Environmental Review for Renewal of Nuclear Power Plant Operating Licenses

Federal RegisterJun 5, 1996

Ask Donna

What actually matters in this document.

Text

SUMMARY: The Nuclear Regulatory Commission (NRC) is amending its

regulations regarding environmental protection regulations for domestic

licensing and related regulatory functions to establish new

requirements for the environmental review of applications to renew the

operating licenses of nuclear power plants. The amendment defines those

environmental impacts for which a generic analysis has been performed

that will be adopted in plant-specific reviews for license renewal and

those environmental impacts for which plant-specific analyses are to be

performed.

The amendment improves regulatory efficiency in environmental

reviews for license renewal by drawing on the considerable experience

of operating nuclear power reactors to generically assess many of the

environmental impacts that are likely to be associated with license

renewal. The amendment also eliminates consideration of the need for

generating capacity and of utility economics from the environmental

reviews because these matters are under the regulatory jurisdiction of

the States and are not necessary for the NRC's understanding of the

environmental consequences of a license renewal decision.

The increased regulatory efficiency will result in lower costs to

both the applicant in preparing a renewal application and to the NRC

for reviewing plant-specific applications and better focus of review

resources on significant case specific concerns. The results should be

a more focused and therefore a more effective NEPA review for each

license renewal. The amendment will also provide the NRC with the

flexibility to address unreviewed impacts at the site-specific stage of

review and allow full consideration of the environmental impacts of

license renewal.

The NRC is soliciting public comment on this rule for a period of

30 days. In developing any comment specific attention should be given

to the treatment of low-level waste storage and disposal impacts, the

cumulative radiological effects from the uranium fuel cycle, and the

effects from the disposal of high-level waste and spent fuel.

DATES: Absent a determination by the NRC that the rule should be

modified, based on comments received, the final rule shall be effective

on August 5, 1996. The comment period expires on July 5, 1996.

ADDRESSES: Send comments to: The Secretary of the Commission, U.S.

Nuclear Regulatory Commission, Washington, DC 20555-0001, Attention:

Docketing and Services Branch, or hand deliver comments to the Office

of the Secretary, One White Flint North, 11555 Rockville Pike,

Rockville, Maryland between 7:30 a.m. and 4:15 p.m. on Federal

workdays. Copies of comments received and all documents cited in the

supplementary information may be examined at the NRC Public Document

Room, 2120 L Street NW. (Lower Level), Washington, DC between the hours

of 7:45 a.m. and 4:15 p.m. on Federal workdays.

FOR FURTHER INFORMATION CONTACT: Donald P. Cleary, Office of Nuclear

Regulatory Research, U.S. Nuclear Regulatory Commission, Washington, DC

20555-0001, telephone: (301) 415-6263; e-mail [email protected].

SUPPLEMENTARY INFORMATION:

I. Introduction

II. Rulemaking History

III. Analysis of Public Comments

A. Commenters

B. Procedural Concerns

1. Public Participation and the Periodic Assessment of the Rule

and GEIS

2. Economic Costs and Cost-Benefit Balancing

3. Need for Generating Capacity and Alternative Energy Sources

C. Technical Concerns

1. Category and Impact Magnitude Definitions

2. Surface Water Quality

3. Aquatic Ecology

4. Groundwater Use and Quality

5. Terrestrial Ecology

6. Human Health

7. Socioeconomics

8. The Uranium Fuel Cycle and Solid Waste Management

9. Accidents

10. Decommissioning

11. Need for Generating Capacity

12. Alternatives to License Renewal

13. License Renewal Scenario

14. Environmental Justice

IV. Discussion of Regulatory Requirements

A. General Requirements

B. The Environmental Report

1. Environmental Impacts of License Renewal

2. Consideration of Alternatives

C. Supplemental Environmental Impact Statement

1. Public Scoping and Public Comments on the SEIS

2. Commission's Analysis and Preliminary Recommendation

3. Final Supplemental Environmental Impact Statement

D. NEPA Review for Activities Outside NRC License Renewal

Approved Scope

V. Availability of Documents

VI. Submittal of Comments in an Electronic Format

VII. Finding of No Significant Environmental Impact Availability

VIII. Paperwork Reduction Act Statement

IX. Regulatory Analysis

X. Regulatory Flexibility Act Certification

XI. Small Business Regulatory Enforcement Fairness Act

XII. Backfit Analysis

I. Introduction

The Commission has amended its environmental protection regulations

in 10 CFR part 51 to improve the efficiency of the process of

environmental review for applicants seeking to renew an operating

license for up to an additional 20 years. The amendments are based on

the analyses conducted for and reported in NUREG-1437, ``Generic

Environmental Impact Statement for License Renewal of Nuclear Plants''

(May 1996). The Commission's initial decision to undertake a generic

assessment of the environmental impacts associated with the renewal of

a nuclear power plant operating license was motivated by its beliefs

that:

(1) License renewal will involve nuclear power plants for which the

[[Page 28468]]

environmental impacts of operation are well understood as a result of

data evaluated from operating experience to date;

(2) Activities associated with license renewal are expected to be

within this range of operating experience, thus environmental impacts

can be reasonably predicted; and

(3) Changes in the environment around nuclear power plants are

gradual and predictable with respect to characteristics important to

environmental impact analyses.

Although this amendment is consistent with the generic approach and

scope of the proposed amendment published on September 17, 1991 (56 FR

47016), several significant modifications have been made in response to

the public comments received. The proposed amendment would have

codified the findings reached in the draft generic environmental impact

statement (GEIS) as well as certain procedural requirements. The draft

GEIS established the bounds and significance of potential environmental

impacts at 118 light-water nuclear power reactors that, as of 1991,

were licensed to operate or were expected to be licensed in the future.

All potential environmental impacts and other matters treated by

the NRC in an environmental review of nuclear power plants were

identified and combined into 104 discrete issues. For each issue, the

NRC staff established generic findings encompassing as many nuclear

power plants as possible. These findings would have been codified by

the proposed amendment. Of the 104 issues reviewed for the proposed

rule, the staff determined that 80 issues could be adequately addressed

generically and would not have been reviewed in plant-specific license

renewal reviews. For 22 of the issues, it was found that the issue was

adequately addressed for some but not all plants. Therefore, a plant-

specific review would be required to determine whether the plant is

covered by the generic review or whether the issue must be assessed for

that plant. The proposed amendment provided guidance on the application

of these findings at the site-specific license renewal stage. For the

two remaining issues, it was found that the issue was not generically

addressed for any plant, and thus a plant-specific review would have

been required for all plants.

Other major features of the proposed amendment included a

conditional finding of a favorable cost-benefit balance for license

renewal and a provision for the use of an environmental assessment that

would address only those issues requiring plant-specific review. A

finding of no significant impact would have resulted in a favorable

cost-benefit balance for that plant. If a finding of no significant

impact could not be made for the plant, there would have to have been a

determination as to whether the impacts found in the environmental

assessment were sufficient to overturn the conditional cost-benefit

balance found in the rule.

Although the final amendments to 10 CFR part 51 maintain the same

generic approach used in the proposed rule, there are several

modifications.The final amendments to 10 CFR part 51 now contain 92

issues. The reduction of the number of issues from 104 in the proposed

rule to 92 in the final rule is due to (1) the elimination from the

review of the consideration of the need for electric power and

associated generating capacity and of the direct economic benefits and

costs associated with electric power, (2) removing alternatives as an

issue from Table B-1 and addressing review requirements only in the

text of the rule, (3) combining the five severe accident issues used in

the proposed rule into one issue, (4) eliminating several regional

economic issues under socioeconomics that are not directly related to

environmental impacts, (5) making minor changes to the grouping of

issues under aquatic ecology and groundwater, (6) identifying

collective offsite radiological impacts associated with the fuel cycle

and all impacts of high level waste and spent fuel disposal as separate

issues, and (7) adding environmental justice as an issue for

consideration.

Of the 92 issues in the final rule, 68 issues were found to be

adequately addressed in the GEIS, and therefore, additional assessment

will not be required in a plant-specific review. Twenty-four issues

were found to require additional assessment for at least some plants at

the time of the license renewal review. In the final rule, the 2 issues

in the proposed rule that would have required review for all plants are

now included in the set of 24 issues of the final rule.

Public comments on the adequacy of the analysis for each issue were

considered by the NRC staff. Any changes to the analyses and findings

that were determined to be warranted were made in the final GEIS and

incorporated in the rule. Several changes were made to the procedural

features of the proposed rule in response to comments by the Council on

Environmental Quality, the Environmental Protection Agency, and a

number of State agencies. First, the NRC will prepare a supplemental

site-specific environmental impact statement (SEIS), rather than an

environmental assessment (as initially proposed), for each license

renewal application. The SEIS will be issued for public comment as part

of the individual plant review process. The NRC will delay any

conclusions regarding the acceptability of the overall impacts of the

license renewal until completion of the site-specific review. In

addition, the SEIS will be prepared in accordance with existing public

scoping requirements. The NRC will also review and consider any new and

significant information presented during the review of individual

license renewal applications. In addition, any person may challenge the

validity of the conclusions codified in the rule by filing a petition

for rulemaking pursuant to 10 CFR 2.802. Finally, the NRC will review

the rule and the GEIS on a schedule that allows revisions, if required,

every 10 years. This review will be initiated approximately 7 years

after the completion of the previous revision cycle.

In addition to the changes involving public participation, this

final rule also contains several changes regarding the scope of

analysis and conclusions in the rule and GEIS. The conditional cost-

benefit balance has been removed from the GEIS and the rule. In place

of the cost-benefit balancing, the NRC will use a new standard that

will require a determination of whether or not the adverse

environmental impacts of license renewal are so great, compared with

the set of alternatives, that preserving the option of license renewal

for future decisionmakers would be unreasonable. The final amendment

also eliminates NRC's consideration of the need for generating capacity

and the preparation of power demand forecasts for license renewal

applications. The NRC acknowledges the primacy of State regulators and

utility officials in defining energy requirements and determining the

energy mix within their jurisdictions. Therefore, the issue of need for

power and generating capacity will no longer be considered in NRC's

license renewal decisions. The final GEIS has been revised to include

an explicit statement of purpose and need for license renewal

consistent with this acknowledgment. Lastly, the final rule has

eliminated the consideration of utility economics from license renewal

reviews under the National Environmental Policy Act (NEPA) except when

such benefits and costs are either essential for a determination

regarding the inclusion of an alternative

[[Page 28469]]

in the range of alternatives considered or relevant to mitigation.

These and other features of the final rule are explained in detail

below.

The NRC is soliciting public comment on this rule for a period of

30 days. In developing any comment specific attention should be given

to the treatment of low-level waste storage and disposal impacts, the

cumulative radiological effects from the uranium fuel cycle, and the

effects from the disposal of high-level waste and spent fuel. Absent a

determination by the NRC that the rule should be modified, based on

comments received, the final rule shall be effective on August 5, 1996.

II. Rulemaking History

In 1986, the NRC initiated a program to develop license renewal

regulations and associated regulatory guidance in anticipation of

applications for the renewal of nuclear power plant operating licenses.

A solicitation for comments on the development of a policy statement

was published in the Federal Register on November 6, 1986 (51 FR

40334). However, the Commission decided to forgo the development of a

policy statement and to proceed directly to rulemaking. An advance

notice of proposed rulemaking was published on August 29, 1988 (53 FR

32919). Subsequently, the NRC determined that, in addition to the

development of license renewal regulations focused on the protection of

health and safety, an amendment to its environmental protection

regulations in 10 CFR part 51 was warranted.

On October 13, 1989 (54 FR 41980), the NRC published a notice of

its intent to hold a public workshop on license renewal on November 13

and 14, 1989. One of the workshop sessions was devoted to the

environmental issues associated with license renewal and the possible

merit of amending 10 CFR part 51. The workshop is summarized in NUREG/

CP-0108, ``Proceedings of the Public Workshop on Nuclear Power Plant

License Renewal'' (April 1990). Responses to the public comments

submitted after the workshop are summarized in NUREG-1411, ``Response

to Public Comments Resulting from the Public Workshop on Nuclear Power

Plant License Renewal'' (July 1990).

On July 23, 1990, the NRC published an advance notice of proposed

rulemaking (55 FR 29964) and a notice of intent to prepare a generic

environmental impact statement (55 FR 29967). The proposed rule was

published on September 17, 1991 (56 FR 47016). The same Federal

Register notice described the supporting documents that were available

and announced a public workshop to be held on November 4-5, 1991. The

supporting documents for the proposed rule included:

(1) NUREG-1437, ``Draft Generic Environmental Impact Statement for

License Renewal of Nuclear Plants'' (August 1991);

(2) NUREG-1440, ``Regulatory Analysis of Proposed Amendments to

Regulations Concerning the Environmental Review for Renewal of Nuclear

Power Plant Operating Licenses: Draft Report for Comment'' (August

1991);

(3) Draft Regulatory Guide DG-4002, Proposed Supplement 1 to

Regulatory Guide 4.2, ``Guidance for the Preparation of Supplemental

Environmental Reports in Support of an Application To Renew a Nuclear

Power Station Operating License'' (August 1991); and

(4) NUREG-1429, ``Environmental Standard Review Plan for the Review

of License Renewal Applications for Nuclear Power Plants: Draft Report

for Comment'' (August 1991).

After the comment period, the NRC exchanged letters with the

Council on Environmental Quality (CEQ) and the Environmental Protection

Agency (EPA) to address their concerns about procedural aspects of the

proposed rule. The Commission also decided that the staff should

discuss with the States the concerns raised in comments by a number of

States that certain features of the proposed rule conflicted with State

regulatory authority over the need for power and utility economics. To

facilitate these discussions, the NRC staff developed an options paper

entitled ``Addressing the Concerns of States and Others Regarding the

Role of Need for Generating Capacity, Alternative Energy Sources,

Utility Costs, and Cost-Benefit Analysis in NRC Environmental Reviews

for Relicensing Nuclear Power Plants: An NRC Staff Discussion Paper.''

A Federal Register notice published on January 18, 1994 (59 FR 2542)

announced the scheduling of three regional workshops during February

1994 and the availability of the options paper. A fourth public meeting

on the State concerns was held in May 1994 in order for the NRC staff

to better understand written proposals that had been submitted by two

industry organizations after the regional workshops. After considering

the comments from the workshops and the written comments, the NRC staff

issued a proposed supplement to the proposed rule published on July 25,

1994 (59 FR 37724), that it believed would resolve the States' concerns

regarding the Commission's consideration of need for power and utility

economics. Comments were requested on this proposal. The discussion

below contains an analysis of these comments and other comments

submitted in response to the proposed rule.

III. Analysis of Public Comments

The analysis of public comments and the NRC's responses to these

comments are documented in NUREG-1529, ``Public Comments on the

Proposed 10 CFR part 51 Rule for Renewal of Nuclear Power Plant

Operating Licenses and Supporting Documents: Review of Concerns and NRC

Staff Response'' (May 1996). The extent of comments received during the

various stages of the rulemaking process and the principal concerns

raised by the commenters, along with the corresponding NRC responses to

these concerns, are discussed below.

A. Commenters

In response to the Federal Register notice on the proposed rule

published on September 17, 1991 (56 FR 47016), 68 organizations and 49

private citizens submitted written comments. The 68 organizations

included 5 Federal agencies; 26 State, regional, and local agencies; 19

nuclear industry organizations and engineering firms; 3 law firms; and

15 public interest groups. Before the close of the initial comment

period, the NRC conducted a 2-day workshop on November 4-5, 1991, in

Arlington, Virginia, to discuss the proposed rule. Representatives from

Federal agencies, State agencies, utilities, engineering firms, law

firms, and public interest groups attended the workshop. Workshop

panelists included the NRC staff as well as representatives from the

Department of Energy (DOE), Department of Interior (DOI), Environmental

Protection Agency (EPA), Council on Environmental Quality (CEQ),

several State agencies, the nuclear industry, and public interest

groups.

