Accidental Release Prevention Requirements: Risk Management Programs Under Clean Air Act Section 112(r)(7)

Federal RegisterJun 20, 1996

Ask Donna

What actually matters in this document.

Text

SUMMARY: The Clean Air Act requires EPA to promulgate regulations to

prevent accidental releases of regulated substances and reduce the

severity of those releases that do occur. EPA is promulgating rules

that apply to all stationary sources with processes that contain more

than a threshold quantity of a regulated substance. Processes will be

divided into three categories based on: the potential for offsite

consequences associated with a worst-case accidental release; accident

history; or compliance with the prevention requirements under OSHA's

Process Safety Management Standard. Processes that have no potential

impact on the public in the case of an accidental release will have

minimal requirements. For other processes, sources will implement a

risk management program that includes more detailed requirements for

hazard assessment, prevention, and emergency response. Processes in

industry categories with a history of accidental releases and processes

already complying with OSHA's Process Safety Management Standard will

be subject to a prevention program that is identical to parallel

elements of the OSHA Standard. All other processes will be subject to

streamlined prevention requirements. All sources must prepare a risk

management plan based on the risk management programs established at

the source. The source must submit the plan to a central point

specified by EPA; the plan will be available to state and local

governments and the public. These regulations will encourage sources to

reduce the probability of accidental releases of substances that have

the potential to cause immediate harm to public health and the

environment and will stimulate the dialogue between industry and the

public to improve accident prevention and emergency response practices.

DATES: The rule is effective August 19, 1996.

ADDRESSES: Supporting material used in developing the proposed rule,

supplemental notice, and final rule is contained in Docket No. A-91-73.

The docket is available for public inspection and copying between 8:00

a.m. and 5:30 p.m., Monday through Friday (except government holidays)

at Room 1500, 401 M St. SW, Washington, DC 20460. A reasonable fee may

charged for copying.

FOR FURTHER INFORMATION CONTACT: Craig Matthiessen at (202) 260-8600,

Chemical Emergency Preparedness and Prevention Office, U.S.

Environmental Protection Agency, 401 M St. SW, Washington, DC 20460, or

the Emergency Planning and Community Right-to-Know Hotline at 1-800-

424-9346 (in the Washington, DC, metropolitan area, (703) 412-9810).

SUPPLEMENTARY INFORMATION: Judicial Review. Accidental Release

Prevention Requirements: Risk Management Programs Under Clean Air Act

Section 112(r)(7) were proposed in the Federal Register on October 20,

1993 (58 FR 54190). A supplemental notice was issued on March 13, 1995

(60 FR 13526). This Federal Register action announces the EPA's final

decisions on the rule. Under section 307(b)(1) of the Act, judicial

review of the Accidental Release Prevention Requirements: Risk

Management Programs is available only by the petition for review in the

U.S. Court of Appeals for the District of Columbia Circuit within 60

days of today's publication of this final rule. Under section 307(b)(2)

of the Act, the requirements that are the subject of today's notice may

not be challenged later in civil or criminal proceedings brought by the

EPA to enforce these requirements.

Regulated Entities

Entities potentially regulated by this action are those stationary

sources that have more than a threshold quantity of a regulated

substance in a process. Regulated categories and entities include:

------------------------------------------------------------------------

Category Examples of regulated entities

------------------------------------------------------------------------

Chemical Manufacturers............ Industrial organics & inorganics,

paints, pharmaceuticals, adhesives,

sealants, fibers

Petrochemical..................... Refineries, industrial gases,

plastics & resins, synthetic rubber

Other Manufacturing............... Electronics, semiconductors, paper,

fabricated metals, industrial

machinery, furniture, textiles

Agriculture....................... Fertilzers, pesticides

Public Sources.................... Drinking and waste water treatment

works

Utilities......................... Electric and Gas Utilities

Others............................ Food and cold storage, propane

retail, warehousing and wholesalers

Federal Sources................... Military and energy installations

------------------------------------------------------------------------

This table is not intended to be exhaustive, but rather provides a

guide for readers regarding entities likely to be regulated by this

action. This table lists the types of entities that EPA is now aware

could potentially be regulated by this action. Other types of entities

not listed in the table could also be regulated. To determine whether a

stationary source is regulated by this action, carefully examine the

provisions associated with the list of substances and thresholds under

Sec. 68.130 (59 FR 4478), the proposed modifications (61 FR 16598,

April 15, 1996) and the stay of implementation of the affected

provisions until the proposed modifications are final published

elsewhere in today's Federal Register, and the applicability criteria

in Sec. 68.10 of today's rule. If you have questions regarding the

applicability of this action to a particular entity, consult the person

listed in the preceding FOR FURTHER INFORMATION CONTACT section.

The following outline is provided to aid in reading this preamble:

I. Introduction and Background

A. Statutory Authority

B. Background

II. Discussion of Final Rule

A. Applicability

B. Program Criteria and Requirements

C. Hazard Assessment

D. Prevention Programs

E. Emergency Response

F. Risk Management Plan (RMP)

G. Air Permitting

H. Other Issues

III. Discussion of Comments

A. Tiering

1. Rationale

2. Program 1 vs. Program 2 and Program 3 Criteria

[[Page 31669]]

a. Potential for Offsite Impact

b. Accident History

c. Other

3. Program 2 vs. Program 3 Criteria

a. Number of Employees

b. SIC Code

c. Site-specific, Risk-based Criteria

d. Accident History

e. Other

4. Program 1 Requirements

a. Certification of No Environmental Impact

b. Signs

c. Emergency Response Program

d. Other

5. Program 2 Requirements

a. Streamlined Program

b. Other Regulations

c. Emergency Response Program

B. Offsite Consequence Analysis

1. Worst-Case Release Scenario

2. Mitigation Systems

a. Worst-Case Release Scenario

b. Alternative Scenarios

3. Populations Affected

4. Number of Scenarios

5. Technical Guidance

6. Modeling Parameters

a. Endpoints

b. Meteorology

C. Consideration of Environmental Impact

1. Inclusion of Environmental Impacts

2. Environments to be Considered

3. Level of Analysis Required

D. Program 3 Consistency with OSHA PSM Standard

1. Prevention Program

2. Enforcement

3. Exemptions

E. Relationship to Air Permits

1. General Relationship between the Part 68 and Part 70 programs

2. Impact of EPA's Proposal on Air Permitting Programs

3. Part 68 as an ``Applicable Requirement'' under Part 70

4. Role of the Air Permitting Authority

5. Air Permit Application Contents

6. Air Permit Contents

7. Completeness Review

8. Interaction of the Implementing Agency and the Permitting

Authority

9. Designated Agency

10. Reopening Air Permits to Incorporate Section 112(r)

Requirements

11. Use of Air Funds

12. Other Issues

F. General Definitions

1. Significant Accidental Release

2. Stationary Source

3. Process

4. Offsite

5. Other Definitions

G. Risk Management Plan (RMP)

1. Level of Detail

2. RMP Content

3. Submission

4. Other Issues

H. Prevention Program

I. Accident History

J. Emergency Response Program

K. Registration

L. Model Risk Management Programs

M. Implementing Agency Audits

N. Public Participation

O. Inherently Safer Technologies

P. Coverage by Other Regulations

1. General Issues

2. DOT Transportation Regulations

3. Other EPA Regulations

4. Other Federal Regulations

5. State and Local Regulations

Q. Industry-Specific Issues

1. Oil and Gas Facilities

2. Retail Facilities

a. Propane Retailers

b. Ammonia Retailers

3. Refrigeration Systems

4. Other Operations

R. Implementing Agency Delegation

S. Accident Reporting

T. Other Issues

1. OSHA VPP

2. Qualified Third Party

3. Documentation

IV. Section-by-Section Analysis of the Rule

V. Required Analyses

A. E.O. 12866

B. Regulatory Flexibility Act

C. Unfunded Mandate Reform Act

D. Paperwork Reduction Act

E. Submission to Congress and the General Accounting Office

I. Introduction and Background

A. Statutory Authority

This rule is promulgated under sections 112(r), 301(a)(1), Title V

of the Clean Air Act (CAA) as amended (42 U.S.C. 7412(r), 7601(a)(1),

7661-7661f).

B. Background

The CAA Amendments of 1990 amend section 112 and add paragraph (r).

The intent of section 112(r) is to prevent accidental releases to the

air and mitigate the consequences of such releases by focusing

prevention measures on chemicals that pose the greatest risk to the

public and the environment. Section 112(r)(3) mandates that EPA

promulgate a list of regulated substances, with threshold quantities;

this list defines the stationary sources that will be subject to

accident prevention regulations mandated by section 112(r)(7). EPA

promulgated its list of substances on January 31, 1994 (59 FR 4478)

(``List Rule'').

As noted elsewhere in today's Federal Register, EPA has stayed

certain provisions of part 68 that were promulgated as part of the List

Rule. The stayed provisions are being addressed in amendments to the

List Rule, which were proposed in 61 FR 16598 (April 15, 1996).

Therefore, EPA has not taken final action on provisions of the Risk

Management Program rule that apply to regulated substances, mixtures,

and stationary sources addressed by the stayed provisions. Final action

will be deferred until EPA takes final action on the proposed

amendments to the List Rule.

Section 112(r)(7) mandates that EPA promulgate regulations and

develop guidance to prevent, detect, and respond to accidental

releases. Stationary sources covered by these regulations must develop

and implement a risk management program that includes a hazard

assessment, a prevention program, and an emergency response program.

The risk management program must be described in a risk management plan

(RMP) that must be registered with EPA, submitted to state and local

authorities, and made available to the public. On October 20, 1993, EPA

published a Notice of Proposed Rulemaking (NPRM) for the section

112(r)(7) regulations (58 FR 54190). (For a summary of the statutory

requirements of section 112(r) and related statutory provisions, see

the October 20, 1993, NPRM).

Following publication of the proposed rule, EPA held four public

hearings and received approximately 770 written comments. Because of

these comments, EPA issued a supplemental notice of proposed rulemaking

(SNPRM) on March 13, 1995 (60 FR 13526) for comment on: approaches for

setting different requirements for sources that pose different levels

of hazard (tiering); worst-case releases and other hazard assessment

issues; accident information reporting; public participation;

inherently safer approaches; and implementation and integration of

section 112(r) with state programs, particularly state air permitting

programs. EPA held a public hearing on March 31, 1995, in Washington,

DC, and received more than 280 written comments. Today's rule reflects

EPA's consideration of all comments; major issues raised by commenters

and EPA's response are briefly discussed in Section III of this

preamble. A summary of all comments submitted and EPA's response to

them is available in the Docket (see ADDRESSES).

EPA has proposed to delist explosives from Sec. 68.130.

Consequently, explosives are not addressed in this rule. EPA had also

requested at the time of the final List Rule comments on whether

flammable substances, when used as fuel, posed a lesser intrinsic

hazard than the same substance handled otherwise (59 FR 4500, January

31, 1994). The comments submitted lacked data that would justify a

lesser level of hazard consideration for flammable fuels; hence, the

Agency will not adopt a fuel use exemption for purposes of threshold

quantity determination.

With today's rule, EPA continues the philosophy that the Agency

embraced in implementing the Emergency Planning and Community Right-to-

Know Act of

[[Page 31670]]

1986 (EPCRA). Specifically, EPA recognizes that regulatory

requirements, by themselves, will not guarantee safety. Instead, EPA

believes that information about hazards in a community can and should

lead public officials and the general public to work with industry to

prevent accidents. For example, today's rule requires covered sources

to provide information about possible worst-case scenarios. EPA intends

that officials and the public use this information to understand the

chemical hazards in the community and then engage in a dialogue with

industry to reduce risk. In this way, accident prevention is focused

primarily at the local level where the risk is found. Further, today's

rule builds on existing programs and standards. For example, EPA has

coordinated with Occupational Safety and Health Administration (OSHA)

and the Department of Transportation (DOT) in developing this

regulation. To the extent possible, covered sources will not face

inconsistent requirements under these agencies' rules. EPA is

encouraging sources to use existing emergency response programs, rather

than develop a separate and duplicative program under this rule. In

addition, today's rule scales requirements based on the potential risk

posed by a source and the steps needed to address the risk, rather than

imposing identical requirements on all sources.

To accommodate the concerns of small businesses, EPA is providing

guidance with reference tables that covered sources can use to model

the offsite consequences of a release. EPA is providing a model RMP

guidance for the ammonia refrigeration industry, and will develop

similar guidance for propane handlers and drinking water systems. As

today's rule is implemented, EPA hopes that other industry sectors will

work with EPA to develop model RMPs for other processes, thereby

reducing costs for individual sources. Finally, today's rule requires

industry to submit RMPs centrally in a format and method to be

determined by EPA. Working with stakeholders, EPA will develop

mechanisms to allow industry to use appropriate electronic technology

to register with EPA and submit RMPs. In turn, all interested parties

will be able to access electronically the data in RMPs. This method of

submission and access avoids a potentially significant amount of

paperwork for all involved parties and promotes uniformity. Users will

be able to develop databases for specific purposes and compare RMPs for

various sites across the country. In turn, industries' use of the data

will promote continuous improvement, for example, through new safety

technologies. As the method for submitting RMPs is developed, EPA

invites the participation of all stakeholders, including industry,

state and local governments, local emergency planning committees,

environmental groups, and the general public.

II. Discussion of Final Rule

A. Applicability

The owner or operator of a stationary source that has more than a

threshold quantity of a regulated substance in a process must comply

with these requirements no later than June 21, 1999; three years after

the date on which a regulated substance is first listed under

Sec. 68.130; or the date on which a regulated substance is first

present in more than a threshold quantity in a process, whichever is

later.

B. Program Criteria and Requirements

Under today's rule, processes subject to these requirements are

divided into three tiers, labeled Programs 1, 2, and 3. EPA has adopted

the term ``Program'' to replace the term ``Tier'' found in the SNPRM to

avoid confusion with Tier I and Tier II forms submitted under EPCRA,

also known as Title III of the Superfund Amendments and Reauthorization

Act of 1986 (SARA Title III). Eligibility for any given Program is

based on process criteria so that classification of one process in a

Program does not influence the classification of other processes at the

source. For example, if a process meets Program 1 criteria, the source

need only satisfy Program 1 requirements for that process, even if

other processes at the source are subject to Program 2 or Program 3. A

source, therefore, could have processes in one or more of the three

Programs.

Program 1 is available to any process that has not had an

accidental release with offsite consequences in the five years prior to

the submission date of the RMP and has no public receptors within the

distance to a specified toxic or flammable endpoint associated with a

worst-case release scenario. Program 3 applies to processes in Standard

Industrial Classification (SIC) codes 2611 (pulp mills), 2812 (chlor-

alkali), 2819 (industrial inorganics), 2821 (plastics and resins), 2865

(cyclic crudes), 2869 (industrial organics), 2873 (nitrogen

fertilizers), 2879 (agricultural chemicals), and 2911 (petroleum

refineries). Program 3 also applies to all processes subject to the

OSHA Process Safety Management (PSM) standard (29 CFR 1910.119), unless

the process is eligible for Program 1. Owners or operators will need to

determine individual SIC codes for each covered process to determine

whether Program 3 applies. All other covered processes must satisfy

Program 2 requirements. Program requirements and differences are

illustrated on Tables 1 and 2:

Table 1--Program Eligibility Criteria

------------------------------------------------------------------------

Program 1 Program 2 Program 3

------------------------------------------------------------------------

No offsite accident history. .................. Process is subject

to OSHA PSM.

