DEPARTMENT OF LABOR

Mine Safety and Health Administration

Summary of Decisions Granting in Whole or in Part Petitions for

Modification

AGENCY: Mine Safety and Health Administration (MSHA), Labor.

ACTION: Notice of affirmative decisions issued by the Administrators

for Coal Mine Safety and Health and Metal and Nonmetal Mine Safety and

Health on petitions for modification of the application of mandatory

safety standards.

-----------------------------------------------------------------------

SUMMARY: Under section 101(c) of the Federal Mine Safety and Health Act

of 1977, the Secretary of Labor may modify the application of a

mandatory safety standard to a mine if the Secretary determines either

that an alternate method exists at a specific mine that will guarantee

no less protection for the miners affected than that provided by the

standard, or that the application of the standard at a specific mine

will result in a diminution of safety to the affected miners.

Summaries of petitions received by the Secretary appear

periodically in the Federal Register. Final decisions on these

petitions are based upon the petitioner's statements, comments and

information submitted by interested persons, and a field investigation

of the conditions at the mine. MSHA has granted or partially granted

the requests for modification submitted by the petitioners listed

below. In some instances, the decisions are conditioned upon compliance

with stipulations stated in the decision.

FOR FURTHER INFORMATION: Petitions and copies of the final decisions

are available for examination by the public in the Office of Standards,

Regulations, and Variances, MSHA, Room 627, 4015 Wilson Boulevard,

Arlington, Virginia 22203. Contact Barbara Barron at 703-235-1910.

Dated: March 24, 1997.

Patricia W. Silvey,

Director, Standards, Regulations, and Variances.

Affirmative Decisions on Petitions for Modification

Docket No.: M-92-096-C.

FR Notice: 57 FR 43476.

Petitioner: Zeigler Coal Company.

Reg Affected: 30 CFR 75.352.

Summary of Findings: Petitioner's proposal to ventilate the belt

haulage slope with return air and monitor the belt slope with an

automatic fire sensor and warning device system considered acceptable

alternative method. Granted for the Spartan Mine with conditions for

the use of the conveyor belt in the slope portion of the main return.

Docket No.: M-92-097-C.

FR Notice: 57 FR 43476.

Petitioner: Costain Coal, Inc.

Reg Affected: 30 CFR 75.350.

Summary of Findings: Petitioner's proposal to install a low-level

carbon monoxide detection system in all belt entries where a sensor

location is identified instead of a monitoring system which identifies

each belt flight considered acceptable alternative method. Granted for

the Baker Mine with conditions to allow air coursed through conveyor

belt entries to be used to ventilate working places.

Docket No.: M-93-080-C.

FR Notice: 58 FR 39235.

Petitioner: Synder Coal Company.

Reg Affected: 30 CFR 75.1405

Summary of Findings: Petitioner's proposal to use bar and pin or

link and pin couplers on underground haulage equipment instead of

automatic couplers considered acceptable

[[Page 17642]]

alternative method. Granted for the N and L Slope Mine with conditions.

Docket No.: M-93-154-C.

FR Notice: 58 FR 39570.

Petitioner: Little Rock Coal Company.

Reg Affected: 30 CFR 75.1100-2(a)(2).

Summary of Findings: Petitioner's proposal to use only portable

fire extinguishers to replace existing requirements where rock dust,

water cars, and other water storage are not practical considered

acceptable alternative method. Granted for the No. 1 Slope Mine with

conditions for firefighting equipment in the working section.

Docket No.: M-93-158-C.

FR Notice: 58 FR 41294.

Petitioner: Mountain Coal Company.

Reg Affected: 30 CFR 75.350.

Summary of Findings: Petitioner's proposal that condition number 16

requiring sections to be designed by entry location, by number of

entries, or by pressure differential to enhance the protection of the

intake escapeway from contamination by fires in adjacent entries of

MSHA Proposed Decision and Order, docket number M-90-061-C be deleted

considered acceptable alternative method. Granted for the West Elk Mine

with conditions.

Docket No.: M-93-211-C.

FR Notice: 58 FR 44701.

Petitioner: Drummond Company, Inc.

Reg Affected: 30 CFR 75.350.

Summary of Findings: Petitioner's proposal to use all belt entries

as intake air courses to eliminate any possible dead air areas and

prevent air reversals due to changes in ventilation pressure; to

continue separating the belt entries used as intake entries from other

intake and return entries using a continuous permanent type stopping;

and to install a carbon monoxide monitoring system in all belt entries

used as intake air courses considered acceptable alternative method.

Granted for the Shoal Creek Mine with conditions for the use of belt

air to ventilate active working sections. Application for Relief to

Give Effect to April 22, 1996 Granted.

