Record of Decision for the Sierra Nevada Customer Service Region 2004 Power Marketing Program
Federal RegisterApr 28, 1997
Ask Donna
What actually matters in this document.
Text
DEPARTMENT OF ENERGY
Western Area Power Administration
[DOE/EIS-0232]
Record of Decision for the Sierra Nevada Customer Service Region
2004 Power Marketing Program
AGENCY: Western Area Power Administration, DOE.
ACTION: Record of Decision.
-----------------------------------------------------------------------
SUMMARY: The Department of Energy (DOE), Western Area Power
Administration (Western), has decided to develop and implement a
marketing program for marketing Federal electric power resources from
the Central Valley Project (CVP) after year 2004 that is within the
range of the actions defined in Western's preferred alternative
described in the 2004 Power Marketing Program Final Environmental
Impact Statement (final 2004 EIS). In making this decision, Western has
considered all comments received on its alternatives and the analysis
contained in the 2004 Power Marketing Program Draft and Final
Environmental Impact Statements (2004 EIS) issued for the project (DOE/
EIS-0232) in May 1996 and March 1997, respectively. The program for
marketing Federal electric power resources from the CVP is being
developed through a public process now underway pursuant to the
Administrative Procedure Act (APA). Although the marketing of Federal
power from the Washoe Project (Washoe) may change, operations of
Stampede Reservoir and generating facilities will not, so no
environmental effects are expected from marketing program changes at
this facility.
Western's 2004 EIS evaluated alternatives that cover the reasonable
range of options for marketing CVP and Washoe power. The analyses of
the environmental effects of these alternatives bracket the greatest
possible range of potential impacts which could occur. The 2004 Power
Marketing Program Draft Environmental Impact Statement (draft 2004 EIS)
analyzed four alternatives: (1) no action (continue present approach of
marketing CVP
[[Page 22935]]
power), (2) maximize CVP hydropower peaking capability, (3) operate CVP
in a base-loaded mode (relatively constant power output), and (4) a
renewable case involving the purchase of 50 megawatts (MW) of power
from renewable resource generation sources. In the baseload and peaking
alternatives, the effects of various levels of power purchases from 0
to 900 MW were also analyzed for potential environmental effects.
Western's final 2004 EIS analyzed a fifth alternative identified as
Western's preferred alternative. It addressed CVP operations similar to
the maximized peaking alternative, except in Western's preferred
alternative CVP hydropower resources and Federal power customers'
resources are dispatched together in an integrated (economically
optimized) fashion, and each customer is allowed to choose the level of
firming purchases they would like Western to make to supplement the
hydropower generation.
The 2004 EIS did not identify any environmental effects associated
with Western's preferred alternative. Therefore, a monitoring program
or mitigation measures is not warranted.
DATES: Decision is effective April 11, 1997.
FOR FURTHER INFORMATION CONTACT: Mr. Jerry Toenyes, 2004 EIS Project
Manager, Sierra Nevada Region, Western Area Power Administration, 114
Parkshore Drive, Folsom, CA 95630-4710, (916) 353-4455.
SUPPLEMENTARY INFORMATION: The hydroelectric generation facilities of
the CVP are operated by the Bureau of Reclamation (Reclamation).
Reclamation manages and releases water in accordance with the various
acts authorizing specific projects and with other laws, permits, and
enabling legislation. The authority to market Federal electric power,
set rates for the power, and construct and operate transmission
facilities was transferred from the Department of the Interior (DOI) to
DOE through enactment of the Department of Energy Organization Act of
1977 (Public Law 95-91). Western is a power marketing administration
within DOE created to carry out Federal power marketing
responsibilities. Western's power marketing responsibility includes
managing the Federal power transmission system, scheduling power
production, and marketing the power produced. The Sierra Nevada Region
(SNR), with a marketing area covering most of northern and central
California and Nevada, currently markets approximately 1,480 MW of
power from the CVP in California and other sources, and available
nonfirm energy from Washoe.
