NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-321 and 50-366]
Georgia Power Company, Oglethorpe Power Corporation, Edwin I.
Hatch Nuclear Plant, Units 1 and 2; Environmental Assessment and
Finding of No Significant Impact
The U.S. Nuclear Regulatory Commission (the Commission) is
considering issuance of amendments to Facility Operating License Nos.
DPR-57 and NPF-5 issued to Georgia Power Company, et al. (GPC or the
licensee), for operation of the Edwin I. Hatch Nuclear Plant, Units 1
and 2, located in Appling County, Georgia.
Environmental Assessment
Identification of the Proposed Action
This Environmental Assessment, provided by the licensee, addresses
potential environmental issues related to GPC's application to amend
Plant Hatch, Units 1 and 2, Operating Licenses. The proposed amendments
would increase the licensed core thermal power from 2436 MWt to 2558
MWt, which represents an increase of 5 percent over the current
licensed power level. This request is in accordance with the generic
boiling water reactor (BWR) power uprate program established by the
General Electric Company (GE) and approved by the NRC staff in a letter
from W.T. Russell, NRC, to P.W. Marriott, GE, dated September 30, 1991.
Implementation of the proposed power uprate at Plant Hatch will result
in an increase of steam flow to approximately 106 percent of the
current value, but will not require changes to the basic fuel design.
Core reload design and fuel parameters will be modified as power uprate
is implemented to support the current 18-month reload cycle. The higher
power level will be achieved by expanding the power/flow map and
slightly increasing reactor vessel dome pressure. The maximum core flow
limit will not be increased over the pre-uprate value. Implementation
of this proposed power uprate will require minor modifications, such as
resetting of the safety relief setpoints, as well as calibrating plant
instrumentation to reflect the uprated power. Plant operating,
emergency, and other procedure changes will be made where necessary to
support uprated operation.
The proposed action involves NRC issuance of license amendments to
uprate the authorized power level by changing the Operating Licenses,
including Appendix A (Technical Specifications). Appendix B of the
Operating License (Environmental Technical Specifications) does not
require revision as a result of power uprate.
The Need for the Proposed Action
The proposed action would authorize GPC to increase the potential
electrical output of Plant Hatch by approximately 40 megawatts per unit
and thus would provide additional electrical power to service GPC's
grid.
Environmental Impacts of the Proposed Action
The ``Final Environmental Statement'' (FES) related to operation of
Plant Hatch Units 1 and 2 (Reference 6) evaluates the nonradiological
impact of operation at a maximum design reactor power level of 2537 MWt
per unit. By letter dated January 13, 1995 (Reference 1), GPC submitted
the proposed amendment to implement power uprate for Hatch Units 1 and
2 which is the subject of this environmental assessment. Enclosure 2 of
that submittal provided information on the noradiological environmental
aspects of the amendment request. Enclosure 4 was the Plant Hatch power
uprate licensing report (GE report NEDC-32405P) which provided
information on the radiological environmental impact of power uprate.
The proposed amendments allowing power uprate operation will not
have a significant impact on the environment and the change does not
constitute an unreviewed environmental question. The nonradiological
and radiological effects of the proposed action on the environment are
described below.
Nonradiological Environmental Assessment
Power uprate will not change the method of generating electricity
nor the method of handling any influents from the environment or
effluents to the environment. Therefore, no new or different types of
environmental impacts are expected.
The detailed evaluation presented below and in Reference 1
concludes that nonradiological parameters affected by power uprate will
remain within the bounding conditions cited in the FES, which concludes
that no significant environmental impact will result from operation of
Plant Hatch. This conclusion remains valid for power uprate.
The FES evaluated the nonradiological impact at a maximum design
reactor power level of 2537 MWt per unit (approximately 104 percent of
the current licensed power level). The parameters evaluated in the
Environmental Report and the subsequent FES (References 4 through 6)
were re-evaluated at 2558 MWt to determine whether the proposed change
is significant relative to adverse environmental impact. Table E2-1 of
Reference 1 provided a comparison of environmental-related operation
parameters at rated and uprated power. Both units at Plant Hatch
utilize a closed-loop circulating year system and forced air cooling
towers for dissipating heat from the main turbine condenser. Other
equipment is cooled by the plant service water (PSW) and residual heat
removal (RHR) service water systems. The cooling towers and service
water systems are operated in accordance with the requirements of the
National Pollutant Discharge Elimination System (NPDES) Permit No. GA
0004120, which expires October 31, 1997. No notification changes or
other action relative to the NPDES Permit are required.