Docket No.: M-93-280-C.

FR Notice: 58 FR 58566.

Petitioner: Andalex Resources, Inc.

Reg Affected: 30 CFR 75.350.

Summary of Findings: Petitioner's proposal to use a two-entry

development system and use the belt entry as a return air course during

longwall development and as an intake air course during longwall

extraction to ensure adequate ventilation quantity to dilute and render

harmless any methane or other noxious gases that otherwise may

accumulate considered acceptable alternative method. Granted for the

Pinnacle Mine with conditions for the use of belt air in two-entry

mining systems.

Docket No.: M-94-009-C.

FR Notice: 59 FR 6975.

Petitioner: SBM Coal Company.

Reg Affected: 30 CFR 75.1100-2(a)(2).

Summary of Findings: Petitioner's proposal to use only portable

fire extinguishers to replace existing requirements where rock dust,

water cars, and other water storage are not practical considered

acceptable alternative method. Granted for the M&R Slope Mine.

Docket No.: M-94-019-C.

FR Notice: 59 FR 10171.

Petitioner: Utah Fuel Company.

Reg Affected: 30 CFR 75.380(d)(4).

Summary of Findings: Petitioner's proposal to continue utilizing

the five-foot wide stairways at overcasts in the secondary escapeway

which was installed prior to November 16, 1992 considered acceptable

alternative method. Granted for Skyline No. 1 Mine with conditions for

the use of the existing steel stairways with 5-foot wide stairs

providing access to cross overcasts which were constructed prior to

November 15, 1992.

Docket No.: M-94-067-C.

FR Notice: 59 FR 32465.

Petitioner: Andalex Resources, Inc.

Reg Affected: 30 CFR 75.352.

Summary of Findings: Petitioner's proposal to install a beltline in

the return air course during development of two-entry longwall gate

entries considered acceptable alternative method. Granted for the

Pinnacle Mine with conditions for the use of the conveyor belt in a

return aircourse during development of a two-entry mining system.

Docket No.: M-94-080-C.

FR Notice: 59 FR 35148.

Petitioner: K & S Coal Company.

Reg Affected: 30 CFR 75.360.

Summary of Findings: Petitioner's proposal to examine each seal for

physical damage from the slope gunboat during the preshift examination

after an air quantity reading is taken in by the intake portal and to

test for the quantity and quality of air at the intake air split

locations off the slope in the gangway portion of the working section

considered acceptable alternative method. Granted for the First Chance

Slope with conditions for examinations of seals (conducted from the

gunboat) in the intake air haulage slope of this mine.

Docket No.: M-94-101-C.

FR Notice: 59 FR 40924.

Petitioner: H. L. & W. Coal Company.

Reg Affected: 30 CFR 75.340.

Summary of Findings: Petitioner's proposal to charge batteries on

the mine's locomotive when all miners are out of the mine and to have

the intake air which is used to ventilate the charging station continue

through its normal route to the last open crosscut and into the monkey

airway considered acceptable alternative method. Granted for the No. 2

Slope Mine with conditions for underground battery charging station in

the intake (gangway) entry.

Docket No.: M-94-120-C.

FR Notice: 59 FR 43869.

Petitioner: Somerset Mining Company.

Reg Affected: 30 CFR 75.350.

Summary of Findings: Petitioner's proposal to use belt air to

ventilate active working places in order to enhance the operator's

ability to ventilate remote sections of the mine considered acceptable

alternative method. Granted for the Sanborn Creek Mine with conditions

to allow air coursed through conveyor belt entries to be used to

ventilate working places.

Docket No.: M-94-147-C.

FR Notice: 59 FR 52840.

Petitioner: Leeco, Inc.

Reg Affected: 30 CFR 75.1103-4(a)(1).

Summary of Findings: Petitioner's proposal to install a low-level

carbon monoxide detection system as an early warning fire detection

system in all belt entries used as intake air courses considered

acceptable alternative method. Granted for Mine No. 68 with conditions

for the use of a carbon monoxide monitoring system that identifies the

location of sensors in lieu of identifying belt flights.

Docket No.: M-94-148-C.

FR Notice: 59 FR 52840.

Petitioner: Leeco, Inc.

Reg Affected: 30 CFR 75.350.

Summary of Findings: Petitioner's proposal to use belt air to

ventilate active working places to aid in controlling respirable dust

and dissipating methane considered acceptable alternative method.

Granted for Mine No. 68 with conditions to allow air coursed through

conveyor belt entries to be used to ventilate working places.

Docket No.: M-94-157-C.

FR Notice: 59 FR 55298.

Petitioner: Arch of Illinois.

