Energy Conservation Program for Consumer Products: Decision and Order Granting a Waiver From the Furnace Test Procedure to Nordyne

Federal RegisterMar 27, 1997

Ask Donna

What actually matters in this document.

Text

DEPARTMENT OF ENERGY

Office of Energy Efficiency and Renewable Energy

[Case No. F-088]

Energy Conservation Program for Consumer Products: Decision and

Order Granting a Waiver From the Furnace Test Procedure to Nordyne

AGENCY: Office of Energy Efficiency and Renewable Energy, Department of

Energy.

ACTION: Decision and Order.

-----------------------------------------------------------------------

SUMMARY: Notice is given of the Decision and Order (Case No. F-088)

granting a Waiver to Nordyne from the existing Department of Energy

(DOE or Department) test procedure for furnaces. The Department is

granting Nordyne's Petition for Waiver regarding blower time delay in

calculation of Annual Fuel Utilization Efficiency (AFUE) for its G5RD

and G5RL series furnaces.

FOR FURTHER INFORMATION CONTACT: Mr. Cyrus H. Nasseri, U.S. Department

of Energy, Office of Energy Efficiency and Renewable Energy, Mail

Station EE-431, Forrestal Building, 1000 Independence Avenue, SW.,

Washington, DC 20585-0121, (202) 586-9138 or Mr. Eugene Margolis, Esq.,

U.S. Department of Energy, Office of General Counsel, Mail Station GC-

72, Forrestal Building, 1000 Independence Avenue, SW., Washington, DC

20585-0103, (202) 586-9507.

SUPPLEMENTARY INFORMATION: In accordance with 10 CFR 430.27(j), notice

is hereby given of the issuance of the Decision and Order as set out

below. In the Decision and Order, Nordyne has been granted a Waiver for

its G5RD and G5RL series furnaces permitting the company to use an

alternate test method in determining AFUE.

Issued in Washington, DC, on March 19, 1997.

Christine A. Ervin,

Assistant Secretary, Energy Efficiency and Renewable Energy.

Decision and Order--Department of Energy, Office of Energy

Efficiency and Renewable Energy

In the Matter of: Nordyne (Case No. F-088).

Background

The Energy Conservation Program for Consumer Products (other than

automobiles) was established pursuant to the Energy Policy and

Conservation Act, Public Law 94-163, 89 Stat. 917, as amended (EPCA),

which requires DOE to prescribe standardized test procedures to measure

the energy consumption of certain consumer products, including

furnaces. The intent of the test procedures is to provide a comparable

measure of energy consumption that will assist consumers in making

purchasing decisions. These test procedures appear at 10 CFR Part 430,

Subpart B.

The Department amended the prescribed test procedures by adding 10

CFR 430.27 to create a waiver process. 45 FR 64108, September 26, 1980.

Thereafter, DOE further amended its appliance test procedure waiver

process to allow the Assistant Secretary for Energy Efficiency and

Renewable Energy (Assistant Secretary) to grant an Interim Waiver from

test procedure requirements to manufacturers that have petitioned DOE

for a waiver of such prescribed test procedures. 51 FR 42823, November

26, 1986.

The waiver process allows the Assistant Secretary to waive

temporarily test procedures for a particular basic model when a

petitioner shows that the basic model contains one or more design

characteristics which prevent testing according to the prescribed test

procedures or when the prescribed test procedures may evaluate the

basic model in a manner so unrepresentative of its true energy

consumption as to provide materially inaccurate comparative data.

Waivers generally remain in effect until final test procedure

amendments become effective, resolving the problem that is the subject

of the waiver.

Nordyne filed a ``Petition for Waiver,'' dated September 6, 1996,

in accordance with section 430.27 of 10 CFR Part 430. The Department

published in the Federal Register on October 22, 1996, Nordyne's

Petition and solicited comments, data and information respecting the

Petition. 61 FR 54783, October 22, 1996. Nordyne also filed an

``Application for Interim Waiver'' under section 430.27(b)(2), which

DOE granted on October 15, 1996. 61 FR 54783, October 22, 1996.

No comments were received concerning either the ``Petition for

Waiver'' or the ``Application for Interim Waiver.'' The Department

consulted with The Federal Trade Commission (FTC) concerning the

Nordyne Petition. The FTC did not have any objections to the issuance

of the waiver to Nordyne.

