Missouri Regulatory Program

Federal RegisterMay 28, 1996

Ask Donna

What actually matters in this document.

Text

DEPARTMENT OF THE INTERIOR

30 CFR Part 925

[SPATS No. MO-026-FOR]

Missouri Regulatory Program

AGENCY: Office of Surface Mining Reclamation and Enforcement (OSM),

Interior.

ACTION: Final rule; approval of amendment.

-----------------------------------------------------------------------

SUMMARY: OSM is approving, with a reporting stipulation, a proposed

amendment to the Missouri regulatory program (hereinafter referred to

as the ``Missouri program'') under the Surface Mining Control and

Reclamation Act of 1977 (SMCRA). The proposed amendment consists of

revisions to the Revised Statutes of Missouri (RSMo) and the Code of

State Regulations (CSR) along with supporting documentation and

information pertaining to Missouri's alternative bonding system. The

amendment is intended to revise the Missouri program to be consistent

with the corresponding Federal regulations and SMCRA.

EFFECTIVE DATE: May 28, 1996.

FOR FURTHER INFORMATION CONTACT:

Brent Wahlquist, Regional Director, Mid-Continent Regional Coordinating

Center, Alton Federal Building, 501 Belle Street, Alton, Illinois,

62002 Telephone: (618) 463-6460.

SUPPLEMENTARY INFORMATION:

I. Background on the Missouri Program

II. Submission of the Proposed Amendment

III. Director's Findings

IV. Summary and Disposition of Comments

V. Director's Decision

VI. Procedural Determinations

I. Background on the Missouri Program

On November 21, 1980, the Secretary of Interior conditionally

approved the Missouri program. General background information on the

Missouri program, including the Secretary's findings, the disposition

of comments, and the conditions of approval of the Missouri program can

be found in the November 21, 1980, Federal Register (45 FR 77017).

Subsequent actions concerning Missouri's program and program amendments

can be found at 30 CFR 925.12, 925.15, and 925.16.

II. Submission of the Proposed Amendment

By letter dated March 7, 1995, Missouri submitted a proposed

amendment to its program pursuant to SMCRA (Administrative record No.

MO-617). Missouri submitted the proposed amendment in response to a

January 30, 1986, letter (Administrative record No. MO-351) that OSM

sent to Missouri in accordance with 30 CFR 732.17(c) and in response to

the required program amendments at 30 CFR 925.16(g). The provisions of

the Revised Statutes of Missouri (RSMo) and the Code of State

Regulations (CSR) that Missouri proposed to revise were: RSMO 444.805,

Definition of Phase I reclamation bond; RSMO 444.830, Bond

requirements, when a bond must be filed, the amount of a bond, and

allowance for bond substitution; RSMO 444.950, Phase I reclamation bond

requirements; RSMO 444.960, Establishment, purpose, and duties of the

Coal Mine Land Reclamation Fund (CMLR Fund); RSMO 444.965.1, Assessment

for fund; 10 CSR 40-7.011, Bond requirements; 10 CSR 40-7.021, Duration

and release of reclamation liability; 10 CSR 40-7.041, Form and

administration of the CMLR Fund. In addition, Missouri submitted: (1) A

[[Page 26446]]

narrative explaining the current and projected balances of the bond

pools (Fund A and Fund B) of the CMLR Fund; (2) a discussion of how

each outstanding required program amendment codified in the final rule

in the May 8, 1991, Federal Register (56 FR 21281) will be resolved

(Administrative Record No. MO-536); (3) an explanation of how the

deficiencies identified in OSM's issue letter dated March 9, 1994

(Administrative Record No. MO-592) will be resolved; (4) a table of

reclamation cost estimates for all permits except those that represent

a minimal liability to the bond pools; (5) a statement from the

Missouri Attorney General that explains the legal basis for using

Abandoned Mine Land Funds for the reclamation of Bill's Coal Forfeiture

Project; and (6) copies of the revised bond forms utilized by Missouri.

By letter dated March 28, 1995 (Administrative Record No. MO-623),

Missouri informed the OSM Kansas City Field Office of an inadvertent

omission in its program amendment request, and requested inclusion in

the proposed amendment of statutory revisions at RSMO 444.805 that

removes the definition for ``full cost bond'' and revises the

definition for ``Phase I reclamation bond.'' These changes correspond

to regulation changes at 10 CSR 40-7.011 and have been incorporated

into this amendment.

By letter dated February 21, 1996, (Administrative Record No. MO-

636), Missouri informed OSM it was removing the proposed revisions

concerning administrative rulemaking procedures at RSMO 444.950(2)-(8).

The main provisions of the amendment propose to:

Eliminate the option to post a ``full cost bond'' and

require mandatory participation in Missouri's alternative bonding

program.

Require that up to 20 percent of Phase I reclamation bond

be held until Phase III liability is released.

Establish minimum rate adjustable Phase I reclamation bond

amounts.

Establish the CMLR Fund as part of the alternative bonding

system (ABS), with 40 percent of the assessments placed in Fund A for

reclamation of permits revoked prior to September 1, 1988, and 60

percent of the assessments placed in Fund B for reclamation of permits

revoked after September 1, 1988.

Allow expenditure of CMLR funds for completion of Phase I

reclamation.

Allow expenditure of Phase I reclamation bond for any

phase of reclamation.

OSM published a notice in the March 27, 1995, Federal Register (58

FR 15728) announcing receipt of the amendment and inviting public

comment on the adequacy of the proposed amendment. The public comment

period ended April 26, 1995. The public hearing scheduled for April 21,

1995, was not held because no one requested an opportunity to testify.

III. Director's Findings

Set forth below, pursuant to SMCRA and the Federal regulations at

30 CFR 732.15 and 732.17, are the Director's findings concerning the

proposed amendment.

Revisions not specifically discussed below concern nonsubstantive

wording changes or revised cross-references and paragraph notations to

reflect organizational changes resulting from this amendment.

A. Revisions to Missouri's Regulations That Are Substantively Identical

to the Corresponding Federal Regulations

Missouri proposes revisions to the following regulations that

contain language that is identical in meaning to the counterpart

Federal regulations (Federal regulation counterparts are indicated in

brackets): 10 CSR 40-7.11(1)(H), Definition of Surety bond [30 CFR

800.5(a)]; 10 CSR 40-7.011(2), Requirement to file a bond [30 CFR

800.11]. The Director, therefore, finds these proposed revisions to

Missouri's regulations are no less effective than the federal

regulations.

B. Required Program Amendments

Missouri submitted proposed revisions in response to required

program amendments that the Director placed on the Missouri program at

30 CFR 925.16(g) on May 8, 1991 (56 FR 21281).

1. Required Program Amendments Satisfied by Statute or Regulation

Changes in the Proposed Amendment

The Director finds that the proposed revisions to the following

State statutes and regulations satisfy the indicated required program

amendments and are not inconsistent with the requirements of section

509(c) of SMCRA and 30 CFR 800.11(e) of the Federal regulations.

Missouri's proposed revisions and accompanying fiscal demonstration

indicate these revisions will resolve the issues associated with

currently approved alternative bonding provisions. Therefore, the

Director is approving them. For clarity, the required program

amendments are listed below, verbatim, along with Missouri's proposed

revisions.

a. 30 CFR 925.16(g)(1). At RSMo 444.830.1; 444.965.1; 10 CSR 40-

7.011(2)(B); and 10 CSR 40-7.041(1)(A); demonstrate that the resulting

financial aspect of the proposed optional participation by an applicant

of either a full-cost bond or Phase I bond will ensure that the ABS can

meet the requirements of 30 CFR 800.11(e) or remove this provision.