Reg Affected: 30 CFR 75.350.

Summary of Findings: Petitioner's proposal to use belt air to

ventilate active working faces to maintain and to better control the

air ventilating the belt entries and the mining faces considered

acceptable alternative method. Granted for the Conant Mine with

conditions to allow air coursed through conveyor belt entries to be

used to ventilate working places.

[[Page 17643]]

Docket No.: M-95-025-C.

FR Notice: 60 FR 16165.

Petitioner: Southern Utah Fuel Company.

Reg Affected: 30 CFR 75.380(d)(3), (4), and (5)

Summary of Findings: Petitioner's proposal to use the main return

to #3 crosscut where the escapeway will then enter the #1 beltline

entry considered acceptable alternative method. Granted for the SUFCo

Mine with conditions for the use of 2 East alternate escapeway with

reduced travelway height or width from the conveyor belt crossing,

alongside the belt conveyor and to the surface.

Docket No.: M-95-040-C.

FR Notice: 60 FR 18147.

Petitioner: C&B Mining Company.

Reg Affected: 30 CFR 75.360.

Summary of Findings: Petitioner's proposal to examine each seal for

physical damage from the slope gunboat during the preshift examination

after an air quantity reading is taken in by the intake portal and to

test for the quantity and quality of air at the intake air split

locations off the slope in the gangway portion of the working section

considered acceptable alternative method. The petitioner proposes also

to physically examine the entire length of the slope once a month.

Granted for the No. 2 Vein Slope Mine with conditions for examinations

of seals (conducted from the gunboat) in the intake air haulage slope

of this mine.

Docket No.: M-95-049-C.

FR Notice: 60 FR 18148.

Petitioner: Kerr-McGee Coal Corporation.

Reg Affected: 30 CFR 75.350.

Summary of Findings: Petitioner's proposal to use the air in the

belt entry to ventilate active working places; to examine the belt

conveyor entry at least once during each coal producing shift at

intervals that would be most effective while miners are working; to

follow all other MSHA fire protection requirements, especially those

pertaining to water lines, fire hoses, fire suppression systems,

warning devices, and flame-resistant belting; and to install a low-

level carbon monoxide detection system in all belt entries used as

intake air courses as an early warning fire detection system considered

acceptable alternative method. Granted for Mine No. 10 with conditions

to allow air coursed through conveyor belt entries to be used to

ventilate working places.

Docket No.: M-95-050-C.

FR Notice: 60 FR 18148.

Petitioner: Cross Mountain Coal, Inc.

Reg Affected: 30 CFR 75.1103-4.

Summary of Findings: Petitioner's proposal to install a low-level

carbon monoxide detection system as an early warning fire detection

system in all belt entries where a monitoring system would identify a

sensor location instead of each belt flight considered acceptable

alternative method. Granted for Mine No. 10 with conditions for the use

of a carbon monoxide system that identifies the location of sensors in

lieu of identifying belt flights.

Docket No.: M-95-052-C.

FR Notice: 60 FR 18148.

Petitioner: Peabody Coal Company.

Reg Affected: 30 CFR 75.364(b).

Summary of Findings: Petitioner's proposal to eliminate coverage of

the 1 South seals, 2 South seals, 3 South seals, 4 South seals, and 1

West seals off the 1 Submain North in the Decision because these areas

have been sealed considered acceptable alternative method. Granted for

Camp No. 1 Mine with conditions.

Docket No.: M-95-066-C.

FR Notice: 60 FR 26903.

Petitioner: Shell Energy Company, Inc.

Reg Affected: 30 CFR 75.364(b)(2)

Summary of Findings: Petitioner's proposal to establish monitor

points ``A'' and ``B'' to test for methane and quantity of air in the

affected area; to have a certified person examine each monitoring point

on a weekly basis and record the results in a record book kept on the

surface available for inspection by interested persons; to record daily

examinations of the water gauge on the active section until corrective

action has been made; to cease mining if a 10 percent decrease in the

quantity of air is measured at either monitor point ``A'' or ``B'' in

the active section until corrective action has been made; and to cease

mining if an increase of .05 per centum of methane is detected at

either monitor point in the active section until corrective action has

been made considered acceptable alternative method. Granted for the

Stacy-Meranda Mine with conditions for approximately 675-feet of the

mine's main return aircourse beginning 130-feet inby the mine's return

air portal.

Docket No.: M-95-068-C.

FR Notice: 60 FR 29714.

Petitioner: C. H. & S. Coal Company.

Reg Affected: 30 CFR 75.1711-2.