No public receptors in worst- The process is not Process is in SIC

case circle. eligible for code 2611, 2812,

Program 1 or 3. 2819, 2821, 2865,

2869, 2873, 2879,

or 2911.

Emergency response ..................

coordinated with local

responders.

------------------------------------------------------------------------

Table 2--Comparison of Program Requirements

------------------------------------------------------------------------

Program 1 Program 2 Program 3

------------------------------------------------------------------------

Hazard Assessment:

Worst-case analysis......... Worst-case analysis. Worst-case analysis.

Alternative releases Alternative

releases.

5-year accident history..... 5-year accident 5-year accident

history. history.

Management Program:

Document management Document management

system. system.

[[Page 31671]]

Prevention Program:

Certify no additional steps Safety Information.. Process Safety

needed. Information.

Hazard Review....... Process Hazard

Analysis.

Operating Procedures Operating

Procedures.

Training............ Training.

Maintenance......... Mechanical

Integrity.

Incident Incident

Investigation. Investigation.

Compliance Audit.... Compliance Audit.

.................. Management of

Change.

.................. Pre-startup Review.

.................. Contractors.

.................. Employee

Participation.

.................. Hot Work Permits.

Emergency Response Program:

Coordinate with local Develop plan and Develop plan and

responders. program. program.

Risk Management Plan

Contents:

Executive Summary........... Executive Summary... Executive Summary

Registration................ Registration........ Registration.

Worst-case data............. Worst-case data..... Worst-case data.

5-year accident history..... Alternative release Alternative release

data. data.

Certification............... 5-year accident 5-year accident

history. history.

Prevention program Prevention program

data. data.

Emergency response Emergency response

data. data.

Certification....... Certification.

------------------------------------------------------------------------

The owner or operator of a covered process must: (1) prepare and

submit a single risk management plan (RMP), including registration that

covers all affected processes and chemicals; (2) conduct a worst-case

release scenario analysis, review accident history, ensure emergency

response procedures are coordinated with community response

organizations to determine eligibility for Program 1 and, if eligible,

document the worst case and complete a Program 1 certification for the

RMP; (3) conduct a hazard assessment, document a management system,

implement a more extensive, but still streamlined prevention program,

and implement an emergency response program for Program 2 processes;

and (4) conduct a hazard assessment, document a management system,

implement a prevention program that is fundamentally identical to the

OSHA PSM Standard, and implement an emergency response program for

Program 3 processes.

Measures taken by sources to comply with OSHA PSM for any process

that meets OSHA's PSM standard are sufficient to comply with the

prevention program requirements of all three Programs. EPA will retain

its authority to enforce the prevention program requirements and the

general duty requirements of CAA Section 112(r)(1). EPA and OSHA are

working closely to coordinate interpretation and enforcement of PSM and

accident prevention programs. EPA will also work with state and local

agencies to coordinate oversight of worker and public safety and

environmental protection programs.

C. Hazard Assessment

EPA has adopted the worst-case definition proposed in the SNPRM.

For all substances, the worst-case release scenario will be defined as

the release of the largest quantity of a regulated substance from a

vessel or process line failure, including administrative controls and

passive mitigation that limit the total quantity involved or the

release rate. For most gases, the worst-case release scenario assumes

that the quantity is released in 10 minutes. For liquids, the scenario

assumes an instantaneous spill; the release rate to the air is the

volatilization rate from a pool 1 cm deep unless passive mitigation

systems contain the substance in a smaller area. For flammables, the

worst case assumes an instantaneous release and a vapor cloud

explosion.

For the final rule, EPA has adopted the term ``alternative release

scenarios'' to replace the term ``other more likely scenarios'' found

in the NPRM and SNPRM. The non-worst-case accidental releases for the

hazard assessment portion of the risk management plan were presumed

``more likely to occur'' and ``more realistic'' than the worst case.

EPA believes sources should have flexibility to select non-worst-case

scenarios that are the most useful for communication with the public

and first responders and for emergency response preparedness and

planning. Catastrophic accidental releases are typically rare events;

the words ``more likely'' suggests certainty of occurrence.

Consequently, the scenarios other than worst case provided in the

hazard assessment are called alternative release scenarios. For

alternative scenarios, sources may consider the effects of both passive

and active mitigation systems.

One worst-case release scenario will be defined to represent all

toxics, and one worst-case release scenario will be defined to

represent all flammables held above the threshold at the source.

Additional worst-case release scenario(s) must be analyzed and reported

if such a release from another covered process at the source

potentially affects public receptors that would not be potentially

affected by the first scenario. EPA recognizes that this approach may

be problematic for some sources such as batch processors and warehouses

where use of listed substances or inventory may vary considerably

within an RMP reporting period. EPA suggests that owners or operators

of such processes develop a worst-case scenario for future chemical use

and inventory based on past practices to minimize the need for frequent

revision of their worst-case scenario. For alternative release

scenarios, one scenario is required for each toxic substance and one to

represent all flammable substances held in covered processes at the

source.

An endpoint is needed for the offsite consequence analysis.

Appendix A of today's rule lists the endpoints for toxic substances

that must be used in worst-

[[Page 31672]]

case and alternative scenario assessment. The endpoint for a toxic

substance is its Emergency Response Planning Guideline level 2 (ERPG-2)

developed by the American Industrial Hygiene Association (AIHA). If a

substance has no ERPG-2, then the endpoint is the level of concern

(LOC) from the Technical Guidance for Hazards Analysis, updated where

necessary to reflect new toxicity data. EPA recognizes the limitations

associated with ERPG-2 and LOC values and is working with other

agencies to develop Acute Exposure Guideline Limits (AEGLs). When these

values have been developed and peer-reviewed, EPA intends to adopt them

through rulemaking as the toxic endpoints for this rule. For

flammables, vapor cloud explosion distances will be based on an

overpressure of 1 psi; for alternative flammable releases, radiant heat

distances will be based on an exposure of 5 kW/m\2\ for 40 seconds. For

vapor cloud fires and jet fires, the lower flammability limit provided

by the National Fire Protection Association (NFPA) or other sources

shall be used.

EPA selected 1.5 meter per second (m/s) wind speed and F

atmospheric stability class as the default worst-case scenario

meteorological conditions. If the owner or operator has meteorological

data that show that higher minimum wind speeds or less stable

atmospheric class conditions existed at the source at all times in the

previous three years, then the higher wind speed and different

stability class may be used. Alternative release analyses may use site-

specific, typical meteorological conditions. If the owner or operator

has no data on typical meteorological conditions, then conditions used

in the RMP Offsite Consequence Analysis Guidance (3 m/s and D

stability), may be used. Although EPA is providing technical guidance

and reference tables for worst-case and alternative release scenario

assessments, owners or operators may use any generally recognized,

commercially or publicly available air dispersion modeling techniques,

provided the modeling parameters specified in the rule are used.

For the hazard assessment and the RMP, populations potentially

affected are defined as those within a circle that has as its center

the point of release and its radius the distance to the toxic or

flammable endpoint. Owners or operators may use Census data to define

this population, and may update those data if they are inaccurate. EPA

suggests that owners or operators use LandView, an electronic

publication of environmental, geographic and demographic information

published by EPA and the Bureau of Census. The presence of schools,

hospitals, other institutions, public arenas, recreational areas, and

large commercial and industrial developments that can be identified on

street maps within this circle must be noted in the RMP, but the number

of people occupying them need not be enumerated. The presence of

environmental receptors within this circle must also be listed. EPA has

defined environmental receptors as natural areas such as national or

state parks, forests, or monuments; officially designated wildlife

sanctuaries, preserves, refuges, or areas; and Federal wilderness

areas, that can be exposed to an accidental release. All of these can

be identified on local U.S. Geological Survey maps or maps based on

USGS data.

The five-year accident history will cover all accidents involving

regulated substances, but only from covered processes at the source

that resulted in serious on site or certain known offsite impacts in

the five years prior to the submission of each RMP. EPA has replaced

the definition of significant accidental release with specific

definitions of the types of releases to be covered under each of the

specific requirements previously associated with this definition.

D. Prevention Programs

EPA has retained the management system requirement proposed in the

NPRM, but only for Program 2 and 3 processes. EPA has moved the

management system requirement from the prevention program section to

the general requirements section because it should be designed to

oversee the implementation of all elements of the risk management

program. The owner or operator must designate a qualified person or

position with overall responsibility for the program and specify the

lines of authority if responsibility for implementing individual

requirements is assigned to other persons or positions.

In the SNPRM, EPA proposed a Program 2 prevention program that

covered training, maintenance, safety precautions, and monitoring, but

did not specify any particular actions. EPA solicited comment on

whether specific prevention activities should be required for Program 2

sources, such as any of the specific activities initially proposed in

the NPRM. For today's rule, EPA has developed seven specific elements

for the Program 2 prevention program: safety information (Sec. 68.48),

hazard review (Sec. 68.50), operating procedures (Sec. 68.52), training

(Sec. 68.54), maintenance (Sec. 68.56), compliance audits (Sec. 68.58),

and incident investigation (Sec. 68.60). Most Program 2 processes are

likely to be relatively simple and located at smaller businesses. EPA

believes owners or operators of Program 2 processes can successfully

prevent accidents without a program as detailed as the OSHA PSM, which

was primarily designed for the chemical industry. EPA combined and

tailored elements common to OSHA's PSM and EPA's NPRM to generate

Program 2 requirements and applied them to non-petrochemical industry

processes. EPA is also developing model risk management programs (and

RMPs) for several industry sectors that will have Program 2 processes.

These model guidances will help sources comply by providing standard

elements that can be adopted to a specific source. EPA expects that

many Program 2 processes will already be in compliance with most of the

requirements through compliance with other Federal regulations, state

laws, industry standards and codes, and good engineering practices.

The Program 3 prevention program includes the requirements of the

OSHA PSM standard, 29 CFR 1910.119 (c) through (m) and (o), with minor

wording changes to address statutory differences. This makes it clear

that one accident prevention program to protect workers, the general

public, and the environment will satisfy both OSHA and EPA. For

elements that are in both the EPA and OSHA rules, EPA has used OSHA's

language verbatim, with the following changes: the replacement of the

terms ``highly hazardous substance,'' ``employer,'' ``standard'' and

``facility'' with ``regulated substance,'' ``owner or operator,''

``part or rule,'' and ``stationary source''; the deletion of specific

references to workplace impacts or to ``safety and health;'' changes to

specific schedule dates; and changes to references within the standard.

The ``safety and health'' and ``workplace impacts'' references occur in

OSHA's PSM standard in process safety information (29 CFR 1910.119

(d)(2)(E)), process hazards analysis (29 CFR 1910.119(e)(3)(vii)), and

incident investigation (29 CFR 1910.119(m)(1)). These changes are

designed to ensure that OSHA retains its oversight of actions designed

to protect workers while EPA retains its oversight of actions to

protect public health and the environment and to remove possible

interpretations that certain elements of process safety management fail

to account for offsite impacts. Commenters were particularly concerned

about the phase-in of process hazard analyses

[[Page 31673]]

(PHAs). Under the final rule, PHAs conducted for OSHA are considered

adequate to meet EPA's requirements. They will be updated on the OSHA

schedule (i.e., by the fifth anniversary of their initial completion).

This approach will eliminate any need for duplicative analyses.

Documentation for the PHA developed for OSHA will be sufficient to meet

EPA's purposes.

EPA anticipates that sources whose processes are already in

compliance with OSHA PSM will not need to take any additional steps or

create any new documentation to comply with EPA's Program 3 prevention

program. Any PSM modifications necessary to account for protection of

public health and the environment along with protection of workers can

be made when PSM elements are updated under the OSHA requirements. EPA

has modified the OSHA definition of catastrophic release, which serves

as the trigger for an incident investigation, to include events ``that

present imminent and substantial endangerment to public health and the

environment.'' As a result, this rule requires investigation of

accidental releases that pose a risk to the public or the environment,

whereas the OSHA rule does not. EPA recognizes that catastrophic

accidental releases primarily affect the workplace and that this change

will have little effect on incident investigation programs already

established. However, EPA needs to ensure that deviations that could

have had only an offsite impact are also addressed.

E. Emergency Response

EPA has adopted the emergency response requirements found in the

statute, without additional specific planning requirements beyond those

necessary to implement the statute. This action is consistent with the

Agency's effort to develop a single Federal approach for emergency

response planning. The Presidential Review of Federal release

prevention, mitigation, and response authorities (required under

section 112(r)(10) of the Clean Air Act) found that there is seldom

harmony in the required formats or elements of response plans prepared

to meet various Federal regulations. Accordingly, EPA has committed not

to specify new plan elements and/or a specific plan format in today's

rule beyond those that are statutorily required. EPA believes that

plans developed to comply with other EPA contingency planning

requirements and the OSHA Hazardous Waste and Emergency Operations

(HAZWOPER) rule (29 CFR 1910.120) will meet most of the requirements

for the emergency response program. In addition, EPA and other National

Response Team agencies have prepared Integrated Contingency Plan

Guidance (``one plan'') (NRT, May 1996). The NRT and the agencies

responsible for reviewing and approving federal response plans to which

the one plan option applies agree that integrated response plans

prepared in the format provided in this guidance will be acceptable and

be the federally preferred method of response planning. An emergency

response plan that includes the elements specified in this guidance can

be used to meet the requirements in today's rule. The final rule also

provides relief for sources that are too small to respond to releases

with their own employees; these sources will not be required to develop

emergency response plans provided that procedures for notifying non-

employee emergency responders have been adopted and that appropriate

responses to their hazards have been addressed in the community

emergency response plan developed under EPCRA (42 U.S.C. 11003) for

toxics or coordinated with the local fire department for flammables.

F. Risk Management Plan (RMP)

Owners or operators must submit their first RMP by the date

specified in Sec. 68.10. After the RMP is submitted, changes at the

source may require updates to the RMP other than the standard update

every five years. If a new substance or new process is added, the RMP

will need to be revised and submitted by the date the substance is

first in the process above the threshold quantity. If changes to

processes require revised hazard assessments or PHAs, or if a process

changes Program level, the source must submit a revised RMP within six

months.

EPA intends that the RMP will be submitted in a method and format

to a central point as specified by EPA. States, local entities

including local emergency planning committees (LEPCs), and the public

will be able to access all RMPs electronically. This process will

relieve states and local entities of the burden of filing documents and

providing public access to them without limiting these agencies' or the

public's access to the information.

The RMP is a multi-purpose document. The CAA requires that the RMP

indicate compliance with the regulations and also include the hazard

assessment, prevention program, and emergency response program. EPA is

mandated to develop a program for auditing RMPs and requiring

revisions, where appropriate. The RMP, therefore, must include enough

data to allow the implementing agency to determine, through review of

the RMP, whether the source is in compliance with the rule. EPA,

however, believes that the RMP must serve another function; to provide

information to the public in a form that will be understandable and

will encourage the public to use the information to improve the

dialogue with sources on issues related to prevention and preparedness.

