SUMMARY: The Stikine and Chatham Areas of the USDA Forest Service
propose to harvest 123 million board feet (MMBF) of timber volume (net
sawlog) from the Port Houghton/Cape Fanshaw area of the Tongass
National Forest, and to construct 84.2 miles of road and one log
transfer facility (LTF). The timber would be harvested from 94 units
covering 5,860 acres. The harvest units were selected from a unit pool
of 186 units containing a total of 225 MMBF of timber volume (net
sawlog) over 10,904 acres. The roads associated with the proposed
action were selected from a road pool of 174 miles for the entire
project area. The proposed action would offer timber in one or more
sales. (A map of the unit pool, the proposed action, and roads is
available from the address provided.)
The project area includes Value Comparison Units (VCUs) 79 through
89 on the Mainland in southeast Alaska, encompassing approximately
193,000 acres. VCUs 80-89 have been allocated by the Tongass Land
Management Plan to Land Use Designation (LUD) IV, emphasizing primarily
commodity or market resources. VCU 79 has been allocated to LUD III,
emphasizing a variety of uses, both commodity and amenity, to provide
the greatest combination of benefits.
The purpose of this project is to provide 110 to 125 MMBF of timber
for harvest according to direction described in the Tongass Land
Management Plan, to meet the Federal obligation to make timber volume
available for harvest by timber operators, and to improve the timber
productivity of the project area by harvesting mature stands of timber
and replacing them with faster growing stands of second-growth timber.
The decision to be made is whether to make timber available for
harvest and improve timber productivity in the Port Houghton/Cape
Fanshaw Project area while also providing a combination of recreation,
fish, water, and wildlife for the resource uses of society now and into
the future. This decision will be made by Abigail R. Kimbell, Forest
Supervisor of the Stikine Area.
If timber is made available for harvest, the Forest Supervisor will
also decide (a) the volume of timber to make available, (b) the
location and design of the timber harvest units and log transfer
facilities, (c) the location and design of associated mainline and
local road corridors, and (d) appropriate mitigation measures for all
alternatives in the project area.
EFFECTIVE DATE: Public scoping will begin in September 1994 and will
continue over the life of the analysis. The Draft EIS is scheduled for
publication in June 1995 and the Final EIS in January 1996. Written
comments concerning this proposed action should be received within 30
days of the date of publication of this Notice in the Federal Register,
estimated to be September 16th.
FOR FURTHER INFORMATION CONTACT:
The Port Houghton/Cape Fanshaw analysis is being conducted by
Parametrix, Inc. under contract to the Stikine and Chatham Areas of the
Tongass National Forest. Questions and written comments and suggestions
concerning the analysis should be sent to Pamela Gunther, Team Leader,
Parametrix Inc., 5808 Lake Washington Blvd N.E., Kirkland, WA 98033,
phone (206) 822-8880, fax (206) 889-8808.
SUPPLEMENTARY INFORMATION: A public scoping letter will be sent to all
persons indicating an interest in the project by responding to the
Stikine Area Project Schedule or Chatham Area Schedule of Proposed
Actions, or who otherwise notify the Stikine or Chatham Areas that they
are interested in the Port Houghton/Cape Fanshaw Timber Harvest
project. Public scoping meetings will be scheduled during the last week
in September in the communities of Wrangell, Kake, Petersburg, Juneau,
and Hobart Bay.
The EIS will evaluate a number of timber harvest alternatives
ranging from a no-action alternative to harvesting 110 to 125 MMBF of
timber. Action-alternatives are likely to vary according to volume of
timber (110-125 MMBF), the amount and location of roads, the number and
location of log transfer facilities, the number and location of harvest
units, and the silvicultural methods applied to each unit. Each action
alternative will be designed by selecting units and roads from the unit
pool and road pool, and each alternative will fulfill the purpose and
need for the project and will respond to at least one of the
significant issues.
Preliminary issues include:
1. Soils: Portions of the project area are mapped as rough
mountainous land characterized by steep rocky slopes, icefields, and
glaciers. High soil hazard classes also occur in the project area. How
will the alternatives be designed to protect the area from landslides?
What effect would each alternative have on the soil resources?
2. Fisheries/Watershed: Harvest operations could affect water
quality, sedimentation, and fish passage. Mass-wasting of sediments
from cut-and-fill slopes can deliver sediment to streams. Harvest
adjacent to streams without fish may increase water temperature in
waters what would ultimately drain to Class I and Class II streams. How
will fish streams be protected from direct and indirect impacts caused
by harvesting timber and building roads? What effect would each
alternative have on fisheries and watershed?
3. Wildlife: Several goshawks and their nests have been located in
the project area. Mountain goats inhabit the rocky mountain terrain.
Marbled murrelets are well distributed in the project area and use the
Sandborn Canal and Port Houghton Salt Chuck for foraging. How will
these and other wildlife be protected? How will travel corridors among
high-intensity use areas be preserved? What effect will each
alternative have on wildlife?
