DEPARTMENT OF ENERGY
Western Area Power Administration
Proposed Principles of Integrated Resource Planning for Use in
Resource Acquisition and Transmission Planning
AGENCY: Western Area Power Administration, DOE.
ACTION: Notice of proposed principles and request for public comments.
-----------------------------------------------------------------------
SUMMARY: Western Area Power Administration (Western) proposes to use
principles of integrated resource planning (IRP) in its acquisition of
resources (supply-side and demand-side) and in its transmission
planning program. Western has developed the proposal contained in this
notice for public consideration. After considering public comment on
this proposal, Western will adopt final principles of IRP as the policy
under which project-specific resource acquisition and transmission
planning procedures will be developed. These project-specific
procedures will be developed through separate public processes.
DATES: Western seeks comments on the proposed principles outlined in
this notice. To be considered, comments need to be received by March 7,
1995.
In addition to publication in the Federal Register, Western is
mailing this notice to parties it has identified as likely to be
interested, including those who have expressed an interest in the
public involvement processes for Western's power marketing and
transmission planning programs. Western will also send information on
these principles to those who request it.
At this time, Western plans to hold one public information and
comment meeting to provide information about and to accept public
comment on these proposed principles. This public meeting will be held
in Denver, Colorado, at 1 p.m., January 12, 1995, at the Stapleton
Plaza Hotel, 3333 Quebec Street. Additional public meetings at other
locations will be considered. Written comments will also be accepted. A
summary of comments received and Western's responses will be provided
in a subsequent Federal Register notice and to parties indicating they
wish to continue receiving information about this process.
FURTHER INFORMATION: To receive information on these principles, and/or
to make requests to receive subsequent mailings on this process,
contact: Mr. Michael S. Cowan, Director, Division of Power Operations
and Resources, Western Area Power Administration, P.O. Box 3402,
Golden, CO 80401-0098, (303) 275-1630.
Background
On August 9, 1994, Western provided notice of its proposed Energy
Planning and Management Program (Program), 59 FR 40543, concerning
requirements for Western's customers to undertake integrated resource
planning consistent with the statutory requirements of the Energy
Policy Act of 1992. In that notice, Western committed to develop and
use principles of IRP in its resource acquisition and transmission
planning programs. The separate public process to develop IRP
principles for Western's programs begins with publication of these
draft principles.
The draft principles outlined in this notice differ from those
proposed for Western's customers. Western's resource aquisitions are
primarily short-term purchases of supplemental resources to firm
variable hydropower generation, not aquisition's of resources to meet
long-term load growth through the principles set forth in section 114
of the Energy Policy Act of 1992. The principles have also been
modified so that they can be applied to Western's transmission planning
process, which does not deal with new generation resources, only new or
upgraded transmission facilities.
Western is currently involved in other public processes that can
have an impact on future purchase power requirements. These processes
are the Replacement Resources Process, pursuant to the Grand Canyon
Protection Act of 1992 (Public Law 102-575); the Central Valley Project
2004 Power Marketing Environmental Impact Statement (EIS); and the Salt
Lake City Area Integrated Projects Power Marketing EIS. The principles
being developed under this public process will be applied when
acquiring resources related to the decisions from these other public
processes. These principles will serve as the policy under which
specific procedures are developed as each project identifies the need
to acquire resources or increase Western's transmission capability.
Scope
The proposed formal principles of IRP would apply specifically to:
1. Resource acquisitions involving a commitment to purchase a
resource continuously or a commitment to make recurring purchases.
Normally, formal principles would not be applied to unpredictable
seasonal purchases, day-to-day economy energy purchases, and other
short-term transactions.
2. New or upgraded transmission system construction with a 1995
total cost estimate in excess of $5 million for an individual project.
This 1995 cost level would be adjusted each year using the construction
cost index.
Where practicable, principles of IRP will also be applied
informally to other Western transmission projects and/or resource
acquisitions.
Proposed Principles of Integrated Resource Planning
I. Resource Acquisition Principles: Western's resource acquisition
activities would be determined by project-specific power marketing
plans, hydropower production capability, and the application of the
following proposed principles of IRP:
1. Western will consider a full range of resource options, both
supply-side and demand-side, as well as renewable resource options.