To satisfy 30 CFR 925.16(g)(1), Missouri proposes (1) at RSMo

444.830.1 to delete the option that allows an applicant to file a full-

cost bond and pay a one time assessment to the CMLR Fund (the one time

assessment only being required until September 1, 1993), thereby making

participation in the ABS mandatory; (2) at RSMo 444.950.1 to remove the

reference to a full-cost bond and to require all applicants to file a

Phase I reclamation bond; (3) at RSMo 444.965.1 to delete language

related to the option to file a full-cost bond; (4) at 10 CSR 40-

7.011(2) (B) and (C) to delete provisions concerning filing of a full-

cost bond; and (5) at 10 CSR 40-7.041(1) to delete provisions

concerning assessment lump sum payments by permittees who file full

cost bonds.

These proposed revisions satisfy the concerns raised by 30 CFR

925.16(g)(1), and the Director is removing this paragraph.

b. 30 CFR 925.16(g)(2). At RSMo 444.950.1 and 10 CSR 40-7.011(4)

(A), (B), (C), and (D) to ensure that the Phase I reclamation bond

amounts will cover the cost of reclamation and maintain the flexibility

of conventional bonds in all situations and that the open pit minimum

bond will be sufficient to assure the completion of the required

reclamation in all cases.

At the time this required amendment was imposed, Missouri's program

would not allow expenditure of bond pool moneys on Phase I reclamation.

Missouri proposes in this amendment to (1) at RSMo 444.950.1 and 10 CSR

40-7.011(5) establish adjustable Phase I reclamation bond rates; (2) at

RSMo 444.950.4 and 10 CSR 40-7.021(2)(D)1 allow retention of up to 20

percent of Phase I bond until completion of Phase III reclamation; and

(3) at RSMo 444.960.5 and 10 CSR 40-7.041(4)(A)1 allow expenditure of

CMLR funds for completion of Phase I reclamation.

The proposed revisions add flexibility to Missouri's alternative

bonding system to ensure coverage of the cost of reclamation, and the

Director is removing the required amendment at 30 CFR 925.16(g)(2).

c. 30 CFR 925.16(g)(4). AT RSMo 444.950.3 and 444.830.3 to require

the Secretary of the Interior's approval

[[Page 26447]]

before adopting an alternative bonding system or delete the provision.

In response to the required program amendment at 30 CFR

925.16(g)(4), Missouri proposes to modify its requirements at RSMO

444.830.3 and 444.950.3 regarding the ability of the commission to

approve an alternative bonding system by adding the language, ``* * *

and which is consistent with or pursuant to the purposes of Public Law

95-87, the Surface Mining Control and Reclamation Act.''

Section 509(c) of SMCRA specifically requires that the Secretary of

the Interior must approve an alternative bonding system prior to a

State being able to adopt the system. In a letter to Missouri dated

March 9, 1994 (Administrative Record No. MO-592), OSM stated its

interpretation of Missouri's intent in making this change to its

statute was to indicate Missouri's agreement that the Secretary of the

Interior's approval is required and Missouri would first obtain the

Secretary's approval prior to implementing any alternative bonding

system. Missouri's response letter dated April 4, 1994 (Administrative

Record No. MO-594), confirmed that OSM's interpretation was correct and

Missouri agrees that the Secretary of the Interior's approval is

required prior to implementing any alternative bonding system.

therefore, the Director is removing the required program amendment at

30 CFR 925.16(g)(4).

d. 30 CFR 925.16(g)(5). At RSMo 444.960.1 to clarify how the CMLR

Fund may be expended.

At RSMo 444.960.1, Missouri's currently approved statute states

that moneys within the CMLR Fund will be used by the Land Reclamation

Commission (LRC) to complete the reclamation plan for any permitted

lands after the proceeds from any applicable performance bond for such

reclamation have been exhausted. This would conceivably allow use of

moneys in the CMLR Fund to complete Phases I, II, and III reclamation

requirements. However, the existing statute at RSMO 444.960.5, while

allowing moneys within the 40 percent fund (Fund A) to be used for any

aspect of reclamation, stipulates that moneys within the 60 percent

fund (Fund B) may be used for Phases II and III reclamation only.

To satisfy 30 CFR 925.16(g)(5), Missouri proposes at RSMO 444.960.5

to allow moneys from both Fund A and Fund B to be used for all phases

of reclamation. The proposed revision clarifies how the CMLR Fund may

be expended, and the Director is removing the required amendment at 30

CFR 925.16(g)(5).

e. 30 CFR 925.16(g)(6). At RSMo 444.960.5 and 10 CSR 40-

7.041(4)(A)1, to ensure that the 40 percent fund portion (Fund A) will

provide sufficient funding to fully reclaim those sites forfeited prior

to September 1, 1988, and demonstrate that the 60 percent fund portion

(Fund B) generation of monies will be adequate to reclaim all defaulted

lands as required by 30 CFR 800.11(e).

To satisfy 30 CFR 925.16(g)(6), Missouri proposes at RSMo

444.960.5, 10 CSR 40-7.041(1)(A), and 10 CSR 40-7.041(4)(A)1 to require

that moneys paid into the CMLR Fund be allocated so that 40 percent of

the assessments would be used for reclaiming permits revoked by the LRC

prior to September 1, 1988 (Fund A), and 60 percent of the assessments

would apply to reclamation of permits revoked by the LRC after

September 1, 1988 (Fund B). Moneys that existed in the CMLR Fund as of

September 1, 1988, would be allocated to Fund A, as would 40 percent of

all moneys assessed for the CMLR Fund after September 1, 1988, until

such time that the accumulation of money in Fund A would be sufficient

to complete reclamation of those permits revoked by the commission

prior to September 1, 1988, after which time all moneys assessed for

the CMLR Fund would be allocated to Fund B. In addition, moneys from

both Fund A and Fund B would be used on any aspect of reclamation.

Missouri also proposes language changes at 10 CSR 40-7.041(1) (B), (C),

and (E) to maintain consistency with the proposed changes at 10 CSR 40-

7.041(1)(A) and 10 CSR 40-7.041(4)(A)1.

These proposed changes will allow Fund A to accrue additional

moneys to assure sufficient funding is available to fully reclaim those

sites forfeited prior to September 1, 1988. The portion of 30 CFR

925.16(g)(6) that requires a demonstration that Fund B generation of

moneys will be adequate to reclaim all defaulted lands as required by

30 CFR 800.11(e) is incorporated into and discussed in Finding B.2

since it is redundant with 30 CFR 925.16(g)(3), which also requires a

demonstration that Missouri's ABS will meet the requirements of SMCRA.

Therefore, since Missouri's proposed changes satisfy the Fund A portion

of the required amendment and the Fund B portion is a redundant

requirement, the Director is removing 30 CFR 925.16(g)(6) in its

entirety.

f. 30 CFR 925.16(g)(8). At RSMo 444.965.3 and 10 CSR 40-7.041(1)(B)

3, 4, 5, and 6; demonstrate that the buy out option would still allow

the ABS to meet the requirements of 30 CFR 800.11(e)(1) or remove this

option.