To meet both of these purposes, the RMP will consist of the

source's registration; an executive summary that will provide a brief

description of the source's activities as they relate to covered

processes and program elements; and data elements that address

compliance with each of the rule elements. While the public and

implementing agencies could make use of all sections of the RMP, the

executive summary will provide text descriptions and give the source a

chance to explain its programs in a format that will be easy for

communities to read and understand. The data elements will provide the

implementing agency with the basic data it needs to assess compliance

without asking for detailed documentation. The Agency is considering

development of an RMP form where the data elements of the form would

provide the implementing agency with the basic data it needs to assess

compliance without asking for detailed documentation. All data elements

would be checkoff boxes, yes/no answers, or numerical entries.

This approach will provide data that anyone can download or search.

States, communities, trade associations, or public interest groups may

want to use the data or a subset of the data to create databases that

allow them to compare sources in the same industry or same area. For

example, a local entity will be able to download data from all

reporting sources that are similar to ones in its community to

determine whether the quantities stored and process controls used are

typical. The information will provide the public with data that will

enhance their dialogue with sources. It will also help sources and

trade associations to understand practices in their industries and

identify practices that could be used to reduce risks. The risk

management program documentation will remain at the source and will be

available for review by EPA and the implementing agency.

G. Air Permitting

The SNPRM discussed the relationship between section 112(r) and CAA

air permitting requirements for sources subject to both provisions.

Under the CAA, air permitting authorities must ensure that sources are

[[Page 31674]]

in compliance with applicable requirements to issue a permit. Because

section 112(r) is an applicable requirement, EPA has identified in the

final rule the permit conditions and the actions owners or operators

and air permitting authorities must take to ensure compliance. The

permit must identify part 68 as an applicable requirement and establish

conditions that require the owner or operator of the source to submit

either a compliance schedule for meeting the requirements of part 68 by

the date specified in Sec. 68.10(a) or, as part of the compliance

certification submitted under 40 CFR 70.6(c)(5), a certification

statement that, to the best of the owner or operator's knowledge, the

source is in compliance with all requirements of this part, including

the registration and submission of the RMP. The owner or operator must

also submit any additional relevant information requested by the air

permitting authority or designated agency to ensure compliance with the

requirements of this section. If a permit is already issued that does

not contain the provisions described above, then, the owner or operator

or air permitting authority shall initiate permit revision or reopening

according to the procedures in 40 CFR 70.7 or 71.7 to incorporate the

terms and conditions as described above. EPA also allows the state to

assign the authority to implement and enforce these requirements to

another agency or agencies (the ``designated agency'') to take

advantage of resources or accident prevention expertise that might be

available in these other agencies. Finally, the air permitting

authority or designated agency must: (1) Verify that the source owner

or operator has registered and submitted an RMP or a revised plan when

required; (2) verify that the source owner or operator has submitted

the proper certification or compliance schedule; (3) for some or all

sources, use one or more mechanisms such as, but not limited to, a

completeness check, source audits, record reviews or facility

inspections to ensure that permitted sources are in compliance; and (4)

initiate enforcement action, based on the requirements of this section,

as appropriate.

H. Other Issues

In the SNPRM, EPA discussed three other issues raised by

commenters: accident information reporting, public participation, and

inherently safer technologies. EPA has decided not to develop any

requirements related to these issues at this time. Although EPA

continues to believe that accident reports that provide more detail on

the causes and impacts of accidents could be useful, the Agency has

decided to limit such reporting required under this rule to the five-

year accident history mandated by the CAA. When necessary, EPA will use

its authority to investigate individual accidents and to seek

additional information to the extent authorized by CAA section 114

(i.e., to determine compliance with this rule and CAA section

112(r)(1), to support further rule development, and to assist research

on hazard assessment).

Secondly, the Agency encourages sources, the public, and local

entities to work together on accident prevention issues, but believes

that the wide variety and large number of sources subject to this rule

make any single mandatory approach to public participation

inappropriate. RMP information should be used as the basis for dialogue

between the community and sources on accidental release prevention,

risk reduction and preparedness for emergency response. Industry and

the public should continue to use the LEPC as a mechanism for this

dialogue.

Finally, EPA does not believe that a requirement that owners or

operators conduct searches or analyses of alternative process

technologies for new or existing processes will produce significant

additional benefits. Many commenters, including those who support these

analyses, indicated that an assessment of inherently safer design

alternatives has the most benefit in the development of new processes.

Industry generally examines new process alternatives to avoid the

addition of more costly administrative or engineering controls

associated with a design that may be more hazardous in nature. Although

some existing processes may be judged to be inherently less safe than

others, EPA believes most of these processes can be safely operated

through management and control of the hazards without spending

resources searching for unavailable or unaffordable new process

technologies. Application of good PHA techniques often reveals

opportunities for continuous improvement of existing processes and

operations without a separate analysis of alternatives. EPA encourages

owners or operators to continue to examine and adopt viable alternative

processing technologies, system safeguards, or process modifications to

make new and existing processes and operations inherently safer.

Through the process and prevention program information in the RMP,

sources can demonstrate, and users of the RMP information can observe

and promote, progress toward safer processes and operations.

EPA is considering the development of incentives and awards to

stimulate inherently safer alternative research and development, public

outreach and education, and risk communication efforts. The Agency

welcomes ideas and participation in this effort.

III. Discussion of Comments

EPA received 1220 comments, including 180 relevant comments

submitted for the List Rule, 757 comments on the NPRM, and 283 comments

on the SNPRM. The commenters represented 92 chemical manufacturers, 81

other chemical users, 111 petroleum industry companies, 174 industry

trade associations, 40 other trade associations, 58 agricultural supply

retailers, 102 propane retailers, 132 explosives users, 29 water

treatment facilities, 26 utilities, 66 state agencies, 63 local

governments, 8 other Federal agencies, 52 academics and consultants, 61

environmental groups, 6 labor unions, and 31 private citizens. The

remaining 88 letters were requests for extensions of the comment

period, interim or duplicate sets of comments, or had been sent to the

incorrect docket. The major issues raised by the commenters are briefly

addressed below; a complete presentation of the Agency's response to

the comments received on this rulemaking is available in the Risk

Management Program Rule: Summary and Response to Comments in the docket

(see ADDRESSES).

Many commenters requested that EPA's list be identical to OSHA's

list of highly hazardous substances and no thresholds should be less

than OSHA's. These comments were addressed in the final list rule (59

FR 4478; January 21, 1994) and background material related to these

issues is available in docket number A-91-74 (see ADDRESSES).

A. Tiering

Commenters on the NPRM suggested that EPA create different levels

of requirements for sources that pose different risks. In the SNPRM,

EPA proposed three tiers: a low hazard tier for sources whose worst-

case release would not affect any public or environmental receptors of

concern; a medium hazard tier for sources that were not eligible or

covered by the low or high hazard tiers; and a high hazard tier based

on either industry sector accident history and number of employees or

simply based on the number of employees. Generally, commenters were

concerned that all processes at a source would need to be eligible for

Program 1 before any process could be. EPA has revised the rule to

clarify that eligibility for any tier

[[Page 31675]]

(Program) is based on process criteria, not source. If a process meets

Program 1 criteria, the owners or operators need only meet Program 1

requirements for that process even if other processes at the source are

subject to Program 2 or Program 3.

1. Rationale. Only 2 of the 57 commenters opposed tiering arguing

that the CAA mandates that all covered sources be required to complete

a full prevention program and that Congress had considered and rejected

exemptions. One commenter argued that EPA had already accounted for

``differences in size, operations, processes, class and categories of

sources'' in developing the list and thresholds. Most commenters

supported tiering as an appropriate way to recognize different levels

of risks and to allow sources and emergency responders to focus on the

highest risk processes.

EPA disagrees that the CAA requires all covered processes to comply

with the same detailed risk management program. EPA listed regulated

substances because of their inherent hazards, such as toxicity and

volatility. EPA did not consider, nor does the CAA indicate that it may

consider, ``differences in size, operations, processes, class and

categories of sources'' in selecting chemicals or setting thresholds.

In establishing section 112(r)(7) requirements, however, Congress

clearly recognized that a ``one-size-fits-all'' approach may not be

appropriate for these regulations and directed EPA to consider these

factors in the development of the accident prevention regulations.

Furthermore, EPA strongly disputes the assertion that it has exempted

any source from regulation by creating different programs for different

sources. As noted below, all covered processes will be addressed in

RMPs that contain hazard assessment, prevention, and response

information, as required by statute.

2. Program 1 vs. Program 2 and Program 3 Criteria. Commenters

generally supported Program 1 for low-risk sources, but argued that

few, if any, sources would qualify because the requirements were too

stringent.

a. Potential for Offsite Impact. Commenters generally agreed that

sources that can demonstrate no offsite impact should be eligible for

Program 1, but only public health should be considered, not

environmental impacts. Others stated that only sources posing a threat

of ``considerable'' impacts should not be eligible for Program 1. One

commenter stated that EPA's worst-case scenario is unrealistic and its

use as a Program 1 trigger is unreasonable. Other commenters want EPA

to allow site-specific modeling for the offsite consequence analysis,

rather than look-up tables.

In today's rule, EPA specifically allows owners or operators to use

site-specific air dispersion modeling for their offsite consequence

analyses. EPA disagrees that offsite impacts should be limited to

``considerable'' impacts. When offsite impacts are possible, it may be

reasonable to implement some additional measures to reduce accidental

releases, especially when the burden of measures such as additional

training or safety precautions is low. Programs 2 and 3 provide

flexibility to allow source-specific consideration of the appropriate

level of effort. Program 1 requires no additional prevention measures,

which is only categorically justifiable if such measures would not

reduce offsite impact. It is reasonable to couple a no impact criterion

with a conservative worst-case scenario to conclude categorically the

public would not benefit from additional prevention measures. If no

impact can be demonstrated for a conservative worst-case release, then

no impact is likely to occur for any other release event, and the

process could be judged to pose a low threat to the surrounding area.

EPA has decided that potential impact on environmental receptors

resulting from a worst-case scenario will not be a criterion to

determine eligibility for Program 1. EPA agrees that very little, if

any, data exist on the potential acute environmental impacts or

environmental endpoints associated with listed chemicals upon

accidental release. In addition, the offsite consequence distances

estimated using human acute toxicity or overpressure effects may not be

directly relevant to environmental effects. However, owners or

operators will be required to document in the RMP the presence of such

receptors within the distance determined for the worst case. EPA

believes that natural resource agencies and the public will be able to

benefit from the environmental receptors information in the RMP in

discussions with the source.

b. Accident History for Program 1. Many commenters objected to

accident history as a Program 1 criterion, arguing that a process that

had a significant accidental release in the previous five years may

have been changed to reduce or eliminate future events and public

impact. Several commenters suggested that such processes that otherwise

meet Program 1 criteria should remain eligible, but be required to

justify and document the changes. Some commenters also objected to

EPA's proposed definition of significant accidental release, arguing

that many companies and emergency responders conservatively evacuate or

shelter-in-place during minor incidents. Under the proposed definition,

these actions disqualify a process from Program 1 even if there were no

offsite impacts. Some commenters stated that the accident history

provision was unnecessary because, by definition, a Program 1 process

is not capable of an accidental release that could affect public

receptors.

EPA has decided to retain the accident history criterion for

Program 1 processes, excluding events with evacuations and shelterings

in place, and to drop the definition of significant accidental release.

Program 1 eligibility is not a one-time exercise; owners or operators

must certify in each RMP that no qualifying releases have occurred

since the previous RMP submission and provide current worst-case

release data indicating no offsite impacts are anticipated in the

future. Program 1 criteria and accident history provide owners or

operators an opportunity to demonstrate to the community ongoing

excellence in accident prevention and an incentive to search for and

implement ways, such as inventory reduction, to reduce the potential

for offsite impacts associated with large scale accidental releases.

Further, the unique circumstances surrounding past accidents can

provide a reality check on the theoretical modeling and worst-case

scenario claims used for the offsite consequence assessment and serve

to verify that administrative controls and passive mitigation measures

work as intended. EPA decided to delete public evacuations or

shelterings-in-place as criteria for Program 1 eligibility. EPA is that

inclusion of these criteria in Program 1 eligibility may create a

perverse incentive not to report releases and it may encourage sources

and local emergency officials to take more chances during an event when

there may be potential exposures that do not rise to the endpoint

specified in this rule but would otherwise be worthy of precautionary

actions by the source or by local officials. If the evacuation or

sheltering takes place because of a concern for public exposure to an

endpoint as specified in this rule, then public receptors necessarily

would be under the worst case distance and the process would not be

eligible for Program 1 under the criteria of the rule. Owners or

operators of processes that meet Program 1 eligibility requirements are

required to report a 5 year accident history for that process. If local

[[Page 31676]]

emergency planners, first responders or the public have concerns about

processes in Program 1 because of a past evacuation or sheltering-in-

place event, then mechanisms under EPCRA could be used to gather more

information from the source about its prevention program (such as EPCRA

sections 302(b)(2) [designation of a facility if it does not already

handle extremely hazardous substances listed under section 302] and

303(d)(3) [provision of information to the emergency planning

committee]) and involve the source in emergency planning. Sources and

local first responders should be discussing evacuation and sheltering-

in-place criteria and decisions as part of emergency response planning.

c. Other. Many commenters asked that specific industries such as

ammonia refrigeration, retail fertilizer outlets, all flammables, and

all non-PSM sources be assigned to Program 1. EPA disagrees because

each source has unique surroundings that must be considered in the

worst-case assessment and each source must demonstrate favorable

accident history. All ammonia refrigeration units covered by this rule

are already subject to OSHA PSM; many of these have had accidents that

affected the community and should be required to complete the

requirements of the hazard assessment and emergency response program

and provide the community with full RMP information. According to the

industry, a typical ammonia fertilizer retailer handles 200 tons of

ammonia. Some retailers may be very geographically isolated and can

qualify for Program 1, but EPA expects that most will be subject to

Program 2. Given the large quantity of ammonia involved, EPA considers

it important that the community have information on offsite

consequences from these sources and that the owner or operator takes

the necessary steps to address accidental release prevention and

emergency response.

EPA expects that some sources handling flammables will qualify for

Program 1 because the distance to a 1 psi overpressure is generally

less than distances to toxic endpoints. Nonetheless, those sources

handling flammables in sufficient quantity to generate a potential

offsite impact should provide the community with information on hazards

and address prevention and response steps. Many sources handling

flammables are already subject to PSM; the only additional steps

required under this rule are completion of the hazard assessment and

emergency response programs and submission of an RMP.

EPA does not agree that non-PSM sources should be assigned to

Program 1. Many of these sources could have an accidental release that

can affect the community. OSHA exempted retailers because they are

covered by other OSHA or state regulations that address workplace

safety, not because they are incapable of having offsite impacts. All

retailers are in Program 2 unless they can meet Program 1 criteria;

thus, they should be taking prevention steps and will be providing the

community with information. Compliance with other existing Federal and

state programs may satisfy many Program 2 prevention requirements,

thereby limiting the burden. In addition, EPA expects to develop model

risk management programs for these sectors. Public sources in states

without delegated OSHA programs are not covered by OSHA PSM because

OSHA is barred by law from regulating them. Nonetheless, these sources

may pose a threat to the community. Today's rule places these sources

in Program 2.