Summary of Findings: Petitioner's proposal to install bat gates on

openings at Mine No. 3 and Portals C in addition to the two bat gates

already installed by the Virginia Department of Mines, Minerals and

Energy at openings Portal A and Portal B in 1987 considered acceptable

alternative method. Granted for Mine No. 3 with conditions to allow bat

gates to be installed in Portal of the No. 1 entry and Portal ``C'' in

this mine.

Docket No.: M-95-070-C.

FR Notice: 60 CFR 29714.

Petitioner: Clinchfield Coal Company.

Reg Affected: 30 CFR 75.350.

Summary of Findings: Petitioner's proposal to install a low-level

carbon monoxide monitoring system as an early warning fire detection

system in all belt entries used as intake air courses to ventilate the

active working faces and to dilute and render harmless respirable dust

and harmful gases considered acceptable alternative method. Granted for

the McClure No. 2 Mine with conditions to allow air coursed through

conveyor belt entries to be used to ventilate working places.

Docket No.: M-95-080-C.

FR Notice: 60 FR 31499.

Petitioner: Andalex Resources, Inc.

Reg Affected: 30 CFR 75.325(b).

Summary of Findings: Petitioner's proposal to mine panels by

driving a set of entries a specified distance and then drive another

set of entries parallel and adjoining the first set; and to measure the

air volume in the panels at the location indicated on the diagram

accompanying the petition considered acceptable alternative method.

Granted for Island Mine No. 1 with conditions.

Docket No.: M-95-081-C.

FR Notice: 60 FR 31499.

Petitioner: Andalex Resources, Inc.

Reg Affected: 30 CFR 75.360(c)(1).

Summary of Findings: Petitioner's proposal to mine panels by

driving a set of entries a specified distance and then drive another

set of entries parallel and adjoining the first set; and to measure the

air volume in the panels at the location indicated on the diagram

accompanying the petition considered acceptable alternative method.

Granted for Island Mine No. 1 with conditions.

Docket No.: M-95-082-C.

FR Notice: 60 FR 31499.

Petitioner: Andalex Resources, Inc.

Reg Affected: 30 CFR 75.362(c)(1).

Summary of Findings: Petitioner's proposal to mine panels by

driving a set of entries a specified distance and then drive another

set of entries parallel and adjoining the first set; and to measure the

air volume in the panels at the location indicated on the diagram

accompanying the petition considered acceptable alternative method.

Granted for Island Mine No. 1 with conditions.

Docket No.: M-95-083-C.

FR Notice: 60 FR 33437.

Petitioner: Birdeye Coal Company, Inc.

Reg Affected: 30 CFR 75.342.

Summary of Findings: Petitioner's proposal to monitor continuously

with

[[Page 17644]]

a hand-held methane and oxygen detector instead of using machine-

mounted methane monitors on three-wheel tractors with drag bottom

buckets considered acceptable alternative method. Granted for the No. 4

Mine with conditions for the Mescher permissible three-wheel battery-

powered tractors used to load coal.

Docket No.: M-95-087-C.

FR Notice: 60 FR 35236.

Petitioner: Keystone Coal Mining Corporation.

Reg Affected: 30 CFR 75.380(d)(4).

Summary of Findings: Petitioner's proposal to continue utilizing

its secondary/alternate escapeway for the Emilie No. 1 Mine through to

the East Mains Section cut through to the Emilie No. 2 Mine's main line

track entry, along the belt and track, and up the belt slope to the

surface; to have two features in and about the slope area of the

escapeway less than the requirements of the standard; and to have the

distance from the sidewall of the slope to the edge of the belt 54

inches wide and the two airlock doors in the slope 46 inches wide

considered acceptable alternative method. Granted for the Emilie No. 1

Mine with conditions for the continued use of the alternate escapeway

at a travel width of 54 inches through the belt/track haulage slope.

Docket No.: M-95-089-C.

FR Notice: 60 FR 35236.

Petitioner: R. S. Coal Company.

Reg Affected: 30 CFR 75.1400.

Summary of Findings: Petitioner's proposal to use a slope

conveyance (gunboat) in transporting persons without installing safety

catches or other no less effective devices but instead use an increased

rope strength/safety factor and secondary safety rope connection in

place of such devices considered acceptable alternate method. Granted

for the No. 1 Slope Mine with conditions for the use of the gunboat

without safety catches.

Docket No.: M-95-092-C.

FR Notice: 60 FR 39429.

Petitioner: Consolidation Coal Company.

Reg Affected: 30 CFR 75.1002.

Summary of Findings: Petitioner's proposal to use high-voltage

(4,160 volts) cables inby the last open crosscut to supply power to

longwall mining equipment considered acceptable alternative method.

Granted for the Loveridge No. 22 Mine with conditions for the 4,160-

volt longwall equipment.