In response to 30 CFR 925.16(g)(8), Missouri proposes to delete

RSMO 444.965.3 and 10 CSR 40-7.041(1)(B)3, 4, 5, and 6, all of which

either provide for or relate to a buy out option. The removal of the

buy out option provisions from the Missouri program satisfies OSM's

concerns, and the Director is removing the required amendment at 30 CFR

925.16(g)(8).

g. 30 CFR 925.16(g)(20). At 10 CSR 40-7.021(2)(D)(1. to clarify

that its Phase I bond release for an ABS is consistently defined and

used throughout its program and to provide a legal opinion of its Phase

I reclamation bond release and bond coverage liability.

Missouri proposes to revise 10 CSR 40-7.021(2)(D)1 to reduce Phase

I bond by 80 percent when Phase I liability is released and to clarify

the remaining bond is permit specific. For consistency throughout its

program, Missouri also proposes (1) at 10 CSR 40-7.011(1)(D) to modify

the definition of Phase I bond to include release of 80 percent of the

bond upon successful completion of Phase I reclamation of a permit

area; (2) at RSMo 444.805(15), recodified from 444.805(16), to modify

the definition of Phase I reclamation bond to include release of no

less than 80 percent of the bond upon successful completion of Phase I

reclamation of a permit area; and (3) at RSMo 444.950.4 to allow for

release of no less than 80 percent of Phase I reclamation bond upon

completion of Phase I reclamation.

These proposed changes assure that Missouri's Phase I bond release

for its ABS is consistently defined and used throughout its program.

The Federal regulations at 30 CFR 800.40(c)(1), in reference to a

conventional bonding system, allow for release of 60 percent of the

bond when Phase I reclamation requirements are satisfied. Since

Missouri proposes mandatory participation in its alternative bonding

system, which will allow moneys to be used in any phase of reclamation,

release of 80 percent of the Phase I reclamation bond upon completion

of Phase I reclamation would be no less effective than the Federal

requirement to release 60 percent of a full cost bond upon completion

of Phase I reclamation.

Replacement of the word ``mine'' with the word ``permit'' and

addition of the word ``remaining'' at 10 CSR 40-7.021(2)(D)1 clarifies

that Phase I reclamation bond release is permit specific. Therefore, a

legal opinion of Missouri's Phase I reclamation bond release and bond

coverage liability is no longer necessary.

Based upon the above discussions, the Director is removing the

required

[[Page 26448]]

program amendment at 30 CFR 925.16(g)(20).

2. Required Program Amendments Satisfied by Missouri's Fiscal

Demonstration

Missouri's fiscal demonstration satisfies the required program

amendments at 30 CFR 925.16(g)(3), the Bond B portion of 30 CFR

925.16(g)(6), and 30 CFR 925.16(g)(7), which are set forth in the May

8, 1991, Federal Register (56 FR 21281). For clarity, the required

program amendments are listed below.

30 CFR 925.16(g)(3). * * *, demonstrate that the combination of

bond liability between the operator's Phase I bond and the CMLR Fund

bond will meet the requirements of SMCRA.

30 CFR 925.16(g)(6). * * *, demonstrate that the 60 percent fund

portion (Fund B) generation of moneys will be adequate to reclaim all

defaulted lands as required by 30 CFR 800.11(e).

30 CFR 925.16(g)(7). * * *, to assure that the fee assessment

structure of the CMLR Fund will ensure that the Fund will operate in a

financially solvent manner as required by 30 CFR 800.11(e).

In response to these three required program amendments, Missouri

submitted the report entitled ``Evaluation of Missouri's Alternative

Bonding System.'' Information in this demonstration shows that as of

February 1, 1996, Missouri's projected CMLR Fund assets exceed

liabilities in both Fund A and Fund B. In addition, projection tables

in the report indicate continued assessment fee payments to the Fund

will enable the State to reclaim all forfeiture sites and meet

contractual commitments in a timely manner without the Fund incurring a

deficit through September 1998.

Section 509(c) of SMCRA and 30 CFR 800.11(e) both require that

under an alternative bonding system, the regulatory authority must have

available sufficient money to complete the reclamation plan for any

site that may be in default at any time. An alternative bonding system

cannot be allowed to incur a deficit if it is to have available

adequate revenues to complete the reclamation of all outstanding bond

forfeiture sites. Since Missouri's demonstration shows that the CMLR

Fund has sufficient funds to fund the reclamation of forfeiture sites

that may be in default at any time, the Director finds that Missouri's

alternative bonding system meets the requirements of 30 CFR 800.11(e),

and it is achieving the objectives and purposes of the conventional

bonding program set forth in section 509 of SMCRA. However, due to the

possibility of future unanticipated bond forfeitures or increased

reclamation costs on pending or existing forfeiture sites that could

have significant impacts on solvency of Missouri's CMLR Fund, OSM must

have a means of monitoring continued solvency of the Fund. Therefore,

the Director is removing the required program amendments at 30 CFR

925.16 (g)(3), (g)(6), and (g)(7), with the stipulation that Missouri

submit semi-annual reports to demonstrate continued solvency of the

CMLR Fund, beginning with the first report due October 1, 1996, until

such time that OSM informs Missouri of a less frequent reporting

period.

C. Revisions to Missouri's Statutes That Are Not Substantively

Identical to the Corresponding Provisions of the Federal Statutes

1. RSMo 444.805--Definitions

Missouri proposes to recodify this section, delete the definition

of ``full-cost bond,'' and revise the definition of ``Phase I

reclamation bond.''

a. Full-Cost Bond. Missouri proposes to delete the term ``full-cost

bond'' previously defined at subsection (8), as this term is no longer

used in the revised statutes. Operators will no longer have the option

of posting a ``full-cost bond,'' but will be required to post a ``Phase

I reclamation bond'' at a minimum rate of $2,500 an acre and pay

assessments to the CMLR fund. The requirement for mandatory

participation in Missouri's alternative bonding program will make the

term ``full-cost bond'' obsolete. The Director finds that Missouri's

deletion of the definition of ``full-cost bond'' does not render RSMo

444.805 less stringent than the requirements of SMCRA for performance

bonds at section 509(a). The Director is, therefore, approving

Missouri's proposal to delete the definition of ``full-cost bond'' at

RSMo 444.805(8).

b. Phase I Reclamation Bond. At recodified subsection (15),

previously codified subsection (16), Missouri redefines the term

``Phase I reclamation bond'' to mean ``a bond for performance filed by

a permittee pursuant to section 444.450 that may have no less than

eighty percent released upon the successful completion of Phase I

reclamation of a permit area in accordance with the approved

reclamation plan, with the rest of the bond remaining in effect until

Phase III liability is released.'' The previous definition for ``Phase

I reclamation bond'' allowed Missouri to release all Phase I

reclamation bond upon the successful completion of Phase I reclamation.

By requiring the retention of 20 percent of the Phase I bond until

after Phase III liability is released, the revised definition provides

incentive for operators to successfully complete Phase II and Phase III

reclamation as required by 30 CFR 800.11(e)(2). There is no Federal

counterpart to Missouri's proposed definition. However, since the

Federal regulations at 30 CFR 800.13(a)(2) authorize regulatory

authorities to accept phased bonding and the Federal regulations at 30

CFR 800.40(c) allow regulatory authorities to release bond if they are

satisfied that all the reclamation or a phase of the reclamation

covered by the bond has been accomplished, the Director finds this

definition is not inconsistent with Federal program requirements.

Therefore, the Director is approving Missouri's proposed revision to

its definition of ``Phase I reclamation bond'' at RSMo 444.805(15).