3. Program 2 vs. Program 3 Criteria. In the SNPRM, EPA's preferred

approach assigned sources to Program 3 based on SIC code and number of

employees; sources in specified SIC codes with 100 or more full-time

employees (FTE) would have been subject to the full program in 3 years;

sources in a subset of these SIC codes with 20 to 99 FTEs would have

been subject to the full program in 8 years. The alternative was to

impose the full program on all sources with more than 100 FTEs. Most

SNPRM commenters submitted suggestions and arguments about this

approach.

a. Number of Employees. Only two commenters supported using the

number of employees as the sole criterion, arguing it would be the

easiest approach to implement with the greatest amount of industry

participation. Commenters opposed it because the number of employees

proposed does not reliably correlate with risk, hazard, or quantity on

site, and because it could act as an incentive to reduce employment. In

addition, some commenters stated that smaller sources may have fewer

resources to manage hazards and, therefore, may pose a greater risk to

the public.

EPA agrees and has deleted the number of employees as a Program 3

criterion. Although size of a source in the manufacturing sectors may

be related to the quantities on site and complexity of the processes,

many other sources may have similar characteristics with fewer

employees. Complexity is more directly associated with the type of

industry (i.e., SIC code) than with number of employees; a highly

automated process may involve fewer employees and be more complex than

a more labor intensive process. Quantity, if relevant, can be directly

measured rather than indirectly by number of employees. In addition,

EPA was concerned that the data on which the Agency based its proposed

approach may not be representative of all accidental releases. These

data, drawn from reports to the National Response Center and EPA

regions, appear to indicate that larger sources have more and larger

accidental releases than do smaller sources. This finding, however, may

in part reflect different levels of reporting, rather than different

levels of accidents. Both Federal and state officials report that the

number of releases has risen in recent years as more sources learn

about their reporting obligations. EPA has decided that, because the

processes within the SIC codes basically handle the same chemicals in

the same way, smaller sources should not be moved to a different

Program based on the number of employees.

b. SIC Code. Fifty-seven commenters, particularly those in the oil

industry, utilities, and public systems, supported the use of SIC codes

based on accident history; 28 commenters opposed it. Supporters argued

that industry accident records represented a reasonable criterion for

identifying high-risk sources. If an entire industry has a long history

without accidental release, it may indicate that the materials handled

and handling conditions generate a smaller potential for serious

releases or that the industry is effectively controlled by government

or industry standards. Some commenters argued that industry accident

histories reflect underlying risk better than individual source

accident histories because accidents are rare events; a source with no

accidental releases over the previous five years is not necessarily

safe.

Commenters opposing the use of SIC codes stated that the approach

is arbitrary, that accidents with only onsite effects should not be

used, that sources in other industry sectors handle similar quantities

and pose similar risks, and that sources within an industry that have

successful risk management practices are penalized by a few isolated

sources within the industry.

EPA has decided to retain the use of SIC codes, adding SIC 2865

based on further review of accident histories, and to add coverage by

the OSHA PSM standard as a separate criterion for Program 3. EPA

selected the SIC codes by analyzing accident data filed by

[[Page 31677]]

sources in response to EPA's request for information in the Accidental

Release Information Program (ARIP). ARIP collects data from certain

sources that report releases under CERCLA section 103. EPA selected the

SIC codes that showed a high frequency of the most serious accidents

across a significant percentage of all sources within the SIC code to

avoid mischaracterizing an industry based on isolated, problematic

sources. Data on the selection criteria were summarized in the SNPRM

and the docket at the time of the SNPRM. The accident history of the

cyclic crudes industry (SIC code 2865) is similar to that of the

categories selected. EPA disagrees that only offsite impacts should be

considered; accidental releases that caused death, hospitalizations, or

injuries on site are also of concern because they indicate significant

safety problems that could lead to releases that cause impacts offsite.

The SIC codes selected by EPA are basically the same ones OSHA selected

for its PSM program inspection focus. EPA disagrees that sources are

``penalized'' by this approach because owners or operators of processes

in these SIC codes have an opportunity to present their safety record,

demonstrate the success of their accident prevention programs, and

communicate with the local community the basis for their risk

management practices. Sources that receive Merit or Star status in the

OSHA Voluntary Protection Program will be favorably distinguished from

others in the same industry when implementing agencies are selecting

sources for audits (see section III.T.1 below).

EPA agrees that serious accidents occur infrequently even at

sources with poor safety practices and that industry-wide accident

records provide a better mechanism than the accident history at a

single source for identifying those sectors whose chemicals and

processes may lead to serious releases. A high proportion of the

sources in some SIC codes reported releases; EPA's analysis

specifically took into account the number of reports from individual

sources to avoid selecting an SIC code because of a small number of

sources with serious safety problems.

The OSHA PSM already applies to most covered processes in the

selected SIC codes. EPA expects that there will be fewer than 400

additional processes assigned to Program 3 that are not already subject

to the OSHA PSM standard at the approximately 1,400 sources in these

SIC codes and that all of these sources will already have other

processes covered by OSHA PSM. Consequently, fulfilling the RMP

requirements imposes little additional burden.

EPA decided to include all covered processes currently subject to

the OSHA PSM standard in Program 3 to eliminate any confusion and

inconsistency between the prevention requirements that the owners or

operators of such processes must meet. EPA's Program 3 prevention

program is identical to the OSHA PSM standard. Including OSHA PSM

processes in Program 3, therefore, imposes no additional burden on

these processes; the only new requirements for such processes are the

hazard assessment, emergency response program, and the RMP, which are

the same under Programs 2 and 3.

c. Site-Specific, Risk-based Criteria. Many commenters stated that

Program assignment should be based on site-specific risk-based

criteria. Accident history is one such criterion and is discussed

separately in Section III.A.3.d. Other criteria suggested include

population density or proximity, quantity on site, number of substances

held above the threshold, process conditions, toxicity, volatility,

alternative release scenario results, or combinations of these factors

as a risk index.

EPA agrees with commenters that Program assignments should be risk-

based to the extent possible; however, as the variety of suggestions

indicates, a considerable number of variables would need to be

considered. EPA knows of no standard approach or equation that is used

and generally accepted. The variety of suggestions indicate the

likelihood that any proposed formula would meet opposition. No

commenter provided a method to comprehensively address these factors on

a nation-wide basis.

An important consideration for EPA in developing the rule

provisions for Program assignment was to avoid undue complexity,

confusion, and resource expenditure by sources and implementing

agencies implementing the rule's criteria. To some extent, EPA has

incorporated risk factors, including site-specific factors, in

determining which sources are eligible for which Program. For example,

Program 1 eligibility already considers the potential for offsite

impacts; any process for which there are no public receptors within the

distance to an endpoint from a worst-case release may be eligible for

Program 1, provided there have been no releases with certain offsite

consequences within the previous five years. Today's rule allows

sources to consider passive mitigation and administrative controls in

conducting the worst-case release analysis. Such site-specific

considerations affect the extent of potential exposure to a worst-case

release, and thus are reflected in the Program 1 eligibility criteria.

Elements of risk such as process complexity and accident history are

also reflected the design of Program 2 and Program 3 requirements and

the assignment of processes to these Programs. Program 2 sources

generally handle and store regulated substances, but do not react or

manufacture them. EPA believes Program 2 sources can take prevention

steps that are less detailed than those in the OSHA PSM standard and

still accomplish accident prevention that is protective of any

population nearby. Program 3 is reserved for processes already subject

to the OSHA PSM standard and processes with high accidental release

histories. The SIC codes with an accident history selected by EPA for

Program 3 are typically complex processes. The PSM standard was

designed for, and is particularly appropriate for, these processes.

EPA takes issue with the appropriateness of some of the suggested

factors. Meteorological conditions vary too much to be considered in

determining a risk level. Chemical quantity alone does not accurately

relate to risk because the location and handling conditions can

dramatically change the potential for exposures.

In addition, EPA has implementation concerns about a detailed,

national, multi-factor, risk-based approach, were it to be feasible.

States such as Delaware have used a simple version of a risk-based

approach and found that it created serious problems for the state and

the sources. Smaller sources and those without technical staff have had

great difficulty in implementing the approach and have had to rely on

state officials to determine applicability for them. Delaware

specifically recommended that EPA not attempt implementing a similar

approach on a national basis because of the burden it imposes on the

state and the confusion and uncertainty it creates for sources.

Delaware has fewer than 100 sources; nationally, EPA estimates that

66,000 sources will be subject to the rule, approximately 62,000 of

which are outside of the chemical and refining sectors. If implementing

agencies had to help most of these sources determine the index score

and Program for each process, not only would the burden on the agencies

be extreme, but implementation would also be delayed. Furthermore, were

EPA to simply identify risk factors without an index and leave the

determination of Program

[[Page 31678]]

level to sources or implementing agencies, the process for such site-

specific determinations would be even more complex and resource

intensive for sources and implementing agencies; it would create

disincentives for a state to become involved and to take on the role of

an implementing agency. EPA believes it is better to have sources and

agencies focus their resources on prevention activities.

EPA considered, but decided against, a less comprehensive risk-

based approach using proximity or population density as criteria for

distinguishing between Program 2 and 3. EPA recognizes that accidental

releases from sources near or in densely populated areas may harm more

individuals and be perceived to pose a greater risk than other sources.

However, as stated above, EPA believes that the type of process, its

complexity and accident history should be considered for Program 2 or 3

assignment, regardless of the number of people potentially exposed. In

other words, EPA does not believe the streamlined Program 2 prevention

elements should apply to a complex Program 3 process just because fewer

persons could be potentially exposed or that the Program 3 prevention

elements should apply to a Program 2 process because more people could

be potentially exposed. EPA believes that populations offsite should be

protected from harm based on the type of process; the Program 2

prevention elements, properly applied to the expected types of Program

2 processes, serves to protect off-site populations, just as the

Program 3 prevention elements for complex processes serves to protect

offsite populations.

If Program assignments were based on the alternative release

scenario results, sources would not have the flexibility and latitude

in today's rule for these scenarios because more definite criteria

would need to be considered to ensure the proper scenarios and results

are assessed. This places more emphasis and burden for sources on the

offsite consequence assessment rather than on accident prevention and

communication with the public and first responders. Furthermore,

because active mitigation includes process and control equipment that

may fail, considering such equipment in evaluating risk would not be

appropriate without detailed review by the source and oversight by the

implementing agency.

Some commenters suggested yet another variation of a less

comprehensive, ``risk''-based approach that would have EPA use a site-

specific analysis of likelihood of release to assign Program levels.

Many of the same difficulties in developing a ``risk index'' for

determining Program assignments would apply to an attempt to

incorporate likelihood in a more sophisticated manner than EPA was able

to do in its analysis of accident history by SIC code. In addition to

the substance-specific properties considered as part of the chemical

listing criteria, the site-specific likelihood of a release depends on

a number of factors, including the appropriateness of the equipment in

use, the maintenance of that equipment, operator performance, and

safety systems and their performance. Evaluating site-specific

likelihood of release requires data on each of these items; such data

rarely exist especially for complex processes where a variety of

equipment must be evaluated along with the performance of multiple

operators and maintenance workers. Using surrogate data (e.g.,

manufacturer's failure rate data) introduces error of an unknown

magnitude to the analysis. Such analyses are very costly and produce

results that are, at best, questionable.

EPA also believes that assessing the likelihood of a release at

most sites for site-specific individualized Program-level

determinations is neither technically feasible nor cost-effective. In

most cases, the data do not exist to conduct a meaningful analysis;

where they do exist, the cost of developing a defensible analysis and

overseeing it could well exceed the cost of compliance with the rule.

Such an approach would resemble a permit program, which would be

resource-intensive for sources and implementing agencies. EPA

determined that the simpler approach for assigning sources to Program 1

would provide regulatory relief for those sources that could not affect

the public while allowing other sources to devote their resources to

prevention activities rather than to analyses that would be subject to

legal challenges.

EPA notes that sources have the flexibility to implement

appropriate accident prevention measures based on the hazards and risks

discovered in the hazard review or process hazard analysis. The

structure of Programs 2 and 3, therefore, reflect site-specific risk

criteria. Further, the purpose of the risk management program and RMP

effort is to prevent accidents and facilitate local level dialogue

about the risks, prevention measures, and emergency response effort in

place at the source. The local community and first responders may have

far different concerns that should, and can be addressed better through

today's approach than those reflected by a risk index approach.

d. Accident History. Some commenters argued that EPA should assign

sources to Program 3 based on the accident history of the source. One

commenter suggested that any source with no accidental release that

exceeded a reportable quantity (as defined in CERCLA) for the previous

five years should be in Program 2. Others argued that a source should

be in Program 2 if it had no significant accidental release in the

previous five years. Some commenters said that a one-release standard

was too stringent and that two or more significant accidental releases

should be allowed before a source was assigned to Program 3. Another

commenter suggested that a source with no significant accidental

releases in the past five years and with few potentially impacted

neighbors should be placed in Program 2.

Other commenters opposed this approach, arguing that, in many

cases, sources take steps to prevent recurrences following a serious

release. In some cases, the offsite impacts from releases are minor and

would not justify assigning a source to a particular Program. Other

commenters stated that the absence of an accidental release can be

indicative of lower risk, but it can also simply mean that a release

has not yet occurred. Several commenters noted that a five-year time

period is statistically insignificant because accidental releases are

infrequent events.

EPA agrees that source-specific accident history is not a

reasonable basis for assigning processes to Programs 2 and 3. Given the

relative infrequency of serious accidents, a five- or even ten-year

period without an accident may not be indicative of safe operations. In

addition, the criteria necessary to define the types of past accidental

release for the purposes of program classification would need to be

based on a wide variety of variables and site-specific factors, which

would lead to confusion and unnecessary complexity. Factors such as

weather conditions at the time of the release, rather than the size of

a source or its management practices, often determine whether a release

has offsite consequences. EPA believes that accident history is

appropriately used on an industry-wide basis as described above for

selection of Program 3 sources. If accidental releases with

consequences appear to occur at a large proportion of sources within an

SIC code, where similar processes, equipment and chemicals are used,

then it is reasonable to conclude that

[[Page 31679]]

processes in that SIC code pose a greater likelihood of a high hazard

release than others. This approach removes the need for at least one

accident to occur at every source that EPA believes ought to be

assigned to a particular Program, especially when such accidents are

rare events. EPA is also concerned that using source-specific accident

history as a criterion would create an incentive for sources to fail to

report releases. Finally, as EPA has stated, assignments to Program 2

and 3 also consider the appropriateness of the prevention steps for the

types of sources. EPA believes that both Programs move sources to

greater accident prevention.

e. Other. Some commenters asked that the implementing agency be

given discretion to move a source into a different Program based on

local concerns and knowledge. EPA notes that states have the authority,

under the CAA, to impose more, but not less, stringent standards than

EPA (see CAA section 112(r)(11)).