In February 1994, the NRC conducted three public meetings to

solicit views on the NRC staff's options for addressing the need for

generating capacity, alternative energy sources, economic costs, and

cost-benefit analysis in the proposed rule. The intent to hold public

meetings and the availability of the options paper was noticed in the

Federal Register on January 12, 1994 (59 FR 2542). Written comments

were also solicited on the options paper. The public meetings were held

in Rockville, Maryland; Rosemont, Illinois; and Chicopee,

Massachusetts.

[[Page 28470]]

Representatives from several States, the National Association of

Regulatory Utility Commissioners (NARUC), the nuclear industry, and

public interest groups actively participated. Nineteen separate written

comments were also submitted, primarily by the States and the nuclear

industry. In their submittals, the Nuclear Energy Institute (NEI),

formerly known as the Nuclear Management and Resources Council

(NUMARC), and Yankee Atomic Electric Company (YAEC) each proposed an

approach to handling the issues of need for generating capacity and

alternative energy sources in the rule. For the NRC staff to better

understand these proposals, an additional public meeting was held with

NEI and YAEC on May 16, 1994, in Rockville, Maryland.

After considering the public comments on the NRC staff's options

paper, the NRC issued a proposed supplement to the proposed rule; it

was published in the Federal Register on July 25, 1994 (59 FR 37724).

The proposed supplement set forth the NRC staff's approach to the

treatment of need for generating capacity and alternative energy

sources, as well as the staff's revision to the purpose of and need for

the proposed action (i.e., license renewal), which was intended to

satisfy the States' concerns and to meet NEPA requirements. Twenty

separate written comments were received in response to this

solicitation from Federal and State agencies, the nuclear industry, a

public interest group, and two private citizens.

B. Procedural Concerns

The commenters on the proposed rule raised significant concerns

regarding the following procedural aspects of the rule:

(1) State and public participation in the license renewal process

and the periodic assessment of the GEIS findings;

(2) The use of economic costs and cost-benefit balancing; and

(3) Consideration of the need for generating capacity and

alternative energy sources in the environmental review of license

renewal applications.

Each of these concerns and the NRC response is discussed below.

1. Public Participation and the Periodic Assessment of the Rule and the

GEIS

Concern. Many commenters criticized the draft GEIS finding that 80

of 104 environmental issues could be generically applied to all plants

and, therefore, would not be subject to plant-specific review at the

time of license renewal. As a consequence, these commenters believe

they are being denied the opportunity to participate in the license

renewal process. Moreover, they pointed out that the site-specific

nature of many important environmental issues does not justify a

generic finding, particularly when the finding would have been made 20

years in advance of the decision to renew an operating license. The

commenters believe that only a site-specific EIS to support a license

renewal decision would satisfy NEPA requirements.

Federal and State agencies questioned how new scientific

information could be folded into the GEIS findings because the GEIS

would have been performed so far in advance of the actual renewal of an

operating license. There were differing views on exactly how the NRC

should address this question. A group of commenters, including CEQ and

EPA, noted that the rigidity of the proposed rule hampers the NRC's

ability to respond to new information or to different environmental

issues not listed in the proposed rule. They believe that incorporation

of new information can only be achieved through the process of amending

the rules. One commenter recommended that, if the NRC decides to pursue

the approach of making generic findings based on the GEIS, the

frequency of review and update should be specifically stated in the

rule. Recommendations on the frequency of the review ranged from 2

years to 5 years.

Response. In SECY-93-032, February 9, 1993, the NRC staff reported

to the Commission their discussions with CEQ and EPA regarding the

concerns these agencies raised, which were also raised by other

commenters, about limiting public comment and the consideration of

significant new information in individual license renewal environmental

reviews. The focus of the commenters concerns is the limited nature of

the site-specific reviews contemplated under the proposed rule. In

response, the NRC has reviewed the generic conclusions in the draft

rule, expanded the opportunity for site-specific review, and confirmed

that what remains as generic is so. Also, the framework for

consideration of significant new information has been revised and

expanded.

The major changes adopted as a result of these discussions are as

follows:

1. The NRC will prepare a supplemental site-specific EIS, rather

than an environmental assessment (as initially proposed), for each

license renewal application. This SEIS will be a supplement to the

GEIS. Additionally, the NRC will review comments on the draft SEIS and

determine whether such comments introduce new and significant

information not considered in the GEIS analysis. All comments on the

applicability of the analyses of impacts codified in the rule and the

analysis contained in the draft supplemental EIS will be addressed by

NRC in the final supplemental EIS in accordance with 40 CFR 1503.4,

regardless of whether the comment is directed to impacts in Category 1

or 2. Such comments will be addressed in the following manner:

a. NRC's response to a comment regarding the applicability of the

analysis of an impact codified in the rule to the plant in question may

be a statement and explanation of its view that the analysis is

adequate including, if applicable, consideration of the significance of

new information. A commenter dissatisfied with such a response may file

a petition for rulemaking under 10 CFR 2.802. If the commenter is

successful in persuading the Commission that the new information does

indicate that the analysis of an impact codified in the rule is

incorrect in significant respects (either in general or with respect to

the particular plant), a rulemaking proceeding will be initiated.

b. If a commenter provides new information which is relevant to the

plant and is also relevant to other plants (i.e., generic information)

and that information demonstrates that the analysis of an impact

codified in the final rule is incorrect, the NRC staff will seek

Commission approval to either suspend the application of the rule on a

generic basis with respect to the analysis or delay granting the

renewal application (and possibly other renewal applications) until the

analysis in the GEIS is updated and the rule amended. If the rule is

suspended for the analysis, each supplemental EIS would reflect the

corrected analysis until such time as the rule is amended.

c. If a commenter provides new, site-specific information which

demonstrates that the analysis of an impact codified in the rule is

incorrect with respect to the particular plant, the NRC staff will seek

Commission approval to waive the application of the rule with respect

to that analysis in that specific renewal proceeding. The supplemental

EIS would reflect the corrected analysis as appropriate.

2. The final rule and the GEIS will not include conditional cost-

benefit conclusions or conclusions about alternatives. Conclusions

relative to the overall environmental impacts including cumulative

impacts will be left entirely to each site-specific SEIS.

3. After consideration of the changes from the proposed rule to the

final rule and further review of the environmental issues, the NRC has

concluded that it is

[[Page 28471]]

adequate to formally review the rule and the GEIS on a schedule that

allows revisions, if required, every 10 years. The NRC believes that 10

years is a suitable period considering the extent of the review and the

limited environmental impacts observed thus far, and given that the

changes in the environment around nuclear power plants are gradual and

predictable with respect to characteristics important to environmental

impact analyses. This review will be initiated approximately 7 years

after completion of the last cycle. The NRC will conduct this review to

determine what, if anything, in the rule requires revision.

Concern. As part of their comments on the July 1994 Federal

Register notice, NEI, several utilities, and the DOE asked that the NRC

reconsider its understanding with CEQ and EPA regarding the preparation

of a site-specific supplemental EIS for each license renewal action.

These commenters supported an approach that would allow the preparation

of an environmental assessment for reviewing the environmental impacts

of license renewal.

Response. The NRC does not agree with this position. The NRC

believes that it is reasonable to expect that an assessment of the full

set of environmental impacts associated with an additional 20 years of

operation of any plant would not result in a ``finding of no

significant impact.'' Therefore, the review for any plant would involve

an environmental impact statement.

2. Economic Costs and Cost-Benefit Balancing

Concern. State, Federal, and utility representatives expressed

concern about the use of economic costs and cost-benefit balancing in

the proposed rule and the draft GEIS. Commenters criticized the NRC's

heavy emphasis on economic analysis and the use of economic decision

criteria. They argued that the regulatory authority over utility

economics falls within the States' jurisdiction and to some extent

within the jurisdiction of the Federal Energy Regulatory Commission.

Commenters also believe that the cost-benefit balancing used in the

proposed rule and the draft GEIS went beyond NEPA requirements and CEQ

regulations (40 CFR Parts 1500 to 1508). They noted that CEQ

regulations interpret NEPA to require only an assessment of the

cumulative effects of a proposed Federal action on the natural and man-

made environment.

Response. In response to these concerns, the NRC has eliminated the

use of cost-benefit analysis and consideration of utility economics in

its NEPA review of a license renewal application except when such

benefits and costs are either essential for a determination regarding

the inclusion of an alternative in the range of alternatives considered

or relevant to mitigation. As discussed in more detail in the following

section, the NRC recognizes that the determination of the economic

viability of continuing the operation of a nuclear power plant is an

issue that should be left to appropriate State regulatory and utility

officials.

3. Need for Generating Capacity and Alternative Energy Sources

Concern. In their comments on the proposed rule and the draft GEIS,

several States expressed concern that the NRC's analysis of need for

generating capacity would preempt or prejudice State energy planning

decisions. They argued that the determination of need for generating

capacity has always been the States' responsibility. Recommendations on

how to address this issue ranged from withdrawing the proposed rule to

changing the categorization of the issue so that a site-specific review

can be performed, thus allowing for meaningful State and public

participation. Almost all the concerned States called on the NRC to

modify the rule to state explicitly that NRC's analysis does not

preempt a State's jurisdiction over the determination of need for

generating capacity.

Regarding the issue of alternative energy sources, several

commenters contended that the site-specific nature of the alternatives

to license renewal did not justify the generic finding in the GEIS. One

significant concern about this finding is the States' perception that a

generic finding, in effect, preempts the States' responsibility to

decide on the appropriate mix of energy alternatives in their

respective jurisdictions.

Three regional public meetings were held during the February 1994

to discuss the concerns of the States. At these meetings, and later in

written comments, the State of New York proposed an approach to resolve

the problem. The approach was endorsed by several other States. This

approach had three major conditions:

(1) A statement in the rule that the NRC's findings on need and

alternatives are only intended to satisfy the NEPA requirements and do

not preclude the States from making their own determination with

respect to these issues;

(2) The designation of the need for generating capacity and

alternative energy sources as Category 3 (i.e., requiring site-specific

evaluation); and

(3) A requirement that all site-specific EISs and relicensing

decisions reference State determinations of need for generating

capacity and alternative energy sources, and that they defer to those

State determinations to the maximum extent possible.

Response. After consideration, the NRC staff did not accept all

elements of the States' approach because the approach would have

continued to require the NRC to consider the need for generating

capacity and utility economics as part of its environmental analysis.

In addition, the approach would have required the NRC to develop

guidelines for determining the acceptability of State economic

analyses, which some States may have viewed as an intrusion on their

planning process.

The NRC staff developed and recommended another approach, which was

published on July 25, 1994 (59 FR 37724), after consideration of

information gathered at the regional meetings and from the written

comments. This approach, which borrows some elements from NEI and YAEC

proposals, has five major features:

(1) Neither the rule nor the GEIS would contain a consideration of

the need for generating capacity or other issues involving the economic

costs and benefits of license renewal and of the associated

alternatives;

(2) The purpose and need for the proposed action (i.e., license

renewal) would be defined as preserving the continued operation of a

nuclear power plant as a safe option that State regulators and utility

officials may consider in their future planning actions;

(3) The only alternative to the proposed action would be the ``no-

action'' alternative, and the environmental consequences of this

alternative are the impacts of a range of energy sources that might be

used if a nuclear power plant operating license were not renewed;

(4) The environmental review for license renewal would include a

comparison of the environmental impacts of license renewal with impacts

of the range of energy sources that may be chosen in the case of ``no

action''; and

(5) The NRC's NEPA decision standard for license renewal would

require the NRC to determine whether the environmental impacts of

license renewal are so great that preserving the option of license

renewal for future decisionmakers would be unreasonable.

[[Page 28472]]

The statement that the use of economic costs will be eliminated in

this approach refers to the ultimate NEPA decision regarding the

comparison of alternatives and the proposed action. This approach does

not preclude a consideration of economic costs if these costs are

essential to a determination regarding the inclusion of an alternative

in the range of alternatives considered (i.e., an alternative's

exorbitant cost could render it nonviable and unworthy of further

consideration) or relevant to mitigation of environmental impacts.

Also, the two local tax issues and the two economic structure issues

under socioeconomics in the table would be removed from consideration

when applying the decision standard.

Concern. Comments received from several States on the NRC staff's

July 1994 recommended approach ranged from rejection to endorsement.

Some States supported the three conditions proposed by the State of New

York. Several States were still concerned about whether a meaningful

analysis of need for generating capacity and alternative energy sources

could be undertaken 20 years ahead of time. One State asked that the

proposed rule be withdrawn. Another State wanted the proposed rule to

be reissued for public comment. CEQ supported the approach proposed by

the State of New York. CEQ believed that the NRC's recommended approach

was in conflict with the NEPA process because the proposed statement of

purpose and need for the proposed action was too narrow and did not

provide for an appropriate range of alternatives to the underlying need

for the proposed action. CEQ wanted the NRC to address other energy

sources as separate alternatives, rather than as consequences of the

no-action alternative. Moreover, CEQ stated that the proposed decision

standard places a ``weighty and improper burden of proof'' on

consideration of the alternative. The EPA endorsed CEQ's comments. In

general, the nuclear industry was supportive of the recommended

approach. However, NEI and the utilities strongly expressed the opinion

that, with the redefined statement of purpose and need, alternative

energy sources would no longer be alternatives to the proposed action

and, therefore, need not be considered.

Response. After consideration of the comments received on the

Commission's July 1994 proposal, the Commission has modified and

clarified its approach in order to address the concerns of CEQ relative

to consideration of appropriate alternatives and the narrow definition

of purpose and need. These modifications and clarifications addressed

the States' concerns relative to treatment of need for generating

capacity and alternatives. Specifically, the Commission has clarified

the purpose and need for license renewal in the GEIS as follows:

The purpose and need for the proposed action (renewal of an

operating license) is to provide an option that allows for power

generation capability beyond the term of a current nuclear power

plant operating license to meet future system generating needs, as

such needs may be determined by State, utility, and, where

authorized, Federal (other than NRC) decisionmakers.

Using this definition of the purpose of and need for the proposed

action, which stresses options for the generation of power, the

environmental review will include a characterization of alternative

energy sources as being the alternatives to license renewal and not

merely the consequences of the no-action alternative and, thus, it

addresses CEQ's concern that the scope of the alternatives analysis is

unacceptably restricted.

With respect to the States' concerns regarding need for generating

capacity analysis, the NRC will neither perform analyses of the need

for power nor draw any conclusions about the need for generating

capacity in a license renewal review. This definition of purpose and

need reflects the Commission's recognition that, absent findings in the

safety review required by the Atomic Energy Act of 1954, as amended, or

in the NEPA environmental analysis that would lead the NRC to reject a

license renewal application, the NRC has no role in the energy planning

decisions of State regulators and utility officials. From the

perspective of the licensee and the State regulatory authority, the

purpose of renewing an operating license is to maintain the

availability of the nuclear plant to meet system energy requirements

beyond the term of the plant's current license. The underlying need

that will be met by the continued availability of the nuclear plant is

defined by various operational and investment objectives of the

licensee. Each of these objectives may be dictated by State regulatory

requirements or strongly influenced by State energy policy and

programs. In cases of interstate generation or other special

circumstances, Federal agencies such as the Federal Energy Regulatory

Commission (FERC) or the Tennessee Valley Authority (TVA) may be

involved in making these decisions. The objectives of the various

entities involved may include lower energy cost, increased efficiency

of energy production and use, reliability in the generation and

distribution of electric power, improved fuel diversity within the

State, and environmental objectives such as improved air quality and

minimized land use.