2. RSMo 444.830--Filing Phase I Reclamation Bond

Missouri proposes to remove a provision from RSMo 444.830.1 and

insert the provision at RSMo 444.850.1. This provision concerns the

factors to be considered when determining the required Phase I bond

amount. Since the provision is to be inserted in RSMo 444.950.1, the

Director finds this change does not render the previously approved

provisions at RSMo 444.830.1 and 444.950.1 less stringent than the

requirements for performance bonds at section 509(a) of SMCRA and is

approving the provision move.

3. RSMo 444.950--Phase I Reclamation Bond Requirements

a. Adjustable Phase I Bond. (1) Minimum Adjustable Rate Phase I

Reclamation Bond. At RSMO 444.950.1, Missouri proposes to establish a

minimum Phase I reclamation bond rate of $2,500 per acre for all

permitted acreage, except for coal preparation areas for which the

minimum bond rate would be $10,000 per permitted acre. OSM previously

approved the $2,500 per acre Phase I bond amount in the February 26,

1988, Federal Register (53 FR 5766) and the $10,000 per acre bond

requirement for coal preparation areas in the October 31, 1988, Federal

Register (53 FR 43866) for unbonded acreage under new permits, after

April 30, 1986, or permits undisturbed as of that date. Both approvals

were considered to be adequate partial responses to OSM's January 30,

1986, 30 CFR part 732 notification to Missouri.

Missouri's proposal includes provisions that would allow annual

adjustments of up to $250 for the $2,500

[[Page 26449]]

minimum rate and $500 for the $10,000 minimum rate, with maximum bond

rates of $5,000 and $15,000, respectively, Bond amount adjustments

would have to be approved through rulemaking.

Establishment of adjustable Phase I bond rates is an improvement

over the previously approved fixed rats. Adjustable rates will provide

the necessary flexibility to accommodate changes in the cost of future

reclamation, a component essential to ensure the CMLR Fund's solvency

and hence its ability to meet the criteria of 300 CFR 800.11(e).

Therefore, the Director finds these revised provisions at RSMo

444.950.1 are not inconsistent with the requirements of section 509(a)

of SMCRA, and he is approving them.

(2) Factors Used to Determine Phase I Reclamation Bond Amounts.

Missouri proposes to insert a provision at RSMo 444.950.1, that was

removed from RSMO 444.830.1, with no substantive changes in language.

This provision concerns the factors to be considered when determining

the required Phase I reclamation bond amount. These factors will be

used to assess all mine sites annually to determine if an adjustment in

the Phase I reclamation bond amount is necessary. The Director finds

that the addition of this previously approved provision does not render

the provisions at RSMo 444.950.1 less stringent that the Federal

requirements for performance bonds at section 509(a) of SMCRA.

Therefore, the Director is approving Missouri's proposed change.

(3) Minimum Amount of Phase I Reclamation Bond. Missouri proposes

to remove the language ``permitted surface coal mining operation'' and

add the word ``permit'' in that portion of the provision which

currently requires a minimum of $10,000 of Phase I reclamation bond be

posted by an operator. The $10,000 minimum will now apply to each

permit instead of a surface coal mining operation, which might include

multiple permits. Missouri also proposes to delete the language ``at

two thousand five hundred dollars per acre'' in that portion of the

provision which requires a minimum bond equivalent to 20 acres of Phase

I reclamation bond be posted for each acre of open pit. This change is

necessary to be consistent with Missouri's proposal to establish

adjustable Phase I reclamation bond amounts. These changes are not

inconsistent with section 509 of SMCRA, and represent an improvement to

Missouri's alternative bonding system. Therefore, the Director is

approving these revisions to RSMo 444.950.1.

b. Acceptance of Phase I Reclamation Bond. At RSMO 444.950.3,

Missouri proposes to add the language ``Phase I reclamation.'' This

change is necessary to maintain consistency with Missouri's proposal to

delete the term ``full-cost bond'' and revise the term ``Phase I

reclamation bond'' at section 444.805. This proposed change is

nonsubstantive and does not render section 444.950.3 less stringent

than section 509(c) of SMCRA. Therefore, the Director is approving the

proposed change.

c. Release of Phase I Reclamation Bond. At RSMO 444.950.4, Missouri

proposes to add language which would allow retention of up to 20

percent of Phase I reclamation bond after completion of Phase I

reclamation with the retained bond remaining in effect until completion

of Phase III reclamation. This is an improvement over the existing

provision which requires all Phase I bond to be released on completion

of Phase III reclamation. This is an improvement over the existing

provision which requires all Phase I bond to be released on completion

of Phase I reclamation, and it would provide the economic incentive

required by 30 CFR 800.11(e)(2) for permittees to comply with all

reclamation provisions.

Missouri further proposes to allow Phase I reclamation bond be

available for all phases of reclamation in the event of forfeiture.

This is an improvement in the event of forfeiture. This is an

improvement over the existing provision which allows the expenditure of

Phase I reclamation bond only for Phase I reclamation in the event of

forfeiture. Section 509(a) of SMCRA requires that the amount of the

bond be sufficient to assure the completion of the reclamation plan in

the event of forfeiture.

Based on the above discussions, the Director finds the proposed

changes at RSMO 444.950.4 are not inconsistent with sections 509 and

519 of SMCRA, and represent an improvement in the Missouri alternative

bonding program. Therefore, the Director is approving Missouri's

proposed changes.

4. RSMo 444.960-Coal Mine Land Reclamation Fund

Section 509(c) of SMCRA provides that ``in lieu of establishment of

a bonding program, as set forth in this section, the Secretary may

approve * * * an alternative system that will achieve the objectives

and purposes of the bonding program pursuant to this section.'' As

stated in section 509(a) of SMCRA, one of the key objectives and

purposes of the bonding program is ``to assure the completion of the

reclamation plan if the work had to be performed by the regulatory

authority in the event of forfeiture * * *.'' In furtherance of this

objective, 30 CFR 800.11(e)(1) provides, in pertinent part, that OSM

may approve an alternative bonding system if the alternative assures

that ``the regulatory authority will have available sufficient money to

complete the reclamation plan for any areas which may be in default at

any time. Reclamation liability under a bond pool must be continuous.

The liability and obligation of an ABS does not disappear if the bond

pool finds itself unable to meet its obligations as they mature, its

existing capital structure is impaired, or its ability to perform any

of its obligations is impaired.

To meet the requirements of 30 CFR 800.11(e), an alternative

bonding system must assure that the regulatory authority will have

available sufficient money to complete the reclamation plan for any

areas which may be in default at any time, and must provide a

substantial economic incentive for the permittee to comply with all

reclamation provisions.

In this proposed program amendment submittal, Missouri proposes

several changes to its statutes to strengthen its ABS and meet

requirements of section 509 of SMCRA and 30 CFR 800.11(e).

a. Fund A. At RSMO 444.960, Missouri established Fund A in response

to the Director's January 30, 1986, letter that required the State to

outline plans to reclaim its backlog of forfeited sites. The proposed

fee structure of Fund A allocates moneys that existed in the CMLR Fund

as of September 1, 1988, to Fund A and allocates 40 percent of all

moneys assessed for the CMLR Fund after September 1, 1988, to Fund A

until such time that the accumulation of money in Fund A would be

sufficient to complete reclamation of those permits revoked by the

commission prior to September 1, 1988.