All existing long-term CVP sales contracts expire on December 31,
2004. SNR has examined the environmental effects of alternative ways to
fulfill its responsibilities to market CVP and Washoe hydropower in its
2004 EIS. The 2004 EIS examined the impacts of alternatives related to
(1) The level and character of capacity, energy, and other services to
be marketed beyond 2004; and (2) establishment of eligibility and
allocation criteria for the allocations of electric power resources to
be marketed under contracts that will replace those expiring in 2004.
In implementing its proposed action, SNR desires to achieve a balanced
mix of purposes. The purposes of the proposed 2004 power marketing plan
are listed below:
To be consistent with SNR's statutory and other legal
constraints,
To provide long-term resource and contractual stability
for SNR and for customers contracting with SNR,
To provide the greatest practical value of the power
resource to SNR and to customers contracting with SNR,
To protect the human and natural environment,
To be responsive to future changes in the CVP, Washoe, and
the utility industry.
Western prepared its 2004 EIS in compliance with the National
Environmental Policy Act of 1969 (NEPA) (42 USC 4321, et seq.), the
Council on Environmental Quality regulations for implementing NEPA (40
CFR Parts 1500-1508), and the DOE regulations for compliance with NEPA
(10 CFR Part 1021) to describe the potential environmental consequences
of the range of reasonable marketing program alternatives.
Public Involvement
SNR developed a public involvement plan early in the evolution of
the 2004 EIS process. The public involvement plan was designed to guide
SNR through a collaborative and systematic decision-making process and
facilitate input from the public and interested parties and agencies.
The primary purposes of public involvement, as set out in the public
involvement plan, were to:
Inform the public,
Gather information from the public to identify public
concerns and values, and
Responsibly address stakeholder input regarding
environmental and allocation concerns and consider such input in
decision making.
Through SNR's public involvement process, an extensive effort was
made to notify all potentially interested parties about the 2004 EIS
and opportunities for involvement. Approximately 25 prescoping
stakeholder meetings (involving customers, agencies, interested groups,
and individuals) were informally held during the summer of 1993 to
provide information and to discuss issues and concerns related to the
project. An interested parties mailing list was used to keep track of
those showing an interest in the project. The list was expanded to
include any new interested parties as they were identified. The Federal
Register notice of the scoping period was published on August 10 and
13, 1993 (58 FR 42536 and 58 FR 43105). In conjunction with the notice,
a news release was sent to local newspapers, and scoping invitation
letters were mailed to those on the interested parties mailing list.
Three public scoping meetings were held in August and September 1993 to
receive written and verbal comments on environmental and marketing-
related issues. SNR held two more public meetings to facilitate
information sharing and to obtain further public comment: an Issues and
Alternatives Public Workshop on May 18, 1994, and an Alternatives
Workshop on January 18, 1995. The draft 2004 EIS was distributed to
interested parties and agencies for public review and comment. Notice
of availability of the draft 2004 EIS was published in the Federal
Register on May 24, 1996 (61 FR 26174 and 61 FR 26177). A public
hearing concerning the draft 2004 EIS was held on June 13, 1996. The
public comment period for the draft 2004 EIS closed on July 31, 1996.
Additionally, public information and involvement opportunities were
supplemented by 12 separate mailings of the project informational
bulletin, the 2004 EIS Update, designed to keep all interested groups
and individuals apprised of project details and scheduled events.
The final 2004 EIS was distributed to the public beginning in late
February 1997. The Environmental Protection Agency (EPA) notice of
availability was published on March 7, 1997 (62 FR 10559).
Description of Alternatives
In developing alternatives for the 2004 EIS, SNR focused on six key
component groups--key elements of the marketing program--that vary
across the alternatives. SNR's intent in establishing the ranges for
the variable components was to use a ``tent stakes'' approach to
constructing alternatives. Using this approach, the alternatives were
designed to cover the range of reasonable options and thus the
[[Page 22936]]
analyses of their environmental effects would bracket the range of
potential impacts. Although the final marketing plan, after completion
of the public process, may not be identical with any one of the 2004
EIS alternatives, the values for the final plan and its components will
be within the range considered and its impacts will fall within the
range of impacts assessed.