The consideration of alternatives has been shifted to the site-

specific review. The rule contains no information or conclusions

regarding the environmental impacts of alternative energy sources, it

only indicates that the environmental impact of alternatives will be

considered during the individual plant review. However, the GEIS

contains a discussion of the environmental impacts of alternative

energy sources based on currently available information. The

information in the GEIS is available for use by the NRC and the

licensee in performing the site-specific analysis of alternatives and

will be updated as appropriate. For individual plant reviews,

information codified in the rule, information developed in the GEIS,

and any significant new information introduced during the plant-

specific review, including any information received from the State,

will be considered in reaching conclusions in the supplemental EIS. The

NRC's site-specific comparison of the impacts of license renewal with

impacts of alternative energy sources will involve consideration of

information provided by State agencies and other members of the public.

This approach should satisfy the States' concerns relative to a

meaningful analysis of alternative energy sources.

The Commission disagrees with CEQ's assertion that the new decision

standard is inappropriate. Under this decision standard, the NRC must

determine if the adverse environmental impacts of license renewal are

so great that preserving the option of license renewal for energy

planning decisionmakers would be unreasonable. The Commission expects

that license renewal would be denied only if the expected environmental

effects of license renewal significantly exceed all or almost all

alternatives. The Commission believes that this is a reasonable

approach to addressing the issue of environmental impacts of license

renewal, given NRC's limited role in the area of energy systems

planning. The operation of a nuclear power plant beyond its initial

license term involves separate regulatory actions, one taken by the

utility and the NRC, and the other taken by the utility and the State

regulatory authorities. The decision standard would be used by NRC to

determine whether, from an environmental perspective, it is

[[Page 28473]]

reasonable to renew the operating license and allow State and utility

decisionmakers the option of considering a currently operating nuclear

power plant as an alternative for meeting future energy needs. The test

of reasonableness focuses on an analysis of whether the environmental

impacts anticipated for continued operation during the term of the

renewed license reasonably compare with the impacts that are expected

from the set of alternatives considered for meeting generating

requirements. The NRC would reject a license renewal application if the

analysis demonstrated that the adverse environmental impacts of the

individual license renewal were so great that preserving the option of

license renewal for energy planning decisionmakers would be

unreasonable.

After the NRC makes its decision based on the safety and

environmental considerations, the final decision on whether or not to

continue operating the nuclear plant will be made by the utility,

State, and Federal (non-NRC) decisionmakers. This final decision will

be based on economics, energy reliability goals, and other objectives

over which the other entities may have jurisdiction. The NRC has no

authority or regulatory control over the ultimate selection of future

energy alternatives. Likewise, the NRC has no regulatory power to

ensure that environmentally superior energy alternatives are used in

the future. Given the absence of the NRC's authority in the general

area of energy planning, the NRC's rejection of a license renewal

application based on the existence of a single superior alternative

does not guarantee that such an alternative will be used. In fact, it

is conceivable that the rejection of a license renewal application by

the NRC in favor of an individual alternative may lead to the

implementation of another alternative that has even greater

environmental impacts than the proposed action, license renewal.

Given the uncertainties involved and the lack of control that the

NRC has in the choice of energy alternatives in the future, the

Commission believes that it is reasonable to exercise its NEPA

authority to reject license renewal applications only when it has

determined that the impacts of license renewal sufficiently exceed the

impacts of all or almost all of the alternatives that preserving the

option of license renewal for future decision makers would be

unreasonable. Because the objectives of the utility and State

decisionmakers will ultimately be the determining factors in whether a

nuclear power plant will continue to operate, NRC's proposed decision

standard is appropriate. The decision standard will not affect the

scope or rigor of NRC's analyses, including the consideration of the

environmental impacts relevant to the license renewal decision and

associated alternatives. The NRC staff believes that, under the

circumstances, the decision standard does not place ``a weighty and

improper burden of proof'' on other alternatives as CEQ claims.

With respect to the industry's desire to eliminate consideration of

alternative energy sources, the Commission does not agree. The

Commission does not support the views of NEI and others that

alternative energy sources need not be considered in the environmental

review for license renewal. The Commission is not prepared to state

that no nuclear power plant will fall well outside the range of other

reasonably available alternatives far in advance of an actual

relicensing decision. Following NEI's suggestion would not lead to a

meaningful set of alternatives with which to compare a proposed action.

The Commission has always held the view that alternative sources of

energy should be compared with license renewal and continued operation

of a nuclear power plant.

Lastly, the Commission does not believe it is necessary to reissue

this rule for public comment as a State commenter requested. The

Commission has taken many measures to involve the public concerning the

resolution of public comments on the proposed rule. The Commission has

conducted a number of public meetings and published for public comment

its recommended procedural revisions to the proposed rule. The

Commission believes that modifications made to the proposed rule

reflect the logical outgrowth of the proposed rule based on the public

comments received by the Commission.

C. Technical Concerns

1. Category and Impact Magnitude Definitions

Concerns. Many commenters expressed concern that the category

definitions and the impact-significance definitions were ambiguous and

appeared somewhat interconnected. The EPA expressed concern that

mitigation of adverse impacts was not addressed adequately.

Commenters expressed a number of concerns about the use of the

applicability categories and the magnitude-level categories. With

respect to the applicability categories, concerns ranged from a general

concern that Category 1 precludes or hinders public involvement in an

issue at the time of the plant-specific review to specific concerns

about the technical adequacy of the analysis supporting a Category 1

finding for an issue. Several commenters believed that the definitions

create confusion, especially as to whether the finding of small impact

and Category 1 are interdependent. The GEIS appears to use Category 1

and ``small'' interchangeably. Concern was also expressed that the

requirement to consider mitigative actions was inadequately addressed

in the draft GEIS and proposed rule.

Response. To reduce potential confusion over the definitions, the

use of the categories, and the treatment of mitigation within the

context of the categorization scheme, the NRC has revised the

definitions to eliminate any ambiguity as to how they are used.

Further, the GEIS has been modified to clearly state the reasons behind

the category and magnitude findings.

In order to facilitate understanding of the modifications to the

GEIS, the previous approach is discussed as follows. In the proposed

rule and the draft GEIS, findings about the environmental impact

associated with each issue were divided into three categories of

applicability to individual plant reviews. These categories were:

Category 1: A generic conclusion on the impact has been

reached for all affected nuclear power plants.

Category 2: A generic conclusion on the impact has been

reached for affected nuclear power plants that fall within defined

bounds.

Category 3: A generic conclusion on the impact was not

reached for any affected nuclear power plants.

The significance of the magnitude of the impact for each issue was

expressed as one of the three following levels.

Small impacts are so minor that they warrant neither

detailed investigation nor consideration of mitigative actions when

such impacts are negative.

Moderate impacts are likely to be clearly evident and

usually warrant consideration of mitigation alternatives when such

impacts are negative.

Large impacts involve either a severe penalty or a major

benefit, and mitigation alternatives are always considered when such

impacts are negative.

With respect to the categories of applicability, under the proposed

rule applicants would have:

(1) Not provided additional analyses of Category 1 issues;

(2) Not provided additional analyses if their plant falls within

the bounds

[[Page 28474]]

defined in the rule for a Category 2 issue;

(3) Provided additional plant-specific analyses if their plant does

not fall within the bounds defined in the rule for a Category 2 issue;

and

(4) Provided plant-specific analyses of Category 3 issues.

In order to address the comments on these magnitude and category

definitions, the GEIS has been modified to clearly state the reasons

behind the category and magnitude findings.

The revised definitions are listed below.

Category 1: For the issue, the analysis reported in the

Generic Environmental Impact Statement has shown:

(1) The environmental impacts associated with the issue have been

determined to apply either to all plants or, for some issues, to plants

having a specific type of cooling system or other specified plant or

site characteristic;

(2) A single significance level (i.e., small, moderate, or large)

has been assigned to the impacts (except for collective off site

radiological impacts from the fuel cycle and from high level waste and

spent fuel disposal); and

(3) Mitigation of adverse impacts associated with the issue has

been considered in the analysis and it has been determined that

additional plant-specific mitigation measures are likely not to be

sufficiently beneficial to warrant implementation.

The generic analysis of the issue may be adopted in each plant-

specific review. Issues for which the impact was found to be favorable

were also defined to be Category 1 issues.

Category 2: For the issue, the analysis reported in the

GEIS has shown that one or more of the criteria of Category 1 cannot be

met and, therefore, additional plant-specific review is required.

If, for an environmental issue, the three Category 1 criteria apply

to all plants, that issue is Category 1 and the generic analysis should

be used in a license renewal review for all plant applications. If the

three Category 1 criteria apply to a subset of plants that are readily

defined by a common plant characteristic, notably the type of cooling

system, the population of plants is partitioned into the set of plants

with the characteristic and the set without the characteristic. For the

set of plants with the characteristic, the issue is Category 1 and the

generic analysis should be used in the license renewal review for those

plants. For the set of plants without the characteristic, the issue is

Category 2 and a site-specific analysis for that issue will be

performed as part of the license renewal review. The review of a

Category 2 issue may focus on the particular aspect of the issue that

causes the Category 1 criteria not to be met. For example, severe

accident mitigation under the issue ``severe accidents'' is the focus

for a plant-specific review because the other aspects of the issue,

specifically the offsite consequences, have been adequately addressed

in the GEIS. With the revised definitions, the two issues previously

designated as Category 3 are now designated Category 2. For an issue to

be a Category 1, current mitigation practices and the nature of the

impact were considered and a determination was made that it is unlikely

that additional measures will be sufficiently beneficial. In the GEIS,

in discussing the impacts for each issue, consideration was given to

what is known about current mitigation practices.

The definitions of the significance level of an environmental

impact have been revised to make the consideration of the potential for

mitigating an impact separate from the analysis leading to a conclusion

about the significance level of the impact. Further, the significance

level of an impact is now more clearly tied to sustaining specific

attributes of the affected resource that are important to its

viability, health or usefulness. General definitions of small, moderate

and large significance levels are given below. These definitions are

adapted to accommodate the resource attributes of importance for each

of the environmental issues in the GEIS. The definition of ``small''

clarifies the meaning of the term as it applies to radiological

impacts. The definition of ``small'' in the proposed rule did not

logically apply to such impacts.

The general definitions of significance level are:

Small: For the issue, environmental effects are not

detectable or are so minor that they will neither destabilize nor

noticeably alter any important attribute of the resource. For the

purposes of assessing radiological impacts, the Commission has

concluded that those impacts that do not exceed permissible levels in

the Commission's regulations are considered small.

Moderate: For the issue, environmental effects are

sufficient to alter noticeably but not to destabilize important

attributes of the resource.

Large: For the issue, environmental effects are clearly

noticeable and are sufficient to destabilize important attributes of

the resource.

The discussion of each environmental issue in the GEIS includes an

explanation of how the significance category was determined. For issues

in which probability of occurrence is a key consideration (i.e.,

accident consequences), the probability of occurrence has been factored

into the determination of significance. The determination of the

significance category was made independently of the consideration of

the potential benefit of additional mitigation.

The major concerns (organized by topical areas) about the

environmental issues examined in the draft GEIS and the NRC staff's

response to those concerns are summarized next.

2. Surface Water Quality

Concern. Several commenters expressed concerns related to the

National Pollutant Discharge Elimination System (NPDES) permitting

process for surface water discharge. They believe that the NRC may have

overlooked its legal obligation to comply with Section 401 of the Clean

Water Act (CWA). Their recommendations included withholding approval

for license renewal until a facility has complied with Section 401 and

treating license renewal as an opportunity for a new NEPA review. On

the other hand, other commenters recommended decoupling the NRC

relicensing process from the NPDES permitting process.

Response. In issuing individual license renewals, the Commission

will comply, as has been its practice, with the provisions of Section

401 of the Federal Water Pollution Control Act (see 10 CFR 51.45(d) and

51.71(c)). In addition, pursuant to Section 511(c) of the Federal Water

Pollution Control Act of 1972, the Commission cannot question or

reexamine the effluent limitations or other requirements in permits

issued by the relevant permitting authorities. Nevertheless, compliance

with the environmental quality standards and requirements of these

permits does not negate the requirement for the Commission to consider

all environmental effects of the proposed action. Accordingly, the

Commission has not only taken existing permits into account in its

analysis of the water quality impacts of license renewal but has also

considered information on actual operating impacts collected from

individual plants, State and Federal regulatory agencies, and published

literature. As a result of this analysis, the Commission has concluded

that the environmental impacts on surface water quality are small for

those effluents subject to existing permit or certification

requirements. A total decoupling of the license renewal process and the

NPDES permitting process is not appropriate because, for

[[Page 28475]]

issues with incomplete Clean Water Act determinations, the NRC cannot

complete its weighing and balancing of impacts without independently

addressing the issues.

Concern. Several commenters raised concerns that various issues

within the Surface Water Quality topic should be Category 2 or 3

issues. These included water use conflicts as experienced in Arizona

and the Midwest, thermal stratification and salinity gradients

associated with once-through cooling systems, and the toxicity of

biofouling compounds.

Response. Regarding the water use conflicts, the NRC has considered

the impacts of water use during the renewal period and has concluded

that these impacts are small for plants with a once-through cooling

system and that this is a Category 1 issue for those plants. However,

this issue is designated Category 2 for plants with cooling towers and

cooling ponds because, for those plants, the impacts might be moderate

(they could also be small). In either case, pursuant to 10 CFR

51.45(d), an applicant for license renewal must identify and indicate

in its environmental report the status of State and local approvals

regarding water use issues. For those reactor sites where thermal

stratification or salinity gradient was found to be the most

pronounced, the issues were reviewed during preparation of the GEIS and

found to be acceptable by the States within the NPDES process. No

change in the categorization in the GEIS would be required. Similarly,

the NPDES permit for a facility establishes allowable discharges,

including biocides. The NRC has no indication that residual

environmental impacts would occur as a result of license renewal

activities at any nuclear plant site other than perhaps water use

conflicts arising at plants with cooling ponds or cooling towers using

make-up water from a small river with low flow. For those plants, this

issue is Category 2.

3. Aquatic Ecology

Concern. A number of comments regarding the ecological impact of

cooling water withdrawal from aquatic bodies were received. Specific

concerns included fish kills associated with the entrainment and

impingement of fish within once-through and cooling pond cooling

systems, the use of chlorine and molluscicides to control mussel and

clam growth, and the long-term effects of heavy metal discharges from

plants with copper-nickel condenser tubes. Another commenter noted that

license extension affords the opportunity to review the intake and

discharge configuration of plant cooling water systems, since the best

available technology that is economically available may be different

given the additional 20 years of plant operating life.

Response. The Commission has considered the impacts of license

renewal on aquatic ecology and, in doing so, has reviewed existing

NPDES permits and other information. Based on this analysis, the

Commission has concluded that these impacts are small with the

exception that plants with once-through cooling and cooling ponds may

have larger effects associated with entrainment of fish and shellfish

in early life stages, impingement, and heat shock. Agencies responsible

for existing permits are not constrained from reexamining the permit

issues if they have reason to believe that the basis for their issuance

is no longer valid. The Commission does not have authority under NEPA

to impose an effluent limitation other than those established in

permits issued pursuant to the Clean Water Act. The problem of the

long-term effects of heavy metal discharges from plants with copper-

nickel condenser tubes has been found at only one plant. The affected

condenser tubes have been replaced with tubing of a more corrosion-

resistant material.