[[Page 38594]]
The withdrawal of cooling water from the Altamaha River is expected
to increase slightly, primarily due to the increase in the evaporation
rate from the cooling towers. Emergency system flows are expected to
remain generally unchanged. Although increased heat loads are expected
for nonsafety-related loads, such as the main generator stator coolers,
hydrogen coolers, and exciter coolers, heat loads will remain within
the existing design heat loads of the service water systems.
The circulating water system design flow rate is the primary basis
for determining makeup water for the Plant Hatch cooling towers. Other
factors affecting tower makeup are tower performance and meteorological
conditions. Based on the review of cooling tower performance parameters
associated with power uprate, the design flow rate of the cooling
towers will not change. Makeup requirements may increase slightly due
to increased heat load on the towers and the associated increase in
evaporation. As discussed in Enclosure 2 of Reference 1, the increase
in makeup (withdrawal rate is expected to be approximately 5 percent or
500 gpm. This projected increase associated with the uprate is not
significant and is enveloped by the river water withdrawal rates
discussed in the FES and the rates approved under the current Georgia
Surface Water Withdrawal Permit for Plant Hatch. Intake canal velocity
will not be significantly affected. No measurable effects on fish
impingement or plankton entrainment are expected.
Changes in cooling tower blowdown rate and cooling tower chemistry
as a result of the uprate are not significant. Any changes in blowdown
rate and cooling tower cycles of concentration resulting from uprated
power operation are enveloped by the existing design criteria discussed
in FES.
Cooling tower drift does not increase as a result of the uprate
since the circulating water flow rate does not change. Cooling tower
blowdown temperature associated with power uprate operation increase
slightly (<1 deg.F), thereby producing a slight increase in river
discharge temperature. A review of the increase in the river discharge
temperature relative to the conclusions of the FES and thermal studies
required to support licensing of the plant indicates the slight
temperature increase is not significant.
The thermal plume characteristics are not expected to change
significantly as a result of power uprate. Circulating water and
service water flow rates remain unchanged. The discharge temperature to
the cooling towers should increase by no more than 1 deg.F due to
operation at power uprate conditions. The corresponding change in
discharge temperature at the river will not significantly impact the
size or characteristics of the thermal plume. Thermal plume studies
conducted during original licensing and the FES conclusions relative to
thermal impacts remain valid for the uprated condition.
No significant change in discharge flow rate, velocity, or chemical
composition will occur due to the proposed power uprate. Power uprate
does not impact the discharge characteristics upon which the NPDES
Permit is based. No notification, changes, or other actions relative to
the NPDES Permit are required.
No change in the groundwater withdrawal required to supply the
Hatch treatment plant or fire protection system will result from the
proposed uprate.
The evaluation also considered the flow rate required by the liquid
radwaste system (e.g., floor and equipment drains) due to the proposed
uprate. No significant change in liquid radwaste quantities or activity
levels which would increase the required radwaste dilution flow are
expected. Therefore, the impact on the environment from these systems
as a result of operation at the uprate power levels is not significant.
Plant operation at uprated power conditions will not affect current
noise levels. Major plant equipment is housed within structures located
on the plant site and is not a major contributor to surrounding noise
levels. Equipment, such as the main turbines/generators and the cooling
towers, will continue to operate at the current speed and noise level.
The generator step-up transformers will operate at an increased KVA
level; however, the overall noise level will not increase
significantly.
Thus, the proposed uprate will not result in any significant
environmental impact and is not an unreviewed environmental question.
In addition, no actions relative to the Environmental Technical
Specifications (ETS), NPDES permit or other environmental documents are
required.