In addition, at the time this proposed amendment was submitted,

Missouri submitted a letter from its Attorney General that explains the

legal basis for using Abandoned Mine Land Funds for the reclamation of

Bill's Coal Forfeiture Project. When the proposed amendment was

submitted, Missouri's statutes were silent on expenditure of Abandoned

Mine Land Funds (AML Funds) on forfeiture sites where the surety became

insolvent. Since then, OSM approved a proposed amendment in which

Missouri made changes to its statutes to specifically allow use of AML

Funds on sites where insolvency of the surety occurred (60 FR 43972,

August 24, 1995). Approval of this amendment assures Missouri's statute

includes

[[Page 26450]]

language which allows use of AML Funds on the Bill's Coal Forfeiture

Project. Use of AML Funds at this site would lessen the financial

burden on Fund A, thereby reducing the time period for which

assessments to Fund A must continue.

Separation of Fund A from Fund B in the CMLR Fund system as

proposed by Missouri will allow the funds necessary to reclaim the

backlog of sites forfeited prior to September 1, 1988, and is not

inconsistent with section 509(c) of SMCRA. Therefore, the Director

finds that Missouri's proposed establishment of Fund A under section

RSMo 444.960.1 is no less stringent than section 509(c) of SMCRA and is

no less effective than 30 CFR 800.11(e). Accordingly, the Director is

approving Missouri's proposed establishment of Fund A in the ABS.

b. Fund B. Missouri's proposed Fund B will be used to fund

reclamation of sites where forfeiture occurred after September 1, 1988.

The proposed fee structure requires that 60 percent of the moneys

assessed for the CMLR Fund be allocated to Fund B until enough moneys

accrue in Fund A to complete reclamation of sites where forfeiture

occurred prior to September 1, 1988, after which Fund B will receive

100 percent of the CMLR Fund assessments.

Missouri proposes other changes which will specifically strengthen

Fund B. At RSMo 444.830.1, Missouri proposes to remove the option of

operators to file a full cost bond. This would require all permittees

to participate in the ABS program, thereby providing potential for

increased assessments to the CMLR Fund. At RSMo 444.950.4, Missouri

proposes to allow retention of up to 20 percent of Phase I reclamation

bond after completion of Phase I reclamation with the retained bond

remaining in effect until completion of Phase III reclamation. Also at

RMSo 444.950.4, Missouri proposes to allow the expenditure of Phase I

reclamation bond for all phases of reclamation in the event of

forfeiture. The existing provisions at RMSo 444.950.4 allow release of

all Phase I bond on completion of Phase I reclamation and the

expenditure of Phase I reclamation bond only for Phase I reclamation in

the event of forfeiture. These changes would potentially lessen the

burden on Fund B when forfeitures occur. As previously discussed in

this final rule, all of these proposed changes are being approved by

the Director.

The Director finds that Missouri's proposed concept of Fund B is

not inconsistent with section 509(c) of SMCRA or 30 CFR 800.11(e).

Therefore, the Director is approving Missouri's proposed establishment

of Fund B under section RMSo 444.960.

5. RMSo 444.965--Payments to the CMLR Fund

a. Redesignations. In Missouri's proposed amendment, RMSo 444.965.4

is redesignated 444.965.3, section 444.965.5 is redesignated section

444.965.4, and section 444.965.6 is redesignated section 444.965.5.

These changes do not render the previously approved provisions of RMSo

444.965 less stringent than the requirements of section 509 of SMCRA.

Therefore, the Director is approving the redesignations.

b. CMLR Fund Adjustment. Proposed language at newly codified RMSO

444.965.4, recodified from section 444.965.5, would require that after

the date when enough moneys have accumulated in the 40 percent pool

(Fund A) to complete reclamation on sites revoked prior to September 1,

1988, whenever the fund balance falls below $7 million, tonnage

assessments would resume at the rate of 25 cents per ton for the first

50,000 tons and 15 cents per ton for the second 50,000 tons of coal

sold, shipped, or otherwise disposed of in a calendar year by a

permittee, and the assessments would remain in effect until the fund

balance once again achieved at least $7 million dollars at the close of

the State's fiscal year.

Missouri's proposed tonnage rate assessments at section 444.965.4

would allow reductions in the assessment rates provided at section

444.965.2. Such fee assessments reductions would probably not

jeopardize solvency of the CMLR Fund because at the time of such

reductions, enough moneys would already have accumulated to reclaim the

backlog of forfeited sites where revocation occurred prior to September

1, 1988. The Director finds the changes proposed by Missouri are not

inconsistent with the requirements of section 509(c) of SMCRA.

Therefore, the Director is approving Missouri's proposed changes at

section 444.965.4.

c. CMLR Fund Balance Below $2 Million. At newly codified RMSo

444.965.5, recodified from section 444.965.6, Missouri proposes that:

``After September 1, 1998, whenever the fund balance falls below $2

million, the assessment rate established in subsection 2 of the section

[RMSo 444.965.2] shall increase to a per ton rate of 30 cents per ton

for the first 50,000 tons and 20 cents per ton for the second 50,000

tons of coal sold, shipped, or otherwise disposed of in a calendar year

by a permittee. The increased tonnage assessment shall remain in effect

until the fund balance is at least $3 million at the close of the

State's fiscal year, at which time the assessment rate will revert to

the rate established pursuant to subsection 4 of this section [RSM

444.965.4].'' The proposed increase in assessment rates after September

1, 1998, whenever the fund balance falls below $2 million will increase

Missouri's ability to adjust the fee schedule for the CMLR Fund when

necessary. The Director finds the changes proposed by Missouri are not

inconsistent with the requirements of section 509(c) of SMCRA.

Therefore, the Director is approving the changes proposed by Missouri

at section 444.965.5.

D. Revisions to Missouri's Regulations That Are Not Substantively

Identical to the Corresponding Provisions of the Federal Regulations

1. 10 CSR 40-7.011--Bond Requirements

a. 10 CSR 40-7.011(1), Definitions. (1) Redesignations. In

Missouri's proposed amendment, 10 CSR 40-7.011(1)(B) is redesignated 10

CSR 40-7.011(1)(A), 10 CSR 40-7.011(1)(C) is redesignated 10 CSR 40-

7.011(1)(B), 10 CSR 40-7.011(1)(D) is redesignated 10 CSR 40-

7.011(1)(C), 10 CSR 40-7.011(1)(E) is redesignated 10 CSR 40-

7.011(1)(D), 10 CSR 40-7.011(1)(F) is redesignated 10 CSR 40-

7.011(1)(G), and 10 CSR 40-7.011(1)(G) is redesignated 10 CSR 40-

7.011(1)(H). These changes do not render the previously approved

provisions at 10 CSR 40-7.011(1) less effective than the Federal

regulations. Therefore, the Director is approving the redesignations.

(2) Definition of ``Full Cost Bond.'' At 10 CSR 40-7.011(1)(A),

Missouri proposes to delete the definition of ``full-cost bond.''

Deletion of this definition is discussed in Finding C.1.a. of this

document. In that finding, the Director is approving Missouri's

proposal to delete the definition of ``full-cost'' bond from its

statutes. Therefore, the Director is also approving Missouri's proposal

to delete the definition of ``full-cost bond'' from its regulations at

10 CSR 40-7.011(1)(A).

(3) Definition of ``Phase I Bond.'' At 10 CSR 40-7.011(1)(D),

previously designated 10 CSR 40-7.011(1)(E), Missouri proposes to

redefine the term ``Phase I reclamation bond.'' Redefinition of this

term is discussed in Finding C.1.b. of this document. In that finding,

the Director is approving Missouri's proposal to redefine the term in

its statutes. Since the definition in Missouri's regulation is

substantively the same as the definition in its statute,

[[Page 26451]]

the Director is also approving Missouri's proposal to redefine the term

``Phase I bond'' in its regulation at 10 CSR 40-7.011(1)(D).