Docket No.: M-95-104-C.

FR Notice: 60 FR 42921.

Petitioner: Old Hickory Coal Company.

Reg Affected: 30 CFR 77.1304(a).

Summary of Findings: Petitioner's proposal to blend recycled oil, a

petroleum-based lubrication oil recycled from equipment at the No. 7

Surface Mine blended with fuel oil to create ammonium nitrate/fuel oil

(ANFO) for use as a blasting agent considered acceptable alternative

method. Granted for the Peat's Branch No. 3 Mine with conditions.

Docket No.: M-95-105-C.

FR Notice: 60 FR 42921.

Petitioner: Hobet Mining, Inc.

Reg Affected: 30 CFR 77.1304(a).

Summary of Findings: Petitioner's proposal to blend recycled oil, a

petroleum-based lubrication oil recycled from equipment at the No. 7

Surface Mine blended with fuel oil to create ammonium nitrate/fuel oil

(ANFO) for use as a blasting agent considered acceptable alternative

method. Granted for the No. 7 Surface Mine with conditions.

Docket No.: M-95-106-C.

FR Notice: 60 FR 42921.

Petitioner: Hobet Mining, Inc.

Reg Affected: 30 CFR 77.1304(a).

Summary of Findings: Petitioner's proposal to blend recycled oil, a

petroleum-based lubrication oil recycled from equipment at the No. 21

Surface Mine blended with fuel oil to create ammonium nitrate/fuel oil

(ANFO) for use as a blasting agent considered acceptable alternative

method. Granted for the No. 21 Surface Mine with conditions.

Docket No.: M-95-111-C.

FR Notice: 60 FR 46871.

Petitioner: Solar Sources Underground, L.L.C.

Reg Affected: 30 CFR 75.1700.

Summary of Findings: Petitioner's proposal to plug and mine through

oil and gas wells considered acceptable alternative method. Granted for

the Monroe City Mine with conditions for mining through oil and gas

wells.

Docket No.: M-95-117-C.

FR Notice: 60 FR 52217.

Petitioner: Snyder Coal Company.

Reg Affected: 30 CFR 75.1200(d) & (j).

Summary of Findings: Petitioner's proposal to use cross-sections

instead of contour lines through the intake slope, at locations of rock

tunnel connections between veins, and at 1,000-foot intervals of

advance from the intake slope and to limit the required mapping of mine

workings above and below to those present within 100 feet of the veins

being mined except when veins are interconnected to other veins beyond

the 100-foot limit through rock tunnels considered acceptable

alternative method. Granted for the N & L Slope Mine with conditions

for the use of cross sections, in lieu of contour lines, limiting the

mapping of mines above or below this mine to those within 100 feet of

the vein being mined.

Docket No.: M-96-119-C.

FR Notice: 60 FR 52217.

Petitioner: Doverspike Bros. Coal Company, Inc.

Reg Affected: 30 CFR 75.380(d)(4).

Summary of Findings: Petitioner's proposal to maintain an alternate

escapeway that would have a travelway with a minimum width of four feet

and a total of 350 lineal feet instead of the required six-foot-wide

escapeway considered acceptable alternate method. Granted for the Dora

No. 6 Mine with conditions for top portion of the duel compartment

conveyor-belt slope for a distance of 350 feet from the surface.

Docket No.: M-95-123-C.

FR Notice: 60 FR 52218.

Petitioner: H & S Coal Company.

Reg Affected: 30 CFR 75.335.

Summary of Findings: Petitioner's request for a modification of the

standard to permit alternative methods of construction using wooden

materials of moderate size and weight due to the difficulty in

accessing previously driven headings and breasts containing

inaccessible abandoned workings; to accept a design criteria in the 10

psi range; and to permit the water trap to be installed in the gangway

seal and sampling tube in the monkey seal for seals installed in pairs

considered acceptable alternative method. Granted for the No. 1 Slope

Mine with conditions for seals installed in this mine.

Docket No.: M-95-128-C.

FR Notice: 60 FR 52218.

Petitioner: H & S Coal Company.

Reg Affected: 30 CFR 75.1100-2.

Summary of Findings: Petitioner's proposal to use only portable

fire extinguishers to replace existing requirements where rock dust,

water cars, and other water storage are not practical considered

acceptable alternative method. Granted for the No. 1 Slope Mine with

conditions for firefighting equipment in the working section.

Docket No.: M-95-129-C.

FR Notice: 60 FR 52218.

Petitioner: H & S Coal Company.

Reg Affected: 30 CFR 75.1200 (d) & (i).