The six key component groups that are varied in the analysis of
alternatives include the following:
(1) Baseload Operations--Within the operational constraints
established by DOI, this refers to releasing water from hydroelectric
facilities to generate electricity at a relatively constant rate. This
approach would emphasize a steady water release rate from dams above
regulating reservoirs.
(2) Peaking Operations--Within the operational constraints
established by DOI, this refers to storing and releasing water from
hydroelectric facilities to generate electricity during the relatively
short period of maximum demand. This approach would emphasize periodic
water releases from dams above regulating reservoirs timed to produce
electricity when it is most needed.
(3) Power Purchases--These refer to SNR power purchases used to
supplement the Federal hydroelectric resource. Purchases were assumed
to be made from markets in California, the Pacific Northwest, and the
Desert Southwest. For purposes of modeling and analysis in the 2004
EIS, purchase levels of 0 MW, 450 MW, and 900 MW, each at capacity
factors up to 15 percent and 85 percent, are assumed. The no-action
alternative has an approximate average monthly purchase level of about
478 MW assuming average hydrologic conditions and no contractual
interchanges or exchanges.
(4) Renewable Resources--These resource types are emphasized in one
alternative and could be acquired through either selective purchases or
allocations of Federal resources to SNR's customers active in
developing renewable resources.
(5) Power Cost Analysis--This refers to analyzing cost impacts to
SNR's customers from combining the costs for purchases with SNR's
hydropower resources (aggregated), or treating these resources
individually, each with its own cost (disaggregated).
(6) Allocation to Customer Groups--This refers to assessing the
impacts of changing the quantities of power that customer groups
currently receive from the SNR. For 2004 EIS analysis purposes,
customers were divided into the following three groups, with the
customers in each group having similar load characteristics: utilities,
agriculture, and other (such as State and Federal agencies).
Nonvariable and independent components were identified which do not
vary across alternatives; therefore, the environmental effects
attributable to these components are constant under all alternatives.
Nonvariable and independent components include eligibility criteria,
first preference, preference, marketing area, delivery conditions,
transmission requirements, minimum load requirements, executed contract
requirements, alternative financing arrangements, termination
provisions, and standard provisions. Such components may be included in
the proposed 2004 power marketing plan. Because they are already
included in SNR's present activities, they represent no change from the
no-action alternative. Environmental impact analyses in the 2004 EIS
focus on those components that vary across the alternatives. Constant
effects associated with nonvariable and independent components were
included in the overall impact assessment.
Components that were analyzed in the Western's 1995 Energy Planning
and Management Program (EPAMP) EIS (Record of Decision for EPAMP EIS
was published October 12, 1995, 60 FR 53181) were not analyzed in the
2004 EIS. These components include contract length, power planning
requirements (such as integrated resource planning for customers),
withdrawal provisions, and contract adjustment provisions.
An analysis of allocations to customer groups was done to
characterize the impacts that may result from changing the quantity of
resources available to different customer groups. Such changes may
result if SNR emphasizes sales to a particular type of customer
(utility, agricultural, or other) or encourages special actions, such
as acquiring renewable resources, or customer allocations change due to
resource availability or marketing options. In the analysis, customer
allocations are both increased and decreased for each customer group.
This approach captures the range of beneficial and negative impacts
that may result from changes affecting a particular customer group.
Four alternatives structured around operations of the CVP
hydroelectric system were developed for analysis in the draft 2004 EIS.
The alternatives were refined following completion of the draft 2004
EIS and receipt of public comments. The key change from the draft 2004
EIS affecting alternative structure is the treatment of the energy
market assumed for 2005. In the draft 2004 EIS, each of the
alternatives incorporated varying levels of firm capacity purchases at
different capacity factors. In these types of contracts, Western would
be required to purchase the energy and capacity even if it were not
needed or if it were not the most economic purchase available at any
given time.
Description of Draft 2004 EIS Alternatives
The four original alternatives include the following:
The no-action alternative refers to a continuation of
SNR's present approach to marketing power, meeting 2005 loads that are
comparable to SNR's 1996 load patterns. Within operating constraints,
hydropower facilities are operated close to maximum peaking. For
modeling purposes the no-action alternative includes an average monthly
purchase of about 478 MW assuming average hydrologic conditions and no
contractual interchanges or exchanges.