(4) Definition of ``Phase II Bond.'' At 10 CSR 40-7.011(1)(E),

Missouri proposes to add a definition for ``Phase II bond.'' It is

defined as ``performance bond conditioned on the release of Phase II

liability.'' There is no direct Federal counterpart to Missouri's

proposed definition. However, since the Federal regulations at 30 CFR

800.13(a)(2) authorize regulatory authorities to accept phased bonding

and the Federal regulations at 30 CFR 800.40(c) allow regulatory

authorities to release bond if they are satisfied that all the

reclamation or a phase of the reclamation covered by the bond has been

accomplished, the Director finds Missouri's proposed definition of

``Phase II bond'' is not inconsistent with the Federal regulation

requirements. therefore, the Director is approving Missouri's proposal

to add a definition for ``Phase II bond'' at 10 CSR 40-7.011(1)(E).

(5) Definition of ``Phase III Bond.'' At 10 CSR 40-7.011(1)(F),

Missouri proposes to add a definition for ``Phase III bond.'' It is

defined as ``performance bond conditioned on the release of Phase III

liability.'' There is no direct Federal counterpart to Missouri's

proposed definition. However, since the Federal regulations at 30 CFR

800.13(a)(2) authorize regulatory authorities to accept phased bonding

and the Federal regulations at 30 CFR 800.40(c) allow regulatory

authorities to release bond if they are satisfied that all the

reclamation or a phase of the reclamation covered by the bond has been

accomplished, the Director finds Missouri's proposed definition of

``Phase III bond'' is not inconsistent with the Federal regulation

requirements. Therefore, the Director is approving Missouri's proposal

to add a definition for ``Phase III bond'' at 10 CSR 40-7.011(1)(F).

b. 10 CSR 40-7.011(3), Incremental Bonding. (1) Filing Incremental

Bond. At 10 CSR 40-7.011(3)(A), Missouri proposes to add the provision,

``Disturbance is prohibited on succeeding increments, underground

shafts, tunnels, or operations prior to acceptance of bond.'' This

provision is substantially the same as that found at 10 CSR 40-

7.011(c). Therefore, the Director finds that addition of this provision

does not render 10 CSR 40-7.011(3)(A) less effective than the Federal

regulations, and he is approving the addition as proposed by Missouri.

(2) Identification of Increments for Bonding. At 10 CSR 40-

7.011(3)(D), Missouri proposes to add the language, ``* * * submit an

incremental bonding schedule and * * *.'' Although the counterpart

Federal regulation at 30 CFR 800.11(b)(3) does not require submission

of an incremental bonding schedule, the Federal regulation at 30 CFR

800.11(d)(3) does require the applicant to submit an incremental bond

schedule if he elects to bond in increments. Therefore, the Director

finds that addition of this requirement to 10 CSR 40-7.011(3)(D) does

not render it less effective than 30 CFR 800.11(b)(3), and is approving

the addition of language as proposed by Missouri.

(c) 10 CSR 40-7.011(4), Bond Amounts. (1) Minimum per Acre Phase I

Bond Amounts. At 10 CSR 40-7.011(4)(A), Missouri proposes to make

language changes and deletions to retain consistency with proposed

changes at RSMo 444.950.1 concerning minimum Phase I reclamation bond

amounts. Missouri, also, proposes to add the provision now found at 10

CSR 40-7.011(4)(C) which establishes the minimum amount of Phase I

reclamation bond required for each acre of coal preparation area. The

proposed revisions to Missouri's statute requirements for minimum Phase

I reclamation bond amounts are discussed in Finding C.3.a.(1) in this

document. In that finding, the Director approved Missouri's proposed

changes to its statute at RSMo 444.950.1. Therefore, the Director is

also approving Missouri's proposed language changes, additions, and

deletions as proposed at 40 CSR 40-7.011(4)(A), since they are

consistent with the approved statute revisions at RSMo 444.950.1.

(2) Minimum Phase I Bond for a Permit. At existing 10 CSR 40-

7.011(4)(D), redesignated as 10 CSR 40-7.011(4)(B), Missouri proposes

to change language so that the minimum amount of Phase I bond required

for mines with fewer than 1,000 acres shall be $10,000, or the

equivalent of 20 acres of bond for each acre of open pit area, for a

single permit instead of mine, and remove the definition of a ``single

mine.'' The Federal regulations at 30 CFR 800.14(b) set a minimum bond

requirement of $10,000 for the entire area under one permit. Missouri's

proposed changes at 10 CSR 40-7.011(4)(B) would also establish a

minimum bond rate of $10,000 for the area under one permit. Therefore,

the Director finds Missouri's proposed changes are no less effective

than the Federal regulations at 30 CFR 800.14(b), and he is approving

Missouri's proposed changes at redesignated 10 CSR 40-7.011(4)(B).

(3) Deleted Regulations. Missouri proposes to delete existing 10

CSR 40-7.011(4) (B), (C), (E), (F), (G), (H), and (I).

(a) At existing 10 CSR 40-7.011(4)(B), the provision allows for a

lesser amount of bond per acre than the $2,500 minimum bond per acre

set by 10 CSR 40-7.011(4)(A). Deletion of existing 10 CSR 40-

7.011(4)(B) will allow bond on any permitted acreage to be no less than

the $2,500 bond per acre required by 10 CSR 40-7.011(4)(A). The

Director finds deletion of existing 10 CSR 40-7.011(4)(B) will not

render 10 CSR 40-7.011(4) less effective than the Federal requirements

at 30 CFR 800.14(b).

(b) The provision at 10 CSR 40-7.011(4)(C) is being added to 10 CSR

40-7.011(4)(A). The Director finds deletion of 10 CSR 40-7.011(4)(C)

and insertion of the provision at 10 CSR 40-7.011(4)(A) will not render

10 CSR 40-7.011(4) less effective than the Federal requirements at 30

CFR 800.14(b).

(c) The provisions at 10 CSR 40-7.011(4) (E), (F), (G), (H), and

(I) all pertain to full-cost bonding. Deletion of the option to file a

full-cost bond in the Missouri statutes is discussed in Finding B.1.a.

In that finding, the Director approved Missouri's proposal at RSMo

444.830.1 to delete the option to file a full-cost bond. Therefore, the

Director is approving Missouri's proposal to delete existing

regulations pertaining to full-cost bond at 10 CSR 40-7.011(4) (B),

(C), (E), (F), (G), (H), and (I).

d. 10 CSR 40-7.011(5), Adjustment of Bond Amounts. Missouri

proposes to add new section 10 CSR 40-7.011(5), which includes

provisions at subsections (A), (B), (C), (D), and (E), that would allow

the State to adjust Phase I bond rates to ensure adequate bonding

amounts. The provisions at proposed new section 10 CSR 40-7.011(5) are

substantially the same as the proposed provisions of Missouri's statute

at RSMo-444.950.1, which are discussed in Finding C.3.a.(1). In that

finding, the Director is approving Missouri's proposed statute

provisions concerning adjustment of Phase I bond amounts. Therefore,

the Director is approving Missouri's proposed regulation provisions at

10 CSR 40-7.011(5).

2. 10 CSR 40-7.021 Duration and Release of Reclamation Liability

a. 10 CSR 40-7.021(2) Criteria and Schedule for Release of

Reclamation Liability. (1) General. At 10 CSR 40-7.021(2), Missouri

proposes to remove the provision concerning retention of bond on

unreclaimed temporary structures, such as roads, sediment ponds,

diversions, and stockpiles where

[[Page 26452]]

Phase I, II, and III liabilities under the alternative bonding system

apply and on a reclamation cost estimate basis where full-cost bonding

applies. Missouri is proposing to move that portion of the provision

pertaining to Phase I bond to 10 CSR 40-7.021(2)(A), and is proposing

to delete that portion of the provision pertaining to full-cost

bonding. As discussed in Finding B.1.a., the Director is approving

Missouri's proposal to delete the option to file a full-cost bond.