A few commenters suggested that Program 2 be limited to sources for

which a model risk management program had been developed. The models

would be designed to reflect risks associated with categories of

sources that all use the same type of equipment and handle the

substances in the same way (e.g., propane retailers and users, ammonia

retailers). EPA considered this approach and decided that the Program 2

prevention program provides a better, generic prevention approach for

processes for which the more detailed PSM program would be

inappropriate. Limiting Program 2 to those industrial sectors where

industry-specific models are feasible would place some manufacturing

sources at a disadvantage simply because their chemical uses,

processes, and equipment were too varied to allow development of a

model or because there are too few sources to justify use of EPA or

industry resources to develop a model. In addition, if EPA were to

limit Program 2 to sources with model programs, Program 2 regulations

would need sufficient specificity to enforce the use of these models;

otherwise, sources would be able to ignore both PSM and the models. EPA

is also concerned that codifying the model plans could stifle

innovation in safety practices. If industry codes or other Federal

regulations on which parts of the models may be based were updated, EPA

would have to revise its models; given the time needed to propose and

adopt regulations, sources might have to delay implementation of new

systems and, in some cases, might be caught between complying with a

revised EPA or OSHA regulation or state law or complying with the

model. Consequently, EPA decided it was better to have models available

as guidance, but not require compliance with them. Further, EPA

believes that the key elements of good accident prevention practices

are captured within the requirements of the Program 2 prevention

program. Model programs and plans are likely to build on these

approaches, making it easier for sources in Program 2 to use models

that are later developed by others.

EPA is working with industry to develop model risk management

programs and RMPs for ammonia refrigeration systems, propane

distributors and users, and water treatment systems. EPA also expects

to develop models for ammonia retailers and wastewater treatment

systems. EPA encourages other industrial sectors to work together on

additional model development.

4. Program 1 Requirements. Commenters were generally opposed to

posting signs, and certification of no environmental impact.

a. Certification of No Environmental Impact. Many commenters stated

that it would be ``virtually impossible'' to certify ``no potential for

environmental impacts,'' as required by the SNPRM. Commenters said that

the definition of environmental impact was too vague, that the list of

environments suggested in the SNPRM was too broad, and that the

language seemed to require a full environmental consequence assessment,

making the requirement impossible. One commenter noted that companies

would find it difficult to assert that there could be ``no

environmental impacts'' even after an environmental consequence

assessment reveals insignificant impacts. Two commenters suggested that

EPA substitute ``low potential for environmental impact'' or ``no

potential for long-term, adverse environmental impact.'' Other

commenters requested that environmental impact be dropped or that the

requirement be changed to mirror the Program 1 eligibility criteria

with an indication in the RMP that no environmental receptors of

concern were within the worst-case distance to an endpoint.

As described above in section III.A.2.a. Potential for Offsite

Impact, EPA has decided not to make the presence of environmental

receptors a part of the eligibility criteria for Program 1 and has

deleted the certification requirement. Instead, owners or operators of

all covered processes will have to identify in the RMP any

environmental receptors that are within the distance potentially

affected by the worst case.

b. Signs. Commenters generally opposed the SNPRM requirement that

sources with Program 1 processes post signs warning of the hazards on

site if the only regulated substances present at the site above the

threshold quantity were listed for flammability. Commenters stated that

local and state fire and safety codes often already require such signs.

In addition, sources are already required under EPCRA section 312 to

file annual inventories with the LEPC and fire department that identify

hazards on site. Signs would have fulfilled the emergency response

program requirements for a source. Because Program 1 eligibility will

now be determined on a by-process basis rather than by source-wide

criteria and because EPA has revised the emergency response program

provisions as noted below, EPA has dropped the requirement for signs.

c. Emergency Response Program. In the SNPRM, EPA asked whether

additional emergency response planning and coordination should be

required for Program 1 processes. Some commenters supported this

requirement, while others stated that most sources are already covered

by EPCRA and participate in community response planning. Commenters

stated that because the worst-case release could not reach public

receptors, such efforts were not necessary.

In the final rule, EPA is requiring the owner or operator of a

Program 1 process to ensure that any necessary response actions have

been coordinated with local response agencies. EPA believes that local

responders may become involved in an incident, even if the public is

not threatened. No additional CAA-related planning activities are

required, however.

d. Other. Many commenters stated that, since Program 1 processes

generate no offsite impact, they should be exempt from this rule. One

commenter objected to Program 1 because members of the public,

particularly first responders and business visitors, could still be

hurt by a release. Other commenters suggested that the annual EPCRA

section 312 form could be amended to indicate that a source was covered

by the rule, replacing the RMP registration form.

The CAA requires that all sources with more than a threshold

quantity of a listed substance register an RMP, perform a hazard

assessment, and develop accidental release prevention and emergency

response programs. Therefore, total exemption of processes that meet

Program 1 criteria is not

[[Page 31680]]

possible. See S. Rep. No. 228, 101st Cong., 1st session, at 208

(``Senate Report'') (precursor of RMP provision mandating hazard

assessments for sources that exceed threshold for listed substance);

136 Congressional Record S16927 (daily ed. October 27, 1990) (remarks

of Sen. Durenburger, sources with more than a threshold quantity are

subject to regulations); 136 Cong. Rec. H12879 (daily ed. Oct. 26,

1990)(remarks of Rep. Barton)(all users of hazardous chemicals are

required to plan for accidents). Moreover, even if an exemption for

processes that exceed a threshold were permissible, the owner or

operator would need to take steps that are equivalent to the hazard

assessment to establish eligibility for the exemption. The offsite

consequence analysis is the most significant burden for a Program 1

process under this rule. The minimal additional actions required in

today's rule for Program 1 simply establish a record of eligibility and

a response coordination mechanism.

EPA recognizes that emergency responders and site visitors could be

hurt by an accidental release from any process, but notes that

responder safety is covered by OSHA and EPA under the HAZWOPER

regulations. It is the owners' or operators' responsibility to inform

visitors about the hazards and the appropriate steps to take in the

event of an accidental release from any process subject to today's

rule.

Finally, EPA has based the registration information requirements in

today's rule on the EPCRA section 312 Tier II form. The CAA requires

that the RMP be registered with EPA. Because the EPCRA form is not

submitted to EPA, it would not substitute for registration with EPA

either in its present or amended form. Completion of the registration

portion of the RMP should impose little additional burden on owners or

operators. However, EPA recognizes the information overlap between the

Tier II form and the RMP registration and is considering use of the RMP

registration for the Tier II reporting requirement.

5. Program 2 Requirements. Commenters were generally concerned

about the lack of specific requirements for the Program 2 streamlined

prevention program and emergency response requirements, and how

compliance with other regulations would be incorporated.

a. Streamlined Program. Commenters stated that the Program 2

prevention program does not provide much, if any, regulatory relief

because sources would need to address most of the ten elements of the

Program 3 prevention program. Others said that the majority of the

sources affected by the rule are already covered by OSHA PSM and

chemical industry standards, the Program 2 requirements do not satisfy

the CAA mandate, and that only a full process hazard analysis would

meet the hazard assessment requirements under section 112(r). Another

commenter argued that EPA's statement that sources must comply with the

CAA's general duty clause was inadequate because EPA has not used, and

has no policy about, the clause.

EPA agrees that the preferred approach in the SNPRM did not provide

sufficient detail on Program 2 prevention requirements to distinguish

it from Program 3. EPA solicited comments on whether Program 2 should

require additional, specific prevention steps. Today's rule provides

specific requirements as discussed in section I.D above and in Section

IV below. In the RMP, the owner or operator will be required to report

on other Federal or state regulations, industry codes, and standards

used to comply with prevention elements as well as any major hazards,

process controls, mitigation systems, monitoring and detection systems

examined in the hazard review. This streamlined prevention program

addresses many of the PSM elements as the basis for sound prevention

practices, but is tailored to processes with less complex chemical

uses; this program provides considerable regulatory relief by

substantially reducing the documentation and recordkeeping burden of

PSM. In addition, EPA will provide guidance and model risk management

programs to further assist Program 2 processes in developing and

maintaining good prevention program practices.

EPA disagrees that only a full PHA would meet the requirements of

the Act. Section 112(r) does not contain detailed requirements for the

hazard assessment, beyond the key components of accidental release

scenarios and a five-year accident history. EPA believes that a PHA is

more appropriately considered an element of a prevention program, such

as PSM. The statute does not mandate detailed PHA engineering analyses

for all sources, whether as part of the hazard assessment or the

prevention program. EPA believes PHAs involve a more detailed

engineering analysis than is necessary to prevent accidents at Program

2 sources. The ``hazard review'' provisions of Program 2 should be

sufficient to detect process hazards at these simpler processes. EPA

recognizes that although hazard assessments and PHAs or process hazard

reviews are discreet elements that can be performed independently,

hazard assessment results can enhance PHA or process hazards reviews

and in turn, the results of the PHA or review can enhance the hazard

assessment. EPA encourages owners or operators to make maximum use of

the PHA or review and hazard assessment information to manage risks and

prevent accidents.

Finally, sources with Program 2 requirements, as well as sources

with Program 1 or 3 requirements, must comply with the general duty

clause of CAA Section 112(r)(1). The general duty clause provides that

owners and operators have a general duty to identify hazards that may

result from accidental releases, design and maintain a safe facility,

and minimize the consequences of any releases that occur. The general

duty clause is a self-executing statutory requirement: it requires no

regulations or other EPA action to take effect. The clause provides a

separate statutory mechanism that EPA will use in appropriate

circumstances to ensure the protection of public health and the

environment. To date, EPA has undertaken several inspections designed

in part to determine compliance with Section 112(r)(1). As appropriate

at a future date, EPA may issue policies or guidance on application of

the general duty clause.

b. Other Regulations. Commenters generally agree that OSHA PSM,

HAZWOPER, the OSHA hazard communication standard (29 CFR 1910.1200),

and NFPA-58 are examples of other regulations or voluntary industry

standards that could be cited to meet the requirements of a Program 2

prevention program. Commenters requested that EPA provide a matrix or

crosswalk that indicates which other regulations, standards, and codes

met specific requirements. One commenter opposed the use of other

regulations or referencing of voluntary industry standards, stating

that, other than OSHA PSM, no other OSHA standard addresses safety

precautions or maintenance. Another commenter objected that this

approach creates another documentation burden without any commensurate

benefit.

EPA agrees that the SNPRM preferred approach for Program 2 was not

specific enough and has provided more detailed requirements in this

rule as noted above. EPA continues to believe that many of the Program

2 prevention requirements are already met through industry compliance

with existing regulations and voluntary standards. For example, ammonia

retailers whose processes are designed to meet the OSHA ammonia

handling rule (29 CFR

[[Page 31681]]

1910.111) should be able to meet the Program 2 requirement that the

process design meets good engineering practices. This effectively

allows sources to cite compliance with these other regulations and

standards instead of developing specific, duplicative elements solely

to comply with Program 2. EPA will also use these existing regulations

and standards as it develops model programs.

c. Emergency Response Program. Commenters supported considering

HAZWOPER programs as adequate to meet the Program 2 emergency response

program. A few commenters said that HAZWOPER is inadequate because it

does not consider offsite impacts or the environment. Some commenters

also said that coverage of a source by an EPCRA community emergency

response plan should be sufficient. Others said that any contingency

plan developed under Federal or state law should be considered

sufficient because the requirements under these programs are generally

consistent with EPA's proposed emergency response program; one

commenter noted that, for flammable processes, compliance with 29 CFR

1910.38 should be adequate because the response is usually evacuation

of employees. Five commenters opposed any requirement that sources with

Program 2 processes conduct drills or exercises because they represent

lower hazards.

Consistent with its efforts to consolidate Federal emergency

planning requirements, EPA has included language in the final rule that

will allow any source in compliance with another Federal emergency

response program that includes the elements specified in this rule to

use that program to meet these requirements. In particular, this

applies to response plans prepared in accordance with the National

Response Team's Integrated Contingency Plan Guidance (``one plan'')

(NRT, May 1996). EPA believes that sources should have a single

response plan; creation of multiple response plans to meet slightly

different Federal or state standards is counterproductive, diverting

resources that could be used to develop better response capabilities.

EPA recognizes that some sources will only evacuate their employees

in the event of a release. For these sources, EPA will not require the

development of emergency response plans, provided that appropriate

responses to their hazards have been discussed in the community

emergency response plan developed under 42 U.S.C. 11003 for toxics or

coordinated with the local fire department for flammables.

B. Offsite Consequence Analysis

1. Worst-Case Release Scenario. EPA proposed in the NPRM to define

the worst-case release as the ``loss of all of the regulated substance

from the process * * * that leads to the worst offsite consequences''

and that the scenario should assume ``instantaneous release.'' Hundreds

of commenters stated that instantaneous loss of the total process

contents is not technically feasible for complex systems and,

therefore, represents a non-credible worst case that would provide no

useful information to the public or the source for risk communication,

accident prevention, and emergency preparedness. Many commenters also

argued that this approach differed from the release modeling

assumptions contained in EPA's Technical Guidance for Hazards Analysis,

which has been the basis for community emergency planning activities

under EPCRA. Although some commenters were generally opposed to the

concept of worst case, most of the commenters were supportive of an

approach similar to that taken in the Technical Guidance.

In response to these comments, EPA proposed in the SNPRM to

redefine a worst-case scenario as the release, over a 10-minute period,

of the largest quantity of a regulated substance resulting from a

vessel or process piping failure. The 10-minute release time is drawn

from the Technical Guidance for Hazards Analysis. EPA believes this

duration is reasonable and accounts for comments arguing that an

``instantaneous'' release is unrealistic for large-scale releases.

EPA has decided to adopt the SNPRM approach for worst-case toxic

vapor releases in the final rule because most of the SNPRM comments

agreed that the redefinition is generally more credible and that the

10-minute time frame particularly applies to vapor releases. Although

some commenters argued that this approach still does not account for

all process-specific conditions, EPA believes it is reasonable and

representative of accident history. EPA notes that owners or operators

may use air dispersion modeling techniques that better account for

site-specific conditions, provided modeling parameters as specified in

the rule are applied. This release scenario will apply to substances

that are gases at ambient conditions, including those liquefied under

pressure. Gases liquefied by refrigeration only may be analyzed as

liquids if the spill would be contained by passive mitigation systems

to a depth greater than 1 cm.

Under the SNPRM, worst-case liquid spills were assumed to form a

pool in 10 minutes, with the release rate to the air determined by

volatilization rate. EPA recognized that this approach differs from the

use of an instantaneous release in the Technical Guidance, which EPA

cited as an alternative to its favored approach. The few comments

received were divided between support of this approach and arguments

that the 10-minute time frame was unrealistic for liquid releases

(particularly for pipelines and connected equipment) and thus did not

properly account for process-specific conditions.

EPA's approach for the liquid worst-case scenario in the final rule

is similar to the Technical Guidance methodology, in which the total

quantity of liquid in a vessel or pipeline is instantaneously spilled

upon failure, considering administrative controls or passive mitigation

discussed below. The rate of release to the air is not instantaneous;

it is determined by the volatilization rate of the spilled liquid,

which depends on the surface area of the pool formed after the spill.

