DEPARTMENT OF DEFENSE
Department of the Navy
Record of Decision for the Lease of Fleet and Industrial Supply
Center Property to the Port of Oakland for Development of Intermodal
Rail Facilities and Maritime Cargo-Related Tenant Uses at Oakland, CA
Pursuant to section 102(2) of the National Environmental Policy Act
(NEPA) of 1969 and the Council on Environmental Quality Regulations on
Implementing NEPA Procedures (40 CFR 1500-1508), the Department of the
Navy announces its decision to implement the preferred alternative
presented in the Final Environmental Impact Report/Environmental Impact
Statement (FEIR/EIS) for the Lease of Fleet and Industrial Supply
Center property to the Port of Oakland for development of intermodal
rail facilities and maritime-related tenant uses at Oakland,
California. This decision fulfills Navy responsibility in compliance
with NEPA process. The Port of Oakland will make its decision in
compliance with the California Environmental Quality Act (CEQA).
In response to 10 U.S.C. 2667 and Public Law 102-484 (Section
2834(b)) of the Fiscal Year 1993 Defense Authorization Act, as amended,
the Navy is authorized to lease to the Port of Oakland, real property,
together with improvements thereon, at the Fleet and Industrial Supply
Center, Oakland (FISCO), Alameda County, California.
The action is granting of a lease of up to 220 acres of the FISC
Oakland property to the Port of Oakland for expansion of their existing
intermodal rail facilities and maritime-related tenant activities. In
addition, the proposed development includes another 87 acres of the
Port of Oakland's and Union Pacific Railroad's properties directly
south of the Supply Center. The Port of Oakland proposes to establish
maritime and transportation activities and to redevelop the site for
port operations in support of the Oakland Harbor Area.
The 307 total acres have been divided into six areas for planning
purposes. Development of Area A (83 acres of the Center) would include
demolition of most of the existing facilities and construction of new
intermodal railtracks and associated appurtenances, such as straddle
carrier runways and container staging support areas. Development of
Area B (40 acres of the Center) would include demolition of existing
facilities and construction of new container transfer and storage areas
and a transloading facility. The transloading facility would be a
narrow, dock-high platform with rail tracks on one side and truck
spaces on the other side. Development of Area C (67 acres of the
Center) would include demolition of some existing facilities,
construction of an entrance for the intermodal rail facility (including
a gatehouse and maintenance and repair building) and maintenance of
existing warehouses for continued warehousing and/or distribution uses.
Development of Areas D and E (87 acres of Port and Union Pacific
Railroad properties) would include demolition of existing facilities
and construction of a new terminal expansion area to be used for
development of Area F (20 to 30 acres of the Center) may be included in
the lease, depending on the results of discussions between the Port of
Oakland and the Center. If the agreement is reached, the additional
area would be used for warehousing and/or distribution.
The alternatives, including the preferred alternative, may be
categorized as four development alternatives and the ``no action''
alternative. The development alternatives vary from extensive
[[Page 28589]] intermodal rail facilities to increased maritime
related/industrial tenant activities. The lease and development
alternatives would introduce major changes in scale and character of
the Historic District at FISCO. In compliance with Section 106 of the
National Historic Preservation Act (16 U.S.C. Section 470(f)), the Navy
has consulted the State Historic Preservation Officer, and a Memorandum
of Agreement has been reached regarding mitigation for adverse effects.
The action will result in net air pollution emissions that will be
below established threshold levels. A record of non-applicability for
the proposed action has been prepared pursuant to 40 CFR Parts 51 and
93 and no Clean Air Act Conformity determination is necessary. There
will not be any disproportionately high and adverse human health or
environmental effects from the action on minority and low-income
populations.
A Draft EIR/EIS was prepared by the Port and the Navy, and
distributed to agencies and officials of federal, state and local
governments, citizen groups and associates, public libraries, and other
interested parties for review and comment. A public hearing to inform
the public of the DEIR/EIS findings and to solicit comments was held on
September 19, 1994. Public comments concentrated on existing adverse
commercial truck traffic conditions in the West Oakland neighborhood.
The Port of Oakland has been working with community-based organizations
to arrive at appropriate and reasonable measures to ease these existing
conditions. Copies of all comments received were included in the Final
EIR/EIS. Six sets of written comments were received in response to the
FEIR/EIS during the 30-day public review period. Two sets of these
comments focused on technical questions pertaining to FISCO biological
resources, and the asbestos survey at the site. The organizations
making these comments will be directed to the appropriate sections of
the FEIR/EIS that addressed their concerns. The principal emphasis of
the remaining four sets of comments was regarding the action and its
relationship to the Port's broader long-term expansion plan, including
associated impacts--especially from increased commercial truck traffic.
As part of the Port's ``Vision 2000'' long-term conceptual plan, the
Port is investigating the feasibility of leasing an additional 200
acres of FISCO property for future expansion and development of
maritime and rail facilities beyond the action. The Port will prepare a
separate or supplemental NEPA/CEQA document that will suitably evaluate
the environmental impacts of such future expansion plan, as components
of the plan become reasonably foreseeable.
Questions regarding the Draft and Final Environmental Impact
Report/Environmental Impact Statement prepared for this action may be
directed to: (1) Mr. Raymond Chiang, Environmental Planning Branch,
Engineering Field Activity West, Naval Facilities Engineering Command,
P.O. Box 727, San Bruno, California 94066, FAX (415) 244-3737 for
questions pertaining to the Navy action; and (2) Mr. Charles Schwarz,
Environmental Department, Port of Oakland, 530 Water Street, Oakland,
California 94607, FAX (510) 465-3755 for questions pertaining to the
Port of Oakland action.
Dated: May 25, 1995
Robert B. Pirie, Jr.,
Assistant Secretary of the Navy (Installation and Environment).
[FR Doc. 95-13429 Filed 5-31-95; 8:45 am]
BILLING CODE 3810-FF-M