Maximize hydropower peaking (the peaking alternative)
refers to operating the CVP hydropower facilities to maximize power
generation during peak load periods within operating constraints.
Federal CVP hydropower is dispatched first, before any customer
hydropower resources. Five purchase cases were considered including no
power purchases, 450 MW at 15-percent capacity factor, 450 MW at 85-
percent capacity factor, 900 MW up to a 15-percent capacity factor, and
900 MW up to an 85-percent capacity factor.
The baseload alternative refers to operating the CVP
hydropower facilities for relatively constant power output within
operating constraints. The same five purchase cases were examined as
with the peaking alternative described above.
Renewable resource acquisition (the renewables
alternative) refers to operating the CVP hydropower facilities to
maximize power generation during peak load periods within operating
constraints, and power purchases were set at 50 MW of capacity to
support the use of renewable resources. Generation was assumed to be
equally distributed among biomass, wind, solar and geothermal
facilities. A sensitivity test was run without biomass in the resource
mix for purposes of analyzing air quality and non-CVP impacts of land
use, water quality, and wastes.
Changes to Alternatives in the Final 2004 EIS
Because of utility industry restructuring presently taking shape
nationally and in California, in the final 2004 EIS the energy market
is assumed to operate with open access for both
[[Page 22937]]
wholesale and retail customers. Further, power could be purchased on an
hourly basis, as needed. Because of this flexibility, when Western
makes purchases, it is unlikely that customers would make a similar
purchase to meet the same need. In addition, because both Western and
its customers would have equal access to the market, purchases would be
under similar terms and conditions. Thus, a purchase by Western would
be offset by purchases foregone by Western's customers and vice versa.
The results of these assumptions about equal access and hourly pricing
include the following:
Purchase levels described in the alternatives would be the
maximum purchased in any 1 hour by the SNR.
SNR could purchase up to the maximum capacity factor noted
but need not purchase more than it requires.
All purchases in the final 2004 EIS are assumed to be made
from power markets. The SNR's market costs would be passed on to its
customers, meaning there would be no difference between an SNR purchase
and a customer's direct market purchase. The no purchase option
represents the effects of SNR disaggregating costs associated with any
purchases. Purchase options were also analyzed on an aggregated basis.
For renewable resources, the final 2004 EIS assumed that prices
incorporating technological advancements will be available in 20
percent of the renewable resources that would be available in 2005.
This assumption was based on the Western System Coordinating Council
1995 Summary of Estimated Loads and Resources. The final 2004 EIS
analyses placed the amount of capacity from renewable resources that
could be economically supported at 50 MW.
Western's Preferred Alternative
In the final 2004 EIS, Western's preferred alternative was
described and analyzed. The preferred alternative is similar to the
maximum peaking alternative. In this alternative additional power will
be purchased if requested by customers to meet their load requirements.
This alternative was chosen to provide the greatest flexibility to meet
customer needs in making purchases and to economically optimize the
operation of Western's and its customers' power resources.
Environmentally Preferred Alternative
The maximum peaking alternative was also determined to be the
environmentally preferred alternative. This alternative was so
designated because it would provide the greatest load-carrying capacity
and best offset the need for additional powerplants. This alternative
generally results in the greatest benefits or least impacts to the
environment when impacts are quantified. Peaking with no purchases
results in the greatest environmental benefits.
Environmental Consequences
The impact analyses followed three basic steps. Historic
hydrological conditions were analyzed using the PROSIM (CVP simulation
model) model. The PROSIM outputs (in the form of monthly water flows
and available hydropower capacity and energy) were input to the PROSYM
model, a production cost simulation model of electric utility
operations. PROSYM outputs (in the form of estimated levels of electric
generation, production costs, and hourly water flows in the CVP) were
used to assess the environmental impacts.