The pool surface area is determined by assuming the spilled liquid

rapidly spreads out and forms a one-centimeter deep pool, unless

passive mitigation systems contain the pool to a smaller area. EPA

believes this approach is reasonable because total vessel or pipeline

failure will generally lead to immediate and rapid spillage followed by

pool volatilization. Further, if the liquid were assumed to spill over

a particular time frame rather than instantaneously, owners or

operators would need to calculate the amount of vapor emitted to the

air as the liquid is spilled, in addition to the volatilization rate as

the pool spreads out and reaches its maximum size. Computer-based

models are available for such calculations, but they are complex and

require considerable data input to use. EPA believes that liquid

spillage from a worst-case scenario is likely to be extremely rapid

such that the most significant portion of the release rate is given by

pool volatilization; consequently, liquid release time is not

necessary. Liquid spill rates and times could be reflected in

alternative scenarios discussed below.

As proposed, the worst-case for flammables assumes that the total

quantity of the substance in the vessel or pipeline vaporizes,

resulting in a vapor cloud explosion. If the vapor cloud explosion is

modeled using a TNT-equivalent methodology, then a 10 percent yield

factor must be used.

EPA requested comment in the SNPRM on whether the worst-case

scenario should include an additional

[[Page 31682]]

amount of substance that could potentially drain or flow from process

equipment interconnected with the failed vessel or pipeline. Many

commenters opposed this option, suggesting that it is technically

uncertain and would have little value in terms of what they saw as

EPA's intended purpose for the worst-case assessment. Other commenters

requested that ``interconnected equipment'' be defined and clarified.

Given the assumption of rapid release associated with initial equipment

failure, EPA agrees that determination of the spill rate from connected

piping and equipment is likely to be technically complex, very

different from that of the quantity in the vessel or failed pipeline,

and likely to extend the duration of volatilization rather than

affecting the rate overall. Therefore, EPA has not included this

requirement in the final rule.

EPA also sought comment in the SNPRM on options for the

determination of the relevant quantity of regulated substance in a

vessel or process piping for a worst-case release scenario: the maximum

possible vessel inventory (design capacity) at any time without regard

for operational practices and administrative controls; the maximum

possible vessel inventory unless there are internal administrative

controls (written procedural restrictions) that limit inventories to

less than the maximum; or historic or projected maximum operating

inventories without regard to administrative controls. EPA preferred

that the maximum vessel inventory including administrative controls

that might limit or raise the vessel quantity to be used in the worst-

case assessment and reported in the worst-case release analysis section

of the RMP. If the quantity used in the assessment were exceeded (e.g.,

an administrative control were ignored), then the source would be in

violation of the rule (i.e., failure to perform a worst-case analysis)

and RMP reporting unless the administrative control was revised, the

worst-case analysis updated to reflect any changes in the analysis, and

a revised RMP submitted. This approach acknowledges the efforts by

sources to increase process safety by intentionally reducing the

inventory of regulated substances (e.g., vessels kept at half capacity

to allow for process upsets, emergency shutdowns, and deinventorying or

maintenance turnarounds). EPA notes that at some sources, as a result

of inventory reduction measures, the largest quantity may be held in a

transportation container that is loaded or unloaded at the source (See

section P.2).

A few commenters supported the other options, noting that

administrative controls may fail, potentially generating a larger

scenario. However, the majority of commenters supported EPA's preferred

approach based on the historical reliability of such controls at many

sources and the role that such a provision could play in encouraging

their use at additional locations. Other commenters asked whether

mechanical controls, alone or in combination with administrative

controls, should be incorporated into the proposal. Although mechanical

controls may also serve to limit the quantity, EPA has decided not to

include them in the quantity determination for the worst-case release

scenario because the definition for administrative control as ``written

procedural mechanisms used for hazard control'' provides a backup for

possible failure of mechanical controls. For more discussion of

mechanical controls, see section III(B)(2), mitigation systems, below.

In the SNPRM, EPA considered providing the implementing agency with

the discretion to determine the appropriate quantity for the worst-case

release scenario on a site-specific or industry-specific basis. EPA

noted in the SNPRM, and most of the few comments received on this issue

agreed, that implementing agency discretion would result in increased

administrative burden on the implementing agency and cross-

jurisdictional differences in the methodology used for the worst-case

analyses. EPA has decided not to incorporate this approach in the final

rule. States, however, may impose more stringent requirements, such as

additional modeling, under state authority.

In the NPRM worst-case definition, EPA did not specify what

constitutes or how to determine the worst offsite consequences. Some

commenters indicated that without clear direction, EPA's proposed worst

case might not actually capture the scenario that leads to the most

severe offsite impact. In the SNPRM, EPA indicated that the worst-case

scenario should be the scenario that generates the greatest distance to

a specified endpoint (i.e., the toxic vapor cloud or blast wave from a

vapor cloud explosion that travels the farthest).

EPA recognizes that there may be other release scenarios that could

generate a greater distance than the release from the largest vessel or

pipeline. Consequently, EPA has added paragraph (h) to Sec. 68.25 to

require owners or operators to consider other scenarios if those

scenarios generate greater distances to the endpoint than the distance

generated by the largest vessel or pipeline scenario. Owners or

operators need to consider releases from smaller vessels if those

vessels contain the substance at higher temperature or pressures or if

they are closer to public receptors. In some cases, the largest vessel

will be a storage vessel where the substance is held at ambient

conditions. A reactor vessel may hold a smaller quantity, but at high

pressures and temperatures, generating a release that could travel

farther offsite to an endpoint. Vessel location is important,

especially at large sources. A smaller vessel located nearer to the

stationary source boundary may generate a greater impact distance than

a larger vessel farther away. This difference may be particularly

important for flammables, because impact distances for flammables are

generally shorter than those for toxic releases.

2. Mitigation Systems

a. Worst-case scenario. In the NPRM worst-case scenario, EPA

indicated that sources must assume that both active and passive systems

fail to mitigate the release. Commenters were generally split between

those who wanted passive (as well as certain redundant active)

mitigation systems to be included and those who argued that historical

evidence from catastrophic releases suggests that the worst case should

assume the failure of all such systems. Those who supported mitigation

argued that inclusion provides a more credible scenario for improved

risk communication, accident prevention, and emergency planning.

EPA proposed in the SNPRM to include passive mitigation systems in

the worst-case release scenario as long as the system is capable of

withstanding, and continuing to function as intended during and after a

destructive event, such as an earthquake, storm, or explosion, which

causes a vessel or pipeline to fail. Passive systems such as dikes,

catch basins, and drains for liquids, and enclosures for both liquids

and gases, could be assumed to mitigate the release. Some commenters

opposed this approach, arguing again that the worst case should account

for the possibility of passive mitigation failure. The majority

supported this approach because the assumption that passive systems

specifically designed and installed as protection against a potential

catastrophe fail is unrealistic. Furthermore, the approach recognizes

and encourages prevention through additional passive mitigation and

supports more realistic emergency

[[Page 31683]]

planning. A few commenters also suggested that active mitigation

measures that were unlikely to fail (e.g., redundant or backup systems)

should be considered, for similar reasons. Historical data, however,

indicate that certain events compromise active mitigation systems

(e.g., explosions have destroyed fire water piping systems).

For the final rule, EPA has decided to adopt the SNPRM approach.

Passive mitigation systems would be defined as those systems that

operate without human, mechanical, or other energy input and would

include building enclosures, dikes, and containment walls. EPA also

agrees that reservoirs or vessels sufficiently buried underground are

passively mitigated or prevented from failing catastrophically. In this

case, sources should evaluate the failure of piping connected to

underground storage for the worst case or alternative case scenarios.

In addition to the requirements outlined in Sec. 68.25, EPA provides

guidance on how passive mitigation would affect release rate and

distance to endpoints in its RMP Offsite Consequence Analysis Guidance.

b. Alternative scenarios. EPA initially proposed that sources could

include passive mitigation systems in their alternative scenario

assessments, but that active mitigation systems (e.g., excess flow

valves, fail-safe and automatic shutdown valves, scrubbers, flares,

deluge systems, and water curtains) would be assumed to fail. Some

commenters generally opposed inclusion of any mitigation systems in the

hazard assessment, while other commenters noted that the alternative

release scenario should recognize and encourage industry accident

prevention efforts, specifically the installation of additional

mitigation systems, and support more realistic emergency planning.

EPA proposed in the SNPRM to allow sources to consider passive and

active mitigation measures in the alternative release scenario

assessment. Commenters supported this approach and EPA has decided to

retain it in the final rule. EPA agrees that the assumption that both

passive and active mitigation measures fail when such measures are

specifically designed and installed to mitigate catastrophic releases

is unrealistic for the alternative scenarios. Although not required,

EPA notes that sources may choose to apply passive and active

mitigation measures to a worst-case type scenario to illustrate the

capabilities of such systems to reduce the potential impact of a worst-

case accidental release. In addition to the requirements outlined in

Sec. 68.28, EPA provides guidance in its RMP Offsite Consequence

Analysis Guidance on how passive and active mitigation would affect

release rate and distance to endpoints.

3. Populations Affected. EPA described in the NPRM preamble certain

locations (e.g., schools and hospitals) where sensitive populations

might be present and proposed in the rule that owners or operators

identify potentially exposed populations as part of the offsite

consequence assessment. Commenters generally opposed requirements for

population surveys; several commenters suggested that Census data or

other readily available population information should be sufficient,

while other commenters indicated that the LEPC or other local planning

entities were the appropriate entity to prepare these data.

EPA believes owners or operators need to be aware of the magnitude

of impact on populations associated with the worst-case and alternative

scenarios. However, EPA learned that, although much of this information

is readily available, identification of some sensitive populations

could require considerable effort, especially if the distance to an

endpoint generated in the offsite consequence assessment is large or

crosses several jurisdictions. Consequently, EPA proposed in the SNPRM

that offsite populations be defined using available Census data;

information on the number of children and people over 65 could be

considered a proxy for sensitive populations, thereby accomplishing the

same objective as the proposed rule. EPA also indicated that it has

developed a geographic information system, LandView, that will

facilitate analysis of resident populations. (LandView can be ordered

from the U.S. Bureau of the Census customer service at (301) 457-4100.)

In general, commenters agreed with the SNPRM approach. However, some

commenters questioned the accuracy of potentially ten-year-old Census

data and requested additional flexibility, or a greater role for local

government, in this analysis.

EPA has decided to adopt the approach outlined in the SNPRM for the

final rule. Sources will be allowed to use available Census data to

estimate populations potentially affected. Sources may update these

data if they believe the data are inaccurate, but are not required to

do so. Populations shall be reported to two significant digits. Because

Census data are limited to residential populations, sources will also

have to note in the RMP whether other, non-residential populations,

such as schools, hospitals, prisons, public recreational areas or

arenas, and major commercial or industrial areas, are within the

distance to an endpoint. These institutions and areas are those that

can generally be found on local street maps. Sources will not be

required to estimate the number of people who might be present at these

locations. EPA provides further guidance on the identification of

affected populations in its RMP Offsite Consequence Analysis Guidance.

4. Number of Scenarios In the NPRM. EPA required a worst-case

release scenario for each regulated substance. Commenters requested

clarification, because one substance could be present in more than one

process at the source and sources would need to select the ``worst''

worst case for substances in multiple processes. In addition, one

process may have several, similar listed substances and multiple worst-

case analyses of similar substances (e.g., flammables) would not

provide additional useful information to the public.

EPA proposed in the SNPRM that sources report in the RMP one worst-

case release scenario representative of all toxic substances present at

the source and one worst-case release scenario representative of all

flammable substances present at the source. Even though additional

screening analyses to determine the appropriate worst-case scenario

might be necessary, this approach reduces to a maximum of two the

number of worst-case analyses reported in the RMP by a source. In

general, commenters favored this approach, particularly for flammables,

which do not produce markedly different adverse effects. A few

commenters argued that a single toxic substance should not be

considered representative of all toxic substances at a source, since

there are considerable differences in toxic endpoint and adverse

affect.

EPA has decided to adopt the approach outlined in the SNPRM for the

final rule: report one worst-case release scenario for all flammables

and one worst-case release scenario for all toxics at the source. EPA

notes that the worst-case scenario is designed principally to support a

dialogue between the source and the community on release prevention,

and not to serve as the sole or primary basis for local emergency

planning. The ``worst'' worst-case release scenario will inform the

broadest range of individuals that they may be impacted by the source

so that they may participate in dialogue with the source about

prevention, preparedness, and emergency response actions. Lesser worst-

case release scenarios would not

[[Page 31684]]

inform any person not already within the range of the ``worst'' worst

case even though the health effects may be different; consequently, EPA

believes that only a single toxic worst case is necessary. However,

sources must also analyze and report another worst-case release

scenario (for flammables or toxics) if such a release from another

location at the source potentially affects public receptors different

from those potentially affected by the first scenario (e.g., if a

large-sized source is located between two communities and has a covered

process adjacent to each community).

In the NPRM, EPA did not specify the number of alternative

scenarios to be reported for each regulated substance. EPA noted in the

preamble that this approach, while providing flexibility, may also

create uncertainty about what EPA will consider to be an adequate

number of scenarios. While a few commenters argued against scenarios

beyond the worst case, many commenters supported a requirement for a

maximum of two: the worst case plus one additional scenario; others

supported a maximum of three. Many of the commenters noted that local

entities could request further information under EPCRA section

303(d)(3) authority if they desired. At the same time, a number of

commenters suggested that this determination should be made by the

source based on their scenario analysis, perhaps in coordination with a

local agency.

In the SNPRM, EPA proposed to require one alternative release

scenario for all flammable substances at the source and one alternative

scenario for each toxic substance at the source. As discussed above,

the listed flammable substances behave similarly upon release and have

the same endpoint, while each toxic substance has a different endpoint

and different atmospheric behavior. EPA sought comment on whether one

toxic substance alternative scenario could represent all toxic

substances at a source or in a process. Although commenters generally

agreed with the approach for flammables, only a few argued that a

single alternative scenario for all toxics was also appropriate; most

others supported EPA's proposal.

Upon review of the comments, EPA has decided to adopt the approach

outlined in the SNPRM: an alternative release scenario must be reported

in the RMP for each toxic held above the threshold at the source, and

one alternative scenario must be reported that represents all

flammables held above the threshold. As EPA noted in the SNPRM preamble

and commenters echoed, the differences in the hazards posed by

individual toxic regulated substances are significant and should be

reflected in the alternative scenarios. This information has

significant value for emergency planning purposes and could increase

public interest in prevention at the source.