Concern. A commenter pointed out that the issue of riparian zones

should be addressed in the GEIS because the vegetation region along a

water course can be affected by water withdrawal and is important in

maintaining the habitat.

Response. The NRC agrees with the importance of addressing the

impacts of license renewal on the riparian habitat. The final GEIS

provides a discussion of the riparian habitat as an important resource

and the potential effects of consumptive water use on riparian zones.

4. Groundwater Use and Quality

Concern. Several commenters indicated that groundwater issues

should be reviewed on a site-specific basis because of groundwater use

conflicts (in particular, the effect on aquifer recharge of using

surface water for cooling water), opportunities for saltwater

intrusion, and concerns over tritium found in wells at one site. On the

other hand, a commenter requested that the issue of groundwater use for

cooling tower makeup water be changed from Category 2 to Category 1

because the issue is based solely on data from Ranney wells at the

Grand Gulf Nuclear Station, where tests have shown that the elevation

of the water plain around Grand Gulf is not dropping.

Response. Based on consideration of comments, the issue of

groundwater use conflicts resulting from surface water withdrawals for

cooling tower makeup water or cooling ponds is now Category 2 for

plants withdrawing surface water from small water bodies during low

flow conditions. The GEIS has identified a potential reduction in

aquifer recharge as a result of competing water use. These conflicts

are already a concern at two closed-cycle nuclear power plants. The NRC

does not agree that saltwater intrusion should be considered a Category

2 issue. When saltwater intrusion has been a problem, the major cause

has been the large consumption of groundwater by agricultural and

municipal users. Groundwater consumption by nuclear power plants is

small by comparison and does not contribute significantly to the

saltwater intrusion problem. With regard to traces of tritium found in

the groundwater at one nuclear power plant, the tritium was attributed

to a modification in the plant's inlet and discharge canal that did not

take into consideration a unique situation in topology and groundwater

flow. The releases were minor and the situation has been corrected.

Regarding the issue of the use of groundwater for cooling water

makeup, the NRC has designated this issue as Category 2 even though

only the Grand Gulf Nuclear Station is currently using Ranney wells to

withdraw groundwater. This water intake does not conflict with other

groundwater uses in the area. It is not possible to predict whether or

not water use conflicts will occur at the Grand Gulf facility in the

future. It is also not possible to determine the significance of the

environmental impacts associated with Ranney well use at other nuclear

plants that may choose to adopt this method in the future.

5. Terrestrial Ecology

Concern. Several commenters recommended that the issue of bird

mortality resulting from collisions with transmission lines, towers, or

cooling towers be characterized as a Category 2 issue. Such a

characterization would provide for a review of mitigation at those

plants with cooling towers that do not have illumination and for power

plant transmission lines that transect major flyways or that cross

wetlands used by large concentrations of birds.

Response. The NRC does not agree with this recommendation. The GEIS

cites several studies that conclude that bird mortalities resulting

from collision with transmission lines, towers, or cooling towers are

not significantly

[[Page 28476]]

reducing bird populations. Mitigation measures in place, such as safety

lights, were found adequate and additional measures were not warranted.

Therefore, the issue remains a Category 1 issue because refurbishment

will not involve construction of any additional transmission lines or

natural draft cooling towers.

Concern. One commenter expressed concern that the GEIS analysis of

land use did not adequately encompass the impact of onsite spent fuel

storage on land use and that the Category 1 finding is questionable. A

specific concern was the potential need for the construction of

additional spent fuel storage facilities associated with the license

renewal term, along with their associated impacts on the terrestrial

environment.

Response. The NRC does not agree that there is a need to change the

Category 1 determination for onsite land use. Waste management

operations could require the construction of additional storage

facilities and thus adversely affect land use and terrestrial ecology.

However, experience has shown that the land requirements would be

relatively small (less than 9 acres), impacts to land use and

terrestrial ecology would also be relatively small, and the land that

may be used is already possessed by the applicant; thus, its basic use

would not be altered. Onsite land use is Category 1. Terrestrial

ecology with disturbance of sensitive habitat is treated as a separate

issue and is Category 2.

6. Human Health

Concern. In the human health section of the GEIS, the radiological

impacts of plant refurbishment and continued operations during the

license renewal term to workers and the general public were examined.

Several commenters indicated that it was inappropriate to compare the

radiation exposures associated with license renewal to natural

background levels. These commenters believed that the appropriate

argument should be that the risks associated with the additional

exposures are so small that no additional mitigative measures are

required.

Response. The NRC agrees that the assessment of radiation exposure

should not be simply a comparison with background radiation. In

response to comments on the draft generic environmental impact

statement and the proposed rule, the standard defining a small

radiological impact has changed from a comparison with background

radiation to sustained compliance with the dose and release limits

applicable to the various stages of the fuel cycle. This change is

appropriate and strengthens the criterion used to define a small

environmental impact for the reasons that follow. The Atomic Energy Act

requires the Nuclear Regulatory Commission to promulgate, inspect and

enforce standards that provide an adequate level of protection of the

public health and safety and the environment. The implementation of

these regulatory programs provides a margin of safety. A review of the

regulatory requirements and the performance of facilities provides the

bases to project continuation of performance within regulatory

standards. For the purposes of assessing radiological impacts, the

Commission has concluded that impacts are of small significance if

doses to individuals and releases do not exceed the permissible levels

in the Commission's regulations.

With respect to whether additional mitigative measures are

required, it should be noted that in 10 CFR parts 20 and 50 there are

provisions that radiological impacts associated with plant operation be

reduced to levels as low as reasonably achievable (ALARA).

Concern. Several commenters indicated that the GEIS needs a broader

treatment of uncertainty as it relates to human health issues.

Response. The NRC agrees that there is considerable uncertainty

associated with health effects, especially at low occupational and

public dose levels, and particularly with respect to electromagnetic

fields. Health effect estimates from radiation exposures are based on

the best scientific evidence available and are considered to be

conservative estimates. Several sections of the GEIS have been expanded

to more thoroughly explain how predicted impacts could be affected by

changes in scientific information or standards.

Concern. One commenter indicated that, in the GEIS and the proposed

rule, risk coefficients should have been used for chemicals and

radiation to obtain upper bound risk estimates of cancer incidence.

Response. The NRC does not agree with this comment. In making

comparisons of alternatives, comparisons of the central or best

estimates of impacts are consistent with NEPA requirements because they

provide the fairest determination. The GEIS is written using current,

Commission-approved risk estimators.

Concern. Two commenters expressed concern regarding the GEIS

conclusion that the impact of radiation exposure to the public is

small, citing a study done by the Massachusetts Department of Public

Health (MDPH). This study concluded that adults who live within 10

miles of the Pilgrim Nuclear Power Plant have a risk of contracting

leukemia four times greater than other individuals.

Response. The NRC staff reviewed the MDHP study and compared it

with various other studies. The results of the study have been

contradicted by a National Cancer Institute (NCI) study entitled

``Cancer in Populations Living Near Nuclear Facilities'' (July 1990).

The NCI study, which included the Pilgrim plant in its analysis, found

no reason to suggest that nuclear facilities may be linked causally

with excess deaths from leukemia or from other cancers. The findings of

the NCI study are consistent with the findings of several similar

epidemiological studies in foreign countries and with the latest

conclusions of expert bodies such as the National Research Council's

Committee on the Biological Effects of Ionizing Radiation. The NRC

continues to base its assessment of the health effects of ionizing

radiation on the overall body of scientific knowledge and on the

recommendations of expert groups.

7. Socioeconomics

Concern. A commenter concerned with historic preservation pointed

out that this issue must be addressed through compliance with the

National Historic Preservation Act (NHPA) and cannot be resolved

generically.

Response. The NRC agrees with this comment. Historical and

archaeological impacts have been changed from a Category 1 to a

Category 2 issue (that is, it must be evaluated site-specifically).

Consultation with State historical preservation offices and other

Government agencies, as required by NHPA, must be undertaken to

determine whether protected historical or archaeological resources are

in areas that might be disturbed during refurbishment activities and

operation during the renewal period.

Concern. Several commenters indicated that transportation issues

associated with refurbishment activities should be changed from

Category 3 to Category 2 because the impacts will be insignificant in

the majority of cases. One recommendation was to use a level of service

(LOS) determination for specific plants as the bounding criterion. The

analysis would require that LOS be determined for that part of the

refurbishment period during which traffic not related to the plant is

expected to be the heaviest. Another recommendation was to establish

bounding criteria based on past major routine outages.

Response. The NRC agrees that use of the LOS approach may prove to

be

[[Page 28477]]

acceptable. Transportation still must be reviewed on a plant-specific

basis, that is, it is a Category 2 issue (based on the revised

definition).

Concern. There were recommendations to make the housing impacts

during refurbishment a Category 1 issue instead of Category 2. One

commenter noted that the construction period data used in the analysis

appears to overestimate the impact on housing.

Response. The NRC does not agree that this should be a Category 1

issue. Although negligible housing impacts are anticipated for most

license renewals, significant housing impacts have occurred during a

periodic plant outage at one of the case plants studied for the

analysis. This issue is now a Category 2 issue because moderate and

large impacts on housing are possible depending on local conditions

(e.g., areas with extremely slow population growth or areas with growth

control measures that limit housing development).

8. The Uranium Fuel Cycle and Solid Waste Management

Concern. Wide-ranging concerns were expressed in the comments on

the proposed rule and the draft GEIS about the treatment of storage and

disposal of low-level waste (LLW), mixed waste, spent fuel,

nonradiological waste, and the transportation of fuel and waste to and

from nuclear power plants as a consequence of license renewal. Concern

was expressed about the uncertain availability of disposal facilities

for LLW, mixed waste, and spent fuel; the prospect of generation and

onsite storage of an additional 20 years output of waste; and the

resulting pressure that would be put on the States to provide LLW

disposal facilities. Various commenters expressed concern about the

adequacy of the treatment of the cost of waste management and the

implications for the economic viability of license renewal. Numerous

comments were provided on updating and clarifying data on waste

management presented in the draft GEIS. Finally, various questions were

raised about the applicability of Table S-3 (10 CFR 51.51 Uranium fuel

cycle environmental data--Table S-3, Table of Uranium Fuel Cycle

Environmental Data) to the management of waste generated as a result of

license renewal.

With regard to spent fuel, several commenters expressed concern

that dry cask storage is not a proven technology and that onsite

storage of spent fuel from an additional 20 years of plant operation

will present environmental and safety problems. Therefore, onsite

storage of spent fuel should be considered on a site-specific basis

within a plant license renewal review.

Response. The Commission acknowledges that there is uncertainty in

the schedule of availability of disposal facilities for LLW, mixed

waste, and spent fuel. However, the Commission believes that there is

sufficient understanding of and experience with the storage of LLW,

mixed waste, and spent fuel to conclude that the waste generated at any

plant as a result of license renewal can be stored safely and without

significant environmental impacts before permanent disposal. In

addition, the Commission concluded that the classification of storage

and ultimate disposal as a Category 1 issue is appropriate because

States are proceeding, albeit slowly, with the development of new

disposal facilities; LLW and mixed waste have been and can be safely

stored at reactor sites until new disposal capacity becomes available.

Analyses to support this conclusion are presented in Chapter 6 of the

final GEIS (NUREG-1437). The following summary of the responses to

comments emphasizes the main features of these analyses.

In the draft GEIS, the environmental data in Table S-3 were

discussed with respect to applicability during the license renewal

period and supplemented with an analysis of the radiological release

and dose commitment data for radon-222 and technetium-99. The proposed

rule would have had this discussion apply to each plant at the time of

its review for license renewal.

Further, in the draft GEIS, Chapter 6, ``Solid Waste Management,''

covered the generation of LLW, mixed waste, spent fuel, and

nonradiological waste as a result of license renewal; the

transportation of the radiological waste; and the environmental impacts

of waste management, including storage and disposal. The findings that

were to have been codified in the rule were that, for nonradiological

waste, mixed waste, spent fuel, and transportation, the environmental

impacts are of small significance and that the analysis in the GEIS

applies to each plant (Category 1). For LLW, the finding that would

have been codified in the rule was that, if an applicant does not have

access to a low-level radioactive waste disposal facility through a

low-level waste compact or an unaffiliated State, the applicant must

present plans for interim waste storage with an assessment of potential

ecological habitat destruction caused by construction activities

(Category 2).

In response to the questions about the applicability of Table S-3

to the management of waste associated with license renewal and to the

various comments challenging the treatment of the several forms of

waste in the draft GEIS and in the proposed rule, the discussion of

Table S-3 has been moved from Section 4.8 of the draft GEIS to Chapter

6 of the final GEIS in order to provide a more integrated assessment of

the environmental impacts associated with waste management as a

consequence of license renewal. Also in response to various comments,

the discussion of Table S-3 and of each of the types of waste has been

expanded.

Supplemental data are presented in Chapter 6 of the final GEIS in

order to extend the coverage of the environmental impacts of the

uranium fuel cycle presented in the current Table S-3 and of

transportation of radioactive waste presented in the current Table S-4

to radon-222, technetium-99, higher fuel enrichment, and higher fuel

burnup. In part, the current Table S-3 and the data supplementing it

cover environmental impacts of:

(1) Onsite storage of spent fuel assemblies in pools for 10 years,

packaging and transportation to a Federal repository, and permanent

disposal; and

(2) Short-term storage onsite of LLW, packaging and transportation

to a land-burial facility, and permanent disposal.

The following conclusions have been drawn with regard to the

environmental impacts associated with the uranium fuel cycle.

The radiological and nonradiological environmental impacts of the

uranium fuel cycle have been reviewed. The review included a discussion

of the values presented in Table S-3, an assessment of the release and

impact of \222\Rn and of \99\Tc, and a review of the regulatory

standards and experience of fuel cycle facilities. For the purpose of

assessing the radiological impacts of license renewal the Commission

uses the standard that the impacts are of small significance if doses

and releases do not exceed permissible levels in the Commission's

regulations. Given the available information regarding the compliance

of fuel cycle facilities with applicable regulatory requirements, the

Commission has concluded that, other than for the disposal of spent

fuel and high-level waste, these impacts on individuals from

radioactive gaseous and liquid releases will remain at or below the

Commission's regulatory limits. Accordingly, the Commission concludes

that offsite radiological impacts of the fuel cycle (individual effects

from other than the disposal of

[[Page 28478]]

spent fuel and high-level waste) are small. ALARA efforts will continue

to apply to fuel cycle activities. This is a Category 1 issue.

The radiological impacts of the uranium fuel cycle on human

populations over time (collective effects) have been considered within

the framework of Table S-3. The 100 year environmental dose commitment

to the U.S. population from the fuel cycle, high level waste and spent

fuel disposal excepted, is calculated to be about 14,800 man-rem, or 12

cancer fatalities, for each additional 20 year power reactor operating

term. Much of this, especially the contribution of radon releases from

mines and tailing piles, consists of tiny doses summed over large

populations. This same dose calculation can theoretically be extended

to include many tiny doses over additional thousands of years as well

as doses outside the U.S. The result of such a calculation would be

thousands of cancer fatalities from the fuel cycle, but this result

assumes that even tiny doses have some statistical adverse health

effect which will not ever be mitigated (for example no cancer cure in

the next thousand years), and that these dose projections over

thousands of years are meaningful. However these assumptions are

questionable. In particular, science cannot rule out the possibility

that there will be no cancer fatalities from these tiny doses. For

perspective, the doses are very small fractions of regulatory limits,

and even smaller fractions of natural background exposure to the same

populations. No standards exist that can be used to reach a conclusion

as to the significance of the magnitude of the collective radiological

effects. Nevertheless, some judgement as to the regulatory NEPA

implication of this issue should be made and it makes no sense to

repeat the same judgement in every case. The Commission concludes that

these impacts are acceptable in that these impacts would not be

sufficiently large to require the NEPA conclusion, for any plant, that

the option of extended operation under 10 CFR part 54 should be

eliminated. Accordingly, while the Commission has not assigned a single

level of significance for the collective effects of the fuel cycle,

this issue is considered Category 1. For other Category 1 issues, the

impacts will be considered at the individual renewal stage as a means

of judging the total impact of an individual license renewal decision.

