Intent To Prepare a Draft Environmental Impact Statement (DEIS) for the Arroyo Pasajero Investigation, California
Federal RegisterMar 3, 1994
Ask Donna
What actually matters in this document.
Text
DEPARTMENT OF DEFENSE
Department of the Army
Corps of Engineers
Intent To Prepare a Draft Environmental Impact Statement (DEIS)
for the Arroyo Pasajero Investigation, California
AGENCY: U.S. Army Corps of Engineers, DoD.
ACTION: Notice of intent.
-----------------------------------------------------------------------
SUMMARY: The action being taken is a feasibility investigation to
identify and assess potential measures to provide additional flood
protection for the study area including the cities of Coalinga and
Huron, Lemoore Naval Air Station, surrounding agricultural land, and
the California Aqueduct, and to prevent sediment and water contaminated
with asbestos from entering the aqueduct. The feasibility investigation
area includes the Arroyo Pasajero basin in southwest Fresno County.
Measures to be investigated include enlarging the retention basin west
of the aqueduct, constructing an overchute structure, upstream
reservoirs, conducting local levee and channel work, and implementing
an asbestos hazard abatement treatment.
FOR FURTHER INFORMATION CONTACT: Questions regarding this DEIS should
be addressed to Mr. Robert Koenigs, Planning Division, Corps of
Engineers, 1325 J Street, Sacramento, California, 95814-2922, telephone
(916) 557-6712.
SUPPLEMENTARY INFORMATION:
Proposed Action
The Corps of Engineers, and a non-Federal sponsor (California State
Department of Water Resources) are conducting a feasibility
investigation to identify and assess alternative measures for providing
additional flood protection to the cities of Coalinga and Huron, to
Lemoore Naval Air Station, to the California Aqueduct, and to
agricultural lands, and for preventing sediment and water contaminated
with asbestos from entering the aqueduct. In 1958 and 1969 major
flooding occurred in the area causing over $5 million in property loss.
Alternatives
The feasibility report and EIS will address the full range of
alternatives discussed in the 1992 reconnaissance report on the basin
including evaluation of plans to:
(1) Enlarge the retention basin west of the California Aqueduct.
(2) Provide an overchute structure over the aqueduct or an aqueduct
canal siphon and provide a retention basin on the east side of the
aqueduct.
(3) Construct a channel from the aqueduct and/or the retention
basin to a natural channel at the valley trough. Also included will be
an evaluation of upstream reservoirs, local levees and channel work,
the potential for groundwater injection, potential water treatment
methods to permit Arroyo Pasajero runoff into the aqueduct, special
asbestos hazard abatement treatment for construction, operation and
maintenance requirements for any constructed facilities, and
environmental mitigation and restoration. The No-Action alternative
will also be explored during the study.
Scoping Process
a. A notice of initiation for the Arroyo Pasajero Investigation
will be sent to public agencies, organizations, and individuals in the
study area. This notice will invite those parties to participate in the
scoping process for this investigation. This will include an
opportunity for the public to identify the significant flood control
problems, potential solutions, and resources within the study area
which may be affected by a project. Responses to the notice, will be
used in determining the scope of the feasibility report and
accompanying environmental impact statement.
b. Significant topics that will be discussed in the DEIS include
the hydrology of the basin; planning objectives; alternatives analysis;
impacts on fish and wildlife resources, endangered species, vegetation,
water quality, air quality, esthetics, cultural resources, and
cumulative impacts of related projects in the study area. The potential
for contamination of air and water resources by naturally occurring
asbestos will also be addressed.
c. The U.S. Fish and Wildlife Service will provide a Fish and
Wildlife Coordination Act Report to accompany the DEIS.
d. A 45-day review period will be allowed for all interested
agencies and individuals to review and comment on the DEIS. A public
hearing will be held during the comment period. All interested persons
are encouraged to respond to this notice and to provide scoping
comments and a current address if they wish to be contacted about the
DEIS.
Public Meeting
A public scoping meeting has been scheduled for Tuesday, March 29,
1994 at 7 p.m. in the Coalinga area to initiate coordination with local
governmental representatives, elected officials, State and Federal
agencies, special interest groups, and the general public.
Availability
The DEIS is scheduled to be available for public review and comment
in mid 1997.
Gregory D. Showalter,
Alternative Army Federal Register Liaison Officer.
[FR Doc. 94-4784 Filed 3-2-94; 8:45 am]
BILLING CODE 3710-08-M
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.