Northern Natural Gas Company, et al.; Natural Gas Certificate Filings

Federal RegisterAug 11, 1994

Ask Donna

What actually matters in this document.

Text

DEPARTMENT OF ENERGY

[Docket No. CP94-681-000., et al.]

Northern Natural Gas Company, et al.; Natural Gas Certificate

Filings

August 4, 1994.

Take notice that the following filings have been made with the

Commission:

1. Northern Natural Gas Company

[Docket No. CP94-681-000]

Take notice that on July 22, 1994, Northern Natural Gas Company

(Northern), 1111 South 103rd Street, Omaha, Nebraska 68124-1000, filed

in Docket No. CP94-681-000 a request pursuant to Sections 157.205 and

157.212 of the Commission's Regulations under the Natural Gas Act for

authorization to construct and operate facilities to implement a new

delivery point near Blair, Nebraska to accommodate natural gas

deliveries to Peoples Natural Gas Company (Peoples), under its blanket

certificate issued in Docket No. CP82-401-000,1 all as more fully

set forth in the request for authorization on file with the Commission

and open for public inspection.

---------------------------------------------------------------------------

\1\See, 20 FERC  62,410 (1982).

---------------------------------------------------------------------------

Northern states it has entered into a transportation service

agreement with Peoples for the firm transportation and delivery of

natural gas to Peoples at the proposed delivery point of up to 10 Bcf

annually and 11,500 Mcf per peak day. Northern holds a blanket

transportation certificate pursuant to Part 284 of the Commission's

Regulations issued in Docket No. CP86-435-000.2 Peoples has

requested a new delivery point from Northern so they may serve the new

Cargill plant near Blair, Nebraska. Northern states that the lateral

pipeline route will begin at Northern's ``C'' mainline 24-inch takeoff

in the NW \1/4\ of Section 16, Township 18 North, Range 8 East, Dodge

County, and continue in an easterly direction approximately 16 miles to

Northern's town border station (TBS) following within 30 feet to the

north or south, Northern's existing 6-inch lateral line servicing

Blair. Northern states that Peoples will construct the entire 24 miles

of 8-inch pipeline from Northern's ``C'' mainline to the Cargill.

Northern will own and operate approximately 16 miles of the 8-inch

lateral pipeline, and Peoples will own and operate 8 miles from

Northern's TBS to the Cargill plant.

---------------------------------------------------------------------------

\2\See, 37 FERC  61,268 (1986).

---------------------------------------------------------------------------

Northern states that the total volumes to be delivered to the

customer after the request do not exceed the total volumes authorized

prior to the request. Northern states that construction of the proposed

delivery point is not prohibited by its existing tariff and that it has

sufficient capacity to deliver the requested gas volumes without

detriment or disadvantage to it's other customers. Northern estimates

the cost of the proposed facilities at $192,000; which includes the

meter run, the take-off from the ``C'' mainline and the flange setting.

Comment date: September 19, 1994, in accordance with Standard

Paragraph G at the end of this notice.

2. Transcontinental Gas Pipe Line Corporation

[Docket No. CP94-692-000]

Take notice that on August 1, 1994, Transcontinental Gas Pipe line

Corporation (Transco), Post Office Box 1396, Houston, Texas 77251,

filed in Docket No. CP94-692-000 an application pursuant to Section 7

(b) and (c) of the Natural Gas Act for permission and approval to

abandon approximately 0.86 miles of 30-inch pipeline and for a

certificate of public convenience and necessity authorizing the

construction and operation of approximately 0.86 miles of 30-inch

replacement pipeline on its Main Line A across the Neches River in

Hardin and Jasper Counties, Texas and across the Village Creek in

Hardin County, Texas, all as more fully set forth in the application

which is on file with the Commission and open to public inspection.

Transco proposes to: (1) Construct and operate approximately 4,270

feet of 30-inch pipeline by horizontal directional drilling under the

Neches River at its existing pipeline river crossing located 8 miles

north of Beaumont, Texas and 20 miles west of the Texas-Louisiana

boundary and construct and operate approximately 512 feet of

conventionally installed tie-in piping on the banks of the river to

connect the drilled crossing to Transco's Main Line A; (2) construct

and operate approximately 260 feet of 30-inch pipeline by conventional

ditching approximately 25 feet to the north of its existing Village

Creek crossing of Main Line A located 1.8 miles west of the Neches

River crossing in Hardin County, Texas with tie-ins to Main Line A on

each river bank when the replaced portion of Main Line A is removed

from service; and (3) abandon by removal the portions of Main Line A

replaced at the Neches River and the Village Creek crossings. Transco

states that the proposed replacements will restore the long-term

integrity of its transmission system at the Neches River and the

Village River crossings and that the capacity will remain at the

existing 624 MMcf per day.