However, the Commission has already judged the impact of collective

effects of the fuel cycle as part of this rule.

There are no current regulatory limits for off-site releases of

radionuclides for the current candidate repository site. However if we

assume that limits are developed along the lines of the 1995 National

Academy of Sciences (NAS) report, and that in accordance with the

Commission's Waste Confidence Decision, a repository can and likely

will be developed at some site which will comply with such limits, peak

doses to virtually all individuals will be 100 millirem per year or

less. However, while the Commission has reasonable confidence that

these assumptions will prove correct there is considerable uncertainty

since the limits are yet to be developed, no repository application has

been completed or reviewed, and uncertainty is inherent in the models

used to evaluate possible pathways to the human environment. The

National Academy report indicated that 100 millirem per year should be

considered as a starting point for limits for individual doses, but

notes that some measure of consensus exists among national and

international bodies that the limits should be a fraction of the 100

millirem per year. The lifetime individual risk from 100 millirem per

year dose limit is about 3 x 10-3. Doses to populations from

disposal cannot now (or possibly ever) be estimated without very great

uncertainty. Estimating cumulative doses to populations over thousands

of years is more problematic. The likelihood and consequences of events

that could seriously compromise the integrity of a deep geologic

repository were evaluated by the Department of Energy in the ``Final

Environmental Impact Statement: Management of Commercially Generated

Radioactive Waste,'' October 1980. The evaluation estimated the 70-year

whole-body dose commitment to the maximum individual and to the

regional population resulting from several modes of breaching a

reference repository in the year of closure, after 1,000 years, after

100,000 years, and after 100,000,000 years. The release scenarios

covered a wide range of consequences from the limited consequences of

humans accidentally drilling into a waste package in the repository to

the catastrophic release of the repository inventory by a direct meteor

strike. Subsequently, the NRC and other Federal agencies have expended

considerable effort to develop models for the design and for the

licensing of a high level waste repository, especially for the

candidate repository at Yucca Mountain. More meaningful estimates of

doses to population may be possible in the future as more is understood

about the performance of the proposed Yucca Mountain repository. Such

estimates would involve very great uncertainty, especially with respect

to cumulative population doses over thousands of years. The standard

proposed by the NAS is a limit on maximum individual dose. The

relationship of potential new regulatory requirements, based on the NAS

report, and cumulative population impacts has not been determined,

although the report articulates the view that protection of individuals

will adequately protect the population for a repository at Yucca

Mountain. However, EPA's generic repository standards in 40 CFR part

191 generally provide an indication of the order of magnitude of

cumulative risk to population that could result from the licensing of a

Yucca Mountain repository, assuming the ultimate standards will be

within the range of standards now under consideration. The standard in

40 CFR part 191 protects the population by imposing ``containment

requirements'' that limit the cumulative amount of radioactive material

released over 10,000 years. The cumulative release limits are based on

EPA's population impact goal of 1,000 premature cancer deaths world-

wide for a 100,000 metric tonne (MTHM) repository.

Nevertheless, despite all the uncertainty surrounding the effects

of the disposal of spent fuel and high-level waste, some judgement as

to the regulatory NEPA implications of these matters should be made and

it makes no sense to repeat the same judgement in every case. Even

taking the uncertainties into account, the Commission concludes that

these impacts are acceptable in that these impacts would not be

sufficiently large to require the NEPA conclusion, for any plant, that

the option of extended operation under 10 CFR part 54 should be

eliminated. Accordingly, while the Commission has not assigned a single

level of significance for the impacts of spent fuel and high-level

waste disposal, this issue is considered Category 1. Excepting the

collective effects previously discussed, for other Category 1 issues,

the impacts will be considered at the individual renewal stage as a

means of judging the total impact of an individual license renewal

decision. However, the Commission has already judged the impacts of

high level waste disposal as part of this rule.

With respect to the nonradiological impact of the uranium fuel

cycle, data concerning land requirements, water requirements, the use

of fossil fuel, gaseous effluent, liquid effluent, and tailings

solutions and solids, all listed in Table S-3, have been reviewed to

[[Page 28479]]

determine the significance of the environmental impacts of a power

reactor operating an additional 20 years. The nonradiological impacts

attributable to the relicensing of an individual power reactor are

found to be of small significance. License renewal of an individual

plant is so indirectly connected to the operation of fuel cycle

facilities that it is meaningless to address the mitigation of impacts

identified above. This is a Category 1 issue.

Table S-3 does not take into account long-term onsite storage of

LLW, mixed waste, and storage of spent fuel assemblies onsite for

longer than 10 years, nor does it take into account impacts from mixed

waste disposal. The environmental impacts of these aspects of onsite

storage are also addressed in Chapter 6 of the final GEIS and the

findings are included in the final rule in Table B-1 of appendix B to

10 CFR part 51.

Chapter 6 of the GEIS discusses the impacts of offsite disposal of

LLW and mixed waste and concludes that impacts will be small. The

conclusion that impacts will be small is based on the regulations and

regulatory programs in place (e.g., 10 CFR part 61 for LLW and 40 CFR

parts 261, 264, and 268 for hazardous waste), experience with existing

sites, and the expectation that NRC, EPA, and the States will ensure

that disposal will occur in compliance with the applicable regulations.

The Low-Level Radioactive Waste Policy Act of 1980 (LLRWPA) made

the States responsible for the disposal of commercially generated LLW.

At present, 9 compacts have been formed, representing 42 States. The

Texas Compact (Texas, Maine, and Vermont) is pending before the U.S.

Congress.

New LLW disposal facilities in the host States of California, North

Carolina, and Texas are forecast to be operational between 1997 and

1998. Facilities in the host States of Connecticut, Illinois,

Massachusetts, Nebraska, New Jersey, Pennsylvania, and New York are

scheduled for operation between 1999 and 2002. Envirocare, in Utah,

takes limited types of waste from certain generators.

There are uncertainties in the licensing process and in the length

of time needed to resolve technical issues, but in NRC's view there are

no unsolvable technical issues that will inevitably preclude successful

development of new sites or other off-site disposal capacity for LLW by

the time they will be needed. For example, in California, the proposed

Ward Valley LLW disposal facility was unexpectedly delayed by the need

to resolve technical issues raised by several scientists independent of

the project after the license was issued. These issues were recently

reviewed and largely resolved by an independent review group. In North

Carolina, Texas, and Nebraska, the license application review period

has been longer than is required by the LLRWPA, but progress continues

to be made.

The State's LLW responsibilities include providing disposal

capacity for mixed LLW. Mixed waste disposal facility developers face

the same types of challenges as LLW site developers plus difficulties

with dual regulation and small volumes. However, in NRC's view there

are no technical reasons why offsite disposal capacity for all types of

mixed waste should not become available when needed. NRC and EPA have

developed guidance on the siting of mixed waste disposal facilities as

well as a conceptual design for a mixed waste disposal facility. A

disposal facility for certain types of mixed waste is operated by

Envirocare in Utah. States have begun discussions with DOE about

accepting commercial mixed waste for treatment and disposal at DOE

facilities. Although these discussions have yet to result in DOE

accepting commercial mixed waste at DOE facilities, it appears that

progress is being made toward DOE's eventual acceptance of some portion

of commercial mixed waste at its facilities.

While the NRC understands that there have been delays and that

uncertainties exist such as those just discussed, the Commission

concludes that there is reasonable assurance that sufficient LLW and

mixed LLW disposal capacity will be made available when needed so that

facilities can be decommissioned consistent with NRC decommissioning

requirements. This conclusion, coupled with the expected small impacts

from both storage and disposal justify classification of LLW and mixed

waste disposal as Category 1 issues.

The GEIS addresses the matter of extended onsite storage of both

LLW and mixed waste from refurbishment and operations for a renewal

period of up to 20 years. Summary data are provided and radiological

and nonradiological environmental impacts are addressed. The analysis

considers:

(1) The volumes of LLW and mixed waste that may be generated from

license renewal;

(2) Specific requirements under the existing regulatory framework;

(3) The effectiveness of the regulations in maintaining low average

doses to members of the public and to workers; and

(4) Nonradiological impacts, including land use, fugitive dust, air

quality, erosion, sedimentation, and disturbance of ecosystems.

In addition, under 10 CFR 50.59, licensees are allowed to make

changes to their facilities as discussed in the final safety analysis

report without NRC permission if the evaluation indicates that a change

in the technical specifications is not required or that an unreviewed

safety question does not exist. Licensees would have to ensure that any

new LLW activities would not represent an unreviewed safety question

for routine operations or for conditions that might arise from

potential accidents. Both onsite and offsite impacts would have to be

considered. If a LLW or mixed waste activity fails either of the two

tests in 10 CFR 50.59, a license amendment is required. Subject to the

two possible review requirements just noted, the Commission finds that

continued onsite storage of both LLW and mixed waste resulting from

license renewal will have small environmental impacts and will require

no further review within the license renewal proceeding.

The GEIS addresses extended onsite storage of spent fuel during a

renewal period of up to 20 years. The Commission has studied the safety

and environmental effects of the temporary storage of spent fuel after

cessation of reactor operation and has published a generic

determination of no significant environmental impact (10 CFR 51.23).

The environmental data on storing spent fuel onsite in a fuel pool for

10 years before shipping for offsite disposal have been assessed and

reported in NUREG-0116, ``The Environmental Survey of the Reprocessing

and Waste Management Portions of the LWR Fuel Cycle'' (October 1976),

and published in the Commission's regulations (10 CFR 51.51).

Environmental assessments (EA) for expanding the fuel pool storage

capacity have been conducted for numerous plants. In each case, a

finding of no significant environmental impact was reached.

Radioactive exposures, waste generation, and releases were

evaluated and found to be small. The only nonradiological effluent from

waste storage is additional heat from the plant that was found to have

a negligible effect on the environment. Accidents were evaluated and

were found to have insignificant effects on the environment. Dry cask

storage at an independent spent fuel storage installation (ISFSI) is

another technology used to store under a general license. The

environmental impacts of allowing onsite dry cask storage under a

general license were

[[Page 28480]]

assessed in an EA and found to be insignificant. Further, the

Commission has conducted EAs for seven specific licensed ISFSIs and has

reached a finding of no significant environmental impact for each site.

Each EA addressed the impacts of construction, use, and

decommissioning. Potential impacts that were assessed include

radiological impacts, land use, terrestrial resources, water use,

aquatic resources, noise, air quality, socioeconomics, radiological

impacts during construction and routine operation, and radiological

impacts of off-normal events and accidents. Trends in onsite spent fuel

storage capacity and the volume of spent fuel that will be generated

during an additional 20 years of operation are considered in the GEIS.

Spent fuel storage capacity requirements can be adequately met by

ISFSIs without significant environmental impacts. The environmental

impacts of onsite storage of spent fuel at all plants have been

adequately assessed in the GEIS for the purposes of an environmental

review and agency decision on renewal of an operating license; thus, no

further review within the license renewal proceeding is required. This

provision is relative to the license renewal decision and does not

alter existing Commission licensing requirements specific to on-site

storage of spent fuel.

The environmental impacts from the transportation of fuel and waste

attributable to license renewal are found to be small when they are

within the range of impacts of parameters identified in Table S-4. The

estimated radiological effects are within regulatory standards. The

nonradiological impacts are those from periodic shipments of fuel and

waste by individual trucks or rail cars and thus would result in

infrequent and localized minor contributions to traffic density.

Programs designed to further reduce risk, which are already in place,

provide for adequate mitigation. Recent, ongoing efforts by the

Department of Energy to study the impacts of waste transportation in

the context of the multi-purpose canister (see, 60 FR 45147, August 30,

1995) suggest that there may be unresolved issues regarding the

magnitude of cumulative impacts from the use of a single rail line or

truck route in the vicinity of the repository to carry all spent fuel

from all plants. Accordingly, NRC declines to reach a Category 1

conclusion on this issue at this time. Table S-4 should continue to be

the basis for case-by-case evaluation of transportation impacts of fuel

and waste until such time as a detailed analysis of the environmental

impacts of transportation to the proposed repository at Yucca Mountain

becomes available.

9. Accidents

Concern. Several commenters expressed concerns regarding the

appropriateness of the severe accident determination in the GEIS and

with the treatment of severe accident mitigation design alternatives

(SAMDAs) for license renewal. A group of commenters identified areas of

concern that they believe justify severe accidents being classified as

a Category 3 issue. The areas included seismic risks to nuclear power

plants and site-specific evacuation risks. Several commenters

questioned whether the analyses of the environmental impacts of

accidents were adequate to make a Category 1 determination for the

issue of severe accidents. The contention is that a bounding analysis

would be established only if plant-specific analyses were performed for

every plant, which was not the case. Instead, the GEIS analysis made

use of a single generic source term for each of the two plant types.

Response. The Commission believes that its analysis of the impacts

of severe accidents is appropriate. The GEIS provides an analysis of

the consequences of severe accidents for each site in the country. The

analysis adopts standard assumptions about each site for parameters

such as evacuation speeds and distances traveled, and uses site-

specific estimates for parameters such as population distribution and

meteorological conditions. These latter two factors were used to

evaluate the exposure indices for these analyses. The methods used

result in predictions of risk that are adequate to illustrate the

general magnitude and types of risks that may occur from reactor

accidents. Regarding site-evacuation risk, the radiological risk to

persons as they evacuate is taken into account within the individual

plant risk assessments that form the basis for the GEIS. In addition,

10 CFR Part 50 requires that licensees maintain up-to-date emergency

plans. This requirement will apply in the license renewal term as well

as in the current licensing term.

As was done in the GEIS analysis, the use of generic source terms

(one set for PWRs and another for BWRs) is consistent with the past

practice that has been used and accepted by the NRC for individual

plant Final Environmental Impact Statements (FEISs). The purpose of the

source term discussion in the GEIS is to describe whether or not new

information on source terms developed after the completion of the most

recent FEISs indicates that the source terms used in the past under-

predict environmental consequences. The NRC has concluded that analysis

of the new source term information developed over the past 10 years

indicates that the expected frequency and amounts of radioactive

release under severe accident conditions are less than that predicted

using the generic source terms. A summary of the evolution of this

research is provided in NUREG-1150, ``Severe Accident Risks: An

Assessment for Five U.S. Nuclear Power Plants'' (December 1990), and

its supporting documentation. Thus, the analyses performed for the GEIS

represent adequate, plant-specific estimates of the impacts from severe

accidents that would generally over-predict, rather than under-predict,

environmental consequences. Therefore, the GEIS analysis of the impacts

of severe accidents for license renewal is retained and is considered

applicable to all plants.