4. Subsistence: A preliminary review of subsistence use in the Port
Houghton/Cape Fanshaw project area has identified eight subsistence
resources (deer, harbor seals, salmon, fin fish, waterfowl, marine
invertebrates, mountain goat, and mammal trapping) by three different
communities (Petersburg, Wrangell, and Kake). How will these resources
be protected either from loss of the resource or overuse due to
increased accessibility that may occur from road construction? To what
extend will each alternative affect subsistence resources and use
within the project area?
5. Recreation: Recreation sites at the project area occur as
natural, unmodified environments with little evidence of human
activity. Most of these sites occur along shoreline areas and include
boating, camping, hunting, and fishing. What affect would the change
from primitive to semi-primitive roaded recreational opportunity have
on existing and future uses? How will the alternatives address future
recreational uses while preserving the type of opportunities used
historically?
6. Cultural Resources: A total of 47 cultural sites have been
documented at the Port Houghton project area through field
investigations conducted this summer. One site consists of well
preserved artifacts that date as early as 10,000 years old. How will
these resources be protected from timber harvest, road construction,
and potential vandalism? What effect would each alternative have on the
cultural resources in the project area?
7. Visual Resources: Timber management activities will alter the
appearance and perceived visual quality of the project area and
vicinity. What type of mitigation measures will be developed to reduce
impacts to the visual quality of the area? What effect will the
alternatives have on the visual quality?
PERMITS: To proceed with the timber harvest as proposed, various
permits must be obtained from other agencies. Applications for these
permits would take place after the Final EIS is filed with the
Environmental Protection Agency (EPA) and not sooner than 30 days
following publication of this decision in the Petersburg Pilot
newspaper, published in Petersburg, Alaska.
Both the EPA and the U.S. Army Corps of Engineers have been
requested to participate as cooperating agencies in preparation of the
EIS. The agencies and their responsibilities are as follows: U.S. Army
Corps of Engineers has the responsibility for approval of discharge of
dredged or fill materials into the waters of the United States (Section
404 of the Clean Water Act), and approval of construction of structures
or work in navigable waters of the United States (Section 10 of the
Rivers and Harbors Act of 1899); EPA has responsibility for the
National Pollutant Discharge Elimination System Review (Section 402 of
the Clean Water Act). Other agencies which will participate are as
follows: State of Alaska, Department of Natural Resources has
responsibility for authorization for occupancy and use of tidelands and
submerged lands; State of Alaska, Department of Environmental
Conservation has responsibility for the Solid Waste Disposal Permit
(Section 402 of Clean Water Act) and the Certificate of Reasonable
Assurance (Section 404 of Clean Water Act); U.S. Coast Guard has
responsibility for Coast Guard Bridge Permits (in accordance with the
General Bridge Act of 1946) required for all structures constructed
within the tidal influence zone.
PUBLIC COMMENT: Interested parties are invited to comment. The comment
period on the Draft EIS will be 45 days from the date the Environmental
Protection Agency Notice of Availability appears in the Federal
Register.
The Forest Service believes, at this early stage, it is important
to give reviewers notice of several court rulings related to public
participation in the environmental review process. First, reviewers of
draft environmental impact statements must structure their
participation in the environmental review of the proposal so it is
meaningful and alerts an agency to the reviewer's position and
contentions (Vermont Yankee Nuclear Power Corp. v. NRDC, 435 U.S. 519,
533 [1978]). Also, environmental objections that could have been raised
at the Draft EIS stage may be waived if not raised until after the
completion of the final environmental impact statement may be waived or
dismissed by the courts (City of Angoon v. Hodel, 803 F.2d 1016, 1022
[9th Cir. 1986] and Wisconsin Heritages, Inc. v. Harris, 490 F. Supp.
1334, 1338 [E.D. Wis. 1980]). Because of these court rulings, it is
very important that those interested in this proposed action
participate by the close of the 45 day comment period so substantive
comments and objections are made available to the Forest Service at a
time when it can meaningfully consider them and respond to them in the
final environmental impact statement.
To assist the Forest Service in identifying and considering issues
and concerns on the proposed action, comments on the draft
environmental impact statement should be as specific as possible. It is
helpful if comments refer to specific pages or chapters of the draft
environmental impact statement. Comments may also address the adequacy
of the draft environmental impact statement or the merits of the
alternatives formulated and discussed in the statement. Reviewers may
wish to refer to the Council on Environmental Quality regulations for
implementing the procedural provisions of the National Environment
Policy Act in 40 CFR 1503.3 while addressing these points.
The responsible official for the decision is Abigail R. Kimbell,
Forest Supervisor of the Stikine Area, Tongass National Forest, Alaska
Region, Petersburg, Alaska.
Dated: September 2, 1994.
Abigail R. Kimbell,
Forest Supervisor.
[FR Doc. 94-22383 Filed 9-9-94; 8:45 am]