The manner in which hydropower generating plants would be operated
is one of the fundamental differences across the alternatives. The
PROSYM analyses show that, when operated to provide electricity at peak
times (the peaking alternative), the hydropower system can offset up to
317 MW of electric generating capacity from other sources when compared
to the no-action alternative. The replacement capacity needed to offset
the difference between the baseload and no-action alternatives is 581
MW of load-carrying capacity. The amount of replacement capacity needed
to offset capacity losses from any alternative when compared to the no
action alternative is an important vector identified in the analyses
for determining the extent of possible impacts. Building new capacity
causes land-use impacts and uses physical, natural, and financial
resources needed to build the powerplant and connect it with the
interconnected transmission grid. Western is not presently planning to
build such a powerplant, but Western's actions could cause such a
powerplant to be constructed if the baseload alternative were selected.
The CVP hydropower system does not require additional facilities or
modifications to change from baseload to peaking operations or vice
versa. Thus, the lost load-carrying capacity from baseload operations
would be retrievable for CVP operations if a decision to subsequently
implement peaking operations was made. However, if the baseload
alternative is implemented and replacement capacity is built,
replacement capacity is expected to remain in place. If this occurs, a
potential shift from baseload back to peaking CVP operations would
likely result in temporary surplus capacity in the region.
Impacts resulting from CVP water releases within SNR's discretion
are limited. In comparison to the no-action alternative, the peaking
alternative results in only slightly greater pool-level fluctuation in
regulating reservoirs. Impacts are restricted to the regulating
reservoirs at Lewiston, Keswick, Lake Natoma, and Tulloch because the
regulating dams are operated to control releases downstream. The
baseload alternative would result in constant water releases from the
main dams that would avoid pool-level fluctuation and potentially
improve recreation and resident fisheries slightly in the regulating
reservoirs.
The hourly water releases from the main dams, whether operating for
peaking or baseload, affect temperature fluctuation a very minor
amount. The temperature differences are so small that, although they
can be calculated, they could not be measured in the regulating
reservoirs or the rivers downstream.
Given these findings about pool-level and temperature fluctuations,
in comparison with the no-action alternative, no alternative would
result in adverse impacts to fisheries, threatened and endangered
species, recreation, the terrestrial environment, or cultural
resources.
The more constant flows of the baseload alternative may result in
minor beneficial effects to fisheries, recreation, and cultural
resources associated with the regulating reservoirs. A reduction in
pool-level fluctuation may improve habitat for resident fish and
improve boating conditions. Stable pool elevations could also reduce
erosion at shoreline cultural resource sites, but may increase exposure
to other sources of erosion such as wave action.
Impacts to air quality, solid waste, and wastewater would be
related to the generation of electricity at powerplants apart from the
CVP. The variation across the alternatives comes from changes in
operation of combustion turbines (CTs) and combined-cycle combustion
turbines that may be located throughout northern and central
California, the Pacific Northwest, or the Desert Southwest. The most
substantial air quality impacts would come from changes in hourly
operations of other nonhydropowerplants in response to the manner in
which the CVP hydroelectric facilities are scheduled (peaking or
baseload). Generally, compared to the no-action alternative, scheduling
the hydropower system as a baseload system would result in an increase
of
[[Page 22938]]
emissions from other powerplants during the day when ambient levels are
high because thermal generation would be needed for peaking. Peaking
the hydropower system offsets daytime thermal production and reduces
daytime emissions, but increases nighttime thermal production and
emissions, when ambient levels are less. This can be important for
areas having problems meeting air quality standards during summer
afternoons when industrial, utility, and transportation emissions are
at their peak. During summer afternoons, the difference in oxides of
nitrogen emissions between the peaking and baseload alternatives would
reach over 400 pounds per hour. These emissions are equivalent to those
from a 400-MW combustion turbine plant.
Without biomass, the renewables alternative results in the most
beneficial effects on annual air emissions. Including biomass with the
other renewables sources in the renewables alternative would produce
the greatest levels of annual air emissions.
In comparison with the no-action alternative, all of the other
alternatives would result in beneficial effects on wastewater
production. As with annual air emissions, the renewables alternative
without biomass would result in the greatest benefit in reducing
wastewater production. Renewables with biomass would produce the least
benefit but would still result in a reduction in wastewater production
in comparison with the no-action alternative.