Based on an evaluation of the comments, the Commission has

reconsidered its previous conclusion in the draft GEIS concerning site-

specific consideration of severe accident mitigation. The Commission

has determined that a site-specific consideration of alternatives to

mitigate severe accidents will be required at the time of license

renewal unless a previous consideration of such alternatives regarding

plant operation has been included in a final environmental impact

statement or a related supplement. Because the third criterion required

to make a Category 1 designation for an issue requires a generic

consideration of mitigation, the issue of severe accidents must be

reclassified as a Category 2 issue that requires a consideration of

severe accident mitigation alternatives, provided this consideration

has not already been completed. The Commission's reconsideration of the

issue of severe accident mitigation for license renewal is based on the

Commission's NEPA regulations that require a consideration of

mitigation alternatives in its environmental impact statements (EISs)

and supplements to EISs, as well as a previous court decision that

required a review of severe mitigation alternatives (referred to as

SAMDAs) at the operating license stage. See, Limerick Ecology Action v.

NRC, 869 F.2d 719 (3d Cir. 1989).

Although the Commission has considered containment improvements for

all plants pursuant to its Containment Performance Improvement (CPI)

program, which identified potential containment improvements for site-

specific consideration by licensees,

[[Page 28481]]

and the Commission has additional ongoing regulatory programs whereby

licensees search for individual plant vulnerabilities to severe

accidents and consider cost-beneficial improvements, these programs

have not yet been completed. Therefore, a conclusion that severe

accident mitigation has been generically considered for license renewal

is premature.

The Commission believes it unlikely that any site-specific

consideration of severe accident mitigation alternatives for license

renewal will identify major plant design changes or modifications that

will prove to be cost-beneficial for reducing severe accident frequency

or consequences. This Commission expectation regarding severe accident

mitigation improvements is based on the analyses performed to date that

are discussed below.

The Commission's CPI program examined each of the five U.S.

containment types to determine potential failure modes, potential plant

improvements, and the cost-effectivenesses of such improvements. As a

result of this program, only a few containment improvements were found

to be potentially beneficial and were either identified for further NRC

research or for individual licensee evaluation.

In response to the Limerick decision, an NRC staff consideration of

SAMDAs was specifically included in the Final Environmental Impact

Statement for the Limerick 1 and 2 and Comanche Peak 1 and 2 operating

license reviews, and in the Watts Bar Supplemental Final Environmental

Statement for an operating license. The alternatives evaluated in these

analyses included the items previously evaluated as part of the CPI

Program, as well as improvements identified through other risk studies

and analyses. No physical plant modifications were found to be cost-

beneficial in any of these severe accident mitigation considerations.

Only plant procedural changes were identified as being cost-beneficial.

Furthermore, the Limerick analysis was for a high-population site.

Because risk is generally proportional to the population around a

plant, this analysis suggests that other sites are unlikely to identify

significant plant modifications that are cost-beneficial.

Additionally, each licensee is performing an individual plant

examination (IPE) to look for plant vulnerabilities to internally

initiated events and a separate IPE for externally initiated events

(IPEEE). The licensees were requested to report their results to the

Commission. Seventy-eight IPE submittals were received and seventy-five

IPEEE submittals will be received, covering all operating plants in the

United States. These examinations consider potential improvements to

reduce the frequency or consequences of severe accidents on a plant-

specific basis and essentially constitute a broad search for severe

accident mitigation alternatives. The NRC staff is conducting a process

review of each plant-specific IPE submittal and IPEEE submittal. To

date, all IPE submittals have received a preliminary review by the NRC

with 46 out of 78 completed; for the IPEEE submittals, 24 of the 75 are

under review. These IPEs have resulted in a number of plant procedural

or programmatic improvements and some plant modifications that will

further reduce the risk of severe accidents.

In conclusion, the GEIS analysis of severe accident consequences

and risk is adequate, and additional plant-specific analysis of these

impacts is not required. However, because the ongoing regulatory

program related to severe accident mitigation (i.e., IPE and IPEEE) has

not been completed for all plants and consideration of severe accident

mitigation alternatives has not been included in an EIS or supplemental

EIS related to plant operations for all plants, a site-specific

consideration of severe accident mitigation alternatives is required at

license renewal for those plants for which this consideration has not

been performed. The Commission expects that if these reviews identify

any changes as being cost beneficial, such changes generally would be

procedural and programmatic fixes, with any hardware changes being only

minor in nature and few in number. NRC staff considerations of severe

accident mitigation alternatives have already been completed and

included in an EIS or supplemental EIS for Limerick, Comanche Peak, and

Watts Bar. Therefore, severe accident mitigation alternatives need not

be reconsidered for these plants for license renewal.

Based on the fact that a generic consideration of mitigation is not

performed in the GEIS, a Category 1 designation for severe accidents

cannot be made. Therefore, the Commission has reclassified severe

accidents as a Category 2 issue, requiring only that alternatives to

mitigate severe accidents be considered for those plants that have not

included such a consideration in a previous EIS or supplemental EIS.

The Commission notes that upon completion of its IPE/IPEEE program, it

may review the issue of severe accident mitigation for license renewal

and consider, by separate rulemaking, reclassifying severe accidents as

a Category 1 issue.

The Commission does not intend to prescribe by rule the scope of an

acceptable consideration of severe accident mitigation alternatives for

license renewal nor does it intend to mandate consideration of

alternatives identical to those evaluated previously. In general, the

Commission expects that significant efficiency can be gained by using

site-specific IPE and IPEEE results in the consideration of severe

accident mitigation alternatives. The IPEs and IPEEEs are essentially

site-specific PRAs that identify probabilities of core damage (Level 1

PRA) and include assessments of containment performance under severe

accident conditions that identify probabilities of fission product

releases (Level 2 ). As discussed in Generic Letter 88-20, ``Individual

Plant Examination for Severe Accident Vulnerabilities'' (November 23,

1988), one of the important goals of the IPE and IPEEE was to reduce

the overall probabilities of core damage and fission product releases

as necessary by modifying hardware and procedures to help prevent or

mitigate severe accidents.

Although Level 3 PRAs have been used in SAMDA analyses to generate

site-specific offsite dose estimates so that the cost-benefit of

mitigation alternatives could be determined, the Commission does not

believe that site-specific Level 3 PRAs are required to determine

whether an alternative under consideration will provide sufficient

benefit to justify its cost. Licensees can use other quantitative

approaches for assigning site-specific risk significance to IPE results

and judging whether a mitigation alternative provides a sufficient

reduction in core damage frequency (CDF) or release frequency to

warrant implementation. For example, a licensee could use information

provided in the GEIS analysis (exposure indices, wind frequencies, and

demographics) to translate the dominant contributors to CDF and the

large release frequencies from the IPE/IPEEE results into dose

estimates so that a cost-benefit determination can be performed. In

some instances, a consideration of the magnitude of reduction in the

site-specific CDF and release frequencies alone (i.e., no conversion to

a dose estimate) may be sufficient to conclude that no significant

reduction in off-site risk will be provided and, therefore,

implementation of a mitigation alternative is not warranted. The

Commission will review each severe accident mitigation consideration

provided by a license renewal applicant on its merits and determine

whether it

[[Page 28482]]

constitutes a reasonable consideration of severe accident mitigation

alternatives.

10. Decommissioning

Concern. Several commenters requested further clarification of the

NRC's position regarding decommissioning requirements, especially

whether the total impacts address returning the site to green field

conditions.

Response. The decommissioning chapter of the GEIS analyzes the

impact that an additional 20 years of plant operation would have on

ultimate plant decommissioning; it neither serves as the generic

analysis of the environmental impacts associated with decommissioning

nor establishes decommissioning requirements. An analysis of the

expected impacts from plant decommissioning was previously provided in

NUREG-0586, ``Final Generic Environmental Impact Statement on

Decommissioning of Nuclear Facilities'' (August 1988). The analysis in

the GEIS for license renewal examines the physical requirements and

attendant effects of decommissioning after a 20-year license renewal

compared with decommissioning at the end of 40 years of operation and

finds little difference in effects.

With respect to returning a site to green field condition, the

Commission defines decommissioning as the safe removal of a nuclear

facility from service, the reduction of residual contamination to a

level that permits release of the property for unrestricted use, and

termination of the license. Therefore, the question of restoring the

land to a green field condition, which would require additional

demolition and site restoration beyond addressing residual

contamination and radiological effects, is outside the current scope of

the decommissioning requirements. Moreover, consistent with the

Commission's conclusion that license renewal is not expected to affect

future decommissioning, any requirement relative to returning a site to

a green field and the attendant effects of such a requirement would

also not be affected by an additional 20 years of operation. Therefore,

the issue of returning a site to pre-construction conditions is beyond

the scope of license renewal review.

Concern. Several commenters expressed concern that, because a

residual radioactivity rule is still not in place, the LLW estimates

should be reexamined.

Response. The NRC does have criteria in place for the release of

reactor facilities to unrestricted access following decommissioning.

These include the guidance in Regulatory Guide 1.86, ``Termination of

Operating Licenses for Nuclear Reactors'' (which provides guidance for

surface contamination), dose rate limits from gamma-emitting

radionuclides included in plant technical specifications, and

requirements for keeping residual contamination as low as reasonably

achievable (ALARA) as included in 10 CFR part 20. These criteria were

used in developing NUREG-0586, the final GEIS on decommissioning of

nuclear facilities, which was published in August of 1988. One

conclusion from the analysis conducted for NUREG-0586 was that waste

volumes from decommissioning of reactors are not highly sensitive to

the radiological criteria. A proposed rule dated August 22, 1994, would

codify radiological criteria for unrestricted release of reactors and

other nuclear facilities and for termination of a facility license

following decommissioning. NUREG-1496, the draft GEIS for the proposed

rule on radiological criteria, included analyses of a range of

radiological release criteria and confirmed the earlier conclusions

that waste volumes from decommissioning of reactors are not sensitive

to the residual radiological criteria within the range likely to be

selected. This range included residual dose levels comparable to the

radiological criteria currently being used for reactor decommissioning.

Based on the insensitivity of the waste volume from reactor

decommissioning to the radiological criteria, the Commission continues

to believe, as concluded in the decommissioning section of the GEIS,

that the contribution to environmental impacts of decommissioning from

license renewal are small. The Commission further concludes that these

impacts are not expected to change significantly as a result of the

ongoing rulemaking. Therefore, the determinations in the GEIS remain

appropriate.

11. Need for Generating Capacity

Concern. In addition to the major procedural concern discussed

earlier about the treatment of need for generating capacity, several

commenters raised concerns about the power demand projections used in

the GEIS. Some commenters noted that any determination of need quickly

becomes dated and, therefore, the demand for and the source of

electrical power at the time of license renewal cannot be accurately

predicted at this time. Moreover, they believe that the NRC's analysis

is not definitive enough to remain unchallenged for 40 years. Another

commenter criticized the analysis because it focused only on energy

requirements without making appropriate distinctions between energy and

peak capacity requirements, plant availability, and capacity factors.

Response. The NRC has determined that a detailed consideration of

the need for generating capacity is inappropriate in the context of

consideration of the environmental impacts of license renewal. Thus,

the NRC will limit its NEPA review of license renewal applications to

the consideration of the environmental impacts of license renewal

compared with those of other available generating sources. Hence, the

concerns regarding demand projections used in the draft GEIS are no

longer an issue and they have been removed from the GEIS.

12. Alternatives to License Renewal

Concern. In addition to the procedural concern discussed earlier

about the treatment of alternative energy sources as a Category 1

issue, several commenters expressed concerns about the comparison and

analysis of alternative energy sources, as well as the economic

analysis approach used in the draft GEIS. Consistent with their

arguments against the Category 1 designation of alternatives, the

commenters questioned the approach adopted in the GEIS of comparing

only single alternative energy sources to license renewal. They believe

that the NRC's failure to consider a mix of alternatives ignores the

potential for other alternative sources of power that are available to

different regions of the nation, such as demand-side management,

cogeneration, purchased power from Canada, biomass, natural gas, solar

energy, and wind power. They also indicated that this approach neglects

a utility's ability to serve its customers with a portfolio of supply

that is based on load characteristics, cost, geography, and other

considerations, and fails to consider the collective impact of the

alternatives. Furthermore, the possible technological advances in

renewable energy sources over the next 40 years are not addressed.

One commenter argued that designating the issue of alternative

energy sources as Category 1 allows a license renewal applicant not to

consider the additional requirement of economic threshold analysis.

Relative to the economic analysis of the alternatives to license

renewal, another commenter questioned the proposed requirement for the

license renewal applicant to demonstrate that the ``replacement of

equivalent generating capacity by a coal-fired plant has no

demonstrated cost advantage over the individual nuclear power plant

license renewal.''

[[Page 28483]]

According to the commenter, this requirement would force the applicant

to perform an economic analysis of an alternative to license renewal.

The commenter further argued that NEPA does not require an economic

consideration.

Response. In response to these concerns, the final rule no longer

requires a cost comparison of alternative energy sources relative to

license renewal. Furthermore, the alternative energy sources discussed

in the final GEIS include energy conservation and energy imports as

well as the other sources discussed by the commenters. An analysis of

the environmental impacts of alternative energy sources is included in

the GEIS but is not codified in 10 CFR part 51.

The NRC believes that its consideration of alternatives in the GEIS

is representative of the technologies available and the associated

environmental impacts. With regard to consideration of a mix of

alternative sources, the Commission recognizes that combinations of

various alternatives may be used to replace power generation from

license renewal.

13. License Renewal Scenario

Concern. Several commenters raised concerns related to the license

renewal scenario evaluation methodology as implemented in the GEIS. The

fundamental issues were the degree of conservatism built into the

scenario and the appropriateness of an upper bound type approach in

characterizing the refurbishment activities (and associated costs) in

light of NEPA requirements to determine reasonable estimates of the

environmental impacts of Federal actions.

Regarding the concerns that the refurbishment schedules and

scenarios developed for the GEIS were too conservative, several

commenters indicated that many of the activities slated for completion

during the extended refurbishment before license renewal would actually

be completed by many facilities during the course of the current

licensing term. The effect of having only one major outage instead of

leveling work over three or four outages could lead to an over-estimate

of the refurbishment activities and costs that any particular plant

would expect to see.

Response. In response to this concern, the NRC has revised the GEIS

to include two license renewal program scenarios. The first scenario

refers to a ``typical'' license renewal program and is intended to be

representative of the type of programs that many plants seeking license

renewal might implement. The second scenario retains the original

objective of establishing an upper bound of the impacts likely to be

generated at any particular plant. The typical scenario is useful for

estimating impacts at plants that have been well maintained and have

already undertaken most major refurbishment activities necessary for

operation beyond the current licensing term. The conservative scenario

estimates continue to be useful for estimating the maximum impacts

likely to result from license renewal.

The revised approach of providing two separate license renewal

scenarios also alleviates the concern about the use of a bounding

scenario for license renewal activities. The NRC acknowledges that some

applicants for license renewal may not be required to perform certain

major refurbishment or replacement activities and, therefore, may have

fewer or shorter outages. However, the two scenarios described in the

GEIS are neither unrealistic nor overconservative in representing the

range of activities that could be expected for license renewal and the

possible schedule for performing these activities.

14. Environmental Justice

On February 11, 1994, the President issued Executive Order (E.O.)

12898, ``Federal Actions To Address Environmental Justice in Minority

Populations and Low-Income Populations'' (59 FR 7629, February 16,

1994). This order requires each Federal agency to make achieving

environmental justice part of its mission by identifying and

addressing, as appropriate, disproportionately high and adverse human

health or environmental effects of its programs, policies, and

activities on minority and low income populations. The Commission will

endeavor to carry out the measures set forth in the executive order by

integrating environmental justice into NRC's compliance with the

National Environmental Policy of 1969 (NEPA), as amended. E.O. 12898

was issued after publication of the proposed rule and the receipt of

comments on the proposed rule. As a result, no comments were received

regarding environmental justice reviews for license renewal. Therefore,

a brief discussion of this issue relative to license renewal is

warranted.