Radiological Environmental Assessment
Georgia Power Company evaluated the impact of the proposed power
uprate amendment and concluded that the applicable regulatory
acceptance criteria relative to radiological environmental impacts will
continue to be satisfied for the uprated power conditions. Existing
Technical Specifications limits on radiological effluents will be
maintained. In conducting this evaluation, GPC considered the effect of
the higher power level on liquid radioactive wastes, gaseous
radioactive wastes, and radiation levels both in the plant and offsite
during both normal operation and post-accident.
Enclosure 4 of Reference 1 provides the power uprate safety
analyses report for Plant Hatch, as well as an assessment of the
radiological effects of power uprate operation during both normal and
postulated accident conditions. Sections 8.1 and 8.2 discuss the
potential effect of power uprate on the liquid and gaseous radwaste
systems. Sections 8.3, 8.4, and 8.5 discuss the potential effect of
power uprate on radiation sources within the plant and radiation levels
during normal and post-accident conditions. Section 4.4 discusses the
standby gas treatment system (SGTS). Section 9.2 presents the results
of the calculated whole body and thyroid doses at the exclusion area
boundary and the low population zone that might result from the
postulated design basis radiological accidents. All offsite doses
remain below established regulatory limits for power uprate operation.
The floor drain collector subsystem and the waste collector
subsystem both receive inputs from a variety of sources (e.g., leakage
from component cooling water system, reactor coolant system, condensate
and feedwater system, turbine, and plant cooling water system).
However, leakages from these systems are not expected to increase
significantly since the operating pressures of these systems are either
being maintained constant or are being increased only slightly due to
the proposed power uprate.
The largest source of liquid radioactive waste is from the backwash
of the condensate demineralizers. These demineralizers remove activated
corrosion products which are expected to increase proportionally to the
proposed power uprate. However, the total volume of processed waste is
not expected to increase significantly, since the only appreciable
increase in processed waste will be due to the slightly more frequent
cleaning of these demineralizers. Based on a review of plant effluent
reports and the slight increase expected due to the proposed power
uprate, GPC has concluded that the slight increase in the processing of
liquid radioactive wastes will not have a significant increase in
environment impact and that requirements of 10 CFR part 20 and 10 CFR
part 50, Appendix I, will continue to be met.
[[Page 38595]]
Gaseous radioactive effluents are produced during both normal
operation and abnormal operation occurrences. These effluents are
collected, controlled, processed, stored, and disposed of by the
gaseous radioactive waste management systems which include the various
building ventilation systems, the off gas system, and the SGTS. The
concentration of radioactive gaseous effluents released through the
building ventilation systems during normal operation is not expected to
increase significantly due to the proposed power uprate since the
amount of fission products released into the reactor coolant (and
subsequently into the building atmosphere) depends on the number and
nature of fuel rod defects and is not dependent on reactor power level.
The concentration of activation products contained in the reactor
coolant is expected to remain unchanged, since the linear increase in
the production of these activation products will be offset by the
linear increase in steaming rate. Therefore, based on its review of the
various building ventilation systems, GPC has concluded that there will
not be a significant adverse effect on airborne radioactive effluents
as a result of the proposed power uprate.
Radiolysis of the reactor coolant causes the formation of hydrogen
and oxygen, the quantities of which increase linearly with core power.
These additional quantities of hydrogen and oxygen would increase the
flow to the recombiners by 5 percent during uprated power conditions.
However, the operational increases in hydrogen and oxygen remain within
the design capacity of the system.
The SGTS is designed to minimize offsite and control room radiation
dose rates during venting and purging of both the primary and secondary
containment atmospheres under accident or abnormal conditions. This is
accomplished by maintaining the secondary containment at a slightly
negative pressure with respect to the outside atmosphere and
discharging the secondary containment atmosphere through high-
efficiency particulate air (HEPA) filters and charcoal absorbers. The
SGTS charcoal absorbers are designed for a charcoal loading capacity of
2.5 mgI/gC for the 30-day loss-of-coolant accident (LOCA) scenario. The
proposed power uprate will increase the post-LOCA iodine loading by 5
percent; however, the charcoal loading will remain within the 2.5 mgI/
gC design limit. Therefore, there will be no significant increase in
environmental impact.