Solid waste production also would be most changed by the renewables
alternative. Biomass-fueled plants that burn municipal solid waste
produce a great deal of ash as solid waste but also reduce the quantity
of solid waste requiring disposal in a landfill. For every pound of ash
produced by biomass combustion, municipal solid waste is reduced by
about 5 pounds. When this reduction is taken into account, solid waste
would be reduced by nearly 40,000 tons with the renewables alternative.
In comparison, the other alternatives (including renewables without
biomass) are very similar to the no-action alternative.
The baseload alternative results in about 90 acres of land needed
for replacement capacity. The renewables alternative would result in
land-use impacts. Renewables, such as solar photovoltaic and wind, may
require up to about 30 times the land area per megawatt of capacity of
thermal resources such as CTs. In comparison to the no-action
alternative, the renewables alternative would require an additional 70
to 90 acres of land for powerplants.
SNR's 2004 power marketing plan would influence the overall power
costs of its customers. The alternatives were structured to determine
the maximum range of impacts to gauge socioeconomic effects in the
areas of output, employment, and labor income. When compared to the
economy of northern and central California, or of any one of four
economic regions analyzed within northern and central California, the
estimated impacts are very small. Based on results from the power
production cost analysis described in Section 4.2 of the 2004 EIS, the
associated economic impacts of the alternatives are nearly
indistinguishable in all cases and in all regions. The economic effects
of the preferred alternative and all other alternatives are not
significant; however, some indication of their positive or negative
direction is possible. Western's preferred alternative results in
economic impacts that are slightly positive in comparison to the no-
action and the peaking alternatives.
All of these socioeconomic effects reflect averaging across regions
and customer groups and do not capture the effects on individual
customers. Economic effects on SNR's customers who lose or gain
allocations may be substantial in individual cases but cannot be
determined because specific allocations have not been made. In general,
however, customers who lose allocations would be balanced by other
customers who gain equivalent allocations. Specific allocations will be
made in a separate public process under the APA.
Across the alternatives and the affected economic regions, economic
impacts are minimal, and are not disproportional across income or race
groupings of the population. In the case of agriculture customers, low-
income and minority groups make up a larger proportion of the
employment in that sector. The impacts identified do not affect
agricultural gross revenues or production levels. Thus, employment
levels are not affected, and the impacts of alternatives do not
disproportionately affect low-income or minority groups.
The effects of emphasizing the use of renewable resources (assuming
technological improvements) in the generation mix have a negative
economic impact compared to the same quantity of thermal purchases.
Improvements in technology should occur prior to 2005 that reduce the
cost of the renewable resources. The amount of renewables to be
included in the renewables alternative was determined by melding the
anticipated cost of renewables in 2004 together with the anticipated
2004 hydropower cost. The renewables share of the mix was increased
until the combined rate for SNR energy equaled the anticipated market
rate in 2004. This resulted in melding the CVP hydropower operated to
maximize peaking with 50 MW of renewable resource purchases.
Summary of Public Comments
A number of comments were provided by agencies, stakeholders, and
the public during the public review period of the draft 2004 EIS. Some
customers suggested that SNR may have underestimated the future cost of
energy generated from renewable resources and overestimated the market
price of power in post-2004 projections in the draft 2004 EIS. It was
also suggested this may have resulted in SNR's projections of
unrealistically high amounts of renewable resource power in its future
resource mix. Comments also noted a concern to reflect the most current
industry developments. Western revised these estimates in the final
2004 EIS, provided updated model assumptions and the analysis of
alternatives to more accurately represent these developments. The
resulting decision takes these factors into account.
More information was requested on how alternatives would be formed
into a cohesive power product, including purchase levels and capacity
factors that are specifically tailored to customer needs. Western will
be able to better identify these products as they are addressed within
the APA process. The final 2004 EIS focused on the environmental
impacts from the resources needed to develop products and services. The
final 2004 EIS identified the most aggressive range of actions possible
to determine the potential boundaries of environmental effects and to
establish a high degree of flexibility for Western's decisions.
Another comment requested that referenced documents, such as the
EPAMP EIS, be summarized in the final 2004 EIS. Western added
information to better describe the findings of referenced documents.
Some comments pointed out errors and differences of perception in
the descriptions of various CVP facilities and operations. These errors
and differences were corrected or explained in the final 2004 EIS.