Summary of Findings: Petitioner's proposal to use cross-sections

instead of contour lines through the intake slope, at locations of rock

tunnel connections between veins, and at 1,000-foot intervals of

advance from the intake slope and to limit the required mapping of the

mine workings above and below to those present within 100 feet of the

[[Page 17645]]

veins being mined except when veins are interconnected to other veins

beyond the 100-foot limit through rock tunnels considered acceptable

alternate method. Granted for the No. 1 Slope Mine with conditions for

the use of cross sections, in lieu of contour lines, limiting the

mapping of mines above or below this mine to those within 100 feet of

the vein being mined.

Docket No.: M-95-130-C.

FR Notice: 60 FR 52218.

Petitioner: H & S Coal Company.

Reg Affected: 30 CFR 75.1202-1(a).

Summary of Findings: Petitioner's proposal to revise and supplement

mine maps annually instead of every 6 months, as required, and to

update maps daily by hand notations considered acceptable alternative

method. Granted for the No. 1 Slope Mine with conditions for annual

revisions and supplements of the mine map.

Docket No.: M-95-131-C.

FR Notice: 60 FR 52219.

Petitioner: Performance Coal Company.

Reg Affected: 30 CFR 75.1002.

Summary of Findings: Petitioner's proposal to use high-voltage

(4,160 volts) cables to power longwall equipment considered acceptable

alternate method. Granted for the Upper Big Branch South Mine with

conditions for the 4,160-volt longwall equipment.

Docket No.: M-95-143-C.

FR Notice: 60 FR 54392.

Petitioner: Three Way Coal Company.

Reg Affected: 30 CFR 75.335.

Summary of Findings: Petitioner's request for a modification of the

standard to permit alternative methods of construction using wooden

materials of moderate size and weight due to the difficulty in

accessing previously driven headings and breasts containing

inaccessible abandoned workings; to accept a design criteria in the 10

psi range; and to permit the water trap to be installed in the gangway

seal and sampling tube in the monkey seal for seals installed in pairs

considered acceptable alternative method. Granted for the Little Vein

Slope Mine with conditions for seals installed in this mine.

Docket No.: M-95-147-C.

F.R. Notice: 60 FR 54392.

Petitioner: Three Way Coal Company.

Reg Affected: 30 CFR 75.1102.

Summary of Findings: Petitioner's proposal to use only portable

fire extinguishers to replace existing requirements where rock dust,

water cars, and other water storage are not practical considered

acceptable alternative method. Granted for the Little Vein Slope Mine

with conditions for firefighting equipment in the working section.

Docket No.: M-95-148-C.

FR Notice: 60 FR 54392.

Petitioner: Three Way Coal Company.

Reg Affected: 30 CFR 75.1200 (d) & (i).

Summary of Findings: Petitioner's proposal to use cross-sections

instead of contour lines through the intake slope, at locations of rock

tunnel connections between veins, and at 1,000-foot intervals of

advance from the intake slope and to limit the required mapping of the

mine workings above and below to those present within 100 feet of the

veins being mined except when veins are interconnected to other veins

beyond the 100-foot limit through rock tunnels considered acceptable

alternate method. Granted for the Little Vein Slope Mine with

conditions for the use of cross sections, in lieu of contour lines,

limiting the mapping of mines above or below this mine to those within

100 feet of the vein being mined.

Docket No.: M-95-149-C.

FR Notice: 60 FR 54392.

Petitioner: Three Way Coal Company.

Reg Affected: 30 CFR 75.1202-1(a).

Summary of Findings: Petitioner's proposal to revise and supplement

mine maps annually instead of every 6 months, as required, and to

update maps daily by hand notations considered acceptable alternative

method. Granted for the Little Vein Slope Mine with conditions for

annual revisions and supplements of the mine map.

Docket No.: M-95-151-C.

FR Notice: 60 FR 54393.

Petitioner: Heatherly Mining, Inc.

Reg Affected: 30 CFR 75.1700.

Summary of Findings: Petitioner's proposal to plug and mine through

certain abandoned wells which lie in the path of engineered mine

workers considered acceptable alternative method. Granted for the

Pollyanna No. 8 Mine with conditions for permanent plugging prior to

the mining within 300 feet of or through oil or gas wells.

Docket No.: M-95-158-C.

FR Notice: 60 FR 64079.

Petitioner: R. S. Coal Company.

Reg Affected: 30 CFR 75.335.

Summary of Findings: Petitioner's request for a modification of the

standard to permit alternative methods of construction using wooden

materials of moderate size and weight due to the difficulty in

accessing previously driven headings and breasts containing

inaccessible abandoned workings; to accept a design criteria in the 10

psi range; and to permit the water trap to be installed in the gangway

seal and sampling tube in the monkey seal for seals installed in pairs

considered acceptable alternative method. Granted for the No. 1 Slope

Mine with conditions for seals installed in this mine.

