Altresco Pittsfield, L.P., et al.; Electric Rate and Corporate Regulation Filings

Federal RegisterOct 31, 1994

Ask Donna

What actually matters in this document.

Text

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. EG95-4-000, et al.]

Altresco Pittsfield, L.P., et al.; Electric Rate and Corporate

Regulation Filings

October 24, 1994.

Take notice that the following filings have been made with the

Commission:

1. Altresco Pittsfield, L.P.

[Docket No. EG95-4-000]

On October 11, 1994, Altresco Pittsfield, L.P. (``Altresco''), with

its address at One Bowdoin Square, Boston MA 02114, filed with the

Federal Energy Regulatory Commission (the ``Commission'') an

application for determination of exempt wholesale generator status

pursuant to part 365 of the Commission's regulations.

Altresco is the lessee and operator of an approximately 165 MW

(net) gas-fired cogeneration facility (the ``Facility'') located in

Pittsfield, Massachusetts. The Facility commenced commercial operation

in September, 1990. Altresco will sell all of the electric energy

produced by the Facility at wholesale. Electric energy produced by the

Facility is sold to New England Power Company, Commonwealth Electric

Company and Cambridge Electric Light Company.

Comment date: November 14, 1994, in accordance with Standard

Paragraph E at the end of this notice. The Commission will limit its

consideration of comments to those that concern the adequacy or

accuracy of the application.

2. Nevada Power Company

[Docket No. EL92-41-002]

Take notice that on September 30, 1994, Nevada Power Company

tendered for filing a revised copy of its refund report in the above-

referenced docket.

Comment date: November 7, 1994, in accordance with Standard

Paragraph E at the end of this notice.

3. Midwest Power Systems, Inc.

[Docket No. ER94-985-000]

Take notice that on October 5, 1994, Midwest Power Systems, Inc.

tendered for filing Amendment No. 2 to the Electric Interchange and

Interconnection Agreement with Indianola Waterworks.

Comment date: November 7, 1994, in accordance with Standard

Paragraph E at the end of this notice.

4. New England Power Company

[Docket No. ER94-1155-000]

Take notice that on October 17, 1994, New England Power Company

tendered for filing an amendment to its April 14, 1994, filing in the

above-referenced docket.

Comment date: November 7, 1994, in accordance with Standard

Paragraph E at the end of this notice.

5. LG&E Power Marketing, Inc.

[Docket No. ER94-1188-002]

Take notice that on October 11, 1994, LG&E Power Marketing, Inc.

(LG&E) filed certain information as required by the Commission's August

19, 1994, order in Docket No. ER94-1188-000. Copies of LG&G's

informational filing are on file with the Commission and are available

for public inspection.

6. Camelot Energy Services

[Docket No. ER94-1457-001]

Take notice that on October 11, 1994, Camelot Energy Services (CES)

filed certain information as required by the Commission's September 30,

1994, letter order in Docket No. ER94-1457-000. Copies of CES's

informational filing are on file with the Commission and are available

for public inspection.

7. Central Maine Power Company

[Docket No. ER94-1669-000]

Take notice that on October 17, 1994, Central Maine Power Company

(CMP), tendered for filing supplemental information in support of a

Power Purchase Agreement between CMP and Unnamed Subsidiary, under

which CMP will purchase and Subsidiary will sell all of the energy and

capacity from a 32 MW biomass-fueled generating facility located in the

Town of Fort Fairfield, Maine. CMP now provides supplemental

information containing a formula for determining the Capacity Charge

component of the rate.

Comment date: November 7, 1994, in accordance with Standard

Paragraph E at the end of this notice.

8. Virginia Electric and Power Company

[Docket No. ER95-37-000]

Take notice that on October 14, 1994, Virginia Electric and Power

Company (Virginia Power) tendered for filing a Service Agreement

between AES Power, Inc. and Virginia Power, dated September 27, 1994,

under the Power Sales Tariff to Eligible Purchasers dated May 27, 1994.

Under the tendered Service Agreement Virginia Power agrees to provide

services to AES Power, Inc. under the rates, terms and conditions of

the Power Sales Tariff as agreed by the parties pursuant to the terms

of the applicable Service Schedules included in the Power Sales Tariff.

Copies of the filing were served upon the Virginia State

Corporation Commission and the North Carolina Utilities Commission.

Comment date: November 7, 1994, in accordance with Standard

Paragraph E at the end of this notice.

9. Virginia Electric and Power Company

[Docket No. ER95-38-000]

Take notice that on October 14, 1994, Virginia Electric and Power

Company (Virginia Power) tendered for filing a Service Agreement

between Ohio Edison and Virginia Power, dated September 20, 1994, under

the Power Sales Tariff to Eligible Purchasers dated May 27, 1994. Under

the tendered Service Agreement Virginia Power agrees to provide

services to Ohio Edison under the rates, terms and conditions of the

Power Sales Tariff as agreed by the parties pursuant to the terms of

the applicable Service Schedules included in the Power Sales Tariff.

Copies of the filing were served upon the Virginia State

Corporation Commission and the North Carolina Utilities Commission.

Comment date: November 7, 1994, in accordance with Standard

Paragraph E at the end of this notice.

10. Douglas M. Costle

[Docket No. ID-2855-000]

Take notice that on October 11, 1994, Douglas M. Costle (Applicant)

tendered for filing an application under section 305(b) of the Federal

Power Act to hold the following positions:

Director--Niagara Mohawk Power Corporation

Director--Air & Water Technologies Corporation

Comment date: November 10, 1994, in accordance with Standard

Paragraph E at the end of this notice.

Standard Paragraphs

E. Any person desiring to be heard or to protest said filing should

file a motion to intervene or protest with the Federal Energy

Regulatory Commission, 825 North Capitol Street, N.E., Washington, D.C.

20426, in accordance with Rules 211 and 214 of the Commission's Rules

of Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such

motions or protests should be filed on or before the comment date.

Protests will be considered by the Commission in determining the

appropriate action to be taken, but will not serve to make protestants

parties to the proceeding. Any person wishing to become a party must

file a motion to intervene. Copies of this filing are on file with the

Commission and are available for public inspection.

Lois D. Cashell,

Secretary.

[FR Doc. 94-26862 Filed 10-28-94; 8:45 am]

BILLING CODE 6717-01-P