Transco states that the abandonment of the portions of the Main

Line A at the Neches River crossing will be completed in two separate

projects. Transco proposes to remove approximately 260 feet of the

existing 30-inch line from the point of tie-in on the west side of the

river and approximately 80 feet of the existing 30-inch line from the

point of tie-in on the east side of the river in 1994, at the time of

the pipeline replacement construction. The abandonment of the remaining

facilities at the Neches River crossing will be completed in 1995, as a

separate project, after necessary permits are obtained. Transco

proposes to remove, in 1994, approximately 240 feet of its Main Line A

at the Village Creek crossing after the replacement line is constructed

and tied in. Transco also requests temporary authorization to complete

the river crossing replacements if permanent authorization is not

issued by August 19, 1994, for security of gas service during the

upcoming heating season. The estimated cost of construction is

$4,694,455 with abandonment cost estimated at $972,000. The cost will

be initially financed by Transco by funds on hand and short-term loans

which will be rolled into permanent financing.

Comment date: August 19, 1994, in accordance with Standard

Paragraph F at the end of this notice.

3. National Fuel Gas Supply Corporation

[Docket No. CP94-693-000]

Take notice that on August 1, 1994, National Fuel Gas Supply

Corporation (National Fuel), 10 Lafayette Square, Buffalo, New York

14203, filed in Docket No. CP94-693-000 a request pursuant to Sections

157.205 and 157.212 of the Commission's Regulations under the Natural

Gas Act (18 CFR 157.205 and 157.212) for authorization to construct and

operate a new point of delivery to provide service to an existing

customer, National Fuel Gas Distribution Corporation (Distribution),

under National Fuel's blanket certificate issued in Docket No. CP83-4-

000, pursuant to Section 7(c) of the Natural Gas Act, all as more fully

set forth in the request that is on file with the Commission and open

to public inspection.

National Fuel states that the new delivery point will be located in

the town of Grand Island, Erie County, New York, at the same station at

which National Fuel will interconnect with the facilities of Empire

State Pipeline, an intrastate pipeline, and will be used to provide

service to Distribution, and to Distribution's present and future

transportation customers. Additionally, National Fuel states that the

total volumes to be delivered are estimated to be no more than

3,200,000 Dth annually and will have no impact on National Fuel's total

peak day and annual deliveries, but will make it more likely that

National Fuel will be able to make the deliveries at the points and in

the quantities desired by Distribution and its customers. National Fuel

estimates that the total cost of constructing the delivery point is

$1,525,000.

National Fuel notes that it has previously applied for approval

under Section 7(c) of the Natural Gas Act for the acquisition and

construction of certain facilities, including construction of the Grand

Island delivery point, and received conditional approval by order

issued June 1, 1994, in Docket Nos. CP94-112-000 and CP88-94-008 (67

FERC  61,270 (1994)). National Fuel states that it has been unable to

commence acquisition and construction because National Fuel cannot

satisfy all the conditions included in the June 1 order. National Fuel

contends that it urgently needs to commence construction of the Grand

Island station in September, in order to have the station in operation

by November 1. National Fuel asserts that the new station is necessary

to relieve some of the load which currently must be satisfied from gas

fed into the eastern end of Line U because Line U operates at its

absolute peak capacity on a cold day.

Comment date: September 19, 1994, in accordance with Standard

Paragraph G at the end of this notice.

4. Distrigas of Massachusetts Corporation

[Docket No. CP94-694-000]

Take notice that on August 1, 1994, Distrigas of Massachusetts

Corporation (DOMAC), 200 State Street, Boston, Massachusetts 02109,

filed in Docket No. CP94-694-000, an abbreviated application pursuant

to Section 7(c) of the Natural Gas Act, for a certificate of public

convenience and necessity authorizing DOMAC to install additional air

stabilization equipment at DOMAC's liquefied natural gas (LNG) terminal

in Everett, Massachusetts. DOMAC also requests, pursuant to Section

157.17 of the Regulations of the Federal Energy Regulatory Commission

(Commission), a temporary certificate authorizing the installation and

use, on a temporary basis, of leased air injection equipment, pending

the installation and operation of the requested permanent equipment,

all as more fully set forth in the application which is on file with

the Commission and open to public inspection.