2. On a project-by-project basis, Western, in concert with
interested stakeholders, will develop (1) methods and procedures to
determine the need for resource acquisition and (2) criteria to be used
in evaluating power resource alternatives.
3. Evaluation criteria will address cost, environmental impact,
dependability, dispatchability, risk, diversity, and the ability to
verify demand-side alternatives. Evaluation criteria will be reviewed
as the need for resources changes or when long-term commitments to
purchase power expire.
4. Evaluation criteria will be consistent with Western's power
marketing policy, which states that Federal power is to be marketed in
such a manner as to encourage the most widespread use thereof at the
lowest possible rates to consumers consistent with sound business
principles. The policy, found in Delegation Order No. 0204-108 (58 FR
59716, November 10, 1993), is derived from section 5 of the Flood
Control Act of 1944, 16 U.S.C. 825s.
5. Resource acquisition planning will be consistent with power
marketing plans and associated contractual obligations.
6. Resource acquisition decisions will be documented and made
available to Western's power customers and the public.
II. Transmission Planning Principles: Western's transmission
planning is conducted to assess the capability of the Federal
transmission system to provide adequate and reliable electric service
to its customers and the interconnected power grid. The principles of
IRP that will apply to Western's transmission planning are as follows:
1. Western will conduct early and wide public involvement to
confirm the purpose and need of a proposed transmission project.
Western proposes that a public meeting be held early in the planning
process once the need for system modifications has been identified and
prior to start of the National Environmental Policy Act (NEPA) process.
2. At the public meeting, Western will describe the need to be met
and seek comments on alternative ways to address the need, including
demand-side management, new construction, or upgrade of existing
facilities.
3. Western will notify interested parties, including power
customers, residents of the area, environmental groups, various
resource suppliers including renewable generation entities, and other
transmission utilities in the area, as well as other participants in
the project if it is a joint project.
4. Alternatives that are feasible will be evaluated for cost,
general environmental impacts, and system reliability concerns in
coordination with interested parties.
5. The results of this evaluation will be made available to
Western's power customers and the public.
Transmission facilities needed for reliability will be based on
mitigating problems related to power system operations or replacing
unsafe, aged, worn out, or inefficient equipment.
Western is committed to join the Western Regional Transmission
Association and has joined the Southwest Regional Transmission
Association (SWRTA). Both groups will promote coordinated planning and
efficient use of transmission capacity and will provide another means
for involvement by Western's customers. As appropriate, Western can
invite other interested parties to attend SWRTA meetings as guests of
Western. It is anticipated that some form of regional transmission
group will be established in the Mid-continent Area Power Pool. This
will also facilitate public involvement in considering Western's future
transmission needs.
Public Process
The public process to determine the principles of integrated
resource planning that Western will incorporate into its resource
acquisition and transmission planning processes begins with publication
of this notice.
Comments on these proposed principles are being sought during a 90-
day comment period. Following this comment period, the principles to be
adopted will be published in the Federal Register. This public process
ends with publication of final principles in the Federal Register.
Final principles will be effective 30 days after publication.
Environmental Evaluation
Western is seeking comment on the IRP principles outlined in this
notice through a public process. Methods, procedures, and criteria for
implementing these principles have yet to be developed and will be
project-specific. Western is committed to initiating an appropriate
public process under NEPA and its implementing regulations for these
project-specific actions at the earliest possible time. The potential
environmental effects of the methods, procedures, and criteria will be
evaluated in addition to analyzing the effects of the acquisition of
resources in these subsequent processes.
Determination Under Executive Order 12866
DOE has determined this is not a significant regulatory action
because it does not meet the criteria of Executive Order 12866, 58 FR
51735. Western has an exemption from centralized regulatory review
under Executive Order 12866; accordingly, no clearance of this notice
by the Office of Management and Budget is required.
Issued at Golden, Colorado, November 10, 1994.
J.M. Shafer,
Administrator.
[FR Doc. 94-29706 Filed 12-5-94; 8:45 am]
BILLING CODE 6450-01-P
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.