, of additional USFS, BLM, and COE agency decisions

that will be triggered by the project, and to seek additional comments

relating to these agency decisions.

DATES: Additional Public Comment Period: SEA will continue to make

available to the public a draft scope of the EIS. The Agencies will

also provide an additional thirty-day period for the public to submit

written comments on the draft scope. The additional comment period will

close 30 days after the publication date of this Amended Notice of

Intent in the Federal Register, which shall be September 8, 1998.

Please Note: If you have previously submitted comments to SEA

regarding this project, you are not required to re-submit those

comments to be considered by the Agencies. However, you may submit

additional comments if you so desire.

FOR FURTHER INFORMATION CONTACT: Victoria Rutson, Project Manager,

Surface Transportation Board, Powder River Basin Expansion Project, 1-

877-404-3044; U.S.D.A. Forest Service, Wendy Schmitzer (307) 358-4690;

U.S.D.I. Bureau of Land Management, Bill Carson, (307) 746-4453; U.S.

Army Corps of Engineers, Patsy Freeman, (402) 221-3803 or Jerry Folkers

(402) 221-4173.

SUPPLEMENTARY INFORMATION:

Background

The proposed rail construction project, referred to as the ``Powder

River Basin Expansion Project,'' would involve the construction and

operation of approximately 280.9 miles of new rail line by the Dakota,

Minnesota & Eastern Railroad Corporation (DM&E), Brookings, South

Dakota. The project would provide access for a third rail carrier to

serve the region's coal mines and transport coal eastward from the

Powder River Basin. New rail construction would include approximately

262.03 miles of rail line extending off DM&E's existing system near

Wasta, South Dakota, extending generally southwesterly to Edgemont,

South Dakota, and then westerly into Wyoming to connect with existing

coal mines located south of Gillette, Wyoming. This portion of the new

construction would traverse portions of Custer, Fall River, Jackson,

and Pennington Counties, South Dakota and Campbell, Converse, Niobrara,

and Weston Counties, Wyoming.

New rail construction would also include an approximate 13.31 mile

line segment around Mankato, Minnesota, within Blue Earth and Nicollet

Counties. DM&E currently has trackage on both sides of Mankato,

accessed by trackage rights on rail line operated by Union Pacific

Railroad (UP). The proposed Mankato construction would provide DM&E

direct access between its existing lines, avoid operational conflicts

with UP, and route rail traffic around the southern side of Mankato,

avoiding the downtown area.

The final proposed segment of new rail construction would involve a

connection between the existing rail systems of DM&E and I&M Rail Link.

The connection would include construction and operation of

approximately 2.94 miles of new rail line near Owatonna, Steele County,

Minnesota. The connection would allow interchange of rail traffic

between the two carriers.

In order to transport coal over the existing system, DM&E proposes

to rebuild approximately 597.8 miles of rail line along its existing

system. The majority of this, approximately 584.95 miles, would be

along DM&E's mainline between Wasta, South Dakota, and Winona,

Minnesota. An additional approximate 12.85 miles of existing rail line

between Oral and Smithwick, South Dakota, would also be rebuilt. Rail

line rebuilding would include rail and tie replacement, additional

sidings, signals, grade crossing improvements, and other systems.

DM&E's plans to transport coal as its principal commodity. However,

shippers desiring rail access could ship other commodities in addition

to coal over DM&E's rail line. Existing shippers along the existing

DM&E system would continue to receive rail service.

Environmental Review Process

The Surface Transportation Board shall be the lead agency, pursuant

to 40 CFR 1501.5(c), and shall supervise the preparation of the EIS.

The USFS, the BLM, and the COE shall be cooperating agencies, pursuant

to 40 CFR 1501.6, and shall adopt the EIS and base their respective

decisions on it. In order to assure that the EIS includes all of the

information necessary for the decisions by each of the Agencies, they

are requesting information and general comments on the scope of

environmental issues to be addressed in the EIS for the proposed

project. The National Environmental Policy Act (NEPA) process is

intended to assist the Agencies and the public in identifying and

assessing the potential environmental consequences of a proposed action

before a decision on the proposed action is made. The SEA has developed

and will continue to make available a draft scope of study for the EIS

and provide a period of submission of written comments on it. Following

this additional comment period, SEA will issue a final scope of study

for the EIS.

Thereafter, SEA will prepare a Draft Environmental Impact Statement

(DEIS) for the proposed project. The DEIS will address those

environmental issues and concerns identified during the scoping process

and detailed in the scope of study. It will also contain a reasonable

range of alternatives to the proposed action and recommended

environmental mitigation measures. The DEIS will be made available upon

its completion for public review and comment. A Final EIS (FEIS) will

then be prepared reflecting SEA's further analysis and the comments on

the DEIS. In reaching each decision in this case, the Agencies will

take into account the DEIS, the FEIS, and all public and agency

comments received.

[[Page 42482]]

Filing Comments

The Agencies encourage broad participation in the EIS process.

Interested persons and agencies are invited to participate in the

scoping phase through reviewing the scope of study and submitting

written comments to the SEA. A signed original of comments should be

submitted to: Office of the Secretary, Case Control Unit, STB Finance

Docket No. 33407, Surface Transportation Board, 1925 K Street, NW,

Washington, D.C. 20423-0001.

To ensure proper handling of your comments, you must mark your

submission: Attention: Elaine K. Kaiser, Chief, Section of

Environmental Analysis, Environmental Filing.

By following this procedure, your comments will be placed in the

formal public record for this case. In addition, SEA will add your name

to its mailing list for distribution of the final scope of study for

the DEIS and FEIS and the decision documents relating thereto.

By the Board, Elaine K. Kaiser, Chief, Section of Environmental

Analysis.

Vernon A. Williams,

Secretary.

[FR Doc. 98-21215 Filed 8-6-98; 8:45 am]

BILLING CODE 4915-00-P