5. Technical Guidance The proposed rule required sources to

evaluate the consequences (vapor cloud dispersion, blast wave, or

radiant heat modeling calculations) associated with the worst-case and

alternative release scenarios. EPA did not specify a methodology or

models, expecting that sources would have, contract for, or find the

expertise and modeling tools needed to perform potentially complex

modeling calculations. Because of the potential burden associated with

this approach, EPA began working on the development of a set of simple,

generic tools that could provide useful results and become part of the

technical guidance for the rule. Based on its experience in developing

the Technical Guidance for Hazards Analysis and on advice from

commenters, EPA understands that a generic methodology depends on

approximations to capture a wide variety of situations, will likely

ignore site-specific conditions, and potentially may generate overly

conservative or less realistic estimates of offsite impacts. In spite

of these limitations, EPA believes that generic modeling tools are

capable of supporting greater understanding of the hazards posed by

substances and emergency planning. Commenters agreed this approach

would reduce the burden on smaller sources unfamiliar with such

activities as long as use of the guidance was not mandatory, and the

guidance addressed specific industry sectors or was used as part of a

screening process to focus resources on significant problem areas. Many

commenters recommended that sources be given the flexibility to use any

appropriate modeling techniques for the offsite consequence analysis to

take advantage of expertise and to apply site-specific considerations

to the hazard assessment. Other commenters argued that EPA should

establish mandatory guidelines or specify certain dispersion modeling

tools to make release scenario results more comparable across sources.

Some commenters were concerned about the development of modeling tools

by EPA outside of the rulemaking process and requested the opportunity

to participate in their development.

In the SNPRM, EPA stated it would develop a generic methodology and

reference tables in an offsite consequence assessment guidance to

assist sources with the analyses required by the rule. EPA believed

that the Technical Guidance could be revised, expanded, and updated to

address the rule requirements. The methodologies and tables would be

subject to public review prior to publication of the final rule; once

finalized, the tables would replace the Technical Guidance. EPA added

that sources that wish to conduct more sophisticated modeling could do

so, provided the techniques used account for the modeling parameters

described in the rule. Alternatively, EPA proposed that only Program 2

sources use the guidance; Program 3 sources would be required to

conduct their own dispersion modeling.

Most commenters supported the SNPRM approach, especially if sources

were given the option to use their own site-specific modeling. Some

commenters argued that the generic methodology and reference tables and

the option for site-specific modeling should be applied to processes in

all three Programs, while others suggested that they be applied only to

a specific Program. In recognition of these comments, EPA prepared

draft modeling methodologies and reference tables, provided an

opportunity for their review (see 61 FR 3031, January 30, 1996), and

has published them as the RMP Offsite Consequence Analysis Guidance.

EPA intends to conduct peer review of the RMP Offsite Consequence

Analysis Guidance and will revise it as appropriate. For the final

rule, EPA will allow sources in all Programs to use the guidance or

conduct their own site-specific modeling, provided the modeling

techniques used account for the parameters described in the rule. For

example, EPA's Office of Air Quality Planning and Standards has

prepared a publicly available modeling tool called TScreen that can

assist owners and operators with consequence assessments. EPA also

encourages local emergency planners, fire departments, and others who

use tools such as CAMEO/ALOHA or other modeling techniques to assist

businesses in their community who may need help in their modeling

efforts. EPA believes the final rule approach takes advantage of the

broad range of expertise and modeling tools already available and will

provide more useful results at the local level for chemical emergency

prevention, preparedness, and response. This approach will also

stimulate accidental release modeling research, new and existing model

development, and model validation to generate new tools for better

understanding of hazards and the behavior of substances in accidental

release situations.

[[Page 31685]]

6. Modeling Parameters. a. Endpoints. In the NPRM, EPA did not

specify toxic or flammable substance endpoints that must be used in the

offsite consequence assessment modeling. Most commenters recommended

that EPA specify endpoints to provide a consistent basis for modeling;

many favored the use of existing standards or guidelines, primarily the

emergency response planning guidelines (ERPGs) developed by the

American Industrial Hygiene Association for toxic substances. For

flammables, commenters suggested overpressure, heat radiation, and

explosion or flammability limits. In addition to other specific

standards, a few commenters recommended a hierarchy of values if

certain levels for some chemicals were not available.

In the SNPRM, EPA indicated that it would select one endpoint for

each toxic substance for use in the offsite consequence assessment

methodology and sought comment on whether it should use a single

endpoint to the extent possible (e.g., the Immediately Dangerous to

Life and Health (IDLH) value developed by the National Institute for

Occupational Safety and Health (NIOSH), unless one does not exist for a

substance), or a hierarchy of endpoints (e.g., ERPGs; if one does not

exist, then the IDLH; and finally toxicity data if no other value is

available). EPA also asked whether overpressure or both overpressure

and radiant heat effects should be used for flammable substance

endpoints. Some commenters supported the use of ERPG values for the

toxic substance endpoint, or a hierarchy of values beginning with the

ERPG. Others opposed IDLH or the IDLH divided by 10 for technical

reasons.

EPA agrees with commenters that one toxic endpoint should be set

for each substance. The endpoint for each listed toxic substance is

provided in Appendix A to the final rule. The endpoint, applicable

whether the source uses the EPA guidance or conducts site-specific

modeling described below, is the AIHA ERPG-2 or, if no ERPG-2 is

available, the level of concern (LOC) developed for the Technical

Guidance, corrected where necessary to account for new toxicity data.

The LOCs that were based on IDLHs have been updated only if the IDLHs

were revised between the original LOC listing in 1987 and the 1995 IDLH

revisions. The most recent IDLH revisions were not used because they

are based on a methodology that EPA has not reviewed; the previous IDLH

methodology was reviewed by EPA's Science Advisory Board for use as

LOCs. EPA chose the ERPG-2 first because ERPGs are subject to peer

review and are specifically developed by a scientific committee for

emergency planning to protect the general public in emergency

situations. The ERPG-2 represents the maximum airborne concentration

below which the committee judges that nearly all individuals could be

exposed for up to an hour without experiencing or developing

irreversible or other serious human health effects or symptoms that

could impair their ability to take protective action. EPA rejected the

ERPG-3, which is a lethal exposure level, because it is not protective

enough of the public in emergency situations. About 30 listed toxic

substances have ERPGs. EPA chose to use LOC levels for substances with

no ERPG because LOCs have been peer reviewed by EPA's Science Advisory

Board, they are intended to be protective of the general public for

exposure periods of up to an hour, they are widely used by the

emergency response planning community, and, for a majority of the

listed toxic substances, there are no acceptable alternatives. EPA

notes that, for substances with both values, the LOC is comparable to,

and in some cases is identical to, the ERPG-2.

EPA recognizes potential limitations associated with the ERPG and

LOC and is working with other agencies to develop Acute Exposure

Guideline Limits (AEGLs). See Establishment of a National Advisory

Committee for Acute Exposure Guideline Levels (AEGLs) for Hazardous

Substances, (60 FR 55376; October 31, 1995). When these values have

been developed and peer-reviewed, EPA intends to adopt them, through

rulemaking, as the toxic endpoint for substances under this rule.

As proposed, vapor cloud explosion distances will be based on an

overpressure of 1 psi, and for analysis of worst-case releases, a yield

factor of 10 percent. Yield factors (the percentage of the available

energy released in the explosion process) can vary considerably. EPA

selected 10 percent to generate conservative worst-case consequences.

For flammables, EPA selected a radiant heat exposure level of 5 kW/

m2 for 40 seconds as recommended by the commenters, and, for vapor

cloud fire and jet fire dispersion analysis, the lower flammability

limit (LFL) as specified by NFPA or other recognized sources.

b. Meteorology. In the NPRM, EPA proposed that sources model the

downwind dispersion of the worst-case release scenario using an F

atmospheric stability class and 1.5 m/s wind speed and model the

alternative release scenarios using both the worst-case conditions and

the meteorological conditions prevailing at the source. EPA did not

revise the meteorological assumptions in the SNPRM.

Several commenters argued that the worst-case meteorological

conditions were too conservative or not applicable on a national basis

and that site-specific conditions should be used, while others agreed

that for worst case, minimum wind speeds and the most stable

atmospheric conditions should be used. In the final rule, EPA has

decided that sources must conduct worst-case dispersion modeling using

an F atmospheric stability class and a 1.5 m/s wind speed. A higher

wind speed or less stable atmospheric stability class may be used if

the owner or operator has local meteorological data applicable to the

source that show that the lowest recorded wind speed was always greater

or the atmospheric stability class was always less stable during the

previous three years.

In the final rule, EPA also requires sources to conduct alternative

release scenario dispersion modeling using the typical meteorological

conditions applicable to the source. If meteorological data are not

available, typical conditions in the RMP Offsite Consequence Analysis

Guidance may be used. EPA believes typical meteorological conditions

should be used to generate realistic hazard assessments for

communication with the public and first responders and for emergency

planning.

C. Consideration of Environmental Impact

The issue of whether and how environmental impacts should be

addressed in the hazard assessment and the rule in general drew

considerable comment. The comments divide into three questions: Should

EPA consider environmental impacts from accidental releases? If so,

which environments should be identified? What constitutes an

environmental impact?

1. Inclusion of Environmental Impacts. Environmental groups argued

that the CAA requires assessment of potential impacts to the

environment and that the environmental receptors listed in the SNPRM

should be broadened. One commenter stated that since the CAA Amendments

of 1990 strengthened limits of continuous air toxic emissions, wildlife

is now threatened more by accidental releases. However, the majority of

commenters on this issue, principally industry groups, opposed

consideration of the environment because it is adequately protected by

other environmental statutes, environmental protection in section

112(r) relates only to emergency

[[Page 31686]]

response, and Congress intended in section 112(r) for the environment

to be addressed only to the extent that human health is protected.

Several commenters argued that flammable substances were unlikely to

generate environmental impacts. Commenters also stated that many

industries have voluntarily developed nature reserves around their

sources, often at the urging of government agencies. Additional

regulations based on ``environmental'' impact consideration would

``penalize'' these sources for their efforts. Finally, two commenters

noted that EPA's endpoints are based on acute human effects; applying

these to the environment may not be valid.

EPA disagrees that section 112(r) was not intended to protect the

environment as well as human health. Although section 112(r)(5) links

the threshold quantity to human health, section 112(r)(3) requires EPA

to select substances that could impact human health and the

environment. EPA agrees that the only time sections 112(r)(7)(B)(I) and

(ii) mention protection of the environment is in conjunction with

emergency response; however, this is also true for protection of human

health. Congress did not intend to limit concern about either impact

strictly to emergency response procedures; Congress may not have

mentioned either impact relative to prevention because the act of

preventing an accident eliminates the impact on both. When accidents

occur, human health and the environment need protection. By mentioning

both impacts in the response or post accident phase, Congress was

stressing its concern for the environment as well as human health.

Given the integrated nature of the RMP, it would be an inappropriately

narrow reading of CAA section 112(r)(7)(B) to say environmental impacts

must be ignored in hazard assessments and in the design of the

prevention program, but must be accounted for in emergency response. In

addition, section 112(r)(9) provides authority for EPA to take

emergency action when an actual or threatened accidental release of a

regulated substance may cause imminent and substantial endangerment to

human health, welfare, or the environment. Clearly, section 112(r)(9)

allows EPA to take action to prevent, as opposed to simply respond to,

accidental releases to protect the environment. Because section

112(r)(7) is intended to prevent situations that could lead to

emergency orders under section 112(r)(9), it is logical to conclude

that Congress meant EPA to develop regulations that would prevent

accidental releases that could cause environmental damage. Although the

consequences may not be precisely known, EPA believes that impacts

could occur at environmental receptors located within the distance to a

human acute exposure endpoint associated with a worst-case or

alternative scenario because wildlife may be more sensitive or require

less exposure to cause an adverse effect than humans.

2. Environmental Receptors to Be Considered. In the SNPRM, EPA

proposed that sources report in their RMP which sensitive environments

listed by the National Oceanographic and Atmospheric Administration

(NOAA) for the Clean Water Act are within the distance determined by

the worst-case or alternative case scenario. A few commenters argued

that the list should include state and local level analogues to Federal

entities (e.g., state parks), all surface waters that are fishable or

swimmable or supply drinking water, and ground water recharge areas.

Many commenters opposed the NOAA list, arguing that the list is

extremely broad, covers millions of acres in primarily rural areas, and

contains areas that are difficult for both the regulated community and

the government to clearly identify (e.g., habitat used by proposed

threatened or endangered species, cultural resources, and wetlands).

They stated that the NOAA list is not appropriate for this rule because

it represents guidance applicable to offshore sources, and to a limited

number of very large onshore sources, that could have catastrophic oil

spills. A few commenters suggested limiting the list to Federal Class I

areas designated under the CAA prevention of significant deterioration

program, or reducing the list of sensitive areas to national parks and

the designated critical habitat for listed endangered species, and

limiting environmental concern to those accidents that generate a

significant and long-term impact, such as an actual ``taking'' of an

endangered species.

For the final rule, EPA has not used the NOAA list. Instead EPA

requires owners or operators to indicate in the RMP the environmental

receptors located within circles whose radii are the distances to an

endpoint for the worst-case and alternative release scenarios. EPA

agrees with commenters that the locations of certain natural resources

are difficult to identify. Consequently, EPA has defined environmental

receptors as natural areas such as national or state parks, forests, or

monuments; officially designated wildlife sanctuaries, preserves,

refuges, or areas; and Federal wilderness areas, that can be exposed to

an accidental release. All such receptors typically can be found on

local U.S. Geological Survey (USGS) maps or maps based on USGS data.

Habitats of endangered or threatened species are not included because

the locations of these habitats are frequently not made public to

protect the species. Natural resource agencies will have access to the

RMP information and can raise concerns with local officials about

potential harm to these habitats, as necessary. Local emergency

planners and responders may want to consult with environmental

management agencies as part of emergency preparedness.

3. Level of Analysis Required. In the SNPRM, EPA proposed that

sources only identify sensitive environments within the area of the

worst-case release, rather than analyzing potential impacts. A few

commenters opposed this approach, stating that the CAA requires that

sources analyze impacts. Most commenters supported EPA's position

because extensive expertise at considerable cost is required to

adequately assess all environmental impacts associated with the

environments list EPA provided. Commenters stated that this cost would

make fewer resources available for prevention activities and providing

no benefit. Other commenters noted that much of the data needed for

such analyses is not available.

EPA agrees that extensive environmental analysis is not justified.

Irreversible adverse effect exposure level data for the wide variety of

environmental species potentially exposed in an accidental release

event are not available for most of the listed substances. EPA believes

that identification of potentially affected environmental receptors in

the RMP is sufficient for purposes of accident prevention,

preparedness, and response by the source and at the local level.

D. Program 3 Consistency with OSHA PSM Standard

1. Prevention Program. In EPA's original proposal, the prevention

program requirements were based on the elements of OSHA's PSM standard

(29 CFR 1910.119), and some commenters supported this approach. But EPA

added a paragraph to each OSHA prevention program element to explain

the purpose of the provision and, in some instances, added additional

recordkeeping, reporting, or substantive provisions to ensure that

statutory requirements were met. Several commenters argued that these

additions cause confusion and appear to require sources to create two

separate

[[Page 31687]]

prevention programs, which could cause conflicting inspection and

enforcement actions and greater cost for sources that must comply with

both the OSHA and EPA requirements. Many commenters suggested that EPA

simply reference the OSHA requirements.

EPA agrees that the Program 3 prevention program requirements

should be identical to OSHA's PSM standard to avoid confusion and

redundant requirements and to ensure that sources develop one

accidental release prevention program that protects workers, the

general public, and the environment. Therefore, EPA has moved the

Management System requirement (see section I.D) supported by most

commenters to a section separate from the Prevention Program and

deleted the introductory paragraphs and modifications to the PSM

language. The Agency recognizes that many workplace hazards also

threaten public receptors and that the majority of accident prevention

steps taken to protect workers also protect the general public and the

environment; thus, a source owner or operator responsible for a process

in compliance with the OSHA PSM standard should already be in

compliance with the Program 3 prevention program requirements.