Therefore, none of the existing Missouri program provisions are

rendered less effective by this proposed move and deletion, and the

Director is approving Missouri's proposed revision at 10 CSR 40-

7.021(2).

(2) 10 CSR 40-7.021(2)(A) Qualification for Release of Phase I

Liability. As discussed above, Missouri proposes to move the

requirement that Phase I bond be retained on unreclaimed temporary

structures, such as roads, sediment ponds, diversions, and stockpiles

from 10 CSR 40-7.021(2) to 10 CSR 40-7.021(2)(A). Retention of bond for

unreclaimed temporary structures is not addressed as separate

requirements in the Federal regulations for bond release; however,

Phase I bond release may not be approved until backfilling, grading,

and drainage control in accordance with the reclamation plan is

complete. Since 10 CSR 40-7.021(2)(A) retains its requirement for

completion of backfilling, grading, and drainage control prior to Phase

I bond release, the existing regulation provisions are not rendered

less effective by the inclusion of the requirement for retention of

bond for unreclaimed temporary structures. Therefore, the Director

finds the proposed revision is no less effective than the Federal

regulations at 30 CFR 800.40(c)(1), and is approving Missouri's

proposed change at 10 CSR 40-7.021(2)(A).

(3) 10 CSR 40-7.021(2)(D)1 Release of Phase I Bond When Phase I

Reclamation is Completed. In addition to the proposed changes at 10 CSR

40-7.021(2)(D)1 previously discussed in Finding B.1.b., Missouri

proposes to add language to require that after 80 percent of Phase I

bond is released, the total remaining bond for a single permit shall

not be below the amount required by 10 CSR 40-7.011(4)(B). As discussed

in Finding D.1.c.(2), the Director is approving new 10 CSR 40-

7.011(4)(B) which requires that the minimum amount of Phase I bond

applied to a single permit shall be $10,000, or the equivalent of 20

acres of bond for each acre of open pit area, whichever is greater. The

Director finds Missouri's proposed change does not render 10 CSR 40-

7.021(2)(D)1 less effective than the requirements of 30 CFR

800.40(c)(1), and he is approving it.

(4) 10 CSR 40-7.021(2)(D)2 Release of Remaining Phase I Reclamation

Bond. At 10 CSR 40-7.021(2)(D)2, Missouri proposes to delete language

pertaining to release of full-cost bonds and to add the following

language pertaining to release of Phase I reclamation bond: ``The

remaining amount of the bonds shall be released when Phase III

liability is released.'' Deletion of the option to file a full-cost

bond is discussed in Finding B.1.a. In that finding, the Director

approved Missouri's proposal to delete the option to file a full-cost

bond from its statutes. Retention of a portion of Phase I bond until

completion of Phase III reclamation is discussed in Finding C.3.c. In

that finding, the Director approved Missouri's provision in its

statutes to retain up to 20 percent of Phase I bond until completion of

Phase III reclamation. These changes proposed by Missouri are necessary

to maintain consistency in its program and are not inconsistent with

SMCRA or the Federal regulations. Therefore, the Director is approving

Missouri's proposed changes at 10 CSR 40-7.021(2)(D)2.

(5) 10 CSR 40-7.021(2)(E) Release of Bond from Undisturbed Areas.

At 10 CSR 40-7.021(2)(E), Missouri proposes to clarify its provision

for release of bond liability from undisturbed areas which are adjacent

to disturbed lands by specifying that the bond ``may'' be released

instead of ``shall'' be released and by adding language pertaining to

surface mining disturbances: ``All bonding liability may be released in

full from undisturbed areas when further disturbances from surface

mining have ceased.'' In addition, Missouri proposes to clarify that

``The permit shall terminate on all areas where all bonds have been

released.'' Federal regulations at 30 CFR 800.15(c) allow reduction of

bond liability for undisturbed land. Although the Federal regulations

for undisturbed areas do not contain specific language pertaining to

permit termination, the Director finds the proposed changes would not

render 10 CSR 40-7.021(2)(E) inconsistent with SMCRA or the Federal

regulations and is approving them.

b. 10 CSR 40-7.021(5) Requirement to File an Affidavit. On the

State's initiative, additional requirements for bond release are

proposed to be added to the Missouri program. Specifically, Missouri

proposes to add a new section 10 CSR 40-7.021(5) which would require an

operator who is seeking a Phase III bond release to file an affidavit

with the recorder of deeds in the county where mining occurred

describing the parcel(s) of land where operations such as underground

mining, auger mining, covering of slurry ponds, or other underground

activities occurred which could impact or limit future use of the land.

This requirement would be applicable to mined land where Phase I

reclamation was completed on or after September 1, 1992. There is no

Federal counterpart to the proposed provision for Phase III bond

release at section 519 of SMCRA or 30 CFR 800.40(c). The Director finds

the additional requirements would not adversely impact the Missouri

program as none of the existing program provisions are rendered less

effective than the Federal regulations by the inclusion of the

additional requirements. Therefore, he is approving 10 CSR 40-7.021(5)

as proposed.

3. 10 CSR 40-7.041 Form and Administration of the Coal Mine Land

Reclamation Fund

Missouri proposes to delete 10 CSR 40-7.041(4)(A)2. This provision

stipulates that Reclamation Fund moneys cannot be expended for

reclamation or areas bonded by full-cost bonds. Since Missouri also

proposes in this amendment to remove the option to file a full-cost

bond, this proposed deletion is necessary to maintain consistency in

the Missouri program. As discussed in Finding B.1.a., the Director is

approving the deletion of the option to file a full-cost bond from the

Missouri program. Therefore, the Director finds Missouri's proposed

deletion of 10 CSR 40-7.041(4)(A)2 will not render 10 CSR 40-

7.041(4)(A) less effective than the Federal regulations.

IV. Summary and Disposition of Comments

Public Comments

The Director solicited public comments and provided an opportunity

for a public hearing on the proposed amendment. No public comments were

received, and because on one requested an opportunity to speak at a

public hearing, no hearing was held.

Federal Agency Comments

Pursuant to 30 CFR 732.17(h)(11)(i), the Director solicited

comments on the proposed amendment from various Federal agencies with

an actual or potential interest in the Missouri program. No comments

from Federal agencies were received.

Environmental Protection Agency (EPA)

Pursuant to 30 CFR 732.17(h)(11)(ii), OSM is required to obtain the

written

[[Page 26453]]

concurrence of the EPA with respect to those provisions of the proposed

program amendment that relate to air or water quality standards

promulgated under the authority of the Clean Water Act (33 U.S.C. 1251

et seq.).

