DEPARTMENT OF THE INTERIOR
Bureau of Land Management
[NV-030-1992-02]
Notice of Availability for the Olinghouse Mine Project Draft
Environmental Impact Statement and Notice of Comment Period and Public
Open-Houses
AGENCY: Bureau of Land Management, Department of the Interior.
COOPERATING AGENCIES: U.S. Fish & Wildlife Service, U.S. Army Corps of
Engineers, U.S. Bureau of Indian Affairs, Washoe County, Pyramid Lake
Paiute Tribe, Lyon County-Town of Fernley.
ACTION: Notice of availability for the Olinghouse Mine Project Draft
Environmental Impact Statement (EIS), Washoe County, Nevada; and Notice
of Comment Period and Public Open-Houses.
-----------------------------------------------------------------------
SUMMARY: Pursuant to section 102(2)(C) of the National Environmental
Policy Act, 40 CFR parts 1500-1508, and 43 CFR part 3809, notice is
given that the Bureau of Land Management (BLM) has prepared, with the
assistance of a third-party consultant, a Draft EIS on the proposed
Olinghouse Mine Project, and has made copies available for public and
agency review.
DATES: Written comments on the Draft EIS must be submitted or
postmarked to the BLM no later than November 14, 1997. Oral and/or
written comments may also be presented at two public open-houses, to be
held:
October 20, 1997, 5:00-8:00 p.m., Washoe Co. Commissioners Chambers--
Reno, NV
October 21, 1997 5:00-8:00 p.m., Fernley Town Complex--Fernley, NV
ADDRESSES: Written comments on the Draft EIS should be addressed to:
Bureau of Land Management, Carson City Field Office, 5665 Morgan Mill
Road, Carson City, NV 89701, Attn.: Terri Knutson, Olinghouse Mine EIS
Project Manager. A limited number of copies of the Draft EIS and
supporting documentation may be obtained at the same address.
FOR FURTHER INFORMATION CONTACT: Terri Knutson, Olinghouse Mine EIS
Project Manager, Bureau of Land Management, 5665 Morgan Mill Road,
Carson City, NV 89701, (702) 885-6156.
SUPPLEMENTARY INFORMATION: Alta Gold Company has submitted a Plan of
Operations for the development of the Olinghouse Mine located
approximately 6 miles west of Wadsworth, NV and 33 miles east of Reno,
NV. The proposed operation includes: development and condemnation
drilling necessary for development of future operations; development of
two open-pits and a waste rock disposal area; construction of a heap
leach pad and plant for ore processing; construction of a haul road and
other mine facilities. The proposal would disturb a total of 503 acres
of public and private land.
This Draft EIS analyzes the environmental impacts associated with
the proposed development of the Olinghouse Mine, an alternate access
alternative, and the no action alternative. Issues analyzed in the
Draft EIS include geology and minerals, water resources, soils,
vegetation, wildlife and fisheries, range resources, paleontological
resources, cultural resources and Native American concerns, air
quality, access and land use, recreation and wilderness, social and
economic values, visual resources, noise, and hazardous materials.
A copy of the Draft EIS has been sent to all individuals, agencies,
and groups who have expressed interest in the project or as mandated by
regulation or policy. A limited number of copies are available upon
request from the BLM at the address listed above.
Public participation has occurred during the EIS process. A Notice
of Intent was filed in the Federal Register on June 13, 1996, and an
open scoping period was held until August 23, 1996. Two public scoping
open-houses to solicit comments and ideas were held on July 3, 1996 in
Reno, NV and August 8, 1996 in Fernley, NV. All comments presented to
the BLM throughout the EIS process have been considered.
To assist the BLM in identifying and considering issues and
concerns on the proposed action and alternatives, comments on the Draft
EIS should be as specific as possible. It is also helpful if comments
refer to specific pages or chapters in the document. Comments may
address the adequacy of the Draft EIS and/or the merits of the
alternatives formulated and discussed in the document. Reviewers may
wish to refer to the Council on Environmental Quality Regulations for
Implementing the Procedural Provisions of the National Environmental
Policy Act at 40 CFR 1503.3 in addressing these points. After the
comment period ends on the Draft EIS, comments will be analyzed and
considered by the BLM in preparing the Final EIS.
Dated: August 29, 1997.
John O. Singlaub,
District Manager.
[FR Doc. 97-23751 Filed 9-8-97; 8:45 am]
BILLING CODE 4310-HC-P