DEPARTMENT OF THE INTERIOR
Bureau of Reclamation
Option and Lease Agreement Among the Ak-Chin Indian Community,
the United States, and Del Webb Corporation, Maricopa County, AZ
AGENCY: Bureau of Reclamation, Interior.
ACTION: Notice to prepare an environmental assessment and notice of
public scoping meeting.
-----------------------------------------------------------------------
SUMMARY: Pursuant to the National Environmental Policy Act (NEPA) of
1969, as amended, and the Council on Environmental Quality's
Regulations for Implementing the Procedural Provisions of NEPA, the
Bureau of Reclamation (Reclamation) proposes to prepare a draft
environmental assessment (EA) for approval of the provision of leased
settlement water under an option and lease agreement among the Ak-Chin
Indian Community, the United States, and the Del Webb Corporation.
Reclamation is initiating early scoping for the proposed EA and will be
conducting a scoping meeting. Reclamation intends that this scoping
meeting be used to serve as public scoping for preparation of an
environmental impact statement (EIS), should it be determined that one
is required.
ADDRESSES: Written comments may be sent to Mr. Bruce D. Ellis, Chief,
Environmental Resource Management Division, Phoenix Area Office, Bureau
of Reclamation, P.O. Box 9980, Phoenix, AZ 85068-0980. The scoping
meeting will be held at New River Elementary School, 48827 North Black
Canyon Highway, New River, AZ.
DATES: The scoping meeting to solicit comments on the contents of the
EA will be November 2, 1996, at 10:00 a.m. To ensure consideration in
the environmental analysis, the comments should be received by Mr.
Ellis no later than November 9, 1996.
FOR FURTHER INFORMATION CONTACT: Ms. Sandra Eto, Environmental Resource
Management Division, Phoenix Area Office, Bureau of Reclamation, P.O.
Box 9980, Phoenix, Arizona 85068-0980; telephone (602) 870-6771.
SUPPLEMENTARY INFORMATION: The Ak-Chin Indian Community has agreed to
lease between 6,000 and 10,000 acre-feet per year of water to the Del
Webb Corporation (Del Webb). Del Webb plans to construct a 9-mile long
water delivery pipeline from Waddell Canal to Villages at Desert Hills
(Villages) project, a proposed 5,661-acre future master planned
community. The location of Villages is approximately 3 miles north of
Carefree Highway and 7 miles east of Lake Pleasant on Interstate 17 in
Maricopa County, Arizona.
Reclamation approved categorical exclusion No. PXAO-95-9 in
December of 1994 for the Option and Lease Agreement Among the Ak-Chin
Indian Community, the United States, and Del Webb Corporation according
to Exclusion Category 9.4.D.14. The Categorical Exclusion indicated,
however, that ``[t]he environmental impacts which will result from the
Secretary's approval of the option and lease agreement are not clear at
this time since Del Webb has not yet finalized its plans for taking and
using the leased settlement water.'' Del Webb has developed its plans
for taking and using the leased settlement water. Reclamation has
determined an EA should be prepared to determine whether a Finding of
No Significant Impact is appropriate or if an EIS needs to be prepared.
The EA will describe the environmental consequences that would
result from the delivery of leased settlement water. Reclamation plans
to focus on impacts associated with construction of a water delivery
pipeline and treatment plant. The EA will evaluate in detail the
proposed action and will discuss alternative pipeline alignments that
were considered but rejected from detailed consideration. Key issues to
be addressed in the EA will include:
Biological resource effects, including loss of desert
habitat, impacts on plant and wildlife species, and special status
species effects;
Historic and prehistoric cultural resource effects;
Hydrology, water quality and soils effects;
Air quality and noise effects;
Traffic and circulation effects; and
Land use and aesthetic effects.
The EA will also evaluate indirect effects of the proposed action.
In addition, the EA will include a No-Action Alternative. The No-Action
Alternative represents the conditions that are assumed to exist in the
absence of the Federal action, and provides a basis for comparison with
the proposed action. Del Webb has identified alternative water supply
options that could be used in the absence of the leased settlement
water. Based on this information, Reclamation assumes development of
the Villages project will occur in the absence of the proposed action.
Reclamation is circulating this notice for preparation of an EA and
early scoping because of considerable public interest and the need to
ensure that all
[[Page 53757]]
relevant issues are evaluated in the EA. Reclamation will consult with
other Federal, State, and local agencies with specific expertise
regarding environmental impacts related to the project. If you would
like to be placed on a mailing list for any subsequent information,
please write or telephone Ms. Eto.
If an EIS is later required, Reclamation will submit a Notice of
Intent to prepare an EIS and will provide opportunity for the public to
submit written comments suggesting impacts and alternatives that should
be addressed in the EIS.
Dated: October 8, 1996.
Larry D. Morton,
Assistant Area Manager.
[FR Doc. 96-26297 Filed 10-11-96; 8:45 am]
BILLING CODE 4310-94-P
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.