DOMAC states that it anticipates in the near future it will receive

additional cargoes of higher Btu LNG that will require air

stabilization capability in excess of DOMAC's current installed

capacity.3 In addition, DOMAC states that it needs to be able to

accept LNG of varying thermal contents at any time of the year, whether

supplied through the long-term contracts of SONATRACH, Distrigas

Corporation's Algerian supplier, or short-term or spot transactions

with other suppliers in the international marketplace. DOMAC states

that the new facilities will consist of one integrated unit of two

electric driven compressors and will be constructed wholly within

DOMAC's existing Everett facility and placed on a concrete pad within a

weather enclosure. DOMAC requests approval on an expedited basis so

that the permanent facilities can be installed and operational by

January 1, 1995.

---------------------------------------------------------------------------

\3\ A 1990 Operating Agreement requires that DOMAC air stabilize

any regasified LNG with a heating value in excess of 1,090 Btus per

standard cubic foot prior to delivery to Algonquin Gas Transmission

Company (Algonquin). DOMAC's existing equipment is capable of air

stabilizing high Btu LNG (up to 1125 Btu per standard cubic foot)

into Algonquin at an average throughput of 45,000 MMBtu per day.

---------------------------------------------------------------------------

DOMAC states that it will likely require additional air

stabilization capacity for one or more cargoes in the fall of 1994,

before a permanent certificate can be issued and the permanent

equipment can be installed and become operational. DOMAC proposes to

lease and install by September 1, 1994, temporary air stabilization

equipment to permit DOMAC to air stabilize regasified LNG before

delivering it into the J-System of Algonquin at the high throughput

rates expected for that time period. DOMAC states that the leased

temporary air stabilization equipment will consist of one integrated

unit of two truck-mounted diesel powered compressors. DOMAC requests

that a temporary certificate be issued on or before August 20, 1994, to

permit DOMAC to install this leased equipment by September 1, 1994, and

to operate the leased equipment pending the Commission's determination

concerning the permanent authorization and until such time as the new

permanent equipment is operational.

DOMAC states that the estimated cost of the temporary leased air

stabilization facilities will be approximately $295,000, assuming a

four-month period of operation, and the cost of the permanent air

stabilization facilities will be approximately $1,280,000. DOMAC

further states that it will finance the facilities by using funds on

hand and it will be fully at risk for the cost of these proposed

facilities. DOMAC also states that any financial risk associated with

the additional facilities will be borne by DOMAC alone, and not its

customers.

Comment date: August 14, 1994, in accordance with Standard

Paragraph F at the end of this notice.

Standard Paragraphs

F. Any person desiring to be heard or to make any protest with

reference to said application should on or before the comment date,

file with the Federal Energy Regulatory Commission, Washington, D.C.

20426, a motion to intervene or a protest in accordance with the

requirements of the Commission's Rules of Practice and Procedure (18

CFR 385.214 or 385.211) and the Regulations under the Natural Gas Act

(18 CFR 157.10). All protests filed with the Commission will be

considered by it in determining the appropriate action to be taken but

will not serve to make the protestants parties to the proceeding. Any

person wishing to become a party to a proceeding or to participate as a

party in any hearing therein must file a motion to intervene in

accordance with the Commission's Rules.

Take further notice that, pursuant to the authority contained in

and subject to the jurisdiction conferred upon the Federal Energy

Regulatory Commission by Sections 7 and 15 of the Natural Gas Act and

the Commission's Rules of Practice and Procedure, a hearing will be

held without further notice before the Commission or its designee on

this application if no motion to intervene is filed within the time

required herein, if the Commission on its own review of the matter

finds that a grant of the certificate and/or permission and approval

for the proposed abandonment are required by the public convenience and

necessity. If a motion for leave to intervene is timely filed, or if

the Commission on its own motion believes that a formal hearing is

required, further notice of such hearing will be duly given.

Under the procedure herein provided for, unless otherwise advised,

it will be unnecessary for applicant to appear or be represented at the

hearing.

G. Any person or the Commission's staff may, within 45 days after

issuance of the instant notice by the Commission, file pursuant to Rule

214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to

intervene or notice of intervention and pursuant to Section 157.205 of

the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to

the request. If no protest is filed within the time allowed therefore,

the proposed activity shall be deemed to be authorized effective the

day after the time allowed for filing a protest. If a protest is filed

and not withdrawn within 30 days after the time allowed for filing a

protest, the instant request shall be treated as an application for

authorization pursuant to Section 7 of the Natural Gas Act.

Linwood A. Watson, Jr.,

Acting Secretary.

[FR Doc. 94-19608 Filed 8-10-94; 8:45 am]

BILLING CODE 6717-01-P

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.