EPA did not cross-reference sections of the PSM standard in today's

rule because, under Office of Federal Register requirements at 1 CFR

21.21(c)(2), EPA cannot adopt OSHA's requirements. EPA and OSHA have

separate legal authority to regulate chemical process safety to prevent

accidental releases. Furthermore, cross-referencing the OSHA standard

would be tantamount to a delegation of authority to set standards in

this area from the Administrator of EPA to the Secretary of Labor,

because OSHA would be able to modify the PSM requirements without an

EPA rulemaking under CAA Sec. 307(d). The Senate explicitly considered

and rejected the possibility of the Administrator delegating to OSHA

responsibility for hazard assessment. Senate Report at 226. As that

term was used in the Senate bill, hazard assessment included many of

the elements of PSM.

With the exception of some key terms and phrases, the Program 3

prevention program language in the final rule is identical to the OSHA

standard language (the rulemaking docket contains a side-by-side

analysis of the OSHA standard and EPA rule text with word differences

highlighted). Most of the differences are terms based on specific

legislative authorities given to OSHA or EPA that have essentially the

same meaning:

------------------------------------------------------------------------

OSHA term EPA term

------------------------------------------------------------------------

Highly hazardous substance............. Regulated substance.

Employer............................... Owner or operator.

Facility............................... Stationary source.

Standard............................... Rule or part.

------------------------------------------------------------------------

EPA also agrees with commenters that sound process safety

management systems ideally address chemical accident prevention in a

way that protects workers, the public, and the environment. Since

OSHA's responsibility is to protect workers, there are phrases in the

OSHA standard that are designed to focus employer attention on

accidents that affect the workplace. It could be argued that these

phrases inadvertently exclude consideration of offsite impacts. EPA has

deleted the phrases noted below to ensure that all sources implement

process safety management in a way that protects not only workers, but

also the public and the environment:

------------------------------------------------------------------------

OSHA PSM requirement EPA program 3 requirement

------------------------------------------------------------------------

1910.119(d)(2)(E) An evaluation of the 68.65(c)(1)(v) An evaluation of

consequences of deviations, including the consequences of

those affecting the safety and health deviations.

of employees.

1910.119(e)(3)(ii) The identification 68.67(c)(2) The identification

of any previous incident which had a of any previous incident which

likely potential for catastrophic had a likely potential for

consequences in the workplace. catastrophic consequences.

1910.119(e)(3)(vii) A qualitative 68.67(c)(7) A qualitative

evaluation of a range of the possible evaluation of a range of the

safety and health effects of failure possible safety and health

of controls on employees in the effects of failure of

workplace. controls.

1910.119(m)(1) The employer shall 68.81(a) The owner or operator

investigate each incident which shall investigate each

resulted in, or could reasonably have incident which resulted in, or

resulted in a catastrophic release of could reasonably have resulted

a highly hazardous chemical in the in a catastrophic release of a

workplace. regulated substance.

------------------------------------------------------------------------

EPA also made changes to specific schedule dates to coordinate with

the OSHA PSM requirements, made internal references consistent, and

added a provision to the PHA section specifically grandfathering all

OSHA PHAs and allowing sources to update and revalidate these PHAs on

their OSHA schedule. EPA believes these modifications do not cause

source owners or operators to make major adjustments to their PSM

systems established under OSHA. These minor modifications ultimately

lead to the development of one comprehensive process safety management

system satisfying both OSHA and EPA that works to prevent accidents

affecting workers, the public, and the environment.

EPA also modified the OSHA definition of catastrophic release,

which serves as a trigger for an accident investigation, to include

events ``that present imminent and substantial endangerment to public

health and the environment.'' This modification, in combination with

the changes noted above, ensure that sources covered by both OSHA and

EPA requirements must investigate not only accidents that threaten

workers, but also those that threaten the public or the environment.

EPA agrees with commenters and recognizes that most catastrophic

accidental releases affect workers first. However, the Agency also

believes that there are accidental release situations where workers are

protected but the public and the environment are threatened, e.g.

vessel overpressurizations that cause emergency relief devices to work

as designed and vent hazardous atmospheres away from the workplace and

into the air where they are carried downwind. Although many sources

through the PHA process will have recognized and addressed the

potential impact offsite associated with safety measures that protect

workers (e.g. an

[[Page 31688]]

emergency vent scrubber system), EPA believes that the requirements in

today's rule ensure that all sources routinely consider such

possibilities and integrate the protection of workers, the public, and

the environment into one program.

2. Enforcement. Many commenters expressed concern for conflicting

audit procedures, interpretations, and enforcement actions when EPA and

OSHA auditors inspect the same processes. EPA has no authority to

exempt a source covered under the PSM standard and today's rule from

any prospect of an EPA enforcement action for violations of section

112(r) and EPA regulations issued under it. EPA and OSHA are working

closely to ensure that enforcement actions are based on consistent

interpretations and coordinated to avoid overlapping audits. Such

coordination in enforcement was recognized as an appropriate method for

exercising the Administrator's duty to coordinate the EPA program with

OSHA (Senate Report at 244).

3. Exemptions. Many commenters suggested that the Agency exempt

small businesses or certain industry sectors because the rule is too

costly, some industries are already subject to substantial regulation

by other Federal or state agencies, OSHA exempts certain industries

from the PSM standard, and some sources have effective self-policing

regimes in place.

Regardless of whether the source is covered under some other

Federal, state, or local program, EPA has no authority to exempt a

source that has more than a threshold quantity of a regulated substance

from complying with the risk management program rule (CAA section

112(r)(7)(B)(ii)). EPA established the tiered approach to acknowledge

that different industries pose different potential risks to human

health and the environment and that elements of other regulatory

programs may serve to prevent accidents. EPA believes that owners or

operators can indicate in their Program and RMP how compliance with

other particular regulations and standards satisfies Program or RMP

elements, thereby, avoid duplication. Only those processes in certain

SIC codes or covered by OSHA's PSM standard must implement the full PSM

program under Program 3. A source owner or operator can demonstrate

compliance with the Program 2 or 3 prevention program under today's

rule for a covered process by showing that it complies with the PSM

standard. This approach is consistent with the authority to set

different standards for different types of sources under CAA section

112(r)(7)(B)(I).

E. Relationship to Air Permitting

Several commenters on the NPRM requested that EPA clarify the

relationship between the risk management program and the air permit

program under Title V of the CAA for sources subject to both

requirements. In the SNPRM, EPA indicated that in Title V, section

502(b)(5)(A), Congress clearly requires that permitting authorities

must have the authority to ``assure compliance by all sources required

to have a permit under this title with each applicable standard,

regulation or requirement under this Act.'' EPA further states in part

70.2 that ``Applicable Requirement means * * * (4) Any standard or

other requirement under section 112 of the Act, including any

requirement concerning accident prevention under section 112(r)(7) of

the Act; * * *'' Consequently, EPA must require that air permitting

authorities implementing Title V permit programs be able to assure

compliance with section 112(r). In the SNPRM, EPA attempted to identify

the section 112(r) ``applicable requirements,'' clarify the minimum

content of part 70 permits with respect to these requirements, and to

specify the role and responsibilities of the part 70 permitting

authority in assuring compliance with these requirements.

The sections below address the major issue areas raised by

commenters on the SNPRM. More detail can be found in the Risk

Management Program Rule: Summary and Response to Comments in the

Docket. The SNPRM also addressed the role and responsibilities of the

implementing agency with respect to section 112(r). This issue is

addressed separately in Section R below.

1. General relationship between the part 68 and air permitting

programs. Some commenters agreed with EPA's proposed role for the air

permitting authority with respect to section 112(r), but encouraged EPA

to avoid new, confusing, and duplicative state and source permitting

requirements. A few commenters suggested that all part 68 requirements

should become permit conditions, that it be fully enforced through the

part 70 permitting program, and that anything less violates the CAA.

Most commenters (state air permitting authorities and industry),

opposed EPA's proposal stating that Congress did not intend, and

legislative history does not support, section 112(r) to be implemented

or enforced through the Title V permit program.

EPA agrees that Congress did not intend for section 112(r) to be

implemented and enforced primarily through Title V and recognizes the

potential for confusion and burden on sources and air permitting

authorities associated with section 112(r). EPA believes that the

requirements in today's rule are flexible, impose minimal burden,

address the concerns raised by commenters and satisfy the CAA

requirement for assurance of compliance with section 112(r) as an

applicable requirement for permitting. The requirements apply only to

sources subject to both part 68 and parts 70 or 71; there are no

permitting requirements on sources subject solely to part 68. EPA

agrees that ideally, one authority should implement part 68 oversight;

however, air permitting authorities should not be responsible for

implementation just as implementing agencies should not be responsible

for permitting (see implementing agency discussion in Section R,

below). The air permitting authority has the flexibility under today's

rule to obtain assistance, expertise or resources from other agencies

in fulfilling its responsibilities with respect to section 112(r). This

will foster interaction and coordination of air pollution, pollution

prevention, public and worker safety and health and environmental

programs at the state and local levels leading to more effective

oversight.

2. Impact of EPA's proposal on air permitting programs. Several

commenters stated that EPA's proposal places an unreasonable burden on

air permitting programs because states would need to amend or develop

new legislative authority and implementing regulations which diverts

limited state resources away from the development and operation of more

important routine emissions permit programs.

EPA disagrees that today's rule places an unreasonable burden on

air permitting programs. Part of the approval process for a state air

permitting program is confirmation that states have the authority to

ensure that sources are in compliance with air toxics requirements

under section 112 including section 112(r). The provisions of section

68.215 are sufficient to meet the obligations under part 70. Thus, for

state and local agencies that have approved part 70 programs, states

would need to develop new legislative authorities only if they seek

delegation to implement part 68 beyond the narrow responsibilities

provided in Sec. 68.215 (see Section R, below). State obligations under

Sec. 68.215, which should be covered by permit fees (see section E.11,

below), should not impose a substantial burden on state resources

because the rule streamlines the RMP requirements and establishes

centralized recordkeeping for RMPs.

[[Page 31689]]

3. Part 68 as an ``applicable requirement'' under part 70. As

described above, the CAA requires that air permitting authorities

ensure that sources are in compliance with applicable requirements as a

condition of permitting. In the preamble of previous rulemakings for

part 70 (57 FR 32301), EPA indicated that the definition of

``applicable requirement'' under Title V includes ``any requirement

under section 112(r) to prepare and register a risk management plan

(RMP).'' This explanatory statement preceded development of part 68,

which implements section 112(r)(7). In the SNPRM, EPA proposed more

specific provisions to assure compliance with applicable requirements

for section 112(r) than the part 70 preamble so that air permitting

authority responsibility is clear. EPA believed that all elements of

part 68 are applicable requirements; however, compliance with

applicable requirements could be assured by including generic terms in

permits and certain minimal oversight activities. Together, these steps

ensure that permitted sources fulfill their accident prevention and

information sharing responsibilities.

EPA proposed standard permit conditions that would allow air

permitting authorities to verify compliance with part 68. Commenters

stated that alteration of the part 70 rule definition of the term

`applicable requirement' under the part 68 rulemaking is inappropriate

and that the role of the air permitting authority with respect to

section 112(r) should be defined in part 70 rulemakings rather than in

part 68.

EPA's action today does not alter the definition of ``applicable

requirements'' under 40 CFR 70.2, which already includes ``any

requirement concerning accident prevention under section 112(r)(7).''

Rather, EPA is establishing very simple permit terms and flexible,

minimal oversight responsibilities that will assure compliance with

part 68. EPA disagrees that part 68 cannot establish more specific

terms for permits than those given in part 70 or 71 with respect to

section 112(r). As mentioned in the SNPRM preamble, part 70 does not

preclude EPA from clarifying or even expanding air permitting

responsibilities. Specific permit requirements are useful to clearly

establish the minimum permit conditions and state responsibilities

essential to ensuring compliance with part 68 and to reduce

uncertainties that may lead to overly broad interpretations of the

requirements. However, air permitting authorities still have the

flexibility to establish additional terms for the permit if it so

chooses.

4. Role of the air permitting authority. In the SNPRM, EPA proposed

certain air permitting authority responsibilities necessary to ensure

that sources are in compliance with part 68 for purposes of permitting.

Commenters stated that the role of the Title V permitting authority

should be defined in part 70, not in part 68 and opposed EPA's proposal

arguing that it causes unnecessary confusion for sources. Commenters

also argued that air permitting authorities do not have the relevant

expertise needed and that states should have the flexibility to

implement risk management programs in whichever agency they see fit.

Other commenters argued that air permitting authorities, without

section 112(l) delegation, could not accept the responsibilities

assigned by the SNPRM and that EPA was unlawfully attempting to

delegate the responsibility for implementing section 112(r) to the

state permitting authorities. Several commenters believed the

permitting authority should have no responsibilities beyond those set

forth in EPA's April 13, 1993, policy memorandum from John Seitz,

Director of the Office of Air and Quality Planning and Standards

(OAQPS), to EPA Regional Air Division Directors, available in the

docket because states invested significant resources and effort into

the development of their programs, guided by this EPA memorandum.

However, a state permitting authority stated that the EPA memorandum

did not account for many of the key program elements, including the

necessary incorporation of standard permit conditions. Many commenters

also opposed requiring extensive details or all aspects of part 68

compliance in the permit, finding this approach excessive and overly

burdensome on both state air permitting authorities and sources and

contrary to the law and Congressional intent in that it would have

required section 112(r)(7) to be fully implemented by state permit

programs.

Several commenters were concerned that a single violation of part

68 could potentially be enforced by both the permitting authority and

the implementing agency. One commenter suggested that the only case

where a violation of a part 68 requirement should also be considered a

violation of part 70 would be the failure to register an RMP on time

under the requirements of Sec. 68.12. Another commenter requested that,

at Sec. 68.58(b)(3), EPA should allow the state the discretion to

determine whether a penalty should be assessed. Several commenters,

uncertain how the Programs proposed by EPA in the SNPRM would affect

the role of the permitting authority, suggested that EPA develop a

process to inform states of the tiering approach and to exclude Program

1 and 2 sources from additional permitting requirements.

EPA believes that part 68 should more clearly define the role of

the air permitting authority with respect to section 112(r). Part 70

requirements were established well before part 68 and are therefore

vague. Consequently, EPA is using part 68 to clarify the applicable

requirements, to specify permit terms and to establish the minimum

permit conditions and activities to avoid misinterpretations and to

ensure compliance with part 68. EPA agrees that air permitting

authorities may not have the expertise necessary with respect to part

68; consequently, the requirements in today's rule only specify the

actions the state must take to assure that sources have met their part

68 responsibilities while giving the state flexibility to assign or

designate by agreement entities other than the permitting auth

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.

Accidental Release Prevention Requirements: Risk Management Programs Under Clean Air Act Section 112(r)(7) · 61 FR 31668 | Frix