Assertions and Determinations

Nordyne's Petition seeks a waiver from the DOE test provisions that

require a 1.5-minute time delay between the ignition of the burner and

the starting of the circulating air blower. Nordyne requests the

allowance to test using a 30-second blower time delay when testing its

G5RD and G5RL series furnaces. Nordyne states that since the 30-second

delay is indicative of how these models actually operate, and since

such a delay results in an improvement in AFUE of approximately 2.0

percent, the Petition should be granted.

Under specific circumstances, the DOE test procedure contains

exceptions which allow testing with blower delay times of less than the

prescribed 1.5-minute delay. Nordyne indicates that it is unable to

take advantage of any of these exceptions for its G5RD and G5RL series

furnaces.

Since the blower controls incorporated on the Nordyne furnaces are

designed to impose a 30-second blower delay in every instance of start

up, and since the current test procedure provisions do not specifically

address this type of control, DOE agrees that a waiver should be

granted to allow the 30-second blower time delay when testing the

Nordyne G5RD and G5RL series furnaces. Accordingly, with regard to

testing the G5RD and G5RL series furnaces, today's Decision and Order

exempts Nordyne from the existing test procedure provisions regarding

blower controls and allows testing with the 30-second delay.

It is, therefore, ordered That:

(1) The ``Petition for Waiver'' filed by Nordyne (Case No. F-088)

is hereby granted as set forth in paragraph (2) below, subject to the

provisions of paragraphs (3), (4), and (5).

(2) Notwithstanding any contrary provisions of Appendix N of 10 CFR

Part 430, Subpart B, Nordyne shall be permitted to test its G5RD and

G5RL series furnaces on the basis of the test procedure specified in 10

CFR Part 430, with modifications set forth below:

(I) Section 3.0 of Appendix N is deleted and replaced with the

following paragraph:

3.0 Test Procedure. Testing and measurements shall be as specified

in section 9 in ANSI/ASHRAE Standard 103-82 with the exception of

sections 9.2.2, 9.3.1, and 9.3.2, and the inclusion of the following

additional procedures:

(ii) Add a new paragraph 3.10 to Appendix N as follows:

3.10 Gas-and Oil-Fueled Central Furnaces. The following paragraph

is in

[[Page 14677]]

lieu of the requirement specified in section 9.3.1 of ANSI/ASHRAE

Standard 103-82. After equilibrium conditions are achieved following

the cool-down test and the required measurements performed, turn on the

furnace and measure the flue gas temperature, using the thermocouple

grid described above, at 0.5 and 2.5 minutes after the main burner(s)

comes on. After the burner start-up, delay the blower start-up by 1.5

minutes (t-), unless: (1) the furnace employs a single motor to drive

the power burner and the indoor air circulating blower, in which case

the burner and blower shall be started together; or (2) the furnace is

designed to operate using an unvarying delay time that is other than

1.5 minutes, in which case the fan control shall be permitted to start

the blower; or (3) the delay time results in the activation of a

temperature safety device which shuts off the burner, in which case the

fan control shall be permitted to start the blower. In the latter case,

if the fan control is adjustable, set it to start the blower at the

highest temperature. If the fan control is permitted to start the

blower, measure time delay, (t-), using a stopwatch. Record the

measured temperatures. During the heat-up test for oil-fueled furnaces,

maintain the draft in the flue pipe within 0.01 inch of

water column of the manufacturer's recommended on-period draft.

(iii) With the exception of the modifications set forth above,

Nordyne shall comply in all respects with the test procedures specified

in Appendix N of 10 CFR Part 430, Subpart B.

(3) The Waiver shall remain in effect from the date of issuance of

this Order until DOE prescribes final test procedures appropriate to

the G5RD and G5RL series furnaces manufactured by Nordyne.

(4) This Waiver is based upon the presumed validity of statements,

allegations, and documentary materials submitted by the petitioner.

This Waiver may be revoked or modified at any time upon a determination

that the factual basis underlying the Petition is incorrect.

(5) Effective March 19, 1997, this Waiver supersedes the Interim

Waiver granted Nordyne on October 15, 1996. 61 FR 54783, October 22,

1996 (Case No. F-088).

Issued in Washington, DC, on March 19,1997.

Christine A. Ervin,

Assistant Secretary, Energy Efficiency and Renewable Energy.

[FR Doc. 97-7794 Filed 3-26-97; 8:45 am]

BILLING CODE 6450-01-P