Docket No.: M-95-160-C.

FR Notice: 60 FR 64080.

Petitioner: R. S. Coal Company.

Reg Affected: 30 CFR 75.1100-2(a)(2).

Summary of Findings: Petitioner's proposal to use only portable

fire extinguishers to replace existing requirements where rock dust,

water cars, and other water storage are not practical considered

acceptable alternative method. Granted for the No. 1 Slope Mine with

conditions for firefighting equipment in the working section.

Docket No.: M-95-161-C.

FR Notice: 60 FR 64080.

Petitioner: R. S. Coal Company.

Reg Affected: 30 CFR 75.1200 (d) & (i).

Summary of Findings: Petitioner's proposal to use cross-sections

instead of contour lines through the intake slope, at locations of rock

tunnel connections between veins, and at 1,000-foot intervals of

advance from the intake slope and to limit the required mapping of the

mine workings above and below to those present within 100 feet of the

veins being mined except when veins are interconnected to other veins

beyond the 100-foot limit through rock tunnels considered acceptable

alternate method. Granted for the No. 1 Slope Mine with conditions for

the use of cross sections, in lieu of contour lines, limiting the

mapping of mines above or below this mine to those within 100 feet of

the vein being mined.

Docket No.: M-95-162-C.

FR Notice: 60 FR 64080.

Petitioner: R. S. Coal Company.

Reg Affected: 30 CFR 75.1202-1(a).

Summary of Findings: Petitioner's proposal to revise and supplement

mine maps annually instead of every 6 months, as required, and to

update maps daily by hand notations considered acceptable alternative

method. Granted for the No. 1 Slope Mine with conditions for annual

revisions and supplements of the mine map.

Docket No.: M-95-163-C.

FR Notice: 60 FR 64080.

Petitioner: R. S. Coal Company.

Reg Affected: 30 CFR 75.804(a).

Summary of Findings: Petitioner's proposal to use a high-voltage

(4,160-volt) cable with an internal ground check conductor smaller than

No. 10 (A.W.G.) as a part of its longwall mining system considered

acceptable alternative method. Granted for the

[[Page 17646]]

Blacksville No. 2 Mine with conditions for Consolidation Coal

Company's, Blacksville No. 2 Mine's longwall system.

Docket No.: M-95-164-C.

FR Notice: 60 FR 64080.

Petitioner: The Pittsburg & Midway Coal Mining Company.

Reg Affected: 30 CFR 75.1700.

Summary of Findings: Petitioner's proposal to plug and mine through

oil and gas wells considered acceptable alternative method. Granted for

the North River No. 1 Mine with conditions.

Docket No.: M-96-001-C.

FR Notice: 61 FR 13881.

Petitioner: Energy West Mining Company.

Reg Affected: 30 CFR 75.326 (now 75.350).

Summary of Findings: Petitioner's request to amend paragraph

III(c)(4) and paragraph (o) of MSHA's Proposed Decision and Order (PDO)

for its previously granted petition to permit the use of longwall

mining with two entries in the longwall panels under deep cover at the

Deer Creek Mine, Case No. 86-MSHA-3, Docket No. M-85-17-C considered

acceptable. Granted with conditions. The PDO is modified to permit the

use of non-Part 36 diesel-powered equipment in the two entry system,

except in those areas where permissible electric face equipment is

required and only Part 36 approved diesel equipment is allowed.

Docket No.: M-96-022-C.

FR Notice: 61 FR 17734.

Petitioner: KenAmerican Resources, Inc.

Reg Affected: 30 CFR 75.380(g).

Summary of Findings: Petitioner's request for a modification of the

standard to allow the primary escapeway for the No. 9 Slope to be

separated from the belt entries after completion of the two-phase

Initial Development Stage (the normal course of mining in the No. 9

Seam, the time required from the commencement of mining until

connection to the airshaft) considered acceptable alternative method.

Granted for the No. 9 Slope Mine with conditions for the slope, during

Phase 2 development, until development can progress to the airshaft and

make the connections.

Docket No.: M-96-030-C.

FR Notice: 61 FR 20544.

Petitioner: Amax Coal Company.

Reg Affected: 30 CFR 75.503.

Summary of Findings: Petitioner's proposal to extend the length of

portable trailing cables to 825 feet to carry electrical power from the

working face transformer to the mobile roof supports considered

acceptable alternative method. Granted with conditions for the four(4)

Voest-Alpine Mobile roof supports, Model No. ABLS130/275-540, Approved

No. 2G-3736A.3, Serial Nos. 111, 112, 113 and 114 used in second mining

at the Wabash mine.