As called for in Section 1-102 of E.O. 12898, the EPA established a

Federal interagency working group to, among other things, ``* * *

provide guidance to Federal agencies or criteria for identifying

disproportionately high and adverse human health or environmental

effects on minority populations and low-income populations * * *.'' The

CEQ was assigned to provide this guidance to enable agencies to better

comply with E.O. 12898. Until the CEQ guidance is received, the

Commission intends to consider environmental justice in its evaluations

of individual license renewal applications. Greater emphasis will be

placed on discussing impacts on minority and low-income populations

when preparing NEPA documents such as EISs, supplemental EISs, and,

where appropriate, EAs. Commission requirements regarding environmental

justice reviews will be reevaluated and may be revised after receipt of

the CEQ guidance.

IV. Discussion of Regulatory Requirements

A. General Requirements

In this final rule, the regulatory requirements for performing a

NEPA review for a license renewal application are similar to the NEPA

review requirements for other major plant licensing actions. Consistent

with the current NEPA practice for major plant licensing actions, this

amendment to 10 CFR Part 51 requires the applicant to submit an

environmental report that analyzes the environmental impacts associated

with the proposed action, considers alternatives to the proposed

action, and evaluates any alternatives for reducing adverse

environmental effects. Additionally, the amendment requires the NRC

staff to prepare a supplemental environmental impact statement for the

proposed action, issue the statement in draft for public comment, and

issue a final statement after considering public comments on the draft.

The amendment deviates from NRC's current NEPA review practice in

some areas. First, the amendment codifies certain environmental impacts

associated with license renewal that were analyzed in NUREG-1437,

``Generic Environmental Impact Statement for License Renewal at Nuclear

Plants'' (xxxx 1996). Accordingly, absent new and significant

information, the analyses for certain impacts codified by this

rulemaking need only be incorporated by reference in an applicant's

environmental report for license renewal and in the Commission's

(including NRC staff, adjudicatory officers, and the Commission itself)

draft and final SEIS and other environmental documents developed for

the proceeding. Secondly, the amendment reflects the Commission's

decision to limit its NEPA review for license renewal to a

consideration of the environmental

[[Page 28484]]

effects of the proposed action and alternatives to the proposed action.

Finally, the amendment contains the decision standard that the

Commission will use in determining the acceptability of the

environmental impacts of individual license renewals.

The Commission and the applicant will consider severe accident

mitigation alternatives to reduce or mitigate environmental impacts for

any plant for which severe accident mitigation alternatives have not

been previously considered in an environmental impact statement or

related supplement or in an environmental assessment. The Commission

has concluded that, for license renewal, the issues of need for power

and utility economics should be reserved for State and utility

officials to decide. Accordingly, the NRC will not conduct an analysis

of these issues in the context of license renewal or perform

traditional cost-benefit balancing in license renewal NEPA reviews.

Finally, in a departure from the approach presented in the proposed

rule, this final rule does not codify any conclusions regarding the

subject of alternatives. Consideration of and decisions regarding

alternatives will occur at the site-specific stage. The discussion

below addresses the specific regulatory requirements of this amendment

and any conforming changes to 10 CFR part 51 to implement the

Commission's decision to eliminate cost-benefit balancing from license

renewal NEPA reviews.

B. The Environmental Report

1. Environmental Impacts of License Renewal

Through this final rule, the NRC has amended 10 CFR 51.53 to

require an applicant for license renewal to submit an environmental

report with its application. This environmental report must contain an

analysis of the environmental impacts of renewing a license, the

environmental impacts of alternatives, and mitigation alternatives. In

preparing the analysis of environmental impacts contained in the

environmental report, the applicant should refer to the data provided

in appendix B to 10 CFR part 51, which has been added to NRC's

regulations as part of this rulemaking. The applicant is not required

to provide an analysis in the environmental report of those issues

identified as Category 1 issues in Table B-1 in Appendix B. For those

issues identified as Category 2 in Table B-1, the applicant must

provide a specified additional analysis beyond that contained in Table

B-1. In this final rule, 10 CFR 51.53(c)(3)(ii) specifies the subject

areas of the analysis that must be addressed for the Category 2 issues.

Pursuant to 10 CFR 51.45(c), 10 CFR 51.53(c)(2) requires the

applicant to consider possible actions to mitigate the adverse impacts

associated with the proposed action. This consideration is limited to

designated Category 2 matters. Pursuant to 10 CFR 51.45(d), the

environmental report must include a discussion of the status of

compliance with applicable Federal, State, and local environmental

standards. Also, 10 CFR 51.53(c)(2) specifically excludes from

consideration in the environmental report the issues of need for power,

the economic costs and benefits of the proposed action, economic costs

and benefits of alternatives to the proposed action, or other issues

not related to environmental effects of the proposed action and

associated alternatives. In addition, the requirements in 10 CFR 51.45

are consistent with the exclusion of economic issues in 10 CFR

51.53(c)(2).

2. Consideration of Alternatives

Pursuant to 10 CFR 51.45(c), 10 CFR 51.53(c)(2) requires the

applicant to consider the environmental impacts of alternatives to

license renewal in the environmental report. The treatment of

alternatives in the environmental report should be limited to the

environmental impacts of such alternatives.

The amended regulations do not require a discussion of the economic

costs and benefits of these alternatives in the environmental report

for the operating license renewal stage except as necessary to

determine whether an alternative should be included in the range of

alternatives considered or whether certain mitigative actions are

appropriate. The analysis should demonstrate consideration of a

reasonable set of alternatives to license renewal. In preparing the

alternatives analysis, the applicant may consider information regarding

alternatives in NUREG-1437, ``Generic Environmental Impact Statement

for License Renewal of Nuclear Plants'' (xxxx 1996).

The Commission has developed a new decision standard to be applied

in environmental impact statements for license renewal as discussed in

Section IV.C.2. The amended regulations for license renewal do not

require applicants to apply this decision standard to the information

generated in their environmental report (although the applicant is not

prohibited from doing so if it desires). However, the NRC staff will

use the information contained in the environmental report in preparing

the environmental impact statement upon which the Commission will base

its final decision.

3. Consideration of Mitigation Alternatives

Consistent with the NRC's current NEPA practice, an applicant must

include a consideration of alternatives to mitigate adverse

environmental impacts in its environmental report. However, for license

renewal, the Commission has generically considered mitigation for

environmental issues associated with renewal and has concluded that no

additional site-specific consideration of mitigation is necessary for

many issues. The Commission's consideration of mitigation for each

issue included identification of current activities that adequately

mitigate impacts and evaluation of other mitigation techniques that

might or might not be warranted, depending on such factors as the size

of the impact and the cost of the technique. The Commission has

considered mitigation for all impacts designated as Category 1 in Table

B-1. Therefore, a license renewal applicant need not address mitigation

for issues so designated.

C. Supplemental Environmental Impact Statement

This amendment also requires that the Commission prepare a

supplemental environmental impact statement (SEIS), consistent with 10

CFR 51.20(b)(2). This statement will serve as the Commission's

independent analysis of the environmental impacts of license renewal as

well as a comparison of these impacts to the environmental impacts of

alternatives. This document will also present the preliminary

recommendation by the NRC staff regarding the proposed action.

Consistent with the revisions to 10 CFR 51.45 and 51.53 discussed above

in regard to the applicant's environmental report, this rulemaking

revises portions of 10 CFR 51.71 and 51.95 to reflect the Commission's

approach to addressing the environmental impacts of license renewal.

The issues of need for power, the economic costs and benefits of

the proposed action, and economic costs and benefits of alternatives to

the proposed action are specifically excluded from consideration in the

supplemental environmental impact statement for license renewal by 10

CFR 51.95(c), except as these costs and benefits are either essential

for a determination regarding the inclusion of an alternative in the

range of alternatives considered or relevant to mitigation. The

supplemental

[[Page 28485]]

environmental impact statement does not need to discuss issues other

than environmental effects of the proposed action and associated

alternatives. This rule amends the requirements in 10 CFR 51.71 (d) and

(e) so that they are consistent with the exclusion of economic issues

in 10 CFR 51.95(c). Additionally, 10 CFR 51.95 has been amended to

allow information from previous NRC site-specific environmental

reviews, as well as NRC final generic environmental impact statements,

to be referenced in supplemental environmental impact statements.

1. Public Scoping and Public Comments on the SEIS

Consistent with NRC's current NEPA practice, the Commission will

hold a public meeting in order to inform the local public of the

proposed action and receive comments. In addition, the SEIS will be

issued in draft for public comment in accordance with 10 CFR 51.91 and

51.93. In both the public scoping process and the public comment

process, the Commission will accept comments on all previously analyzed

issues and information codified in Table B-1 of appendix B to 10 CFR

part 51 and will determine whether these comments provide any

information that is new and significant compared with that previously

considered in the GEIS. If the comments are determined to provide new

and significant information bearing on the previous analysis in the

GEIS, these comments will be considered and appropriately factored into

the Commission's analysis in the SEIS. Public comments on the site-

specific additional information provided by the applicant regarding

Category 2 issues will be considered in the SEIS.

2. Commission's Analysis and Preliminary Recommendation

The Commission's draft SEIS will include its analysis of the

environmental impacts of the proposed license renewal action and the

environmental impacts of the alternatives to the proposed action. With

the exception of offsite radiological impacts for collective effects

and the disposal of spent fuel and high level waste, the Commission

will integrate the codified environmental impacts of license renewal as

provided in Table B-1 of appendix B to 10 CFR part 51 (supplemented by

the underlying analyses in the GEIS), the appropriate site-specific

analyses of Category 2 issues, and any new issues identified during the

scoping and public comment process. The results of this integration

process will be utilized to arrive at a conclusion regarding the sum of

the environmental impacts associated with license renewal. These

impacts will then be compared, quantitatively or qualitatively as

appropriate, with the environmental impacts of the considered

alternatives. The analysis of alternatives in the SEIS will be limited

to the environmental impacts of these alternatives and will be prepared

in accordance with 10 CFR 51.71 and subpart A of appendix A to 10 CFR

part 51. The analysis of impacts of alternatives provided in the GEIS

may be referenced in the SEIS as appropriate. The alternatives

discussed in the GEIS include a reasonable range of different methods

for power generation. The analysis in the draft SEIS will consider

mitigation actions for designated Category 2 matters and will consider

the status of compliance with Federal, State, and local environmental

requirements as required by 10 CFR 51.71(d). Consistent with 10 CFR

51.71(e), the draft supplemental environmental impact statement must

contain a preliminary recommendation regarding license renewal based on

consideration of the information on the environmental impacts of

license renewal and of alternatives contained in the SEIS. In order to

reach its recommendation, the NRC staff must determine whether the

adverse environmental impacts of license renewal are so great that

preserving the option of license renewal for energy planning

decisionmakers would be unreasonable. This decision standard is

contained in 10 CFR 51.95(c)(4).

3. Final Supplemental Environmental Impact Statement

The Commission will issue a final supplemental environmental impact

statement for a license renewal application in accordance with 10 CFR

51.91 and 51.93 after considering the public comments related to new

issues identified from the scoping and public comment process, Category

2 issues, and any new and significant information regarding previously

analyzed and codified Category 1 issues. Pursuant to 10 CFR 51.102 and

51.103, the Commission will provide a record of its decision regarding

the environmental impacts of the proposed action. In making a final

decision, the Commission must determine whether the adverse

environmental impacts of license renewal (when compared with the

environmental impacts of other energy generating alternatives) are so

great that preserving the option of license renewal for energy planning

decisionmakers would be unreasonable.

D. NEPA Review for Activities Outside NRC License Renewal Approval

Scope

The Commission wishes to clarify that any activity that requires

NRC approval and is not specifically required for NRC's action

regarding management of the effects of aging on certain passive long-

lived structures and components in the period of extended operation

must be subject to a separate NEPA review. The actions subject to NRC

approval for license renewal are limited to continued operation

consistent with the plant design and operating conditions for the

current operating license and to the performance of specific activities

and programs necessary to manage the effects of aging on the passive,

long-lived structures and components identified in accordance with 10

CFR part 54. Accordingly, the GEIS does not serve as the NEPA review

for other activities or programs outside the scope of NRC's part 54

license renewal review. The separate NEPA review must be prepared

regardless of whether the action is necessary as a consequence of

receiving a renewed license, even if the activity were specifically

addressed in the GEIS. For example, the environmental impacts of spent

fuel pool expansion are addressed in the GEIS in the context of the

environmental consequences of approving a renewed operating license,

rather than in the context of a specific application to expand spent

fuel pool capacity, which would require a separate NEPA review.

These separate NEPA reviews may reference and otherwise use

applicable environmental information contained in the GEIS. For

example, an EA prepared for a separate spent fuel pool expansion

request may use the information in the GEIS to support a finding of no

significant impact.

V. Availability of Documents

The principal documents supporting this supplementary information

are as follows:

(1) NUREG-1437, ``Generic Environmental Impact Statement for

License Renewal of Nuclear Plants'' (May 1996).

(2) NUREG-1529, ``Public Comments on the Proposed 10 CFR part 51

Rule for Renewal of Nuclear Power Plant Operating Licenses and

Supporting Documents; Review of Concerns and NRC Staff Response'' (May

1996).

(3) NUREG-1440, ``Regulatory Analysis of Amendments to Regulations

Concerning the Environmental Review

[[Page 28486]]

for Renewal of Nuclear Power Plant Operating Licenses'' (May 1996).

Copies of all documents cited in the supplementary information are

available for inspection and for copying for a fee in the NRC Public

Document Room, 2120 L Street NW. (Lower Level), Washington, DC. In

addition, copies of NRC final documents cited here may be purchased

from the Superintendent of Documents, U.S. Government Printing Office,

PO Box 37082, Washington, DC 20013-7082. Copies are also available for

purchase from the National Technical Information Service, 5285 Port

Royal Road, Springfield, VA 22161.

VI. Submittal of Comments in an Electronic Format

Commenters are encouraged to submit, in addition to the original

paper copy, a copy of their letter in an electronic format on IBM PC

DOS-compatible 3.5- or 5.25-inch, double-sided, double-density (DS/DD)

diskettes. Data files should be provided in Wordperfect 5.1 or later

version of Wordperfect. ASCII code is also acceptable or, if formatted

text is required, data files should be provided in IBM Revisable-Form

Text Document Content Architecture (RFT/DCA) format.

VII. Finding of No Significant Environmental Impact: Availability

The NRC has determined that this final rule is the type of action

described as a categorical exclusion in 10 CFR 51.22(c)(3). Therefore,

neither an environmental impact statement nor an environmental

assessment has been prepared for this regulation. This action is

procedural in nature and pertains only to the type of environmental

information to be reviewed.

VIII. Paperwork Reduction Act Statement

This final rule amends information collection requirements that are

subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et

seq.). These requirements were approved by the Office of Management and

Budget, approval number 3150-0021.

The public reporting burden for this collection of information is

estimated to average 4,200 hours per response, including the time for

reviewing instructions, searching existing data sources, gathering and

maintaining the data needed, and completing and reviewing the

collection of information. Send comments regarding this burden estimate

or any other aspect of this collection of information, including

suggestions for reducing the burden, to the Information and Records

Management Branch (T-6F33), U.S. Nuclear Regulatory Commission,

Washington, DC 20555-0001, or by Internet electronic mail at

BJS[email protected]; and to the Desk Officer, Office of Information and

Regulatory Affairs, NEOB-10202 (3150-0021), Office of Management and

Budget, Washington, DC 20503.

