Pressure Testing Older Hazardous Liquid and Carbon Dioxide Pipelines

Federal RegisterOct 21, 1997

Ask Donna

What actually matters in this document.

Text

DEPARTMENT OF TRANSPORTATION

Research and Special Programs Administration

49 CFR Part 195

[Docket No. PS-121; Amdt. 195-58]

RIN 2137-AD 05

Pressure Testing Older Hazardous Liquid and Carbon Dioxide

Pipelines

AGENCY: Research and Special Programs Administration (RSPA), DOT.

ACTION: Direct final rule; extension of time for compliance.

-----------------------------------------------------------------------

SUMMARY: This direct final rule extends the time for compliance with

the requirements for pressure testing of older hazardous liquid and

carbon dioxide pipelines. Plans for testing, or establish maximum

operating pressure, which were to be completed by December 7, 1997,

would now be required by December 7, 1998. The dates for actual

completion of the testing, previously December 7, 1999, and December 7,

2002, are also extended by one year. RSPA is extending these compliance

dates to allow time to complete a rulemaking based on the American

Petroleum Institute's (API) petition for a risk-based alternative to

the required pressure testing rule. In a separate notice, RSPA intends

to issue a proposed rule for a risk-based alternative to the existing

pressure testing rule.

DATES: Effective date: This direct final rule takes effect January 20,

1998. If RSPA does not receive any adverse comment or notice of intent

to file an adverse comment by December 22, 1997, the rule will become

effective on the date specified. RSPA will issue a subsequent document

in the Federal Register by January 5, 1998, to confirm that fact and

reiterate the effective date. If an adverse comment or notice of intent

to file an adverse comment is received, RSPA will issue a timely notice

in the Federal Register to confirm that fact and RSPA would withdraw

the direct final rule in whole or in part. RSPA may then incorporate

the adverse comment into a subsequent direct final rule or may publish

a notice of proposed rulemaking.

Compliance dates: The deadline that establishes regulations for

planning and scheduling pressure testing is to be extended to December

7, 1998. All other deadlines are extended by a year.

ADDRESSES: Written comments must be submitted in duplicate and mailed

to the Docket Facility, U.S. Department of Transportation, Plaza 401,

400 Seventh Street SW., Washington, DC 20590-0001. Comments should

identify the docket number and the RSPA rulemaking number. All comments

received before December 22, 1997, will be considered before final

action is taken. Late-filed comments will be considered so far as

practicable. All comments and other docketed material will be available

for inspection and copying in room 401 Plaza between the hours of 10

a.m. and 5 p.m., Monday through Friday, except Federal holidays.

FOR FURTHER INFORMATION CONTACT: Mike Israni, (202) 366-4571, e-mail:

[email protected], regarding the subject matter of this

document, or the Dockets Unit (202) 366-9329, for copies of this

document or other information in the docket.

SUPPLEMENTARY INFORMATION:

API Proposal

In a petition dated June 23, 1995, API submitted a risk-based

alternative to the pressure testing rule and requested that RSPA delay

implementation of the rule until the API proposal was given full

consideration. A copy of the API proposal is available in the docket.

API argued that the rule on pressure testing older hazardous liquid and

carbon dioxide pipelines presents an opportunity to apply a risk-based

approach to pressure testing, and proposed a risk-based alternative to

the final rule issued on June 7, 1994 (59 FR 29379).

RSPA has been working with the pipeline industry to develop a risk

management framework for pipeline regulation and decided to carefully

evaluate the API proposal. Because substantial planning is required

before pressure testing older pipelines, an extension of time for

compliance was needed to avoid unnecessary costs in planning.

RSPA decided to initiate rulemaking on the API proposal. A notice

of proposed rulemaking on risk-based alternative to pressure testing of

older hazardous liquid and carbon dioxide pipelines is being published

separately.

RSPA published a Final Rule (Docket PS-121; 61 FR 43026; August 20,

1996) extending the compliance deadline to plan and schedule pressure

testing or establish maximum operating pressure to December 7, 1997.

The dates for actual completion of testing were extended by one year.

To determine merits of the API proposal, RSPA held a public meeting

on March 25, 1996. On May 8 and November 6, 1996, and again on May 7,

1997, RSPA briefed the Technical Hazardous Liquid Pipeline Safety

[[Page 54592]]

Committee (THLPSSC) on the API proposal and changes proposed by RSPA.

RSPA also discussed those changes at the API conference on March 13,

1997, in Dallas, Texas.

RSPA received several comments from the industry during these

meetings that all the compliance deadlines for the current pressure

test rule should be extended. Industry argued that they were not sure

what changes RSPA might suggest in the risk-based alternative

rulemaking, so they could not plan in advance.

RSPA agrees with the comments about the need for extension of the

comment period while rulemaking on the risk-based alternative is

conducted. These new compliance dates are as follows:

--Before December 7, 1998, plan and schedule testing; or establish the

pipeline's maximum operating pressure under Sec. 195.406(a)(5).

--Before December 7, 2000, pressure test each pipeline containing more

than 50 percent by mileage of electric resistance welded pipe

manufactured before 1970; and at least 50 percent of the mileage of all

other pipelines; and

--Before December 7, 2003, pressure test the remainder of the pipeline

mileage.

Regulatory Analyses and Notices

Executive Order 12866 and DOT Policies and Procedures

The Office of Management and Budget (OMB) does not consider this

final rule to be a significant regulatory action under section 3(f) of

Executive Order 12866. Therefore, OMB did not review the direct final

rule under that order. Also, DOT does not consider the direct final

rule to be significant under its regulatory policies and procedures (44

FR 11034, February 26, 1979). This extension of compliance dates does

not warrant preparation of a Regulatory Evaluation.

Executive Order 12612

We analyzed the final rule under the principles and criteria in

Executive Order 12612 (``Federalism''). The final rule does not have

sufficient federalism impacts to warrant preparation of a federalism

assessment.

Regulatory Flexibility Act

I certify, under section 605 of the Regulatory Flexibility Act,

that this final rule will not have a significant economic impact on a

substantial number of small entities.

Unfunded Mandates Reform Act of 1995

This rule does not impose unfunded mandates under the Unfunded

Mandates Reform Act of 1995. It does not result in costs of $100

million or more to either State, local, or tribal governments, in the

aggregate, or to the private sector, and is the least burdensome

alternative that achieves the objective of the rule.

List of Subjects in 49 CFR Part 195

Carbon dioxide, Petroleum, Pipeline safety, Reporting and

recordkeeping requirements.

In consideration of the foregoing, RSPA amends part 195 of title 49

of the Code of Federal Regulations as follows:

PART 195--[AMENDED]

1. The authority citation for part 195 continues to read as

follows:

Authority: 49 U.S.C. 60102, 60104, 60108, 60109; and 49 CFR

1.53.

2. Section 195.302, paragraphs (c)(1), introductory text, and

(c)(2)(i), introductory text, and (c)(2)(ii) are revised to read as

follows:

Sec. 195.302 General requirements.

* * * * *

(c) * * *

(1) Before December 7, 1998, for each pipeline each operator

shall--

* * * * *

(2) * * *

(i) Before December 7, 2000, pressure test--

* * * * *

(ii) Before December 7, 2003, pressure test the remainder of the

pipeline mileage.

* * * * *

Issued in Washington, DC, on October 15, 1997.

Kelley S. Coyner,

Acting Administrator.

[FR Doc. 97-27740 Filed 10-20-97; 8:45 am]

BILLING CODE 4910-60-P