Notice of Lodging of Consent Decree Pursuant to Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA)
Federal RegisterDec 15, 1994
Ask Donna
What actually matters in this document.
Text
DEPARTMENT OF JUSTICE
Notice of Lodging of Consent Decree Pursuant to Comprehensive
Environmental Response, Compensation, and Liability Act (CERCLA)
In accordance with Section 122(d) of the Comprehensive
Environmental Response, Compensation, and Liability Act, as amended
(CERCLA), 42 U.S.C. Sec. 9622(d), and the policy of the United States
Department of Justice, as provided in 28 CFR 50.7, notice is hereby
given that on November 21, 1994, a proposed Consent Decree in United
States v. Florida Steel Corporation, Civil No. 94-14241, was lodged
with the United States District Court for the Southern District of
Florida. From 1970 until 1982, Florida Steel operated a steel mill and
metal recycling facility on the Site, which is located near Indiantown,
Florida. As a result of these operations, the Site is contaminated with
heavy metals, PCB's and other hazardous substances. The proposed
Consent Decree addresses Operable Unit Two of the Site, which concerns
contaminated groundwater and wetland sediments. Pursuant to Sections
106 and 107(a) of CERCLA, 42 U.S.C. Secs. 9606 and 9607(a), the
Complaint in this action seeks defendant's performance of the remedy
selected by EPA for Operable Unit Two, as well as recovery of all
previously unreinbursed response costs incurred by the United States at
the Site, and of all future and oversight costs to be incurred by the
United States in connection with Operable Unit Two.
Florida Steel has agreed in the proposed Consent Decree to (1)
perform the remedy selected by EPA for Operable Unit Two, at a total
estimated cost of $1.2 million, and (2) reimburse the United States for
all of its previously unreimbursed response costs incurred at the Site,
and for all of its future response and oversight costs incurred in
connection with Operable Unit Two. The selected remedy for Operable
Unit Two requires (1) pumping and treatment of contaminated
groundwater, and (2) excavation of contaminated wetland sediments and
solidification of those sediments in an on-Site landfill.
The Department of Justice will receive for a period of thirty (30)
days from the date of this publication comments concerning the proposed
Consent Decree. Comments should be addressed to the Assistant Attorney
General, Environment and Natural Resources Division, U.S. Department of
Justice, P.O. Box 7611, Ben Franklin Station, Washington, D.C., 20044,
and should refer to United States v. Florida Steel Corporation, D.J.
Ref. 90-11-2-833A (Operable Unit Two).
The proposed Consent Decree may be examined at any of the following
offices: (1) The Office of the United States Attorney for the Southern
District of Florida, 99 NE. 4th Street, suite 300, Miami, Florida; (2)
the U.S. Environmental Protection Agency, Region 4, 345 Courtland
Street, NE., Atlanta, Georgia; and (3) the Consent Decree Library, 1120
G Street, NW., 4th Floor, Washington, DC 20005, (202) 624-0892. Copies
of the proposed Decree may be obtained by mail from the Consent Decree
Library, 1120 G Street, NW., 4th Floor, Washington, DC 20005. For a
copy of the Consent Decree with attachments (Record of Statement of
Work and Site map) please enclose a check for $37.50 ($.25 per page
reproduction charge) payable to ``Consent Decree Library.'' For a copy
of the Consent Decree without those attachments please enclose a check
for $19.00 ($.25 per page reproduction charge) payable to ``Consent
Decree Library.''
Bruce S. Gelber,
Acting Chief, Environmental Enforcement Section, Environment & Natural
Resources Division.
[FR Doc. 94-30830 Filed 12-14-94; 8:45 am]
BILLING CODE 4410-01-M
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.