Georgia Power Company evaluated the effects of the power uprate on
in-plant radiation levels for Plant Hatch during both normal operation
and post-accident. GPC's conclusions are that radiation levels during
both normal operation and post-accident may increase slightly
(approximately proportional to the increase in power level). The slight
increases in in-plant radiation levels expected due to the proposed
power uprate should not affect radiation zoning or shielding
requirements. Individual worker occupational exposures will be
maintained within acceptable limits by the existing as low as
reasonably achievable (ALARA) program which GPC uses to control access
to radiation areas. Therefore, the slightly increased in-plant
radiation levels will not have a significant environmental impact.
The offsite doses associated with normal operation are not
significantly affected by operation at the proposed uprated power level
and are expected to remain well within the limits of 10 CFR part 20 and
10 CFR part 50, Appendix I. Existing Technical Specifications limits
will not be changed due to uprate. Therefore, offsite doses due to
power uprate conditions will not result in a significant environmental
impact.
Georgia Power Company performed does evaluations for design basis
accidents at or above 102% of the uprated power level and reported
these results in Reference 1. The offsite doses remain below regulatory
limits and the increase due to power uprate is 5% or less.
The NRC staff agrees with GPC's assessment of the radiological
effects of the proposed action.
Alternatives to the Proposed Action
Since the Commission has concluded there is no measurable
environmental impact associated with the proposed action, any
alternatives with equal or greater environmental impact need not be
evaluated. As an alternative to the proposed action, the staff
considered denial of the proposed action. Denial of the application
would result in no change in current environmental impacts of plant
operation, but would restrict operation of Plant Hatch to the currently
licensed power level. The environmental impacts of the proposed action
and the alternative action are similar.
Alternative Use of Resources
This action does not involve the use of any resources not
previously considered in the Final Environmental Statement for Plant
Hatch.
Agencies and Persons Consulted
In accordance with its stated policy, on July 20, 1995, the staff
consulted with the Georgia State official, James L. Setser of the
Environmental Protection Division, Department of Natural Resources,
regarding the environmental impact of the proposed action. The State
official had no comments.
Finding of No Significant Impact
Based upon the environmental assessment, the Commission concludes
that the proposed action will not have a significant effect on the
quality of the human environment. Accordingly, the Commission has
determined not to prepare an environmental impact statement for the
proposed action.
For further details with respect to the proposed action, see the
licensee's letter dated January 13, 1995, as supplemented by letters
dated April 5 and June 20, 1995, which are available for public
inspection at the Commission's Public Document Room, The Gelman
Building, 2120 L Street, NW., Washington, DC, and at the local public
document room located at the Appling County Public Library, 301 City
Hall Drive, Baxley, Georgia.
References
1. Georgia Power Company HL-4724, J. T. Beckham, Jr., to NRC,
``Power Uprate Operation,'' dated January 13, 1995.
2. Georgia Power Company HL-4812, J. T. Beckham, Jr., to NRC,
``Response to Request for Additional Information--Power Uprate
Submittal,'' dated April 5, 1995.
3. Federal Register Vol. 60, No. 41, ``Niagara Mohawk Corporation;
Environmental Assessment and Finding of No Significant Impact,'' dated
March 2, 1995.
4. Georgia Power Company ``Final Environmental Statement for Edwin
I. Hatch Nuclear Plant Units 1 and 2,'' October 1972.
5. Georgia Power Company Edwin I. Hatch Nuclear Plant--Unit 2
Environmental Report, Operating License Stage, June 1975.
6. Georgia Power Company ``NUREG-0417,'' Final Environmental
Statement Related to Operation of Edwin I. Hatch Nuclear Plant Unit No.
2, March 1978.
Dated at Rockville, Maryland, this 21st day of July 1995.
For the Nuclear Regulatory Commission.
Herbert N. Berkow,
Director, Project Directorate II-2, Division of Reactor Projects--I/II,
Office of Nuclear Reactor Regulation.
[FR Doc. 95-18444 Filed 7-26-95; 8:45 am]
BILLING CODE 7590-01-M