None of the revisions that Missouri proposed to make in its

amendment pertain to air or water quality standards. Nevertheless, OSM

requested EPA's concurrence with the proposed amendment (Administrative

Record Nos. MO-621 and MO-624). EPA did not respond to OSM's request.

V. Director's Decision

Based on the above findings, the Director is approving, with a

reporting stipulation, the proposed amendment as submitted by Missouri

on March 7, 1995, and March 28, 1995. This stipulation requires

Missouri to submit semi-annual reports to demonstrate continued

solvency of the CMLR Fund, beginning with the first report due October

1, 1996, until such time that OSM informs Missouri of a less frequent

reporting period.

The changes approved in this rulemaking strengthens the Missouri

program and, as such, are consistent with SMCRA and the Federal

regulations at 30 CFR 732.17(g).

The Director approves the regulations and statutes as proposed by

Missouri with the provision that they be fully promulgated in identical

form to the regulations and statutes submitted to and reviewed by OSM

and the public.

The Federal regulations at 30 CFR Part 925, codifying decisions

concerning the Missouri program, are being amended to implement this

decision. With respect to those changes in State laws and regulations

approved in this document, the Director is making the final rule

effective immediately.

Effect of Director's Decision

Section 503 of SMCRA provides that a State may not exercise

jurisdiction under SMCRA unless the State program is approved by the

Secretary. Similarly, 30 CFR 732.17(a) requires that any alteration of

an approved State program be submitted to OSM for review as a program

amendment. In the oversight of the Missouri program, the Director will

recognize only the statutes, regulations, and other materials approved

by OSM, together with any consistent implementing policies, directives,

and other materials, and will require the enforcement by Missouri of

only such provisions.

VI. Procedural Determinations

Executive Order 12866

This rule is exempted from review by the Office of Management and

Budget (OMB) under Executive Order 12866 (Regulatory Planning and

Review).

Executive Order 12988

The Department of the Interior has conducted the reviews required

by section 3 of Executive Order 12988 (Civil Justice Reform) and has

determined that, to the extent allowed by law, this rule meets the

applicable standards of subsections (a) and (b) of that section.

However, these standards are not applicable to the actual language of

State regulatory programs and program amendments since each such

program is drafted and promulgated by a specific State, not by OSM.

Under sections 503 and 505 of SMCRA (30 U.S.C. 1253 and 1255) and 30

CFR 730.11, 732.15, and 732.17(h)(10), decisions on proposed State

regulatory programs and program amendments submitted by the States must

be based solely on a determination of whether the submittal is

consistent with SMCRA and its implementing Federal regulations and

whether the other requirements of 30 CFR Parts 730, 731, and 732 have

been met.

National Environmental Policy Act

No environmental impact statement is required for this rule since

section 702(d) of SMCRA (30 U.S.C. 1292(d)) provides that agency

decisions on proposed State regulatory program provisions do not

constitute major Federal actions within the meaning of section

102(2)(C) of the National Environmental Policy Act (42 U.S.C.

4332(2)(C)).

Paperwork Reduction Act

This rule does not contain information collection requirements that

require approval by OMB under the Paperwork Reduction Act (44 U.S.C.

3507 et seq.).

Regulatory Flexibility Act

The Department of the Interior has determined that this rule will

not have a significant economic impact on a substantial number of small

entities under the Regulatory Flexibility Act (5 U.S.C. 601 et seq.).

The State submittal which is the subject of this rule is based upon

corresponding Federal regulations for which an economic analysis was

prepared and certification made that such regulations would not have a

significant economic effect upon a substantial number of small

entities. Accordingly, this rule will ensure that existing requirements

previously promulgated by OSM will be implemented by the State. In

making the determination as to whether this rule would have a

significant economic impact, the Department relied upon the data and

assumptions for the corresponding Federal regulations.

Unfunded Mandates

This rule will not impose a cost of $100 million or more in any

given year on any governmental entity or the private sector.

List of Subjects in 30 CFR Part 925

Intergovernmental relations, Surface mining, Underground mining.

Dated: May 8, 1996.

Brent Wahlquist,

Regional Director, Mid-Continent Regional Coordinating Center.

For the reasons set out in the preamble, Title 30, Chapter VII,

Subchapter T of the Code of Federal Regulations is amended as set forth

below:

PART 925--MISSOURI

1. The authority citation for Part 925 continues to read as

follows:

Authority: 30 U.S.C. 1201 et seq.

2. Section 925.15 is amended by adding paragraph (t) to read as

follows:

Sec. 925.15 Approval of regulatory program amendments.

* * * * *

(t) Revisions to the following statutes and regulations, as

submitted to OSM on March 7 and March 28, 1995, are approved effective

May 28, 1996, with a reporting stipulation that requires Missouri to

submit semi-annual reports to demonstrate continued solvency of the

CMLR Fund, beginning with the first report due October 1, 1996, until

such time that OSM informs Missouri of a less frequent reporting

period.

(1) Revisions to the Revised Statutes of Missouri (RSMo).

RSMo 444.805--Deletion of the definition of full-cost bond and revision

of the definition of Phase I reclamation bond.

RSMo 444.830.1--Deletion of option to file a full-cost bond and

revision to Phase I reclamation bond filing requirements.

RSMo 444.830.3--Commission's adoption of an alternative bonding system.

RSMo 444.950.1--Phase I reclamation bond amount requirements, including

annual adjustments proposed through the Missouri rulemaking process.

[[Page 26454]]

RSMo 444.950.3--Self-bonding requirements and adoption of an

alternative bonding system.

RSMo 444.950.4--Phase I reclamation bond liability.

RSMo 444.960.1--Establishment of the CMLR Fund.

RSMo 444.960.5--Allocation and use of the A (40%) and B (60%) portions

of the CMLR Fund.

RSMo 444.965.1--CMLR initial assessments.

RSMo 444.965.3--Deletion of buy-out option.

RSMo 444.965.4--CMLR Fund Adjustment.

RSMo 444.965.5--CMLR assessment increase.

(2) Revisions to the Missouri Code of Regulations (CSR) at 10 CSR

40-7.

10 CSR 40-7.011(1)--Deletion of the definition of full-cost bond,

revision of the definition of Phase I bond, and addition of definitions

for Phase II and Phase III bond.

10 CSR 40-7.011(2)--Revision of requirements to file a bond.

10 CSR 40-7.011(3)--Filing of incremental bond and identification of

increments for bonding.

10 CSR 40-7.011(4)--Minimum per acre Phase I bond amounts, minimum

Phase I bond for a permit, and deletion of full-cost bonding

provisions.

10 CSR 40-7.011(5)--Annual adjustment of Phase I bond amounts.

10 CSR 40-7.021(2)--Concerning criteria and schedule for release of

reclamation liability, qualification for release of Phase I liability,

release of Phase I bond when Phase I reclamation is completed, and

release of bond from undisturbed areas.

10 CSR 40-7.021(5)--Requirement to file an affidavit at Phase III

release of underground mining acreage.

10 CSR 40-7.041(1)--Payment to the 40 percent pool, assessment rates,

continuation of monthly assessments, and reinstatement rates.

10 CSR 40-7.041(4)--Expenditure of reclamation fund moneys.

Sec. 925.16 [Amended]

3. Section 925.16 is amended by removing and reserving paragraphs

(g)(1) through (g)(8) and (g)(20).

[FR Doc. 96-13261 Filed 5-24-96; 8:45 am]

BILLING CODE 4310-05-M

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.