Concerns were raised about the level of detail given to the
analysis of customer group allocations and to results for the utility
customer group. Refinements in modeling to better reflect the changing
utility industry addressed these issues.
[[Page 22939]]
Decision
Western has decided to develop and implement a marketing program
for marketing Federal electric power resources from the CVP and Washoe
that is within the range of actions defined in Western's preferred
alternative described in the 2004 EIS, to replace power contracts
expiring in the year 2004. This alternative is based on peaking the
hydropower system in an integrated (economically optimized) fashion
with Western's customer's hydropower resources. In addition, each
customer can choose the level of firming purchases it would like
Western to make on its behalf to supplement the CVP hydropower
generation. Although the marketing of Federal power from Washoe may
change, operation of the Stampede Reservoir and generation facilities
will not, so no environmental effects are expected. The modified
program for CVP power will apply to power marketing contracts
superseding those that expire December 31, 2004. Western's preferred
alternative falls within the tent stakes established in the 2004 EIS,
and is the alternative selected in the development of Western's
proposed 2004 power marketing plan.
Rationale
Western's decision considered comments received from customers and
stakeholders throughout the processes and the analyses related to the
draft and final 2004 EIS that were issued for the project (DOE/EIS-
0232) in May 1996 and March 1997, respectively. This decision is within
the scope of the alternatives discussed in the final 2004 EIS and
addresses concerns by customers and stakeholders in those documents.
The environmental effects of the environmentally preferred and the
agency preferred alternatives are nearly identical, although the
selected alternative provides economic advantages over the
environmentally preferred alternative.
A 2004 Power Marketing Plan is needed to fulfill Western's Federal
power marketing responsibilities to market Federal CVP power beyond the
year 2004.
In addition, the purpose and need for the 2004 EIS provides factors
which were used to gauge the alternatives. The purposes and their
relationship with the alternatives and other analyses are described in
the following sections and summarized in Table 1.
Legal Obligations
The first of the listed purposes was met by all of the
alternatives. This first purpose reads as follows: to be consistent
with SNR's statutory and other legal obligations. This purpose does not
favor any one alternative and is met by the decision.
Resource and Contractual Stability
The second purpose to provide long-term resource and contractual
stability for SNR and for customers contracting with SNR applies to
contract length and the quantity of resources that are allocated to
customers. Both issues were analyzed in the EPAMP EIS. The EPAMP EIS
analysis found that longer-term contracts reduced uncertainty in power
planning and were of greater value to Western's customers. All of the
alternatives could have been implemented with different contract
lengths.
The 2004 EIS analyzed impacts from extreme changes in allocations
to customer groups. The 2004 EIS analysis found that the most adverse
effects on cost and socioeconomic effects come from reducing
allocations to the utility customer group. Reducing the allocation to
the utility customer group to nothing results in adverse socioeconomic
effects.
The EPAMP EIS also analyzed reducing allocations of available
resources in order to create resource pools. These pools could be used
for allocations to new customers or to support desired policies, such
as customers who are willing to implement conservation or develop
renewable resources. The manner in which the resource pool is used was
not assessed because allocations have not yet been determined.
Table 1
--------------------------------------------------------------------------------------------------------------------------------------------------------
Preferred Peaking* Baseload Renewables No action
--------------------------------------------------------------------------------------------------------------------------------------------------------
Alternative Description............ Peaking optimized with Peaking operations Baseload operations Peaking operations Existing operations--
customer operations-- with purchase options. with purchase coupled with a 50 MW similar to peaking--
customers choose options. purchase from 478 MW average
purchases. renewables. monthly purchases.
--------------------------------------------------------------------------------------------------------------------------------------------------------
Legal Obligations
(4)Met by all alternatives
--------------------------------------------------------------------------------------------------------------------------------------------------------
Resource and Contractual Stability
(4)Analyzed in the EPAMP EIS and
the analysis of allocation to
customer groups within the 2004
EIS may be applied to all
alternatives
--------------------------------------------------------------------------------------------------------------------------------------------------------
Greatest Practical Value........... Lowest cost Federal Low cost but does not High costs--least Greatest costs--CVP Costs similar to
resource, available economically optimize available CVP customer capacity baseload--midlevel
load-carrying CVP resources-greatest customer load- same as peaking. CVP customer load-
customer capacity CVP customer load- carrying capacity. carrying capacity.
similar to peaking. carrying capacity.
