DEPARTMENT OF DEFENSE

Department of the Army

Corps of Engineers

Intent To Prepare A Draft Environmental Impact Statement (DEIS)

for the Proposed Avila Beach Remediation Plan in San Luis Obispo

County, CA

AGENCY: U.S. Army Corps of Engineers, DoD.

ACTION: Notice of intent.

-----------------------------------------------------------------------

SUMMARY: Pursuant to Section 102(2)(c) of the National Environmental

Policy Act of 1969 (NEPA) as implemented by the regulations of the

Council on Environmental Quality (CEQ), 40 CFR 1500-1508, Corps of

Engineers announces its intent to prepare a Draft Environmental Impact

Statement (DEIS) to evaluate the potential effects of the proposed

Avila Beach Remediation Plan on the environment. To eliminate

duplication of paperwork, the Corps of Engineers intends on combining

the DEIS with the existing Draft Environmental Impact Report (DEIR)

prepared by the County of San Luis Obispo and California Regional Water

Quality Control Board per 40 CFR 1560.2 and 1506.4.

FOR FURTHER INFORMATION CONTACT:

Any questions regarding the proposed action and/or issuance of the DEIS

may be directed to: Ms. Tiffany Welch, (805) 641-2935, Regulatory

Branch, U.S. Army Corps of Engineers, 2151 Alessandro Drive, Suite 255,

Ventura, California 93001 (e mail: [email protected]).

SUPPLEMENTARY INFORMATION:

1. Background

Union Oil of California (UNOCAL) has spilled petroleum products,

including gasoline, diesel and crude oil, to soil and ground water

beneath the beach and intertidal area of Avila Beach.

The beach plume runs from Avila Beach Drive to about even with San

Luis Street with an additional area off of San

[[Page 48631]]

Antonio Street. Contamination has been identified at depths ranging

from 0.5 feet at the west end of the beach to 25 feet near the pier.

The highest concentration level observed in a sample has been 61,000

parts per million (ppm) located near the pier at about the high tide

line at a depth of 11.5 feet. The average total recoverable hydrocarbon

(TPH) value is approximately 4,100 ppm at an average depth of 10 feet.

The highest benzene, toluene, ethylbenzene, and xylene (BTEX) value

observed has been 760 ppm, located down from San Francisco Street at a

depth of 13.5 feet.

The intertidal plume extends seaward along the pier to at least a

distance of 400 feet south of Front Street with TPH concentrations as

high as 63,000 ppm. The seaward extent of this plume has not been

determined. This part of the plume is covered with water except for

periods with extremely low tides during full and new moons.

2. Proposed Action

UNOCAL has applied to the Corps of Engineers (Corps) for a

Department of the Army permit to conduct remediation activities

oceanward of the high tide line (7.2 feet Mean Lower Low Water) at

Avila Beach. Current activities that lie within the Corps' regulatory

jurisdiction include the installation of wave energy dissipator

cofferdams, solidification of hydrocarbon and hydrocarbon-affected

sediment underlying the East Beach area, and no action for

contamination in the intertidal zone.

3. Scope of Analysis

The scope of analysis of the DEIS includes the entire Avila Beach

area, intertidal zone, and San Luis Obispo Creek estuary located in the

community of Avila Beach, San Luis Obispo County, California.

4. Alternatives

The following alternative remedial technologies, and combinations

thereof, are being considered: (1) No action; (2) Excavation; (3) Steam

Stripping; and (4) Oxygen/Nutrient Delivery.

5. Scoping Process

a. Federal, State, and local agencies and other interested private

citizens and organizations are encouraged to send their written

comments to Ms. Tiffany Welch at the address provided above. This

scoping comment period will expire 30 days from this date of this

notice.

b. Significant issues to be analyzed in depth in the DEIS include

biological resources, surface and ground water quality, air quality,

recreation, erosion/sedimentation, noise, transportation, aesthetics

and socioeconomics.

c. Coordination will be undertaken with the U.S. Environmental

Protection Agency, U.S. Fish and Wildlife Service, California

Department of Fish and Game, California Regional Water Quality Control

Board, and the California Coastal Commission.

6. Scoping Meetings

A scoping meeting will be held on October 7, 1997 from 6-8 p.m. to

assess preliminary issues relative to UNOCAL's proposed remediation

plan. The scoping meeting will be held on the top floor of the

Community Center, 191 San Miguel Street, Avila Beach. Participation in

the scoping meeting by Federal, state, and local agencies, and other

interested private citizens and organizations is encouraged.

7. DEIS Schedule

The current schedule estimates that the DEIS will be available for

public review and comment in November 1997.

Robert L. Davis,

Colonel, Corps of Engineers, District Engineer.

[FR Doc. 97-24573 Filed 9-15-97; 8:45 am]

BILLING CODE 3710-KF-M

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.