Docket No.: M-96-032-C.

FR Notice: 61 FR 20544.

Petitioner: Pittsburg & Midway Coal Mining Company.

Reg Affected: 30 CFR 75.325(b).

Summary of Findings: Petitioner's proposal to provide positive

ventilation by using the stopping line constructed to separate the

intake and return air courses in the rooms previously developed on the

same panel and maintained in accordance with the requirements in 30 CFR

75.333; to construct permanent stopping lines when rooms are driven

more than 600 feet deep and to use temporary stopping lines when rooms

are driven 600 feet deep or less, as measured from the centerline of

the panel from which the rooms are driven; and to measure the air flow

volumes in accordance with 30 CFR 75.360(c)(1) and 75.362(c)(1)

considered acceptable alternative method. Granted for the Sebree No. 1

Mine with conditions for the relocation of the site at which air

measurements shall be taken in the last open crosscut.

Docket No.: M-96-033-C.

FR Notice: 61 FR 20544.

Petitioner: Pittsburg & Midway Coal Mining Company.

Reg Affected: 30 CFR 75.360(c)(1).

Summary of Findings: Petitioner's proposal to provide positive

ventilation by using the stopping line constructed to separate the

intake and return air courses in the rooms previously developed on the

same panel and maintained in accordance with the requirements in 30 CFR

75.333; to construct permanent stopping lines when rooms are driven

more than 600 feet deep and to use temporary stopping lines when rooms

are driven 600 feet deep or less, as measured from the centerline of

the panel from which the rooms are driven; and to measure the air flow

volumes in accordance with 30 CFR 75.360(c)(1) and 75.362(c)(1)

considered acceptable alternative method. Granted for the Sebree No. 1

Mine with conditions for the relocation of the site at which air

measurements shall be taken in the last open crosscut.

Docket No.: M-96-034-C.

FR Notice: 61 FR 20544.

Petitioner: Pittsburg & Midway Coal Mining Company.

Reg Affected: 30 CFR 75.362(c)(1).

Summary of Findings: Petitioner's proposal to provide positive

ventilation by using the stopping line constructed to separate the

intake and return air courses in the rooms previously developed on the

same panel and maintained in accordance with the requirements in 30 CFR

75.333; to construct permanent stopping lines when rooms are driven

more than 600 feet deep and to use temporary stopping lines when rooms

are driven 600 feet deep or less, as measured from the centerline of

the panel from which the rooms are driven; and to measure the air flow

volumes in accordance with 30 CFR 75.360(c)(1) and 75.362(c)(1)

considered acceptable alternative method. Granted for the Sebree No. 1

Mine with conditions for the relocation of the site at which air

measurements shall be taken in the last open crosscut.

Docket No.: M-96-035-C.

FR Notice: 61 FR 20544.

Petitioner: Pittsburg & Midway Coal Mining Company.

Reg Affected: 30 CFR 75.1700.

Summary of Findings: Petitioner's proposal to mine through oil and

gas wells considered acceptable alternative method. Granted for the

Sebree No. 1 Mine with conditions for mining-through oil and gas wells,

in the Kentucky No. 9 coalbed.

Docket No.: M-95-004-M.

FR Notice: 60 FR 18148.

Petitioner: Holnam, Inc.

Reg Affected: 30 CFR 56.6901.

Summary of Findings: Petitioner's proposal to destroy substandard

model rocket engines containing black powder and desensitized black

powder sweepings in conjunction with high explosives routinely

detonated in mining activities considered acceptable alternative

method. Granted for the Portland Quarry with conditions.

Docket No.: M-95-008-M.

FR Notice: 60 FR 29715.

Petitioner: Cyprus Bagdad Copper Corporation.

Reg Affected: 30 CFR 56.6309.

Summary of Findings: Petitioner's proposal to blend recycled oil

with fuel oil in preparing ammonium nitrate-fuel oil (ANFO) for use as

a blasting agent considered acceptable alternative method. Granted for

the Bagdad Mine with conditions.

Docket No.: M-94-047-M.

FR Notice: 60 FR 3437.

Petitioner: Pluess-Staufer (California), Inc.

Reg Affected: 30 CFR 56.13020.

Summary of Findings: Petitioner's proposal to establish blow-off

stations with a low pressure (2-6 psi) compressed airflow at various

areas in the plant for employees to blow dust off their clothing

considered acceptable

[[Page 17647]]

alternative method. Granted for the Limestone Plant with conditions.

[FR Doc. 97-9241 Filed 4-9-97; 8:45 am]

BILLING CODE 4510-43-P