Protect the Human and Natural Similar to peaking-- Most beneficial or Adverse effects Same as peaking for Similar to peaking
Environment. most beneficial least adverse except for least pool fluctuation-- physical effects--
socioeconomic effects. physical effects-- pool fluctuation in physical effects unfavorable
socioeconomic effects reregulating range from least to socioeconomic
depend on purchase reservoirs--some most depending on effects.
levels--no purchase adverse presence of biomass
similar to preferred socioeconomic in resource mix--
alternative. effects. Least favorable
socioeconomic effect.
Responsiveness..................... Greatest flexibility Less flexibility...... Less flexibility..... Less flexibility..... Less flexibility.
for customers.
--------------------------------------------------------------------------------------------------------------------------------------------------------
*Environmentally Preferred Alternative.
[[Page 22940]]
Greatest Practical Value
The third purpose was to provide the greatest practical value of
the power resource to SNR and to customers contracting with SNR. The
2004 EIS analysis found that Federal hydropower is a good value on the
power market. However, the structure and cost of supplemental purchases
can change the cost of the Federal resource and result in very small
socioeconomic effects. The baseload alternative was considered and not
selected because it represented the least-effective use of the CVP
hydropower resource in the overall energy market. The preferred
alternative was found to result in the lowest costs and most beneficial
socioeconomic effects.
Protect the Human and Natural Environment
The fourth purpose was to protect the human and natural
environment. The baseload alternative was considered but not selected
because of the adverse environmental effects of constructing and
operating necessary replacement capacity to maintain existing load-
carrying capability in the northern and central California region. In
addition, no significant positive benefits were identified to
environmental resources that would offset the negative impacts of
construction and operation of new generation capacity.
Although designated as environmentally preferred, the peaking
alternative was not selected because it does not economically optimize
integrated scheduling of Western's hydropower generation with the
generation of its customers. The preferred alternative provides nearly
identical environmental benefits as the peaking alternative, but
provides greater economic benefits, and has no major negative
environmental impacts.
The no-action alternative was not selected because it is not
consistent with customers' needs in a restructured utility industry
environment. Many of Western's customers have indicated they would like
the hydropower priced separately from purchases, and would like to make
their own purchases without incurring economic penalties. The no-action
alternative includes substantial firming purchases with the purchased
power cost melded with the hydropower cost, contrary to these
customers' preference and to price optimization in a restructured
utility environment.
The renewables alternative was not selected because it does not
economically optimize the use of CVP power resources and because the
preferred alternative allows purchases of power generated from
renewable resources. In the preferred alternative, Western can make
power purchases on behalf of customers at the customers' request, and
these purchases can be from renewable resource generation if costs are
competitive or if the customer is willing to pay the added cost. The
renewables alternative is based on costs of hydropower and purchases
being melded, while the preferred alternative is based on the
hydropower and purchased power costs being disaggregated, allowing more
freedom of choice among customers whether to take delivery of purchased
power. The latter approach is considered to be more compatible with the
developing competitive marketplace resulting from electric industry
restructuring.
Responsiveness
Regarding responsiveness to future changes in CVP, Washoe, and the
utility industry, the preferred alternative provides the greatest
flexibility to customers and keeps the Federal resources at their
highest, practical economic value while having no measurable impact on
the environment.
Mitigation Action Plan
No Mitigation Action Plan will be prepared, as the 2004 EIS did not
identify any significant environmental effects associated with
Western's selected alternative that warrant the adoption of a
monitoring program or mitigation measures.
Documents Available
For a copy of this Record of Decision or a copy of the final 2004
EIS and supporting documents, write to the 2004 EIS Project Manager at
the address listed in the For Further Information Contact Section.
Dated: April 11, 1997.
J.M. Shafer,
Administrator.
[FR Doc. 97-10859 Filed 4-25-97; 8:45 am]
BILLING CODE 6450-01-P