Public Protection Notification

The NRC may not conduct or sponsor, and a person is not required to

respond to, a collection of information unless it displays a currently

valid OMB control number.

IX. Regulatory Analysis

The Commission has prepared a regulatory analysis for this final

rule. The analysis examines the costs and benefits of the alternatives

considered by the Commission. The two alternatives considered were:

(A) Retaining the existing 10 CFR part 51 review process for

license renewal, which requires that all reviews be on a plant-specific

basis; and

(B) Amending 10 CFR part 51 to allow a portion of the environmental

review to be conducted on a generic basis.

The conclusions of the regulatory analysis show substantial cost

savings of alternative (B) over alternative (A). The analysis, NUREG-

1440, is available for inspection in the NRC Public Document Room, 2120

L Street NW. (Lower Level), Washington, DC. Copies of the analysis are

available as described in Section V.

X. Regulatory Flexibility Act Certification

As required by the Regulatory Flexibility Act of 1980, 5 U.S.C.

605(b), the Commission certifies that this final rule will not have a

significant impact on a substantial number of small entities. The final

rule states the application procedures and environmental information to

be submitted by nuclear power plant licensees to facilitate NRC's

obligations under NEPA. Nuclear power plant licensees do not fall

within the definition of small businesses as defined in Section 3 of

the Small Business Act, 15 U.S.C. 632, or the Commission's Size

Standards, April 11, 1995 (60 FR 18344).

XI. Small Business Regulatory Enforcement Fairness Act

In accordance with the Small Business Regulatory Enforcement

Fairness Act of 1996, the NRC has determined that this action is not a

major rule and has verified this determination with the Office of

Information and Regulatory Affairs of OMB.

XII. Backfit Analysis

The NRC has determined that these amendments do not involve any

provisions which would impose backfits as defined in 10 CFR

50.109(a)(1); therefore, a backfit analysis need not be prepared.

List of Subjects in 10 CFR Part 51

Administrative practice and procedure, Environmental impact

statement, Nuclear materials, Nuclear power plants and reactors,

Reporting and recordkeeping requirements.

For the reasons set out in the preamble and under the authority of

the Atomic Energy Act of 1954, as amended; the Energy Reorganization

Act of 1974, as amended; the National Environmental Policy Act of 1969,

as amended; and 5 U.S.C. 552 and 553, the NRC is adopting the following

amendments to 10 CFR part 51.

PART 51--ENVIRONMENTAL PROTECTION REGULATIONS FOR DOMESTIC

LICENSING AND RELATED REGULATORY FUNCTIONS

1. The authority citation for part 51 continues to read as follows:

Authority: Sec. 161, 68 Stat. 948, as amended, Sec. 1701, 106

Stat. 2951, 2952, 2953 (42 U.S.C. 2201, 2297f); secs. 201, as

amended, 202, 88 Stat. 1242, as amended, 1244 (42 U.S.C. 5841,

5842).

Subpart A also issued under National Environmental Policy Act of

1969, secs. 102, 104, 105, 83 Stat. 853-854, as amended (42 U.S.C.

4332, 4334, 4335); and Pub. L. 95-604, Title II, 92 Stat. 3033-3041.

Sections 51.20, 51.30, 51.60, 51.61, 51.80, and 51.97 also issued

under secs. 135, 141, Pub. L. 97-425, 96 Stat. 2232, 2241, and sec.

148, Pub. L. 100-203, 101 Stat. 1330-223 (42 U.S.C. 10155, 10161,

10168). Section 51.22 also issued under sec. 274, 73 Stat. 688, as

amended by 92 Stat. 3036-3038 (42 U.S.C. 2021) and under Nuclear

Waste Policy Act of 1982, sec. 121, 96 Stat. 2228 (42 U.S.C. 10141).

Sections 51.43, 51.67, and 51.109 also issued under Nuclear Waste

Policy Act of 1982, sec. 114(f), 96 Stat. 2216, as amended (42

U.S.C. 10134(f)).

2. Section 51.45 is amended by revising paragraph (c) to read as

follows:

Sec. 51.45 Environmental report.

* * * * *

(c) Analysis. The environmental report shall include an analysis

that considers and balances the environmental effects of the proposed

action, the environmental impacts of alternatives to the proposed

action, and alternatives available for reducing or avoiding adverse

environmental effects. Except for environmental reports prepared at the

license renewal stage pursuant to Sec. 51.53(c), the analysis in the

environmental report should also

[[Page 28487]]

include consideration of the economic, technical, and other benefits

and costs of the proposed action and of alternatives. Environmental

reports prepared at the license renewal stage pursuant to Sec. 51.53(c)

need not discuss the economic or technical benefits and costs of either

the proposed action or alternatives except insofar as such benefits and

costs are either essential for a determination regarding the inclusion

of an alternative in the range of alternatives considered or relevant

to mitigation. In addition, environmental reports prepared pursuant to

Sec. 51.53(c) need not discuss other issues not related to the

environmental effects of the proposed action and alternatives. The

analyses for environmental reports shall, to the fullest extent

practicable, quantify the various factors considered. To the extent

that there are important qualitative considerations or factors that

cannot be quantified, those considerations or factors shall be

discussed in qualitative terms. The environmental report should contain

sufficient data to aid the Commission in its development of an

independent analysis.

* * * * *

3. Section 51.53 is revised to read as follows:

Sec. 51.53 Postconstruction environmental reports.

(a) General. Any environmental report prepared under the provisions

of this section may incorporate by reference any information contained

in a prior environmental report or supplement thereto that relates to

the production or utilization facility or any information contained in

a final environmental document previously prepared by the NRC staff

that relates to the production or utilization facility. Documents that

may be referenced include, but are not limited to, the final

environmental impact statement; supplements to the final environmental

impact statement, including supplements prepared at the license renewal

stage; NRC staff-prepared final generic environmental impact

statements; and environmental assessments and records of decisions

prepared in connection with the construction permit, the operating

license, and any license amendment for that facility.

(b) Operating license stage. Each applicant for a license to

operate a production or utilization facility covered by Sec. 51.20

shall submit with its application the number of copies specified in

Sec. 51.55 of a separate document entitled ``Supplement to Applicant's

Environmental Report--Operating License Stage,'' which will update

``Applicant's Environmental Report--Construction Permit Stage.'' Unless

otherwise required by the Commission, the applicant for an operating

license for a nuclear power reactor shall submit this report only in

connection with the first licensing action authorizing full-power

operation. In this report, the applicant shall discuss the same matters

described in Secs. 51.45, 51.51, and 51.52, but only to the extent that

they differ from those discussed or reflect new information in addition

to that discussed in the final environmental impact statement prepared

by the Commission in connection with the construction permit. No

discussion of need for power, or of alternative energy sources, or of

alternative sites for the facility, or of any aspect of the storage of

spent fuel for the facility within the scope of the generic

determination in Sec. 51.23(a) and in accordance with Sec. 51.23(b) is

required in this report.

(c) Operating license renewal stage. (1) Each applicant for renewal

of a license to operate a nuclear power plant under part 54 of this

chapter shall submit with its application the number of copies

specified in Sec. 51.55 of a separate document entitled ``Applicant's

Environmental Report--Operating License Renewal Stage.''

(2) The report must contain a description of the proposed action,

including the applicant's plans to modify the facility or its

administrative control procedures as described in accordance with

Sec. 54.21 of this chapter. This report must describe in detail the

modifications directly affecting the environment or affecting plant

effluents that affect the environment. In addition, the applicant shall

discuss in this report the environmental impacts of alternatives and

any other matters described in Sec. 51.45. The report is not required

to include discussion of need for power or the economic costs and

economic benefits of the proposed action or of alternatives to the

proposed action except insofar as such costs and benefits are either

essential for a determination regarding the inclusion of an alternative

in the range of alternatives considered or relevant to mitigation. The

environmental report need not discuss other issues not related to the

environmental effects of the proposed action and the alternatives. In

addition, the environmental report need not discuss any aspect of the

storage of spent fuel for the facility within the scope of the generic

determination in Sec. 51.23(a) and in accordance with Sec. 51.23(b).

(3) For those applicants seeking an initial renewal license and

holding either an operating license or construction permit as of June

30, 1995, the environmental report shall include the information

required in paragraph (c)(2) of this section subject to the following

conditions and considerations:

(i) The environmental report for the operating license renewal

stage is not required to contain analyses of the environmental impacts

of the license renewal issues identified as Category 1 issues in

appendix B to subpart A of this part.

(ii) The environmental report must contain analyses of the

environmental impacts of the proposed action, including the impacts of

refurbishment activities, if any, associated with license renewal and

the impacts of operation during the renewal term, for those issues

identified as Category 2 issues in appendix B to subpart A of this

part. The required analyses are as follows:

(A) If the applicant's plant utilizes cooling towers or cooling

ponds and withdraws make-up water from a river whose annual flow rate

is less than 3.15 x 1012 ft3/year (9 x 1010 m3/

year), an assessment of the impact of the proposed action on the flow

of the river and related impacts on instream and riparian ecological

communities must be provided. The applicant shall also provide an

assessment of the impacts of the withdrawal of water from the river on

alluvial aquifers during low flow.

(B) If the applicant's plant utilizes once-through cooling or

cooling pond heat dissipation systems, the applicant shall provide a

copy of current Clean Water Act 316(b) determinations and, if

necessary, a 316(a) variance in accordance with 40 CFR part 125, or

equivalent State permits and supporting documentation. If the applicant

can not provide these documents, it shall assess the impact of the

proposed action on fish and shellfish resources resulting from heat

shock and impingement and entrainment.

(C) If the applicant's plant uses Ranney wells or pumps more than

100 gallons of ground water per minute, an assessment of the impact of

the proposed action on ground-water use must be provided.

(D) If the applicant's plant is located at an inland site and

utilizes cooling ponds, an assessment of the impact of the proposed

action on groundwater quality must be provided.

(E) All license renewal applicants shall assess the impact of

refurbishment and other license-renewal-related construction activities

on important plant and animal habitats. Additionally, the applicant

shall assess the impact of the proposed action on threatened or

[[Page 28488]]

endangered species in accordance with the Endangered Species Act.

(F) If the applicant's plant is located in or near a nonattainment

or maintenance area, an assessment of vehicle exhaust emissions

anticipated at the time of peak refurbishment workforce must be

provided in accordance with the Clean Air Act as amended.

(G) If the applicant's plant uses a cooling pond, lake, or canal or

discharges into a river having an annual average flow rate of less than

3.15 x 1012 ft3/year (9 x 1010 m3/year), an

assessment of the impact of the proposed action on public health from

thermophilic organisms in the affected water must be provided.

(H) If the applicant's transmission lines that were constructed for

the specific purpose of connecting the plant to the transmission system

do not meet the recommendations of the National Electric Safety Code

for preventing electric shock from induced currents, an assessment of

the impact of the proposed action on the potential shock hazard from

the transmission lines must be provided.

(I) An assessment of the impact of the proposed action on housing

availability, land-use, and public schools (impacts from refurbishment

activities only) within the vicinity of the plant must be provided.

Additionally, the applicant shall provide an assessment of the impact

of population increases attributable to the proposed project on the

public water supply.

(J) All applicants shall assess the impact of the proposed project

on local transportation during periods of license renewal refurbishment

activities.

(K) All applicants shall assess whether any historic or

archaeological properties will be affected by the proposed project.

(L) If the staff has not previously considered severe accident

mitigation alternatives for the applicant's plant in an environmental

impact statement or related supplement or in an environmental

assessment, a consideration of alternatives to mitigate severe

accidents must be provided.

(M) The environmental effects of transportation of fuel and waste

shall be reviewed in accordance with Sec. 51.52.

(iii) The report must contain a consideration of alternatives for

reducing adverse impacts, as required by Sec. 51.45(c), for all

Category 2 license renewal issues in Appendix B to Subpart A of this

part. No such consideration is required for Category 1 issues in

Appendix B to Subpart A of this part.

(iv) The environmental report must contain any new and significant

information regarding the environmental impacts of license renewal of

which the applicant is aware.

(d) Postoperating license stage. Each applicant for a license

amendment authorizing the decommissioning of a production or

utilization facility covered by Sec. 51.20 and each applicant for a

license or license amendment to store spent fuel at a nuclear power

plant after expiration of the operating license for the nuclear power

plant shall submit with its application the number of copies specified

in Sec. 51.55 of a separate document entitled ``Supplement to

Applicant's Environmental Report--Post Operating License Stage.'' This

supplement will update ``Supplement to Applicant's Environmental

Report--Operating License Stage'' and ``Applicant's Environmental

Report--Operating License Renewal Stage,'' as appropriate, to reflect

any new information or significant environmental change associated with

the applicant's proposed decommissioning activities or with the

applicant's proposed activities with respect to the planned storage of

spent fuel. Unless otherwise required by the Commission, in accordance

with the generic determination in Sec. 51.23(a) and the provisions in

Sec. 51.23(b), the applicant shall address only the environmental

impact of spent fuel storage for the term of the license.

4. In Sec. 51.55, paragraph (a) is revised to read as follows:

Sec. 51.55 Environmental report--number of copies; distribution.

(a) Each applicant for a license to construct and operate a

production or utilization facility covered by paragraphs (b)(1),

(b)(2), (b)(3), or (b)(4) of Sec. 51.20, each applicant for renewal of

an operating license for a nuclear power plant, each applicant for a

license amendment authorizing the decommissioning of a production or

utilization facility covered by Sec. 51.20, and each applicant for a

license or license amendment to store spent fuel at a nuclear power

plant after expiration of the operating license for the nuclear power

plant shall submit to the Director of the Office of Nuclear Reactor

Regulation or the Director of the Office of Nuclear Material Safety and

Safeguards, as appropriate, 41 copies of an environmental report or any

supplement to an environmental report. The applicant shall retain an

additional 109 copies of the environmental report or any supplement to

the environmental report for distribution to parties and Boards in the

NRC proceedings; Federal, State, and local officials; and any affected

Indian tribes, in accordance with written instructions issued by the

Director of the Office of Nuclear Reactor Regulation or the Director of

the Office Nuclear Material Safety and Safeguards, as appropriate.

* * * * *

5. In Sec. 51.71, paragraphs (d) and (e) are revised to read as

follows:

Sec. 51.71 Draft environmental impact statement--contents.

* * * * *

(d) Analysis. The draft environmental impact statement will include

a preliminary analysis that considers and weighs the environmental

effects of the proposed action; the environmental impacts of

alternatives to the proposed action; and alternatives available for

reducing or avoiding adverse environmental effects. Except for

supplemental environmental impact statements for the operating license

renewal stage prepared pursuant to Sec. 51.95(c), draft environmental

impact statements should also include consideration of the economic,

technical, and other benefits and costs of the proposed action and

alternatives and indicate what other interests and considerations of

Federal policy, including factors not related to environmental quality

if applicable, are relevant to the consideration of environmental

effects of the proposed action identified pursuant to paragraph (a) of

this section. Supplemental environmental impact statements prepared at

the license renewal stage pursuant to Sec. 51.95(c) need not discuss

the economic or technical benefits and costs of either the proposed

action or alternatives except insofar as such benefits and costs are

either essential for a determination regarding the inclusion of an

alternative in the range of alternatives considered or relevant to

mitigation. In addition, the su

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.