DEPARTMENT OF TRANSPORTATION

Research and Special Programs Administration

49 CFR Part 194

[Docket No. PS-130; Amdt. 194-1]

RIN 2137-AD12

Pipeline Safety: Change in Response Plan Review Cycle

AGENCY: Research and Special Program Administration (RSPA), DOT.

ACTION: Direct final rule.

-----------------------------------------------------------------------

SUMMARY: This direct final rule changes the reporting cycle for

facility response plan submissions to 5 years for operators who are

required to submit facility response plans to RSPA. Pipeline operators

were previously required to submit facility response plans every 3

years.

OPS is undertaking this change to improve safety by ensuring

consistency between OPS requirements and those of the other federal

agencies under the Oil Pollution Act of 1990, and encouraging the use

of integrated plans, while easing the burden on the regulated

community. The comments to the docket have fully supported this change.

EFFECTIVE DATES: This direct final rule takes effect February 23, 1998.

If RSPA does not receive adverse comment or notice of intent to file an

adverse comment by January 23, 1998, the rule will become effective on

the date specified. RSPA will issue a subsequent notice in the Federal

Register by February 9, 1998 after the close of the comment period to

confirm that fact and reiterate the effective date. If an adverse

comment or a notice of intent to file an adverse comment is received,

RSPA will issue a timely notice in the Federal Register to confirm that

fact and RSPA would withdraw direct final rule in whole or in part.

RSPA may then incorporate the adverse comment into a subsequent direct

final rule or may publish a notice of proposed rulemaking.

ADDRESSES: Send comments in duplicate to the Dockets Unit, room 8421,

Research and Special Programs Administration, U.S. Department of

Transportation, 400 Seventh Street, S.W., Washington, DC 20590.

Identify the docket number stated in the heading of this notice. All

comments and docketed material will be available for inspection and

copying in room 8419 between 8:30 a.m. and 5:00 p.m. each business day.

FOR FURTHER INFORMATION CONTACT: Jim Taylor, (202) 366-8860, or by e-

mail ([email protected]), regarding the subject matter of this

Notice; or the RSPA Dockets Unit, (202) 366-5046, for copies of this

final rule or other material in the docket. General information about

OPS programs can be obtained by accessing OPS'' Internet home page at

ops.dot.gov.

SUPPLEMENTARY INFORMATION:

Background

In recent years, several catastrophic oil spills have damaged the

marine environment of the United States. These spills have resulted in

extensive environmental impact, including the loss of fish and

wildlife. In response to these catastrophic spills, Congress passed the

Oil Pollution Act of 1990, 33 U.S.C. 2701-2761 (OPA 90). OPA 90 amended

section 1321(j) of the Federal Water Pollution Control Act (FWPCA) (33

U.S.C. 1251-1387), and established a new national planning and response

system, including a requirement for the development of facility

response plans.

The FWPCA requires the President to issue regulations that require

the operator of a tank vessel, an onshore facility, and certain

offshore facilities, to prepare and submit to the President, a plan for

responding, to the maximum extent practicable, to a worst case oil

discharge and to a substantial threat of such a discharge. 33 U.S.C.

1321(j)(5). The FWPCA also requires the President to review and approve

facility response plans and periodic reviews of each plan. 33 U.S.C.

1321(j)(5)(D).

To be consistent with OPA 90 and FWPCA plan submission requirements

of the Environmental Protection Agency and U.S. Coast Guard, RSPA is

revising 49 CFR Sec. 194.121(b) to require a response plan to be

resubmitted every 5 years for review and approval. For significant and

substantial harm facilities, the plan shall be resubmitted 5 years

after the latest approval date by RSPA. For substantial harm

facilities, operators must resubmit the plan to RSPA 5 years after the

date of initial submission and every 5 years thereafter.

In the event there are no changes in the plan, the operator must

submit a written certification to RSPA stating that there are no

changes to the plan previously submitted to RSPA. Upon receipt of the

certification, RSPA will review the existing plan and, for significant

and substantial harm facilities, RSPA will re-approve the plan.

Substantial harm facility plans will be reviewed only. Although the

current 3-year cycle for all plans is ending, when this rule becomes

effective there will be no requirement to

[[Page 67293]]

resubmit existing response plans until 2 years from now.

Regulatory History

RSPA published an interim final rule (IFR) on January 5, 1993 (58

FR 244). This interim final rule implemented provisions of OPA 90. With

limited exceptions, this direct final rule applies to all onshore

transportation-related oil pipelines whether or not such pipelines are

exempt from existing Federal pipeline safety regulations or statutes.

RSPA conducted a public meeting in New Orleans, Louisiana on January

27, 1997, to solicit feedback from interested parties on implementation

of the regulation and revisions to the IFR. A copy of the transcript of

the public meeting is available in the docket. This direct final rule

modifies the interim final rule, 49 CFR Part 194 (58 FR 244, January 5,

1993). RSPA intends to issue a final rule for 49 CFR Part 194 at a

later date.

Rulemaking Notices and Analyses

Executive Order 12866 and DOT Regulatory Policies and Procedures

This direct final rule is not a significant regulatory action under

section 3(f) of Executive Order 12866 (58 FR 51735) and, therefore, was

not reviewed by the Office of Management and Budget (OMB). The direct

final rule is not significant under the Regulatory Policies and

Procedures of the Department of Transportation (44 FR 11034).

Executive Order 12612

The direct final rule has been analyzed with the principles and

criteria in Executive Order 12612 (``Federalism'') (52 FR 41685), and

does not have sufficient federalism impacts to warrant the preparation

of a federalism assessment.

Regulatory Flexibility Act

Based on the facts available, I certify that this direct final rule

will not have a significant economic impact on a substantial number of

small entities.

Paperwork Reduction Act

There are no new information collection requirements in this direct

final rule. In fact, this rulemaking eases the paperwork burden on

pipeline operators by reducing the reporting frequency from three to

five years.

Unfunded Mandates Reform Act of 1995

This direct final rule does not impose unfunded mandates under the

Unfunded Mandates Reform Act of 1995. It does not result in costs of

$100 million or more to either State, local, or tribal goverments, in

the aggregate, or to the private sector, and is the least burdensome

alternative that achieves the objective of the direct final rule.

List of Subjects in 49 CFR Part 194

Oil pollution, Facility Response Plan, Pipeline safety.

In consideration of the foregoing, RSPA amends part 194 of title 49

of the Code of Federal Regulations as follows:

1. The authority citation for Part 194 continues to read as

follows:

Authority: 33 U.S.C. 1231, 1321(j)(1)(C), (j)(5) and (j)(6);

sec. 2, E.O. 12777, 56 FR 54757, 3 CFR, 1991 Comp., p. 351; 49 CFR

1.53.

2. Section 194.121(a) is revised to read as follows:

Sec. 194.121 Response plan review and update procedures.

(a) Each operator shall review its response plan at least every 5

years from the date of submission and modify the plan to address new or

different operating conditions or information included in the plan.

* * * * *

Issued in Washington, DC on December 16, 1997.

Kelley S. Coyner,

Acting Administrator.

[FR Doc. 97-33289 Filed 12-23-97; 8:45 am]

BILLING CODE 4910-60-P

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.